29
MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014 ROADS, STREETS, DRAINS & BRIDGES CDB L 49,438,000 11,910,749 37,527,251 GOB C 8,917,000 1,620,964 7,296,036 CDB G 498,000 429,581 68,419 GOB C 71,000 - 71,000 TOTAL $58,924,000 CABEI MOWT L 12,400,000 5,234,047 7,165,953 GOB C 2,400,000 385,574 2,014,426 TOTAL $14,800,000 KFAED MOWT L 9,600,001 9,221,830 378,171 OFID L 23,400,000 20,035,344 3,364,656 CABEI L 9,000,000 16,849,806 (7,849,806) GOB C 11,420,000 3,186,775 8,233,225 TOTAL $53,420,001 CDB MOWT L 17,600,000 10,863,273 6,736,727 GOB C 4,010,000 1,084,077 2,925,923 TOTAL $21,610,000 EXPENDITURE FOR QUARTER ENDING 30/6/2014 3 Completion of the Southern Highway (Dump to Jalacte) Upgrade of 20 miles of the Southern Highway from Dump (Ml. 14) to the Belize/Guatemala Border he project is progressing satisfactorily with only minor delays. Completion is estimated at 85% complete. Completion of the works is set for January/February 2015. Considerable progress is being made with the concrete bridges replacements.. 4 Natural Disaster Management - Bridge Rehabilitation, TS Arthur (Kendal & Mullins River Bridges) Reconstruction of the Kendal and Mullins River Bridges Procurement arrangement are in progress to replace the old Mullins River Bridge thru a turn key contract as approved by CDB Review of Belize's road safety management capacity and preparation of a short-term action plan for its improvement; and assessment of the main road network and development of a prioritised capital investment programme of road safety improvements. Completed; the balance of the grant has been cancelled. 2 Corozal Border Crossing Reconstruction Project Improvement and rehabilitation of infrastructure at the Corozal Border Construction works underway with 50% complete BALANCE PROJECT UPDATE INFRASTRUCTURE 1 San Ignacio/ Santa Elena Bypass Project Construction of a bypass road and new all- weather bridge across the Macal River to increase the efficiency of road transportation in and through San Ignacio and Santa Elena. The project also includes activities to determine the extent of vehicle overloading and the accompanying economic and financial impacts. MOWT Lot 1 - Loma Luz Boulevard from Western Highway: new bridge approach is 100% complete. Lot 4 - Joseph Andrews Drive, including Benque Road: works are underway with 85% complete, BEL power poles keeping back the construction of the center island. Lot 3 - Branch Mouth Road to Joseph Andrews Drive: Contract awarded. Works underway - 50% complete. The Consultants supervising the road works is Beca International Consultants Ltd. Road Safety Assessment and Management Capacity Review TOTAL EXPENDITURE TO 30/6/2014 PROJECT DESCRIPTION FUNDING AGENCY EXECUTING AGENCY L/G COST (BZD)

MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

ROADS, STREETS, DRAINS & BRIDGESCDB L 49,438,000 11,910,749 37,527,251

GOB C 8,917,000 1,620,964 7,296,036

CDB G 498,000 429,581 68,419

GOB C 71,000 - 71,000

TOTAL $58,924,000

CABEI MOWT L 12,400,000 5,234,047 7,165,953

GOB C 2,400,000 385,574 2,014,426

TOTAL $14,800,000

KFAED MOWT L 9,600,001 9,221,830 378,171

OFID L 23,400,000 20,035,344 3,364,656

CABEI L 9,000,000 16,849,806 (7,849,806)

GOB C 11,420,000 3,186,775 8,233,225

TOTAL $53,420,001CDB MOWT L 17,600,000 10,863,273 6,736,727

GOB C 4,010,000 1,084,077 2,925,923

TOTAL $21,610,000

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

3 Completion of the Southern Highway (Dump to Jalacte)

Upgrade of 20 miles of the Southern Highway from Dump (Ml. 14) to the Belize/Guatemala Border

he project is progressing satisfactorily with only minor delays. Completion is estimated at 85% complete. Completion of the works is set for January/February 2015. Considerable progress is being made with the concrete bridges replacements..

4 Natural Disaster Management - Bridge Rehabilitation, TS Arthur (Kendal & Mullins River Bridges)

Reconstruction of the Kendal and Mullins River Bridges

Procurement arrangement are in progress to replace the old Mullins River Bridge thru a turn key contract as approved by CDB

Review of Belize's road safety management capacity and preparation of a short-term action plan for its improvement; and assessment of the main road network and development of a prioritised capital investment programme of road safety improvements.

Completed; the balance of the grant has been cancelled.

2 Corozal Border Crossing Reconstruction Project

Improvement and rehabilitation of infrastructure at the Corozal Border

Construction works underway with 50% complete

BALANCE PROJECT UPDATE

INFRASTRUCTURE

1 San Ignacio/ Santa Elena Bypass Project Construction of a bypass road and new all-weather bridge across the Macal River to increase the efficiency of road transportation in and through San Ignacio and Santa Elena. The project also includes activities to determine the extent of vehicle overloading and the accompanying economic and financial impacts.

MOWT Lot 1 - Loma Luz Boulevard from Western Highway: new bridge approach is 100% complete. Lot 4 - Joseph Andrews Drive, including Benque Road: works are underway with 85% complete, BEL power poles keeping back the construction of the center island. Lot 3 - Branch Mouth Road to Joseph Andrews Drive: Contract awarded. Works underway - 50% complete. The Consultants supervising the road works is Beca International Consultants Ltd.

Road Safety Assessment and Management Capacity Review

TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

Page 2: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

IADB MOWT L 20,000,000 3,250,027 16,749,973

GOB C 1,500,000 325,340 1,174,660

TOTAL $21,500,000

IADB MOWT G 900,000 425,240 474,760

GOB C 230,000 - 230,000

TOTAL $1,130,000

CDB MOWT L 700,000 700,000 -

GOB C 176,000 538,399 (362,399)

TOTAL $876,000OFID L 14,140,000 1,113,434 13,026,566

GOB C 9,040,328 711,868 8,328,460

OFID MHDST L 7,860,000 - 7,860,000

GOB C 5,006,579 3,416,330 1,590,249

TOTAL $36,046,907WB SIF L 30,000,000 10,971,881 19,028,119

GOB/LGA C 1,460,000 410,171 1,049,829

TOTAL $31,460,000

The Project has come to a conclusion. The last phase involved construction and repairs to about six homes.

9 Belize Municipal Development Project Improved access to basic municipal infrastructure and enhanced municipal management in selected town and city councils.

Progress and expenditure updates pending.

7 Feasibility Study & Detailed Designs - Phillip Goldson Highway, (formerly Northern Highway) Belize

Feasibility study and detailed designs for upgrading the Phillip Goldson Highway between the Airport Junction and Haulover Bridge.

The Consultant has completed the Detailed Design and the project has been approved by the Funding Agency (CDB). Procurement of Contractors for the Civil Works of Sections "A" and "B" has commenced.

8 Belize City Southside Poverty Alleviation (Phase 2)

Infrastructural, social and economic improvements in Southside Belize City. MOWT is responsible for drainage works, street and drainage improvement.

MOWT The Ministry of Works & Transport is only responsible for the component Streets Improvement & Drainage Works. Presently one (1) contract is under rehabilitation: Lot 2 - Central American Boulevard Rehabilitation Works. In progress - 95% complete.

MHDST is responsible for the social components: Land Reclamation; Improvement of Housing Units; Education, Training and Social Development; and Institutional Support, Audit and Supervision

5 Flood Mitigation Project Rehabilitation of drains and streets on Belize City's north side

Civil Works for Parks and Juliet Soberanis has been completed. Civil Works for Upgrading of Loop Road signed with Teichroeb & Sons Limited is on-going. NOB for Negoatiations for Maheia's Canal, Bill Lindo Canal, and Link Road has been requested from the Bank. Contract Negotiations for Douglas Jones Canal and Northside Canal is currently underway. Contracts with Utility Companies(BTL, BEL, BWSL) for the relocation of Public Utilities have been signed. Payment to landowners for Friendly Acquisition has been completed and funds to pay landowners under Compulsory Acquisition has been transferred to an Escrow Account at the Central Bank of Belize. Procurement process for Studies on Impact of Dredging the Mouth of Belize River is ongoing.

6 Support to Sustainable Urban Infrastructure Systems in Belize City

Development of an operational manual for the Flood Mitigation Project, and engineering designs and socio-environmental management plans for civil works projects to be financed by the loan programme.

GIS study is still under negotiations with the succesful bidder. This study will feed Risk Assessment & Maintenance Management System.

Page 3: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

EU/AMS MOWT G 8,642,098 6,985,822 1,656,276

TOTAL $8,642,098EU/AMS MOWT G 12,620,294 4,997,940 7,622,353

TOTAL $12,620,294

EU/AMS MOWT G 4,105,871 3,276,838 829,033

TOTAL $4,105,781

EU/AMS MOWT G 7,294,658 740,557 6,554,101

TOTAL $7,294,658EU/AMS MOWT G 8,217,260 834,221 7,383,039

TOTAL $8,217,260EU/AMS MOWT (AMS

PEU)G 2,000,000 1,977,134 22,866

TOTAL $2,000,000

15 Long Term Supervision of AMS Road Works Assistance in the long term supervision and administration of works undertaken by various contractors for the implementation of EU infrastructure programmes in general, and AMS- Phases II and III.

Progress update pending.

