ID Task Name Duration Start Finish Predecessors 1 PEMBANGUNAN JALAN R3 SECTION II 200 days Fri 13/06/14 Thu 19/03/15 2 DIVISI 1. UMUM 17 days Fri 13/06/14 Mon 07/07/14 3 Pek. Pengukuran Site 7 days Fri 13/06/14 Mon 23/06/14 4 Pek. Mobilisasi dan Demobilisasi (termasuk pengujian bahan dan test beton) 14 days Mon 16/06/14 Thu 03/07/14 3SS+1 day 5 Pek. Direksi keet 7 days Mon 16/06/14 Tue 24/06/14 4SS 6 Pek. Los Kerja/bahan 7 days Wed 25/06/14 Thu 03/07/14 5 7 Pek. Papan Nama Proyek 7 days Tue 17/06/14 Wed 25/06/14 5FF+1 day 8 Pek. Bouplank 3x pakai 14 days Wed 18/06/14 Mon 07/07/14 12FF+2 days 9 Pek. Pengaturan lalu lintas dan Pagar Pengaman 14 days Mon 16/06/14 Thu 03/07/14 5SS 10 Pek. Kisdam 7 days Wed 25/06/14 Thu 03/07/14 5 11 Pek. Pembersihan Damija 7 days Wed 25/06/14 Thu 03/07/14 5 12 Pek. Pembersihan Saluran 7 days Wed 25/06/14 Thu 03/07/14 5 13 DIVISI 2. DRAINASE 57 days Fri 27/06/14 Mon 15/09/14 14 Pek. Pasangan bata 30 days Fri 27/06/14 Thu 07/08/14 8SS+7 days 15 Pek. Plesteran + acian t=1,5 cm (Adukan 1 : 3) 30 days Fri 27/06/14 Thu 07/08/14 14FF 16 Pek. Saluran pipa beton bertulang 6 1500 mm 7 days Thu 17/07/14 Fri 25/07/14 14SS+14 days 17 Pek. Siar dalam batu belah (adukan 1 : 2 30 days Thu 24/07/14 Wed 03/09/14 16SS+5 days 18 Pek. Drainase Buis Beton Bulat 1/2 Dia 30 (gravel) 14 days Mon 28/07/14 Thu 14/08/14 16 19 Pek. Drainase Buis Beton Bulat Dia 30 14 days Mon 28/07/14 Thu 14/08/14 16 20 Pek. Saluran Drainase Beton Bertulang (Ready mix K-225 40 days Tue 22/07/14 Mon 15/09/14 21SS 21 Pek. Saluran pipa beton bertulang 6 2000 mm 7 days Tue 22/07/14 Wed 30/07/14 16SS+3 days 22 DIVISI 3. PEKERJAAN TANAH 110 days Thu 19/06/14 Wed 19/11/14 23 Pek. Galian Tanah 30 days Thu 19/06/14 Wed 30/07/14 8SS+1 day 24 Pek. Urugan tanah kembali bekas galian (dipadatkan 40 days Tue 16/09/14 Mon 10/11/14 16;18;19;21;20 25 Pek. Penyiapan badan jalan 8 days Fri 31/10/14 Tue 11/11/14 24FF+1 day 26 Pek. Buangan tanah bekas galian 7 days Tue 11/11/14 Wed 19/11/14 24 27 DIVISI 5. PERKERASAN BERBUTIR 14 days Thu 23/10/14 Tue 11/11/14 28 Pek. Limestone tebal 30 cm 14 days Thu 23/10/14 Tue 11/11/14 25FF;24FF 29 DIVISI 7. STRUKTUR 156 days Thu 31/07/14 Thu 05/03/15 30 Pek. Beton K-225 (site mix) tiang railing 7 days Thu 05/02/15 Mon 16/02/15 40SF 31 Pek. Beton K-250 (Ready mix) (Pelat Decker STA 2+450) 7 days Fri 05/09/14 Tue 16/09/14 24SF 32 Pek. Beton K-225 (Ready mix) (Box Utilitas 40 days Thu 31/07/14 Wed 24/09/14 19SS+3 days 33 Pek. Beton Sikloop 7 days Fri 21/11/14 Mon 01/12/14 38 34 Pek. Lantai kerja Ready mix K-125 (Box Utilitas) 7 days Wed 26/11/14 Thu 04/12/14 39SS+10 days 35 Pek. Bekisting (2x pakai) 7 days Thu 29/01/15 Fri 06/02/15 36FF+1 day 36 Pek. Besi tulangan polos U24 50 days Fri 28/11/14 Thu 05/02/15 43SS+2 days 37 Pek. Besi tulangan ulir U32 7 days Wed 27/08/14 Fri 05/09/14 31SF 38 Pek. Cerucuk dolken 6 7 cm (STA 1800 s/d 1925) 7 days Wed 12/11/14 Thu 20/11/14 28 39 Pek. Pasangan batu belah 1 PC : 4 PS termasuk sulingan pipa PVC 1,5"+ ijuk 14 days Wed 12/11/14 Mon 01/12/14 28 40 Pek. Sandaran (railing) pipa galvanis 3" 7 days Mon 16/02/15 Tue 24/02/15 42 41 Pek. Bongkaran pas. batu 7 days Wed 25/02/15 Thu 05/03/15 40 42 Pek. Beton Struktur FS-45 Tb. 25 c 6 days Fri 06/02/15 Fri 13/02/15 35FF+5 days 43 Pek. Wet lean concrete tebal 5 cm (ready mix K-125 7 days Wed 26/11/14 Thu 04/12/14 39SS+10 days 44 DIVISI 8. PEKERJAAN MINOR 30 days Fri 06/02/15 Thu 19/03/15 45 Pek. Kerb pracetak ukuran 60x30x25 c 7 days Fri 06/02/15 Mon 16/02/15 42SS 46 Pek. Kerb inlet pracetak ukuran 60x30x25 c 14 days Fri 06/02/15 Wed 25/02/15 45SS 47 Pek. Pengecatan tiang railin 7 days Wed 11/03/15 Thu 19/03/15 41FS+3 days 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 r '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14 Nov '14 Dec '14 Jan '15 Feb '15 Mar '15 Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline Page 1 Project: PEMBANGUNAN JALAN R3 S Date: Tue 15/04/14

