Upload
gerik
View
44
Download
2
Tags:
Embed Size (px)
DESCRIPTION
NYISO U.S. Department of Energy Smart Grid Investment Grant Project. Michael Swider Manager – Research & Development New York Independent System Operator Advanced Energy Conference 2013 New York City, NY April 30, 2013. Topics. Introduction to the NYISO Project Overview - PowerPoint PPT Presentation
Citation preview
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Michael SwiderManager – Research & Development
New York Independent System Operator
Advanced Energy Conference 2013New York City, NY
April 30, 2013
NYISO U.S. Department of Energy
Smart Grid Investment Grant Project
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Topics Introduction to the NYISO Project Overview Project Participants Accomplishments Project Schedule Challenges & Lessons
Learned Road Map
2
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved. 3
• Reliable operation of the bulk electricity grid Managing the flow of power on 11,000 circuit-miles of
transmission lines from more than 300 generating units• Administration of open and competitive
wholesale electricity markets Bringing together buyers and sellers of energy and
related products and services• Planning for New York’s energy future
Assessing needs over a 10-year horizon and evaluating projects proposed to meet those needs
• Advancing the technological infrastructure of the electric system Developing and deploying information technology and
tools to make the grid smarter
NYISO Roles
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
SGIG Project Summary Budget: $75,710,733 Timeline: July 1, 2010 – June 30, 2013 Equipment: Phasor Measurement Units,
Phasor Data Concentrators, Phasor Measurement Network, Capacitors
Applications: Enhanced State Estimator, Voltage Stability Monitoring, Situational Awareness (Visualization), Post-Mortem Analysis
Benefits: Improved Grid Reliability & Power Flow Efficiency, Reduced Costs, Reduced Likelihood of Disturbances
4
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Project Participants NYISO as the Primary Awardee for the Grant New York Transmission Owners as
SubAwardees Quanta Technology as the primary consultant,
providing Engineering and Technical expertise Crowe Horwath LLP as a subcontractor to
provide Grant Administration and Compliance expertise
PMOLink, LLC as a subcontractor to provide Project Planning and Management services
Utilicast, EPG, & ABB for Application Development, Integration, Testing & Deployment
EPRI & EnerNex to conduct Controlled System Separation Feasibility Study and Dynamic Model Calibration Study
5
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved. 6
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
New York Control Area
7
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Accomplishments PMU Design & Build-Out
40 (of 41) Substations Covered 47 (of 48) PMUs Installed
PDC Design & Build-Out 8 (of 8) TO Control Center PDCs Installed
Capacitor Installations 458.2 (of 938.2) MVAr of Capacitors
Installed Phasor Measurement Network
Wide Area Network Build-Out Complete for 10 (of 10) Sites
6 (of 8) Transmission Owner Control Center PDCs Networked
Photos courtesy of Central Hudson Gas & Electric and New York Power Authority
8
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Accomplishments Situational Awareness (Visualization) Applications
Began testing EPG base product in early 2012 Development continued to meet NYISO
requirements Currently Executing Site Acceptance Testing
Enhanced State Estimator Applications Development / Testing in 2012 Q1 2013 Deployment
Voltage Stability Monitoring Applications Development began in late 2012 Currently Executing Site Acceptance Testing Q2 2013 Deployment
9
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Visualization
10
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Accomplishments System Studies: Controlled System Separation
Conducted by EnerNex All deliverables received in 2012 Final approval by NYISO in Q1 2013
System Studies: Dynamic System Model Calibration Conducted by EPRI All deliverables received in 2012 Additional scope added to be complete by June 2013
11
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Anticipated Benefits Situational Awareness
Enhance NYISO’s ability to detect system vulnerabilities and disturbances in real time and to potentially mitigate their impact
Phasor Enhanced State Estimation Addition of time-synchronized data will improve the
existing state estimation function Reduction in Transmission Losses
Capacity and energy savings as capacitors reduce losses by improving power factors and voltage profiles
12
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Challenges & Lessons Learned
Project Execution Challenges External Dependencies Coordination Among Multiple Entities Schedule Delays Business Owner Acceptance
Technical Challenges Knowledge / Experience Performance / Support Cyber Security Data Retention
Lessons Learned Shared Requirements/Goals Expansion
13
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
Road Map People
Post-Project Support from IT & Operations Show Benefits to Stakeholders
Process Ongoing Planning for NYS and Beyond Data Analysis & Technology Growth
Technology Ongoing Equipment Installations Redundancy Advanced Applications
14
© 2000-2013 New York Independent System Operator, Inc. All Rights Reserved.
The New York Independent System Operator (NYISO) is a not-for-profit corporation
responsible for operating the state’s bulk electricity grid, administering New York’s competitive wholesale electricity markets,
conducting comprehensive long-term planning for the state’s electric power system, and
advancing the technological infrastructure of the electric system serving the Empire State.
www.nyiso.com
15