13 Sugar Belt Road Rehabilitation Project (Ph. III: Lot A: San Lazaro - August Pine Ridge Village Phase 2 of Blue Creek Road)

Upgrade of 6.56 miles of road to chip seal surface dress.

Survey setting out and site clearance completed; and earthworks begun. Works progressing at a reasonable rate. Project is delayed by 1 month (actual work vs. work plan) due to weather conditions. Project completion still expected within the 1 year implementation period (by 23/6/2014).

14 Sugar Belt Road Rehabilitation Project (Ph. III, Lot C: San Narciso - San Victor Village and Old Northern Highway - BSI Junction)

Upgrade of 7.84 miles of road to chip seal surface dress.

Survey setting out completed and earthworks about to start. Work progressing at a reasonable rate. MOWT is working with the San Jose Palmar village council to settle a misunderstanding over a small plot of land. Work is delayed by 1 month (actual work vs. work plan) due to weather conditions. Completion still expected within the 1 year implementation period (by 23/6/2014).

11 Sugar Belt Road Rehabilitation Project (Ph. II, Lot B: Orange Walk Town - San Estevan - Progresso)

Upgrade of 15.94 miles of road to chip seal surface dress.

Works are 5% complete: The contractor requested a second pre-finance which was granted on 2/9/13. The Contractor is updating the work-plan and other relevant documents for approval by the supervisor before starting the works on 15/10/13. The project should end by 31/12/2014.

12 Sugar Belt Road Rehabilitation Project (Ph. II, Lot C: Xaibe - Patchakan, Xaibe - San Roque, Calcutta - Xaibe)

Upgrade of 5.46 miles of road to chip seal surface dress.

Works are 95% complete. All paving completed; remedial works on line markings, placement of road reflectors, and road signs are outstanding. Work delayed due to Contractor's cash flow problems. Provisional acceptance expected by 15/11/2013.

10 Sugar Belt Road Rehabilitation Project (Ph. II, Lot A: Orange Walk Town - Blue Creek; Ph. 1 Orange Walk Town - San Lazaro)

Upgrade of 8.5 miles of road pavement to chip seal surface dress.

Works are 70% complete. Contractor requested second pre-finance which was granted 2/9/13. The Contractor is updating the workplan and other relevant documents for approval by the supervisor before starting the works on 15/10/13. New estimated completion date 28/2/2014.

Page 4: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

EU/AMS MOWT (AMS PEU)

G 3,145,888 907,490 2,238,398

TOTAL $3,145,888

CDB L 14,496,000 491,517 1,497,129 12,998,871

GOB C 3,191,000 88,480 329,668 2,861,332

TOTAL $17,687,000

CDB/SIF II SIF L 977,218 177,196 800,022

TOTAL EU/BRDP II MOWT (AMS/PEU) G 5,700,000 - 5,700,000

TOTAL $5,700,000

20 Hopkins Road Upgrade Upgrade of 4.5 mls of road from the Southern Highway to Hopkins Village to chip seal surface dress.

Progress and expenditure updates pending.

18 Belize Road Safety Project Infrastructural improvements, education and awareness campaigns, enhancement of road accident emergency services, road safety management capacity building and enforcement activities focused along the George Price Highway from Belize City to Belmopan and thoroughfares including the Ring Road in Belmopan, targeting a reduction in deaths and serious injuries associated with road traffic accidents.

MFED Component 1:Lot1 is at 30% completion due to contractor having to redo work so as in improve on quality. Lot 2 is at 3% completion as there has been delay in obtaining shipment. Lots 3 is at 75% completion - additional work is dependent on progress of Lot 1. Lot 4 is at 10% due to the delay in finalizing transfer of information to the Design and Certification Consultant.Lot 5 will be done after the completion of all four lots. Component 2: 40% completion of the public education and awareness which is inclusive of establishing a baseline and post-project knowledge. The curriculum development and teacher training is at 30% completion - TRL from the UK was contracted to assist the Ministry of Education. Component 3: Apart from the highway patrols purchased and being in-use, other necessary equipment is being acquired. Component 4: In the process of ordering of two fully-equipped Type III Ambulances. Component 5: Road Safety training adapted to Belize to support the improvement of GOBZ’s capacity to manage road safety is underway.

19 Buttonwood Bay Drainage Construction Construction of some 5,700 linear feet of covered ferro-concrete lined drains; replacement of driveways and walkways; installation of new culverts and wing walls; relocation of water mains and service entrances; and installation of new service connections on Park Avenue, Pike Crescent East and West, E Street and Buttonwood Bay Boulevard in the Buttonwood Bay Area, Belize City.

Progress and expenditure updates pending.

16 AMS 2009 Infrastructure Project Supervision (Programme Estimate No 1)

Assistance in the provision of long term supervision and administration of works undertaken by various contractors for the implementation of EU infrastructure programmes in general, and AMS Phase II and III.

The Supervision team commenced operation on 29/7/2013. The position of the team leader was re-advertised (Jamaica, Trinidad, Guyana, Barbados, St. Lucia) with 11/10/2013 as the deadline for submission of CVs. No further expenditure to date.

Page 5: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

BUILDINGS & FACILITIES

GOV MOEYS G 2,000,000 2,000,000 -

ROC L 10,000,000 2,308,444 7,691,556

GOB C 18,000,000 17,105,712 894,288

U 6,000,000 - 6,000,000

TOTAL $36,000,000GOB MOWT C2 510,278 - 510,278

TOTAL $510,278

GOB MHD C2 1,274,058 88,427 1,185,631

TOTAL $1,274,058CDB/BNTF

VISIF G 290,000 272,874 17,126

TOTAL $290,000CDB/SIF II L 888,286 888,286 -

CDI G 47,000 - 47,000

TOTAL $888,286

CDB/SIF II SIF L 324,835 264,826 60,009

TOTAL $324,835

EU/BSP MOWT G 568,983 458,965 110,019

TOTAL $568,983CDB/SIF II SIF L 355,681 349,616 6,065

TOTAL $355,681

28 San Jose Multi-purpose Center Construction of a one-storey ferro-concrete building that will include training rooms, office spaces for the Water Board and Village Council, a space for workshops, and a sanitary block. A fully-equipped computer lab will also be provided to the San Jose Government School to facilitate training for 15 persons.

Progress and expenditure updates pending.

26 Santa Elena Library Rehabilitation Upgrade of the Santa Elena Library building in the Cayo District.

Progress and expenditure updates pending.

27 Independence Bus Terminal Construction of a Bus Terminal in Independence Village

Expenditure update pending.

24 Mental Health Facility Construction of a mental health day care and resource facility in Belize City which will offer a daily meal, medical referral, recreation, and training for income generation to persons with mental disorders.

Progress and expenditure updates pending.

25 Golden Haven Home of the Elderly Completion Substitution Phase 2

Completion of a reinforced concrete single-storey structure that will serve as the new home for residents of the Golden Haven Home for the Elderly in the Belize District (Hattieville)

SIF Progress and expenditure updates pending.

22 Capital Improvements to Building (Post Office)

Renovation of the Administration Building in Punta Gorda Town which houses the Punta Gorda Post Office and the Magistrate's Court.

Progress and expenditure updates pending.

23 Conscious Youth Development Programme (CYDP) Building Construction

Clearing of property on Mussell St. in Belize City and subsequent construction of a building to house the CYDP.

Works have stalled due to lack of funds.

21 Marion Jones Stadium Upgrade of the Marion Jones Sports Complex Progress and expenditure updates pending.

Page 6: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

CDB/SIF II SIF L 282,280 276,996 5,284

TOTAL $282,280

CDB/SIF II SIF L 287,181 273,366 13,815

TOTAL $287,181CDB/SIF II SIF L 737,683 387,566 350,117

TOTAL $887,400

CDB/SIF II SIF L 831,762 533,174 298,588

TOTAL $831,762

USG USG G 3,000,000 3,000,000 -

TOTAL $3,000,000UK MNS G 99,015 97,280 1,735

TOTAL $99,015

GOB/MNS MNS C2 279,551 111,820 167,730

TOTAL $279,551

EU/BRDP II MOWT (AMS/PEU) G 2,000,000 - 2,000,000

TOTAL $2,000,000WATER & SANITATION

CDB L 3,288,000 2,702,791 585,209

BWSL C 930,000 729,161 200,839

TOTAL $4,218,000

37 Belmopan Market Upgrade of existing market facilities in Belmopan. Progress and expenditure updates pending.

38 Second Water Project (Revision in Scope) Upgrade of BWSL's network capacity and reduction of non-revenue water through the upgrade of transmission lines from the N. Highway junction to Burrell Boom, increasing capacity at the Double Run Treatment Plant, replacing storage tank at Wilson St., Belize City, and procuring and installing leak detection equipment.

BWSL All activities complete. Final payments made in July, 2013.

35 Refurbishment of the Training Facility, Queen Street Police Station.

Renovation of the 3rd Floor of the Patrol Branch Building, Queen St. Police Station

Progress and expenditure updates pending.

36 Crooked Tree Village Police Station Construction of a new Police Station in Crooked Tree Village.

Progress and expenditure updates pending.

33 Orange Walk Technical High School Substitution

Construction of a 6-classroom building. Progress and expenditure updates pending.

34 Coast Guard Forward Operating Base, Ambergris Caye

Construction of an operating base on Ambergris Caye for the Belize Coast Guard.

Project is substantially completed and will be inaugurated mid-October, 2013.

30 Sand Hill Multi-purpose Center Upgrade Rehabilitation of the existing community center and supply of library furniture and equipment.

Progress and expenditure updates pending.

