Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
EXTERNAL ENVIRONMENTAL MONITORING REPORT
Report on second phase (Semi-annual)
July, 2012
Project number: L2301-MON
MONGOLIA
URBAN DEVELOPMENT SECTOR PROJECT
BARUUN SALAA and ORBIT-TAHILT ROAD IMPROVEMENT
SUB-PROJECTS IN ULAANBAATAR
Prepared by Dr. Ochir Altansukh
for the Government of Mongolia and the Asian Development Bank.
Second report on external environmental monitoring
1
CURRENCY EQUIVALENTS
(as of July 19, 2012)
Currency Unit – Tugrug (MNT)
MNT 1.00 = $ 0.00074
$ 1.00 = MNT 1344.82
ABBREVIATIONS
ADB Asian Development Bank
DEIA Detailed Environmental Impact Assessment
DEIAR Detailed Environmental Impact Assessment Report
EAO Environmental Administration and Organization
EEM External Environmental Monitoring
EMaP Environmental Management Plan
EMM Environmental Mitigation Measure
EMoP Environmental Monitoring Plan
EP Environmental Protection
LSS Labor Safety and Security
MNET Ministry of Nature, Environment and Tourism
PIU Project Implementation Unit
PMU Project Management Unit
UB Ulaanbaatar
i. The fiscal year of the Government of Mongolia coincides with the calendar year.
ii. In this report, "T" refers to MNT.
Second report on external environmental monitoring
2
CONTENT
INTRODUCTION ....................................................................................................................................5
THE EXTERNAL MONITORING .........................................................................................................5
“UB-ORBIT-TAHILT” ROAD IMPROVEMENT SUB-PROJECT ......................................................7
Results of monitoring the implementation of environmental management plan..................................9
Results of monitoring the budget expenditure of the environmental monitoring plan .......................14
The result of environmental pollution monitoring .............................................................................18
Conclusion..........................................................................................................................................23
“UB-BARUUN SALAA” ROAD IMPROVEMENT SUB-PROJECT .................................................24
Results of monitoring the implementation of environmental management plan................................26
Results of monitoring the budget expenditure of environmental monitoring plan.............................31
The result of environmental pollution monitoring .............................................................................35
Conclusion..........................................................................................................................................40
RECOMMENDATION .........................................................................................................................41
Second report on external environmental monitoring
3
FIGURES
Figure 1. EEM program ...........................................................................................................................6
Figure 2. EEM schedule of an “UB-Orbit-Tahilt” road improvement sub-project ..................................7
Figure 3. The working schedule of the EEM ...........................................................................................7
Figure 4. Location of the start and end points of the road line and the worker’s camp ...........................8
Figure 5. Numerical and percentile expressions of the result ................................................................13
Figure 6. Numerical expression of the EMoP monitoring result............................................................17
Figure 7. Sampling points of environmental pollution monitoring “UB-Orbit-Tahilt” .........................18
Figure 8. AQMS-9000 mobile automatic system for air quality monitoring .........................................19
Figure 9. Soil quality sampling ..............................................................................................................20
Figure 10. EEM schedule of an “UB-Baruun salaa” road improvement sub-project.............................24
Figure 11. The working schedule of the EEM .......................................................................................24
Figure 12. Location of the start and end points of the road line and the worker’s camp .......................25
Figure 13. Numerical and percentile expressions of the result ..............................................................30
Figure 14. Numerical expression of the EMoP monitoring result..........................................................34
Figure 15. Sampling points of environmental pollution monitoring “UB-Orbit-Tahilt” .......................35
Figure 16. AQMS-9000 mobile automatic system for air quality monitoring .......................................36
Figure 17. Noise measurement ...............................................................................................................36
Figure 18. Soil quality sampling ............................................................................................................38
Second report on external environmental monitoring
4
TABLES
Table 1. The overall evaluation of environmental mitigation measures ..................................................6
Table 2. Location of the start and end points of the road line and the worker’s camp.............................8
Table 3. “UB-Orbit-Tahilt” EMaP monitoring – 2nd
phase ......................................................................9
Table 4. Results of the EMaP monitoring ..............................................................................................13
Table 5. “UB-Orbit-Tahilt” EMoP monitoring – 2nd
phase ...................................................................14
Table 6. Breakdown of the planned cost and its expenditure .................................................................17
Table 7. Sampling points of environmental pollution monitoring “UB-Orbit-Tahilt” ..........................18
Table 8. Results of air quality measurement – OT2 ...............................................................................19
Table 9. Results of air quality index – OT2 ...........................................................................................19
Table 10. Results of air quality measurement – OT4 .............................................................................19
Table 11. Results of air quality index – OT4 .........................................................................................20
Table 12. Results of soil quality analysis – OT1 ....................................................................................21
Table 13. Results of soil quality analysis – OT2 ....................................................................................21
Table 14. Results of soil quality analysis – OT3 ....................................................................................21
Table 15. Results of soil quality analysis – OT4 ....................................................................................22
Table 16. Location of the start and end points of the road line and the worker’s camp .........................25
Table 17. “UB-Baruun salaa” EMaP monitoring – 2nd
phase ................................................................26
Table 18. Results of the EMaP monitoring ............................................................................................30
Table 19. “UB-Baruun salaa” EMoP monitoring – 2nd
phase ................................................................31
Table 20. Breakdown of the planned cost and its expenditure ...............................................................34
Table 21. Sampling points of environmental pollution monitoring “UB-Baruun salaa” .......................35
Table 22. Results of air quality measurement – BS1 .............................................................................36
Table 23. Results of air quality index – BS1 ..........................................................................................37
Table 24. Results of noise measurement and index – BS2 ....................................................................37
Table 25. Results of noise measurement and index – BS3 ....................................................................37
Table 26. Results of noise measurement and index – BS4 ....................................................................37
Table 27. Results of air quality measurement – BS5 .............................................................................37
Table 28. Results of air quality index – BS5 ..........................................................................................37
Table 29. Results of soil quality analysis – BS1 ....................................................................................39
Table 30. Results of soil quality analysis – BS4 ....................................................................................39
Second report on external environmental monitoring
5
INTRODUCTION
According to contract number 03/2011 of the “Urban Development Sector” project for consultancy
service, which was made on the 1st of September 2011, the external environmental monitoring of
EMaP and EMoP, these are annexes of DEIAR, on eight sub-projects is being executed by Dr. Ochir
Altansukh and his assistant S.Munhnaran. The sub-projects are:
1. “UB-Hailaast” road improvement sub-project
2. “UB-Orbit-Tahilt” road improvement sub-project
3. “UB-Baruun salaa” road improvement sub-project
4. “UB-Botanic-Sharhad” road improvement sub-project
5. Water supply, sewage system and wastewater treatment plant improvement in Erdenet city,
Orhon aimag
6. Water supply, sewage system and wastewater treatment plant improvement in Altai city,
Govi-Altai aimag
7. Water supply, sewage system and wastewater treatment plant improvement in Bayanhongor
aimag
8. Water supply, sewage system and wastewater treatment plant improvement in Arvaiheer city,
Ovorhangai aimag
THE EXTERNAL MONITORING
The following two courses have been taken:
- Monitoring the implementation of the environmental management plan
- Monitoring the budget expenditure of the environmental monitoring plan
According to the agreement with PMU, EMaP and EMoP monitoring and environmental pollution
monitoring shall be executed three times on each sub-project.
1. Monitoring the implementation of EMaP and EMoP – 1 at the beginning of the project
2. Monitoring the implementation of EMaP and EMoP – 2 at the mid of the project
3. Monitoring the implementation of EMaP and EMoP – 3 at the end of the project
In this report, the second phase of the monitoring on two sub-projects of road improvement is
included. The EEM on “UB-Botanic-Sharhad” and “UB-Hailaast” sub-projects were not executed due
to the project delay and the project accomplishment in last year, respectively.
The EEM on UB road sub-projects followed the below-mentioned sequence. The entire process of
monitoring is divided into three main stages, and the following figure shown the activities in each
stage.
Second report on external environmental monitoring
6
Fie
ld p
hase
Desk
ph
ase
Pre
para
tio
n p
hase
EIA report reading and work planning based on EMaP, EMoP
Documentation collecting
Site visitation and monitoring the implementation of EMaP and EMoP
Data processing and report writing in Mongolian
Report writing in English and delivery of the report
Undertake lab analysis, if necessary
Questionnaire conducting, if necessary
By vocational organization and expert
Figure 1. EEM program
The following assessment is used for the overall evaluation of EEM on sub-projects.
Table 1. The overall evaluation of environmental mitigation measures
№ Percentage assessed
as satisfactory Evaluation Definition Consideration
1 90-100 А – very good Mitigation measures are
implemented well.
Implementation of a few
measures should be improved.
2 80-89 В – good
EMMs are implemented well,
but some of them are
deficient.
Implementation of deficient
measures should be improved.
3 70-79 С – average Some of the measures are
implemented are deficient.
Implementation of deficient
measures should be improved.
4 60-69 D – poor Most of the measures do not
meet requirements.
Implementation of the EMM
must be drastically improved.
5 0-59 F – very poor
Poor implementation of a
majority of the mitigation
measures.
The project should stop, and
implementation of the EMM
must improve drastically.
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
7
“UB-ORBIT-TAHILT” ROAD IMPROVEMENT SUB-PROJECT
According to the proposed plan, this project was started in September, 2010 and had to complete in
June, 2012. However, the project was extended by 3 months. The EEM will be executed in three
stages as mentioned below.
ID Task Name Start Finish20112010 2012
Oct SepMay JunJun MarFebJul NovMarJan Oct AprFeb MayDecNov DecApr JanAug
1
2
3
4
9/28/
2012
9/22/
2010The project duration
9/5/
2011
9/5/
2011
Monitoring the implementation of
EMaP and EMoP – 1
6/8/
2012
6/8/
2012
Monitoring the implementation of
EMaP and EMoP – 2
9/7/
2012
9/7/
2012
Monitoring the implementation of
EMaP and EMoP – 3
Jul Aug Sep
Figure 2. EEM schedule of an “UB-Orbit-Tahilt” road improvement sub-project
A working plan, a schedule and a monitoring program had been agreed upon with PMU in advance.
The second phase of EEM was performed on the 8th of June, 2012 collaboration with the contractor
“Hurdnii zam” Co., Ltd.
The external environmental monitoring specialist, Ochir Altansukh, and an assistant S.Munhnaran
were executing the EEM. An engineer of the contractor, N.Gandorj, an accountant, Gantuya and
workers were involved in the monitoring. It has been completed without any outside influence and by
following the below-mentioned schedule.
Working schedule of the EEM
Duration: 7 days in June, 2012
ID Task Name Start Duration FinishJun 2012
1198 10 126 7
1
2
3
4
5
6
6/6/20121d6/6/2012EIA report reading and work
planning based on EMaP, EMoP
6/7/20121d6/7/2012Documentation collecting
6/8/20121d6/8/2012Site visit and environmental
monitoring
6/10/20122d6/9/2012Data processing and report writing
in Mongolian
6/12/20122d6/11/2012Report writing in English and the
reports delivering
6/12/20127d6/6/2012Total days
Figure 3. The working schedule of the EEM
As shown by table 3, the monitoring has been executed using 43 measures, which are divided into nine
groups. 29 out of the 43 measures were mentioned in EMaP, EMoP and EAO. The remaining 14
measures were stated in the DEIAR.
1. Minimization and mitigation of adverse impact on air and its control
2. Minimization and mitigation of adverse impact on soil and its control
3. Minimization and mitigation of adverse impact on water and its control
4. Minimization and mitigation of adverse impact on the vegetation cover and its control
5. Minimization and mitigation of adverse impact from waste on the environment and its control
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
8
6. Minimization and mitigation of adverse impact from natural risks on the environment, its
control
7. Minimization and mitigation of adverse impact on the socio-economy and public, its control
8. Minimization and mitigation of labor safety and security risk and its control
9. Minimization and mitigation of environmental delict and its control
The implementation period of the mitigation measures has been divided into four different phases:
1. Beginning of the project 8 measures
2. Mid of the project 4 measures
3. End of the project 9 measures
4. During the project 26 measures
Eight measures out of 43 need to be implemented at the beginning of the project. 4, 9 and 26 measures
should be performed mid-project, at the project end, and during the project, respectively. That means
60% of the EMMs have to be conducted during the project implementation, which requires good EAO
of the contractor.
This monitoring was the 2nd
phase of EEM. Therefore, 6 measures, which have to be implemented at
the end of the project, and 3 measures, that belong to the specialist, were not monitored. According to
the EEM schedule, these 6 measures will be monitored in the 3rd
phase of EEM that is shown in figure
2. Therefore, the implementation of the EMaP of the contractor was evaluated by 34 actions, which
had to be implemented at the mid and during the project.
