Page 1: MOM Report

MOM Report

Paul SolerMICE Operations Manager

University of Glasgow

MICOApril 4, 2011

Page 2: MOM Report

April 4, 2011 Commissioning Needs-Soler 2

Commissioning Needs•MICE shift 23/3/11

—Shift went well and most systems tested (see P. Hodgson’s report last week)

—However, BPM was not able to be tested

•Beam Position Monitor:—Contacted Pierrick Hanlet and Alan Bross to see what could

have been the problem—Discovered that HV was badly configured after EPICS tests —There are two CAEN SY127 crates (one on top of large

SY527 crate and one next to BPM) oThese need to be “daisy chained” but were notoSY127 cable connected to SY527 cable (which is at CAEN for repair)

oWith instructions from Pierrick, connected one SY127 to the other and terminated connections properly (however need to test)

Page 3: MOM Report

April 4, 2011 Commissioning Needs-Soler 3

Commissioning Needs•Henry removed MICE DAQ PCs from rack DAQ-04

—It includes: Grid data mover PC, "micestore", all miceacq* servers and DAQ KVM system.

—PCs are currently in R76—Old rack to be removed and new rack to be installed—Goal is to reinstall PCs around 14 April—Consequences:

o No data taking until reinstalled o KVM box has been removed - machines that connect through it will need to use a local keyboard and monitor (miceraid1&2; micecss1; micepps1; targetctl1).

o No backups of eLog, MICEmine, etc. (micestore removed)o Cannot test BPM again until system reinstalled

Page 4: MOM Report

April 4, 2011 Commissioning Needs-Soler 4

Commissioning Needs

•Beam Magnets:—Water leak in trench next to receiver fixed by John Govans—Q6 water remains off until access at the end of this ISIS

period

•Target in R78 —Ran successfully for 1147247 actuations—However, it kept on getting stuck—Ken stopped it on 1/4/11 at ~17:00.—Target will need to be dismantled for inspection to

understand why it is sticking

Page 5: MOM Report

April 4, 2011 Commissioning Needs-Soler 5

Commissioning Needs•Matt Hills is commissioning H2 system with cryostat— However, H2 line has developed leak: 0.73 mbar/hour— System shut down and leak to be fixed next week when Matt

returnsPressure H2 line (mbar) vs time (hrs)

P(mbar) = 0.7295 t(hrs) + 8.0631

0

10

20

30

40

50

60

70

0 20 40 60 80

Time (hours since 16:30 of 1/4/11)

Pre

ss

ure

(m

ba

r)

Page 6: MOM Report

April 4, 2011 Commissioning Needs-Soler 6

Run plan•ISIS schedule:

—1 March – 14 April 2011: ISIS runo15 April – 17 April 2011: machine physicso18 April – 1 May 2011: Easter shutdowno2 May – 8 May: run up and machine physicso 9 May 2011: machine permits

—10 May – 9 June 2011: ISIS runo10 June – 12 June 2011: machine physicso13 June – 26 June 2011: shutdowno27 June – 3 July: run up and machine physicso 4 July 2011: machine permits

—5 July – 4 August 2011: ISIS runo5 August – 7 August 2011: machine physicso8 August – 4 September 2011: shutdown? (subject to change)

•This Friday 8 April (12:30-13:30): Machine scheduling meeting (any requests?)