31 All Saints Anglican Primary Infant School Substitution and Extension

Replacement of the 3-classroom, Infant I building with a 2-storey structure comprising 6 classrooms and sanitary units.

Progress and expenditure updates pending.

29 Guinea Grass Multi-purpose Center Construction of a one-storey ferro-concrete building that will house a sewing training room, office space for the Guinea Grass Village Council and Water Board, a library equipped with computers, and a male and female sanitary block. Furniture and equipment will also be provided to support the sewing classes that are part of the project.

Progress and expenditure updates pending.

Page 7: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

CDB L 6,959,000 2,914,753 4,044,247

GOB C 807,000 261,800 545,200

TOTAL $7,766,000

IADB L 10,000,000 53,293 9,946,707

GEF (CReW)

G 11,025,000 - 11,025,000

GOB C 600,000 - 600,000

TOTAL $21,625,000IADB BWSL G 1,000,000 7,370 992,630

TOTAL $1,000,000

CDI G 980,000 980,000 -

CDB/SIF II L 471,053 235,526 235,526

BWSL C 1,287,355 1,199,000 88,355

TOTAL $2,738,408

CDB L 1,440,000 - 1,440,000

GIZ G 251,752 - 251,752

BWSL C 254,100 100,143 153,957

TOTAL $1,945,852

CDB/SIF II SIF L 634,547 300,883 333,664

TOTAL $634,547

CDB/SIF II SIF L 233,810 132,898 100,912

TOTAL $233,810

47 Corozalito Rural Water Supply Construction of a reservoir and installation of main and secondary pipelines.

Progress and expenditure updates pending.

45 Detailed Designs - San Pedro, A.C. Water and Sewerage Expansion Project

Preparation of detailed designs, bidding documents, cost estimates and technical specifications for the proposed water and sewerage capital works on Ambergris Caye.

BWSL Contract signed 6/9/2013. Inception Mission scheduled for early October, 2013. The assignment should end in December, 2014.

46 Sarteneja RWS Rehabilitation Upgrade of the Reverse Osmosis Plant Progress and expenditure updates pending.

41 Detailed Design - Wastewater Collection & Treatment System in Placencia

Preparation of detailed designs, customer surveys and public awareness campaigns necessary for the implementation of the Placencia wastewater network and treatment facilities.

Progress and expenditure updates pending.

43 Cotton Tree/ St. Matthew's/ Frank's Eddy Rural Water System Upgrade

Extension of the Belmopan water main to the target villages and rehabilitation of the respective distribution networks to ensure adequate and reliable provision of potable water to residents.

BWSL Progress and expenditure updates pending.

39 Belize River Valley Water Supply Project Construction of a system to provide potable water to villagers of Bermudian Landing, Double Head Cabbage, Flowers' Bank, Isabella Bank, Lemonal, St. Paul's Bank, Rancho Dolores, Scotland Halfmoon, and Willows Bank in the Belize River Valley. Work will include pipeline installation and storage tank construction.

BWSL Land documents for 2 tank sites finalised; arrange-ments for Lemonal still in process. The supply of ductile iron pipes is delayed but expected by January 2014; pipeline installation contracts are ongoing; tenders for tanks and pumphouses to be submitted by 31/10/2013. The health subproject is delayed but activities should take place between January and June, 2014. Project end date has been extended to 30/4/2014.

40 Integrated Water and Sanitation Programme for the Placencia Peninsula

The programme will increase Placencia and Seine Bight residents' access to sanitation services through the development of a sewage collection and treatment system on the Placencia Peninsula.

BWSL Progress and expenditure updates pending.

Page 8: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

CDB/SIF II SIF L 623,888 205,577 418,311

TOTAL $623,888

CDB/SIF II SIF L 599,069 299,534 299,534

TOTAL $599,069

CDB/SIF II SIF L 297,537 - 297,537

TOTAL $297,537TRANSPORTATION & COMMUNICATION

BSSB MOWT L 9,500,000 - 9,500,000

TOTAL $9,500,000

ELECTRICITYEU G 4,110,894 2,414,168 1,696,726

GOB C 1,370,298 804,723 565,575

TOTAL $5,481,192

SUB-TOTAL INFRASTRUCTURE 414,597,091 166,167,680 248,429,412 ECONOMIC SERVICES

AGRICULTUREIADB L 7,400,000 553,010 6,846,990

GOB C 1,000,000 39,353 960,647

TOTAL $8,400,000

54 Agriculture Services Programme Strengthening of the core public agricultural services that provide access to applied production technology corresponding to market opportunities, while reducing the risks derived from threats to plant and animal health and food safety.

MNRA, BAHA Progress and expenditure updates pending.

52 Belize City Municipal Airstrip Upgrade and Rehabilitation Project

Expansion of the airport and construction of an office building for the Belize Airports Authority, new exit road, and a 3,300-ft airstrip. The project will also include lighting to accommodate night operations.

Work began in December, 2012 and should last 2 years. Progress and expenditure updates pending.

53 *Project to Provide Electrification to Marginalised and Depressed Rural and Peri-Urban communities in Belize from Renewable Energy Sources through Grid Extension

Provision of electricity from renewable energy sources to residents in rural and peri-urban areas through grid extension.

BEL Project end-date extended to April, 2014 to allow execution of works in 9 additional areas (Frank's Eddy, St. Matthews, 2 areas each in Camalote and Armenia Villages, Big Falls, Indianville and Rhaburn's Ridge in Belize); and the installation of 850 service entrances. Contracts for line extension in Corozal awarded in July, 2013 and construction ended in the following areas in the last quarter: Rockstone Pond (Belize); Cotton Tree and Valley of Peace (Cayo); Carmelita, San Lazaro and Guinea Grass (Orange Walk); and in Libertad and Paraiso (Corozal). Work continues in San Narciso, Patchakan, and Ontario Villages and should end by 31/10/2013.

Progress and expenditure updates pending.

51 Indian Church/San Carlos Water System Construction

Construction of an elevated ferro-concrete 20,000-gal. water tank and a pump house; and installation of submersible pump, chlorinator, generator, and a 28,000 ft pipeline.

Progress and expenditure updates pending.

49 Chan Pine Ridge Water and Sanitation Upgrade

Upgrade of water and sanitation facilities in Chan Pine Ridge.

48 Santa Familia Water System Extension Progress and expenditure updates pending.

Page 9: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

GOV/ALBA MNRA G 4,000,000 1,918,280 2,081,720

TOTAL $4,000,000

FAO MNRA G 597,196 593,670 3,526

TOTAL $597,196

FAO MNRA G 120,000 120,000

TOTAL $120,000

Taiwan ICDF MNRA, TTM G 2,496,292 2,336,666 159,626

TOTAL $2,496,292

58 Horticulture Project Promote agricultural technology, provide training in farm management, cultivation under covered structures, guava cultivation and urban gardening; organise small-holders and assist them in production management, develop agribusiness (pilot papaya export sub-project and vegetable production), install a Rapid Bioassay Pesticide Residue Detection Station, and instruct farmers in the use of pesticide application technologies; introduce a Small Farmholders' Financing Scheme for the pilot papaya export sub-project to expand the industry and earn foreign exchange.

Progress and expenditure updates are pending.

56 Strengthening Policies for the Production of Basic Grain Seeds to support Rural Agriculture for Food Security in ACC Member Countries (Regional Seed Project)

Training for farmers in post-harvest management of grain, the use of threshing and artificial drying equipment, seed selection and management, and business and organizational issues. Two portable dryers, a portable thresher, two moisture testers, and a portable automatic corn husker will be provided as part of the project.

Progress and expenditure updates pending.

57 Telefood Programme Grassroots-level/Community projects aiming to improve poor families' means and volume of production leading to income generation and better access to food. Belize's quota is $100,000 per year and individual projects do not exceed $20,000.00.

Progress and expenditure updates pending.

55 Food Security Programme - ALBA (Integrated Farming Systems)

Promotion of integrated farming systems in Central, Northern, and Southern Belize; purchase of machinery for GOB; establishment of irrigation infrastructure at Central Farm; expansion of seedling facilities, and upgrade of the Biscayne Agriculture Facility.

Progress and expenditure updates pending.

Page 10: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

Taiwan ICDF MNRA, TTM G 3,444,462 2,947,295 497,167

TOTAL $3,444,462

Taiwan ICDF MNRA, TTM G 1,353,902 1,279,414 74,488

TOTAL $1,353,902

Taiwan ICDF MNRA, TTM G 5,000,000 652,630 4,347,370

TOTAL $5,000,000

FAO MNRA, CGA/CREI G 106,000 - 106,000

TOTAL $106,000

FAO MNRA, CGA/CREI G 804,882 490,129 314,753

TOTAL $804,882

EU G 6,116,000 4,412,097 1,703,903

OIRSA C 400,000 - 400,000

BLPA C 2,226,000 - 2,226,000

GOB C 3,497,154 - 3,497,154

TOTAL $12,239,154

64 Belize National Sanitary Cattle Plan (Cattle Sweep) Project

Testing of all cattle in the country for Brucellosis, Tuberculosis; implementation of a surveillance plan for BSE ("Mad Cow" or "Foot and Mouth") Disease; and the development of a national livestock registry for the exportation of cattle to Mexico and other countries.

