CONSTRUCTIONMANAGER’S
WEEKLYPROGRESSREPORT
03/18/2019–03/23/2019
Figure 1: 03/22/2019 – Ongoing installation of pervious sidewalk in the front of property #4127, Minnesot Ave
between Sta. 142+75 – 144+75.
MINNESOTAAVENUENEREVITALIZATIONPHASEII
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 2 of 13
1.EXECUTIVESUMMARY ProjectDescription:
The project consists of the revitalization of Minnesota Avenue starting from 300 feet south of Benning Road, N.E. intersection to Sheriff Road, N.E. The project will improve pedestrian & vehicular traffic through the area and also improve the aesthetics of the neighborhood. Work includes removal of existing rigid pavement and replacing with a flexible pavement, removal of existing sidewalk and replacing with permeable concrete and exposed aggregate sidewalk, removal and replacement of curb and gutter, sign installation and pavement markings as shown on project plans and indicated in the specifications and special provisions. Also, incorporated into the project is Low Impact Development (LID) work, lighting and traffic signals. The project is also a pilot for DC Plug.
The project is 90.00% Federally‐Funded and 10.00% District‐Funded. DDOT selected Fort Myer Construction Corporation (FMCC) as the contractor and awarded the $19,781,553.14 contract on July 21, 2017. DDOT issued notice to proceed with contract work to FMCC on September 11, 2017 with work to begin and an original completion date of October 28, 2019.
2.STATUSOFPROJECTFUNDINGANDSCHEDULE
ContractSchedules:
Firm
NTPDate
OriginalDuration+ApprovedIncrease
Original
CompletionDate
RequestedCompletion
Date
ApprovedChanged
CompletionDate
Fort Myer Construction Corporation
09/11/2017
777
10/28/2019
Belstar Inc.
07/05/2017
837
10/20/2019
Based on the January 2019 schedule update #15 the general contractor shows a completion date of September 27th 2019.
Based on the December 2018 schedule update #14 the general contractor shows a completion date of October 15th 2019.
Based on the November 2018 schedule update #13 the general contractor shows a completion date of November 13th 2019.
On December 4th 2018, the general contractor submitted a letter applying for partial suspension of work between the months of December 1st 2018 and April 1st 2019 to the Contracting & Procurement Office.
Based on the October 2018 schedule update #12 the general contractor shows a completion date of September 4th 2019, the schedule lost 22 days from previous update.
Based on the September 2018 schedule update #11 the general contractor shows a completion date of August 13th 2019.
Based on the August 2018 schedule update #10 the general contractor shows a completion date of September 6, 2019 the schedule lost 14 days from the previous update. And the project currently at 40% completion.
Based on the July 2018 schedule update #09 the general contractor shows a completion date of August 23, 2019.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 3 of 13
The revised schedule does not show the impact of the partial suspension of work which was approved by the contracting officer until a change order has been formally approved for the discounted days. Then the completion date will be adjusted.
A revised MOT plan was submitted by the general contractor and based on this, the baseline schedule was revised to show time gain based on the revised MOT. The schedule was approved as submitted. The new completion date is 19th of July, 2019.
On December 28th 2017, the general contractor submitted a letter applying for partial suspension of work between the months of December 1st 2017 and April 1st 2018 to the Contracting office. Approval was granted on January 12, 2018 any time extension will be formalized by change order.
3.STATUSOFCONSTRUCTION/PROGRESSSUMMARY
The summary is for work done from Monday 18th to Saturday 23rd of March 2019. Work included building of retaining wall, wheelchair, excavation and placing of sidewalk.
Monday03/18/2019:DayTimeWork
FMCC: Continued excavating for pervious concrete sidewalk on the NE corner of Grant St/Minnesota Ave. (Sta
44+25 – 44+91).
Reinstalled granite curb and forming for wheelchair ramp on NE corner of Grant St/Minnesota Ave. (Sta 44+25 – 44+91).
Continued excavating, started installing rebar, and forming for retaining wall #1 footing at the SW corner of Benning Rd. (Sta. 201+00 – 202+00).
WGL(DCI/MillerPipeLine): Miller Pipe Line continued relocating gas main on Minnesota Ave between Hunt Pl and Hayes St.
DCI continued relocating gas main at the SE corner of Minnesota Ave./Benning Rd. (Sta. 127+00 ‐ 128+50).
Tuesday03/19/2019:DayTimeWork
FMCC: Continued excavating for pervious concrete sidewalk and planter boxes on the east side of Minnesota Ave in
the front of JA Auto tire shop.
Installed wheelchair/bike ramp and gutter on NE corner of Grant St/Minnesota Ave. (Sta 44+25 – 44+91).
