Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
METHOD TO RESOLVE BUILDING PROJECT DELAY
MOHD ZAMRI BIN MOHAMUD
A capstone project report submitted in fulfillment of the
requirements for the award of the degree of
Master of Project Management
Faculty of Civil Engineering
Universiti Teknologi Malaysia
JAN 2014
ii
I declare that this project report entitled ‘Method to Resolve Building Project Delay’
is the result of my own research except as cited in the references. The report has not
been accepted for any degree and is not concurrently submitted in candidature of any
other degree.
Signature :…………………………………………………..
Name : MOHD ZAMRI BIN MOHAMUD
Date : JANUARY 2014
iii
A special feeling of gratitude to my loving parents, my beloved wife Siti Norliza Abd
Manaf and my sons Muhammad Rayyan Ukasyah and Muhammad Zayyan
Amsyar, thank you for all the love and support.
iv
ACKNOWLEDGEMENT
Praise to the Almighty Allah the God of the Universe who gave me strength
to complete this thesis. A sincere thank you to Public Works Department (PWD) to
give me an opportunity to broaden horizons. My special gratitude to my supervisor
Assoc. Prof. Dr. Mohamad Ibrahim Mohamad for your guidance, support, and
encouragement, without his continued support & interest this thesis could ever be
realized. I also would like to thanks to Ir Wan Ibrahim Wan Yusoff for the guidance
and cooperation. I am also thankful for the panel members for their constructive
comments during the project presentation. They were Prof.Madya Dr.Maslin
Masrom and Dr.Syuhaida Ismail is appreciated.
I would also like to thanks my colleagues from other branch in PWD head
office Kuala Lumpur for their cooperation for successful this study. To those who
had contributed assistance and advice in this study, either directly or indirectly, yet
their names are not cited here, they deserve my greatest gratitude. Millions thanks to
all.
Last but not least, I would like to thanks my family members and my friends,
who had given a lot of encouragement and motivation to complete this study.
v
ABSTRACT
For many years, the issues of delay in Jabatan Kerja Raya (JKR) project have
been phenomenal. Its impacts were so significant that it tends give bad impression
on the JKR performance and reputation as government technical agency.
Construction delays can be minimized once their causes are identified. The
methodologies used in this study are by using literature review, interview with expert
panels and distribution of questionnaires survey. Data has been collected from the
JKR staff in Design and Business Sector which directly involved in building works.
The results of the study shown that the top five most important factors that
contributed to the causes of delays were poor site management and supervision; poor
cash flow management; inadequate contractor experience; poor communication and
coordination by consultant and slowness in decision making process by client.
Despite a lot of effort and strategies used by JKR to overcome delays issue. However
this study has been undertaken to review the effectiveness of the traditional approach
in dealing with delays problem in JKR. The study also tries to propose new approach
in resolving delays issues as alternative to the existing traditional way. The
traditional approach in resolving delays problem in JKR include more intensive
project monitoring and supervision, imposing penalty and eventually terminating the
contract. However these strategies have not been very effective and the delay
problem remain unresolved. As alternative measure this study has identified new
contemporary management approach to complement the existing method in resolving
the delay problem. The new approach gives more emphasis as using the service of
more competent project manager and adaption of collaborative teamwork working
environment concept. Apart from that the used of new procurement system is seen to
be a viable approach. It is hope that the findings from this study will be able to
provide important guidelines for JKR to reengineer the traditional approach of
project delivery system.
vi
ABSTRAK
Kebelakangan ini isu kelewatan dalam perlaksanaan projek di Jabatan Kerja
Raya (JKR) menjadi amalan biasa. Kelewatan projek disiapkan mengikut jadual telah
memberikan kesan negatif terhadap reputasi JKR sebagai agensi teknikal Kerajaan.
Kelewatan dalam pembinaan projek dapat dikurangkan jika punca-puncanya dapat
dikenalpasti. Metodologi yang digunakan dalam kajian ini adalah menggunakan
kajian literatur , temuduga dengan panel pakar dan edaran borang soal selidik . Data
dikumpulkan daripada kakitangan JKR yang bertugas di sektor rekabentuk dan
bisnes yang terlibat secara langsung dalam kerja-kerja bangunan. Lima punca utama
yang telah menyebabkan kelewatan dalam projek pembinaan di JKR adalah
pengurusan dan penyeliaan tapak yang lemah; masalah kecairan aliran tunai;
kontraktor yang tidak berpengalaman ; masalah komunikasi dan koordinasi antara
perunding dan juga kelewatan dalam proses membuat keputusan oleh pihak
pelanggan. Pelbagai usaha dan strategi telah digunakan oleh JKR untuk mengatasi
isu kelewatan.projek Kajian semula keberkesanan kaedah yang digunapakai melalui
pendekatan tradisional dalam menangani masalah kelewatan dalam JKR dihuraikan
dengan terperinci. Kajian ini juga mencadangkan pendekatan baru dalam
menyelesaikan isu-isu kelewatan sebagai alternatif kepada kaedah tradisional yang
sedia ada. pelanggan Selain itu tiga kaedah tradisional yang digunakan didapati
kurang effektif iaitu mesyuarat penyelarasan ditapak, tatacara mengenakan denda
lewat jadual (LAD ) dan proses penamatan kontrak Kajian ini telah mengenal
beberapa kaedah alternatif dalam menangani projek lewat iaitu mengoptimumkan
bilangan pengurus projek yang kompeten, mengamalkan konsep kerja berpasukan,
dan mengaplikasikan sistem perolehan alternatif. Selain itu, modifikasi terhadap
kaedah alternatif dilihat sebagai pendekatan yang berdaya maju. Adalah diharapkan
kajian ini akan dapat memberi garis panduan penting bagi JKR untuk menyemak
semula pendekatan sedia ada dalam sistem penyampaian projek.
vii
TABLE OF CONTENTS
CHAPTER TITLE PAGE
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF TABLE xii
LIST OF FIGURE xv
LIST OF APPENDICES …… xvi
LIST OF ABBREVIATIONS …… ...xvii
1 INTRODUCTION
1.0 Introduction 1
1.1 Problem Statement 2
1.2 Aims and Objective 3
1.3 Scope and Limitation of the Study 4
1.4 Significance of the Study 4
1.5 Brief Research Methodology 4
2 LITERATURE REVIEW
2.1 Introduction 7
2.2 Types of Delay 8
2.2.1 Excusable Delays 9
viii
2.2.1.1 Excusable with Compensation 9
2.2.1.2 Excusable Delays without Compensation 10
2.2.2 Non-Excusable Delay 10
2.2.3 Concurrent Delay 11
2.3 Causes of Delay 12
2.4 Methods of Minimizing Construction Delays 16
2.5 Traditional Approach Dealing with Delay in JKR Projects 19
2.5.1 Warning Letter ……..20
2.5.2 Rescheduling 20
2.5.3 Extension of Time (E.O.T) 20
2.5.4…Liquidated Damages (LAD) 21
2.5.5 Termination of Contract 22
2.5.6 Appoint the Third Party (Kontraktor Penyelamat) 22
2.6 Contemporary Approach in JKR Project to Minimize Delay 22
2.6.1…Industrialised Building System (IBS) 23
2.6.2 Building Information Modeling (BIM) 23
2.6.3 Project Health Check (PHC) 23
2.6.4 Project Management Plan (PMP) 24
2.6.5 Accredited Project Manager Program 24
2.6.6 Risk Management 24
2.6.7 Value Management 25
2.7 Conclusion 25
3 RESEARCH METHODOLOGY
3.1 Introduction 26
3.2 General Approach of Research Design 26
3.3 Literature Review 26
3.4 Interview with Expert Panel 27
3.5 Questionnaires Survey 29
3.5.1 Section A 30
3.5.2 Section B 30
3.5.3 Section C ……..31
3.5.4 Section D ……..32
ix
3.5.5 Questionnaires Distribution 32
3.6 Data Analysis 33
3.6.1 Data Analyses and/or Analysis of Information 33
3.6.2 Exploratory Interviews and Documents Search.. 33
3.6.3 Reliability Analysis Cronbach’s Coefficient Alpha 33
3.6.4 Normality Tests 34
3.6.5 Relative Important Index (RII) 35
3.7 Conclusion 35
4 RESULT AND ANALYSIS
4.1 Introduction 36
4.2 Content Analysis of the Exploratory Interviews 36
4.3 Document Search 43
4.3.1 Gerbang Nilai 44
4.3.2 Estimation of Time 45
4.4 General Background of Questionnaire Survey Respondents 46
4.4.1 Grade in Organisation 48
4.4.2 Years in Experience 48
4.4.3 Types of Building Project Frequently Delay in JKR 50
4.4.4 Number of Project Delay 51
4.4.5 Time Overrun …….51
4.5 Testing on the Research Data 52
4.5.1 Reliability Analysis: Cronbach’s Coefficient Alpha 52
4.5.2 Normality Test 53
4.5.3 Kurtosis and Skewness Parameter 54
4.5.4 Section B-Factors that contribute to Delays of JKR Project56
4.5.4.1 Factor of Client Related Delays 57
4.5.4.2 Factor of Contractor Related Delays 57
4.5.4.3 Factor of Consultant Related Delays 58
4.5.4.4 Factor of Material Related Delays 59
4.5.4.5 Factor of Equipment Related Delays 60
4.5.4.6 Factor of Labour Related Delays 61
4.5.4.7 Factor of External Factor Related Delays 61
x
4.5.5 Section C- Traditional Approach in JKR Dealing with
Project Delay 62
4.5.6 Section D - Proposed Contemporary Approach to
JKR Dealing With 63
4.6 Conclusion 71
5 DISCUSSION OF RESULTS
5.1 Introduction 72
5.2 Factors that Contribute to Delay in JKR Projects 72
5.3 Traditional Approach in JKR Dealing with Project Delay 74
5.4 Attribute of method in Minimizing Project Delay in
Project Delay 77
5.4.1 Project Manager 78
5.4.2 Collaborative Teamwork 79
5.4.3 Designer 80
5.4.4 Communication Channel 80
5.4.5 Human Resources 80
5.4.6 Monitoring and Controlling 81
5.5 Proposed Guidelines for on Time Project Delivery 81
5.5.1 Workflow Processes and Duration of Activity ….. 85
5.6 Conclusion 91
6 CONCLUSIONS AND RECOMMENDATIONS
6.1 Introduction 92
6.2 Conclusion 92
6.2.1 Objective 1: To Evaluate the Effectiveness of the
Traditional Approach in Addressing Project Delay Issue 93
6.2.2 Objective 2: To Evaluate the Potential Application of
Contemporary Approach in Resolving
Project Delay Issue 94
6.2.3 Objective 3: To Propose Guidelines for on Time Project
Delivery 94
6.3 Recommendation to Jabatan Kerja Raya (JKR) 95
xi
6.4 Recommendations for Further Study 97
6.5 Summary 98
REFERENCES 99
APPENDICES A-D 103 - 120
xii
LIST OF TABLES
TABLE NO. TITLE PAGE
1.1 Report of Building Project Delay in JKR ( SKALA, 2013) 2
2.1 Summary of Previous Studies on the Causes of Delays in
Construction Projects 13
2.2 Summary of Causes on Delays in Construction Projects in
Categorized Group 15
2.3 Method to Minimize Project Delays in Acheh, Indonesia 18
2.4 Method of Minimizing Construction Delays (Dayang, 2009) 19
3.1 List of Interview Questions 28
3.2 Likert Scale Grade Section B 31
3.3 Likert Scale Grade Section C 31
3.4 Likert Scale Grade Section D 32
4.1 Tabulation of Interview with Expert Panels 36
4.2 Summary of Interview Session with Expert Panels 38
4.3 Estimation Time in Pre- Contract Phase 45
4.4 Estimation Time in Pre-Contract Phase 46
4.5 Distribution of Questionnaire Based on Sector and Organisation 46
4.6 Cronbach Alpha’s Value for Each Cayegory in Questionnairer 53
4.7 Results of Skewenss and Kurtosis Values 55
4 8 Cronbach’s Alpha Value for Section B 56
4.9 Ranking Relative Importance (RII) Index for the Client Related 57
4.10 Ranking Relative Importance (RII) Index for the Contractor
Related 58
4.11 Ranking Relative Importance (RII) Index for the Consultant
Related 59
4.12 Ranking Relative Importance (RII) Index for the Material Related 59
xiii
TABLE NO. TITLE PAGE
4.13 Ranking Relative Importance (RII) Index for the Equipment
Related 60
4.14 Ranking Relative Importance (RII) Index for the Labour Related 61
4.15 Ranking Relative Importance (RII) Index for the External Factor
Related 62
4.16 Ranking Relative Importance (RII) Index for the Traditional
Approach in JKR 63
4.17 Cronbach’s Alpha Value for Section D 64
4.18 Ranking Relative Importance (RII) Index for the Scope
Management 65
4.19 Ranking Relative Importance (RII) Index for the Time
Management 65
4.20 Ranking Relative Importance (RII) Index for the Cost
Management 66
4.21 Ranking Relative Importance (RII) Index for the Quality
Management 66
4.22 Ranking Relative Importance (RII) Index for the Communication
Management 67
4.23 Ranking Relative Importance (RII) Index for the Human
Resources Management 67
4.24 Ranking Relative Importance (RII) Index for the Risk
Management 68
4.25 Ranking Relative Importance (RII) Index for the Procurement
Management 68
4.26 Ranking Relative Importance (RII) Index for the Integration
Management 69
4.27 Ranking Relative Importance (RII) Index of the Top Fifteen
Attributes of Method Minimizing Delay 70
5.1 Ranking of Ranking Relative Importance (RII) Index Top Five Causes
of Delay …… 73
5.2 Ranking of Ranking Relative Importance (RII) Index for Top
Three Traditional Approach Dealing with Delay in JKR 75
xiv
TABLE NO. TITLE PAGE
5.3 Ranking of Ranking Relative Importance (RII) Index for Top
Fifteen Attributes of Method Minimizing Project Delay …….. 77
5.4 Inception Activity …….. 82
5.5 Planning Activity …….. 83
5.6 Implementation Activity 84
5.7 Closure Activity 85
5.8 Activity and Duration Purpose for on time Project Delivery 89
xv
LIST OF FIGURE
FIGURE NO. TITLE PAGE
1.1 Schematic of Research Methodology ` 6
2.1 Delay Categories 11
4.1 Grade of Respondents in Organisation 48
4.2 Years of Experience 49
4.3 Years of Experience in Project Management ……..50
4.4 Types of Building Frequently Delay in JKR Project 50
4.5 Number of Executed Project Delay 51
4.6 Time Overrun 52
5.1 Flowchart of Project Implementation in JKR 86
xvi
LIST OF APPENDIX
APPENDIX NO. TITLE PAGE
A Normality Test – Histogram and Q-Q Plot 103
B ` Sample Questionnaire Survey Form 106
C Sample of Questionnaire Interview with Expert on List of
Activity in Project Life Cycle 116
D Sample of Questionnaire Interview with Expert on List of
Activity and Duration of Time 118
xvii
LIST OF ABBREVIATIONS
ACAT - Acquisition Categorization
ACEM - Association of Consulting Engineers Malaysia
CIDB - Construction Industry Development Board
CKBA - Cawangan Kerja Bangunan Am
CKK - Cawangan Kerja Kesihatan
CKS - Cawangan Kerja Kesihatan
CPPT - Cawangan Pendidikan dan Pengajian Tinggi
D&B - Design and Build
E.O.T - Extension of Time
HODT - Head of Design Team
HOPT - Head of Project Team
JKR - Jabatan Kerja Raya
L.A.D - Liquated Ascertain Damages
NAFAM - National Asset and Facility Management
PMO - Project Management Office
SO - Suppertender Officer
SPSS - Statistics Package for Social Science
Q-Q Plot - Quartile-Quartile Plot
RII - Relative Important Index
1
CHAPTER 1
INTRODUCTION
1.1 Introduction
The inability to complete projects on time is a common problem in the
construction industry and in developing countries (Ahmed. 2002). Assaf and Al-
Hejji (2006), defined delay as the time overrun beyond completion date specified
either in a contract or beyond the date that the parties agreed upon for delivery of a
project. It is a project slipping over its planned schedule and consider as a common
problem in construction projects. Bassioni and El-Razek (2008) identified that delay
in construction project is considers as one of the most common problems causing a
multitude negative effect on the project and its stakeholders. Therefore, it is essential
to identify the tangible causes of delay in order to minimize and avoid them and their
corresponding expenses.
This situation has been a long time, been blamed on ineffective management
(Munns and Bjeirimi, 1996) and dominance of traditional construction practices.
Love and Sohal (2002) claim that these practices create unnecessary waste, errors,
and misapprehension amongst the project supply chain.
Delay can have a major effect on construction organizations, resulting in
increased cost, lost opportunity cost, reputation damage, arbitration, litigation and, in
the worst cases, the total abandonment of projects. Construction delay also directly
relates to the performance of the project and the customer satisfaction level.
2
Research in Finland by Karna et al. (2004) found that client satisfaction level
declines when the project negatively deviates from the planned schedule. Therefore,
client appears to be dissatisfied when construction performance is less than what was
regard as standard (Karna et al., 2004)
1.2 Problem Statement
Currently in JKR, delay is a phenomenon during the construction
stage. The term delay means, construction work cannot complete within the period
which stated in the contract document or part of the works run out of the planning
schedule. Typically, delay is attributable to a variety of causes and reasons beyond
the contractor or the client’s expectations. When the unfortunate problem happens,
contractor will encounter problems due to delays in completing the works.
Based on JKR project database module, SKALA (Sistem Kawal, Selia dan
Lapor), there are 810 projects in the Building Sector with total cost of
RM 31,087,763,136.70. From the list of the projects, 216 are under construction and
123 projects are delays, which contribute 57% of the project under construction
(Table 1.1). The duration of delays is one (1) to six (6) months. From data provided
by the JKR Project Monitoring Unit, it shows that 50% of the project in the Ninth
Malaysia Plan supervised by JKR was complete behind schedule. Regarding these
problems, JKR has acknowledged the construction delays (time overrun) and cost
overruns problems as the big headache, especially with government-related funded
projects.
Current approaches used by JKR in dealing with delay problem are intensive
coordination meeting; approval extension of time, imposing penalty; and termination
of contract are the main approaches have been used. Despite a lot of effort and
strategies used by JKR to overcome delays issue. There are contemporary
management approaches to complement the existing method in resolving such as
value management; risk management; using new technology IBS and BIM.
3
Table 1.1: Report on Building Project Delay in JKR (SKALA, 2013)
More than 2 Month above
No Programme Manager
Office
< 1
month
1 -2
month
2 - 3
month
> 3
month
> 6
month > 9 month
> 12
month Total
1 Building Sector 0 0 0 0 0 0 0 0
2
CAWANGAN KERJA
BANGUNAN AM
(CKBA)
14 11 9 13 0 0 0 47
3 CAWANGAN KERJA
KESIHATAN (CKK) 8 8 3 4 2 1 0 26
4
CAWANGAN
PENDIDIKAN &
PENGAJIAN TINGGI
(CPPT)
13 7 4 2 0 1 0 27
5
CAWANGAN KERJA
KESELAMATAN
(CKS)
10 5 3 5 0 0 0 23
Total 45 31 19 24 2 2 0 123
This study has been undertaken to identify the causes of project delay. A
specific focus given on the various methods used in addressing project delay issues
practise in JKR
1.3 Aims and Objective
The main aim of this study is to reviewing the effectiveness of the traditional
practice of addressing the project delay issues in JKR. In order to achieve this aim,
the following objectives outlined are:--
i. To evaluate the effectiveness of the traditional approach in project
delay issues.
ii. To evaluate the potential application of contemporary approach in
resolving project delay issues.
iii. To propose the basic guidelines for on time projects delivery.