Microsoft Office Project - Pembangunan Jalan r3 Section II

Embed Size (px)

DESCRIPTION

Proyek Jalan

Citation preview

ID Task Name Duration Start Finish Predecessors

1 PEMBANGUNAN JALAN R3 SECTION II 200 days Fri 13/06/14 Thu 19/03/15

2 DIVISI 1. UMUM 17 days Fri 13/06/14 Mon 07/07/143 Pek. Pengukuran Site 7 days Fri 13/06/14 Mon 23/06/144 Pek. Mobilisasi dan Demobilisasi (termasuk pengujian bahan dan test beton) 14 days Mon 16/06/14 Thu 03/07/14 3SS+1 day5 Pek. Direksi keet 7 days Mon 16/06/14 Tue 24/06/14 4SS6 Pek. Los Kerja/bahan 7 days Wed 25/06/14 Thu 03/07/14 57 Pek. Papan Nama Proyek 7 days Tue 17/06/14 Wed 25/06/14 5FF+1 day8 Pek. Bouplank 3x pakai 14 days Wed 18/06/14 Mon 07/07/14 12FF+2 days9 Pek. Pengaturan lalu lintas dan Pagar Pengaman 14 days Mon 16/06/14 Thu 03/07/14 5SS

10 Pek. Kisdam 7 days Wed 25/06/14 Thu 03/07/14 511 Pek. Pembersihan Damija 7 days Wed 25/06/14 Thu 03/07/14 512 Pek. Pembersihan Saluran 7 days Wed 25/06/14 Thu 03/07/14 513 DIVISI 2. DRAINASE 57 days Fri 27/06/14 Mon 15/09/1414 Pek. Pasangan bata 30 days Fri 27/06/14 Thu 07/08/14 8SS+7 days15 Pek. Plesteran + acian t=1,5 cm (Adukan 1 : 3) 30 days Fri 27/06/14 Thu 07/08/14 14FF16 Pek. Saluran pipa beton bertulang φ 1500 mm 7 days Thu 17/07/14 Fri 25/07/14 14SS+14 days17 Pek. Siar dalam batu belah (adukan 1 : 2 30 days Thu 24/07/14 Wed 03/09/14 16SS+5 days18 Pek. Drainase Buis Beton Bulat 1/2 Dia 30 (gravel) 14 days Mon 28/07/14 Thu 14/08/14 1619 Pek. Drainase Buis Beton Bulat Dia 30 14 days Mon 28/07/14 Thu 14/08/14 1620 Pek. Saluran Drainase Beton Bertulang (Ready mix K-225 40 days Tue 22/07/14 Mon 15/09/14 21SS21 Pek. Saluran pipa beton bertulang φ 2000 mm 7 days Tue 22/07/14 Wed 30/07/14 16SS+3 days22 DIVISI 3. PEKERJAAN TANAH 110 days Thu 19/06/14 Wed 19/11/1423 Pek. Galian Tanah 30 days Thu 19/06/14 Wed 30/07/14 8SS+1 day24 Pek. Urugan tanah kembali bekas galian (dipadatkan 40 days Tue 16/09/14 Mon 10/11/14 16;18;19;21;2025 Pek. Penyiapan badan jalan 8 days Fri 31/10/14 Tue 