Upload
others
View
19
Download
0
Embed Size (px)
Citation preview
The ultimate in riser shaft maintenance flooring
USING RISERSAFE® ELIMINATES RISK THROUGH DESIGN
Modular Riser Flooring system
02www.ambar-kelly.com
Modular Riser Flooring system
WHEN TO INCORPORATE RISERSAFE®
For maximum benefits, the Modular Riser Flooring System should be incorporated as the buildings riser maintenance platform in RIBA Stage 2.
The RIBA Plan of Work organises the process of briefing, designing, delivering, maintaining, operating and using a building into eight stages. It is a framework for all disciplines on construction projects and should be used solely as guidance for the preparation of detailed professional services and building contracts.
0
Strategic Definition
1
Preparation and Briefing
2
Concept Design
3
Spatial Coordination
4
Technical Design
5
Manufacturing and Construction
6
Handover
7
Use
Projects span from Stage 1 to Stage 6; the outcome of Stage 0 may be the decision to initiate a project and Stage 7 covers the ongoing use of the building.
Stage Outcomeat the end of the stage
The best means of achieving the Client Requirements confirmed
If the outcome determines that a building is the best means of achieving the Client Requirements, the client proceeds to Stage 1
Project Brief approved by the client and confirmed that it can be accommodated on the site
Architectural Concept approved by the client and aligned to the Project Brief
The brief remains “live” during Stage 2 and is derogated in response to the Architectural Concept
Architectural and engineering information Spatially Coordinated
All design information required to manufacture and construct the project completed
Stage 4 will overlap with Stage 5 on most projects
Manufacturing, construction and Commissioning completed
There is no design work in Stage 5 other than responding to Site Queries
Building handed over, Aftercare initiated and Building Contract concluded
Building used, operated and maintained efficiently
Stage 7 starts concurrently with Stage 6 and lasts for the life of the building
Core Tasksduring the stage
Project Strategies might include:– Conservation (if applicable)– Cost– Fire Safety– Health and Safety– Inclusive Design– Planning– Plan for Use– Procurement– SustainabilitySee RIBA Plan of Work 2020 Overview for detailed guidance on Project Strategies
Prepare Client Requirements
Develop Business Case for feasible options including review of Project Risks and Project Budget
Ratify option that best delivers Client Requirements
Review Feedback from previous projects
Undertake Site Appraisals
No design team required for Stages 0 and 1. Client advisers may be appointed to the client team to provide strategic advice and design thinking before Stage 2 commences.
Prepare Project Brief including Project Outcomes and Sustainability Outcomes, Quality Aspirations and Spatial Requirements
Undertake Feasibility Studies
Agree Project Budget
Source Site Information including Site Surveys
Prepare Project Programme
Prepare Project Execution Plan
Prepare Architectural Concept incorporating Strategic Engineering requirements and aligned to Cost Plan, Project Strategies and Outline Specification
Agree Project Brief Derogations
Undertake Design Reviews with client and Project Stakeholders
Prepare stage Design Programme
Undertake Design Studies, Engineering Analysis and Cost Exercises to test Architectural Concept resulting in Spatially Coordinated design aligned to updated Cost Plan, Project Strategies and Outline Specification
Initiate Change Control Procedures
Prepare stage Design Programme
Develop architectural and engineering technical design
Prepare and coordinate design team Building Systems information
Prepare and integrate specialist subcontractor Building Systems information
Prepare stage Design Programme
Specialist subcontractor designs are prepared and reviewed during Stage 4
Finalise Site Logistics
Manufacture Building Systems and construct building
Monitor progress against Construction Programme
Inspect Construction Quality
Resolve Site Queries as required
Undertake Commissioning of building
Prepare Building Manual
Building handover tasks bridge Stages 5 and 6 as set out in the Plan for Use Strategy
Hand over building in line with Plan for Use Strategy
Undertake review of Project Performance
Undertake seasonal Commissioning
Rectify defects
Complete initial Aftercare tasks including light touch Post Occupancy Evaluation
Implement Facilities Management and Asset Management
Undertake Post Occupancy Evaluation of building performance in use
Verify Project Outcomes including Sustainability Outcomes