Hand-held GPS units were used for spatial referencing of the worker’s camp of the contractor and the
road line of “UB-Orbit-Tahilt” sub-project. The worker’s camp was located 25 meters from the road
line, which is the approved distance in the DEIAR.
Table 2. Location of the start and end points of the road line and the worker’s camp
№ Measured points Longitude Latitude Altitude Legend
1 Starting point 47054’55.28’’ 106
045’3.71’’ 1274 m А
2 Ending point 47056’9.7’’ 106
040’57.6’’ 1316 m В
3 Worker’s camp 47054’31.6’’ 106
042’52.9’’ 1280 m С
4 Quarry 47056’44.4’’ 106
039’8.0’’ 1395 m D
5 Temporary road 47055’15.97’’ 106
044’40.76’’ 1285 m E
Figure 4. Location of the start and end points of the road line and the worker’s camp
The worker’s camp should be located and surrounded by a fence 50 meters from the proposed road
line, according to the DEIAR. This was accomplished in practice. A table, showing the results of
monitoring the implementation of EMaP for this sub-project is presented on the next page.
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
9
RESULTS OF MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN
FOR THE “UB-ORBIT-TAHILT” ROAD IMPROVEMENT SUB-PROJECT
Table 3. “UB-Orbit-Tahilt” EMaP monitoring – 2nd
phase
* According to the report on DIEA
** 1, 2, 3, 4, 5th
columns of the table belong to the PIU and IA
Table reading:
1. Planned action The following actions have to be done by solely or collaboration between PIU and IA.
2. The report It tells you that which section of the report on DIEA and EMaP, EMoP, those are annexes of the report, mentioned the following actions.
3. Duration Indicating that when the following actions have to be done. During means the whole period of the project implementation.
4. Monitoring Showing that how the action implementations have been monitored.
5. Fact Presenting what evidence was the base of the conclusion of the action implementation.
6. Implementation Execution of the following actions concluded by three different marks, beneath, based on collected facts.
7. Explanation Background information on assessment of the action implementation was written in this column.
satisfactory incomplete unsatisfactory
№ Planned actions
1
The report
2
Duration
3
Monitoring
4
Fact
5
Implementation
6
Explanation
7
Minimization and mitigation of adverse impact on air, its control
1.
During the construction process, water and
moisturize soil to reduce dusting. EMaP-7
RDEIA-
6.1.3.3
During
Whether soil moisturizes by irrigation machinery,
pays water bills and made a contract with water
supply organization or not.
- Photo picture
- Irrigation machinery
- Questionary among locals
- Contract and bill
Satisfactory
Soil is moisturized.
ОТ1-4, 1-8, 1-9, ОТ2-1, 2-2, 2-3,
2-4
2.
Make a contract with an electric company and
supply electricity from the central station. EMaP-16
RDEIA-1.8 During
Whether electricity supplies from the central
station, a contract made with the organization,
and bills pay or not. - Photo picture Satisfactory
Electricity is supplied from the
central station.
ОТ1-10, 1-11, ОТ2-5
3. According to the EMoP, execute air quality
monitoring during the construction process.
EMaP-17
EMoP Mid
Whether the air monitoring research is executed
or not. Impossible to
assess
This action executes by the
specialist, not the IA.
Minimization and mitigation of adverse impact on soil, its control
4.
Remove, pile and keep a top layer of the soil in
the route of roadbed that is covering 5.82 ha
area.
EMaP-1
RDEIA-6.1.3
Beginning
or mid
Whether soil removed and piled in the specified
area or not. - Photo picture Satisfactory
Soil is removed and piled in the
specified area. ОТ1-12, 1-13
5. Introduce new technology related to removing
the topsoil with plant root and keep, reuse the
soil in rehabilitation activities.
EMaP-12 Beginning
or mid
Whether the new technology introduced and kept
or not. - Photo picture Incomplete It did not follow the technology.
ОТ1-12, 1-13
6.
Control the storage of fuel and lubricants,
prevent spilling of it and clean the area in case
of any leakages.
EMaP-8 During
Whether fuel and lubricants prevent from
spilling, if not the polluted area cleaned or not. - Observation
- Photo picture Satisfactory
The area for change lubricants is
prepared and so far, not spilled.
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
10
ОТ1-14, ОТ2-6, 2-7, 2-8
7.
Locate a technical repair place within 50 m
width from the proposed road line. RDEIA-1.8 During
Whether a technical repair place is located in
appropriate place or not. - Photo picture
- Measurement Satisfactory
The place is located in a camp,
and the camp is situated in 25 m
from the proposed road line.
ОТ1-15, 1-16
8. Do not create a new water channel and runoff
route during the bridge construction. RDEIA-2.2 During Whether a new water channel created or not. - Observation Satisfactory It not created. ОТ2-9
9.
Control the movement of vehicles, prevent from
creating unnecessary roadways, post road signs
where necessary.
RDEIA-
6.1.3.3 During
Whether the vehicle movement is controlled, and
road signs are posted or not. - Photo picture Unsatisfactory
Road signs are not posted, and
unnecessary earth roads created.
ОТ1-17, 1-18
10. Create earth roads as few as possible during the
project implementation and rehabilitate it at the
end of the project.
RDEIA-6.5.3 Mid and
ending
Whether unnecessary earth roads are created, if
yes the eroded areas rehabilitated at the end of
the project or not.
Irrelevant to
2nd phase
11. According to the EMoP, execute soil quality
monitoring.
EMaP-19
EMoP Ending
Whether the soil monitoring research is executed
or not. Impossible to
assess
This action executes by the
specialist, not the IA.
Minimization and mitigation of adverse impact on water, its control
12. Pay the water cost for any purpose, which uses
during project implementation based on a water
counter.
EMaP-14
RDEIA-6.2.3 During
Whether the water bill is paid based on the water
counter or not. - Bill Satisfactory Proved by bills. ОТ1-4
13. Water should provide from the nearest water-
supply system without drilling a new well. RDEIA-2.3.2 During
Whether a new well drilled and a water tank has
or not. - Photo picture
- Bill and note Satisfactory
Water is supplied from nearest
well. ОТ1-4, 1-8, 1-9
Minimization and mitigation of adverse impact on the vegetation cover, its control
14. According to the EMoP, execute rehabilitation
monitoring.
EMaP-18
EMoP Ending
Whether the necessary area rehabilitated, and the
monitoring research is executed or not. Impossible to
assess
This action executes by the
specialist, not the IA.
Minimization and mitigation of adverse impact from waste on environment, its control
15.
Strictly prohibit all kinds of waste, which create
during the project implementation, disposal
without control, deliver to the authorized site. EMaP-2 During
Whether wastes deliver to the authorized site and
made a contract with a vocational organization or
not.
- Photo picture
- Observation Satisfactory
No wastes in surrounding area
and wastes are delivered to the
authorized site. ОТ1-19, 1-20, 1-
21, ОТ2-10, 2-11-15
16.
Store used lubricants, which are hazardous
wastes from construction in a special sealed
container, build a temporary storage of it
according to standard, isolate it from the
environment and deliver used lubricants for
recycling.
EMaP-9, 10
RDEIA-6.2.3 During
Whether lubricants store in a sealed container, it
isolates from the environment, and it delivers for
the recycling. - Observation Unsatisfactory
No container, and deliver for the
recycling is questionable.
17. Properly remove soft materials of roadbed such
as soil that is unsuitable for construction. EMaP-3 During
Whether soft materials are removed properly or
not. - Photo picture Satisfactory
Soft materials are used for land
flattening. ОТ1-13, 1-22, 1-23
18.
Classify solid wastes; build temporary dump site
and monitor, whether the wastes are delivered to
the authorized site, if necessary, transport wastes
to the recycling place.
EMaP-15 During
Whether solid wastes are classified and delivered
to the authorized site or not. - Photo picture Incomplete
Solid wastes are classified and
kept in containers, but not
covered. ОТ1-19, 1-20, 1-21,
ОТ2-16
19. Locate a container for liquid waste, use mobile
toilets during the construction period and
EMaP-24
RDEIA-3.2.6 During
Whether the liquid waste is kept in a container,
mobile toilets are used and disposed of it to the - Photo picture Unsatisfactory No container, and dug a hole for
liquid waste disposal. ОТ1-21,
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
11
dispose of it to the authorized site. authorized site or not. ОТ2-17
20. Clean and collect solid wastes that are in the
project site and deliver to the authorized site. EMaP-11
RDEIA-3.1
Beginning
and ending
Whether solid wastes are cleaned and delivered
to the authorized site or not. - Photo picture Satisfactory
Solid wastes are cleaned. ОТ1-24,
1-25, 1-26, ОТ2-10, 2-11, 2-12, 2-
13, 2-14, 2-15
21. Control the safe disposal of a traditional sewage
system after the resettlement.
EMaP-4
RDEIA-6.2.3 Beginning
Whether a traditional sewage disposed of safely
or not. - Questionary among locals Satisfactory The sewages are disposed of
safely.
22. Do not dispose of waste in flood ditch and water
runoff route.
EMaP-23
RDEIA-6.2.3 During
Whether wastes are disposed of in a flood ditch
or not. - Observation Satisfactory Wastes are not disposed of in a
flood ditch. ОТ2-9
Minimization and mitigation of adverse impact from natural risks on environment, its control
23. Construct trenches for drainage in flood-prone
areas. RDEIA-7 Beginning
Whether trenches constructed in flood-prone
areas or not. - Photo picture Satisfactory
Trenches constructed. ОТ2-9
24. Plant and cover two sides of roadbed and
mountainside with top soil.
EMaP-5
RDEIA-6.3.3 Ending
Whether the places covered by top soil and
planted or not.
Irrelevant to
2nd phase
25. Shape and make small bench for making stable
mountainside, in west side of the roadbed. RDEIA-6.3.3 Ending
Whether a bench for stable mountainside made
and shaped or not.
26. Make a hillside that is not higher than 2 meters
in the east side of the roadbed. RDEIA-6.3.3 Ending
Whether a hillside with specified height made or
not.
Minimization and mitigation of adverse impact on the socio-economy and public, its control
27.
Notify people, including in risk persons such as
pregnant women, elders, neurotic, and with
respiratory disease in the impact zone before
construction and if necessary, make temporary
resettlement.
EMaP-13
RDEIA-6.5.3 Beginning
Whether notified people and resettled them or
not. - Questionary among locals Satisfactory
Examination has been done and
notified people.
ОТ1-33, 1-34, ОТ2-18, 2-19, 2-20
28. Prohibit to work during night time in settlement
area. EMaP-22 During
Whether they work in settlement area during
night time or not. - Questionary among locals Satisfactory
Proved by questionary among
locals.
29.
Locate machineries that use in the project,
within 50 m width from the proposed road line. RDEIA-1.8 During
Whether machineries are located in the specified
place or not. - Photo picture
- Measurement Satisfactory
The machineries are located in a
camp, and the camp is situated in
5 m from the proposed road line.
ОТ1-31, 1-32, 1-33, 1-34
30. To landscape of bus-stop. RDEIA-2.1 Ending Whether bus-stops landscaped or not.
Irrelevant to
2nd phase
31. Rehabilitate and landscape all necessary places,
where soil is influenced during the construction
at the end of the project.
EMaP-6 Ending
Whether the places rehabilitated and landscaped
at the end of the project or not.
32. Resettle and pay compensation to local people
who are settled in the proposed road line. RDEIA-2.2 Beginning
Whether people resettled, and compensation paid
or not. - Questionary among locals Satisfactory
The resettlement executed by
PMU according to law.
Minimization and mitigation of labor safety and security risk, its control
33. Shift electric line, which is in the proposed road.
RDEIA-1.8 Beginning Whether the electric lines shifted or not. - Work plan
- Photo picture Satisfactory
The electric lines shifted. ОТ1-36,
1-37
34. Provide a complete set of firefighting equipment
and check the expiry date of fire extinguishers.
EMaP-25
RDEIA-7 During
Whether firefighting equipment provided, and the
expiry date checked or not. - Photo picture Satisfactory Firefighting equipment is located
in the camp. ОТ1-40, ОТ2-21
35. Provide labor safety equipment such as EMaP-26 During Whether labor safety equipment is provided or - Observation Satisfactory Labor safety equipment is
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
12
earphones, eyeglasses and work clothes for
construction workers.
RDEIA-6.5.3 not. - Photo picture provided. ОТ1-41-43, ОТ2-22
36.