11/11/14 24FF+1 day26 Pek. Buangan tanah bekas galian 7 days Tue 11/11/14 Wed 19/11/14 2427 DIVISI 5. PERKERASAN BERBUTIR 14 days Thu 23/10/14 Tue 11/11/1428 Pek. Limestone tebal 30 cm 14 days Thu 23/10/14 Tue 11/11/14 25FF;24FF29 DIVISI 7. STRUKTUR 156 days Thu 31/07/14 Thu 05/03/1530 Pek. Beton K-225 (site mix) tiang railing 7 days Thu 05/02/15 Mon 16/02/15 40SF31 Pek. Beton K-250 (Ready mix) (Pelat Decker STA 2+450) 7 days Fri 05/09/14 Tue 16/09/14 24SF32 Pek. Beton K-225 (Ready mix) (Box Utilitas 40 days Thu 31/07/14 Wed 24/09/14 19SS+3 days33 Pek. Beton Sikloop 7 days Fri 21/11/14 Mon 01/12/14 3834 Pek. Lantai kerja Ready mix K-125 (Box Utilitas) 7 days Wed 26/11/14 Thu 04/12/14 39SS+10 days35 Pek. Bekisting (2x pakai) 7 days Thu 29/01/15 Fri 06/02/15 36FF+1 day36 Pek. Besi tulangan polos U24 50 days Fri 28/11/14 Thu 05/02/15 43SS+2 days37 Pek. Besi tulangan ulir U32 7 days Wed 27/08/14 Fri 05/09/14 31SF38 Pek. Cerucuk dolken φ 7 cm (STA 1800 s/d 1925) 7 days Wed 12/11/14 Thu 20/11/14 2839 Pek. Pasangan batu belah 1 PC : 4 PS termasuk sulingan pipa PVC 1,5"+ ijuk 14 days Wed 12/11/14 Mon 01/12/14 2840 Pek. Sandaran (railing) pipa galvanis 3" 7 days Mon 16/02/15 Tue 24/02/15 4241 Pek. Bongkaran pas. batu 7 days Wed 25/02/15 Thu 05/03/15 4042 Pek. Beton Struktur FS-45 Tb. 25 c 6 days Fri 06/02/15 Fri 13/02/15 35FF+5 days43 Pek. Wet lean concrete tebal 5 cm (ready mix K-125 7 days Wed 26/11/14 Thu 04/12/14 39SS+10 days44 DIVISI 8. PEKERJAAN MINOR 30 days Fri 06/02/15 Thu 19/03/1545 Pek. Kerb pracetak ukuran 60x30x25 c 7 days Fri 06/02/15 Mon 16/02/15 42SS46 Pek. Kerb inlet pracetak ukuran 60x30x25 c 14 days Fri 06/02/15 Wed 25/02/15 45SS47 Pek. Pengecatan tiang railin 7 days Wed 11/03/15 Thu 19/03/15 41FS+3 days

07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23r '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14 Nov '14 Dec '14 Jan '15 Feb '15 Mar '15

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 1

Project: PEMBANGUNAN JALAN R3 SDate: Tue 15/04/14