Adaptation of a building (at the end of its useful life) triggers a new Stage 0
Core Statutory Processesduring the stage:
PlanningBuilding RegulationsHealth and Safety (CDM)
Strategic appraisal of Planning considerations
Source pre-application Planning Advice
Initiate collation of health and safety Pre-construction Information
Obtain pre-application Planning Advice
Agree route to Building Regulations compliance
Option: submit outline Planning Application
Review design against Building Regulations
Prepare and submit Planning Application
See Planning Note for guidance on submitting a Planning Application earlier than at end of Stage 3
Submit Building Regulations Application
Discharge pre-commencement Planning Conditions
Prepare Construction Phase Plan
Submit form F10 to HSE if applicable
Carry out Construction Phase Plan
Comply with Planning Conditions related to construction
Comply with Planning Conditions as required
Comply with Planning Conditions as required
Procurement Route Traditional Tender
Appoint contractor
Design & Build 1 Stage ER CP Appoint
contractor
Design & Build 2 Stage ER Pre-contract services agreement CP Appoint
contractor
Management Contract Construction Management
Appoint contractor
Contractor-led ER Preferred bidder CP Appoint
contractor
Information Exchangesat the end of the stage
Client Requirements
Business Case
Project Brief
Feasibility Studies
Site Information
Project Budget
Project Programme
Procurement Strategy
Responsibility Matrix
Information Requirements
Project Brief Derogations
Signed off Stage Report
Project Strategies
Outline Specification
Cost Plan
Signed off Stage Report
Project Strategies
Updated Outline Specification
Updated Cost Plan
Planning Application
Manufacturing Information
Construction Information
Final Specifications
Residual Project Strategies
Building Regulations Application
Building Manual including Health and Safety File and Fire Safety Information
Practical Completion certificate including Defects List
Asset Information
If Verified Construction Information is required, verification tasks must be defined
Feedback on Project Performance
Final Certificate
Feedback from light touch Post Occupancy Evaluation
Feedback from Post Occupancy Evaluation
Updated Building Manual including Health and Safety File and Fire Safety Information as necessary
Core RIBA Plan of Work terms are defined in the RIBA Plan of Work 2020 Overview glossary and set in Bold Type. Further guidance and detailed stage descriptions are included in the RIBA Plan of Work 2020 Overview. © RIBA 2020
Stage Boundaries:Stages 0-4 will generally be undertaken one after the other.Stages 4 and 5 will overlap in the Project Programme for most projects.Stage 5 commences when the contractor takes possession of the site and finishes at Practical Completion. Stage 6 starts with the handover of the building to the client immediately after Practical Completion and finishes at the end of the Defects Liability Period.Stage 7 starts concurrently with Stage 6 and lasts for the life of the building.
Planning Note:Planning Applications are generally submitted at the end of Stage 3 and should only be submitted earlier when the threshold of information required has been met. If a Planning Application is made during Stage 3, a mid-stage gateway should be determined and it should be clear to the project team which tasks and deliverables will be required. See Overview guidance.
Procurement:The RIBA Plan of Work is procurement neutral – See Overview guidance for a detailed description of how each stage might be adjusted to accommodate the requirements of the Procurement Strategy.
ER Employer’s Requirements
CP Contractor’s Proposals
RIBAPlan of Work 2020
Appoint client team
Appoint design team
Appoint Facilities Management and Asset Management teams, and
strategic advisers as needed
03www.ambar-kelly.com
Modular Riser Flooring system
Examples of RiserSafe® being installed on site and a visual inspection being made by our team:
Q. WHAT IS RISERSAFE®?
PATENTED CAST-IN SAFETY SYSTEM • Satisfies Joint COP ‘fire prevention on construction sites’• Provides maximum area for services to pass through• Individual pre-cut holes on floor plate with cover plates,
eliminating the need for main contractor to manage• Can be used as part of the M&E permanent fixing system• Shortens project programme• Lowers project costs• Reduces carbon footprint• Permanent maintenance flooring
RiserSafe® is protected by Ambar Kelly’s patent GB 2429021B
A. It is the building’s final maintenance platform which is simply cast in at the start of the project, eliminating the risk of falls and fire.
