13
The ultimate in riser shaft maintenance flooring USING RISERSAFE® ELIMINATES RISK THROUGH DESIGN Modular Riser Flooring system

Modular Riser Flooring system

  • Upload
    others

  • View
    19

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Modular Riser Flooring system

The ultimate in riser shaft maintenance flooring

USING RISERSAFE® ELIMINATES RISK THROUGH DESIGN

Modular Riser Flooring system

Page 2: Modular Riser Flooring system

02www.ambar-kelly.com

Modular Riser Flooring system

WHEN TO INCORPORATE RISERSAFE®

For maximum benefits, the Modular Riser Flooring System should be incorporated as the buildings riser maintenance platform in RIBA Stage 2.

The RIBA Plan of Work organises the process of briefing, designing, delivering, maintaining, operating and using a building into eight stages. It is a framework for all disciplines on construction projects and should be used solely as guidance for the preparation of detailed professional services and building contracts.

0

Strategic Definition

1

Preparation and Briefing

2

Concept Design

3

Spatial Coordination

4

Technical Design

5

Manufacturing and Construction

6

Handover

7

Use

Projects span from Stage 1 to Stage 6; the outcome of Stage 0 may be the decision to initiate a project and Stage 7 covers the ongoing use of the building.

Stage Outcomeat the end of the stage

The best means of achieving the Client Requirements confirmed

If the outcome determines that a building is the best means of achieving the Client Requirements, the client proceeds to Stage 1

Project Brief approved by the client and confirmed that it can be accommodated on the site

Architectural Concept approved by the client and aligned to the Project Brief

The brief remains “live” during Stage 2 and is derogated in response to the Architectural Concept

Architectural and engineering information Spatially Coordinated

All design information required to manufacture and construct the project completed

Stage 4 will overlap with Stage 5 on most projects

Manufacturing, construction and Commissioning completed

There is no design work in Stage 5 other than responding to Site Queries

Building handed over, Aftercare initiated and Building Contract concluded

Building used, operated and maintained efficiently

Stage 7 starts concurrently with Stage 6 and lasts for the life of the building

Core Tasksduring the stage

Project Strategies might include:– Conservation (if applicable)– Cost– Fire Safety– Health and Safety– Inclusive Design– Planning– Plan for Use– Procurement– SustainabilitySee RIBA Plan of Work 2020 Overview for detailed guidance on Project Strategies

Prepare Client Requirements

Develop Business Case for feasible options including review of Project Risks and Project Budget

Ratify option that best delivers Client Requirements

Review Feedback from previous projects

Undertake Site Appraisals

No design team required for Stages 0 and 1. Client advisers may be appointed to the client team to provide strategic advice and design thinking before Stage 2 commences.

Prepare Project Brief including Project Outcomes and Sustainability Outcomes, Quality Aspirations and Spatial Requirements

Undertake Feasibility Studies

Agree Project Budget

Source Site Information including Site Surveys

Prepare Project Programme

Prepare Project Execution Plan

Prepare Architectural Concept incorporating Strategic Engineering requirements and aligned to Cost Plan, Project Strategies and Outline Specification

Agree Project Brief Derogations

Undertake Design Reviews with client and Project Stakeholders

Prepare stage Design Programme

Undertake Design Studies, Engineering Analysis and Cost Exercises to test Architectural Concept resulting in Spatially Coordinated design aligned to updated Cost Plan, Project Strategies and Outline Specification

Initiate Change Control Procedures

Prepare stage Design Programme

Develop architectural and engineering technical design

Prepare and coordinate design team Building Systems information

Prepare and integrate specialist subcontractor Building Systems information

Prepare stage Design Programme

Specialist subcontractor designs are prepared and reviewed during Stage 4

Finalise Site Logistics

Manufacture Building Systems and construct building

Monitor progress against Construction Programme

Inspect Construction Quality

Resolve Site Queries as required

Undertake Commissioning of building

Prepare Building Manual

Building handover tasks bridge Stages 5 and 6 as set out in the Plan for Use Strategy

Hand over building in line with Plan for Use Strategy

Undertake review of Project Performance

Undertake seasonal Commissioning

Rectify defects

Complete initial Aftercare tasks including light touch Post Occupancy Evaluation

Implement Facilities Management and Asset Management

Undertake Post Occupancy Evaluation of building performance in use

Verify Project Outcomes including Sustainability Outcomes

Adaptation of a building (at the end of its useful life) triggers a new Stage 0

Core Statutory Processesduring the stage:

PlanningBuilding RegulationsHealth and Safety (CDM)

Strategic appraisal of Planning considerations

Source pre-application Planning Advice

Initiate collation of health and safety Pre-construction Information

Obtain pre-application Planning Advice

Agree route to Building Regulations compliance

Option: submit outline Planning Application

Review design against Building Regulations

Prepare and submit Planning Application

See Planning Note for guidance on submitting a Planning Application earlier than at end of Stage 3

Submit Building Regulations Application

Discharge pre-commencement Planning Conditions

Prepare Construction Phase Plan

Submit form F10 to HSE if applicable

Carry out Construction Phase Plan

Comply with Planning Conditions related to construction

Comply with Planning Conditions as required

Comply with Planning Conditions as required

Procurement Route Traditional Tender

Appoint contractor

Design & Build 1 Stage ER CP Appoint

contractor

Design & Build 2 Stage ER Pre-contract services agreement CP Appoint

contractor

Management Contract Construction Management

Appoint contractor

Contractor-led ER Preferred bidder CP Appoint

contractor

Information Exchangesat the end of the stage

Client Requirements

Business Case

Project Brief

Feasibility Studies

Site Information

Project Budget

Project Programme

Procurement Strategy

Responsibility Matrix

Information Requirements

Project Brief Derogations

Signed off Stage Report

Project Strategies

Outline Specification

Cost Plan

Signed off Stage Report

Project Strategies

Updated Outline Specification

Updated Cost Plan

Planning Application

Manufacturing Information

Construction Information

Final Specifications

Residual Project Strategies

Building Regulations Application

Building Manual including Health and Safety File and Fire Safety Information

Practical Completion certificate including Defects List

Asset Information

If Verified Construction Information is required, verification tasks must be defined

Feedback on Project Performance

Final Certificate

Feedback from light touch Post Occupancy Evaluation

Feedback from Post Occupancy Evaluation

Updated Building Manual including Health and Safety File and Fire Safety Information as necessary

Core RIBA Plan of Work terms are defined in the RIBA Plan of Work 2020 Overview glossary and set in Bold Type. Further guidance and detailed stage descriptions are included in the RIBA Plan of Work 2020 Overview. © RIBA 2020

Stage Boundaries:Stages 0-4 will generally be undertaken one after the other.Stages 4 and 5 will overlap in the Project Programme for most projects.Stage 5 commences when the contractor takes possession of the site and finishes at Practical Completion. Stage 6 starts with the handover of the building to the client immediately after Practical Completion and finishes at the end of the Defects Liability Period.Stage 7 starts concurrently with Stage 6 and lasts for the life of the building.

Planning Note:Planning Applications are generally submitted at the end of Stage 3 and should only be submitted earlier when the threshold of information required has been met. If a Planning Application is made during Stage 3, a mid-stage gateway should be determined and it should be clear to the project team which tasks and deliverables will be required. See Overview guidance.

Procurement:The RIBA Plan of Work is procurement neutral – See Overview guidance for a detailed description of how each stage might be adjusted to accommodate the requirements of the Procurement Strategy.

ER Employer’s Requirements

CP Contractor’s Proposals

RIBAPlan of Work 2020

Appoint client team

Appoint design team

Appoint Facilities Management and Asset Management teams, and

strategic advisers as needed

Page 3: Modular Riser Flooring system

03www.ambar-kelly.com

Modular Riser Flooring system

Examples of RiserSafe® being installed on site and a visual inspection being made by our team:

Q. WHAT IS RISERSAFE®?

PATENTED CAST-IN SAFETY SYSTEM • Satisfies Joint COP ‘fire prevention on construction sites’• Provides maximum area for services to pass through• Individual pre-cut holes on floor plate with cover plates,

eliminating the need for main contractor to manage• Can be used as part of the M&E permanent fixing system• Shortens project programme• Lowers project costs• Reduces carbon footprint• Permanent maintenance flooring

RiserSafe® is protected by Ambar Kelly’s patent GB 2429021B

A. It is the building’s final maintenance platform which is simply cast in at the start of the project, eliminating the risk of falls and fire.

