Miller Road Project Linden Rd to I-75. INTRODUCTION. John Daly, Manager-Director Genesee County Road Commission. Miller Road Program Lansing Highway – Ballenger Highway. Linden – I75. Linden – I75. Linden to I-75 I-75 to Ballenger Lansing Highway to Van Vleet - PowerPoint PPT Presentation
Citation preview
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Miller Road Project Miller Road Project Linden Rd to I-75Linden Rd to I-75
INTRODUCTIONINTRODUCTIONJohn Daly, Manager-Director John Daly, Manager-Director Genesee County Road CommissionGenesee County Road Commission
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Miller Road Miller Road ProgramProgramLansing Highway – Ballenger HighwayLansing Highway – Ballenger Highway
Linden to I-75Linden to I-75 I-75 to BallengerI-75 to Ballenger Lansing Highway to Van VleetLansing Highway to Van Vleet Computer sequencing of signals Computer sequencing of signals
Linden - BallengerLinden - Ballenger
Linden – I75Linden – I75Linden – I75Linden – I75
01/24/07
Year of Year of ImprovementImprovement Type of ImprovementType of Improvement
19261926 Hard Surface ConcreteHard Surface Concrete
19521952 Widen to 4 LanesWiden to 4 Lanes
19721972 Asphalt ResurfAsphalt Resurf
19741974 Asphalt Widening - 6 LanesAsphalt Widening - 6 Lanes
19811981 Asphalt WideningAsphalt Widening
19871987 Asphalt Widening - 72' - 83'Asphalt Widening - 72' - 83'
Year of Year of ImprovementImprovement
Type of Type of ImprovementImprovement
19261926 Hard Surface Hard Surface ConcreteConcrete
19521952 Widen to 4 LanesWiden to 4 Lanes
19721972 Asphalt ResurfAsphalt Resurf
19741974 Asphalt WideningAsphalt Widening
19891989 Asphalt ResurfAsphalt Resurf
06 PASER: 5 06 PASER: 506 Traffic 24471 06 Traffic 32344
Total project cost: $8,194,000
Linden – I75Linden – I75
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
FUNDING – Federal HPPFUNDING – Federal HPP Senator Debbie Stabenow and Senator Debbie Stabenow and
Representative Dale Kildee introduce Representative Dale Kildee introduce congressional earmark funding into congressional earmark funding into SAFETEA-LUSAFETEA-LU
Identified Miller Rd from Linden Rd to I-75 Identified Miller Rd from Linden Rd to I-75 under HPPunder HPP
$2.4 million and $2.5 million in the bill$2.4 million and $2.5 million in the bill
Appropriation estimate of $4,263,000Appropriation estimate of $4,263,000
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
FUNDING – Michigan Jobs TodayFUNDING – Michigan Jobs Today
Governor Jennifer Granholm Governor Jennifer Granholm announced Michigan Jobs Todayannounced Michigan Jobs Today
Michigan Jobs Today funds cover Michigan Jobs Today funds cover required Local Agency (GCRC) matchrequired Local Agency (GCRC) match
Allows immediate project initiationAllows immediate project initiation
Miller Road approved for $1,065,750Miller Road approved for $1,065,750
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Extra funding required Extra funding required STP/GCRCSTP/GCRC
Federal Surface Transportation Federal Surface Transportation Program (STP) being applied forProgram (STP) being applied for
Needed funds: $2,375,250Needed funds: $2,375,250– GCRC $475,050 GCRC $475,050 – STP $1,900,200STP $1,900,200
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
FUNDING – Flint Township CBDAFUNDING – Flint Township CBDA
Flint Township Central Business Flint Township Central Business Development Authority committed Development Authority committed $490,000$490,000
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Miller Road Funding Package SummaryMiller Road Funding Package Summary
HPPHPP, , $4,263,000$4,263,000
MDOT (JT),MDOT (JT), $$1,065,7501,065,750
CBDACBDA, , $490,000$490,000
GCRC/STP,GCRC/STP, $2,375,250$2,375,250
Total Project Cost:$ 8,194,000
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Design process approvedDesign process approved December, 2006 - MDOT approved using December, 2006 - MDOT approved using
HPP and Jobs Today fundsHPP and Jobs Today funds design projectdesign project perform feasibility studyperform feasibility study
Study will identify needs of the corridorStudy will identify needs of the corridor
Process will incorporate public inputProcess will incorporate public input
Choose best designChoose best design
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Purpose of this meetingPurpose of this meeting
Share informationShare information
Obtain your input , ideas and Obtain your input , ideas and concernsconcerns
Identify significant needs of the Identify significant needs of the corridorcorridor
Help determine best designHelp determine best design
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Critical DatesCritical Dates August 24, 2007 - Final plans August 24, 2007 - Final plans
submitted to MDOTsubmitted to MDOT
November 2, 2007 – Bid lettingNovember 2, 2007 – Bid letting
Early Spring, 2008 – Start Early Spring, 2008 – Start ConstructionConstruction
October, 2008 – Project completionOctober, 2008 – Project completion
January 24, 2007January 24, 2007 Miller Road, Linden to I-75Miller Road, Linden to I-75
Thank you for coming!Thank you for coming!
John Daly, Manager-DirectorJohn Daly, Manager-DirectorGenesee County Road CommissionGenesee County Road Commission
(810) 767- 4920(810) 767- [email protected]@gcrc.org