4
1.4 Scope and Limitations of the Study
The scope of this capstone project is limited to building projects in Building
Sector, JKR only. The data was gathered through comprehensive literature review,
interview with selected expert panel and through questionnaire survey process. The
questionnaire survey has been designed guided by the objective to get the feedback
from respondents. Questionnaire was distributed to get the accurate data from the
person involved directly with building project in JKR related to Cawangan Kerja
Bangunan Am (CKBA), Cawangan Pendidikan Pengajian Tinggi (CPPT), Cawangan
Kerja Keselamatan (CKS) and Cawangan Kerja Kesihatan (CKK).
1.5 Significance of the Study
i. For JKR
This study proposed guidelines on time project delivery and propose
the contemporary approach with the attribute of method to overcome
the project delay and will be beneficial to the organization.
ii. For JKR Staff
This study will provide information’s on causes of the delays in JKR
projects and the effectiveness of the current practice in.JKR dealing
with project delay.
1.6 Brief Research Methodology
Research methodology is a framework for the research on how a study was
carried out such as the process of collecting, analyzing, and interpreting
observations. Therefore, Figure 1.1 outlined the research methodology of this study.
5
It consists of into three phases. Phase 1: encompasses the objective, scope and the
literature review. Phase 2: Preliminary interview with experts in project
management, involves case studies of building project delay and related issues.
Design questionnaires and conducts a questionnaire to get analytical data. Lastly,
Phase 3 consists of developing guidelines for project delivery on time through
validation from expert and final submission. The following Figure 1 represents the
overall proposed of the study.
6
Figure 1.1: Schematic of Research Methodology
Scope and Objective
Proposed the Guidelines for the on Time Project
Delivery
7
CHAPTER 2
LITERATURE REVIEW
2.1 Introduction
The problem regarding the delay in the construction industry is mainly due to
a global phenomenon. In Saudi Arabia, Assaf and Al-Hejji (2006) found that only
30% of the construction projects were completed within the scheduled completion
dates and that the typical overrun time was between 10% and 30%. In Nigeria,
Ajanlekoko (1987) observed that the performance of the construction industry in
terms of time was scanty. Odeyinka and Yusif (1997) have shown that seven out of
ten projects surveyed in Nigeria suffered a setback in their execution. Ogunlana and
Promkuntong (1996) conducted a study on construction delays in Thailand. Al-
Momani (2000) carried out a quantitative examination on construction delay in
Jordan. Frimpong et al. (2003) conducted a survey to identify and evaluate the
relative importance of the significant factors contributing to delay and cost overruns
in Ghana groundwater construction projects. Chan and Kumaraswamy (1997),
studied the delay times in the Hong Kong construction industry. They emphasized
that timely release of projects within a budget and to the level of quality standard
specified by the client is an index of successful project delivery. Failure to achieve
targeted time, budgeted cost and specified quality will result in various unexpected
unfavorable effects on the projects. In Malaysia, Abdullah et al. (2010) have also
reported a 90% delay rate for projects handled by Majlis Amanah Rakyat (MARA), a
government agency that plays an important role in implementing the Malaysian
Government’s construction policies. This problem is manifested in the
8
underachieving Malaysian construction industry (CIDB, 2009), with recent
community project delay rates of 80% (Joshi, 2009).
Majid (2006) stated that delays can be minimized when their causes are
identified. Identification of the factors that contributed to the cause of delays has
been studied by numerous researchers in numerous countries. Delays usually occur
when the contractor, consultant, and client jointly or severally contributed to the non-
completion of the project within the original or the stipulated or agreed contract
period.
Normally when the projects are delayed, they are either extended or
accelerated and therefore, incur additional cost. Although the contract parties agreed
upon the extra time and cost associated with delay, in many cases there were
problems between the owner and contractor as to whether the contractor was entitled
to claim the extra cost. Such situations, usually involved questioning the facts, causal
factors and contracts for interpretation. Knowing the cause of any particular delay in
a construction project would help avoiding the same. By the case, it is the
responsibility of all parties to study, analyze, and identify problems and find
solutions in the latest renewal of methods and strategies for planning and
implementation of the project to control the delay of the project. In most of the
public works done by JKR including construction project under the government,
projects were awarded on a competitive basis using the traditional approach.
Consultants and contractors are engaged in separate contracts.
2.2 Types of Delay
Causes of delays classified into three (3), which include excusable, non-
excusable, and concurrent delay (Alkass, 1996). That purpose type of delay will
determine delay damage.
9
2.2.1 Excusable Delays
According Theodore (2009) an excusable delay is a delay that is due to an
unforeseeable event beyond the contractor’s or the subcontractor’s control.
Normally, based on common general provisions in public agency specifications,
delays resulting from the following events would be considered excusable:
a. General labor strikes
b. Fires
c. Floods
d. Acts of God
e. Owner-directed changes
f. Errors and omissions in the plans and specifications
g. Differing site conditions or concealed conditions
h. Unusually severe weather
i. Intervention by outside agencies
j. Lack of action by government bodies, such as building inspection
2.2.1.1 Excusable with Compensation
It is reasonably established that when a construction schedule delay occurs
through no fault of the contractor, because of the actions and/or inactions of the other
party to the contract (absent an enforceable no-damage-for-delay clause), the
contractor will be entitled to recover damages and be granted a time extension.
Compensable delay can be the result of a variety of occurrences such as:
a. Denied access to the site,
b. Design changes,
c. Differing site conditions,
d. Interference from other trades, and
e. Non-timely delivery of owner-furnished materials.
Another contractor on the project can cause another form of compensable
delay. Although the delayed contractor is only in contract with the owner, he will
likely look to the owner for damages caused by other contractors whether or not
10
contractually the coordination/scheduling duties was delegated elsewhere. Cases in
this area have resulted, however, in mixed decisions.
2.2.1.2 Excusable Delays without Compensation
Not to compensate for delays caused by third parties or circumstances beyond
the control of both owners and contractors. Examples often include acts of God,
anomalous weather conditions, fire, death, government actions kingly, etc. In this
case, the contractor will normally get to claim an extension of time.
2.2.2 Non-Excusable Delays
According Theodore (2009) non-excusable delays are events that are
within the contractor’s control or that are foreseeable. These are some examples
or non-excusable delays:
a. Late performance of sub-contractors
b. Untimely performance by suppliers
c. Faulty workmanship by the contractor or sub-contractors
d. A project-specific labor strike caused by either the contractor’s
unwillingness to meet with labor representative or by unfair labor
practices
In this last type of delay, contractor’s own actions, and/or inactions have been
the causes of the delay. In this event, the contractor will not have the right to recover
either damages or time extensions from the owner. Furthermore, the owner will
likely be able to recover delay damages from the contractor. In the absence of a
liquidated damages clause, the contractor may be exposed to actual damages, which
in particular instances could be financially catastrophic.
11
While some delays might standalone in establishing the net effects (such as
an injunction that halts the work on a project in total), the overwhelming form of
delay solely affects individual construction activities. Because of this, reliance on a
construction schedule, which sets forth the relationships between and among the
diverse activities, is important. The widespread use of the simple bar chart or Gantt
chart has given way to the use of more detailed and modern network analysis
scheduling techniques, such as critical path method arrow diagramming and
precedence diagramming methods. Utilizing these scheduling techniques makes it
possible to assess the effects of delays on individual activities and the overall
construction schedule network.
Figure 2.1: Delay Categories (Theodore, 2009)
2.2.3 Concurrent Delay
The delay is concurrent problems of the construction industry construction.
This problem occurs when two or more events at the same time late in the project
cannot be accomplished in time. In this situation, both the owner and the contractor
are responsible for the delay. Concurrent delays typically associated with two or
more excusable delay, resulting in extended time. When excusable with
12
compensation and non- excusable delays are concurrent, the extension can be
removed, or delays may be distributed between owners and contractors.
2.3 Causes of Delay
Traditional contractual approach is still dominant in Malaysia construction
sector and this may likely continue to be a trend. Malaysia construction sector
comprises the clients or project owners, contractors, subcontractors, suppliers, and
others key professional actors responsible for design and supervision of projects.
These professionals were cross-functional teamwork. Due to this mixed variety of
parties involved in projects, they often encounter difficult situations and some degree
of pressures. Many of these problematic conditions are beyond control and often lead
to delays or project time overrun (Odeh and Battaineh, 2002).
Researchers have studied the many causes of delay in construction industry.
Lo et al. (2007) summarized some of the studies that took place from 1971 to 2007
(Table 2.1) as below.
13
Table 2.1: Summary of Previous Studies on the Causes of Delays in Construction
Projects
No Researchers Country Major Causes of Delay
1 Baldwin et al.
(1971)
United
States
i. Inclement weather
ii. Shortages of labour supply
iii. Subcontracting system
2 Arditi et al.
(1985)
Turkey i. Shortages of resources
ii. Financial difficulties faced by public
agencies and contractors
iii. Organizational deficiencies
iv. Delays in design works
v. Frequent changes in orders/design
vi. Considerable additional work
3 Mansfield et al.
(1994)
Nigeria i. Improper financial and payments
arrangements
ii. Poor contract management
iii. Shortages of materials
iv. Inaccurate cost estimates
v. Fluctuations in cost
4 Semple et al.
(1994)
Canada i. Increases in the scope of the work
ii. Inclement weather
iii. Restricted access
5 Ogunlana et al.
(1996)
Thailand i. Shortages of materials
ii. Changes of design
iii. Liaison problems among the contracting
parties
6 Chan and
Kumaraswamy
(1996)
Hong
Kong
i. Unforeseen ground conditions
ii. Poor site management and supervision
iii. Slow decision making by project teams
iv. Client-initiated variations
7 Al-Monami
(2000)
Jordan i. Poor design
ii. Changes in orders/design
iii. Inclement weather
iv. Unforeseen site conditions
v. Late deliveries
14
Table 2.1: Summary of Previous Studies on the Causes of Delays in Construction
Projects (Cont’d)
No Researchers Country Major Causes of Delay
8 Faridi and El-
Sayegh (2006)
UAE i. Slow preparation and approval of drawing
ii. Inadequate early planning of the project
iii. Slowness of owner’s decision making
iv. Shortage of manpower
v. Poor site management and supervision
vi. Low productivity of manpower
9 Assaf and Al-
Hejji (2006)
Saudi
Arabia
i. Change in orders by the owner during
construction
ii. Delay in progress payment
iii. Ineffective planning and scheduling
iv. Shortage of labor
v. Difficulties in financing on the part of the
contractor
10 Sambasivam et
al. (2007)
Malaysia i. Contractor improper planning
ii. Contractor poor site management
iii. Inadequate contractor experience
iv. Inadequate client’s finance and payments
for completed works
v. Problem with subcontractors
vi. Shortage in material
vii. Labour supply
viii. Equipment availability and failure
ix. Lack of communication between parties
x. Mistakes during the construction stage
Many factors contributed to causes of delays in construction projects. These
range from factors inherent in the technology and its management, to those resulting
from the physical, social, and financial environment. There are in seven groups of
causes for delay in construction project:
15
Table 2.2: Causes of Delay Categorized into Seven (7) Groups (Theodore, 2009)
No Causes of
Delay By
Causes of Delay
1. Client 1. Delay in progress payments by owner
2. Delay to furnish and deliver the site
3. Change orders by owner during construction
4. Late in revising and approving design documents
5. Delay in approving shop drawing and sample materials
6. Poor communication and coordination
7. Slowness in decision making process
8. Conflicts between joint-ownership of the project
9. Suspension of work
2. Contractor 1.Difficulties in financing project by contractor
2. Conflicts in sub-contractors schedule in execution of project
3. Rework due to errors during construction
4. Conflicts between contractor and other parties(consultant and
owner)
5. Poor communication and coordination
6. Ineffective planning and scheduling of project
7. Improper construction methods implement
8. Delays in sub-contractors work
9. Inadequate contractor's work
10. Frequent change of sub-contractors
11. Poor qualification of the contractor's technical staff
12. Delays in site mobilization
3. Consultant 1. Delay in approving major changes in the scope of work
2. Poor communication and coordination
3. Inadequate experience of consultant
4. Mistakes and discrepancies in design documents
5. Delays in producing design documents
6. Unclear and inadequate details in drawings
7. Insufficient data collection and survey before design
8. Un-use of advanced engineering design software
4. Material 1. Shortage of construction materials in market
2. Changes in material types and specifications during
construction
3. Delay in material delivery
4. Damage of sorted material while they are needed urgently
5. Delay in manufacturing special building materials
6. Late procurement of materials
5. Equipment 1. Equipment breakdowns
2. Shortage of equipment
3. Low level of equipment-operator's skill
4. Low productivity and efficiency of equipment
5. Lack of high-technology mechanical equipment
16
Table 2.2: Causes of Delay Categorized into Seven (7) Groups (Theodore, 2009)
(Cont’d)
No Causes of
Delay By
Causes of Delay
6. Labours 1. Shortage of labors
2. Working permit of labors
3. Low productivity level of labors
4. Personal conflicts among labors
7. External
Factor
1. Effects of subsurface conditions (e.g. soil, high water table,
etc.)
2. Delay in obtaining permits from municipality
3. Hot weather effect on construction activities
4. Traffic control and restriction at job site
5. Accident during construction
6. Changes in government regulations and laws
7. Delay in providing services from utilities (such as water,
electricity)
8. Delay in performing final inspection and certification by a
third party
2.4 Methods of Minimizing Construction Delays
According to Nguyen (2004), studied the factors that can be applied as a
method of minimizing of construction delays as follows: competent project manager;
frequent progress meeting; accurate initial cost estimates; accurate initial time
estimates; awarding bids to the right/experience consultant and contractor. According
to Aibinu and Jagboro (2002), identified two methods to minimize or if possible
eliminate time overrun were: acceleration of site activities, and contingency
allowance.
According to Odeh and Battaineh (2002), they recommended to improve the
delay in construction project there are a few solution such as enforce liquidated
damage clauses and offering incentives for early completion; developing human
resources in the construction industry through proper training and classifying of
craftsman. Ahmad S.M (2002) in their study of delays in Florida has recommended
streamlining the building permit approval process to minimize the delay in
17
construction project. Rahman (2006) recommended to mitigate the delay the
contractor should increasing the productivity by working overtime hours or working
by shifts, followed by asking the extension of time. If the problem was shortage of
resources, they suggested rescheduling the activities within the available resources,
using skilled labours and by using subcontractors. Site meeting are essential in
solving the problems with the condition that it should not be too frequent.
Majid (2006), has conducted study of delays in Acheh Indonesia. He listed
thirty-five methods in order to minimize construction delays as shown in the in Table
2.3.
18
Table 2.3: Method to Minimize Project Delay in Acheh,Indonesia
1 Competent project manager; 18. Site management and supervision;
2. Ensure adequate and available source of 19. Use of proper and modern construction
finance; equipment;
3. Multidisciplinary/competent project team; 20. Proper project planning and scheduling;
4. Availability of resources; 21. Accurate initial cost estimates;
5. Commitment to projects; 22. Use of appropriate construction methods;
6. Adopting a new approach to contract award 23. Community involvement;
procedure by giving less weight to prices and 24. Proper emphasis on past experience;
more weight to the capabilities and past 25. Frequent coordination between the parties
performance of contractors; involved;
7. Adopting new approaches to contracting such 26. Absence of bureaucracy;
as Design-Build (D/B) and Construction 27. Clear information and communication
Manager (CM) type of contract; channels;
8. Complete and accurate project feasibility 28. Accurate initial time estimates;
study and site investigation; 29. Proper material procurement;
9. Acceleration of site clearance; 30. Developing human resources in the
10. Comprehensive contract documentation; construction industry through proper
11. Frequent progress meeting; training;
12. Project management assistance; 31. Allocation of sufficient time and money at
13. Use up to date technology utilization; and the design phase;
14. Use of experienced subcontractors and 32. Awarding bids to the right/experience
suppliers; consultant and contractor;
15. Complete and proper design at the right time; 33. Perform a preconstruction planning of
16. Competent personnel of consultant/designer; project tasks and resources needs;
17. Competent and capable of client’s 34. Systematic control mechanism; and
representative 35. Effective strategic planning.
Based on several studies of project success factors and minimizing delay in
construction project, a total twenty-three methods have been identified in order to
minimize construction delays as shown in Table 2.4
19
Table 2.4: Methods of Minimizing Construction Delays (Dayang, 2009)
No. Methods
1. Utilization of the latest construction technology method
2. Frequent site meeting with all functional parties
3. Not awarding contract based on the lowest bid
4. Increase productivity by working overtime, shift, etc
5. Offer incentive for early project completion
6. Ask for extension of time
7. Execute delayed activities by subcontractors
8. Promote team working among project participants
9. Developing human resources management (training, day courses, etc)
10. Timely decision making by all functional group
11. Proper project planning and scheduling
12. Developing appropriate communication system linking to all functional group
13. Early in obtaining permit and approval from relevant authority
14. Thorough project feasibility study and site investigation
15. Accurate initial project cost estimation
16. Hire experience personnel for project implementation
17. Build a systematic project control and monitoring mechanism
18. Absence of bureaucracy
19. Proper emphasis on past experience of project parties
20.
21.
22.
23.
Accurate initial time estimation
Ensure the availability of resources ( finance, materials, equipment, workmen, etc)
Select the competent project manager
Use the appropriate construction methods
2.5 Traditional Approach Dealing with Delay in JKR Project
Basically there are several steps taken by JKR when the project delays. The
steps are as follows: -
a. Warning Letter
b. Rescheduling
c. Extension of Time
d. Liquidated Damages (LAD
e. Termination of Contract
f. Appoint third party
20
2.5.1 Warning Letter
The contractor will receive a warning letter to improve the progress of the
project. The length of time is given to the contractor 14 days to submit feedback.
After feedback received Project Manager will monitor the implementation of the
project through regular site meeting. The contractor must show determination after a
warning letter is issued to avoid the contract is terminated.
2.5.2 Rescheduling
According to Vieira et al. (2003), rescheduling is the change of original
schedule of time in order to respond to disruption and problems, which have
occurred. In the construction industry, schedules may be updated in order to monitor
the time and work in construction projects (Liu and Shih, 2009). The importance of
schedule updates are as mentioned by Liu and Shih (2009): (1) compare the original
schedule with the actual progress of the project; (2) identify all delayed activities; (3)
identify who or what is responsible for delays; and (4) forecast and modify projected
work progress based on actual progress. Once the delay has been identified, JKR
normally required the contractor to prepare the recovery plan. By using the
rescheduling process, the JKR will determine the actual strength of the contractor to
complete during the contract period. Based on the schedule update, a delayed
activity was identifying and usually, rescheduling is required due to the delayed
work. Thus, rescheduling is one of the effects of delay in construction projects. The
contractor should prepare the Recovery Plan by using the 4M methods.
