Mid-Bay Bridge Connector Phase II and III. December 2011 Project Update. Milestone Highlights - Start Date:February 14, 2011 - November Completion Date:January 28, 2014 December Completion Date:January 28, 2014 December CPM Schedule:Approved Time Highlights - PowerPoint PPT Presentation
Citation preview
Mid-Bay Bridge Connector Phase II and III
December 2011 Project Update
Milestone Highlights- Start Date: February 14, 2011- November Completion Date: January 28, 2014- December Completion Date: January 28, 2014- December CPM Schedule: Approved
Time Highlights- Original Contract Day: 298 of 1080- Weather Days: 3- Change Order Days: 0- Total Contract Days: 298 of 1083
Contract Amount Highlights- Contract Amount: $ 48,732465.03 - Change Order Amount: $ 25,000.00- Fuel and Bits Adjustment: $ 343,237.83- New Contract Amount: $49,100,702.86- Amount Paid To Date: $ 14,969,680.06
PHASE II%
Complete
2011 2012 2013 2014 Completion Date
Roadway 29 % Dec. 2013
Range Road Bridge 72 % Apr.
2012
Rocky Creek Bridge 29 % Dec.
2013
Turkey Creek Bridge
18 % Aug. 2012
Total Project Completion 28 % Feb.
2014
Turkey Creek Bridge
Rocky Creek Bridge
Range Road Bridge
Phase II Completion Dates
ActivityOriginal Duratio
n
% Comple
te Start Date
Actual Start
Duration Finish
Actual Finish
Concrete Girder
Placement5 days 100 % Oct. 5,
2011Oct. 12, 2011
Oct. 9, 2011
Oct. 12, 2011
Deck Placement and Cure
31 days 74 % Nov. 11, 2011
Nov. 15, 2011
Dec. 11, 2011
Approach Slab
Placement18 days 0% Dec. 12,
2011Dec. 29, 2011
Traffic Barrier Wall Placement
1 days 0% Apr. 24, 2012
Apr. 24, 2012
Profile and Groove Deck 4 days 0% Jan. 10,
2012Jan. 13, 2012
Range Road Bridge
Range Road Bridge – Milestones
Range Road Bridge – Deck
Phase II Roadway (North of Range)
ActivityOriginal Duratio
n
% Comple
teStart Date
Actual Start
Duration Finish
Actual Finish
Production Piles
(South)65 days 55 % Sept. 12,
2011Sept. 12,
2011Feb. 8, 2012
Substructure (South) 55 days 0% Dec. 13,
2011Feb. 17, 2012
Concrete Girders (South)
41 days 0% Jan. 7, 2012
Feb. 16, 2012
Deck Placement
(South)58 days 0% May 12,
2012Jul. 8, 2012
Production Piles
(North)75 days 0% Nov. 3,
2012Jan. 16, 2013
Substructure (North) 56 days 0% Jan.17,
2013Mar. 1, 2013
Concrete Girders (North )
35 days 0% Mar. 22, 2013
Apr. 25, 2013
Deck Placement
(North)58 days 0% Jul. 27,
2013Sept. 22,
2013
Rocky Creek Bridge
Rocky Creek Bridge – Milestones
Phase II Bridge – Rocky Creek
ActivityOriginal Duratio
n
% Comple
teStart Date
Actual Start
Duration Finish
Actual Finish
Mobilization 6 days 100% Jan. 17, 2013
Oct. 17, 2011
Jan. 22, 2013
Oct. 23, 2011
Test and Production
Piles62 days 34 % Nov. 16,
2011Nov. 17, 2011
Jan. 16, 2012
Substructure
Construction
37 days 0% Feb. 1, 2012
Mar. 8, 2012
Concrete Girder
Placement9 days 0% Mar. 19,
2012Mar. 27,
2012
Deck Placement 40 days 0% May 17,
2012Jun. 25, 2012
Turkey Creek Bridge
Turkey Creek Bridge – Milestones
PHASE III%
Complete
2011 2012 2013 2014 Complete Date
Roadway 29 % Nov. 2013
SR 285 Bridge 34 % Nov.
2012
Swift Creek Bridge 19 % Sept.
2013
Fox Head Branch Bridge
0% Mar. 2013
Mill Creek Bridge 0% Aug.
2012
SR 85 Bridge 26 % July
2012
Total Project
Completion29 % Nov.