Organize training with a vocational organization
and introduce awareness-building measures on
prevention from risks of potential accidents to
the project staff.
EMaP-27
RDEIA-7 During
Whether a training organized, and awareness-
building measures are introduced to the project
staffs or not.
- Questionary among workers
- Photo picture Satisfactory
A regulation of LSS made and
training was organized. ОТ1-1, 1-
44, ОТ2-23, 2-24, 2-25, 2-38, 2-
39
37. Supply fuel from the nearest petrol station and it
should not reserve. RDEIA-1.8 During
Whether fuel is supplied from the nearest petrol
station and reserved or not. - Observation
- Bill Satisfactory
Fuel not reserved, and supplied by
a mobile station. ОТ1-3, ОТ2-26
38. Locate temporary buildings such as wagons
within 50 m width from the proposed road line. RDEIA-2.1 During
Whether the temporary buildings located in the
specified area or not. - Photo picture
- Measurement Satisfactory
The buildings are located in the
camp. ОТ1-45, ОТ2-27, 2-28
Minimization and mitigation of environmental delict, its control
39. Control the preparation of raw materials such as
sand, gravel and stones nearby river basin and
use sand, gravel and stones from licensed mines.
EMaP-20, 21 During
Whether the raw materials are supplied by
licensed mines or not. - Photo picture Satisfactory
The raw materials are supplied by
licensed mines. ОТ2-29, 2-30, 2-
31, 2-32, 2-33, 2-34, 2-35
40. Do not open a new quarry for supply of raw
materials for construction. EMaP-28
RDEIA-2.2 During
Whether a new quarry opened or not.
- Photo picture Satisfactory
A new quarry opened, and has a
license. ОТ2-29, 2-30, 2-31, 2-
32, 2-33, 2-34, 2-35
41.
Implement the environmental management plan,
make a regulation of environmental protection,
assign environmental responsibility to one of the
managerial staffs and s/he controls
implementation of the EMaP and EMoP.
EMaP-29
EAO-1 During
Whether the EMaP implements, a regulation
made and environmental responsibility assigned
or not. - Questionary among workers Unsatisfactory
Environmental responsibility not
assigned, and no plan. ОТ1-2
42.
Constantly implement the EMaP and EMoP,
report implementation of the environmental
actions to the MNET and environmentalist of
the District in every November and consult with
environmental expert.
EAO-2, 4 During
Whether it implements and reported to the
organization or not. Unsatisfactory
Information is inadequate, and no
report.
43.
Finance the environmental actions that were in
EMaP and EMoP, control its expense. EAO-3 During
Whether the economic issue of environmental
actions solved, and its expense is controlled or
not.
- EMaP and EMoP
- Financial report and bill Incomplete
The economic issue solved, but
financial information is
insufficient. ОТ1-3, 1-4, 1-5, 1-6,
1-7, ОТ2-36-...
29 out of aforesaid 43 actions were mentioned in EMaP, EMoP and EAO, remaining 14 actions were stated in the report of DEIA.
The monitoring results in the table are read as below.
A planned action 1:
The requirement in row 1 of this table is stated in 6.1.3.3 section of the DEIA report and 7th row of EMaP. It has to be done the whole period of the project implementation. It assessed as
“Satisfactory” by the auditing of an environmental external specialist based on aforesaid facts. The facts are enclosed in this report.
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
13
Three measures for air, soil, and rehabilitation monitoring out of all 43 measures of the EEM on “UB-
Orbit-Tahilt” road improvement sub-project will be executed by the external environmental
monitoring specialist, who was chosen by the PMU. Six measures out of 40 were irrelevant to the 2nd
phase. The remaining 34 measures should be implemented in the project time. Twenty six out of 34
measures were assessed as satisfactory. Three of them were evaluated as incomplete and 5 were
valued as unsatisfactory.
Table 4. Results of the EMaP monitoring
№ Assessment Count Percent
Air
So
il
Wat
er
Veg
etat
ion
Was
te
Nat
ura
l ri
sk
So
cio-e
con
om
y
and
pu
bli
c
Lab
or
safe
ty
Del
ict
1. Satisfactory 26 76,5 2 4 2 0 5 1 4 6 2
2. Incomplete 3 9 0 1 0 0 1 0 0 0 1
3. Unsatisfactory 5 14,5 0 1 0 0 2 0 0 0 2
Result of 2nd
phase 34 100 2 6 2 0 8 1 4 6 5
Irrelevant to the 2nd
phase 6 0 1 0 0 0 3 2 0 0
Impossible to assess 3 1 1 0 1 0 0 0 0 0
Overall 43 3 8 2 1 8 4 6 6 5
76.5% of 34 measures were assessed as satisfactory, 9% as incomplete, 14.5% evaluated as
unsatisfactory. There are shown in numerical and percentile expressions of the result. As shown in
table 4, for minimization and mitigation of adverse impact on soil, 4 were assessed as satisfactory, 1
was incomplete, one was evaluated as unsatisfactory and two were impossible to assess out of eight
measures. The results of other measures are shown in tables 3 and 4.
Figure 5. Numerical and percentile expressions of the result
26
3 5 9 0
5
10
15
20
25
30
Sat
isfa
cto
ry
Imco
mp
lete
Un
sati
sfac
tory
Impo
ssib
le t
o
asse
ss
Num
ber
Numerical expression of the the
result
76%
9%
15% 0%
Percentile expression of the result
Satisfactory
Imcomplete
Unsatisfactory
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
14
RESULTS OF MONITORING THE BUDGET EXPENDITURE OF THE ENVIRONMENTAL MONITORING PLAN
FOR THE “UB-ORBIT-TAHILT” ROAD IMPROVEMENT SUB-PROJECT
Table 5. “UB-Orbit-Tahilt” EMoP monitoring – 2nd
phase
* According to the report on DIEA
** 1, 2, 3, 4, 5th
columns of the table belong to the PIU and IA
Table reading:
1. Planned action The following actions have to be done by solely or collaboration between PIU and IA.
2. The report It tells you that which section of EMaP and EMoP, those are annexes of the report, mentioned the following actions.
3. Respondent Showing that who is responsible for the action.
4. Duration Indicating that when the following actions have to be done. During means the whole period of the project implementation.
5. Planned cost Amount of money, which was planned to spend for the action before the project.
6. Implementation Execution of the following actions concluded by three different marks, beneath, based on collected facts.
7. Actual cost Amount of money, which is spent for the action during the project.
8. Fact Presenting what evidence was the base of the conclusion of the action implementation.
9. Explanation Background information on assessment of the action implementation was written in this column.
satisfactory incomplete unsatisfactory
№ Planned actions
1
The report
2
Respondent
3
Duration
4
Planned cost, ₮
5
Implementation
6
Actual cost, ₮
7
Fact
8
Explanation
9
Minimization and mitigation of adverse impact on air, its control
1. During the construction process, water
and moisturize soil to reduce dusting.
Fill an irrigation machinery
EMaP-7 IA During
1 310 000
1 870 000 Satisfactory ОТ1 - 890 000
ОТ2 – 1 332 600
ОТ1-3
ОТ2-40-45
See 1st row of the
table on the action
monitoring results.
Transport 560 000
Moisturize -
2.
According to the EMoP, execute air
quality monitoring during the
construction process.
NO2
EMaP-17
EMoP
PIU
IA Mid
800 000
4 160 000 Impossible
to assess no no
This action executes by
the specialist, not the IA.
CO2 800 000
SO2 800 000
Dust 800 000
Noise 960 000
Total 6 030 000 2 222 600
Minimization and mitigation of adverse impact on soil, its control
3. Control the storage of fuel and lubricants, prevent spilling of it and
clean the area in case of any leakages. EMaP-8 IA Mid 70 000 70 000 Satisfactory no no Not spilled.
4. According to the EMoP, execute soil
quality monitoring.
Pb EMaP-19
EMoP
PIU
IA Ending
1 120 000 3 200 000
Impossible
to assess no no
This action executes by
the specialist, not the IA. Petroleum 1 280 000
Humus 800 000
Total 3 270 000 no
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
15
Minimization and mitigation of adverse impact on the vegetation cover, its control
5. According to the EMoP, execute
rehabilitation monitoring.
Growth of the planted vegetation
EMaP-18
EMoP
PIU
IA
Mid or
ending
20 000
110 000 Impossible
to assess no no
This action executes by
the specialist, not the IA.
Well growing species 20 000
Presence of weeds 20 000
Vegetation cover 20 000
Non-rehabilitated area 20 000
Perennial plant yield and height 10 000
Total 110 000 no
Minimization and mitigation of adverse impact from waste on environment, its control
6.
Strictly prohibit all kinds of waste,
which create during the project
implementation, disposal without
control, deliver to the authorized site.
Collect and temporary keep
waste. EMaP-2, 23 IA During
50 000
340 000 Satisfactory ОТ2 – 15 000 ОТ2-36-37 See 15th row of the table
on the action monitoring
results. Deliver to the authorized site 290 000
7.
Store used lubricants, which are hazardous wastes from construction
in a special sealed container, build a temporary storage of it according
to standard, isolate it from the environment and deliver used lubricants
for recycling.
EMaP-9, 10 IA During 30 000 30 000 Unsatisfactory no no No bills. See 16th row of
the table on the action
monitoring results.
8. Properly remove soft materials of
roadbed such as soil that is unsuitable
for construction.
Deliver to the authorized site EMaP-3 IA During
50 000 80 000 Satisfactory no no
No bills. See 17th row of
the table on the action
monitoring results. Give to the necessary person. 30 000
9. Clean and collect solid wastes that are
in the project site and deliver to the
authorized site.
Clean the area. EMaP-11 IA
Beginning
and ending
50 000 150 000 Satisfactory ОТ2 – 15 000 ОТ2-36-37
See 20th row of the table
on the action monitoring
results. Deliver to the authorized site 100 000
10. Control the safe disposal of a traditional sewage system after the
resettlement.
EMaP-4 IA Beginning 175 000 175 000 Satisfactory no no No bills. See 21st row of
the table on the action
monitoring results.
Total 775 000 15 000
Minimization and mitigation of adverse impact from natural risks on environment, its control
11. Plant and cover two sides of roadbed
and mountainside with top soil.
Cover the necessary places by
soil EMaP-5 IA Ending 80 000
580 000 Irrelevant to
2nd phase
Plant perennial vegetation 500 000
Total 580 000 no
Minimization and mitigation of adverse impact on the socio-economy and public, its control
12.
Notify people, including in risk persons
such as pregnant women, elders, neurotic,
and with respiratory disease in the impact
zone before construction and if necessary,
make temporary resettlement.
Notify people before the
construction EMaP-13
PIU
IA Beginning
150 000
1 150 000 Satisfactory ОТ2 – 20 000 ОТ2-46 See 27th row of the table
on the action monitoring
results. Prepare to the survey and
meeting 1 000 000
13. Rehabilitate and landscape all necessary
places, where soil is influenced during the
construction at the end of the project.
Clean the area
EMaP-6 IA Ending 100 000 100 000 Irrelevant to
2nd phase Rehabilitate and
landscape the area
Total 1 250 000 20 000
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
16
Minimization and mitigation of labor safety and security risk, its control
14. Provide a complete set of firefighting equipment and check the expiry
date of fire extinguishers. EMaP-25 IA During 50 000 50 000 Satisfactory no no No bills. See 34th row of
the table on the action
monitoring results.
15. Provide labor safety equipment such as earphones, eyeglasses and
work clothes for construction workers. EMaP-26 IA During 200 000 200 000 Satisfactory ОТ2 – 1 520 000 ОТ2-47-48 See 35th row of the table
on the action monitoring
results.
16. Organize training with a vocational organization and introduce
awareness-building measures on prevention from risks of potential
accidents to the project staff.
EMaP-27 IA During 150 000 150 000 Satisfactory no no No bills. See 36nd row of
the table on the action
monitoring results.
17. Collaborate with an environmental vocational organization for
implementation of EMaP and EMoP. EMaP-30 IA During 2 000 000 2 000 000 Unsatisfactory no no No collaboration
Total 2 400 000 1 520 000
Grand total 14 415 000
From this, for the environmental monitoring 7 470 000
From this, for IA 6 945 000 3 777 600
17 actions with the cost out of 30 actions were mentioned in EMaP, and EMoP, were written in this table. The remaining actions without the cost not belonged to this auditing.
The monitoring results in the table are read as below.
A planned action 1:
The requirement in row 1 of this table is stated in 7th
row of EMaP. It has to be done the whole period of the project implementation. The aforesaid cost was planned to spend for the action before
the project, and the actual cost was calculated based on bills. It assessed as “Satisfactory” by the auditing of an environmental external specialist based on the actual costs. This assessment is
only for cost auditing, not for implementation of environmental action. The facts are enclosed in this report and explanation of assessment was written in a last column of the report.