2.5.3 Extension of Time (E.O.T)
Extension of time is an event where extra time is requested in order to
complete the project (USLegal, 2010). According to Odeh and Battaineh (2002),
client-related delay is the major factor contributing to delays. Thus, contractors can
claim suitable EOT if the cause of delay is beyond the control of the contractor and is
brought about by client-related factors (Othman et al., 2006). This is mentioned by
Williams (2003) in his study on assessing Extension of Time delays on major
21
projects. Usually contractors can claim EOT due to client or owner related delays in
construction projects. In JKR contractor entitled to get EOT for reasons or causes of
delay which is beyond his control accordance with Clause of Contact (COC). The
S.O of project only has one deligation of power based on COC to approval the EOT.
The next application of the EOT must present to EOT Community at Head Quarters
2.5.4 Liquidated Damages (LAD)
According to Twyford (2007), in the construction contracts liquidated
damages clauses are usually inserted to promote compliance with time provisions, in
particular, completion of the work and payment on time. In regard to completion of
the work, a typical clause will provide that if the work is not completed by the
extended date for completion, liquidated damages, at the daily rate provided by the
schedule, shall become due and payable. A similar provision is made for overdue
payments under the contract. Liquidated damages clauses have the virtue of
informing both parties to a contract in advance what the damages payable for an
identified breach will be at the time of entering the contract. This can be equal
advantage to the party who must pay the damages as it is to the party receiving the
damages. The upper limit of the damages payable is fixed and a party can take this
into account in the initial negotiations. It is not uncommon for a contractor who
knows him or she cannot complete within the required time to add the liquidated
damages equivalent of the time overrun to the tendered price.
In JKR, if the contractor fails to complete the works by the Completion Date,
the SO shall issue a certificate of Non-completion. Upon the issuance of the
certificate of Non-Completion the contractor shall pay or allow to the JKR a sum
calculated at the rate stated as Liquidated Damages for the period from the
Completion Date to the Date of Practical Completion. LAD only allow not more than
60 day after Certification Non- Compliance
22
2.5.5 Termination of Contract
A construction contract could terminate for cause or for convenience.
Termination for cause occurs when one party stops work because of a deficiency in
performance by the other party. If the contract was terminated because of a party's
own poor performance, the law typically provides the terminated party with little
recourse in the event of a termination for cause. A termination for convenience, by
contrast, occurs when the owner stop their work for a reasons other than a deficiency
in performance by the contractor. Based on a letter from Deputy Director General
(Business Sector) reference no (38).dlm.JKR-KPKR:109.010/08 dated 30 July 2010,
the S.O should present the project in Jawatankuasa Projek Sakit to get the approval
for termination.
2.5.6 Appoint the Third Party (Kontraktor Penyelamat)
In some cases, because the main contractor was terminating, the project is
abandoned. To restart it will need to appoint ‘kontraktor penyiap’ or ‘kontraktor
penyelamat’. Re-measurement has to be done and price increases of materials have
to be impute so we find the project cost has definitely ballooned and effect the
duration of time. The project is already delaying because to appoint a new contractor
alone will take seven months. In JKR, normally the process of the reappoint the
contractor was using the selected tender. A list of the capable contractor with the
good track record was suggesting to the Ministry of Finance to continue the project.
2.6 Contemporary Approach in JKR Project to Minimize Delay
Besides that, JKR also introduce the contemporary approach to avoid projects
delay and speed up delivery of the project to the client. The contemporary methods
were exposed in implementation of the Rolling Plan (RP) project in Tenth Malaysia
Plan (RMK10).
23
2.6.1 Industrialised Building System (IBS)
Industrialized Building System (IBS).is a term used in Malaysia for a
technique of construction where components are manufactured in a controlled
environment, either at the site or off site, placed and assembled into construction
works. JKR has started to implement IBS to all the government projects for the
projects with a value of more than RM10 million accordingly based on Surat
Pekeliling Perbendaharaan Bil.7 Tahun 2008. Although JKR has adopted the IBS
system since 2008, there are still anticipated delays in the projects. There are
projects that are not complete on time, and has requested for Extension of Time
(EOT). This issue has been monitored and the data was compiled from the project
monitoring system used in SKALA system.
2.6.2 Building Information Modeling (BIM)
Building Information Modeling' (BIM) BIM was introduced nearly ten years
ago to distinguish the information rich architectural 3D modeling from the traditional
2D drawing. Base on the current statistic, the JKR BIM Department is carrying out
two pilot projects using BIM technology. One of the objectives implements BIM in
JKR is to improve the delivery of projects.
2.6.3 Project Health Check (PHC)
Most projects are sick and JKR do not even realize the extent of their
sickness and high percentage of projects finish behind schedule. To reduce the risk of
project failing and improve quality of project, a quick independent assessment of the
overall state of health of a project to be carried out to identify the strength and
weakness of the project as early warning detection and develop recovery plan.
Project Health Check (PHC) can be performed at any time during the project life
cycle. It is highly recommended for the new project that required project
management application. The implementation of the PHC based on selected projects
only. Lack of qualified personnel was one of the factors this method cannot be
implemented in all JKR projects.
24
2.6.4 Project Management Plan (PMP)
PMP is a Project Management Plan for the document provided to help project
managers to implement project management based on best practices. PMP is to use a
template that was developed by PROKOM, JKR where it consists of nine (9) key
knowledge areas in the Project Management and integrated with Total Quality
Management (TQM). PMP was designed to replace the QPLAN template in the
SKALA.
2.6.5 Accredited Project Manager Program
JKR also has embarked on a qualified project manager. Project Manager
Competency involves the knowledge, skills and attitudes of the Project Manager.
Knowledge of project management is applied through a course management projects.
However, the skills gained from practicing or practice of the knowledge gained. JKR
need to increase the number of competent project manager. Competent project
manager can derived the implementation of project successfully with on time project
delivery, within agreed cost and high quality.
2.6.6 Risk Management
Definition of risk management is the “coordinated activities to direct and
control an organization with regard to risk” (ISO 31000:2009). Risk management
includes the processes concerned with first identifying, analyzing and evaluating the
risks presented by the acquisition and/or development of the product, secondly
determining cost-effective treatments for those risks and thirdly implementing the
risk plan, while continuously monitoring and reviewing the plan. JKR also
implement Risk Management to achieve the objective such as minimize project
management by crisis, minimize surprises and problems, increase probability of
project success and better handling of true cost and schedules by planning
contingencies. Risk management was also been determined to be a part of the pre-
condition for the implementation of projects over RM 50 million.
25
2.6.7 Value Management
Value management is defined as a structured, analytical and team oriented
process to explicit the functional benefits of a project and to appraise needs,
problems or opportunities to seek best value system determined by the client. VM
implementation becomes mandatory to the Malaysian Government projects worth
RM50 millions and above (Circular by Economic Planning Unit - EPU, Jabatan
Perdana Menteri “Garis Panduan Pelaksanaan Pengurusan Nilai Bil. 3/2009” dated
29 December 2009). Generally, there are three (3) main interventions of VM in the
Malaysian Government project life cycle. They are termed as Value Assessment
(VA) at the Strategic Planning Stage, Value Engineering (VE) at the Design Stage
and Value Review (VR) at the Use Stage.
2.7 Conclusion
Delay problem is the barbed question in construction business. The cause of
delay in construction stage arises from innumerable factors. The dilemma cannot be
solved thoroughly, if these factors are not identified and restricted or eliminated.
However, the constraint of time and finance does not allow project manager to solve
all influencing factors, so it is necessary to identify the method in minimize the
delay. By understanding this chapter, various information regarding the causes,
methods to mitigate delays and the current practice at JKR were obtained.
26
CHAPTER 3
RESEARCH METHODOLOGY
3.1 Introduction
Research methodology is a way to provide a guideline for researcher to
achieve the aim and objectives of the study. This chapter shows the chronological of
research methodology and discusses the methods of conducting research in order to
achieve the objectives. .
3.2 General Approach of Research Design
Data collection is the most critical part since the accuracy of the data obtained
will determine the success or failure of this research. The data of this research has
been collected through the literature review, interview with the expert panel and
survey questionnaires
3.3 Literature Review
All information regarding delays in construction project was gathered through
a literature review. Literature review has been carried out to enhance the
understanding of theory regarding the research problem. The materials for literature
reviews are generated from books, articles, magazines, internet, journals, documents,
27
and other’s research papers. These reading materials provided a good primary source
for the research. The information, which is relevant, was used as a benchmark
against primary data collected to support the research.
Document search from the JKR documents/seminar papers/speeches was also
done. The speeches were from the Works Minister, the Director General, or other
high-ranking officers in the public service that is related to JKR projects delay.
Review papers has been made on that presented by JKR officers in various seminars
or conferences, which was relate to this research area.
3.4 Interview with Expert Panel
An interview is a verbal interaction between two or more people where one
person (the interviewer) implicitly directs the flow of information. It is a tool to find
out what is on someone’s mind, i.e. to find out from them what is on their mind,
which we cannot observe. Interviews can be conducted face to face, by telephone or
by email. Interviews have become a favorite method of gaining information such as
the collection of data to answer a research question. In this study, the type of
interview that was used is semi-structured interview. Semi structured interview It is
more of qualitative to research and the data collection is not too rigid. The questions
asked are normally open questions and the order is varied since a particular response
will lead ones to other questions.
According to Fischer and Tatum (1997), interviews proved preferable to
questionnaires as the knowledge acquisition method because they allowed direct
interaction between the expert and the interviewer. Besides, a personal interview
process was the best data collection technique for the type of detailed information
required (O’Connor and Miller, 1993)
The interviews with expert were carried out onto 5 JKR officers. As for
JKR staff, the interviews were carried out on the middle management staff. They
28
were at Principal Assistant Directors or Senior Construction Manager or Senior
Project Managers levels. They are holding senior posts in JKR (all grades J52
above). They have at least 20 years of experience behind them. The interviews
were mostly face-to-face interviews whereas one was done through the phone and
one was through emails. The data collected from the interview then was analyzed
and as a basis of questionnaire survey design Samples of questions are as in Table
3.1
Table 3.1: List of Interview Question
No. Interview Question
1. a. There have several factors identified causes of delay in JKR project.
Therefore, based on your experience, could you describe and explain the
causes of delay in JKR project implementation.
b. It is the delay causes similar with previous (e.g:10 years ago) and
today.
2.. The problems stated above, what is the current practice in JKR to solve
the project delay? Rescheduling, E.OT, L.A.D, and Termination of
Contract are the current practice in JKR. Do you agree?
3. With all the method that we already implement, why it is still happening?
4. What is the limitation that JKR facing by using this traditional approach?
5. How about the impact of project implementation the effect of project
delay in term of time overrun, cost overrun, quality and also customer
satisfaction?
6. What is the alternative approach, which practice by JKR to minimize
project delay? Are we in practice using collaborative teamwork, using
alternative procurement system, developing communication channel for
the project team, etc?
7. What challenges or hurdles that you faced in implementing projects at
JKR now day?
29
Table 3.1: Interview Question (Cont’d)
No. Interview Question
8. What is the difference of using IBS, BIM in a project comparing the
conventional method?
Its new systems are more helpful, acceptable, & practical or otherwise,
JKR still convenient using conventional method?
9. Can you identify any improvements in project implementation at JKR
especially in delivery project on time?
…with using new latest construction technology method like IBS, BIM,
approach Project Management Plan, Project Health Check, etc
10. How about using contemporary approach such as collaborative teamwork,
using alternative procurement method, clear information, and proper line of
communication channel?
11. How to avoid delay in every stage project life cycle?
Did JKR have any model for the delivery of projects on time or checklist to
make sure the project is ready to take off? Refer to appendix .
12. In your opinion, can we improve delivery project to the client with consider
the triple constraint with is time, cost and quality and client satisfaction?
3.5 Questionnaire Survey
The questions were designed related to the research objectives especially on the
causes of delays and proposed methods to minimize delays. Before designing the
questionnaire, there a very important point that needs to be considered. The questions
have to be short and precise without touching any sensitive or confidential issues as
reject may be offended (Taylor S, 2005). The purpose is to facilitate the respondent’s
understanding. Subsequently, the questionnaires were sent to 150 respondents with the
proportion of 2:1 in Business Sector and Design Sector.
Questionnaires were created based on the information gathered from interview
with the expert panels and literature review. A thorough checking for the questionnaire
has been made to evade any mistake and to ensure only relevant questions is included in
the form.
30
The questionnaires were separated into four (4) main sections. The respondents
were general asking about their personal and organization background in section A.
Subsequently, in section B, the respondents were asked to state the fifty seven (57) delay
causes, according to their local working experience in construction industry. Next,
section C is about the effectiveness of the traditional approach in JKR dealing with
project delay. Lastly, Section D is about the contemporary approach attribute / methods
that minimize construction project delays. Respondent were required to give their
opinion regarding the effectiveness of minimizing delays method.
.
3.5.1 Section A
Section A is to obtain the information of respondent’s background as well as their
organization and their experience in dealing with project management. The typical
questions that was asked include the following:
The Grade of the respondent in organization
The department in which the respondent represents
The experience of the respondent in years of service at JKR
The experience of the respondent in project management
The type of building which involved most frequent delay
The number of project delay faced by respondent
The actual time spent for the delayed project
3.5.2 Section B
Section B is to obtain the information on causes of delays in construction
projects. There were seven categories with fifty-seven factors of delay causes
identified in this structures question. This section requires the respondent to answer
the frequency of occurrence as well as the severity of their project based on the delay
causes given.
The questionnaire is based on Likert Scale of five ordinal measures from one
(1)to five (5) according to level contributing. According to John F. (2001), Likert
Scale iseasier to use for respondent to express their level of opinion. For the
31
frequency of cause’s occurrence, each scale represents the rating as shown in Table
3.2.
Table 3.2: Likert Scale Grade Section B
Feedback Scale
Strongly Agreeable 5
Agreeable 4
Moderately
Agreeable
3
Slightly Agreeable 2
Least Agreeable 1
3.5.3 Sections C
This section is evaluating the effectiveness of the traditional approach in JKR
dealing with project delay. Eight (8) current practices dealing with project delay at
JKR was determined. The questionnaire is mainly based on Likert’s scale of five
ordinal measures from one (1) to five (5) according to level of ineffectiveness. Each
scale represents the following rating as shown in Table 3.3.
Table 3.3: Likert Scale Grade Section C
Feedback Scale
Highly Ineffective 5
Ineffective 4
Moderately
Ineffective
3
Low Ineffective 2
Least Ineffective 1
32
3.5.4 Sections D
This section is to identify the effective contemporary approach attribute and
methods of minimizing construction delays. Thirty-nine methods were identified
from several literature reviews, which used in the structured question. The
questionnaire is mainly based on Likert’s scale of five ordinal measures from one (1)
to five (5) according to level of effectiveness. Each scale represents the following
rating as shown in Table 3.4.
Table 3.4: Likert Scale Grade Section D
Feedback Scale
Highly effective 5
Effective 4
Moderately
Effective
3
Low Effective 2
Least Effective 1
3.5.5 Questionnaire Distribution
The respondents involved in this research were the JKR staff in business and
design sector. According to Paul Cozby (2003), a large sample data can give result
that is more accurate. Therefore, researcher had distributed about one hundred fifty
set of the questionnaire form. The respondent is randomly selected. A questionnaire
accompanied by covering letter briefly stating the objectives of the survey, was
issued to the selected respondents who were later followed up by telephone. There
were two main method been used for the purpose of this questionnaire distribution;
via mail delivery and by hand method.
33
3.6 Data Analysis
Data that have been collected were analyzed separately according to the
source of data. The data gathered from the interview will be analyzed by
qualitative analysis which using descriptive analysis. Meanwhile, the data
collected from the questionnaire survey will be analyzed by quantitative analysis
by using frequency and mean score statistical analysis. The data will be analyzed
using software so called Statistical Packages for Social Science (SPSS).
3.6.1 Data Analyses and/or Analysis of Information
All information collected from the exploratory interviews and data from the
questionnaire survey was analysed and discussed in Chapter 4 and Chapter 5
respectively.
3.6.2 Exploratory Interviews and Documents Search
The information from the exploratory interview was an analysis using the
content analysis. The main points were tabulated and the main parameters that
constituted as causes of delay were listed to be used later in the questionnaire
surveys. The same was applied to documents in search where any potential causes of
delay was also listed and later used for the questionnaire survey.
3.6.3. Reliability Analysis: Cronbach’s Coefficient Alpha
Cronbach’s coefficient alpha is normally used to test for reliability of data
collected. It is a commonly used technique, internal consistency analysis employed to
measure the reliability of each derived factor in the factor analysis. Using SPSS
reliability analysis program, the analysis was performed separately for the items of
each critical factor (Antony et al, 2002). Black and Porter (1996) was cited by
34
Antony et al, (2002) that generally an alpha of 0.6 or higher (≥ 0.6) will be
considered adequate in exploratory research.
3.6.4 Normality Tests
The Normality Test is the pre-requisite for most of the statistical analysis
based on data collection and inferences statistics. The test is to determine whether a
data set is well modelled by a normal distribution or not. Two methods were used to
test for normality.
a) Kurtosis and Skewness Parameters
In statistics, kurtosis is a measure of the “peakedness” of the statistical
distributions. Skewness is a measure of the asymmetry of the probability distribution
of areal-valued random variable. The skewness value can be positive or negative, or
even undefined. The values of these skewness and kurtosis must be within the range
of ± 2.0 (Chua, 2006). These values were calculated using the SPSS version 18
software.
b) The histograms and Q-Q plot
From the SPSS analysis, when testing for normality, the main area of interest
was the Test of Normality Table and Normal Q-Q Plots. These were the numerical
and graphical methods to test for normality respectively. An informal approach to
testing normality is by plotting the histogram of the collected data. The empirical
distribution of the data (the histogram) should be bell-shaped and resemble the
normal distribution. Normal Q-Q Plot will show a straight line if the data to be
analysed are normally distributed.
35
3.6.5 Relative Importance Index (RII)
Relative Importance Index is the evaluation of the ranking of the questions
relative to other questions in the survey. The weighting is based on the responses to
the questionnaire surveys. It is governed by the formula:
RII = ∑ {[n1x1] + [n2x2] + [n3x3] + [n4x4] + [n5x5]}
∑nix 5
Where:
RII = Relative Importance Index
ni = frequency of occurrence for Likert value i
1, 2,3,4,5 = the Likert Scale chosen
The index value for any given factor is not more than 1. The higher the value
of RII, the higher the importance of the factors compared to the others. These values
were calculated using the Excel Spreadsheet and presented in Chapter 4.
3.7 Conclusion
This study was designed to examine the effectiveness of the traditional
approach in JKR, proposed the cotemporary approach to minimize the delay and
develop guidelines for on time project delivery This study used a descriptive
quantitative approach that finds to understand critical elements to identify the aim of
study. Data was obtained by literature review, interview with expert and
questionnaires.
All questionnaire go through for Normality test before distribute to all
respondent. A resuts from Chronbach's Alpha equals to > 0.7 which refers to an
excellent reliability of the entire questionnaire. So, the questionnaire was considered
valid, reliable, and ready for distribution.