2013
Range Road Bridge
Phase III Completion Dates
SR28
5 Br
idge
Swift
Cre
ek
Brid
ge
Fox
Hea
d Br
anch
Br
idgeM
ill C
reek
Br
idge
SR85
Br
idge
ActivityOrigina
l Duratio
n
% Comple
teStart Date
Actual Start
Duration Finish
Actual Finish
Production Pile
Installation18 days 100% June 27,
2011June 27,
2011July 14, 2011
July 14, 2011
Substructure
Construction
20 days 0% Jan. 3, 2012
Jan. 23, 2012
Steel Girder Placement 10 days 0% May 15,
2012May 25, 2012
Deck Placement and Cure
42 days 0% June 18, 2012
July 29, 2012
Approach Slab
Placement18 days 0% July 4,
2012July 22, 2012
Traffic Barrier Wall Placement
4 days 0% Aug. 1, 2012
Aug. 5, 2012
Range Road Bridge
SR 285 Bridge – Milestones
SR28
5 Br
idge
Phase III – SR285 MSE Wall
Phase III – SR285 MSE Wall
ActivityOrigina
l Duratio
n
% Comple
teStart Date
Actual Start
Duration
FinishActual Finish
Production Pile
Installation30 days 100% Aug. 15,
2011Aug. 15,
2011Sept. 13,
2011Aug. 25,
2011
Substructure
Construction
40 days 0% Feb. 5, 2013
Mar. 16, 2013
Steel Girder Placement 20 days 0% Apr. 21,
2013May 10, 2013
Deck Placement and Cure
38 days 0% Jun. 25, 2013
Aug. 1, 2013
Approach Slab
Placement15 days 0% July 27,
2013Aug. 11,
2013
Traffic Barrier Wall Placement
8 days 0% Aug. 11, 2013
Aug. 19, 2013
Range Road Bridge
Swift Creek Bridge – Milestones
Swift
Cre
ek
Brid
ge
Phase III – Bridge (Swift Creek)
ActivityOrigina
l Duratio
n
% Comple
teStart Date
Actual Start
Duration Finish
Actual Finish
Production Pile
Installation30 days 0% Sept. 8,
2012Oct. 8, 2012
Substructure
Construction
50 days 0% Oct. 9, 2012
Nov. 28, 2012
Concrete Girder
Placement6 days 0% Dec. 2,
2012Dec. 8, 2012
Deck Placement and Cure
35 days 0% Jan. 23, 2013
Feb. 27, 2013
Approach Slab
Placement18 days 0% Feb. 4,
2013Feb. 22, 2013
Traffic Barrier Wall Placement
8 days 0% Feb. 22, 2013
Mar. 2, 2013
Range Road Bridge
Fox Head Branch Bridge – Milestones
Fox
Hea
d Br
anch
Br
idge
Phase III – Bridge (Fox Head Creek)
ActivityOrigina
l Duratio
n
% Comple
teEarly Start
Actual Start
Early Finish
Actual Finish
Production Pile
Installation30 days 0% Feb. 2,
2012Mar. 3, 2012
Substructure
Construction
28 days 0% Mar. 18, 2012
Apr. 15, 2012
Concrete Girder
Placement12 days 0% Apr. 20,
2012May 2, 2012
Deck Placement and Cure
36 days 0% Jun. 19, 2012
July 25, 2012
Approach Slab
Placement18 days 0% July 2,
2012July 20, 2012
Traffic Barrier Wall Placement
8 days 0% July 20, 2012
July 28, 2012
Range Road Bridge
Mill Creek Bridge – Milestones
Mill
Cre
ek
Brid
ge
Phase III – Bridge (Mill Creek)
ActivityOrigina
l Duratio
n
% Comple
teEarly Start
Actual Start
Early Finish
Actual Finish
Production Pile
Installation35 days 100% Oct. 28,
2011Oct. 11, 2011
Dec. 1, 2011
Nov. 14, 2011
Substructure
Construction
39 days 0% Jan. 31, 2012
Mar. 10, 2012
Girder Placement 11 days 0% Mar. 31,
2012Apr. 11, 2012
Deck Placement and Cure
33 days 0% May 14, 2012
Jun. 16, 2012
Approach Slab
Placement16 days 0% May 29
2012Jun. 14, 2012
Traffic Barrier Wall Placement
6 days 0% Jun. 14, 2012
Jun. 20, 2012
Range Road Bridge
SR 85 Bridge – Milestones
SR85
Br
idge
Phase III – Pond No. 14