15
Collaboration meeting, Riverside 24 th -27 th March 2010 Andrew Moss ASTeC Collaboration meeting, Riverside, 24 th 27 th March 2010 MICE RF Amplifier Status

MICE RF Amplifier Status · 2010. 3. 25. · install at RAL by end of 2010 if money allows •RF testing of amplifiers will receive sustained effort for 2010 so that setup in the

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Collaboration meeting, Riverside 24th -27th March 2010

    Andrew Moss

    ASTeC

    Collaboration meeting, Riverside,

    24th – 27th March 2010

    MICE RF Amplifier Status

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    Outline

    • Status of large amplifier

    • Status of power supply

    • MICE hall design/implementation

    • Conclusion

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew MossAndrew Moss

    2 MW

    Amplifier

    2 MW

    Amplifier

    Master Oscillator

    Controls etc

    201 MHz Cavity Module

    2 MW

    Amplifier

    2 MW

    Amplifier

    201 MHz Cavity Module

    LBNL

    CERN300 kW

    Amplifier

    300 kW

    Amplifier

    300 kW

    Amplifier

    300 kW

    Amplifier

    HT

    Supplies

    HT

    Supplies

    Daresbury

    DL Test System

    The Task for Daresbury RF group

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    Daresbury Test system

    What is built at

    DL currently

  • Collaboration meeting, Riverside 24th -27th March 2010

    TH116 amplifier

    Andrew Moss

    •Connected to its test

    load, tested water

    flows, no leaks

    anywhere inside

    circuit or load

    •Manufactured input

    sliding short for input

    tuning, tested

    operation of grid and

    anode tap moving

    circuits, so far all this

    looks good on network

    analyser

  • Collaboration meeting, Riverside 24th -27th March 2010

    116 HT tank

    Andrew Moss

    • ‘Test TH116’ triode in

    amplifier HT tank

    • Water connections

    • HT connection visible,

    water feed and return are

    inside this connection

    • PTFE insulators

    • This part of the amplifier

    is up at 40kV, arcing a

    danger and large risk

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    Protection for the HT tank

    • Installing arc detectors,

    smoke alarm and camera to

    monitor conditions inside

    the HT tank remotely

    • Any arcing will damage

    silver plated components

    and require a

    stripdown/repair to be made,

    this would take months to

    fix and we must be careful

    to avoid this, will gently run

    the amplifier up and

    understand how to operate it

  • Collaboration meeting, Riverside 24th -27th March 2010

    HT power supply• Tested PLC controller that

    monitors and interlocks all the

    auxiliary power supplies with

    cooling, door interlocks and

    equipment protection systems

    •Filament heater tested to full

    power on the test triode

    •Cathode bias unit tested to

    operation levels

    •System earthing assessed and

    corrected to promote return

    current path back through

    monitor circuits

    Andrew Moss

  • Collaboration meeting, Riverside 24th -27th March 2010

    HT power supply

    Andrew Moss

    • Still left to do :-

    – Some wiring control

    wiring between amp and

    HV rack/Aux rack

    – Cathode modulator needs

    building/testing

    – Crowbar circuit needs

    testing

    – HV pressure test of

    amplifier and HV

    components

    – Estimate 1 months effort

  • Collaboration meeting, Riverside 24th -27th March 2010

    Schedule

    •All four MICE 116 tubes

    are on site at Daresbury

    ready for experiment

    •Plan to test assembled

    amplifier then assemble a

    CERN amplifier and test

    •Build new power supplies

    for 4616 and 116 sections

    and move first set down for

    install at RAL by end of

    2010 if money allows

    •RF testing of amplifiers

    will receive sustained effort

    for 2010 so that setup in

    the mice hall can be more

    easily achieved

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    RF Load

    • Altronic Reaserch water

    load, already tested to

    3MW pulse

    • Load

    • Water cooling plant

    • Much smaller than our

    current test load which

    would be a major positive

    design change for the hall

    installation

    • Possibility to have one

    cooling plant for multiple

    waveguide loads - ideal

    for MICE due to low

    average power

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    Amplifier to cavity installation 1

    RF Loads

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    Amplifier to cavity installation 2

    RF Loads

  • Collaboration meeting, Riverside 24th -27th March 2010

    Hall implementation

    • Starting to work on hall plan in more detail

    • Expect to be able to use 3D CAD drawings to be able to understand how to fit the RF equipment under the floor and to see how the system can be built up in installed sections

    • Smaller load identified, need to look for phase shifters and hybrid devices next to reduce size of these items

    • Nitrogen pressure will be used for whole waveguide system to raise voltage stand off and provide a ‘W/guide complete’ interlock

    Andrew Moss

  • Collaboration meeting, Riverside 24th -27th March 2010 Andrew Moss

    Conclusion

    • Large amplifier ready for testing, connected to water,

    test load and checked with network analyser as far as

    possible

    • Some work remains on the power supply, this will

    continue as staff effort allows

    • Hall design in progress and components being

    identified that will be better for the installation, need

    to progress to 3D CAD models as soon as possible

    • Committed RF effort for this year to fully test

    amplifier system