100
Monthly Major Projects Report for October 2003 Prepared by 1

Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Embed Size (px)

Citation preview

Page 1: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Monthly Major Projects Report for

October 2003

Prepared by

1

Page 2: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Page Number

Index

Project Number

4 Executive Summary of Major Projects

7 Architecture Hall 10420

11 Bioengineering & Genome Sciences 3615

17 Conibear Shellhouse Renovation & Addition 1915

23 Golf Driving Range 2758

29 Guggenheim Hall 10419

33 Harborview Bond Program 3927

39 IMA Expansion – Recreation Sports/Fitness 2120

45 Johnson Hall 10106

51 Merrill Hall Replacement Project 3757

59 Paul G. Allen Center for Computer Sciences & Engineering 2507

65 Research Center 10297

71 Soccer / Baseball Stadium 3682

75 Terry Hall 3948

81 UWMC Surgery Pavilion 2731

87 UW Tacoma Campus Phase 2b 2608

95 William H. Gates Hall 1846

2

Page 3: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

This is a report, by the University of Washington Capital Projects Office, on the major capital projects. The intention is to show monthly “snapshots” of key project indicators and describe the development of each project to its conclusion. This information will be made available on the Capital Projects Office website: http://www.cpo.washington.edu. In the effort to keeping printing costs down, if you wish to be removed from this printed distribution, please let us know.

We welcome your comments, suggestions, and corrections.

Distribution

Bruce Abe Doug Holen Jan Arntz Weldon Ihrig

Debra Born Ronald Johnson Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine McCray

Richard Chapman Norm Menter Lee Copeland Alan Nygaard Marilyn Cox Dick Owen

Theresa Doherty John Palewicz Amy Engel Will Smith Ron Fouty Bill Talley JR Fulton David Thorud

Sharon Griffin Catherine Vogt Bryan Hall Olivia Yang

3

Page 4: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

MAJOR PROJECTS EXECUTIVE SUMMARY October 2003

• Architecture Hall – Fee negotiations with the designer are complete. The draft

Project Agreement has been finalized. • Bioengineering & Genome Sciences – An RFP was issued for the exterior façade.

Pile work has begun, 8,000 cuyd of soil has been removed to an approved site. • Conibear Shellhouse Renovation & Addition –The GC/CM contract was

finalized. The PRB approved bidding of subcontractor packages. • Golf Driving Range – The design schedule continues to slip due to program

changes. The client and designer will work to develop a revised program. • Guggenheim Hall – The design contract is being prepared. The final draft Project

Agreement is in circulation for signature. • Harborview Bond Program - Design Development is underway for all buildings

except the Ninth and Jefferson Building. The scope of the NJB has been revised to include two additional floors and additional parking. Schematic Design is underway to effect the changes.

• IMA Expansion – Recreation Sports/Fitness – Beneficial occupancy was taken on September 29th. Change order work from late design changes is on-going.

• Johnson Hall- The Design Development package was submitted and deemed incomplete. The package is expected to be re-submitted November, 17. Schedule delay mitigation plans are being considered.

• Merrill Hall Replacement Project – Early construction activities continue; excavation, site utilities, sub-grade mechanical and electrical.

• Paul G. Allen Center for Computer Sciences & Engineering - Punch list work continues. Commissioning of systems is in the functional performance stage.

• Research Center - Five teams responded to the Design Build Operate Maintain (DBOM) RFP advertised in September. Initial reviews indicate that the budget is tight but achievable. Analysis of the five responses will take two weeks.

• Soccer / Baseball Stadium – Programming tasks are 80% complete. The client and designer met to review the stadium concept and cost model.

• Terry Hall – Design Development Documents have been reviewed and the designer is responding to comments. The designer is proceeding with Construction Documents with the approval of the PRB.

• UWMC Surgery Pavilion – The Medical Center started seeing patients on Level 1 on October 14, 2003. Work on the punch list continues. The UWMC gala event occurred on October 10, 2003.

• UW Tacoma 2B – Interior finishes are progressing at Cherry Parkes and the Mattress Factory, where elevator work has begun. Site work is nearing completion.