36
CHAPTER 4
DATA COLLECTION AND ANALYSIS
4.1 Introduction
This chapter presents the data analysis and discussions based on the interview
with the expert panel and questionnaire survey. The collected were analyzed using the
method as mentioned in Chapter Three.
4.2 Content Analysis of the Interviews with Expert Panel
: The expert panel respondents and method used was tabulated below-
Table 4.1: Method of used Interview with Expert Panels
No. Respondents Organization Method Used
1.. Respondent #1 JKR Face to face
2.. Respondent #2 JKR Face to face
3.. Respondent #3 JKR Telephone
4.. Respondent #4 JKR Telephone
5.. Respondent #5 JKR Face to face
37
The summary of the interviews were analyses using content analysis method
as tabulated in, Table 4.2. The factors of delays issues gathered from the interviews
were listed below. This is the raw factors without amendments even though some of
them were repetitive.
38
Table 4.2: Summary of Interview Session with Expert Panels
Question Respondent #1 Respondent #2 Respondent #3 Respondent #4 Respondent #5
Q1 a)There have a several
factors identified causes of
delay in JKR project.
Therefore, based on your
experience, could you
describes and explains the
causes of delay in JKR
project implementation.
Agree with 7
categories factor
The respondents
highlight major causes
of delay is because
of:-
i.Poor site
management.
ii.Improper planning
Agree with 7
categories factor
The respondents
highlight major
causes of delay is
because of:-
i.Unrealistic project
time
ii.Poor supervision
Agree with 7
categories factor
The respondents
highlight major
causes of delay is
because of:-
i.Lack of consultant
experience
ii.Capabilities of
contractor
Agree with 7
categories factor
The respondents
highlight major causes
of delay is because
of:-
i.Building Permit
ii.Competent Project
Manager
Agree with 7
categories factor
The respondents
highlight major
causes of delay is
because of:-
i.Less communication
ii.VO
iii.EOT
b) It is the delay causes
similar with previous
(e.g:10 years ago) and
today.
Yes Yes Not 100% Yes Yes
Q2 With the problems
stated above, what is the
current practice in JKR to
solve the project delay?
Rescheduling, E.OT,
L.A.D, and Termination of
Contract is the current
practice in JKR. Do you
agree?
Agreed
Add warning letter
Current practice need
to review especially
term of termination
and LAD
Agreed
Add Jawatankuasa
Projek Sakit.
Closely monitoring
Agreed
Current practice
need to review
Agreed
Current practice need
to review
Agreed
Current practice need
to review. Imposed
the LAD by monthly
basic and include in
the COC
39
Table 4.2: Summary of Interview Session with Expert Panels (Cont’d)
Question Respondent #1 Respondent #2 Respondent #3 Respondent #4 Respondent #5
Q3 With all the method
that we already implement,
why it is still happen?
Lack of Monitoring Lack of skills and
experience
Not 100%
implement the COC
SYMP Personnel not
competent
Q4 What is the limitation
that JKR facing by using
this traditional approach?
Only give EOT, LAD
and termination
EOT- Easy to get
the approval from
SO
LAD not 100%.
Imposed.
MOF involved and
give waiver to
contractor
Time and cost
constraint
Litigation
Reputation of JKR as
technical department
Q5 How about the impact
of project implementation
the effect of project delay
in term of time overrun,
cost overrun, quality and
also customer satisfaction?
The most important
customer satisfaction.
Bad reputation
Major effect of
delay to client in
term of cost and
time
Negative effect Yes The impact so big.
Some of the client did
not continue doing
project with JKR
Q6 What is the alternative
approach which practice by
JKR to minimize project
delay? Are we in practice
using collaborative team
work, using alternative
procurement system,
developing communication
channel in project team?
Not 100 %
Just pilot case for BIM
and PMP
No training for the
staff. All the new
approach need the
proper planning and
must make sure all
the staff know
Risk Management
Plan
Project Health
Check
Using IBS
Sistem Perolehan
Alternatif
BIM
Scheduling
Qualified Project
Manager
Matrix system not
functional well
Need some review.
Delivery project not
in stipulated time that
agreed with client
40
Table 4.2: Summary of Interview Session with Expert Panels (Cont’d)
Question Respondent #1 Respondent #2 Respondent #3 Respondent #4 Respondent #5
Q7 What challenges or
hurdles that you faced in
implementing projects at
JKR now day?
Too many procedure
and SOP which is
need to review back
Attitude of the new
officer.
Not competent
Delivery system
need to review
Short of man power
Less experienced of
contractor and
consultant
HODT cannot follow
the time line set up
by HOPT
Q8 What is the difference
of using IBS, BIM in
project comparing the
conventional method?
It’s is new systems are
more helpful, acceptable &
practical or otherwise, JKR
still convenient using
conventional method?
Yes but the limitation
of service provider
Yes Not 100% successful Shortage of time in
delivery project to
client
Quality improvement
Q9 Can you identify any
improvements in project
implementation at JKR
especially in delivery
project on time?
…with using new latest
construction technology
method like IBS, BIM,
approach Project
Management Plan, Project
Health Check, etc
Case study NIC Not sure because
the implementation
just only for the
pilot project only
The current project
using this approach
is Naiktaraf Hospital
Kuala Lumpur
Only 50% of the
project was
successfully because
of the working culture.
Only monitor for the
auditing processes not
as routine in
workplace
Institut Kanser
Negara is the best
practice of Project
Management.
Projects complete
ahead the schedule.
41
Table 4.2: Summary of Interview Session with Expert Panels (Cont’d)
Question Respondent #1 Respondent #2 Respondent #3 Respondent #4 Respondent #5
Q10 How about using
contemporary approach
such as collaborative team
work, using alternative
procurement method, clear
information and proper line
of communication channel?
Communication with
stakeholder need to be
focus.
Reporting and briefing
the progress report to
stakeholder is the best
practice to avoid
delays
No proper line
communication
because HOPT not
control.
New approach need
training for staff
Good but need to do
the pilot case to
measure the
effectives
No experience using
all the method that
mention
JKR must have the
new line up officer to
implement all the
new strategy
approach, reduce
birokrasi, and work in
cross functional
teamwork
Q11 How to avoid delay in
every stage project life
cycle?
Did JKR have any model
for the delivery of project
on time or checklist to
make sure the project is
ready to take off? Refer
appendix
ACAT
Gerbang Nilai
Agreed with the list of
activity and duration
of time proposed in
the guidelines
3 constraint – Land,
Brief of Project and
Cost
Gerbang Nilai
Agreed with the list
of activity and
duration of time
proposed in the
guidelines
Not sure
Agreed with the list
of activity and
duration of time
proposed in the
guidelines
ISO (SPB) JKR as one
of the tool.
Gerbang Nilai
Agreed with the list of
activity and duration
of time proposed in
the guidelines
SKALA not register
if the brief not
completed.
No proper work flow
in delivery project
accept for ISO (SPK)
Agreed with the list of
activity and duration of
time proposed in the
guidelines
42
Table 4.2: Summary of Interview Session with Expert Panels (Cont’d)
Question Respondent #1 Respondent #2 Respondent #3 Respondent #4 Respondent #5
Q12 In your opinion, can
we improve delivery
project to the client with
consider the triple
constraint with is time, cost
and quality and also client
satisfaction?
Yes. Client are more
concern on project
delivery with accepted
quality and time
Yes.
Must follow the
contact. All the
specification is
there.
Just follow the
guidelines.
To ensure JKR
project team are
competent. HODT &
HOPT
Delivery project
become the KPI. If the
SO failed to achieved
the KPI , the project
team can be penalty
and down grade.
Supporting from the
top management.
Blue ocean strategy
with the client and
other technical
department in JKR
project
implementation
43
4.3 Documents Search
Documents search was done on the paper that present in the Mesyuarat
Jawatankuasa Pengurusan Pemandu (JPP) JKR chair by Director General of PWD
and on the speeches that were related to JKR project management. What is available
below is the related paper regarding Project Delays.
In the first National Asset and Facility Management (NAFAM) Convention,
Tan Sri Mohd Sidek Hassan, the Chief Secretary to the Government of Malaysia,
pointed out all civil servants must ensure that the projects are implemented carefully
monitored and enforce existing policies and regulations to avoid delay. Contractors
who fail in their service should be eliminated from the system. (NAFAM @1, 2007).
During the opening remarks of the second National Asset and Facility Management
(NAFAM) Convention 2009, the Director General of JKR stressed that the criteria of
project implementation is not based on the lowest cost and emphasized should also
be given to the aspects of value-added to the projects and the optimum usage of
resources. (NAFAM @2, 2009). At the same convention, Tan Sri Mohd Sidek
Hassan, the Chief Secretary to the Government, insisted that stern action be taken to
the contractors who do not implement what has been agreed in the contract. He also
mentioned that we have to be fair to the contractors by expediting the payments due
to them. On top of that the existing guidelines and procedures are well defined and
the officers have to enforce them (NAFAM @2, 2009).
In addition there are two papers was presented at the Mesyuarat Jawatankuasa
Pengurusan Pemandu (JPP) Bil. 20/2013 dan Mesyuarat Jurutera Daerah Bil. 4/2013
involves issues related to the project delays. This paper describes the performance of
the physical progress of current JKR projects and also describes the trends that have
been identified for the project to be late / sick. Measures to overcome problems later
projects were also discussed and refined by the members. The two papers were-
i. Laporan Khas Projek Lewat > 2 bulan & Projek Sakit
Mesyuarat Jawatankuasa Pemandu Pengurusan (JPP) Bil. 20/2013
(1 October 2013)
44
ii. Cadangan Pelan Tindakan Projek Sakit JKR -
Mesyuarat Jurutera Daerah Bil.4/2013 (18 November 2013)
Tan Sri Dato Setia Haji Ambrin bin Buang, Auditor General National Audit
Department in his speech entitled Enhancing JKR Performance – An Audit
Perspective, in JKR Senior Officers Conference in Terengganu (JKR SOC, 27-29
May 2013 )stressed that the problems in managing JKR project could be minimized
if all the officers involved have good attitude, skills and knowledge and high
integrity values. He also pointed out that weaknesses in the audit reports of these
projects are usually very delayed , or significantly increased project costs and the
project faces many and serious defects which are due to the following factors Site
supervision or poor site supervision and the other is poor contract administration,
lack in project monitoring, and human errors. He also highlight about learnt lessons
of value management, which is currently a standard procedure for planning
government project. Value management is crucial for maximize value for money for
important criteria such as site, project scope, design, maintenance etc. to reduce the
cost and reduce the risk of troubled projects.
4.3.1 Gerbang Nilai (Gateway)
Gateway is an adaption of the United Kingdom’s Office of Government
Commerce (OGC) Gateway Review Process to improve the delivery of major
projects (Gershon, 1999). Concepts of Gateway Review were to help Government
deliver best value from its spending. Key decision points in their lifecycle to provide
assurance that they can progress successfully to the next stage. Gateway is being
introduced in 10th Malaysia Plan. In ensuring the success of the whole project
undertaken by JKR, Gerbang Nilai review shall be imposes to all projects above
RM5 Million.
Based on the factor the guidelines unfold in the following sequence:-
i. Gateway 1 - Planning stages
ii. Gateway 2 - Design stages
45
iii. Gateway 3 - Procurement stages
iv. Gateway 4 - Construction
4.3.2 Estimation of Time in Project Implementation
Based on the Letter from the Director General PWD to Director General
Of Economic Planning Unit (EPU), Prime Minister Department dated 25 September
2013, JKR already set up the time frame for project delivery in the Pre-Contract
phase which include Planning, Design and Procurement. The summary for time
estimation Pre-Contract in JKR project as shows in Table 4.3 below:-
Table 4.3: Estimation Time in Pre-Contract Phase
Phase Planning Design Procurement Total
Conventional
In House
113 days 178 days 70 days 361 days
Conventional
Consultant
107 days 178 days 70 days 355 days
Design & Build 167 days 80 days 90 days 237 days
For construction phase the duration of project were based on cost, scope of
works and the complexity of the project and scope of work. While for the handing
over stage project will hand over to the client normally three (3) months after the
Certificate of Practical Completion (CPC) was issues. The summary for time
estimation Construction stage in JKR project as shows in Table 4.4 below
46
Table 4.4: Estimation Time in Construction Phase
Type of Project Cost <
RM 500,000
Cost between
RM 500,000 to
RM 5 Million
Cost > RM 5
Million
Building 15 month 24 month 36 month
Road &
Infrastructure 9 month 24 month 36 month
Project Complex Duration based on time agreeable with the Client
4.4 General Background of Questionnaire Survey Respondents
This section will discuss and analyze the first part of the questionnaire which
consists of seven questions that focus on the general information about the JKR staff.
The general information about the JKR staff include grade, years of service, years in
project management, department, type of the most building delays, number of executed
projects delay faced and actual time spend for the delayed project.
There is a one hundred fifty (115) set of survey questionnaire was distributed
to the targeted respondent in order to achieve the objective. The total numbers of
questionnaire distribution and responses have been analyzing and shown in table 4.5
and table 4.6 below.
Table 4.5: Distribution of Questionnaire Based on Sector
Organization Total
Distributed Total Return Respond Rate
JKR
(Business Sector)
100 83 83%
JKR
(Design Sector) 50 36 72%
Total 150 119 77.5 %
47
Table 4.6: Distribution of Questionnaire Base on Organization–
Organization Frequency Percentage Cumulative
Percentage
Project Management Office (PMO) 8 6.7 6.7
Cawangan Kejuruteraan Elektrik (CKE) 5 4.2 10.9
Cawangan Pangakalan Udara & Maritim
(CPUM)
4 3.4 14.3
Cawangan Kejuruteraan Mekanikal
(CKM)
3 2.5 16.8
Cawangan Arkitek (CA) 5 4.2 21.0
Cawangan Alam Sekitar & Tenaga
(CAST)
1 0.8 21.8
Cawangan Kontrak & Ukur Bahan
(CKUB)
2 1.7 23.5
Cawangan Kejuruteraan Senggara (Ck
Senggara)
2 1.7 25.2
JKR Kedah 1 0.8 26.1
JKR Selangor 1 0.8 26.9
Cawangan Kerja Bangunan Am (CKBA) 22 18.5 45.4
Cawangan Pendidikan & Pengajian
Tinggi (CPPT)
7 5.9 51.3
Cawangan Kerja Kesihatan (CKK) 10 8.4 59.7
Cawangan Kerja Keselamatan (CKS) 2 1.7 61.3
Cawangan Pengurusan Korporat (CPK) 9 7.6 68.9
Cawangan Kejuruteraan Jalan &
Geoteknik (CKJG)
8 6.7 75.6
Cawangan Pengurusan Projek Kompleks
(PROKOM)
7 5.9 81.5
Cawangan Kejuruteraan Awam &
Struktur and Jambatan (CKASJ)
10 8.4 89.9
Design 2 1 0.8 90.8
District 1 0.8 91.6
JKR Woksyop Persekutuan 1 0.8 92.4
KADER 1 0.8 93.3
Kem.Perumahan Kerajaan Tempatan 1 0.8 94.1
Kementerian Luar Negeri 1 0.8 95.0
KKR 1 0.8 95.8
MINDEF 1 0.8 96.6
PAKAR 1 0.8 97.5
State 1 0.8 98.3
Unit JKR KESEDAR 1 0.8 99.2
Unit Penyelidikan 6 1 0.8 100.0
Total 119 100.0
48
4.4.1 Grade
This question refers to the grade of respondents in JKR organization. Figure
4.1 shown that 70 or 58.8% of the respondents are the officer grade 41/44, 38 or
31.9% of the respondents are officer grade 48/52 and 11 or 9.2% of the respondents
are officer grade 54. It can be concluded that officer grade 41/44 is the most
respondent who participate in this survey. Thus, the respondents are eligible person
to giving this research’s data.
Figure 4.1: Grade of Respondents in Organisation
4.4.2 Years of Experience
The years of experience is divided into four categories include less than 5 years
of experience, 6 to 10 years of experience, 11 to 15 years of experience, 16 to 20 years
of experience and more than 21 years of experience. The results from figure 4.2 shows
that 27.7% of the respondents with less than 5 years’ of experience, 38.7% of the
respondents with 6-10 years’ of experience, 11.8% of the respondents with 11-15
years’ of experience, 6.7% of the respondents with 16 -20 years’ of experience and
6.7% of the respondents with more than 20 years’ of experience
49
Figure 4.2: Years of Experienced
The experience possess by the respondents may helps in providing a better
understanding of this matter and in better position in giving much precise answer
required to the questionnaires form. However, it would be better if the percentage of
respondents whose experiences are 15 years or more can be increased. In fact, these
ratios reflect the current phenomenon of local industry, that is a large amount of
young practitioners have been graduated in current years to meet the vast human
demand, and they have got high positions in their organizations. Figure 4.3 shows
years of the experience in project management by the respondents. 60.5% of the
respondents with less than 5 years’ of experience, 21.0% of the respondents with 6 -
10 years’ of experience, 7.6% of the respondents with 16-20 years’ of experience and
11.0% of the respondents with more than 20 years’ of experience in project
management.
50
Figure 4.3: Years of Experienced in Project Management
4.4.3 Types of Building Projects Frequently Delays in JKR
The types of building is divided into 5 categories include school, office, public
facilities, hospital and others. The results from Figure 4.4 shows that 39 or 32.8% of
the respondents choose hospital as the type of frequently delays, 29 or 24.4% of the
respondents choose office building, 27 or 22.7% of the respondents choose school
project, 15 or 12.6% of the respondents choose public facilities project and 9 or 7.6%
of respondents choose others project such as road and bridge.
Figure 4.4: Type of Building Frequently Delay
51
4.4.4 Numbers of Project Delay
This question refers to the number of executed projects delay which the
respondent participated. The classification of the number of projects includes 1 to 3
projects, between 4 to 6 projects, from 7 to 9 projects, between 10 to 12, and more
than 13 projects. The results indicate that 47.9% of the respondents with 1-3 projects
delay, 34.5% of the respondents with 4-6 projects delay, 6.7% of the respondents
with 7-9 projects delay, 0.8% of the respondents with 10-12 projects delay and r
10.1% of the respondents with more than 12 projects delay. This is important to
ensure they are well qualified to offer reliable opinions on the questionnaire
according to results from figure 4.5.
.
Figure 4.5: Numbers of Executed Project Delay
4.4.5 Time Overrun
This question refers to the actual time taken by respondents to resolve the
project delay based on their experience. Any delay in the project can lead to time
overruns. Whatever the reason, the mistakes can have impact on the progress of the
project. Figure 4.6 shows that 56.3% of the respondents spend more than 6 month,
34.5% of the respondents spend 3-6 month and 9.2% of the respondents spend less
than 3 month to overcome the project delays. This time can consider an additional
time required to complete the project. The experience possess by the respondents
may helps in providing a better understanding of this matter and in better position in
giving much precise answer required to the questionnaires form.
52
Figure 4.6: Time Overrun
4.5 Testing on the Research Data
4.5.1 Reliability Analysis: Cronbach’s Coefficient Alpha
Cronbach-Alpha is one of the most commonly used for reliability analysis
test in statistical analysis. To be reliable as the rules of thumb about Cronbach-Alpha
coefficient size, the p value must at least 0.7 or better. Normally value of 0.7 or
higher of Cronbach-Alpha value will be considered acceptable in most social science
research situations. If the value is less than 0.6, some of the items would be dropped
from the questionnaire.
