ANDERSON MILL ROAD
• Final preliminary engineering
report completed Sept. 2018
• 90% design by March 2019
• Permitting process could last
just over a year
• Bid process anticipated to
take 6 months
• Earliest project could begin
construction would be
summer 2020
3
SPICEWOOD SPRINGS ROAD
• Alternative C selected as the build
alternative
– 2 vehicle lanes each direction
– raised median and left-turn bays
– shared use path on both sides
– new stormwater facilities
• Final preliminary engineering report
completed December 2018
• Design phase of the project is now
underway
4
RM 2222/RM 620 BYPASS
Project 1: RM 2222 (Bonaventure Dr to Ribelin Ranch Dr)
– Construction already underway
– Anticipated completion: mid-2020
– Construction cost: $17.4 million
Project 2: RM 620 (Steiner Ranch Blvd to RM 2222)
– Construction start: Fall 2019
– Anticipated completion: Winter 2020
– Construction cost: $10 million
5
PARMER LANE
Proposed Improvements
– 3 lanes in each direction
– Improve intersections and turn lanes
– Dedicated bicycle/pedestrian path
Project Development Timeline
– Preliminary Design: 2019
– Final Design/Engineering: 2020
– Utility Relocation: 2021
– Estimated Construction Start: 2022
6
2016 MOBILITY BOND UPDATE
Regional Mobility: $101 million to
address regional congestion and enhance
safety
Corridor Mobility: $482 million for
corridor improvement projects
Local Mobility: $137 million to local
mobility projects, including:
– Sidewalks – Safe Routes to School
– Urban Trails – Bikeways
– Vision Zero – Sub-standard Streets
7
AUSTIN STRATEGIC MOBILITY PLAN (ASMP)Final ASMP draft released on Feb. 22nd
ASMP to be adopted later this spring
Important Dates
– Council Mobility Committee:
Feb. 28th 1:00-3:00 pm
– Planning Commission:
• March 12th 6:00 pm (Public Hearing)
• March 26th 6:00 pm
– City Council
• March 28th (Public Hearing)9
PROJECT CONNECT
• CapMetro to adopt Public Engagement
Plan in Spring 2019
• High Capacity Transit
• Service Type
– Commuter Service
– Local Service
• Important Dates
– Joint Meeting of the City Council and
Capital Metro Board: March 4th
10
CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION (CAMPO)
• May 2018 adopted the 2019-2022 TIP
– Secured $13.7 million for Lakeline Blvd
• Project Improvements:
– Add two additional travel lanes
– Upgrade bicycle facilities and sidewalks
11
RM 620COLORADO RIVER TO US 183• RM 2222/RM 620 Bypass Project
– Project 1: RM 2222 - Construction already
underway
– Project 2: RM 620 - Construction start: Fall
2019
• RM 620/Anderson Mill Intersection
– Study in progress
• RM 620 - Anderson Mill Rd to US 183
– Discussions on going for this segment
12
DISTRICT 6
NEWSLETTER
Get ongoing updates from the
D6 office on community
events and the latest from
City Hall!
Subscribe today by visiting:
http://www.atxd6.org/contact/
subscribe/
14