• William H. Gates Hall – Punch list work continues and is being coordinated by CPO to minimize impact on Law School activities.

4

Page 5: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Schedule and Budget Schedule

0 20 40 60 80 100 120

Architecture Hall

Bioengineering and Genome Sciences

Conibear Shellhouse

Golf Driving Range

GuggenHeim Hall

Harborview Bond Program

IMA Expansion

Johnson Hall

Merrill Hall

Paul Allen Center

Research Center

Soccer / Baseball

Surgery Pavilion

Tacoma Campus Phase 2B

Terry Hall

William H. Gates Hall

Months

Duration/M Completed/M

Budget and Forecast

0

50

100

150

200

250

300

Arch

itect

ure

Hal

l

Bioe

ngin

eerin

g an

dG

enom

e Sc

ienc

es

Con

ibea

rSh

ellh

ouse

Gol

f Driv

ing

Ran

ge

Gug

genH

eim

Hal

l

Har

borv

iew

Bon

dPr

ogra

m

IMA

Expa

nsio

n

John

son

Hal

l

Mer

rill H

all

Paul

Alle

n C

ente

r

Res

earc

h C

ente

r

Socc

er /

Base

ball

Surg

ery

Pavi

lion

Taco

ma

Cam

pus

Phas

e 2B

Terr

y H

all

Willi

am H

. Gat

esH

all

Budget/$M Forecast/$M

5

Page 6: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

6

Page 7: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Architecture Hall Renovation

Project Number 10420

Monthly Report

October 2003

Prepared by the Capital Projects Office

Debra Born, Project Manager

7

Page 8: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Architecture Hall Renovation

PROJECT DESCRIPTION The purpose of the Architecture Hall Renovation is to restore and update the 47,500 gross square foot building to accommodate existing uses. Current use includes space for College of Architecture and Urban Planning (CAUP) programs, which occupy 21,740 net square feet, and general assignment classrooms including a 355 seat lecture hall, which occupy approximately 6,300 net square feet.

Originally built as the Fine Arts Palace for the 1909 Alaska-Yukon-Pacific Exposition, Architecture Hall is one of the oldest buildings on the Seattle campus and the last of the Exposition’s buildings. With minimal maintenance and improvements over time, the building has continued to function as an academic building housing offices, classrooms, and studios.

The purpose of the project is to address deficiencies related to seismic stability, accessibility, and major building systems as well as abatement of hazardous materials, correction of unsafe conditions, and functional program improvements.

PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Fee negotiations with Hacker and Associates were on-going throughout the month. The draft Project Agreement was circulated for approval and has been finalized. Pre-design meetings with the Architect were scheduled to begin in November 2003 after execution of the pre-design consultant contract. Completion of programming is anticipated in March 2004. Design phases are expected to begin immediately and extend through summer 2005. Construction is forecast to begin in summer 2005 and end summer 2007.

Plans for Next 30 Days Activities planned to commence in November include:

1. A detailed assessment of the facility by the consultants including an assessment of hazardous materials, geotechnical conditions, and a site survey.

2. Documentation of existing conditions including analysis of current use, exterior elements, and structural system.

3. Meetings to establish programming expectations, guidelines, and priorities. Design Status & Approvals A work plan for pre-design was prepared and approved in October. At the end of the pre-design phase, Capital Projects Office will report to the signatories of the Project Agreement the status of the project scope, budget, and schedule for approval to proceed into the design phases. Construction will be contingent upon funding by the Legislature.

8

Page 9: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Construction Accomplishments This Period Not applicable at this time. PROJECT BUDGET & COST Funding for pre-design and design of $2,634,000 has been allocated by the State Legislature based on a project budget of $20,282,000. CHANGES IN SCOPE No changes in the project scope this month. BUYOUT STATUS Not applicable at this time. SAFETY STATUS Not applicable at this time. Construction has not started on this project. OPPORTUNITIES & CHALLENGES The challenge for the coming month is to establish the stakeholders’ expectations for the project and to reconcile these expectations to the project budget and schedule. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time. The project is in design.