Page 4: Modular Riser Flooring system

04www.ambar-kelly.com

Modular Riser Flooring system

RISERSAFE® WORKS WITH ANY FRAME

3

STEEL FRAME CONCRETE FRAME AND POST TENSIONED

PRE-CAST PLANKS POST FIT

Cladding package

Scaffoldingpackage

Flooringpackage

Logisticspackage

Joinerypackage

Buildersworkspackage

Block workpackage

Raised access flooringpackage

Concrete frame package

Roofing package

Steel frame package

Mechanicalpackage

Ductingpackage

Electricalpackage

Sprinklerpackage

Dryliningpackage

Fire protectionpackage

Ceilingspackage

Risers

Prelims

Trade Interfaces

Page 5: Modular Riser Flooring system

05www.ambar-kelly.com

Modular Riser Flooring system

3D MODELLING BY OUR IN-HOUSE TEAM

The increased productivity on site is the result of pulling the multitude of designs from different disciplines into our model as part of the product detailing, reducing on site challenges and providing a smooth, efficient and safe construction process, where all the problems could be detailed out before they ever reach construction.

1. STEEL FRAME 2. UNITS POSITIONED ON STEEL FRAME NO MEP SERVICES

The 3D Model illustrations show when our team review the models received, which are plotted into our modelling system in collaboration with the designers of the building. They are adjusted so clashes are irradicated and do not occur during construction, reducing last minute issues, making installation faster, safer and more efficient.

3. SERVICES STARTING TO BE MODELLED THROUGH THE UNITS 4. SERVICES MODELLED THROUGH THE UNITS WITH SOME SPARE OPENINGS

Page 6: Modular Riser Flooring system

06

Modular Riser Flooring system

www.ambar-kelly.com

Units arrive on our FORS Gold lorry

Unit being landed Risersafe® Unit

THE INSTALLATION PROCESS

1. Deliver

2. Lift into place

Page 7: Modular Riser Flooring system

07

Modular Riser Flooring system

THE INSTALLATION PROCESS

www.ambar-kelly.com

Unit cast and bolted in position. The fire boarding has been placed around the fire wall beams ready for the walls to be built. Services are just starting to be installed.

Rebar surrounding Casting in unit with concrete

3. Cast into concrete

4. Leave it to do its thing. It’s that simple!

Page 8: Modular Riser Flooring system

08www.ambar-kelly.com

Modular Riser Flooring system

We incorporate the MEP requirements in conjunction with horizontal and vertical fire protection to meet the five standards that are associated with the riser shafts (zone). This has been proven to reduce construction time by up to two months.

MECHANICAL, ELECTRICAL AND PLUMBING (MEP)

RiserSafe® soakers to close off gaps between services and floor plate                                            

Page 9: Modular Riser Flooring system

09www.ambar-kelly.com

Modular Riser Flooring system

CREATES A BARRIER STOPPING THE SPREAD OF SMOKE AND FLAME

Modular riser flooring has been tested and proven to have a fire resistance to a 1000°C for 90 minutes with no loss of integrity during the test, demonstrating an excellent horizontal barrier to the spread of smoke and flame where used.

Building Research Establishment (BRE) fire testing of RiserSafe®

GRP grating RiserSafe®

Horizontal fire protection made simple

RiserSafe® meets the requirements of Approved Document B.

RiserSafe®, in combination with fire compound, recorded no failure in insulation or integrity whilst tested for over 2hrs .

Page 10: Modular Riser Flooring system

10www.ambar-kelly.com

Modular Riser Flooring system

VALUE V COST

The RiserSafe® system is not just a fall protection product, it is a 3D Modelled modular riser flooring system which reduces risk through design by incorporating all the following trade interfaces into one single option.

Therefore what appears an expensive entry price is actually an all-encompassing price fixed for the duration of the project.

The value is based on costs across the whole project, as identified above, providing a single solution with no hidden extras.