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
17
Seventeen measures with the cost out of 30 measures were written in the EMaP of the sub-project, and
a total of 14 415 000 T was planned to be spent. From that amount of money, 7 470 000 T had to be
spent for air, soil and rehabilitation monitoring research, as mentioned in EMoP. The pollution
monitoring will be executed by the specialist, who was chosen by the PMU. The EMoP says that the
remaining 6 945 000 T has to be spent for the rest of the measures, which should be implemented by
the contractor. The following table shows a breakdown of the planned costs that belong to the
contractor.
Table 6. Breakdown of the planned cost and its expenditure
№ Groups The cost
Planned Expenditure
1 Minimization and mitigation of adverse impact on air, its
control 1 870 000 2 222 600
2 Minimization and mitigation of adverse impact on soil, its
control 70 000 no
3 Minimization and mitigation of adverse impact on the
vegetation cover, its control no no
4 Minimization and mitigation of adverse impact from waste
on the environment, its control 775 000 15 000
5 Minimization and mitigation of adverse impact from natural
risks on the environment, its control 580 000 no
6 Minimization and mitigation of adverse impact on the socio-
economy and public, its control 1 250 000 20 000
7 Minimization and mitigation of labor safety and security
risk, its control 2 400 000 1 520 000
Total 6 945 000 3 777 600
Figure 6. Numerical expression of the EMoP monitoring result
As shown in the aforesaid table and figure, the contractor spent some of the planned cost in progress,
and some measures were executed by its internal resources without cost. For the following reasons, it
was impossible to evaluate the implementation of the EMM of the contractor based on the EMoP
0
500000
1000000
1500000
2000000
2500000
3000000
1 2 3 4 5 6 7
The
am
ount
of
mo
ney
Groups
The cost of EPA
Planned Expense
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
18
monitoring result. i) the planned cost was too general and unclear, ii) the cost was different than the
recent market price (maybe it is related to the time that the DEIA was made) and iii) in some cases; it
was not necessary to spend. For instance:
1. In the first row of the EMoP monitoring result, 2 222 600 T was spent out of the planned cost
for moisturizing. It means the contractor overspent the budget before the accomplishment of
the project. Maybe, it is related to the inflation.
2. In the second row of the EMoP monitoring result, the measure was impossible to assess, since
this measure should be implemented by the specialist, not the contractor.
3. In the third row of the EMoP monitoring result, although the contractor did not spend money,
it was assessed as satisfactory. Because of the case was not happened during the project term.
Thus, it is impossible to evaluate the implementation of the EMM of the contractor based on the
EMoP monitoring result. Also, we should consider the results of monitoring the implementation of
EMaP.
The result of environmental pollution monitoring
The environmental pollution monitoring has been executed in the area where the “UB-Orbit-Tahilt”
sub-project is implemented. The aim of this monitoring was to examine the impact of the sub-project
on the environment. The monitoring was conducted in the following two environs and executed by the
“Us-Orchin” Co Ltd., under the guidance of the specialist. Based on EMaP and EMoP, a work task has
been developed as follows:
1. Air quality
2. Soil quality
Table 7. Sampling points of environmental pollution monitoring “UB-Orbit-Tahilt”
№ Sampling points Longitude Latitude Altitude Legend
1 Soil quality sampling - 1 47°56'43,6" 106°39'6,2" 1383 m ОТ1
2 Soil quality sampling - 2
47°56'8,9" 106°40'57,5" 1303 m ОТ2 Air quality sampling - 1
3 Soil quality sampling - 3 47°54'31,1" 106°42'53,5" 1272 m ОТ3
4 Soil quality sampling - 4
47°54'44,6" 106°44'35,1" 1259 m ОТ4 Air quality sampling - 2
Figure 7. Sampling points of environmental pollution monitoring “UB-Orbit-Tahilt”
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
19
Air quality monitoring:
The monitoring has been done at the beginning and end of the new road in Orbit-Tahilt by AQMS-
9000 mobile automatic system and data from UB air quality monitoring stations in between 12-2 pm
on the 8th of June, 2012.
Figure 8. AQMS-9000 mobile automatic system for air quality monitoring
The monitoring was done for 30 minutes with a 10-minute frequency at the above-mentioned two
places. All parameters were measured three times, then averaged and compared with MNS 4585:2007.
In addition to this, the air-quality index was calculated.
Table 8. Results of air quality measurement – OT2
№ Measured parameters Unit Duration
Average Standard Difference Explanation 10‘ 20‘ 30‘
1 Sulfur dioxide SO2 µg/m3 6 3 12 7 450 0,01 unpolluted
2 Nitrogen dioxide NO2 µg/m3 12 18 32 21 85 0,25 unpolluted
3 Particulate matter PM10 µg/m3 15,36-120,3 86 100 0.86 unpolluted
4 Particulate matter PM2,5 µg/m3 3,80-47,43 35,6 50 0,71 unpolluted
5 Noise dB 66,1 66,1 60 1,10 polluted
Air quality measurement has been calculated with the air-quality index.
Table 9. Results of air quality index – OT2
Table 10. Results of air quality measurement – OT4
№ Measured parameters Unit Duration
Average Standard Difference Explanation 10‘ 20‘ 30‘
1 Sulfur dioxide SO2 µg/m3 5 16 25 15,3 450 0,03 unpolluted
2 Nitrogen dioxide NO2 µg/m3 23 47 68 46 85 0.54 unpolluted
3 Particulate matter PM10 µg/m3 16,50-110,35 89 100 0.89 unpolluted
4 Particulate matter PM2,5 µg/m3 12,15-87,54 45 50 0.90 unpolluted
5 Noise dB 59,6 59,6 60 0,99 unpolluted
№ Measured parameters Unit Average Standard Index Explanation
1 SO2 µg/m3 7 450 1 Very good
2 NO2 µg/m3 21 85 25 Very good
3 PM10 µg/m3 86 100 86 Good
4 PM2,5 µg/m3 35,6 50 71 Good
6 Noise dB 66,1 60 110 Average
Overall assessment - Average
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
20
Air quality measurement has been calculated with the air-quality index.
Table 11. Results of air quality index – OT4
Conclusion:
1. Based on a comparison with MNS 4585:2007, air quality at the end of the new road was
assessed as “unpolluted” except for noise pollution. According to the index assessment, the
evaluation was “average” due to noise excess.
2. Based on a comparison with MNS 4585:2007, all air-quality parameters at the beginning of
the new road were assessed as “unpolluted," meaning they did not exceed the permissible
level. According to the index assessment, it was evaluated as “good”.
3. However, the noise pollution was related to the high speed of the vehicles on the straight road.
Measurement of excess noise levels was measured casually very few times. Generally, the
surroundings area of the project is not polluted by noise.
4. In fact, there is impossible to accumulate air pollution when sources of air pollution are few,
the location is upwind, outside of the city and newly settled area.
Soil quality:
The monitoring has been done at the 4 places where the worker’s camp is situated; a quarry for raw
materials and along the road in Orbit-Tahilt in between 12-2 pm on 8th of June, 2012. 1 m
2 area on
each site, that might have been polluted, was selected for soil quality sampling. Five samples from
each site were taken by the grid method and then mixed them into one sample.
Figure 9. Soil quality sampling
In total, 14 parameters, including variables in the work task, were analyzed in the laboratory, and the
results compared to the MNS 5850:2008.
№ Measured parameters Unit Average Standard Index Explanation
1 SO2 µg/m3 15,3 450 3 Very good
2 NO2 µg/m3 46 85 54 Good
3 PM10 µg/m3 89 100 89 Good
4 PM2,5 µg/m3 45 50 90 Good
6 Noise dB 59,6 60 99 Good
Overall assessment - Good
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
21
Table 12. Results of soil quality analysis – OT1
Table 13. Results of soil quality analysis – OT2
Table 14. Results of soil quality analysis – OT3
№ Analyzed parameters Unit Result Standard Difference Explanation
1 Sand % 44,0 - - not mentioned in standard
2 Dirt % 42,4 - - not mentioned in standard
3 Clay % 13,6 - - not mentioned in standard
4 рН 1:2,5 7,31 - - not mentioned in standard
5 СаСО3 % 0,00 - - not mentioned in standard
6 Humus % 5,77 - - not mentioned in standard
7 ЕС2,5 dS/m 0,159 - - not mentioned in standard
8 Р2О5 mg/100g 2,49 - - not mentioned in standard
9 К2О mg/100g 18,6 - - not mentioned in standard
10 Chromium, Cr mg/kg 11,0 150 0,07 Unpolluted
11 Lead, Pb mg/kg 23,5 100 0,24 Unpolluted
12 Cadmium, Cd mg/kg 0,11 3 0,04 Unpolluted
13 Nickel, Ni mg/kg 3,8 150 0,03 Unpolluted
14 Zinc, Zn mg/kg 180,6 300 0,60 Unpolluted
№ Analyzed parameters Unit Result Standard Difference Explanation
1 Sand % 42,5 - - not mentioned in standard
2 Dirt % 45,4 - - not mentioned in standard
3 Clay % 12,1 - - not mentioned in standard
4 рН 1:2,5 7,84 - - not mentioned in standard
5 СаСО3 % 2,18 - - not mentioned in standard
6 Humus % 1,61 - - not mentioned in standard
7 ЕС2,5 dS/m 0,08 - - not mentioned in standard
8 Р2О5 mg/100g 1,02 - - not mentioned in standard
9 К2О mg/100g 12,4 - - not mentioned in standard
10 Chromium, Cr mg/kg 15,0 150 0,1 Unpolluted
11 Lead, Pb mg/kg 9,5 100 0,1 Unpolluted
12 Cadmium, Cd mg/kg 0,11 3 0,04 Unpolluted
13 Nickel, Ni mg/kg 5,6 150 0,04 Unpolluted
14 Zinc, Zn mg/kg 230,6 300 0,77 Unpolluted
№ Analyzed parameters Unit Result Standard Difference Explanation
1 Sand % 44,0 - - not mentioned in standard
2 Dirt % 42,4 - - not mentioned in standard
3 Clay % 13,6 - - not mentioned in standard
4 рН 1:2,5 8,32 - - not mentioned in standard
5 СаСО3 % 0,00 - - not mentioned in standard
6 Humus % 3,19 - - not mentioned in standard
7 ЕС2,5 dS/m 0,17 - - not mentioned in standard
8 Р2О5 mg/100g 2,15 - - not mentioned in standard
9 К2О mg/100g 18,3 - - not mentioned in standard
10 Chromium, Cr mg/kg 12,0 150 0,08 Unpolluted
11 Lead, Pb mg/kg 26,8 100 0,27 Unpolluted
12 Cadmium, Cd mg/kg 0,18 3 0,06 Unpolluted
13 Nickel, Ni mg/kg 7,6 150 0,05 Unpolluted
14 Zinc, Zn mg/kg 224,3 300 0,75 Unpolluted
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
22
Table 15. Results of soil quality analysis – OT4
Conclusion:
1. The soil has slightly eroded by human activity. However, the fertile soil has not disappeared.
The texture of soil is a sandy.
2. Texture and humus were not involved in the evaluation of quality, since these parameters can
be different in variety of places due to natural conditions.
3. Chromium, lead, cadmium, nickel and zinc did not exceed the permissible level, which was
mentioned in the standard. Therefore, there were assessed as “unpolluted”.
4. In fact, there is no condition to accumulate soil pollution when sources of soil pollution are
few and population density is low.
№ Analyzed parameters Unit Result Standard Difference Explanation
1 Sand % 42,5 - - not mentioned in standard
2 Dirt % 43,9 - - not mentioned in standard
3 Clay % 13,6 - - not mentioned in standard
4 рН 1:2,5 8,01 - - not mentioned in standard
5 СаСО3 % 0,51 - - not mentioned in standard
6 Humus % 2,83 - - not mentioned in standard
7 ЕС2,5 dS/m 0,118 - - not mentioned in standard
8 Р2О5 mg/100g 1,94 - - not mentioned in standard
9 К2О mg/100g 14,2 - - not mentioned in standard
10 Chromium, Cr mg/kg 23,0 150 0,15 Unpolluted
11 Lead, Pb mg/kg 45,6 100 0,46 Unpolluted
12 Cadmium, Cd mg/kg 0,17 3 0,06 Unpolluted
13 Nickel, Ni mg/kg 7,4 150 0,05 Unpolluted
14 Zinc, Zn mg/kg 222,5 300 0,74 Unpolluted
Second report on external environmental monitoring – “UB-Orbit-Tahilt” road improvement sub-project
23
CONCLUSION
The following conclusions have been drawn for the EMM regarding the “UB-Orbit-Tahilt” road
improvement sub-project based on the 2nd
phase of monitoring of EMaP and EMoP. Herein:
1. In total, 43 EMMs of the sub-project has been monitored. Forty out of the 43 measures should
be implemented by the contractor. Six out of 40 actions were irrelevant to the 2nd
phase.