Installed PCC edge on westside of Minnesota Ave. (Sta. 144+25 – 144+75).
Continued installing rebar and forming for retaining wall #1 footing at the SW corner of Benning Rd. (Sta. 201+00 – 202+00).
WGL(DCI/MillerPipeLine): Miller Pipe Line continued relocating gas main on Minnesota Ave between Hunt Pl and Hayes St.
DCI continued relocating gas main at the SE corner of Minnesota Ave./Benning Rd. (Sta. 127+00 ‐ 128+50).
Wednesday03/20/2019:DayTimeWork
FMCC: Installed granite curb on NE corner of Minnesota Ave/Gault Pl. (Sta. 144+90 to 145+70)
Installed PCC edge on eastside of Minnesota Ave. (Sta. 144+25 – 144+75).
Removed existing inlet on SE corner of Gaul Pl/ Minnesota Ave. Sta. 146+40.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 4 of 13
Placed concrete for retaining wall #1 footing at the SW corner of Benning Rd. (Sta. 201+00 – 202+00). WGL(DCI/MillerPipeLine):
Miller Pipe Line continued relocating gas main on Minnesota Ave between Hunt Pl and Hayes St.
DCI continued relocating gas main at the SE corner of Minnesota Ave./Benning Rd. (Sta. 127+00 ‐ 128+50).
Thursday03/21/2019:DayTimeWork
FMCC: No work due to inclement weather.
Friday03/22/2019:DayTimeWork
FMCC: Installed pervious concrete sidewalk from Grant St to JA Auto tire shop drive way. (Sta. 142+75 – 144+75).
Placed concrete for gutter on NE corner of Minnesota Ave/Gault Pl. (Sta. 46+21 – 46+75)
Continued installing rebar and building concrete formwork for retaining wall #1 at the SW corner of Benning Rd. (Sta. 201+00 – 202+00).
WGL(DCI/MillerPipeLine):
Miller Pipe Line continued relocation of 12” gas main on Minnesota Ave between Hunt Pl and Hayes St.
Saturday03/23/2019:DayTimeWork
FMCC: No schedule work.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 5 of 13
4.PHOTOSOFWORKPERFORMEDTHISPERIOD
Figure 2: 03/22/2019: ‐ Ongoing installation of pervious sidewalk in the front of property #4127, Sta. 142+75 – 144+75.
Figure 3: 03/22/2019 ‐ Ongoing work on retaining wall #1.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 6 of 13
Figure 4: 03/22/2019 ‐ Ongoing installation of pervious concrete sidewalk in the front of JA Auto Shop (Sta. 144+30 – 144+65).
Figure 5: 03/22/2019 ‐ Inspector conducting test on pervious concrete.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 7 of 13
Figure 6: 03/21/2019 ‐ Area prepared for pervious concrete sidewalk.
Figure 7: 03/21/2019 ‐ Area prepared for retaining wall #1.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 8 of 13
Figure 8: 03/20/2019 – Installation of concrete for retaining wall #1 footing at the SW corner of Minnesota Ave/Benning Rd.
Figure 9: 03/20/2019 – Installation of granite curb at the SE corner of Minnesota Ave/Gault Pl.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 9 of 13
Figure 10: 03/20/2019 – Installation of granite curb at SE corner of Minnesota Ave/Gault Pl.
Figure 11: 03/20/2019 – Installation of PCC edge on eastside of Minnesota Ave (Sta. 144+30 ‐ 144+65).
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 10 of 13
Figure 12: 03/19/2019 – Ongoing rebar work for retaining wall #1 at the SW corner of Minnesota Ave/Benning Rd.
Figure 13: 03/19/2019 – Installation of wheelchair ramp and gutter at NE corner of Minnesota Ave/Grant St.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 11 of 13
Figure 14: 03/19/2019 – Ongoing Wash Gas work.
Figure 15: 03/19/2019 – Excavation for structural sand at SE corner of Minnesota Ave/Gault Pl.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 12 of 13
Figure 16: 03/18/2019 – Building of retaining wall #1 footing at SW corner of Minnesota Ave/Benning Rd intersection.
Figure 17: 03/18/2019 – Installation of granite curb and forming of wheelchair ramp at NE corner of Minnesota Ave/Grant St.
www.minnesotaavephase2.com
CONSTRUCTIONMANAGER’SWEEKLYPROGRESSREPORTWEEKENDING03/23/2019
PAGE 13 of 13
Figure 18: 03/18/2019 – Replacing broken catch basin top on eastside of Minnesota Ave (Sta. 143+75).
Figure 19: 03/18/2019 – Excavation for pervious sidewalk on NE corner of Minnesota Ave/Grant St. (Sta. 143.00)