FRAME- Edge trim- Handrails- Shuttering- Striking

ROOFING- Upstand- Scaffold- Cowl

base

DRY LINING- Fire beams- GRP cuts- Single

workfaces- Re-support

GRP

GEN BUILD- Temp fire

doors required

- Temp locks required

- Single workfaces

– Water Ingress

BWIC- GRP hole

cut- Extra GRP

support- Fire

stopping not compatible

M&E- GRP hole

set out- Single

work fronts 50% less productive

SCAFFOLD- Extended

hire frame- Adaptions

for walls- Attendance

for adapts

£2,9000,000.00

£2,400,000.00

£1,900,000.00

£1,400,000.00

£900,000.00

£400,000.00

COST

Purchase Perception

Entry Price Exit Price

£827,029.72

£629,175.72

GRP ORTHO/ISO Resin (entry level) GRP PHENOLIC Resin

Actual GRP cost

Actual RiserSafe® cost£1,303,798.71

£1,967,506,44

£1,769,652.44

£1,303,798.71

RiserSafe® with 30% replacement

RiserSafe® cost at tender

Perceived GRP cost at tender

Page 11: Modular Riser Flooring system

11www.ambar-kelly.com

Modular Riser Flooring system

QUALITY CONTROL MANUFACTURING STANDARDS

CARBON NEUTRALITY

Ambar Kelly has worked with Carbon Footprint Limited to become a carbon neutral organisation.

We calculate the captured carbon content for every project and offset this, making our RiserSafe® offering carbon neutral to projects.

A Cradle-to-Grave Life-Cycle Assessment has been carried out on RiserSafe®, which is an assessment of the environmental impacts of our product during its life-cycle. It incorporates the analysis of raw materials, manufacture, transport, usage and disposal.

As part of our ongoing commitment to the environment, for every RiserSafe® unit that is manufactured, we calculate the captured carbon content and offset this value at the end of the project. Our customers are then provided with a certificate demonstrating this, which can be used towards environmental credentials for the overall scheme.

CE Marked and manufactured to Execution Class 2

Page 12: Modular Riser Flooring system

12www.ambar-kelly.com

Modular Riser Flooring system

LIST OF PROJECTS

• One Crown Place – 37 Floors• 70 St Mary Axe – 21 floors• Twickenham Stadium • One Angel Court – 20 floors• B Sky B – 4 floors• Barton Court – 3 Floors • Bohunt School – 1 Floor• Vauxhall Sky Gardens – 37 floors• Newfoundland – 58 floors• Triton Square – 10 floors• 245 Hammersmith – 10 floors• Nile Street – 29 floors• Principal Place – 50 floors• London Wall Place – 22 floors• Bloomberg – 10 floors• Twickenham Stadium• Papworth Hospital – 5 floors• 52 Lime Street – 37 floors• Tidal Basin – 23 floors• S1 – 12 floors• 3 Snowhill – 20 floors• Hampton by Hilton Hotel – 4 floors x 2• HCA Hospital – 6 floors • Derby Manor School – 2 floors• Strood School – 2 floors• Kemsley Energy Centre – 4 floors• Krishna Avanti Primary School – 2 floors• Imperial College – 13 floors• Riverside Ice & Leisure Centre – 2 floors• Beaulieu Park School – 2 floors• Valentine House – 10 floors• Dulwich Prep School – 2 floors• Royal Albert Dock – 8 floors• King’s School – 2 floors• Aberdeen Hotel & Conference Centre – 4 floors

• Chertsey High School – 2 floors• Avonmouth Energy Centre – 5 floors• Richmond College – 6 floors• King’s Cross R3 – 10 floors• St Bede’s School – 2 floors• Newcastle University – 5 floors• FitzWimarc School – 2 floors• Katherine Warrington School – 2 floors• Bank Station – 7 Sub floors• Golden Jubilee National Hospital – 1 floor• Mustard Wharf – 11 floors• Little Heath School – 2 floors (Won Considerate contractors award)

• Simon Langton School – 2 floors• Deer Park School – 2 floors• Chelsea Barracks – 4 floors• Tasman House – 7 floors• One The Square – 10 floors• Queen Anne Street – 5 floors• Fetter Lane – 8 floors• Verde – 12 floors• 73-89 Oxford Street – 7 floors• RAF Yeovilton – 1 floor• Project Wren – 4 floors• Forbury Place, Phase 1 – 10 floors• Forbury Place, Phase 2 – 10 floors• North Bristol Hospital – 4 floors• Derwen Vale School – 2 floors• London School of Economics – 14 floors• Pleckgate School – 3 floors• Regent Quarter – 6 floors• GSK B9 – 4 floors• Lister Hospital – 5 floors• Rild Exeter – 4 floors• Oldbury College – 4 floors

Page 13: Modular Riser Flooring system

013

Ambar Kelly Ltd,4a Bridgefields,Welwyn Garden City, Hertfordshire,AL7 1RX

T: 01707 324523 E: [email protected]