MNRA 3 Sweeps - Sweep 1 (86%)- 85,515 cattle tagged & tested and Sweep 2 (20%) – 19,484 cattle tagged and tested. Completed activities in the Corozal and Orange Walk; Belize District by 11 /10/13. Of BZ$1.3 M GOB contribution requested BZ$1M received. Of BZ$1.05M BLPA contribution requested; the project received BZ$559,000. AMS 2009 Financing Agreement extended to 11/10/16. Final Expenditure Verification (audit report) along with Interim Narrative & Financial Reports pending official submission to NAO for drawdown on 2nd tranche.

62 Support to Member Countries of OIRSA for the Control of Huanglongbing (citrus greening) in Citrus

To improve technical capacity of beneficiary countries to control HLB through field surveillance of disease, lab diagnostics and biological control pilot plants.

Progress and expenditure updates pending.

63 Assistance to manage Huanglongbing in Belize

Support to the enhancement of Belize’s capacity to reduce the impact of HLB on citrus farmers' livelihoods through the development and implementation of a holistic and cost effective area-wide strategy to fight the disease.

Project activities, with the exception of training for 6 persons in protocols for operation of the ACP parasitoid rearing facility and for release and evaluation of parasitoid effectiveness in the field due to the building of facilities, are complete. The project comes to an end October 2013.

60 Food Processing Project Introduction of various food processing technologies to improve capacity in Belize and improve opportunities for stakeholders in the sub-sector.

Progress and expenditure update pending

61 Aquaculture Project Assistance to the development of small-scale tilapia farming operations in Belize through the production of high-quality fingerlings, promotion of the use of modern tilapia culture technology among small farmers, and the drafting of a National Tilapia Aquaculture Development Plan which will focus on the small-scale sub-sector.

Construction of the Tilapia Hatchery Center (Agriculture Department, Central Farm) began and is 40% complete. Assistance to fish farmer groups to operate as a Tilapia Farmers' Marketing Group, and the expansion of the domestic market and consumption of tilapia in Belize are pending.

59 Rice Seed Production Project To increase acreage of breeder and stock rice planting sites at Central Farm, produce 20,000 lbs of stock seed, train technicians in rice production, produce 160,000 lbs of commercial rice seed at Poppy Show Farm in Southern Belize, increase cultivated area by an additional 1,000 acres and develop 100 acres of paddy fields in Blue Creek.

Progress and expenditure updates are pending.

Page 11: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

EU/AMS SIRDI, MNRA G 6,245,875 - 6,245,875

IICA G 55,723 55,723

SIRDI C 1,337,013 1,337,013

TOTAL $7,638,611

EU/AMS DFC G 16,250,000 6,498,571 9,751,429

TOTAL $16,250,000

66 Sugar Cane Replanting Scheme Establishment of a credit revolving fund in support of sugar cane replanting.

Credit Component: Cumulative disbursement was $3.8mn, this amount inlcudes a first credit disbursement to La Inmaculada Credit Union. 66 farmers got their ratoon maintenance valued at $500 per acre. Given the slow disbursement of funds for replanting, the GOB is looking at possible ways to overcoming farmers'committment with commercial banks as the main reason why farmers withdraw their loan applications under the Sugar Replanting Scheme. Promotional Component: A promotion assignment which produced items including advertisements and videos with testimonials proved to be very successful and the PMU is looking into another promotion assignment. On July 28, 2014 the bank gave its no objection to hire a local consultant and to submit the TOR and budget for its no objection. M&E Component: Some challenges inclusive of, the need to lend 73% of the projected funds over the two remaining planting seasons still remain. Expenditure figure to be verified

65 Institutional Strengthening of Sugar Industry Research Development Institute (SIRDI)

Strengthening of SIRDI's development strategy, coordination and monitoring capability in the Sugar Cane Industry, and its ability to provide cost-effective support services; and improving the dissemination and adoption of applied sugar cane production research technologies to producers, manufacturers, and associations.

Weather stations procured in 09/2013. SIRDI’s staff participated in study tour and conferences in Costa Rica, Nicaragua and Colombia; and with MNRA in Belmopan/Central Farm. Technical handouts on soil sampling and land preparation; ratoon maintenance; the methodology to evaluate harvesting losses in sugar cane; trial on harvesting losses for San Lazaro Branch; and cutting, loading and harvesting losses in sugar cane were distributed to farmers. Land preparation service for secondary cane seed nurseries (320 ac.) is ongoing and planting should take place between October and November, 2013. Research Protocols were developed for: herbicide applications, integrated pest management, fertilizer application and trash management; and 15 technicians were trained in Research Methodologies.

Page 12: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

IADB MNRA G 113,863 4,000 109,863

G

TOTAL $113,863.36

CAC/ECADERT

MNRA G 400,000 92,323 307,677

GOB G 270,200 10,000 260,200

TOTAL $670,200

JSDF BEST G 5,600,000 134,953 5,465,047

TOTAL $5,600,000

TOURISMIADB L 26,644,000 24,063,205 2,580,795

GOB C 2,720,000 2,284,704 435,296

TOTAL $29,364,000

70 Sustainable Tourism Project Enhancement of the tourism experience and resource sustainability at consolidated destinations subject to pressure (including Ambergris Caye, Belize City, Placencia and San Ignacio); diversification of the overnight tourism product in emerging destinations; and strengthening tourism institutions' capacity for policy, management, and destination planning

MOTC, BTB Component 1: 95% complete - work on the San Pedro Sunset Boardwalk and water taxi terminal, and archaeological sites Cahal Pech and Xunantunich are nearing completion. Work is underway at Bacalar Chico, following slight revisions to site plans and the decision to retain the existing structure. This is five months away from completion and management support will take four months until completion. Component 2: 99% complete. Public consultations for the Land-Use Development Plan for Ambergris Caye are planned for October, 2013. The Independent Final Evaluation of STP has been postponed and the San Pedro Start-Up Coordinator is to be on board in October.

68 Upgrading and Expanding Tilapia Farming for Rural Farmers

To increase the income-earning capacity of farmers through innovative integration systems and thereby expanding the economic opportunities in rural communities while contributing to the reduction of poverty in these areas.

Progress and expenditure updates pending.

70 Promoting Sustainable Natural Resources-Based Livelihoods in Belize

Support for social mobilization, facilitation and community co-management of natural resources; development of community-based sustainable livelihoods of non-timber forest products in and around selected protected areas; support for innovative models of green livelihoods of fishing communities through mariculture development; and community led monitoring and knowledge dissemination.

Project staff - Procurement Officer, Technical Officer and Accounts Officer - have been hired. All initial Consultations and Community Mobilization Workshops were completed for the 25 targeted communities and 4 project applications were submitted by community groups to the Project Implementation Unit for review. Terms of Reference for a Technical Committee for approving projects was developed. The first Committee meeting is scheduled for Q4, 2013.

67 Technological Innovation Strategy to improve Productivity and Competitiveness of Product Chains in Central America and the Dominican Republic

To support the development of value chain agricultural food products through innovative technologies, to strengthen local systems that produce/multiply seeds, and to prepare and disseminate information and strengthen organizations that transfer technology and provide technical assistance.

Activities with respect to the confirmation and activation of a Local Consortium, and the formulation of a baseline study of the corn value chain are almost complete. Implementation of other activities such as the design and preparation of technical manuals have not started.

Page 13: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

EU G 2,750,000 1,590,031 1,159,969

BTB C 1,643,388 - 1,643,388

NICH C 1,643,388 - 1,643,388

TOTAL $3,078,776

BUSINESS & MARKET DEVELOPMENT CDB DFC L 20,000,000 15,145,589 4,854,411

TOTAL $20,000,000

CARTFund G 879,292 291,100 588,192

GOB C 630,700 12,646 618,054

TOTAL $1,509,992

CARTFund G 555,812 151,055 404,757

GOB C 223,630 27,891 195,739

TOTAL $779,442EU DFT G 368,740 229,421 139,319

TOTAL $368,740

74 Strengthening and Capacity Building of the Newly Established Belize Coalition of Service Providers

The objective of the Project is to build the capacity of the newly-established Belize Coalition of Service Providers to serve as an umbrella organization for the development of the services sector.

DFT The BCSP conducted a re-launch activity during Services Week in June, and in which findings of the completed baseline survey exercise were presented. The Export Strategy and Sector Roadmaps Consultancy has commenced and the Consultant's work plan was also presented to stake-holders during Services Week.

75 Training in negotiation techniques for proposed Belize/ Mexico Partial Scope Agreement (PSA).

Training for the national negotiating team and officers from the Ministry of Trade to assist them in negotiating the Partial Scope Agreement (PSA) with Mexico later this year.

Progress and expenditure updates pending.

72 DFC Line of Credit Funds provided to DFC for on lending in priority areas - student loans, SMEs, low-income housing, agriculture and industrial credit, and microfinance.

Disbursements on approved loans continue. Some 1.2 mn remains for on-lending under the residential and financial institution sectors.

73 Capacity Enhancement - Promotion of the CSME and EPA

Provision of technical, institutional and operational support towards enhancing the capacity of the Directorate of Foreign Trade to effectively coordinate and facilitate the implementation of the CARICOM Single Market Economy (CSME) and the Economic Partnership Agreement (EPA).

DFT Efforts continue to resume and finalise outstanding work on the legal component. The Draft National EPA Action Plan has been submitted and is to be validated at a workshop scheduled in the next quarter. Discussions ongoing with the Press Office and other CARTFund beneficiaries (BCSP, NES Secretariat) towards developing an effective, comprehensive communication strategy that would satisfy the requirements of all three interventions.

71 Making Tourism Benefit Communities Adjacent to Archaeological Sites (BTB)

Improving access to product standards and safety at selected tourism sites.