Therefore, these were not monitored. The remaining 34 measures should be implemented in
the project time. Twenty six out of 34 measures were assessed as satisfactory, 3 of them were
evaluated as incomplete and 5 were valued as unsatisfactory. Therefore, we can conclude that
76.5% of the measures were assessed as satisfactory.
2. It was evaluated “F-very poor" at 1st phase. Since the environmental responsibility was
assigned to an engineer, and he has been done several actions according to the report on the
previous monitoring. Therefore, the overall evaluation of EMM of the contractor was
increased by 26.5% and evaluated as “C-average". In further, the activities which assessed
as incomplete and unsatisfactory, should improve.
3. According to the overall evaluation of EMM, the PMU can require the contractor to
improve environmental responsibility and implement EMM of the project.
4. For the contractor, five measures, those assessed as unsatisfactory, were related to the waste
management. Old ways of removing various kinds of waste, such as the use of landfills,
runoff, burning and blowing, should be replaced by more modern ways. It will drastically
improve the evaluation of EMM of the contractor.
5. The unassessable three measures for the monitoring research were not reflected in the overall
evaluation. Those will be implemented by the specialist, who was selected by the PMU.
6. Two measures, those assessed as unsatisfactory, were related to the environmental delict.
Thence, we can conclude that information about environmental management; finance is
inadequate and EAO of the contractor is weak.
7. One action on soil impact was assessed as unsatisfactory due to insufficient information about
a new technology and its process on DEIAR. The technology is related to removing the topsoil
with plant roots, and it was a new to the contractor.
8. There were created many unnecessary earth roads. Therefore, the contractor urgently needs to
post road signs where necessary.
9. It is necessary to collaborate with local administration for minimization and mitigation of
adverse impact on the socio-economy and public.
10. For the contractor, to pay attention to permanent usage of labor safety equipment and uniform.
11. The measures, those assessed as incomplete and unsatisfactory, can be improved by an
initiative of the contractor and collaboration between the PIU and the contractor.
12. So far, the overall actual expense was lower than the planned cost as shown in the result of
monitoring the budget expenditure of the EMoP.
13. According to the results of the environmental pollution monitoring, the project has a positive
impact on surrounding environment.
Recommendations, which were based on the conclusions and observations during the monitoring, are
written at the end of this report.
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
24
“UB-BARUUN SALAA” ROAD IMPROVEMENT SUB-PROJECT
According to the proposed plan, this project was started in September, 2010 and had to complete in
June, 2012. However, the project was extended by 3 months. The EEM will be executed in three
stages as mentioned below.
ID Task Name Start Finish2010 2011
OctOct AprAugNov Jan Mar MayDec JunJan FebJunMar
1
4
9/28/
2012
9/22/
2010The project duration
9/8/
2011
9/8/
2011
Monitoring the implementation of
EMaP and EMoP – 1
9/7/
2012
9/7/
2012
Monitoring the implementation of
EMaP and EMoP – 3 and
environmental pollution monitoring
3
2
6/8/
2012
6/8/
2012
Monitoring the implementation of
EMaP and EMoP – 2
2012
Dec NovFeb Apr SepJulMay Jul Aug Sep
Figure 10. EEM schedule of an “UB-Baruun salaa” road improvement sub-project
A working plan, a schedule and a monitoring program had been agreed upon with PMU in advance.
The second phase of EEM was performed on the 8th of June, 2012 collaboration with the contractor
“Xotiin zam” Co., Ltd.
The external environmental monitoring specialist, Ochir Altansukh, and an assistant S.Munhnaran
were executing the EEM. An environmental and internal affair manager of the contractor,
D.Narangerel, an engineer, B.Hadaa, an accountant, U.Sodov and workers were involved in the
monitoring. It has been completed without any outside influence and by following the below-
mentioned schedule.
Working schedule of the EEM
Duration: 7 days in June, 2011
ID Task Name Start Duration FinishJun 2012
1186 7 10 129
1
2
3
4
5
6
6/6/20121d6/6/2012EIA report reading and work
planning based on EMaP, EMoP
6/7/20121d6/7/2012Documentation collecting
6/8/20121d6/8/2012Site visit and environmental
monitoring
6/10/20122d6/9/2012Data processing and report writing
in Mongolian
6/12/20122d6/11/2012Report writing in English and the
reports delivering
6/12/20127d6/6/2012Total days
Figure 11. The working schedule of the EEM
As shown by table 17, the monitoring has been executed using 43 measures, which are divided into
nine groups. 29 out of the 43 measures were mentioned in EMaP, EMoP and EAO. The remaining 14
measures were stated in the DEIAR.
1. Minimization and mitigation of adverse impact on air and its control
2. Minimization and mitigation of adverse impact on soil and its control
3. Minimization and mitigation of adverse impact on water and its control
4. Minimization and mitigation of adverse impact on the vegetation cover and its control
5. Minimization and mitigation of adverse impact from waste on the environment and its control
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
25
6. Minimization and mitigation of adverse impact from natural risks on the environment and its
control
7. Minimization and mitigation of adverse impact on the socio-economy and public, its control
8. Minimization and mitigation of labor safety and security risk and its control
9. Minimization and mitigation of environmental delict and its control
The implementation period of the mitigation measures has been divided into four different phases:
1. Beginning of the project 8 measures
2. Mid of the project 4 measures
3. End of the project 9 measures
4. During the project 26 measures
Eight measures out of 43 need to be implemented at the beginning of the project. 4, 9 and 26 measures
should be performed mid-project, at the project end, and during the project, respectively. That means
60% of the EMMs have to be conducted during the project implementation, which requires good EAO
of the contractor.
This monitoring was the 2nd
phase of EEM. Therefore, 6 measures, which have to be implemented at
the end of the project, and 3 measures, that belong to the specialist, were not monitored. According to
the EEM schedule, these 6 measures will be monitored in the 3rd
phase of EEM that is shown in figure
10. Therefore, the implementation of the EMaP of the contractor was evaluated by 34 measures, which
had to be implemented at the mid and during the project.
Hand-held GPS units were used for spatial referencing of the worker’s camp of the contractor and the
road line of “UB-Baruun salaa” sub-project. The worker’s camp was located 10 meters from the road
line, which is the approved distance in the DEIAR.
Table 16. Location of the start and end points of the road line and the worker’s camp
№ Measured points Longitude Latitude Altitude Legend
1 Starting point 47057’24.5’’ 106
049’33.5’’ 1348 m А
2 Ending point 47059’16.2’’ 106
048’06.8’’ 1406 m В
3 Worker’s camp 47058’0.0’’ 106
048’50.7’’ 1349 m С
Figure 12. Location of the start and end points of the road line and the worker’s camp
The worker’s camp should be located and surrounded by a fence 50 meters from the proposed road
line, according to the DEIAR. This was accomplished in practice. A table, showing the results of
monitoring the implementation of EMaP for this sub-project is presented on the next page.
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
26
RESULTS OF MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT PLAN
FOR THE “UB-BARUUN SALAA” ROAD IMPROVEMENT SUB-PROJECT
Table 17. “UB-Baruun salaa” EMaP monitoring – 2nd
phase
* According to the report on DIEA
** 1, 2, 3, 4, 5th
columns of the table belong to the PIU and IA
Table reading:
1. Planned action The following actions have to be done by solely or collaboration between PIU and IA.
2. The report It tells you that which section of the report on DIEA and EMaP, EMoP, those are annexes of the report, mentioned the following actions.
3. Duration Indicating that when the following actions have to be done. During means the whole period of the project implementation.
4. Monitoring Showing that how the action implementations have been monitored.
5. Fact Presenting what evidence was the base of the conclusion of the action implementation.
6. Implementation Execution of the following actions concluded by three different marks, beneath, based on collected facts.
7. Explanation Background information on assessment of the action implementation was written in this column.
satisfactory incomplete unsatisfactory
№ Planned actions
1
The report
2
Duration
3
Monitoring
4
Fact
5
Implementation
6
Explanation
7
Minimization and mitigation of adverse impact on air, its control
1.
During the construction process, water and
moisturize soil to reduce dusting. EMaP-7
RDEIA-
6.1.3.3
During
Whether soil moisturizes by irrigation
machinery, pays water bills and made a contract
with water supply organization or not.
- Photo picture
- Irrigation machinery
- Questionary among locals
- Contract and bill
Satisfactory
Soil is moisturized by irrigation
machinery. Бс1-4, 1-7, 1-8, 1-
38, Бс2-1, 2-2
2.
Make a contract with an electric company and
supply electricity from the central station. EMaP-16
RDEIA-1.8 During
Whether electricity supplies from the central
station, a contract made with the organization,
and bills pay or not.
- Contract
- Bill
- Photo picture
Satisfactory
Electricity is supplied from the
central station.
Бс1-2, 1-9, 1-10, 1-38, Бс2-3
3. According to the EMoP, execute air quality
monitoring during the construction process.
EMaP-17
EMoP Mid
Whether the air monitoring research is executed
or not. Impossible to
assess
This action executes by the
specialist, not the IA.
Minimization and mitigation of adverse impact on soil, its control
4.
Remove, pile and keep a top layer of the soil in
the route of roadbed that is covering 2.87 ha
area.
EMaP-1
RDEIA-6.1.3
Beginning
or mid
Whether soil removed and piled in the specified
area or not. - Photo picture Satisfactory
Soil is removed and piled in the
specified area. Бс1-13, Бс2-4
5. Introduce new technology related to removing
the topsoil with plant root and keep, reuse the
soil in rehabilitation activities.
EMaP-12 Beginning
or mid
Whether the new technology introduced and kept
or not. - Photo picture Incomplete It did not follow the technology.
Бс1-13, Бс2-4
6.
Control the storage of fuel and lubricants,
prevent spilling of it and clean the area in case of
any leakages.
EMaP-8 During
Whether fuel and lubricants prevent from
spilling, if not the polluted area cleaned or not. - Observation
- Photo picture Unsatisfactory
There is not the area for change
lubricants and spilled. Бс2-5
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
27
7.
Locate a technical repair place within 50 m
width from the proposed road line. RDEIA-1.8 During
Whether a technical repair place is located in
appropriate place or not. - Photo picture
- Measurement Satisfactory
The place is located in a camp,
and the camp is situated in 5 m
from the proposed road line.
Бс1-15, Бс2-6, 2-7
8. Do not create a new water channel and runoff
route during the bridge construction. RDEIA-2.2 During Whether a new water channel created or not. - Observation Satisfactory It not created.
9.
Control the movement of vehicles, prevent from
creating unnecessary roadways, post road signs
where necessary.
RDEIA-
6.1.3.3 During
Whether the vehicle movement is controlled, and
road signs are posted or not. - Photo picture Satisfactory
Road signs are posted, and
groove made in necessary
places. Бс1-17, 1-18, 1-19, 1-
20, Бс2-8, 2-9, 2-10-11
10. Create earth roads as few as possible during the
project implementation and rehabilitate it at the
end of the project.
RDEIA-6.5.3 Mid and
ending
Whether unnecessary earth roads are created, if
yes the eroded areas rehabilitated at the end of
the project or not.
Irrelevant to
2nd phase
11. According to the EMoP, execute soil quality
monitoring.
EMaP-19
EMoP Ending
Whether the soil monitoring research is executed
or not. Impossible to
assess
This action executes by the
specialist, not the IA.
Minimization and mitigation of adverse impact on water, its control
12. Pay the water cost for any purpose, which uses
during project implementation based on a water
counter.
EMaP-14
RDEIA-6.2.3 During
Whether the water bill is paid based on the water
counter or not. - Bill Satisfactory Water is supplied from the
nearest well. Бс1-38
13. Water should provide from the nearest water-
supply system without drilling a new well. RDEIA-2.3.2 During Whether a new well drilled and a water tank has
or not. - Photo picture
- Bill Satisfactory
A new well is not drilled.
Бс1-4, 1-21, 1-38, Бс2-12
Minimization and mitigation of adverse impact on the vegetation cover, its control
14. According to the EMoP, execute rehabilitation
monitoring.
