CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000661
DESCRIPTION : Planting Works and Earth Pit Installation along Cycle Track
MONTH : October 2016 PHOTOGRAPH NO: 000662
DESCRIPTION : Excavation and Installation of RC Sump along Western Approach
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000663
DESCRIPTION : Excavation and Installation of RC Pipe Culvert along Western Approach
MONTH : October 2016 PHOTOGRAPH NO: 000664
DESCRIPTION : Slope Preparation (South Bound) and Edge Kerb Works along Western Approach
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000665
DESCRIPTION : Cycle Track Base Preparation, Density Testing and Premix along Eastern Approach
MONTH : October 2016 PHOTOGRAPH NO: 000666
DESCRIPTION : Side Ramp and Slope Preparation along Eastern Approach
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000667
DESCRIPTION : Removal of Temporary Deck Beams at Zone - A
MONTH : October 2016 PHOTOGRAPH NO: 000668
DESCRIPTION : Lean Concrete and Concrete Casting of 1.2m thick Baseslab at Zone – A (EJ0-EJ1) West
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000669
DESCRIPTION : S2 Strut Installation and Instrumentation Works at Zone – A (EJ1-EJ2) West
MONTH : October 2016 PHOTOGRAPH NO: 000670
DESCRIPTION : Construction of Ground Beam at Zone – A (EJ1-EJ2) West
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000671
DESCRIPTION : Baseslab Preparation Works at Zone – A (EJ1-EJ2) West
MONTH : October 2016 PHOTOGRAPH NO: 000672
DESCRIPTION : Concrete Casting of Drainage Wall at Zone – A (EJ2-EJ3) West
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000673
DESCRIPTION : Backfilling Works and Removal of Diagonal Strut at Zone – A (EJ2-EJ3) West
MONTH : October 2016 PHOTOGRAPH NO: 000674
DESCRIPTION : Strut Removal and Sheet Pile Extraction along Temp Canal at Zone – A (EJ3-EJ4) West
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000675
DESCRIPTION : Construction of Road along Western Approach at Zone – A (EJ3-EJ4) West
MONTH : October 2016 PHOTOGRAPH NO: 000676
DESCRIPTION : Removal of King Post along Cycle Track at Zone – A (EJ3-EJ4) East
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000677
DESCRIPTION : Bench Granite Installation at Zone – A (EJ7-EJ9)
MONTH : October 2016 PHOTOGRAPH NO: 000678
DESCRIPTION : Planter Wall Granite Installation at Zone – A (EJ7-EJ9)
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000679
DESCRIPTION : SS Strip Installation and Exposed Aggregate Floor Finishing at Zone – A (EJ7-EJ9)
MONTH : October 2016 PHOTOGRAPH NO: 000680
DESCRIPTION : SS Strip Installation and Exposed Aggregate Floor Finishing at Zone – A (EJ7-EJ9)
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000681
DESCRIPTION : RCA Removal and Sheet Pile Extraction (East Bay 10)at Zone – B Cofferdam
MONTH : October 2016 PHOTOGRAPH NO: 000682
DESCRIPTION : RCA Removal and Sheet Pile Extraction (East Bay 11) at Zone – B Cofferdam
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000683
DESCRIPTION : RCA Removal and Sheet Pile Extraction (East Bay 12) at Zone – B Cofferdam
MONTH : October 2016 PHOTOGRAPH NO: 000684
DESCRIPTION : RCA Removal and Sheet Pile Extraction (East Bay 13) at Zone – B Cofferdam
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000685
DESCRIPTION : RCA Removal and Sheet Pile Extraction (East Bay 14) at Zone – B Cofferdam
MONTH : October 2016 PHOTOGRAPH NO: 000686
DESCRIPTION : RCA Removal and Sheet Pile Extraction (West Bay 13) at Zone – B Cofferdam
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000687
DESCRIPTION : RCA Removal and Sheet Pile Extraction (West Bay 14) at Zone – B Cofferdam
MONTH : October 2016 PHOTOGRAPH NO: 000688
DESCRIPTION : RCA Removal and Sheet Pile Extraction (West Bay 15) at Zone – B Cofferdam
CONTRACT NO : CW-DD-33140117
CONTRACT NAME : Improvement of Siglap Canal
(between East Coast and the Sea)
CONTRACTOR : Eng Lee Engineering Pte. Ltd.
MONTH : October 2016 PHOTOGRAPH NO: 000689
DESCRIPTION : RCA Removal and Sheet Pile Extraction (West Bay 16) at Zone – B Cofferdam
MONTH : October 2016 PHOTOGRAPH NO: 000690
DESCRIPTION : Electrical Works (OG Box Energizing) at Zone – B