From the analysis, the Cronbach’s Alpha for all categories as shown in Table
4.6. .Since all value was higher than 0.6, there was no necessity to review the
questionnaire.
53
Table 4.6: Cronbach’s Alpha Value for Each Category in the Questionnaire
Reliability Statistics Cronbach's Alpha Remarks
Client Related 0.815 Section B
Contractor Related 0.857 Section B
Consultant Related 0.906 Section B
Material Related 0.873 Section B
Equipment Related 0.936 Section B
Labour Related 0.845 Section B
External Factor 0.839 Section B
Traditional Approach by JKR 0.776 Section C
Scope Management 0.817 Section D
Time Management 0.911 Section D
Cost Management 0.796 Section D
Quality Management 0.856 Section D
Communication Management 0.825 Section D
Human Resources Management 0.925 Section D
Risk Management 0.743 Section D
Procurement Management 0.801 Section D
Integration Management 0.862 Section D
4.5.2 Normality Test
For this study Normality test is performed by determining skewness and
kurtosis for all variables. All categories are well distributed. Histogram and Q-Q Plot
for the variables tested are shown at Appendix A.
54
4.5.3 Kurtosis and skewness Parameter
As may be seen in Table 4.7, all variables are normally distributed as the
skewness and kurtosis values are within the range of ± 2.0 (Chua, 2006).
55
Table 4.7: Result of Skewness and Kurtosis Values
Categories
CL
IEN
T R
EL
AT
ED
CO
NT
RA
CT
OR
RE
LA
TE
D
CO
NS
UL
TA
NT
RE
LA
TE
D
MA
TE
RIA
L R
EL
AT
ED
EQ
UIP
ME
NT
RE
LA
TE
D
LA
BO
UR
RE
LA
TE
D
EX
TE
RN
AL
FA
CT
OR
TR
AD
ITIO
NA
L A
PP
RO
AC
H
JK
R
SC
OP
E M
AN
AG
EM
EN
T
TIM
E M
AN
AG
EM
EN
T
CO
ST
MA
NA
GE
ME
NT
QU
AL
ITY
MA
NA
GE
ME
NT
CO
MM
UN
ICA
TIO
N
MA
NA
GE
ME
NT
HU
MA
N R
ES
OU
RC
ES
MA
NA
GE
ME
NT
RIS
K M
AN
AG
EM
EN
T
PR
OC
UR
EM
EN
T
MA
NA
GE
ME
NT
INT
ER
GR
AT
ION
MA
NA
GE
ME
NT
Skewness -0.331 -0.680 -0.324 -0.370 -0.294 -0.558 -0.423 0.095 -0.156 -0.803 -0.272 -0.516 -1.002 -1.389 -0.635 -1.091 -1.162
Kurtosis -0.164 -0.333 -0.203 0.325 -0.108 0.243 0.216 -0.141 -1.157 -0.824 -1.134 -0.675 0.256 1.148 -0.377 0.490 0.524
56
4.5.4 Section B – Factor That Contribute to Delays of JKR Project
In this section respondent was giving 57 questions about the factors that
contributed to delay of JKR project. The question was divided into seven groups
The groups were Client Related (BA), Contractor Related (BB), Consultant
Related (BC), Material Related (BD), Equipment Related (BE), Labour Related
(BF), and External Factor (BG).
The data were first analyses on the reliability of the factors using
Cronbach’s Alpha. Results were shown in Table 4.8 for all the factors in Section
B. Results of Cronbach’s Alpha for Section B was acceptable as it ranged from
0.6400 to 0.773. Range of Cronbach’s Alpha value from the analysis was within
the acceptable category.
Table 4.8 : Cronbach’s Alpha Value for Section B
Code Categories Mean Relative Index
BA Client Related 3.484 0.697
BB Contractor Related 3.8655 0.773
BC Consultant Related 3.8471 0.768
BD Material Related 3.4776 0.696
BE Equipment Related 3.19998 0.64
BF Labour Related 3.7626 0.7525
BG External Factor 3.3349 0.6669
These factors were ranked in each group based on Relative Importance
Index (RII). The following is a brief description of these factors in each group.
57
4.5.4.1 Factors of Client Related Delays
In Table 4.9 show the results of survey analysis of factors of client related
delay. Factors to causes of delays were ranked based on Relative Important Index.
The results were acceptable as it ranged from 0.607 to 0.82. Slowness in decision
making was contributing the most of the client related delays. All the factor in the
client related was contribute to the delay in JKR projects.
Table 4.9: Ranking Relative Importance Index for Client Related
Code Client Related Mean Relative Index
BA2 Slowness in decision making process 4.1008 0.82
BA4 Change order 3.9328 0.787
BA1 Client Interference 3.6639 0.733
BA10 Not full fill JKR requirements in terms of
project site, scope and cost 3.5126 0.703
BA9 The land is not free from dispute 3.4706 0.694
BA3 Contract modification 3.4202 0.684
BA8 Unrealistic contract duration 3.4034 0.681
BA5 Client cannot provide enough fund 3.2437 0.649
BA6 Uncooperative client 3.0588 0.612
BA7 Late payment 3.0336 0.607
Average 3.4840 0.697
4.5.4.2 Factor of Contractor Related Delays
In Table 4.10 show the results of survey analysis of factors of contractor
related delay. Factors to causes of delays were ranked based on Relative
Important Index. The results were acceptable as it ranged from 0.692 to 0.859.
Poor site management and supervision was contributing the most of the contractor
related delays. All the factor in the contractor related was contribute to the delay
in JKR projects.
58
Table 4.10: Ranking Relative Importance Index for Contractor Related
Code Contractor Related Mean Relative Index
BB1 Poor site management and supervision 4.2941 0.859
BB2 Financial difficulties - Poor cash flow
management 4.2353 0.847
BB4 Inadequate contractor experience 4.1513 0.83
BB5 Conflicts in sub-contractor schedule in
execution of project 3.958 0.792
BB7 Conflicts between contractor ,others
parties (consultant & client) and also
partners (shareholder) 3.958 0.792
BB10 Delay in sub-contractors work 3.8824 0.776
BB6 Rework due to errors during construction 3.7731 0.755
BB3 Unsuitable construction materials and
improper construction method implement 3.6134 0.723
BB11 Frequent change of sub-contractors 3.605 0.721
BB13 Inappropriate or poor criteria for selection
of subcontractor 3.5882 0.718
BB12 Delay in site mobilization 3.4622 0.692
Average 3.8655 0.773
4.5.4.3 Factors of Consultant Related Delays
In Table 4.11 show the results of survey analysis of factors of consultant
related delay. Factors to causes of delays were ranked based on Relative
Important Index. The results were acceptable as it ranged from 0.667 to 0.824.
Poor communication and coordination was contributing the most of the consultant
related delays. All the factor in the consultant related was contribute to the delay
in JKR projects.
59
Table 4.11: Ranking Relative Importance Index for Consultant Related
Code Consultant Related Mean Relative Index
BC2 Poor communication and coordination 4.1176 0.824
BC8 Poor monitoring and control of progress
of work 4.0504 0.81
BC4 Mistakes and discrepancies in design
documents 4.0084 0.802
BC3 Inadequate experience of consultant 3.992 0.78
BC5 Delay in producing design documents 3.8487 0.77
BC6 Unclear and inadequate details in
drawings 3.8403 0.768
BC1 Delay in approving major changes in the
scope of work 3.8067 0.761
BC7 Insufficient data collection and survey
before design 3.7395 0.748
BC10 Late issue of instruction 3.7311 0.746
BC9 Late valuation work 3.3361 0.667
Average 3.8471 0.768
4.5.4.4 Factor of Material Related Delays
In Table 4.12 show the results of survey analysis of factors of material
related delay. Factors to causes of delays were ranked based on Relative
Important Index. The results were acceptable as it ranged from 0.645 to 0.745.
Noncompliance of material to specification was contributing the most of the client
related delays. All the factor in the material related was contribute to the delay in
JKR projects.
60
Table 4.12: Ranking Relative Importance Index for Material Related
Code Material Related Mean Relative Index
BD6 Noncompliance of material to
specification 3.7227 0.745
BD5 Late procurement of material 3.6134 0.723
BD2 Changes in material and specification
during construction 3.521 0.704
BD3 Delay in material delivery 3.5042 0.701
BD4 Damage of sorted material while they are
needed urgently 3.2773 0.655
BD1 Shortage of construction materials in
markets 3.2269 0.645
Average 3.4776 0.696
4.5.4.5 Factors of Equipment Related Delays
In Table 4.13 show the results of survey analysis of factors of equipment
related delay. Factors to causes of delays were ranked based on Relative
Important Index. The results were acceptable as it ranged from 0.618 to 0.655
Shortage of equipment was contributing the most of the client related delays. All
the factor in the equipment related was contribute to the delay in JKR projects.
Table 4.13: Ranking Relative Importance Index for Equipment Related
Code Equipment Related Mean Relative
Index
BE2 Shortage of equipment 3.2773 0.655
BE5 Lack of high-technology mechanical
equipment 3.2689 0.654
BE4 Low productivity and efficiency of
equipment 3.2437 0.649
BE3 Low level of equipment 3.1176 0.624
BE1 Equipments breakdown 3.0924 0.618
Average 3.19998 0.640
61
4.5.4.6 Factor of Labour Related Delays
In Table 4.14 show the results of survey analysis of factors of labour
related delay. Factors to causes of delays were ranked based on Relative
Important Index. The results were acceptable as it ranged from 0.666 to 0.798.
Shortage of manpower was contributing the most of the labour related delays. All
the factor in the labour related was contribute to the delay in JKR projects.
Table 4.14: Ranking Relative Importance Index for Labour Factor
Code Labour Related Mean Relative Index
BF4 Shortage of manpower 3.9916 0.798
BF2 Lack of skilled labour 3.9664 0.793
BF3 Low productivity level of labour 3.7647 0.753
BF1 Working permit of labours 3.3277 0.666
Average 3.7626 0.7525
4.5.4.7 Factor of External Related Delays
In Table 4.15 show the results of survey analysis of factors of external
factor related delay. Factors to causes of delays were ranked based on Relative
Important Index. Accident during the construction and traffic control and
restriction at job site was the factor not acceptable which the RII 0.548 and 0.578
62
Table 4.15: Ranking Relative Importance Index for External Factor
Code External Factor Mean Relative Index
BG1 Delay in obtaining permits from
municipality 3.7647 0.753
BG2 Slow process of Building Permit 3.6555 0.731
BG3 Delay in providing services from
utilities (such as water, electricity) 3.8908 0.778
BG4 Changes in Government regulations
and laws 3.0672 0.613
BG5 Accident during construction 2.7395 0.548
BG6 Traffic control and restriction at job
site 2.8908 0.578
BG7 Price fluctuation 3.3361 0.667
Average 3.3349 0.6669
4.5.5 Section C – Traditional Approach by JKR Dealing with Project
Delays
In this section respondent were given 8 questions about action taken by
JKR dealing with project delays. The questions were ranked in based on RII as
shown in Table 4.16 below.
63
Table 4.16: Ranking Relative Importance Index for Traditional Approach in JKR
Code Traditional Approach by JKR Mean Relative
Index
C3 Coordination meetings on a weekly basis to
monitor the progress of work on site by S.O.
closely (Weekly and Monthly report)
4.0756 0.815
C6 If the contractor fails to complete the works by the
Completion Date, the contractor shall pay or allow
to the JKR a sum calculated at the rate stated as
Liquidated Ascertained Damages (L.A.D)
4.0504 0.81
C7 Termination based on Clause of Contract (COC). 4.0336 0.807
C8 Appoint Third Party / New Contractor to Continue
the balance of work (Kontraktor Penyelamat) 3.9328 0.787
C5 Contractor ask for Extension of Time (E.O.T) for
reasons or causes of delay which is beyond his
control accordance with Clause of Contract
3.7143 0.743
C2 Contractor prepare the Recovery Plan /
Rescheduling work programme by using the 4M
method ( Machineries, Material, Money and
Manpower)
3.6387 0.728
C1 S.0 will issues the Warning Letter (Surat Amaran
Kemungkiran) for contractor to increase the
productivity of works.
3.4706 0.694
C4 Head of Project Team (HOPT) will prepare the
report of project delays and present in
Jawatankuasa Projek Sakit JKR.
3.3697 0.674
Average 3.7857 0.757
4.5.6 Section D – Proposed Contemporary Approach to JKR Dealing with
Project Delays
In this section respondent were given 39 questions about the method to
resolve delay. The questions were divided into nine main factors based on
PMBOK. The factors were Scope Management, Time Management, Cost
64
Management, Quality Management, Communication Management, Human
Resources Management, Risk Management, Procurement Management and
Integration Management. Data were analyzed using SPSS software and MS
Excel.
Results were shown in Table 4.17 for all the factors in Section B.
From the table below, all the attribute of method minimize delays can be used in
JKR to avoid the project delays accept for attribute in scope management which is
the RII value less than < 0.6.
Table 4.17 : Cronbach’s Alpha Value for Section D
Code Category Mean
Relative
Index
DA Scope Management 2.9630 0.593
DB Time Management 3.4398 0.688
DC Cost Management 3.0340 0.607
DD Quality Management 3.2020 0.641
DE Communication Management 3.5836 0.717
DF Human Resources Management 3.9426 0.788
DG Risk Management 3.6481 0.732
DG Procurement Management 3.6432 0.729
DI Integration Management 3.6927 0.739
Ranking of the questions were conducted based on relative importance
index (RII) using the formula mentioned in Chapter 3. The questions were ranked
in descending format base on RII as shown in Table below.
65
Table 4.18: Ranking Relative Importance Index for Scope Management
Code Scope Management Mean
Relative
Index
DA2 Complete and accurate project feasibility study and
site investigation to all projects done by JKR 3.395 0.679
DA5 Implement Project Management Plan (PMP) to all
JKR projects 3.1261 0.625
DA4 Utilization of the latest construction technology
method by using Building Information System
(BIM)
2.8992 0.58
DA1 Implement Value Management & Value
Engineering Lab to determine scope of work in
Planning & Design Stage
2.8235 0.565
DA3 Utilization of the latest construction technology
method by using Industrialized Building System
(IBS)
2.5714 0.514
Average 2.9630 0.593
Table 4.19: Ranking Relative Importance Index for Time Management
Code Time Management Mean
Relative
Index
DB1 Proper project planning and scheduling using
appropriate scheduling method such as Primavera
or MS Project
3.521 0.704
DB2 Execute delayed activities by subcontractors. Work
breakdown Structure (WBS) as a tool to determine
duration for every task
3.4874 0.697
DB3 Accurate initial time estimation by establish
methodology for estimation process 3.3109 0.662
Average 3.4398 0.688
66
Table 4.20: Ranking Relative Importance Index for Cost Management
Code Cost Management Mean
Relative
Index
DC1 Accurate initial cost estimates. Enough of
information necessary for estimation and adequate
timeframe to perform estimates
3.3025 0.661
DC4 Enforce Liquidated damages clauses on monthly
basic based on Work Programmed as milestone to
achieve and offering incentives for early
completion
3.2564 0.65
DC3 Allow Contingency Cost in the Contract Sum 3.0603 0.612
DC2 Payment processed by the Client. JKR only
prepared and endorsed the JKR 66 Certificate. No
warrant allocation
2.5169 0.504
Average 3.0340 0.607
Table 4.21: Ranking Relative Importance Index for Quality Management
Code Quality Management Mean
Relative
Index
DD5 Site meeting and technical meeting as one of the
tool for monitoring the project 3.6837 0.738
DD3 Frequent coordination between the parties involved
to avoid dispute between stakeholder 3.5299 0.708
DD2 Build a systematic project control and monitoring
mechanism 3.4017 0.679
DD1 Frequent progress meeting with all stakeholder to
monitor the progress of work 3.2101 0.642
DD4 Implement Project Health Check (PHC) to all JKR
projects 2.7931 0.56
DD6 Implement SERQUAL Analysis to evaluate
Customer satisfaction in meeting project schedule,
quality and cost
2.5932 0.519
Average 3.2020 0.641
67
Table 4.22: Ranking Relative Importance Index for Communication Management
Code Communication Management Mean
Relative
Index
DE3 Clear information and communication channels in
roles and responsible of all stakeholder. 3.9237 0.785
DE2 Collaborative teamwork in construction with
effective site management and supervision. 3.8051 0.761
DE1 Developing appropriate communication system
linking to all functional group using new
technology- social network etc
3.4615 0.691
DE4 Community involvement to reduce the absence of
bureaucracy to avoid complaints from publics 3.144 0.629
Average 3.5836 0.717
Table 4.23: Ranking Relative Importance Index for Human Resources Management
Code Human Resources Management Mean
Relative
Index
DF1 Select the competent project manager 4.0504 0.81
DF2 Hire experience personnel for project
implementation 3.8898 0.778
DF3 Apply collaborative teamwork environment
application with multidisciplinary /competent
project team and promotion team working among
project participants
3.9916 0.798
DF4 Competent personnel of consultant/designer to
complete and proper design at the right time 3.9407 0.788
DF5 Developing human resources in the construction
industry through proper training and classifying of
craftsman
3.8403 0.768
Average 3.9426 0.788
68
Table 4.24: Ranking Relative Importance Index for Risk Management
Code Risk Management Mean
Relative
Index
DG1 Early in obtaining permit and approval from
relevant authority 3.724 0.746
DG2 Implement Risk Management Plan (RMP) 3.6287 0.731
DG4 Cross functional collaborative teamwork is an
effective way for collectively dealing with threats
(risk) to the project environment.
3.5915 0.718
DG3 The effectiveness of risk management will be
increase if the project manager see risk as an
opportunity 3.1849 0.637
Average 3.6481 0.732
Table 4.25: Ranking Relative Importance Index for Procurement Management
Code Procurement Management Mean
Relative
Index
DH3 Comprehensive contract documentation 3.8403 0.768
DH2 Not awarding contract based on the lowest bid 3.7983 0.76
DH1 Adopting a new approach to contract award
procedure by giving less weight to prices and more
weight to prices and more weight to the capabilities
and past performance of contractor
3.7815 0.756
DH4 Adopting a new approach to contracting such as
Cost Plus contract, alternative procurement system,
FIDIC type of contract
3.1525 0.63
Average 3.6432 0.729
69
Table 4.26: Ranking Relative Importance Index for Integration Management
Code Integration Management Mean
Relativ
e Index
DI3
Ensure the availability of resources (finance,
materials, equipments, workmen, etc) 3.8632 0.773
DI1
Proper emphasis on past experience of project
parties 3.6639 0.733
DI4
Integrate Risk Management Plan and Work
Programme(CPM) 3.6555 0.731
DI2 Offer incentive for early project completion 3.5882 0.718
Average 3.6927 0.739
From the 39 attributes of method to minimize the delay, six (6) of the
method was not acceptance because the RII < 0.6. The factors are Utilization of
the latest construction technology method by using Building Information System
(BIM); Implement Value Management & Value Engineering Lab to determine
scope of work in Planning & Design Stage; Utilization of the latest construction
technology method by using Industrialized Building System (IBS); Payment
processed by the Client. JKR only prepared and endorsed the JKR 66 Certificate;
Implement Project Health Check (PHC) to all JKR projects and Implement
SERQUAL Analysis to evaluate Customer satisfaction in meeting project
schedule, quality and cost
Project delays have been a topic of concern in the construction industry.