BTB Project is in the first 6 months of implementation. Procurement processes for the design and construction of all 6 major sites to commence shortly.

Page 14: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

IFAD L 6,000,200 2,605,523 3,394,677

CABEI L 3,811,600 472,652 3,338,948

GOB C 1,463,600 702,118 761,482

CU C 807,800 52,600 755,200

TOTAL $12,083,200

EU/AMS G 1,268,487 780,926 487,561

LICU C 424,100 424,100

TOTAL $1,692,287

EU/BRDP II G 907,500 949,692 (42,192)

duPlooy's C 125,000 25,000 100,000

BBG C 102,223 20,445 81,778

TOTAL $1,134,723EU/BRDP II G 1,000,000 885,715 114,285

TCGA/others

C 187,500 50,000 137,500

TOTAL $1,250,000

EU/BRDP II G 1,750,000 888,104 861,896

YWCA C 437,011 87,402 349,609

TOTAL $2,187,011

EU/BRDP II BBS G 1,150,000 844,155 305,845

TOTAL $1,150,000

80 Construction of the National Enterprise Development Center

The YWCA will use the facility to offer capacity building opportunities to women and youths in the Belize, Cayo and Stann Creek districts.

YWCA Project on-going. Expenditure and progress updates pending.

81 Metrology Laboratory Supplies Supply, delivery, unloading, installation and commissioning of metrology equipment for use by the Bureau of Standards.

Progress and expenditure updates pending.

78 Belize Botanic Gardens (BBG): More efficient market driven productive & competitive SMEs

Improving the quality of life of rural households in the Cayo district by developing capacity to find or create employment in gardening and other horticultural areas

BBG Project staff engaged and implementation is on-going. Expenditure update pending.

79 Mayan House of Cacao & Chocolate Museum: More efficient market driven productive & competitive SMEs

Establishment of a Mayan House of Cacao & Chocolate Museum in Toledo.

TCGA Training of farmers and youth is on-going. Expenditure update pending.

76 Belize Rural Finance Programme Support and strengthening of financial services that target poor farmers and small rural communities

MFED, BCUL Institutional Capacity Building: 72.1% complete; The procurement process for the establishment of an M&E Management Information System at the BCUL is nearing completion. Rural Credit Fund: As at 30/9/2013, activities related to this component have not been implemented. Shares and Savings: 15.5% complete. 3,587 persons at 30/9/13 (1,461 males; 2,126 females; 843 youth; and 1,864 very poor). New eligible beneficiaries invested $193,425 at CUs as part of the Shares Incentives Scheme, and $93,425 in incentives has been paid on behalf of eligible members. PMU: Activities 38.4% complete: Financials completed and submitted to IFAD & CABEI by the stipulated deadline, 30/9/2013.

77 Small Scale Enterprise Development in Agriculture and Tourism for the Orange Walk and Corozal Rural Communities (SSEDAT II)

Provision of small grants to beneficiaries for the purpose of enterprise development.

LICU A contract has been signed for the Onion Sector Study; results of the market expansion survey have been delivered; and 483 persons have been assisted through the financial outreach program. the first tour guide certification training was completed and the 6th Quarterly Grantees Meeting was held in Orange Walk Town.

Page 15: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

ENVIRONMENT AND NATURAL RESOURCE MANAGEMENT

IADB L 5,000,000 4,351,525 648,475

GOB C 490,630 788,000 (297,370)

TOTAL $5,490,630

IADB L 22,300,000 14,269,718 8,030,282

OFID L 6,520,000 4,300,650 2,219,350

GOB C 758,000 254,962 503,038

TOTAL $29,578,000

GEF G 1,950,000

PACT G 1,170,000

OAK G 400,000

APAMO G 224,942

UNDP G 100,000

GOB C 265,000 334,298 (69,298)

TOTAL $4,109,942

OAK G 400,000 256,912 143,088

GOB C 639,208 931,713 (292,505)

TOTAL $1,039,208

EU G 7,540,000 2,633,688 4,906,312

GOB C 703,940 - 703,940

TOTAL $8,243,940

86 Enhancing Belize's Resilience to Adapt to the Effects of Climate Change

The project will enhance Belize's resilience to effects of climate change through interventions in the water sector and establishment of governance structures for climate change.

MNRA, MFED Progress and expenditure updates are pending.

2,868,638 976,304 Execution of the legal and institutional reforms component resumed and is moving according to the revised work plan. Under Component 2, activities 2.1 (selected instruments enable protected areas investment) and 2.2 (selected mechanisms increase protected areas revenues) have been removed from the work plan and replaced with the implementation of the Sustainable Financing Strategy.

85 Building Support for an effective National Protected Areas System

Co-financing support from PACT for additional activities under the Strengthening National Capacities Project. Support for marine protected network.

MFFSD Component 2: Improve the Sustainability of the National Protected Areas System (NPAS) through a comprehensive NPAS Act and the review and reform of existing protected area legislation, which cofinances the SNC PAS project, is behind schedule. Activities to strengthen marine protected areas management entities (Component 3) should begin in 2014.

84 Strengthening National Capacities for the Operationalisation, Consolidation, and Sustainability of Belize’s Protected Areas System

Development of effective legal, financial, and institutional capacities to ensure sustainability of the existing NPAS

UNDP, MFFSD

82 Land Management Programme III The programme will improve the quality of land management services country wide.

MNRA The final audit for the project is pending at 95% completion. The project should close thereafter, in November 2013.

83 Solid Waste Management Project Improve solid waste management practices along the Western Corridor; reduce environmental pollution and enhance the image of Belize in the eco-tourism market; strengthen overall Central Government capacity to improve solid waste management countrywide through the institutional strengthening of the SWMA.

SWMA The closure of the Belize City dumpsite is 75% complete; and the construction of a transfer station at the same site is 90% complete. The new regional waste disposal facility has been opened but minor works are outstanding on the landfill. The construction of transfer stations and the closure of open dump sites in San Pedro and Caye Caulker have been delayed due to slow application of resources by the contractor. Work in San Ignacio is 90% complete. The Project Management Unit is awaiting quotations and work plans for the construction of additional transfer stations (Belmopan and Burrell Boom).

Page 16: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

UNDP G 78,000

GEF G 960,000

GOB C 408,000 103,936 304,065

TOTAL $1,446,000

EnvDF MFFSD G 5,000,000 240,000 4,760,000

TOTAL $5,000,000

ACP Fish II MFFSD G 376,260 263,057 113,203

TOTAL $376,260

MARFUND MFFSD G 95,568 35,605 59,963

TOTAL $95,568

CaMPAM MFFSD G 100,000 100,000

TOTAL $100,000

IADB MFFSD G 1,400,000 800,000 600,000

TOTAL $1,400,000UNEP G 258,942 228,543 30,399

GOB C 110,000 - 110,000

TOTAL $368,942

UNEP/UNDP

MFFSD G 160,000 90,621 69,379

TOTAL $160,000

93 Belize SAICM Initiative/ Belize-UNEP Partnership on Development of a coherent legal and institutional framework for the Sound Management of Chemicals

Development of a national policy on the sound management of chemicals in Belize.

MFFSD This project should be completed by November 2013. All planned activities for July- September 2013 quarter have been successfully completed.

94 Hydrochloroflourocarbon Phase-out Management Plan (HPMP), Ozone Programme

This project is intended to phase-out HCFCs, ozone depleting substances.

Implementation has begun on the General Technicians' Training; Refrigeration and Air Conditioning Excellence Centre and Development of National Expertise; and High efficiency HCFC phase out synergy in the Tourism and Hotel Sectors components. The M&E component is on-going. The project has been granted a 1-year extension.

91 Educational Awareness within South Water Caye Marine Reserve

This project will build community awareness through school lectures and hands-on training on visits to the marine reserve.

Expenditure and progress updates pending.

92 Enhancing Management of the Bacalar Chico Marine Reserve

Construction of living quarters and visitor infrastructure; and the acquisition of equipment to support the management of the Bacalar Chico Marine Reserve.

Building of researchers' living quarters and visitor infrastructure, and acquisition of enforcement equipment marker buoys are 60%complete.

89 Review and Update of Fisheries Regulation Support for the review and update of outdated fisheries regulations in Belize.

The project is in its final stages.

90 Enforcement Enhancement within the South Water Caye Marine Reserve

Provision of equipment to the enforcement agency

Equipment (solar panels, moorings and shackles) procurement process is completed. The Project's end date is November 2013.

88 Managed Access and Catch Shares Pilot Project

Support to sustainable fisheries and the economic development of Belize's fishery sector

Personnel to socialise managed access have been engaged and are being trained. Available data is being collected and assessed for the implementation of a total allowance catch for the lobster and conch fishery- (40% complete). The implementation of managed access at Marine Protected Areas is 12% complete.

375,665 662,335 87 Enabling Activities for the Preparation of Belize's Third National Communication to the UNFCCC

This project will support Belize in preparing its Third National Communication to the Conference of the Parties to the United Nations Framework Convention on Climate Change (UNFCCC).

NCCO,MFFSD Progress and expenditure updates are pending.

Page 17: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

UNEP MFFSD G 163,400 109,530 53,870

TOTAL $153,400

GEF/UNDP G 235,000 89,767 145,233

GOB C 86,000 12,000 74,000

TOTAL $321,000

GEF/WB MFFSD G 240,000 239,244 756

GOB C 160,000 185,013 (25,013)

TOTAL $400,000

GEF G 1,986,400

DFC C 1,600,000

UNEP C 50,000

MESTPU C 270,000

CBA C 70,000

BTB C 40,000

TOTAL $4,016,400

4,014,035 The project started in August 2013. The only component of the project which has seen progress in implementation is the establishment of an Assessment and Monitoring System for Energy Efficiency and Renewable Energy Buildings by 25%.