EMaP-18
EMoP Ending
Whether the necessary area rehabilitated, and the
monitoring research is executed or not. Impossible to
assess
This action executes by the
specialist, not the IA.
Minimization and mitigation of adverse impact from waste on environment, its control
15. Strictly prohibit all kinds of waste, which create
during the project implementation, disposal
without control, deliver to the authorized site.
EMaP-2 During
Whether wastes deliver to the authorized site and
made a contract with a vocational organization
or not.
- Photo picture
- Observation Satisfactory
Wastes are collected in one
place and delivered to the
authorized site. Бс1-6
16.
Store used lubricants, which are hazardous
wastes from construction in a special sealed
container, build a temporary storage of it
according to standard, isolate it from the
environment and deliver used lubricants for
recycling.
EMaP-9, 10
RDEIA-6.2.3 During
Whether lubricants store in a sealed container, it
isolates from the environment, and it delivers for
the recycling. - Questionary among workers Satisfactory
Lubricants are stored in a sealed
container, and it delivers for the
recycling.
17. Properly remove soft materials of roadbed such
as soil that is unsuitable for construction. EMaP-3 During
Whether soft materials are removed properly or
not. - Photo picture Satisfactory
Soft materials are used for land
flattening. Бс1-35, Бс2-31
18.
Classify solid wastes; build temporary dump site
and monitor, whether the wastes are delivered to
the authorized site, if necessary, transport wastes
to the recycling place.
EMaP-15 During
Whether solid wastes are classified and delivered
to the authorized site or not. - Photo picture Unsatisfactory
Solid wastes are not classified
and no container. Бс1-22, 1-23,
Бс2-13
19. Locate a container for liquid waste, use mobile
toilets during the construction period and dispose
of it to the authorized site.
EMaP-24
RDEIA-3.2.6 During
Whether the liquid waste is kept in a container,
mobile toilets are used and disposed of it to the
authorized site or not. - Photo picture Unsatisfactory
No container, and dug a hole for
liquid waste disposal. Бс1-22,
1-23, 1-31, Бс2-14
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
28
20. Clean and collect solid wastes that are in the
project site and deliver to the authorized site. EMaP-11
RDEIA-3.1
Beginning
and ending
Whether solid wastes are cleaned and delivered
to the authorized site or not. - Photo picture
- Questionary among locals Satisfactory
Solid wastes are cleaned and
delivered to the authorized site.
Бс1-6, 1-25, Бс2-15
21. Control the safe disposal of a traditional sewage
system after the resettlement.
EMaP-4
RDEIA-6.2.3 Beginning
Whether a traditional sewage disposed of safely
or not. - Questionary among locals Satisfactory The sewages are disposed of
safely.
22. Do not dispose of waste in flood ditch and water
runoff route.
EMaP-23
RDEIA-6.2.3 During
Whether wastes are disposed of in a flood ditch
or not. - Observation Satisfactory Wastes are not disposed of in a
flood ditch.
Minimization and mitigation of adverse impact from natural risks on environment, its control
23. Construct trenches for drainage in flood-prone
areas. RDEIA-7 Beginning Whether trenches constructed in flood-prone
areas or not. - Photo picture Satisfactory Trenches are constructed.
Бс1-25, Бс2-16
24. Plant and cover two sides of roadbed and
mountainside with top soil.
EMaP-5
RDEIA-6.3.3 Ending
Whether the places covered by top soil and
planted or not.
Irrelevant to
2nd phase
25. Shape and make small bench for making stable
mountainside, in west side of the roadbed. RDEIA-6.3.3 Ending
Whether a bench for stable mountainside made
and shaped or not.
26. Make a hillside that is not higher than 2 meters
in the east side of the roadbed. RDEIA-6.3.3 Ending
Whether a hillside with specified height made or
not.
Minimization and mitigation of adverse impact on the socio-economy and public, its control
27.
Notify people, including in risk persons such as
pregnant women, elders, neurotic, and with
respiratory disease in the impact zone before
construction and if necessary, make temporary
resettlement.
EMaP-13
RDEIA-6.5.3 Beginning
Whether notified people and resettled them or
not.
- Questionary among locals
- Handouts Satisfactory
They organized several meeting
with people, collaborating with
local administration. A
presentation posted in the
administration house.
Бс1-33, 1-34, Бс2-17
28. Prohibit to work during night time in settlement
area. EMaP-22 During
Whether they work in settlement area during
night time or not. - Questionary among locals Satisfactory
Proved by questionary among
locals.
29.
Locate machineries that use in the project, within
50 m width from the proposed road line. RDEIA-1.8 During
Whether machineries are located in the specified
place or not. - Photo picture
- Measurement Satisfactory
The machineries are located in a
camp, and the camp is situated
in 5 m from the proposed road
line. Бс1-26, Бс2-18, 2-19, 2-20
30. To landscape of bus-stop. RDEIA-2.1 Ending Whether bus-stops landscaped or not.
Irrelevant to
2nd phase
31. Rehabilitate and landscape all necessary places,
where soil is influenced during the construction
at the end of the project.
EMaP-6 Ending
Whether the places rehabilitated and landscaped
at the end of the project or not.
32. Resettle and pay compensation to local people
who are settled in the proposed road line. RDEIA-2.2 Beginning
Whether people resettled, and compensation paid
or not. - Questionary among locals Satisfactory
The resettlement executed by
PMU according to law. Бс1-5
Minimization and mitigation of labor safety and security risk, its control
33. Shift electric line, which is in the proposed road. RDEIA-1.8 Beginning Whether the electric lines shifted or not. - Questionary Satisfactory The electric lines shifted.
34.
Provide a complete set of firefighting equipment
and check the expiry date of fire extinguishers. EMaP-25
RDEIA-7 During
Whether firefighting equipment provided, and
the expiry date checked or not. - Photo picture Incomplete
Firefighting equipment
provided, but not complete.
Бс1-27, Бс2-21, 2-22
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
29
35. Provide labor safety equipment such as
earphones, eyeglasses and work clothes for
construction workers.
EMaP-26
RDEIA-6.5.3 During
Whether labor safety equipment is provided or
not. - Observation
- Photo picture Satisfactory
Labor safety equipment is
provided. Бс1-28, 1-38, Бс2-23,
2-24
36.
Organize training with a vocational organization
and introduce awareness-building measures on
prevention from risks of potential accidents to
the project staff.
EMaP-27
RDEIA-7 During
Whether a training organized, and awareness-
building measures are introduced to the project
staffs or not. - Plan
- Questionary among workers Satisfactory
A regulation of LSS made, and
it is introduced in every
morning before the work.
Бс1-29, 1-30, 1-36, Бс2-25, 2-
26, 2-27, 2-28, 2-29, 2-30
37. Supply fuel from the nearest petrol station and it
should not reserve. RDEIA-1.8 During
Whether fuel is supplied from the nearest petrol
station and reserved or not. - Observation
- Bill Satisfactory
Fuel not reserved, and supplied
by a mobile station. Бс1-38
38. Locate temporary buildings such as wagons
within 50 m width from the proposed road line. RDEIA-2.1 During
Whether the temporary buildings located in the
specified area or not. - Photo picture
- Measurement Satisfactory
The buildings are located in the
camp. Бс1-24, 1-26, Бс2-19
Minimization and mitigation of environmental delict, its control
39. Control the preparation of raw materials such as
sand, gravel and stones nearby river basin and
use sand, gravel and stones from licensed mines.
EMaP-20, 21 During
Whether the raw materials are supplied by
licensed mines or not. - Bill Satisfactory
The raw materials are supplied
by licensed mines Бс1-38, Бс2-
18
40.
Do not open a new quarry for supply of raw
materials for construction. EMaP-28
RDEIA-2.2 During
Whether a new quarry opened or not.
- Bill
- Photo picture Satisfactory
A new quarry did not open and
raw materials are supplied by
licensed mines. Бс1-37, 1-38,
Бс2-18
41.
Implement the environmental management plan,
make a regulation of environmental protection,
assign environmental responsibility to one of the
managerial staffs and s/he controls
implementation of the EMaP and EMoP.
EMaP-29
EAO-1 During
Whether the EMaP implements, a regulation
made and environmental responsibility assigned
or not. - Work contract Satisfactory
Environmental responsibility
assigned to a manager. Бс1-3
42.
Constantly implement the EMaP and EMoP,
report implementation of the environmental
actions to the MNET and environmentalist of the
District in every November and consult with
environmental expert.
EAO-2, 4 During
Whether it implements and reported to the
organization or not. Unsatisfactory
Information is inadequate, and
no report.
43.
Finance the environmental actions that were in
EMaP and EMoP, control its expense. EAO-3 During
Whether the economic issue of environmental
actions solved, and its expense is controlled or
not.
- EMaP and EMoP
- Financial plan
- Financial report and bill
Satisfactory
The economic issue solved, and
expenses are controlled.
Бс1-1, 1-38
29 out of aforesaid 43 actions were mentioned in EMaP, EMoP and EAO, remaining 14 actions were stated in the report of DEIA.
The monitoring results in the table are read as below.
A planned action 1:
The requirement in row 1 of this table is stated in 6.1.3.3 section of the DEIA report and 7th row of EMaP. It has to be done the whole period of the project implementation. It assessed as
“Satisfactory” by the auditing of an environmental external specialist based on aforesaid facts. The facts are enclosed in this report.
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
30
Three measures for air, soil, and rehabilitation monitoring out of all 43 measures of the EEM on “UB-
Baruun salaa” road improvement sub-project will be executed by the external environmental
monitoring specialist, who was chosen by the PMU. Six measures out of 40 were irrelevant to the 2nd
phase. The remaining 34 measures should be implemented in the project time. Twenty eight out of 34
measures were assessed as satisfactory. Two of them were evaluated as incomplete and 4 were valued
as unsatisfactory.
Table 18. Results of the EMaP monitoring
№ Assessment Count Percent
Air
So
il
Wat
er
Veg
etat
ion
Was
te
Nat
ura
l ri
sk
So
cio-e
con
om
y
and
pu
bli
c
Lab
or
safe
ty
Del
ict
1. Satisfactory 28 82 2 4 2 0 6 1 4 5 4
2. Incomplete 2 6 0 1 0 0 0 0 0 1 0
3. Unsatisfactory 4 12 0 1 0 0 2 0 0 0 1
Result of 2nd
phase 34 100 2 6 2 0 8 1 4 6 5
Irrelevant to the 2nd
phase 6 0 1 0 0 0 3 2 0 0
Impossible to assess 3 1 1 0 1 0 0 0 0 0
Overall 43 3 8 2 1 8 4 6 6 5
82% of 34 measures were assessed as satisfactory, 6% as incomplete, 12% evaluated as unsatisfactory.
There are shown in numerical and percentile expressions of the result. As shown in table 18, for
minimization and mitigation of adverse impact on soil, four were assessed as satisfactory, one was
incomplete, one was evaluated as unsatisfactory and two were impossible to assess out of eight
measures. The results of other measures are shown in tables 17 and 18.
Figure 13. Numerical and percentile expressions of the result
28
2 4 9 0
5
10
15
20
25
30
Sat
isfa
cto
ry
Inco
mp
lete
Un
sati
sfac
tory
Impo
ssib
le t
o
asse
ss
Num
ber
Numerical expression of the the
result
82%
6%
12%
Percentile expression of the result
Satisfactory
Incomplete
Unsatisfactory
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
31
RESULTS OF MONITORING THE BUDGET EXPENDITURE OF ENVIRONMENTAL MONITORING PLAN
FOR THE “UB-BARUUN SALAA” ROAD IMPROVEMENT SUB-PROJECT
Table 19. “UB-Baruun salaa” EMoP monitoring – 2nd
phase
* According to the report on DIEA
** 1, 2, 3, 4, 5th
columns of the table belong to the PIU and IA
Table reading:
1. Planned action The following actions have to be done by solely or collaboration between PIU and IA.
2. The report It tells you that which section of EMaP and EMoP, those are annexes of the report, mentioned the following actions.
3. Respondent Showing that who is responsible for the action.
4. Duration Indicating that when the following actions have to be done. During means the whole period of the project implementation.
5. Planned cost Amount of money, which was planned to spend for the action before the project.
6. Implementation Execution of the following actions concluded by three different marks, beneath, based on collected facts.
7. Actual cost Amount of money, which is spent for the action during the project.
8. Fact Presenting what evidence was the base of the conclusion of the action implementation.
9. Explanation Background information on assessment of the action implementation was written in this column.
satisfactory incomplete unsatisfactory
№ Planned actions
1
The report
2
Respondent
3
Duration
4
Planned cost, ₮
5
Implementation
6
Actual cost, ₮
7
Fact
8
Explanation
9
Minimization and mitigation of adverse impact on air, its control
1. During the construction process, water
and moisturize soil to reduce dusting.