Delays can be minimized only when their causes are identified. Knowing the
cause of any particular delay in a construction project would help avoiding the
effects. Table 4.27 shows ranking of the top fifteen effective methods of
minimizing construction delay for JKR projects. These methods were ranked
based on the relative importance index as mention in Chapter 3.
70
Table 4.27: Ranking of the Top Fifteen Attributes of Method Minimizing Delays
Code Proposed Method
Mean
Relative
Index
Rank
DF1 Select the competent project manager 4.0504 0.81 1
DF3 Apply collaborative teamwork
environment application with
multidisciplinary /competent project
team and promotion team working
among project participants
3.9916 0.798 2
DF4 Competent personnel of
consultant/designer to complete and
proper design at the right time
3.9407 0.788 3
DE3 Clear information and communication
channels in roles and responsible of all
stakeholder.
3.9237 0.785 4
DF2 Hire experience personnel for project
implementation 3.8898 0.778 5
DI3
Ensure the availability of resources
(finance, materials, equipments,
workmen, etc)
3.8632 0.773 6
DF5 Developing human resources in the
construction industry through proper
training and classifying of craftsman
3.8403 0.768 7
DH3 Comprehensive contract
documentation 3.8403 0.768 8
DE2 Collaborative teamwork in
construction with effective site
management and supervision.
3.8051 0.761 9
DH2 Not awarding contract based on the
lowest bid 3.7983 0.76 10
DH1 Adopting a new approach to contract
award procedure by giving less weight
to prices and more weight to prices and
more weight to the capabilities and
past performance of contractor
3.7815 0.756 11
DG1 Early in obtaining permit and approval
from relevant authority 3.724 0.746 12
DD5 Site meeting and technical meeting as
one of the tool for monitoring the
project
3.6837 0.738 13
DI1
Proper emphasis on past experience of
project parties 3.6639 0.733 14
DG2 Implement Risk Management Plan
(RMP) 3.6587 0.731 15
71
4.6 Conclusion
By conducting analysis and discussion in this chapter, various findings
and results are obtained. The pre-defined objective is achieved by focusing to
answer the research question during the analysis and discussion. The major delays
groups and significant causes of delays were identified and ranked. From total 57
causes of delay, five top most significant causes have been identified. The
methods in minimizing projects delay also establish.
This chapter has reported the results of the interview and questionnaire
survey conducted on the project delays in JKR. For ease to understand, the results
from the analysis were presented in tables and figure. The analysis was done by
Cronbach Alfa Reliability Test, and, Normality Test. For the identification of
causes of delay, effectiveness of the current practice in JKR and method in
minimizing projects delays, a relative importance index (RII) and mean method is
used.
Thus, the following chapter, which is the final chapter, will comprise of
conclusion, and recommendation for this study, and recommendation for further
research on this topic. Problems that exist during the study and the limitation will
also be described in the following chapter.
72
CHAPTER 5
DICSUSSION OF RESULTS
5.1 Introduction
This chapter consists of the discussion on the data collected and analyzed
in Chapter 4. The data that has been tabulated further discussed and compared
with the objective of the study. Every objective that has been identified at the
beginning of this research will be compared with the data that has been collected.
5.2 Factors That Contribute to Delays in JKR Projects
Based on the ranking, the five most important causes of the JKR project
delay as perceived by respondents has summarized in Table 5.1.
Based on the analysis conducted on RII it was found that the contractor
capabilities were the main factor to be focused on in order for JKR to determine
the project delay issues. Besides that poor communication and lack of
coordination among consultant also contribute to project delay in JKR. Client also
one of the factors for project delays because the client takes long time to give the
approval. JKR must take seriously in this three stakeholder issues to avoid project
delays.
73
Table 5.1: Ranking of Relative Importance Index (RII) for Top Five Causes of
Project Delay
Code External Factor Mean Relative
Index
Rank
BB1 Poor site management and
supervision 4.2941 0.859 1
BB2 Financial difficulties - Poor cash
flow management 4.2353 0.847 2
BB4 Inadequate contractor experience 4.1513 0.83 3
BC2 Poor communication and
coordination 4.1176 0.824 4
BA2 Slowness in decision making
process 4.1008 0.82 5
Therefore JKR must check the resources and capabilities before awarding
the contractor and should consider the following factors:-
a. Shortage and low productivity of labor: enough number of labors should
be assigned and be motivated to improve productivity;
b. Financial and cash flow problems: contractor should manage his financial
resources and plan cash flow by utilizing progress payment;
c. Site management and supervision: administrative and technical staff
should be assigning as soon as the project was an awarded to arrange to
achieve completion within specified time with the required quality, and
estimated cost.
d. Contractor experience: an adequate contractor experience is very crucial
in executing work efficiently and forecasting the potential problems that
may arise during construction work. As a cost cutting measure, many
contractors prefer to hire young and inexperienced staff especially
technical staffs as these junior staffs accept less pay. This inexperienced
staffs has limited ability and need more guidance in carrying out the job.
74
The smooth management at the site plays important role for the successful
of the project. The failure in managing and attending the daily routine and
problems at the project site contribute to the delay significantly. Most contractors
do not have strong financial background to keep the work in progress. They
would normally rely on the advance money and progress payment to ensure that
their study on site will continue. The contactors’ inability to plan can be attributed
to contractor’s inexperience. Consultant also plays the important roles especially
in communication and coordination with other parties to avoid delays. Client need
to know their roles and responsibilities and take immediate action for any
approval that needs decision-making
From previous study mentioned above shown that the factors contributed
to delay in JKR project almost same with what were resulted from this study. This
was supported by Sambasivan M (2007) and Abd. Majid and McCaffer (1997)
were agreeable.
5.3 Traditional Approach in JKR Dealing with Project Delay Issue
From the analysis conducted through a questionnaire on Section C, three
(3) factors were determined very ineffectiveness of current practice in JKR when
dealing with project delays. Table 5.2 shown top three based ineffective
traditional JKR practice dealing with delays..
75
Table 5.2: Ranking of Relative Importance Index (RII) for Top Three Traditional
Approach Dealing with Delays in JKR
Code Traditional Approach by JKR Mean Relative
Index
Rank
C3 Coordination meetings on a weekly basis to
monitor the progress of work on site by
S.O. closely (Weekly and Monthly report)
4.0756 0.815 1
C6 If the contractor fails to complete the works
by the Completion Date, the contractor
shall pay or allow to the JKR a sum
calculated at the rate stated as Liquidated
Ascertained Damages (L.A.D)
4.0504 0.81 2
C7 Termination based on Clause of Contract
(COC). 4.0336 0.807 3
Coordination meeting on a weekly basis is the high level of the
ineffectiveness for JKR respondents. The weekly meeting is very important, all
problems will be resolve on that meeting and relation division have limited time
to return the request for information of for Agreement from Government. In
coordination meeting Project Manager should using planning and scheduling as
the tools for the monitoring of project. Planning and scheduling are continuing
processes during construction, match with the resources, and time to develop the
work to avoid cost overrun and disputes.
By practice, weekly coordination meeting can avoid poor site management
problem. A project manager is the leader in a construction project in the sense that
he is required to manage all the works on site from monitoring progress of
construction works to managing all the administrative work in the project. It is of
utmost importance for the project manager to manage the work and project team
effectively. Hence poor site management from the project manager will affect the
whole team and the progress of works, resulting in the eventual outcome of
project delay. This view is supported by studies conducted Aibinu and Odenyika
76
(2006) who concluded that poor site management is one of the factors that
contribute to delay in construction projects.
From this analysis, it was establish that almost 81% of JKR staff agreed
implementation of Liquidated Ascertained Damages (L.A.D) to contractor for
JKR Projects was ineffective to minimize project delays. If the contractor fails to
complete the works by the Completion Date, the SO shall issue a certificate of
Non-completion. Upon the issue of the certificate of Non-Completion, the
contractor shall pay or allow to the JKR a sum calculated at the rate stated as
Liquidated Damages for the period from the Completion Date to the Date of
Practical Completion. LAD only allow not more than 60 day after Certification
Non- Compliance date. This result was supported by Odeh and Battaineh (2002).
Results from the analysis show that termination contractor based on
Clause of the Contract (COC) also the ineffective current practice in JKR to
minimize project delays. Termination of contact based on letter from Deputy
Director General (Business Sector) reference no (38).dlm.JKR-KPKR:109.010/08
dated 30 July 2010. Only one warning letter will issue. After monitoring the
progress and S.O not satisfy with the progress of work, Notis untuk Tujuan
Penamatan Pengambilan Kerja Kontraktor will issue and follow by termination of
contract.
Based on Clause 43 PWD 203A standard form of contract, contractor’s
obligations upon it becoming reasonably apparent that the progress of work is
delayed, forthwith give written notice of delay to the S.O. Constantly use his best
endeavor to prevent delays. This result was supported by Yates and Epstein
(2006).
This result also supported and proved by the expert panel from the
interview session. All of them was concluded the current practice by JKR need to
77
be reviewing and improving. JKR need to emphasis in planning and scheduling to
avoid the project delay using Ms Project as one of the tool. Prepare the recovery
plan using method of schedule compression. This analysis was supported by the
document search. Based on JKR projects database module (SKALA), it’s shown
that 57% of the JKR projects under construction were delayed.
5.4 Attributes of Method in Minimizing Project Delay in JKR
From the analysis conducted through a questionnaire on Section D, fifteen
(15) effective attributes of methods minimizing construction delays were ranked
based on the relative importance index. Table 5.3 shown top fifteen attributes of
methods minimize project delay
Table 5.3: Ranking of Relative Importance Index (RII) for Fifteen Effective
Attributes of Method Minimizing Project Delays
Code Proposed Method
Mean
Relative
Index
Rank
DF1 Select the competent project manager 4.0504 0.81 1
DF3 Apply collaborative teamwork
environment application with
multidisciplinary /competent project
team and promotion team working
among project participants
3.9916 0.798 2
DF4 Competent personnel of
consultant/designer to complete and
proper design at the right time
3.9407 0.788 3
DE3 Clear information and communication
channels in roles and responsible of all
stakeholder.
3.9237 0.785 4
78
Table 5.3: Ranking of Relative Importance Index (RII) for Fifteen Effective
Attributes of Method Minimizing Project Delays (Cont’d)
Code Proposed Method Mean
Relative
Index Rank
DF2 Hire experience personnel for project
implementation 3.8898 0.778 5
DI3
Ensure the availability of resources
(finance, materials, equipments,
workmen, etc)
3.8632 0.773 6
DF5 Developing human resources in the
construction industry through proper
training and classifying of craftsman
3.8403 0.768 7
DH3 Comprehensive contract documentation 3.8403 0.768 8
DE2 Collaborative teamwork in construction
with effective site management and
supervision.
3.8051 0.761 9
DH2 Not awarding contract based on the
lowest bid 3.7983 0.76 10
DH1 Adopting a new approach to contract
award procedure by giving less weight to
prices and more weight to prices and
more weight to the capabilities and past
performance of contractor
3.7815 0.756 11
DG1 Early in obtaining permit and approval
from relevant authority 3.724 0.746 12
DD5 Site meeting and technical meeting as
one of the tool for monitoring the project 3.6837 0.738 13
DI1
Proper emphasis on past experience of
project parties 3.6639 0.733 14
DG2 Implement Risk Management Plan
(RMP) 3.6587 0.731 15
5.4.1 Project Manager
During pre-construction stage, JKR should employ a knowledgeable
project manager to organize a good project team member to progress the work.
Besides that the project team member should always discussing with the problem
having the site progress. Leadership is a crucial aspect in project management.
79
There are three different kinds of competencies required in leadership; leadership
competencies such as the ability to lead change; functional competencies such as
technical and human resources management skills and personal skills such as high
achievement motivation and persistence. Therefore a competent project manager
possesses not only technical and managerial skills but also good leadership to do
“the right thing right” and search suitable and intangible assets in today’s
knowledge –based economy
5.4.2 Collaborative Teamwork
Collaborative teamwork is the best practice to avoid the delays which all
the team member share the lesson learned and experience methods on solving site
issues. As a reward if the team member achieves the target and objective, they
should give more advantage and priority as a token of appreciation. On the other
hand, contractor should be employs some employee with experience such as
quantity surveyor. So that during the time or cost estimate they can add on some
unforeseen event to avoid the cost and time overrun.
In a project team, each individual responsibilities and rights must be
clearly defined. JKR must set up the clear project Development Process Flowchart
by using ISO as a working culture and Standard Operation Procedure (SOP) that
is compulsory to follow. The working culture should be improved gradually
aiming at building proper working atmosphere. All the project team must try to
self-improvement skills. Set the interest of works to the highest. They must
recognize delay problems that will lead to large losses as well as benefits of the
project completion on time.
80
5.4.3 Designer
All the JKR staff must have the competency to be a designer. JKR must
monitor the design consultant’s works of every period, if any changes happen,
design consultant must be accelerate in next period for catch up schedule.
Exchange information dissemination and unified design concept from the start to
avoid the disagreement. Furthermore, JKR should be hiring some experience
consultant. It is because once they facing problem, they can refer previous project
to solve the project immediately. So the project can process with smoothly.
5.4.4 Communication Channel
. One of the important factors was clear information and communication
channels, the clear communication are essential when managing activities.
Communication is the passing on of ideas and information; therefore, site
supervisor must ensure that their workers are able to understand his command
before start any site activities.
5.4.5 Human Resources
In Human Resources Management, JKR should organize training the
project construction management group in order for the staff to know how to use
the process to accomplish project and contract condition. JKR must build an
ideology for all the JKR Staff so that they can recognize delay problems that will
lead to large losses as well as benefits of the project completion on time especially
in JKR reputation to client. Simultaneously JKR top management should establish
a fair reward and punishment policy that has to be strictly applied.That is finance,
resources, efforts and leadership should always be available throughout the
project’s life. They ensure that construction projects run smoothly.
81
5.4.6 Monitoring and Control
Site meeting and technical meeting is one of the best practices to avoid
projects delay. During site meeting, the Project Manager should understand and
apply the technique of critical path analysis. This is not hard to neither understand
nor apply, particularly as these days, there are excellent software management
tools freely available to help identify and apply the use of critical path to a given
project. The scheduling should be one of the agenda in the site meeting and must
present lively to determine the task and critical path. The critical path schedule of
activities shows clearly those tasks that if they were to slip, that this delay will
have the same effect on the project end-date and/or key milestones. These are
called critical activities. Critical path will also identify those activities whose
duration can extend by some amount or that their start and end dates can slip –
without creating any delay to the project end-date. The corollary of this is of
tremendous importance, since it allows the project manager to focus on putting
their best people and priority on critical tasks, while assigning resources that are
still developing those skills for example, on non-critical activities.
.
This result was agreed by Sambasivan and Soon (2007) , Aibini and
Jagboro (2002). And Majid, (2006).
5.5 Proposed Guideline for on Time Project Delivery
This part of the study intend to provide a structural systematic process
which professional in the JKR can adopt in realizing projects timely completion.
The most significantly factor in achieving this aim is to a clear guidelines for
work process. It implies that the construction stage is crucial to the delivery of
projects and that whatever transpires in the construction stage affects the project
delivery time. Therefore, the construction stage is the main focus. It is important
82
to note that client briefing and quality of design have an impact on the speed of
construction. The list of activity in every stage that needs to be focused is shown
in table below. The information established for this table are generated from the
interview with expert panel and literiew review as shown in Appendix C.-
Table 5.4: Inception Activity
Inception Activities
1. Defining the scope and background of project
.
2. Identifying business drivers that lead the project and define the strategic
direction
3. Developing the business cases that define the problem/need to be address
by the project and the reason for project launching.
4. Creating a list of project goals and objectives that contribute to solving
the problem.
5. Analyzing options or alternatives to the project.
6. Justifying the project through performing feasibility analysis.
7. Identifying constraints and assumptions.
8. Identifying constraints and assumptions.
9. Defining scope, including boundaries, deliverables and requirements
10. Developing product acceptance criteria.
11. Analyzing stakeholders and their expectations and involvement level.
12. Designing an organizational chart that identifies roles and responsibilities
of stakeholders.
13. Writing a proposal document that summarizes the project and provide the
relevant information for all stakeholders.
14 Getting approval of the proposed project and starting the planning
process.
83
Table 5.5: Planning Activity
Planning Activities
1. Reviewing lessons learned from previous projects (if any) to gain valued
expertise and knowledge for present project.
2. Selecting and interviewing the best candidates to the project team.
3. Creating a team composition chart that includes roles and names of
peoples involved in the implementation process.
4. Writing a staffing plan that explains how to manage the team and
collaborative activities.
5. Designing a change management plan that explores a mechanism of
defining, approving and implementing project changes and updates.
6. Making an issue management plan to define how to document and
manage issues.
7. Defining quality assurance and control activities that identify how to keep
the project and its results relevant to project requirements.
8. Developing the project schedule that defines time required for
implementing the project, along with activity durations and milestones.
9. Establishing contractual relationships with suppliers and procurers.
10. Designing a training plan that explores methods and techniques of staff
training and development.
11. Developing cost estimates that define how much funding will be required
to perform the project and complete its goals and objectives.
12. Making a risk management plan that specifies processes and tools for
analyzing and managing threats and uncertainties.
13. Developing a communications management plan that explains how
communications between stakeholders should be established and
managed.
14. Designing a project management plan that defines key activities for
managing the project and its content.
84
Table 5.6: Implementation Activity
Implementation Activities.
1. Conducting status meetings to review current status of the project.
2. Conducting status meetings to review current status of the project
.
3. Providing training to personnel if necessary.
4. Leading and guiding the project team.
5. Managing changes and updates.
6. Logging issues and developing solutions for handling logged issues.
7. Managing identified risks.
8. Communicating with the team and other stakeholders to get their feedback
and keep the project up-to-date.
9. Managing deliveries and procurement.
10. Controlling and assuring project quality.
11. Using reporting as a mechanism of tracking the implementation process.
12. Reviewing status of project deliverables to ensure they are produced
according to acceptance criteria.
13. Monitoring staff performance to ensure project work is performed according
to the plan.
85
Table 5.7: Inception Activity
Closure Activities.
1. Performing a post implementation review to confirm the project has reached
its goals and objectives and that deliverables are produced.
2. Conducting lessons learned exercises to document successful experience and
practice of the project.
3. Transferring project personnel to other projects, or releasing them.
4. Closing financial operations and transactions.
5. Handing over the project product to the customer.
6. Getting the customer’s approval that meets the customer satisfaction.
5.5.1 Workflow Process and Duration of Activity
Based on interview with the JKR expert panels, an implementation
guideline acquired the project on schedule. These guidelines become effective
accordance with the time frame proposed.