04www.ambar-kelly.com
Modular Riser Flooring system
RISERSAFE® WORKS WITH ANY FRAME
3
STEEL FRAME CONCRETE FRAME AND POST TENSIONED
PRE-CAST PLANKS POST FIT
Cladding package
Scaffoldingpackage
Flooringpackage
Logisticspackage
Joinerypackage
Buildersworkspackage
Block workpackage
Raised access flooringpackage
Concrete frame package
Roofing package
Steel frame package
Mechanicalpackage
Ductingpackage
Electricalpackage
Sprinklerpackage
Dryliningpackage
Fire protectionpackage
Ceilingspackage
Risers
Prelims
Trade Interfaces
05www.ambar-kelly.com
Modular Riser Flooring system
3D MODELLING BY OUR IN-HOUSE TEAM
The increased productivity on site is the result of pulling the multitude of designs from different disciplines into our model as part of the product detailing, reducing on site challenges and providing a smooth, efficient and safe construction process, where all the problems could be detailed out before they ever reach construction.
1. STEEL FRAME 2. UNITS POSITIONED ON STEEL FRAME NO MEP SERVICES
The 3D Model illustrations show when our team review the models received, which are plotted into our modelling system in collaboration with the designers of the building. They are adjusted so clashes are irradicated and do not occur during construction, reducing last minute issues, making installation faster, safer and more efficient.
3. SERVICES STARTING TO BE MODELLED THROUGH THE UNITS 4. SERVICES MODELLED THROUGH THE UNITS WITH SOME SPARE OPENINGS
06
Modular Riser Flooring system
www.ambar-kelly.com
Units arrive on our FORS Gold lorry
Unit being landed Risersafe® Unit
THE INSTALLATION PROCESS
1. Deliver
2. Lift into place
07
Modular Riser Flooring system
THE INSTALLATION PROCESS
www.ambar-kelly.com
Unit cast and bolted in position. The fire boarding has been placed around the fire wall beams ready for the walls to be built. Services are just starting to be installed.
Rebar surrounding Casting in unit with concrete
3. Cast into concrete
4. Leave it to do its thing. It’s that simple!
08www.ambar-kelly.com
Modular Riser Flooring system
We incorporate the MEP requirements in conjunction with horizontal and vertical fire protection to meet the five standards that are associated with the riser shafts (zone). This has been proven to reduce construction time by up to two months.
MECHANICAL, ELECTRICAL AND PLUMBING (MEP)
RiserSafe® soakers to close off gaps between services and floor plate
09www.ambar-kelly.com
Modular Riser Flooring system
CREATES A BARRIER STOPPING THE SPREAD OF SMOKE AND FLAME
Modular riser flooring has been tested and proven to have a fire resistance to a 1000°C for 90 minutes with no loss of integrity during the test, demonstrating an excellent horizontal barrier to the spread of smoke and flame where used.
Building Research Establishment (BRE) fire testing of RiserSafe®
GRP grating RiserSafe®
Horizontal fire protection made simple
RiserSafe® meets the requirements of Approved Document B.
RiserSafe®, in combination with fire compound, recorded no failure in insulation or integrity whilst tested for over 2hrs .
10www.ambar-kelly.com
Modular Riser Flooring system
VALUE V COST
The RiserSafe® system is not just a fall protection product, it is a 3D Modelled modular riser flooring system which reduces risk through design by incorporating all the following trade interfaces into one single option.
Therefore what appears an expensive entry price is actually an all-encompassing price fixed for the duration of the project.
The value is based on costs across the whole project, as identified above, providing a single solution with no hidden extras.