Fill an irrigation machinery
EMaP-7 IA During
1 090 000
1 180 000 Satisfactory Бс1 - 3 781 770
Бс2 – 500 000
Бс1-38, 59-61
Бс2-32
See 1st row of the
table on the action
monitoring results.
Transport 90 000
Moisturize -
2.
According to the EMoP, execute air
quality monitoring during the
construction process.
NO2
EMaP-17
EMoP
PIU
IA Mid
400 000
2 320 000 Impossible to
assess no no
This action executes
by the specialist, not
the IA.
CO2 400 000
SO2 400 000
Dust 400 000
Noise 720 000
Total 3 500 000 4 281 770
Minimization and mitigation of adverse impact on soil, its control
3. Control the storage of fuel and lubricants, prevent spilling of it and
clean the area in case of any leakages. EMaP-8 IA Mid 60 000 60 000 Satisfactory no no Not spilled.
4. According to the EMoP, execute soil
quality monitoring.
Pb EMaP-19
EMoP
PIU
IA Ending
560 000
1 600 000 Impossible to
assess no no
This action executes
by the specialist, not
the IA. Petroleum 640 000
Humus 400 000
Total 1 660 000 no
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
32
Minimization and mitigation of adverse impact on the vegetation cover, its control
5.
According to the EMoP,
execute rehabilitation
monitoring.
Growth of the planted vegetation
EMaP-18
EMoP
PIU
IA
Mid or
ending
20 000
110 000 Impossible to
assess no no
This action executes
by the specialist, not
the IA.
Well growing species 20 000
Presence of weeds 20 000
Vegetation cover 20 000
Non-rehabilitated area 20 000
Perennial plant yield and height 10 000
Total 110 000 no
Minimization and mitigation of adverse impact from waste on environment, its control
6.
Strictly prohibit all kinds of waste,
which create during the project
implementation, disposal without
control, deliver to the authorized site.
Collect and temporary keep
waste. EMaP-2, 23 IA During
50 000
340 000 Satisfactory Бс1 - 45 000 Бс1-38,64 See 15th row of the
table on the action
monitoring results. Deliver to the authorized site 290 000
7.
Store used lubricants, which are hazardous wastes from construction in
a special sealed container, build a temporary storage of it according to
standard, isolate from the environ, deliver used lubricants for recycling.
EMaP-9, 10 IA During 30 000 30 000 Satisfactory no no See 16th row of the
table on the action
monitoring results.
8.
Properly remove soft materials of
roadbed such as soil that is unsuitable
for construction.
Deliver to the authorized site
EMaP-3 IA During
50 000
80 000 Satisfactory no no See 17th row of the
table on the action
monitoring results. Give to the necessary person. 30 000
9.
Clean and collect solid wastes that are
in the project site and deliver to the
authorized site.
Clean the area.
EMaP-11 IA Beginning
and ending
50 000
150 000 Satisfactory Бс – 822 500 Бс2-32, 35-41 See 20th row of the
table on the action
monitoring results. Deliver to the authorized site 100 000
10.
Control the safe disposal of a traditional sewage system after the
resettlement.
EMaP-4 IA Beginning 350 000 350 000 Satisfactory no no See 21st row of the
table on the action
monitoring results.
Total 950 000 867 500
Minimization and mitigation of adverse impact from natural risks on environment, its control
11. Plant and cover two sides of roadbed
and mountainside with top soil.
Cover the necessary places by
soil EMaP-5 IA Ending 80 000
380 000 Irrelevant to
2nd phase
Plant perennial vegetation 300 000
Total 380 000 no
Minimization and mitigation of adverse impact on the socio-economy and public, its control
12.
Notify people, including in risk persons
such as pregnant women, elders, neurotic,
and with respiratory disease in the impact
zone before construction and if necessary,
make temporary resettlement.
Notify people before the
construction EMaP-13
PIU
IA Beginning
150 000
1 150 000 Satisfactory no no See 27th row of the
table on the action
monitoring results. Prepare to the survey and
meeting 1 000 000
13. Rehabilitate and landscape all necessary
places, where soil is influenced during the
construction at the end of the project.
Clean the area
EMaP-6 IA Ending 100 000 100 000 Irrelevant to
2nd phase Rehabilitate and landscape
the area
Total 1 250 000 no
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
33
Minimization and mitigation of labor safety and security risk, its control
14. Provide a complete set of firefighting equipment and check the expiry
date of fire extinguishers. EMaP-25 IA During 50 000 50 000 Incomplete no no See 34th row of the
table on the action
monitoring results.
15. Provide labor safety equipment such as earphones, eyeglasses and work
clothes for construction workers. EMaP-26 IA During 200 000 200 000 Satisfactory Бс1 - 8 637 400
Бс2 - 2 142 500
Бс1-38,65-83
Бс2-32, 49-54
See 35th row of the
table on the action
monitoring results.
16. Organize training with a vocational organization and introduce
awareness-building measures on prevention from risks of potential
accidents to the project staff.
EMaP-27 IA During 150 000 150 000 Satisfactory Бс1 - 75 000
Бс2 – 500 000
Бс1-38,39, 40
Бс2-32
See 36nd row of the
table on the action
monitoring results.
17. Collaborate with an environmental vocational organization for
implementation of EMaP and EMoP. EMaP-30 IA During 2 000 000 2 000 000 Unsatisfactory no no No collaboration
Total 2 400 000 11 354 900
Grand total 10 250 000
From this, for the environmental monitoring 4 030 000
From this, for IA 6 220 000 16 504 170
17 actions with the cost out of 30 actions were mentioned in EMaP, and EMoP, were written in this table. The remaining actions without the cost not belonged to this auditing.
The monitoring results in the table are read as below.
A planned action 1:
The requirement in row 1 of this table is stated in 7th
row of EMaP. It has to be done the whole period of the project implementation. The aforesaid cost was planned to spend for the action before
the project, and the actual cost was calculated based on bills. It assessed as “Satisfactory” by the auditing of an environmental external specialist based on the actual costs. This assessment is
only for cost auditing, not for implementation of environmental action. The facts are enclosed in this report and explanation of assessment was written in a last column of the report.
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
34
Seventeen measures with the cost out of 30 measures were written in the EMaP of the sub-project, and
a total of 10 250 000 T was planned to be spent. From that amount of money, 4 030 000 T had to be
spent for air, soil and rehabilitation monitoring research, as mentioned in EMoP. The pollution
monitoring will be executed by the specialist, who was chosen by the PMU. The EMoP says that the
remaining 6 220 000 T has to be spent for the rest of the measures, which should be implemented by
the contractor. The following table shows a breakdown of the planned costs that belong to the
contractor.
Table 20. Breakdown of the planned cost and its expenditure
№ Groups The cost
Planned Expenditure
1 Minimization and mitigation of adverse impact on air, its
control 1 180 000 4 281 770
2 Minimization and mitigation of adverse impact on soil, its
control 60 000 no
3 Minimization and mitigation of adverse impact on the
vegetation cover, its control no no
4 Minimization and mitigation of adverse impact from waste
on the environment, its control 950 000 867 500
5 Minimization and mitigation of adverse impact from natural
risks on the environment, its control 380 000 no
6 Minimization and mitigation of adverse impact on the socio-
economy and public, its control 1 250 000 no
7 Minimization and mitigation of labor safety and security
risk, its control 2 400 000 11 354 900
Total 6 220 000 16 504 170
Figure 14. Numerical expression of the EMoP monitoring result
As shown in the aforesaid table and figure, the contractor was spent more than the planned cost in
progress, and some measures were executed by its internal resources without cost. For the following
reasons, it was impossible to evaluate the implementation of the EMM of the contractor based on the
0
2000000
4000000
6000000
8000000
10000000
12000000
1 2 3 4 5 6 7
The
amo
unt
of
mo
ney
Groups
The cost of EPA
Planned Expense
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
35
EMoP monitoring result. i) the planned cost was too general and unclear, ii) the cost was different than
the recent market price (maybe it is related to the time that the DEIA was made) and iii) in some cases;
it was not necessary to spend. For instance:
1. In the first row of the EMoP monitoring result, the planned cost was 1 180 000 T for
moisturizing, but actual cost was 4 281 770 T. This means that the planned cost was lower
than the actual market cost.
2. In the second row of the EMoP monitoring result, the measure was impossible to assess, since
this measure should be implemented by the specialist, not the contractor.
3. In the third row of the EMoP monitoring result, although the contractor did not spend money,
it was assessed as satisfactory. Because of the case was not happened during the project term.
Thus, it is impossible to evaluate the implementation of the EMM of the contractor based on the
EMoP monitoring result. Also, we should consider the results of monitoring the implementation of
EMaP.
The result of environmental pollution monitoring
The environmental pollution monitoring has been executed in the area where the “UB-Baruun salaa”
sub-project is implemented. The aim of this monitoring was to examine the impact of the sub-project
on the environment. The monitoring was conducted in the following two environs and executed by the
“Us-Orchin” Co Ltd., under the guidance of the specialist. Based on EMaP and EMoP, a work task has
been developed as follows:
1. Air quality
2. Soil quality
Table 21. Sampling points of environmental pollution monitoring “UB-Baruun salaa”
№ Sampling points Longitude Latitude Altitude Legend
1 Air quality sampling - 1 47°59'15.9" 106°48'5.4" 1410 m BS1
2 Soil quality sampling - 1
3 Noise measurement - 1 47°59'2.2" 106°48'10.7" 1404 m BS2
4 Noise measurement - 2 47°58'16.1" 106°48'22.9" 1380 m BS3
5 Noise measurement - 3 47°58'0.5" 106°48'50.4" 1352 m BS4
6 Soil quality sampling - 2
7 Air quality sampling - 2 47°57'30.2" 106°49'24.4" 1343 m BS5
Figure 15. Sampling points of environmental pollution monitoring “UB-Orbit-Tahilt”
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
36
Air quality monitoring:
The monitoring has been done at the beginning and end of the new road in Baruun salaa by AQMS-
9000 mobile automatic system and data from UB air quality monitoring stations in between 10-11 am
on the 8th of June, 2012.
Figure 16. AQMS-9000 mobile automatic system for air quality monitoring
Figure 17. Noise measurement
The monitoring was done for 30 minutes with a 10-minute frequency at the above-mentioned two
places. All parameters were measured three times, then averaged and compared with MNS 4585:2007.
In addition to this, the air-quality index was calculated.
Table 22. Results of air quality measurement – BS1
№ Measured parameters Unit Duration
Average Standard Difference Explanation 10‘ 20‘ 30‘
1 Sulfur dioxide SO2 µg/m3 0 0 0 0 450 0 Unpolluted
2 Nitrogen dioxide NO2 µg/m3 15 20 15 16 85 0.18 Unpolluted
3 Particulate matter PM10 µg/m3 1,56-50,23 36 100 0.36 Unpolluted
4 Particulate matter PM2,5 µg/m3 1,05-45,70 23 50 0.46 Unpolluted
5 Noise dB 43,8 43,8 60 0,73 Unpolluted
Air quality measurement has been calculated with the air-quality index.
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
37
Table 23. Results of air quality index – BS1
Table 24. Results of noise measurement and index – BS2
№ Measured
parameters Unit
Duration Average Standard Difference Explanation
10‘ 20‘ 30‘
1 Measurement dB 59,3 59,3 60
0,98 Very good
2 Index 98 Good
Overall assessment - Good
Table 25. Results of noise measurement and index – BS3
№ Measured
parameters Unit
Duration Average Standard Difference Explanation
10‘ 20‘ 30‘
1 Measurement dB 61,3 61,3 60
1,02 Polluted
2 Index 102 Average
Overall assessment - Average
Table 26. Results of noise measurement and index – BS4
№ Measured
parameters Unit
Duration Average Standard Difference Explanation
10‘ 20‘ 30‘
1 Measurement dB 72,3 72,3 60
1,21 Polluted
2 Index 121 Average
Overall assessment - Average
Table 27. Results of air quality measurement – BS5
№ Measured parameters Unit Duration
Average Standard Difference Explanation 10‘ 20‘ 30‘
1 Sulfur dioxide SO2 µg/m3 5 3 7 5 450 0,01 Unpolluted
2 Nitrogen dioxide NO2 µg/m3 35 43 86 54,6 85 0.64 Unpolluted
3 Particulate matter PM10 µg/m3 10,82-63,15 57 100 0.57 Unpolluted
4 Particulate matter PM2,5 µg/m3 12,05-60,50 47 50 0.94 Unpolluted
5 Noise dB 74,9 74,9 60 1,25 Polluted
Air quality measurement has been calculated with the air-quality index.