86
Figure 5.1: Flowchart of Project Implementation in JKR
87
Based on the Gerbang Nilai (2009), this study proposed the continuous
improvement for the flowchart of project implementation in JKR. The processes
consist of five stages. The stages and the interventions at each stage are:
a. G1 :Planning Stage
i. Project Brief
ii. Budget
iii. Land
b. G2 :Design Stage
i. Concept Design – well defined functionality of design;
ii. Clear understanding of client and other stakeholders requirements;
iii. Risk analysis;
iv. Value management analysis (project cost more than RM50
Million)
v. Detail Design- accurate coordination design;
vi. Document Tender
c. G3: Procurement Stage
i. Ascertaining contractor Project Quality Plan, OSH Plan etc
ii. Ascertaining past records of contractor-experience
iii. Ascertaining the financial capability of contractor
iv. Inclusion of work schedule in tender document by contractor
v. Inclusion of Human Resource, plant & equipment schedule in
tender document
vi. Evaluation of tender by Head of Design Team based on ratio
agreeable.
88
d. G4: Construction Stage
i. Contractor prepare Site Management Plan;
ii. Method Statement submitted for approval from HODT before
work done by contractor;
iii. Contractor and consultant checking quality of materials supplied as
they arrive on site and carrying out relevant test;
iv. Contractor monitoring of subcontractor work.
v. Weekly/monthly meeting with the project manager/ subcontractor /
key staff;
vi. Proper planning and scheduling of work based on sequence of
works;
vii. Prompt issuance of instructions and payments;
viii. Purchase of equipment listed on document contract;
ix. Prepared the Handing Over Plan
e. G5: Handing Over
i. Testing and Commissioning for all the system
ii. As Built Drawing & Manual Operation
iii. Certificate of Fitness (CF) from Local Authority
iv. Training session for the end user
v. Checklist Building Accepting Criteria from Building Facility
Department JKR
The list of activity in every stage that needs to be focused is shown in
table below. The information established for this table are generated from the
interview with expert panel as shown in Appendix D. The activity and duration
proposed as per shown in Table 5.8.
89
Table 5.8: Activity and Duration Purpose for on Time Project Delivery
No Task Duration
1.0 PRE PLANNING 26 DAYS
1.1 Overview and Early Planning 10 days
1.2 Received list of Project from Economic Planing Unit (EPU), JPM 2 days
1.3 Clarification of Project based on Location, Cost,
Ministry/Agency & ACAT 2 days
1.4 Analysis and Distributed to implementer ( JKR /Agency) 3 days
1.5 Set the Strategy of Implementation 1 day
1.6 Distributed to Busines Sector / Design Sector 7 days
1.7 Coordination Meeting with Director of Sector Unit (SBU) 1 days
2.0 REGISTER PROJECT IN SKALA 9 DAYS
2.1 Determine the Project Team and Appoint Head of Project Team
(HOPT) 1 day
2.2 Finalize the stategy of implementation and download in SKALA 2 days
2.3 Register the project title by Head of Project Office (HPO) 5 days
2.4 Updated the latest list of project to EPU 1 day
3.0 PLANNING 87 DAYS
3.1 Received Brief Project, Land and Badjet (Gate Way 1) 20 days
3.2 Appoint Head of Project Team 1 day
3.3 Review Project Brief 10 days
3.4 Arrange the Site Visit 2 days
3.5 Review and Fullfill the requirement by the local authority 20 days
3.6 Land Surveying 20 days
3.7 Prepare Report / Site Anlysis/Design Brief / Risk Management
Plan / Project Management Plan 20 days
3.8 Soil Investigation 40 days
3.9 Finalize Project Brief, Site and Cost 7 days
4.0 DESIGN 178 DAYS
4.1 CONCEPT DESIGN 65 days
4.1.1 Prepare Concept Design 20 days
4.1.2 Prepare Early Estimate Cost 5 days
4.1.3 Review Concept Design 10 days
4.1.4 Value Engineering & Gate Way 2 10 days
4.1.5 Client Approval 20 days
4.2 PRELIMINARY DESIGN 50 days
4.2.1 Prepare Preliminary design & specification 20 days
4.2.2 Prepare Drawing 100 scale 20 days
4.2.3 Development Order 30 days
90
Table 5.8: Activity and Duration Purpose for on Time Project Delivery (Cont’d)
4.3 DETAIL DESIGN 93 days
4.3.1 Prepare detail design 60 days
4.3.2 Coordination drawing between all displin 20 days
4.3.3 Value Engineering 2 & Gate Way 2 10 days
4.3.4 Amendment Detail Design 10 days
4.3.5 Approval of Building Plan 20 days
5.0 PROCUREMENT 70 DAYS
5.1 Prepare Tender Document / Gateway 3 15 days
5.2 Advertising of Tender 20 days
5.3 Evaluation of Tender 15 days
5.4 Tender Board Meeting 10 days
5.5 Prepare As Tender Detail Abstract (ATDA) & Get Approval from
the Client 10 days
5.6 Letter of Award 5 days
6.0 CONSTRUCTION 36 Month
6.1 Preliminary Item 36 month
6.2 Civil Works 6 month
6.3 Structure Works 12 month
6.4 Architect Works 18 month
6.5 Mechanical Works 18 month
6.6 Electrical Works 18 month
6.7 External Works 12 month
6.8 Provisional Item 12 month
*All the activity depends on the contract duration and scope of
work
7.0 HANDING OVER 60 days
7.1 Installation of TNB transformer, etc & Energizing of TNB Sub
Station 30 days
7.2 Testing & Commissioning 7 days
7.3 As Build Drawing & Operation and Maintenance Manual 30 days
7.4 Cleaning up
14 days
7.5 Hand Over
1 day
91
5.6 Conclusion
By conducting analysis and discussion in this chapter, various findings
and results are obtained. Thus the following chapter will comprise of conclusion
and recommendation for this study, and recommendation for further research on
this topic.
92
CHAPTER 6
CONCLUSIONS AND RECOMMENDATIONS
6.1 Introduction
This chapter concludes the study and briefly describes the conclusion for
each objective. Finally, suggestions to JKR and proposal for further study are
presented.
6.2 Conclusions
The study on delay in JKR project was carried out because delay will
cause the project were late delivered to the client and would gave bad reputation
to JKR as technical department in Malaysia. JKR must identify the major causes
of delays. Factor that contributes to delay in JKR project which has been
identified in this study was agreed upon by the general population of the
respondents. Seven groups of the causes which is client related, contractor related,
consultant related, material related, equipment related, labour related and external
factor related are acceptable with the RII from 0.6400 to 0.773. All the factor was
contribute to the causes of delay in JKR projects which the RII more than 0.6
93
exclude 2 causes in the external factor which is accident during construction and
traffic control at site. In order to overcome the problem of delay in JKR project,
these group causes has to be looked into and rectified during early of planning of
the project cycle.
6.2.1 Objective 1: To Evaluate the Effectiveness of the Traditional
Approach in Addressing Project Delay Issue
From the eight (8) current practices at JKR dealing with project delays, all
of the method was ineffective anymore to avoid delay. Likert Scale chosen from
respondents was 4 and 5 with is ineffective and highly ineffective. The RII was in
the range 0.674 to 0.815. Top three (3) RII based on the ranking were
Coordination meetings on a weekly basis to monitor the progress of work on site
by S.O. closely (Weekly and Monthly report) (RII=0.815), Liquidated
Ascertained Damages (L.A.D) (RII=0.810) and termination based on Clause of
Contract (RII= 0.807). The trend of completed project shows that delayed project
was increasingly by year. This shows that JKR had to take tremendous action in
order to eliminate or reduced the delay focused on effective coordination meeting
based on weekly and monthly basic as the important tolls in project monitoring
and controlling. The work programmed compulsory must be present by the
project manager during the site meeting to project the productivity of work and
cash flow. Clause of Contract regarding the extension of time and termination
must be review from time to time. In order to reduce the extension of time (EOT)
in JKR the factor of time, cost, location of project and scope of works should be
taking into account during project initiated.
94
6.2.2 Objective II: To Evaluate the Potential Application of Contemporary
Approach in Resolving Project Delay Issue
In order to minimize JKR project delay, a total of thirty nine attributes of
methods minimizing delay were identified. Some of the attributes of this method
have been used by JKR during implementation of the project such as risk
management; value management; IBS; etc. The most effective methods proposed
by respondents include: competent project manager; collaborative
teamwork/competent project team and promotion team working; Competent
personnel of consultant/designer; Clear information and communication channels;
and hire experience personnel. 6 from 39 attributes of method minimizing delay
were not acceptable by respondents include utilization IBS and BIM, value
management; payment directly from the client; site meeting and technical meeting
as one of the tool for monitoring project and conduct SERQUAL analysis. Quick
attention and prompt action will get the project back on track as close to original
deadline as possible. Once realize project is a delay, organize a team meeting.
Inform everyone working on the project about the delay, including details such as
factor contributing to the holdup and how far it has the project back.
6.2.3 Objective III: To Proposed the Guideline for on time Project Delivery
From the interview with the expert panel, this study proposed guidelines
with the duration of time as a tool to monitor and controlling every stage of
project life cycle. This guideline was inspiration from the JKR workflow process
in implementation of the project. The research findings enabled the identification
of the factors that are problematic and require attention. In order to achieve the
purpose guideline, which is the improvement of the delivery of construction
projects, the processes commence with a description of the stages involved in the
realizations of the project. The activity in every stage of the project was
determined with the suggested duration of time. The results shown in Table 5.8.
95
6.3 Recommendation to JKR
From this study, some recommendations are given as follows:-
i. Contractor related delays have contributed a large part for
significant causes of delay. The result of the study indicated
that financing projects is one of the major sources of project
delays. Therefore, contractor selection stage must receive more
serious consideration. It is essential to choose a contractor with
strong financial background. Apart from that, the selected
contractor must have sufficient experience, technical
capability, and sufficient manpower to execute the works. A
mechanism that closely stipulates feasibility study contractor
selection must have to strictly apply. Any red tape during the
tender bidding should be removed to improve the local
construction industry.
ii. Poor site management is one of the most significant causes in
causing the JKR project. This factor is responding to the issues
that arise at the site and causes negative impact on the overall
work progress. This requires a competent and experience
personnel. Where possible, project managers need to have
experience and qualifications in project or construction
management so that they can effectively utilize well the project
management tools that are available (project planning and
scheduling tools).
iii. Adequate finance is the hub around the everything else
revolves. Everybody and everything connected with
construction is adversely affected by lack of sufficient cash
flow. JKR must give special attention to the financial standing
of the contractor. Make sure that the contractors to be
96
considered for future projects can prove that they are
financially sound and have a strong backing from financial
institution.
iv. JKR need to check and validate the track record of the
contractors. The recommendations from authority body such as
CIDB are an added advantage.
v. Adopting a new approach to contract award procedure by
giving less weight to prices and high weight to the capabilities
and past performance contract.
vi. Adopting the new alternative procurement such as relational
contracting (RC), serial contracting and earned value
management, contract plus and allow contingency cost in
contract sum.
vii. Apply Collaborative teamwork. Due to the dynamic nature of
project environments, it is inevitable that conflicts among the
project team will arise. All project participants should
recognise that conflicts are inevitable and actually can be
beneficial if resolved in an appropriate manner. Therefore the
conflict management is a need to produce a good working
environment.
viii. Client must take quick decision regarding any matter arise
during the project execution. Low speed of decision is due to
incompetent person who handle the project from the side of
client. Sufficient number of professionals from JKR should be
provided in client part. Hence this can avert the slowness of
decision making made by client.
97
ix. The consultant plays a very important role in Design-Related
Delays because they are in charge of the design process in
conjunction with the owner of the project. Coordination and
communication channel between all the consultant are one of
the tools for monitoring the performance.
x. Planning and scheduling as the main tools to monitor the
progress of works. During site meeting the contractor should
presented the work programmed lively. If realize that there is a
delay, contractor should prepared the Recovery Plan using the
schedule compression.
6.4 Recommendations for Further Study
It is recommended that further study be carried out by expand to the
respondents from other parties such us contractor, consultant and client to get
their feedback according to delay issues. It provides the trend and obtain the more
significant causes contributed to delays. Detailed studies can be done to evaluate
the involvement and effect of a specific party or resources of construction project
to the time overrun in JKR projects. A research can be carried out to investigate
the effect of financing and cash flow problems on delay in JKR projects. Further
study on the performance of the project and customer satisfaction level can be
carried out to investigate the effect of reputation damage to JKR as technical
department on delays in project implementation.
98
6.5 Summary
For many years, the issue of delay in JKR projects has been phenomenal.
Its impacts are so significant that it tends to decelerate the implementation of
projects under the Tenth Malaysia Year Plan. The aim of the study is
accomplished as all the three objectives are met. It is the researchers hope that the
study conducted will be beneficial to the JKR department to overcome the
problem.
.
99
REFERENCE
Abd. Majid Muhd. Zaimi (1997). Non-Excusable Delays in Construction.
Loughborough University of United Kingdom. PhD. Thesis
Abdul Rahman H. et al (2006). Delay Mitigation in the Malaysian Construction
Industry. Journal of Construction Engineering and Management, Vol. 132
(2) 125-133.
Ahmed, S.M, Azhar, S., Castillo, M., & Kappagantula, P. (2002). Construction
Delays in Florida; an Empirical Study. Department of Construction
Management, Florida International University of Miami.
Aibinu A.A, Jagboro G.O (2002). The Effects of Construction Delays on Project
Delivery in Nigerian Construction Industry. International Journal of
Project Management 20: 593- 599
Ajanlekoko JO (1987). Controlling Cost in the Construction Industry. Lagos QS
Digest, Lagos 1(1):8-12
Al-Tmeemy, S.M.H.M, Hamzah Abdul Rahman and Zakaria Harun (2006).
Future Criteria for Success of Building Project in Malaysia. International
Journal of Project Management.
Assaf, S.A. and Al-Hejji,S (2006). Causes of Delay in Large Construction Project.
International Journal of Project Management. 24. 349-357.
Bassioni, H.A and El-Razak (2008). Causes of Delay in Building Construction
Project in Egypt. Journal of Construction Engineering & Management.
Chan D.W.M. and Kumaraswamy M. (1997). A Comparative Study of Causes of
Time Overruns in Hong Kong Construction Projects. International
Journal Project Management. 15(1):55-63
100
Lo. T.Y., Fung, I.W.H, and Tung, K.C.F (2006). Construction Delays in Hong
Kong Civil Engineering Projects. Journal of Construction Engineering
and Management ASCE, 132(6), 636-649.
Lee J.Y., Lee Y.D. and Hoai L.L (2008). Delay and Cost Overrun in Vietnam
Large Construction Projects; A Comparison with others Countries. Korean
Society of Civil Engineering. Journal of Civil Engineering (2008) ASCE
12 (6): 367-377
Construction Industry Development Board Malaysia (CIBD).Construction
Industry Master Plan Malaysia 2006-2015. (2007). Kuala Lumpur,
Malaysia:
Joshi, M. (2009, June 1); 80 per cent of Malaysian government projects delayed,
Minister says. Webpage accessed 01-10-2009 at:
http://www.topnews.in/80-cent-malaysiangovernment-projects-delayed-
minister-says-2173299.
Khair, M. (2010) Improving Time Estimation in JKR Projects. University
Teknologi Malaysia (2010) :Master Thesis
Kho Mei Ye, Hamzah Abdul Rahman (2010); Risk of Late Payment in the
Malaysian Construction Industry .World Academy of Science,
Engineering and Technology 41/ 2010
Koushhi. P.A, Al-Rashid. K and Kartam.N (2005). Delay and Cost Increase in the
Construction of Private Residential Project in Kuwait. Journal of
Construction Management & Economic, 23 (3), 285-294.
Majid, Ibnu Abbas (2006). Causes and Effects of Delays in Acheh Construction
Industry. Faculty of Civil Engineering, Universiti Teknologi Malaysia:
Master Thesis.
Mehdi Riazi, Salman Riazi, Skitmore, Martin, & Cheung, Yan Ki Fiona (2011);
The Use of Supply Chain Management to Reduce delays: Malaysian
Public Sector Construction Projects. Proceedings of the 6th Nordic
Conference on Construction Economics and Organisation in Society
Volume 2, Danish Building Research Institute, Aalborg University,
Copenhagen, Denmark, 403-414
101
M.Haseeb, Xinhai-Lu, Aneesa Bibi, Maloof-UdDyian and Wahab Rabbani (2011)
Problems of Project and Effects of Delays in the Construction Industry of
Pakistan. Australian Journal of Business and Management Research Vol.1
No.5.
Mohd Razaki Abdullah1, Ismail Abdul Rahman2, Ade Asmi Abdul Azis (2009).
Causes of Delay in MARA Management Procurement Construction
Projects. Faculty of Civil and Environmental Engineering, Universiti Tun
Hussein Onn Malaysia
M.R. Abdullah1, A.A. Abdul Azis2 and I. Abdul Rahman3 (2009), Potential
Effects on Large Mara Construction Projects Due To Construction Delay,
Faculty of Civil and Environmental Engineering, Universiti Tun Hussein
Onn Malaysia
Munns, A. K. & Bjeirmi, B. F. (1996). The Role of Project Management in
Achieving Project Success. International Journal of Project Management,
14(2), 81-87.
N. Hamzah, M.A. Khoiry, I. Arshad, W.H.W. Badaruzzaman, and N. M. Tawil
(2012). Identification of the Causes of Construction Delay in Malaysia.
World Academy of Science, Engineering and Technology 72 /2012
Nguyen, L.D., Orgunlana, S.O. and Lan, D.T.X (2004). A Study on Project
Success Factors in Large Construction Projects in Vietnam. Engineering
Construction & Management, 11(6):404-413.
Odeh A.M and Battaineh H.T (2002). Causes of Construction Delay; Traditional
Contract. International Journal of Project Management 20:67-73
Odeyinka HA, Yusif A.(1997). The Causes and Effects of Construction Delays on
Completion Cost of Housing Project in Nigeria. J Financial Manage
Property Construction 2(3):31-44
Project Management Institute. Guide to the Project Management Body of
Knowledge (PMBOK@Guide). 4thed, Newton Square: Project
Management Institute, 2008.
102
Sambasivan, M. & Soon, Y. W. (2007). Causes and effects of delays in Malaysian
Construction Industry. International Journal of Project Management,
25(5), 517-526.
Sami Karna, Juha-Matti Jannonen, and Jouka Kankainen (2004). Customer
Satisfaction in Construction. Journal of Project Management 15: 32- 46
SKALA (2013). Controlling and Reporting System for JKR. Jabatan Kerja Raya
Malaysia. Retrieve 16 December 2013 : https://skala.jkr.gov.my
Shebob, A, Dawood, N and Xu, Q (2011) Analysing construction delay factors: A
case study of building construction project in Libya In: Egbu, C. and Lou,
E.C.W. (Eds.) 27th Annual ARCOM Conference, 5-7 September 2011,
Bristol, UK, Association of Researchers in Construction Management, pg
1005-1012
Odeh, A.M and Battaineh, H.T (2002). Causes of construction delay.
International Journal of Project Management.20. 67-73
O.T. Ibironke, T. O. Oladinrin, O. Adeniyi and I. V. Eboreime (2013), Analysis of
Non-Excusable Delay Factors Influencing Contractors’ Performance in
Lagos State, Nigeria. Journal of Construction in Developing Countries.
Saad Hegazy (2012). Delay Analysis Methodology in UAE Construction Projects.
Project Management World Journal Vol.1 Issue II (access from
www.pmworldjournal.net ).