FRAME- Edge trim- Handrails- Shuttering- Striking
ROOFING- Upstand- Scaffold- Cowl
base
DRY LINING- Fire beams- GRP cuts- Single
workfaces- Re-support
GRP
GEN BUILD- Temp fire
doors required
- Temp locks required
- Single workfaces
– Water Ingress
BWIC- GRP hole
cut- Extra GRP
support- Fire
stopping not compatible
M&E- GRP hole
set out- Single
work fronts 50% less productive
SCAFFOLD- Extended
hire frame- Adaptions
for walls- Attendance
for adapts
£2,9000,000.00
£2,400,000.00
£1,900,000.00
£1,400,000.00
£900,000.00
£400,000.00
COST
Purchase Perception
Entry Price Exit Price
£827,029.72
£629,175.72
GRP ORTHO/ISO Resin (entry level) GRP PHENOLIC Resin
Actual GRP cost
Actual RiserSafe® cost£1,303,798.71
£1,967,506,44
£1,769,652.44
£1,303,798.71
RiserSafe® with 30% replacement
RiserSafe® cost at tender
Perceived GRP cost at tender
11www.ambar-kelly.com
Modular Riser Flooring system
QUALITY CONTROL MANUFACTURING STANDARDS
CARBON NEUTRALITY
Ambar Kelly has worked with Carbon Footprint Limited to become a carbon neutral organisation.
We calculate the captured carbon content for every project and offset this, making our RiserSafe® offering carbon neutral to projects.
A Cradle-to-Grave Life-Cycle Assessment has been carried out on RiserSafe®, which is an assessment of the environmental impacts of our product during its life-cycle. It incorporates the analysis of raw materials, manufacture, transport, usage and disposal.
As part of our ongoing commitment to the environment, for every RiserSafe® unit that is manufactured, we calculate the captured carbon content and offset this value at the end of the project. Our customers are then provided with a certificate demonstrating this, which can be used towards environmental credentials for the overall scheme.
CE Marked and manufactured to Execution Class 2
12www.ambar-kelly.com
Modular Riser Flooring system
LIST OF PROJECTS
• One Crown Place – 37 Floors• 70 St Mary Axe – 21 floors• Twickenham Stadium • One Angel Court – 20 floors• B Sky B – 4 floors• Barton Court – 3 Floors • Bohunt School – 1 Floor• Vauxhall Sky Gardens – 37 floors• Newfoundland – 58 floors• Triton Square – 10 floors• 245 Hammersmith – 10 floors• Nile Street – 29 floors• Principal Place – 50 floors• London Wall Place – 22 floors• Bloomberg – 10 floors• Twickenham Stadium• Papworth Hospital – 5 floors• 52 Lime Street – 37 floors• Tidal Basin – 23 floors• S1 – 12 floors• 3 Snowhill – 20 floors• Hampton by Hilton Hotel – 4 floors x 2• HCA Hospital – 6 floors • Derby Manor School – 2 floors• Strood School – 2 floors• Kemsley Energy Centre – 4 floors• Krishna Avanti Primary School – 2 floors• Imperial College – 13 floors• Riverside Ice & Leisure Centre – 2 floors• Beaulieu Park School – 2 floors• Valentine House – 10 floors• Dulwich Prep School – 2 floors• Royal Albert Dock – 8 floors• King’s School – 2 floors• Aberdeen Hotel & Conference Centre – 4 floors
• Chertsey High School – 2 floors• Avonmouth Energy Centre – 5 floors• Richmond College – 6 floors• King’s Cross R3 – 10 floors• St Bede’s School – 2 floors• Newcastle University – 5 floors• FitzWimarc School – 2 floors• Katherine Warrington School – 2 floors• Bank Station – 7 Sub floors• Golden Jubilee National Hospital – 1 floor• Mustard Wharf – 11 floors• Little Heath School – 2 floors (Won Considerate contractors award)
• Simon Langton School – 2 floors• Deer Park School – 2 floors• Chelsea Barracks – 4 floors• Tasman House – 7 floors• One The Square – 10 floors• Queen Anne Street – 5 floors• Fetter Lane – 8 floors• Verde – 12 floors• 73-89 Oxford Street – 7 floors• RAF Yeovilton – 1 floor• Project Wren – 4 floors• Forbury Place, Phase 1 – 10 floors• Forbury Place, Phase 2 – 10 floors• North Bristol Hospital – 4 floors• Derwen Vale School – 2 floors• London School of Economics – 14 floors• Pleckgate School – 3 floors• Regent Quarter – 6 floors• GSK B9 – 4 floors• Lister Hospital – 5 floors• Rild Exeter – 4 floors• Oldbury College – 4 floors
013
Ambar Kelly Ltd,4a Bridgefields,Welwyn Garden City, Hertfordshire,AL7 1RX
T: 01707 324523 E: [email protected]