Table 28. Results of air quality index – BS5
№ Measured parameters Unit Average Standard Index Explanation
1 SO2 µg/m3 0 450 0 Very good
2 NO2 µg/m3 16 85 19 Very good
3 PM10 µg/m3 36 100 36 Very good
4 PM2,5 µg/m3 23 50 46 Very good
6 Noise dB 43,8 60 73 Good
Overall assessment - Good
№ Measured parameters Unit Average Standard Index Explanation
1 SO2 µg/m3 5 450 1 Very good
2 NO2 µg/m3 54,6 85 64 Good
3 PM10 µg/m3 57 100 57 Good
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
38
Conclusion:
1. Based on a comparison with MNS 4585:2007, all parameters of air quality at the end of the
new road were assessed as “unpolluted”. According to the index assessment, the evaluation
was “good”.
2. Only noise measurements have been done at BS2, BS3, BS4 points and by the standard, they
were assessed as “unpolluted” and “polluted”. By the index assessment, noise was measured
as “good” and “average”.
3. Based on a comparison with MNS 4585:2007, air quality at the BS5 – beginning of the new
road was assessed as “unpolluted” except for noise pollution. According to the index
assessment, the evaluation was “average” due to noise excess.
4. However, the noise pollution was related to the high acceleration of the vehicles on the
ascending road. Measurement of excess noise levels was measured casually very few times.
Generally, the surroundings area of the project is not polluted by noise.
5. In fact, there is impossible to accumulate air pollution when sources of air pollution are few,
the location is upwind and outside of the city.
Soil quality:
The monitoring has been done at the 2 places where the worker’s camp is situated and end of the road
in Baruun salaa in 11 am on 8th of June, 2012. 1 m
2 area on each site, that might have been polluted,
was selected for soil quality sampling. Five samples from each site were taken by the grid method and
then mixed them into one sample.
Figure 18. Soil quality sampling
In total, 14 parameters, including variables in the work task, were analyzed in the laboratory, and the
results compared to the MNS 5850:2008.
4 PM2,5 µg/m3 47 50 94 Good
6 Noise dB 74,9 60 125 Average
Overall assessment - Average
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
39
Table 29. Results of soil quality analysis – BS1
Table 30. Results of soil quality analysis – BS4
Conclusion:
1. The soil has slightly eroded by human activity. However, the fertile soil has not disappeared.
The texture of soil is a sandy.
2. Texture and humus were not involved in the evaluation of quality, since these parameters can
be different in variety of places due to natural conditions.
3. Chromium, lead, cadmium, nickel and zinc did not exceed the permissible level, which was
mentioned in the standard. Therefore, there were assessed as “unpolluted”.
4. In fact, there is no condition to accumulate soil pollution when sources of soil pollution are
few and population density is low.
№ Analyzed parameters Unit Result Standard Difference Explanation
1 Sand % 35,2 - - not mentioned in standard
2 Dirt % 51,2 - - not mentioned in standard
3 Clay % 13,6 - - not mentioned in standard
4 рН 1:2,5 6,77 - - not mentioned in standard
5 СаСО3 % 0,00 - - not mentioned in standard
6 Humus % 7,91 - - not mentioned in standard
7 ЕС2,5 dS/m 0,119 - - not mentioned in standard
8 Р2О5 mg/100g 3,65 - - not mentioned in standard
9 К2О mg/100g 24,6 - - not mentioned in standard
10 Chromium, Cr mg/kg 15,0 150 0,1 Unpolluted
11 Lead, Pb mg/kg 18,3 100 0,18 Unpolluted
12 Cadmium, Cd mg/kg 0,52 3 0,17 Unpolluted
13 Nickel, Ni mg/kg 6,5 150 0,04 Unpolluted
14 Zinc, Zn mg/kg 230,2 300 0,76 Unpolluted
№ Analyzed parameters Unit Result Standard Difference Explanation
1 Sand % 42,5 - - not mentioned in standard
2 Dirt % 42,4 - - not mentioned in standard
3 Clay % 15,0 - - not mentioned in standard
4 рН 1:2,5 7,79 - - not mentioned in standard
5 СаСО3 % 1,16 - - not mentioned in standard
6 Humus % 4,45 - - not mentioned in standard
7 ЕС2,5 dS/m 0,231 - - not mentioned in standard
8 Р2О5 mg/100g 2,97 - - not mentioned in standard
9 К2О mg/100g 20,5 - - not mentioned in standard
10 Chromium, Cr mg/kg 14,0 150 0,09 Unpolluted
11 Lead, Pb mg/kg 28,3 100 0,28 Unpolluted
12 Cadmium, Cd mg/kg 0,88 3 0,29 Unpolluted
13 Nickel, Ni mg/kg 8,7 150 0,06 Unpolluted
14 Zinc, Zn mg/kg 220,5 300 0,74 Unpolluted
Second report on external environmental monitoring – “UB-Baruun salaa” road improvement sub-project
40
CONCLUSION
The following conclusions have been drawn for the EMM regarding the “UB-Baruun salaa” road
improvement sub-project based on the 2nd
phase of monitoring of EMaP and EMoP. Herein:
1. In total, 43 EMMs of the sub-project has been monitored. Forty out of the 43 measures should
be implemented by the contractor. Six out of 40 actions were irrelevant to the 2nd
phase.
Therefore, these were not monitored. The remaining 34 measures should be implemented in
the project time. Twenty eight out of 34 measures were assessed as satisfactory, 2 of them
were evaluated as incomplete and 4 were valued as unsatisfactory. Therefore, we can conclude
that 82% of the measures were assessed as satisfactory.
2. The overall evaluation of EMM of the contractor was evaluated as “B - good". Since the
environmental responsibility was assigned to an internal affair manager. But, overall
assessment of the 1st phase was 85%, and it has been reduced by 3%. That means, the
contractor did not take any additional action to improve the environmental responsibility.
However, the contractor has an opportunity to improve this overall evaluation of EMM.
3. For the contractor, three measures, those assessed as unsatisfactory, were related to the waste
management. Old ways of removing various kinds of waste, such as the use of landfills,
runoff, burning and blowing, should be replaced by more modern ways. It will drastically
improve the evaluation of EMM of the contractor.
4. The unassessable three measures for the monitoring research were not reflected in the overall
evaluation. These will be implemented by the specialist, who was selected by the PMU.
5. One measure, this assessed as unsatisfactory, was related to the environmental delict. Thence,
we can conclude that information about environmental management was inadequate.
6. One action on soil impact was assessed as incomplete due to insufficient information about a
new technology and its process on DEIAR. The technology is related to removing the topsoil
with plant roots, and it was a new to the contractor.
7. For the contractor, to pay attention to complete a set of firefighting equipment.
8. The measures, those assessed as incomplete and unsatisfactory, can be improved by an
initiative of the contractor and collaboration between the PIU and the contractor.
9. So far, the overall actual expense was more than the planned cost as shown in the result of
monitoring the budget expenditure of the EMoP. It was indicating that the effort of the
contractor. However, the planned cost was different than the recent market price.
10. The planned costs of some measures were lower than the recent actual prices, resulting in
unplanned costs. Probably, this difference depends on what year that particular DEIA was
made.
11. According to the results of the environmental pollution monitoring, the project has a positive
impact on surrounding environment.
Recommendations, which were based on the conclusions and observations during the monitoring, are
written at the end of this report.
Second report on external environmental monitoring
41
RECOMMENDATION
The following recommendations have been drawn for the ADB, PMU, PIU and the contractors based
on the results of external environmental monitoring on the road improvement sub-projects.
Considering these recommendations, it is possibly to mitigate adverse impacts of the project on the
environment, socio-economy and public in the near future. In addition, it is possible to avoid legal
liability for the environmental delict, which might be incurred in the future. Herein:
ADB:
1. According to Mongolian law, the DEIA of sub-projects was done before the project
implementation. So, the planned cost in the EMaP and EMoP can either coordinate with the
state inflation during the year of project implementation or balance it with the actual market
price.
2. An environmental specialist and an external monitoring specialist should work on all projects
that will be implemented in the future. Their work would be a main indicator of the ecological
oriented policy of ADB.
3. Before the project began, the environmental quality of the project territory was studied by the
DEIA company, and its result reflected in the DEIAR. It is true that mitigation of the adverse
impact on the environment was done by the PIU and the contractor, according to the EMaP
and EMoP, and its external monitoring was executed by the environmental specialist.
Furthermore, it is necessary to do environmental quality monitoring research after the project
implementation. This is a good opportunity to compare environmental quality at three
different times “past-present-future”, and assess the actual impact of the project on the
environment. In addition, the local people mostly have a negative impression during the
project, but their impression positively changes after the project. Therefore, if environmental
quality assessment such as air, soil, water, rehabilitation, is executed within a short time after
the project closure, then the actual impact of the project on the environment can be assessed.
4. All projects, funded by ADB, should implement the standard MNS ISO 14064-2:2011 “Green
house gases-Part 2: Specification with guidance at the project level for quantification,
monitoring and reporting of green house gas emission reductions or removal enhancements."
This will be an indicator of the world political-economic “green” policy implementation and
will give a good opportunity for minimization of the adverse contributions to earth climate
change.
5. New laws on nature and environment, approved in June, 2012 by the Government, have to
implement in practice.
PMU and PIU
1. The rights and duties of the external environmental monitoring specialist need to be officially
introduced by the PMU to the PIU and the contractor at the beginning of the work. This will
help to avoid misunderstandings between the specialist and the PIU and the contractor during
the monitoring.
2. There needs to be a review checking, whether or not the planned cost of EMaP and EMoP is
enough for the implementation of EMMs and reflects the actual market price.
3. The contractor must be required to hire an environmental specialist or to assign environmental
responsibility to one of the managerial staff.
4. It is proper to carry out environmental quality monitoring such as air, soil, water and
rehabilitation by the environmental specialist, instead of by the PIU and the contractor. This
will give us an opportunity to assess the actual impact of the project on the environment.
5. In some cases, the planned cost, which was proven by Ministry of Nature, Environment and
Tourism is lower than the recent market price. Depends on that, the contractors were spend
Second report on external environmental monitoring
42
more than the budgeted cost. According to the contract and based on the collected bills, it is
necessary to decide whether overspend money can reimburse or not, if necessary.
6. When evaluating the EMM of the contractor, we should consider not only the EMoP
monitoring results but also the monitoring result of EMaP.
7. New laws on nature and environment, approved in June, 2012 by the Government, have to
implement in practice.
Contractor
1. When beginning the project, it is best to hire an environmental specialist or to assign
environmental responsibility to one of the managerial staffs, so that he/she controls the
implementation of the EMaP and EMoP.
2. There should be a schedule of EMM, control of its implementation, collection of financial
bills and a financial plan made for EMM execution.
3. A close reading of the DEIAR and understanding of it will help to avoid a potential accidents
and loss and amenability, which may happen in the future.
4. Executing the environmental quality monitoring such as air, water, soil and rehabilitation by a
vocational organization or expert, as well as understand these results will help prevent
compensation required by environmental degradation.
5. Old ways of removing various kinds of waste, such as the use of landfills, runoff, burning and
blowing, should be replaced by more modern ways. These include mobile bio-toilet and
mobile containers for solid and liquid waste collection, which can drastically improve the
evaluation of EMM of the contractor. Such mobile containers can be reused many times.
Therefore, it is necessary to invest in proper waste disposal. This will increase the contractor’s
reputation; as well encourage the environmental-economic policy of the state.
6. It is necessary to implement the standard MNS ISO 14064-1:2011 “Green house gases-Part 1:
Specification with guidance at the organization level for quantification and reporting of green
house gas emission reductions or removal enhancements." This will be an indicator of the
contractor’s “green” policy implementation and will give a good opportunity for minimization
of the adverse contributions to earth climate change.
7. New laws on nature and environment, approved in June, 2012 by the Government, have to
implement in practice. It will help you to avoid legal liability for the environmental delict in
future.
8. Generally, environmental information and knowledge of contractors is inadequate. Therefore,
they can collaborate with environmental vocational organization.
9. In some cases, the planned cost, which was proven by Ministry of Nature, Environment and
Tourism is lower than the recent market price. Depends on that, the contractors were spend
more than the budgeted cost for environmental protection. In that case, the contractor should
collect all bills and contact with PMU.
By the implementation of the aforesaid recommendations, we will achieve “Environmentally
friendly economic policy and social development."
Reported by: Associate professor, Doctor O.Altansukh