97 Project Preparation Grant for the Management and Protection of Key Biodiversity Areas in Belize

Support for the development of the Management and Protection of Key Biodiversity Areas in Belize Project.

The project preparation was successfully completed during the third quarter of 2013.

98 Energy for Sustainable Development in Caribbean Buildings

The main objective of this project is sustainable energy use through energy efficiency and renewable energy intervention technologies within the project territories. The ESD-Caraibes activities – a mix of policy and demonstrations – are intended to reduce energy intensity from electricity use within the respective project countries by 20 % from the business as usual (BAU) scenario. It is intended that the project activities will serve as harbingers toward an “energy efficient economy” within the Caribbean and commercial uptake of successful models will be encouraged.

MESTPU 2,365

95 Institutional Strengthening Phase VI, Ozone Programme

Support for the HPMP through funding of staff, dissemination of information, and monitoring and reporting.

Data-gathering and reporting activities are complete. Public awareness, exchange of information, and monitoring and evaluation of progress of implementation of Ozone Depleting Substances phase-out activities are ongoing.

96 National Biodiversity Planning to support the Implementation of the Convention on Biological Diversity (CBD) 2011-2020 Strategic Plan

This project integrates Belize’s obligations under the CBD into its national development and sectoral planning frameworks through a renewed and participative ‘biodiversity planning’ and strategising process in a manner that is in line with the global guidance contained in the CBD’s Strategic Plan for 2011-2020.

MFFSD, Forestry The Project Execution Group was formed; the project was successfully launched; TOR for the Rapid Stock Taking and National Target setting exercise was developed and published; TOR for the preparation of the 5th National Report to the UNCBD was drafted and submitted to UNDP and the Project Director; and a vehicle was purchased for the project. Difficulties are being encountered in hiring project personnel.

Page 18: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

IADB MESTPU G 860,000 19,800 840,200

TOTAL $860,000

KOICA MESTPU G 800,000 267,486 532,514

TOTAL $800,000

SUB-TOTAL ECONOMIC SERVICES 210,297,823 108,175,101 102,122,722 EDUCATION

CDB L 4,000,000 100,969 3,899,031

GOB C 1,560,000 155,252 1,404,748

CDB G 180,000 - 180,000

TOTAL $5,740,000

100 Official Development Assistance Cooperation- Korea's Overseas Development Assistance

Overseas Development Assistance partnership between the governments of Belize and the Republic of Korea in which Korea has provided Belize with financial support in the form of a grant to be utilized by the Ministry of Energy, Science & Technology and Public Utilities in Institutional strengthening, IT Equipment upgrade, Public Relations campaign and the for the organisation of national Technology and Innovation Forums.

The project started in February 2013 and ends in July 2014. The project implementation is well on-track and ought to have a timely and successful finish.

98 Education Sector Reform Project Sector-wide reform activities aimed at enhancing learning outcomes at all levels. Activities include strengthening of the regulatory framework, development of a National Human Resource Strategy, sector Disaster Risk Management Plan, and the rationalisation and diversification of the Secondary Curriculum.

MOEYS (1) Strengthened Governance: M&E Consultancy awarded and will commence 1/11/2013; selection process ongoing for the Regulatory Framework Consultant. (2) Enhanced Quality and Relevance: Selection process ongoing for the Second Language Acquisition Strategy Consultant, and the ICT Strategy consultancy will be implemented through the Commonwealth of Learning. (3) Increased Access: Work continues on the development of the School Mapping Plan. (4) Project Management Services: Consultant provided support to PPU during a visit in July, and submitted the Final Draft of the Interim Report.Development of a Disaster Risk

Management Plan for the Education Sector

99 Assessment of the Potential for Distributed Generation using Renewable Energy and Energy Efficiency

To promote and support sustainable energy and energy conservation programmes in order to minimise the dependency on fossil fuels in Belize. The specific objectives are: (i) support the preparation of the Energy Efficiency Strategy of the National Energy Policy; (ii) provide technical assistance to the GOB to develop a baseline of consumption patterns and areas of opportunity for EE measures in, amongst others, public buildings, industry, the residential sector, and SMEs; (iii) explore alternatives for renewable energies in addition to what other donors are already exploring; and (iv) training and dissemination of findings.

Complete financing update is pending. The project started in July 2013. Components to support the preparation of the Energy Efficiency (EE) Strategy of the National Energy Policy and the development of baseline consumption patterns to identify EE opportunities are 65% and 75% complete, respectively.

Page 19: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

CDB/BNTF VI

SIF G 175,000 170,686 4,314

TOTAL $175,000

EU/BSP MOEYS G 1,249,350 1,306,062 (56,712)

TOTAL $1,249,350EU/BSP MOEYS G 1,241,988 1,111,894 130,094

TOTAL $1,241,988

EU/AMS MOEYS G 450,875 274,810 176,065

TOTAL $450,785

HEALTHCDB G 300,000 222,346 77,654

NAC C 70,000 56,700 13,300

TOTAL $370,000WB MOH G 5,992,288 150,189 5,842,099

TOTAL $5,992,288

103 Control & Prevention of HIV/ AIDS To strengthen the national response to controlling and preventing the spread of HIV/AIDS in Belize

NAC The Legal Consultant has been engaged but consultations are on hold. NAC reported no additional expenditure in the June quarter.

104 Improving Children’s Health and Nutrition in Local Mayan Communities in Toledo

The project will support innovative programs which directly respond to the needs of the poorest and most vulnerable groups in society; provide rapid, demonstrable, and sustainable benefits; and build capacity, participation and empowerment of civil society, local communities and NGOs.

The implementation of the baseline survey was completed and the report is pending. Selection processes ongoing for the Supply Chain Management consultant and the Engineer/ Environmental Specialist.

101 Primary School Teacher Training Project in the Banana Belt

Training for teachers with Associates Degrees in areas other than Education leading to a Certificate in Primary Education and eligibility for a full teachers' license.

This project is complete; final report pending.

102 Professional Development Programme for School Leaders

Certificate Training for Primary School Management Authorities and Principals in Northern Belize in School Leadership

Project on track. Open Day event planned for 16th August and Graduation Ceremonies scheduled for 8/9/2013.

99 Silk Grass Methodist Primary School Extension

Extension and rehabilitation of the school building Overall works began in February 2012 and ended in March 2013.

100 Secondary Education Teacher Training Project in Banana Belt

Training (Diploma in Education and Bachelors Degree) for secondary school teachers in English, Math, Science (Biology, Physics etc.), Spanish and General Sciences which qualifies them for a full teachers' license.

Request for final payment submitted March, 2013.

Page 20: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

IADB G 1,000,000 207,753 792,247

GOB C 1,000,000 330,029 669,971

TOTAL $2,000,000

MHI 2015 MOH G 1,400,000 - 1,400,000

TOTAL $1,400,000

Global Fund UNDP, NAC G 13,317,194 7,084,159 6,233,035

TOTAL $13,317,194

EU PAHO G 5,263,452 - 5,263,452

TOTAL $5,263,452

POVERTY AND SOCIAL PROTECTIONCDB G 560,000 353,050 206,950

GOB C 121,960 - 121,960

TOTAL $681,960

109 Preparation of the Youth & Community Transformation Project - Southside

Preparation of a comprehensive youth and community development initiative in Southside Belize City

MFED Consultants are finalizing the designs and tender documents for (i) Lake Independence Resource and Community Centre, (ii) fencing for the Samuel Haynes Institute of Excellence, and (iii) upgrading of the Wilton Cumberbatch Recreational Park.

107 Accelerating the Pace: Reaching Marginalized and Vulnerable Populations with Critical Services

The objective of this project is to improve the HIV National response in Belize by improving the health services available to persons living with and affected by HIV. It will also work towards the expansion of treatment and prevention of HIV and other STIs.

Agreement for Phase 2 activities has not yet been signed, but will be retroactive to January 2013. Proposal for the reprogramming of some funds under Ph. II was developed and submitted to the Fund for approval.

108 Strengthening of Critical Maternal and Neonatal Services in Belize

Improvement of the quality of health care services targeting the most vulnerable population, pregnant women and neonates, through improved access to services (including laboratory, blood bank, and medical equipment).

The project is for 30 months, beginning July, 2013 and ending December 2015. Year 1 activities include: extension of laboratories for the Corozal Community and Northern Regional Hospitals; construction of a new Vaccination Room (to WHO standards); procurement of lab equipment; and establishment of neonatal facilities for all hospitals and KHMH. The financing agreement was signed by the EU in June 2013. Recruitment of project personnel should begin within the next quarter.

105 Salud Mesoamerica Initiative - Belize This is part of the Mesoamerica Health 2015 Initiative which aims to improve the health of women and children under 5 years of age in the poorest populations of the Mesoamerica region. It comprises 3 individual operations, the first of which aims to reduce maternal, infant and child mortality in Corozal, Orange Walk, Toledo and Cayo through interventions that strengthen primary health care services.

MOH The project is 55% complete. Comp. 1- Quality Improvement of Maternal, Neonatal, Child and Reproductive Health Services: URC contracted - 1st learning session completed, Quality Innovation Fund (QIF) proposal designed and in operation, 2 rural health centres linked to BHIS. Comp. 2 -Strengthening Health Services: procurement of neonatal and tubal ligation equipment underway, family planning methods and medical equipment ordered; Community Health Workers' manuals and other medical & non medical items being procured. Comp. 3 - Admin and Auditing: services underway. Vehicle purchased for mobilization.

