Upload
kelly-arigbonu
View
1.489
Download
135
Embed Size (px)
DESCRIPTION
Method Statement for Installation of Transformer
Citation preview
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 1 of 20
METHOD STATEMENT FOR INSTALLATION of transformer
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 2 of 20
Project : *INSERT PROJECT NAME HERE
Contractor : *INSERT CONTRACTOR NAME HERE
Document No. :
Document revision status : 0
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 3 of 20
0 Issued for Review & Comments
Rev. Date DescriptionPrepared by Checked by Approved by
*INSERT CONTRACTOR HERE
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 4 of 20
REVISION CONTROL SHEET
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 5 of 20
REV. NO. DATE PAGE NO. DESCRIPTION
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 6 of 20
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 7 of 20
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 8 of 20
TABLE OF CONTENTS
1 Purpose…………………………………………………………………………….. 11
2 Scope of Work…………………………………………………………………….. 12
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 9 of 20
3 Responsible Personnel on Site..……………………………………………… 12
4 Storage…………………………………………………………….………………. 13
5 Pre-Installation…………………………………………………………………… 4
6 Installation………………………………………………………………………… 5
7 Reference Documents…………………………………………………………. 5
8 Safety……………………………………………………………………………… 6
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 10 of 20
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 11 of 20
1. Purpose
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 12 of 20
This method of statement covers the on-site installations of Dry type Transformer as defined in the General Specification.
2. Scope of Work
This procedure will define the method to off-loading and installation to be used to ensure that the transformers are correct and acceptable and shall conform to the Contract Documents and Specification.
3. Responsible Personnel on Site
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 13 of 20
3.1. Construction Manager3.2. Electrical Field Engineers3.3. Safety Officer3.4. QA/QC Engineer3.5. Electrical Supervisors
4. Storage and Off-loading
4.1 Use Fork Lifts or Mobile Crane to off-load the transformers. Make sure that the capacity of the fork lifts or mobile crane can carry the weight of the transformers.
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 14 of 20
4.2 Off load the transformer on the designated off loading area. Proper care must be observed during off loading to prevent unnecessary damage or dents on the transformers.
4.3 Ensure that the transformers are properly protected and covered with tarpaulin.
5. Pre-Installation
5.1 All materials and documentation relevant to this particular section of works shall be checked by the Construction Department prior to the commencement of works ensuring that these are correct and approved type.
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 15 of 20
5.2 Before any permanent works will continue, pre-inspection on all materials, tools and access for installation to be carried out..
6. Installation
It has been presumed that all related civil works has been completed prior to transformer installation.
6.1 Before the transformer will be delivered to site, ensure that the transformer railing is fixed as per approved drawings and comply on municipality requirement.
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 16 of 20
6.2 Move the transformers from the designated off-loading area or storage area using fork lift and set them in position near to the transformer room. Make sure that the orientation of the transformer with regards to the position of cable entries is correct.
6.3 Push in the transformers inside the transformer room. Set the transformer on their final positions and make sure that they are properly secured and protected.
6.4 Raise Request for Inspection for Transformer Installation.
6.5 Conduct on site test for the transformer. Test shall include winding insulation resistance test and shall conform to manufacturer’s recommendation and specification. All tests must be recorded and conducted in the presence of Consultant by manufacturer testing engineer.
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 17 of 20
6.6 Dress and terminate the incoming and outgoing cables on the transformers. Ensure that the cables were supported properly. Cable glands, lugs and termination kits shall be approved type.
6.7 After termination works has been completed, clean the transformer cable box and ensure that it is free from foreign materials and excess openings must be sealed off and ensure that all the connections are properly tight and torque.
6.8 Raise Request for Inspection for the cable terminations and dressing.
6.9 Cover the cable boxes. Bolts and nuts must be tightened properly. Make sure that the transformer room is clean and free from foreign materials.
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 18 of 20
7. Reference Documents
7.1 Approved Electrical Shop Drawings 7.2 Approved Layout Drawings by municipality 7.3 Contract Material Submittals 7.4 Factory Test Certificates 7.5 Operation and Maintenance Manuals of Transformer
8. Safety`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 19 of 20
8.1 All safety precautions shall be followed as per approved safety plan & procedure. Ensure all involved persons are aware of the same.
8.2 Ensure that tradesman will keep their working places clean and tidy.
------------------------ Procedure End----------------------
You may also visit the link below for more:
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER
*INSERT LOGO HERE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT NAME HERE Date: 03 -31- 2008REV. 0
METHOD STATEMENT FOR INSTALLATION OF TRANSFORMER Page No. : 20 of 20
Discover the life secretsUdistinguish official page
Get lifetime unlimited download of documentations for FREE
`Brought you by udistinguish.com Contact us @ [email protected]
PROJECT MANAGER