103
Appendix: A
Normality Test: Histograms and Q-Q Plots
Distribution of Respondents: Client Related Category
Distribution of Respondents: Contractor Related Category
104
Distribution of Respondents: Consultant Related Category
Distribution of Respondents: Material Related Category
105
Distribution of Respondents: Equipment Related Category
Distribution of Respondents: Labour Related Category
Distribution of Respondents: External Factor Category
106
Appendix: B
Dear Sir/Ms,
RESEARCH ON METHOD TO RESOLVE BUILDING PROJECT
DELAY (JKR - UTM joint-venture programme)
----------------------------------------------------------------------------------------------
At present I am a final year student of the Master in Project Management,
Universiti Teknologi Malaysia (UTM), a joint-venture programme between
JKR-UTM. I am undertaking a research on METHOD TO RESOLVE
BUILDING PROJECT DELAY to fulfil the requirements for the award of
Master Project Management.
The objectives of undertaking this research are as follows:-
i. To evaluate the effectiveness of the traditional approach in project
delay issue.
ii. To evaluate the potential application of contemporary approach in
resolving project delay issue.
iii. To develop guideline for project on time delivery.
I would be very grateful if you would have some time to complete the
questionnaire attached. All data compiled are solely for academic purposes
only. All your answers will be treated as CONFIDENTIAL. Your cooperation
is much appreciated. If you have any questions do not hesitate to contact me at
012-2440944 / 03-26107114 or [email protected] or
Detail of Researcher
Name : MOHD ZAMRI BIN MOHAMUD
Course : Master of Project Management (MAZ)
Department : Secretariat Department, Corporate Affairs Branch
Email : [email protected]
Contact : 012-2440944 / 03-26107114
Supervisor : ASSOC. PROF. DR MOHAMAD IBRAHIM BIN
MOHAMAD
Faculty : Civil Engineering (FKA)
THANK YOU VERY MUCH FOR YOUR KIND COOPERATION AND
TIME
107
SECTION A : GENERAL INFORMATION
1. Grade :
2. Years of Service :
3. Years in Project Management :
4. Depa
rtme
nt
:
5. State the type of building which involved the most frequent for delays
6. State the number of project delays which is faced by respondent
7. State the actual time spend for the most delayed project
Department
1 Project Management Office (PMO)
2 Cawangan Kerja Bangunan Am (CKBA)
3 Cawangan Pendidikan & Pengajian Tinggi (CPPT)
4 Cawangan Kerja Kesihatan (CKK)
5 Cawangan Kerja Keselamatan (CKS)
6 Others :.....................................................(please specify)
School Office Public
Facilities
Hospital Other
1-3
projects
4-6
projects
7-9
projects
10-12
projects
>13
projects
3 <
months
3 - 6 months >6 Month
≤ 5 years 6 - 10 years
11 – 15 years 16 - 20 years ≥ 21 years
52 48/52 41/44 54
≤ 5 years
6 - 10 years ≤ 5 years
11 – 15 years 16 - 20 years ≥ 21 years
108
SECTION B: CAUSES OF DELAYS
The following statement represent factors that contribute to delay of JKR
Projects based on causes of delay categorized into seven (7) groups.
For each option, please circle to show your level of agreement based on the
Likert scale given below.
1 2 3 4 5
Least
Agreeable
Slightly
agreeable
Moderately
agreeable
Agreeable Strongly
Agreeable
No Categories 1: CLIENT RELATED 1 2 3 4 5
BA1 Client Interference
BA2 Slowness in decision making process
BA3 Contract modification
BA4 Change order
BA5 Client cannot provide enough fund
BA6 Uncooperative client
BA7 Late payment
BA8 Unrealistic contract duration
BA9 The land is not free from dispute
BA10 Not full fill JKR requirements in terms of
project site, project scope and cost.
No Categories 2: CONTRACTOR
RELATED 1 2 3 4 5
BB1 Poor site management and supervision
BB2 Financial difficulties – Poor Cash Flow
Management
BB3 Unsuitable construction materials and
improper construction method implement
BB4 Inadequate contractor experience
BB5 Conflicts in sub-contractor schedule in
execution of project
BB6 Rework due to errors during construction
BB7 Conflicts between contractor and others
parties (consultant and client) and also
109
No Categories 3: CONSULTANT
RELATED 1 2 3 4 5
BC1 Delay in approving major changes in the
scope of work
BC2 Poor communication and coordination
BC3 Inadequate experience of consultant
BC4 Mistakes and discrepancies in design
documents
BC5 Delay in producing design documents
BC6 Unclear and inadequate details in drawings
BC7 Insufficient data collection and survey
before design
BC8 Poor monitoring and control of progress of
work
BC9 Late valuation work
BC10 Late issue of instruction
partners (shareholders)
BB8 Poor communication and coordination
BB9 Ineffective planning and scheduling of
project
BB10 Delay in sub-contractors work
BB11 Delay in site mobilization
BB12 Inappropriate or poor criteria for selection of
sub-
contractor
No Categories 4: MATERIAL RELATED 1 2 3 4 5
BD1 Shortage of construction materials in
markets
BD2 Changes in material and specification during
construction
BD3 Delay in material delivery
BD4 Damage of sorted material while they are
needed
urgently
BD5 Late procurement of material
110
No Categories 6: LABOUR RELATED 1 2 3 4 5
BF1 Working permit of labours
BF2 Lack of skilled labour
BF3 Low productivity level of labour
BF4 Shortage of manpower
BF5 Labour injuries / accident in site
BF6 Personal conflicts among labours
No Categories 7: EXTERNAL FACTOR 1 2 3 4 5
BG1 Delay in obtaining permits from
municipality
BG2 Slow process of Building Permit
BG3 Delay in providing services from utilities
(such as
water, electricity)
BG4 Changes in Government regulations and
laws
BG5 Accident during construction
BG6 Traffic control and restriction at job site
BG7 Price fluctuation
SECTION C: TRADITIONAL APPROACH BY JKR DEALING
WITH PROJECT DELAY
BD6 Noncompliance of material to specification
No Categories 5: EQUIPMENT RELATED 1 2 3 4 5
BE1 Equipments breakdown
BE2 Shortage of equipment
BE3 Low level of equipment
BE4 Low productivity and efficiency of
equipment
BE5 Lack of high-technology mechanical
equipment
111
The following statement represents the current practice in JKR when dealing
with projects delays.
Please answer the effectiveness of the current practice according to this scale.
1 2 3 4 5
Least
Ineffective
Low
Ineffective
Moderately
Ineffective
Ineffective Highly
Ineffective
Traditional Approach by JKR 1 2 3 4 5
C1
S.O issues the Warning Letter (Surat Amaran
Kemungkiran) for contractor to increase the
productivity of works
C2
Contractor prepare the Recovery Plan /
Rescheduling Work
Programme by using the 4M method
(Machineries, Material,
Money and Manpower)
C3
Coordination meetings on a weekly basis to
monitor the progress of work on site by S.O.
(Weekly and Monthly report)
C4
Head of Project Team (HOPT) will prepare the
report project delays and present in Jawatankuasa
Projek Sakit JKR.
C5
Contractor ask for Extension of Time (E.O.T) for
reasons or
causes of delay which is beyond his control
accordance with
Clause of Contact
C6
If the contractor fails to complete the works by the
Completion Date, the contractor shall pay or allow
to the JKR a sum calculated at the rate stated as
Liquidated Ascertained Damages (L.A.D)
C7 Termination based on Clause of Contract (COC).
C8
Appoint Third Party / New Contractor to Continue
the balance
of work (Kontraktor Penyelamat)
SECTION D: PROPOSED CONTEMPORARY APPROACH TO JKR
DEALING WITH PROJECT DELAY
112
The following statement represents the proposed method to avoid project
delays in JKR.
How did the effectiveness of the following methods can minimise delays?
Please answer the effectiveness of the proposed method according to this scale.
1 2 3 4 5
Least
Effective
Low Effective Moderately
Effective
Effective Highly Effective
CATEGORY A : SCOPE MANAGEMENT 1 2 3 4 5
DA1
Implement Value Management & Value
Engineering Lab to determine scope of work in
Planning & Design Stage
DA2 Complete and accurate project feasibility study and
site investigation to all projects done by JKR
DA3 Utilization of the latest construction technology
method - Industrialized Building System (IBS)
DA4 Utilization of the latest construction technology
method - Building Information Modeling (BIM)
DA5 Implement Project Management Plan (PMP) to all
JKR Project.
CATEGORY B : TIME MANAGEMENT 1 2 3 4 5
DB1
Proper project planning and scheduling using
appropriate scheduling method such as Primavera
or MS Project
DB2
Execute delayed activities by subcontractors. Work
Breakdown Structure (WBS) as a tool to determine
duration for every task
DB3
Accurate initial time estimation by establish
methodology for
estimation process
CATEGORY C : COST MANAGEMENT 1 2 3 4 5
DC1 Accurate initial cost estimates. Enough of
information necessary for estimation and adequate
113
timeframe to perform estimates
DC2
Payment processed by the Client. JKR only
prepared and endorsed the JKR 66 Certificate. No
warrant allocation
DC3 Allow Contingency Cost in the Contract Sum
DC4
Enforce Liquidated damages clauses on monthly
basic based on Work Programmed as milestone to
achieve and offering incentives for early
completion
CATEGORY F : HUMAN RESOURCES
MANAGEMENT 1 2 3 4 5
DF1 Select the competent project manager
CATEGORY D : QUALITY MANAGEMENT 1 2 3 4 5
DD1 Frequent progress meeting with all stakeholder to
monitor the progress of work
DD2 Build a systematic project control and monitoring
mechanism
DD3 Frequent coordination between the parties involved
to avoid dispute between stakeholder
DD4 Implement Project Health Check (PHC) to all JKR
projects
DD5 Site meeting and technical meeting as one of the
tool for monitoring the project
DD6
Implement SERQUAL Analysis to evaluate
Customer satisfaction in meeting project schedule,
quality and cost
CATEGORY E : COMMUNICATION
MANAGEMENT 1 2 3 4 5
DE1
Developing appropriate communication system
linking to all functional group using new
technology- social network etc
DE2 Collaborative teamwork in construction with
effective site management and supervision.
DE3 Clear information and communication channels in
roles and responsible of all stakeholder.
DE4 Community involvement to reduce the absence of
bureaucracy to avoid complaints from publics
DE5 Developing appropriate communication system
linking to all functional group
114
DF2 Hire experience personnel for project
implementation
DF3
Apply collaborative teamwork environment
application with Multidisciplinary / competent
project team and Promotion team working among
project participants
DF4 Competent personnel of consultant/designer to
complete and proper design at the right time
DF5
Developing human resources in the construction
industry through proper training and classifying of
craftsman.
CATEGORY G : RISK MANAGEMENT 1 2 3 4 5
DG1 Early in obtaining permit and approval from
relevant authority
DG2 Implement Risk Management Plan (RMP)
DG3
The effectiveness of risk management will be
increase if the project manager see risk as an
opportunity
DG4
Cross functional collaborative teamwork is an
effective way for collectively dealing with threats
(risk) to the project environment.
CATEGORY I : INTERGRATION
MANAGEMENT 1 2 3 4 5
DI1 Proper emphasis on past experience of project
parties
CATEGORY H : PROCUREMENT
MANAGEMENT 1 2 3 4 5
DH1
Adopting a new approach to contract award
procedure by giving less weight to prices and
more weight to the capabilities and past
performance of contractor
DH2 Not awarding contract based on the lowest bid
DH3 Comprehensive contract documentation
DH4
Adopting a new approach to contracting such as
Cost Plus Contract, GC/Works, Prime
Contracting Agreement and FIDIC type of
contract
115
DI2 Offer incentive for early project completion
DI3 Ensure the availability of resources (finance,
materials, equipments, workmen, etc)
DI4 Integrate Risk Management Plan and Work
Programme(CPM)
Thank you for completing this questionnaire
116
APPENDIX C
Interview with Expert Panel on Activity in Project Life Cycle
The following statement represent guidelines activity in the project life cycle
For each option, please circle to show your level of agreement based on scale
given below.
1 2 3 4
Least Agreeable Slightly agreeable Agreeable Strongly Agreeable
Respondents
Inception Activities #1 #2 #3 #4 #5
1. Defining the scope and background of project. 3 4 4 4 3
2. Identifying business drivers that lead the project and define
the strategic direction
4 4 4 4 4
3. Developing the business cases that define the problem/need
to be address by the project and the reason for project
launching.
4 3 4 4 4
4. Creating a list of project goals and objectives that contribute
to solving the problem.
4 4 4 4 4
5. Analyzing options or alternatives to the project. 4 3 3 3 4
6. Justifying the project through performing feasibility
analysis.
3 3 3 4 4
7. Identifying constraints and assumptions. 4 4 3 3 3
8. Identifying constraints and assumptions. 4 3 3 3 4
9. Defining scope, including boundaries, deliverables and
requirements
4 4 4 4 4
10. Developing product acceptance criteria. 3 3 3 3 3
11. Analyzing stakeholders and their expectations and
involvement level.
3 4 4 4 4
12. Designing an organizational chart that identifies roles and
responsibilities of stakeholders.
4 4 4 4 4
13. Writing a proposal document that summarizes the project
and provide the relevant information for all stakeholders.
4 4 4 4 4
14 Getting approval of the proposed project and starting the
planning process.
4 4 3 3 3
Planning Activities
1. Reviewing lessons learned from previous projects (if any) to
gain valued expertise and knowledge for present project.
4 3 3 3 4
2. Selecting and interviewing the best candidates to the project
team.
3 3 3 4 4
3. Creating a team composition chart that includes roles and
names of peoples involved in the implementation process.
4 4 3 3 3
4. Writing a staffing plan that explains how to manage the
team and collaborative activities.
4 3 3 3 4
5. Designing a change management plan that explores a
mechanism of defining, approving and implementing project
changes and updates.
4 4 4 4 4
6. Making an issue management plan to define how to
document and manage issues.
3 3 3 3 3
7. Defining quality assurance and control activities that
identify how to keep the project and its results relevant to
project requirements.
3 4 4 4 4
117
8. Developing the project schedule that defines time required
for implementing the project, along with activity durations
and milestones.
4 4 4 4 4
9. Establishing contractual relationships with suppliers and
procurers.
3 3 3 3 4
10. Designing a training plan that explores methods and
techniques of staff training and development.
4 4 4 4 4
11. Developing cost estimates that define how much funding
will be required to perform the project and complete its
goals and objectives.
4 4 3 3 4
12. Making a risk management plan that specifies processes and
tools for analyzing and managing threats and uncertainties.
3 4 4 4 3
13. Developing a communications management plan that
explains how communications between stakeholders should
be established and managed.
4 4 4 4 4
14. Designing a project management plan that defines key
activities for managing the project and its content.
4 3 4 4 4
Implementation Activities.
1. Conducting status meetings to review current status of the
project.
4 4 4 4 4
2. Conducting status meetings to review current status of the
project.
4 4 4 4 4
3. Providing training to personnel if necessary. 4 4 4 4 4
4. Leading and guiding the project team. 4 4 4 4 4
5. Managing changes and updates. 4 4 3 3 3
6. Logging issues and developing solutions for handling logged
issues.
4 3 3 3 4
7. Managing identified risks. 4 4 4 4 4
8. Communicating with the team and other stakeholders to get
their feedback and keep the project up-to-date.
3 3 3 3 3
9. Managing deliveries and procurement. 3 4 4 4 4
10. Controlling and assuring project quality. 4 4 4 4 4
11. Using reporting as a mechanism of tracking the
implementation process.
4 4 4 4 4
12. Reviewing status of project deliverables to ensure they are
produced according to acceptance criteria.
3 3 3 3 3
13. Monitoring staff performance to ensure project work is
performed according to the plan.
4 4 4 4 4
Closure Activities.
1. Performing a post implementation review to confirm the
project has reached its goals and objectives and that
deliverables are produced.
4 4 4 4 4
2. Conducting lessons learned exercises to document successful
experience and practice of the project.
4 4 4 4 4
3. Transferring project personnel to other projects, or releasing
them.
4 4 3 3 3
4. Closing financial operations and transactions. 4 3 3 3 4
5. Handing over the project product to the customer. 4 4 4 4 4
6. Getting the customer’s approval that meets the customer
satisfaction.
4 4 4 4 4
118
Appendix: D
Interview with Expert Panel on Duration of Activity
PROPOSED GUIDELINES FOR ON TIME PROJECT DELIVERY
The workflow consists of five stages, here after referred to as intervention
category
No Task Yes No Duration
1.0 PRE PLANNING
1.1 Overview and Early Planning
1.2 Received list of Project from Economic Planing Unit
(EPU), JPM
1.3 Clarification of Project based on Location, Cost,
Ministry/Agency & ACAT
1.4 Analysis and Distributed to implementer ( JKR
/Agency)
1.5 Set the Strategy of Implementation
1.6 Distributed to Busines Sector / Design Sector
1.7 Coordination Meeting with Director of Sector Unit
(SBU)
2.0 REGISTER PROJECT IN SKALA Yes No Duration
2.1 Determine the Project Team and Appoint Head of
Project Team (HOPT)
2.2 Finalize the stategy of implementation and download
in SKALA
2.3 Register the project title by Head of Project Office
(HPO)
2.4 Updated the latest list of project to EPU
3.0 PLANNING Yes No Duration
3.1 Received Brief Project, Land and Badjet (Gate Way
1)
3.2 Appoint Head of Project Team
3.3 Review Project Brief
3.4 Arrange the Site Visit
3.5 Review and Fullfill the requirement by the local
authority
3.6 Land Surveying
3.7 Prepare Report / Site Anlysis/Design Brief / Risk
Management Plan / Project Management Plan
3.8 Soil Investigation
3.9 Finalize Project Brief, Site and Cost
119
4.0 DESIGN Yes No Duration
4.1 CONCEPT DESIGN
4.1.1 Prepare Concept Design
4.1.2 Prepare Early Estimate Cost
4.1.3 Review Concept Design
4.1.4 Value Engineering & Gate Way 2
4.1.5 Client Approval
4.2 PRELIMINARY DESIGN
4.2.1 Prepare Preliminary design & specification
4.2.2 Prepare Drawing 100 scale
4.2.3 Development Order
4.3 DETAIL DESIGN Yes No Duration
4.3.1 Prepare detail design
4.3.2 Coordination drawing between all displin
4.3.3 Value Engineering 2 & Gate Way 2
4.3.4 Amendment Detail Design
4.3.5 Approval of Building Plan
5.0 PROCUREMENT
5.1 Prepare Tender Document / Gateway 3
5.2 Advertising of Tender
5.3 Evaluation of Tender
5.4 Tender Board Meeting
5.5 Prepare As Tender Detail Abstract (ATDA) & Get
Approval from the Client
5.6 Letter of Award
6.0 CONSTRUCTION Yes No Duration
6.1 Preliminary Item
6.2 Civil Works
6.3 Structure Works
6.4 Architect Works
120
6.5 Mechanical Works
6.6 Electrical Works
6.7 External Works
6.8 Provisional Item
*All the activity depends on the contract duration
and scope of work
7.0 HANDING OVER Yes No Duration
7.1 Installation of TNB transformer, etc & Energizing of
TNB Sub Station
7.2 Testing & Commissioning