106 Molecular Epidemiology and Drug Resistance Surveillance of Human Immunodeficiency Virus in the Mesoamerican Region

Seeks to determine HIV subtypes in the Mesoamerican region and determine the sensitivity to the different antiretroviral currently available. Samples are sent to Instituto Nacional de Enfermedades Respiratorias de Mexico. (TC)

Samples from Corozal were sent to the Institute in June, 2013. The project should end in December 2013.

Page 21: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

IADB G 3,450,000 3,078,678 371,322

GOB C 163,784 271,222 (107,438)

TOTAL $3,613,784

CDB/BNTF VI

SIF G 50,000 26,530 23,470

TOTAL $50,000

CDB/BNTF VI

SIF G 50,000 13,498 36,502

TOTAL $50,000

SUB-TOTAL SOCIAL PROTECTION 41,595,891 14,913,827 26,682,064 PUBLIC ADMINISTRATION

GOVERNANCECDB L 5,032,884 4,991,014 41,870

GOB C 1,105,400 626,810 478,590

TOTAL $6,138,284

GOB MOWT C2 450,000 296,217 153,783

TOTAL $450,000

GOB AGM/MFA C 2,265,778 1,048,364 1,217,414

TOTAL $2,265,778

EU NAO G 2,500,000 1,982,164 517,836

TOTAL $2,500,000

115 CARICOM Law Revision Project Revision of 11 pieces of primary legislation and 6 subsidiary laws related to the CARICOM Single Market and Economy (CSME), and a general revision of the substantive laws.

No expenses were incurred.

116 Technical Assistance to the National Authorising Office (NAO)

Supply a technical assistance team to provide support to the NAO and line ministries in EU procedures and M&E.

Progress and expenditure updates pending.

113 Customs Reform and Modernisation (ASYCUDA)

Strengthening the capacity of the Customs & Excise Dept. to clear goods, collect revenue and efficiently provide trade data

CED The project is expected to receive support into the next year. Expenditure and progress updates pending.

114 Computerization of Drivers’ Licensing System

To improve and upgrade the Department of Transport's National Drivers' Licensing System

Total expenditure represents total recorded to March, 2012. Project was slated to end by 31/3/2013. Expenditure and progress updates pending.

111 Vocational Training for Vulnerable Youths Skills Training for youths country- wide, including funds for tuition & fees, equipment, books, uniforms, accommodation, transportation, and stipend.

Phase 2 funds were disbursed over the 2012/13 academic year; 54% of total funding was disbursed as at 30/6/2013.

112 Academic and Life Skills Training for Vulnerable Youths at Second Chance Schools

Aid for vulnerable youths in the Belize district that includes funds for tuition & fees, equipment, books, uniforms, accommodations, transportation, and stipend.

Phase 2 funds were disbursed over the 2012/13 academic year; 80% of total funding was disbursed as at 30/6/2013.

110 Implementing the Social Agenda of the National Poverty Elimination Strategy and Action Plan (NPESAP)

Technical support to the GOB in advancing the social agenda of the NPESAP

MFED I. Health, nutrition and social protection responses to consequences of food crisis: The IDB will not consider an extension to the TC and the contract will lapse. II. Quality and Coverage of Education Component: Activities under this component are on schedule and are three to four weeks away from completion. III. Targeting Efficiency and Evaluation of Social Services: Phase 2 - Implementation of SISB is in its final phase of completion and the additional TA for implementation phase is three weeks away from completion.

Page 22: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

EU/BRDP II NAO G 6,137,500 3,025,125 3,112,375

TOTAL $6,137,500EU/BRDP II MLLGRD G 250,200 209,299 40,901

TOTAL $250,200

EU/BRDP II DFT G 496,400 355,978 140,422

TOTAL $496,400

EU/BRDP II MFED G 443,713 244,002 199,711

TOTAL $443,713EU/BRDP II NAO G 200,000 148,915 51,085

TOTAL $200,000SECURITY & CIVIL RIGHTS

IADB L 800,000 220,535 579,465

GOB C 200,000 98,025 101,975

TOTAL $1,000,000

UNDP G 1,964,950 962,585 1,002,365

GOB C 215,600 199,510 16,090

TOTAL $2,180,550

IADB L 10,000,000 323,232 9,676,768

GOB C 368,914 - 368,914

TOTAL $10,368,914

122 Strengthening of Disaster Preparedness and Emergency Response Capacity in Belize

To assist Belize in strengthening its framework for disaster coordination and national capacities allowing for effective disaster preparedness, risk reduction and emergency response.

NEMO Expenditure and progress updates pending.

123 Community Action for Public Safety Strengthening of national public safety governance and community action in crime prevention

MHDST, OPM Procurement processes are ongoing for consultancies under Components I and II. Contracts were signed for Youth Center Coordinator and Continuum of Care consultants.

120 Support to City/Town/Village Administrations in the Management of Markets

Activities to enhance the management and administrative capacities and skills of councilors and personnel of the city/town/village administrations and other regulatory authorities overseeing markets in Belize and promote the use of best practices by vendors and the authorities.

Progress and expenditure updates pending.

121 Support for the Implementation of an Integrated Disaster Risk Management Plan

To support the GOB in designing and implementing a national IDRM Plan emphasising ex-ante risk reduction, supporting institutional strengthening and enhancing capacity for IDRM.

NEMO Progress and expenditure updates pending.

119 Trade Negotiations Logistics for Creation of Belize-Mexico PSA

Articulation of a Partial Scope Agreement between the independent nations of Belize and Mexico.

Progress and expenditure updates pending.

120 Belize PEFA Repeated Assessment Financing for a comprehensive assessment of public financial management in Belize (1) as a follow-up to the 2008 PEFA exercise, and (2) in order to assess GOB's eligibility for budget support.

Progress and expenditure updates pending.

117 Technical Assistance to BRDP II Provide support for the successful implementation of BRDP II.

Progress and expenditure updates pending.

118 Technical assistance to the Ministry of Labour, Local Government, Rural Development and NEMO

Assistance to the Ministry in establishing an Area Development Group that supports/ promotes economic growth through an Area Development Plan.

Progress and expenditure updates pending.

Page 23: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

EXPENDITURE FOR QUARTER

ENDING 30/6/2014

BALANCE PROJECT UPDATE TOTAL EXPENDITURE TO 30/6/2014

PROJECT DESCRIPTION FUNDING AGENCY

EXECUTING AGENCY

L/G COST (BZD)

GOB MLLGRD C2 2,600,000 156,569 2,443,431

TOTAL $2,600,000

SUB-TOTAL PUBLIC ADMINISTRATION 35,031,339 14,888,344 20,142,995 TOTALS 701,522,144 304,144,952 397,377,193

*NOTES:1/ This Report excludes projects that are proposed or in the pipeline (financing identified and approved but activities have not yet started; or funding identified but the scope has not been finalised; or project identified but funding pending).2/ For the purposes of this Report, "expenditure" is taken to mean amounts actually spent on project activities, and not amounts released/disbursed by a funding agency. While in the case of the EU funded projects, expenditure is

often equivalent to disbursements since the donor makes payments directly to consultants, contractors and suppliers; the relevant columns are intended to capture actual expenditure from the project funds.3/ "Expenditure for Quarter ending September 2013" records amounts spent between July and September, 2013.4/ "Total Expenditure to September, 2013" records total amounts spent against the approved funding from the start of the project to 30th September, 2013. 5/ "Balance" reflects the difference between the total cost of the project and the amounts spent from the various funding sources as at the end of September, 2013.

124 Countrywide Installation of Hydrants and Accessories

To promote increased safety and reduced losses resulting from fires through the purchase and installation of fire hydrants countrywide.

Progress and expenditure updates pending.

Page 24: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

Totals by Funding Type (BZD)

% of Total Ongoing PSIP

Total Expenditure to June 2014

Expenditure as % of Total Ongoing PSIP to 2014/15

Loans 374,874,516 53.4 491,517 0.1 Grants 213,272,361 30.4 - - Counterpart 102,261,381 14.6 88,480 0.0 Cap II 5,113,887 0.7 - - Unidentified 6,000,000 0.9 - - Total Ongoing PSIP 701,522,144 100.0 579,997 0.1

Totals by Sector (BZD)

% of Total Ongoing PSIP

Total Expenditure to June 2014

Expenditure as % of Total Ongoing PSIP to 2014/15

Infrastructure 414,597,091 59.1 - - Economic Services 210,297,823 30.0 - - Social Protection 41,595,891 5.9 - - Public Administration 35,031,339 5.0 - - Total Ongoing PSIP 701,522,144 100.0 - -

Expenditure to June 2014 by Funding Type and Sector

375

213

102

5 6 0 - 0 - - -

100

200

300

400

Loans Grants Counterpart Cap II Unidentified

Mill

ions

Expenditure to September 2013 by Funding Type

Totals by Funding Type (BZD) Total Expenditure to June 2014

415

210

42 35 - - - - -

100 200 300 400 500

Infrastructure EconomicServices

Social Protection PublicAdministration

Mill

ions

Expenditure to September 2013 by Sector

Totals by Sector (BZD) Total Expenditure to June 2014

0

100

200

300

400

Loans Grants Counterpart Cap II Unidentified

Mill

ions

Expenditure to June 2014 by Funding Type

Totals by Funding Type (BZD) Total Expenditure to June 2013

0100200300400500

Infrastructure EconomicServices

Social Protection PublicAdministration

Mill

ions

Expenditure to June 2014 by Sector

Totals by Sector (BZD) Total Expenditure to June 2013

Page 25: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

Totals by Sector % of Ongoing PSIP

Totals by Sector % of Funding Type Total

Totals by Sector % of Funding Type Total

Totals by Sector

% of Funding Type Total

Totals by Sector

% of Funding Type Total

Infrastructure 257,365,832 36.7 78,496,712 11.2 70,670,660 10.1 2,063,887 0.3 6,000,000 0.9 Economic Services 97,675,800 13.9 88,102,738 12.6 24,519,285 3.5 - - - - Social Protection 4,000,000 0.6 34,680,147 4.9 2,915,744 0.4 - - - - Public Administration 15,832,884 2.3 11,992,763 1.7 4,155,692 0.6 3,050,000 0.4 - - Totals 374,874,516 53.4 213,272,361 30.4 102,261,381 14.6 5,113,887 0.7 6,000,000 0.9

Ongoing PSIP by Funding Type and SectorGrant Counterpart Cap II UnidentifiedLoans

53%

30%

15%

1% 1%

Ongoing PSIP 2013/14 by Funding Type

Loans Grants Counterpart Cap II Unidentified

59% 30%

6% 5%

Ongoing PSIP 2013/14 by Sector

Infrastructure Economic Services Social Protection Public Administration

53%

30%

15%

1% 1%

Ongoing PSIP 2014/15 by Funding Type

Loans Grants Counterpart Cap II Unidentified

59% 30%

6% 5%

Ongoing PSIP 2014/15 by Sector

Infrastructure Economic Services Social Protection Public Administration

Page 26: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

BZD % of Ongoing PSIP

BZD % of Ongoing PSIP

BZD % of Ongoing PSIP

BZD % of Ongoing PSIP

BZD % of Ongoing PSIP

CABEI 25,211,600 3.6 21,400,000 3.1 3,811,600 0.5 - 0.0 - 0.0CDB 132,601,715 18.9 102,253,831 14.6 20,000,000 2.9 5,315,000 0.8 5,032,884 0.7EU 121,986,025 17.4 58,405,946 8.3 45,346,602 6.5 2,942,213 0.4 10,027,813 1.4IADB 110,867,863 15.8 31,900,000 4.5 63,717,863 9.1 4,450,000 0.6 10,800,000 1.5WB 35,992,288 5.1 30,000,000 4.3 - 0.0 5,992,288 0.9 - 0.0GOB 93,461,038 13.3 69,983,541 10.0 13,426,062 1.9 2,845,744 0.4 7,205,692 1.0Other* 181,401,614 25.9 100,653,773 14.3 63,995,696 9.1 20,050,646 2.9 1,964,950 0.3Totals 701,522,144 100.0 414,597,091 59.1 210,297,823 30.0 41,595,891 5.9 35,031,339 5.0

Total Funding by Agency Infrastructure Economic Services Social Protection

Ongoing PSIP by Funding Agency and Sector

Public Administration

CABEI 4%

CDB 19%

EU 17%

IADB 16%

WB 5%

GOB 13%

Other* 26%

Ongoing PSIP 2013/14 by Funding Agency CABEI

4% CDB 19%

EU 17%

IADB 16%

WB 5%

GOB 13%

Other* 26%

Ongoing PSIP 2014/15 by Funding Agency

Page 27: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

MINISTRY OF FINANCE ECONOMIC DEVELOPMENTPUBLIC SECTOR INVESTMENT PROGRAMME REPORT STATUS OF ONGOING PROJECTS AS AT JUNE, 2014

Total by Funding Type

% of Ongoing PSIP

Total by Funding Type

% of Ongoing PSIP

Total by Funding Type

% of Ongoing PSIP

Total by Funding Type

% of Ongoing PSIP

Total by Funding Type

% of Ongoing PSIP

CABEI 25,211,600 3.6 - - - - - - - - CDB 130,498,715 18.6 2,103,000 0.3 - - - - - - EU - - 121,986,025 17.4 - - - - - - IADB 102,144,000 14.6 8,723,863 1.2 - - - - - - WB 30,000,000 4.3 5,992,288 0.9 - - - - - - GOB - - 270,200 0.0 88,356,502 12.6 4,834,336 0.7 - - Other* 87,020,201 12.4 74,196,984 10.6 13,904,878 2.0 279,551 0.0 6,000,000 0.9 Totals 374,874,516 53.4 213,272,361 30.4 102,261,381 14.6 5,113,887 0.7 6,000,000 0.9

Total Ongoing PSIP 701,522,144

Other* includes: APAMO; BBG; BLPA,BWSL; CaMPAM; CARTFund; CDI; CU; EnvDF; FAO; GEF; GOV/ALBA; IFAD; KFAED; MarFUND; OAK; OFID; OIRSA,PACT; ROC; Taiwan ICDF; TCGA; UK; UNDP; UNEP; UNITAR; USG; YWCA

Loans Grants Counterpart CapII Unidentified

Ongoing PSIP by Funding Agency and Funding Type

Page 28: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

Economic Development PSIP REPORT - JUNE, 2014 Policy and Planning Unit

ACP Fish II Programme to Strengthen Fisheries Management in African, Caribbean and Pacific Group of Countries

AF Adaptation FundAGM/MFA Attorney General's Ministry and Ministry of Foreign AffairsALBA Alternativa Bolivariana para las Américas (Bolivarian Alliance for the Peoples

of our Americas)AMS Accompanying Measures for SugarAPAMO Association of Protected Areas Management OrganizationsASYCUDA Automated System for Customs DataBAA Belize Airport AuthorityBAHA Belize Agricultural Health AuthorityBCGA Belize Citrus Growers' Association BCUL Belize Credit Union LeagueBEL Belize Electricity Ltd.BELTRAIDE Belize Trade & Investment Development ServiceBEST Belize Enterprise for Sustainable Technology BLPA Belize Livestock Producers' AssociationBNTF Basic Needs Trust FundBSP Banana Support ProgrammeBSSB Belize Social Security BoardBTB Belize Tourism BoardBWSL Belize Water Services, Ltd.C Counterpart (Local) ContributionCABEI Central American Bank for Economic IntegrationCaMPAM Caribbean Marine Protected Areas Management Network and ForumCAP II Capital II ExpenditureCARTFund Caribbean Aid for Trade and Regional Integration Trust FundCBA Central Building AuthorityCBB Central Bank of BelizeCDB Caribbean Development BankCDI Commonwealth Debt InitiativeCED Customs and Excise DepartmentCGA Citrus Growers' AssociationCREI Citrus Research and Education InstituteCReW Caribbean Regional Fund for Wastewater ManagementCU Credit UnionDFC Development Finance CorporationDFT Directorate of Foreign TradeEU European UnionEDF European Development FundEnvDF Environmental Defense FundFAO Food and Agriculture Organisation of the United NationsFD Forestry DepartmentG GrantGEF Global Environmental FacilityGF Global FundGOB Government of BelizeGOM Government of MexicoGOV Government of VenezuelaGPMP Good Pesticide Management PracticeIADB Inter-American Development BankICDF International Cooperation and Development Fund

LIST OF ABBREVIATIONS

Page 29: MINISTRY OF FINANCE ECONOMIC DEVELOPMENT PUBLIC …med.gov.bz/wp-content/uploads/2016/10/1stquarter... · the Airport Junction and Haulover Bridge. The Consultant has completed the

Economic Development PSIP REPORT - JUNE, 2014 Policy and Planning Unit

LIST OF ABBREVIATIONSIDRM Integrated Disaster Risk Management System

IFAD International Fund for Agricultural Development JSDF Japan Social Development FundKOICA Korea International Cooperation AgencyKFAED Kuwait Fund for Arab Economic DevelopmentL LoanLGA Local Government AgenciesMAR Fund Mesoamerican Reef FundMFED Ministry of Finance & Economic DevelopmentMFFSD Ministry of Forestry, Fisheries and Sustainable Development MHDST Ministry of Human Development, Social Transformation and Poverty AlleviationMHI 2015 Mesoamerican Health Initiative 2015 (Mexico)MLLGRD Ministry of Labour, Local Government, Rural Development, National Emergency

Management and ImmigrationMNRA Ministry of Natural Resources and AgricultureMOEYS Ministry of Education, Youth and SportsMOH Ministry of HealthMOTC Ministry of Tourism and CultureMOWT Ministry of Works & TransportMNS Ministry of National SecurityMPS Ministry of the Public Service and Elections & BoundariesMESTPU Ministry of Energy, Science & Technology and Public UtilitiesNAC National AIDS CommissionNAO National Authorising OfficeNEMO National Emergency Management OrganizationNPESAP National Poverty Elimination Strategy and Action PlanOAK Oak FoundationOFID OPEC Fund for International DevelopmentOIRSA Organismo Internacional Regional de Sanidad Agropecuaria

(Regional International Organisation for Animal and Plant Health)PACT Protected Areas Conservation TrustPEU Project Execution UnitROC Republic of China (Taiwan)SCADA Supervisory Control and Data Acquisition SIF Social Investment FundSIF II Second Loan to the Social Investment FundSIRDI Sugar Industry Research and Development InstituteSWMA Solid Waste Management AuthorityTTM Taiwanese Technical MissionU Unidentified (Funding )UNDP United Nations Development ProgrammeUNEP United Nations Environment ProgrammeUNITAR United Nations Institute for Training and ResearchUK United KingdomUSG United States Government WB World Bank