9

Page 10: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

10

Page 11: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Bioengineering Facility & Genome Sciences

Project Number

3615

Monthly Report

October 2003

Prepared by the Capital Projects Office

Bryan Hall, Project Manager

11

Page 12: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Bioengineering Facility & Genome Sciences

PROJECT DESCRIPTION The new Bioengineering and Genome Sciences building total approximately 265,000 gsf of state-of-the-art research and teaching facilities. The Bioengineering component of the project will house a multi-disciplinary program to support research and academic curriculum including distributed diagnosis and home healthcare, engineered biomaterials, molecular bioengineering and nanotechnology, medical imaging and image guided energy therapy and computational bioengineering. Genome Sciences will contain research spaces to serve the emerging program of genomics research. The program provides a mix of flexible biomedical research laboratories and associated central support spaces such as glass washing, mass spectroscopy and freezer farms. The total project program also includes soil remediation, a shared underground loading facility, auditorium and cafe. The Architect is Anshen + Allen, Los Angeles, CA. The GC/CM is Hoffman Construction Company, Seattle, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Master Use Permit (MUP) and Excavation and Shoring Permits have been issued. Earthwork was rebid on September 5, low bidder was Northwest Construction. The RFP was issued for the exterior facade with pricing anticipated in late December. Bid dates for exterior wall, structure, mechanical, electrical and plumbing have all been moved back one month to allow for a more thorough design review. Plans for Next 30 Days Comments have been received from Engineering Services and EH&S. Resolution of these comments is underway, with approval anticipated in late November/early December. Construction activities will continue with the installation of shoring, continued excavation of the site and the installation of underground sewer and water lines. Bids for Temporary Electric will be due in November. Design Status & Approvals The design for Bioengineering and Genome Sciences was approved by the Architectural Commission in June of 2003. Final CD’s for Bioengineering were received October 1 for Redicheck coordination and comment resolution. Structural package and exterior

12

Page 13: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

enclosure packages for Bioengineering and Genome is now scheduled to advertise for bid in early December, with bid opening in late January. Construction Accomplishments This Period Hoffman awarded contracts to Malcolm Drilling for Bid Package #6, Shoring and Dewatering and to Northwest Construction for Bid Package #7, Earthwork. The formal Notice to Proceed with construction activities was issued on September 15. Shoring pile work began in early October to support the excavation of the site. This work continued throughout the month. As part of this operation, approximately 8,000 yards of hydrocarbon impacted soil were removed to approved disposal sites. Work on site included:

mass excavation installation of shoring setting of perimeter dewatering wells construction of temporary truck wheel wash station installation of underground sewer and water mains placement of pedestrian protection along Pacific Avenue relocation of bike rack enclosure installation of temporary erosion control plan

PROJECT BUDGET & COST Total project cost is $150 million. A GCCM contract for $110,635,546 has been issued to Hoffman; of this amount $90,247,251 is budgeted for subcontract (buyout) work. This project is currently 100% funded. CHANGES IN SCOPE None this period.

Description AmountTotal Changes in Scope to Date $0.00

BUYOUT STATUS We anticipate a total of sixty four (64) bid packages for this project.

Buyout Statistics Awarded Remaining Total

Percent Complete

Number of Packages 2 62 64 3.1%Dollar Value of Pkgs $4,895,363 $85,352,208 $90,247,571 5.4% Savings to Date (+ ahead or – behind) +$1,813,802

13

Page 14: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

SAFETY STATUS

Safety Statistics This Month Project To DateAverage Daily Work Force 28 22Lost Time Incidents 0 0Recordable Incidents 0 0Total Hours Worked All Crafts 4604 5058Project Total Incidence Rate * 0 0

* Incidence Rate = (# of Incidents x 200,000 hrs) / (# of hours worked)

OPPORTUNITIES & CHALLENGES Opportunity:

Optimizing building design within the University Master Plan for bulk and height and achieving the planning objectives for the Vista Design.

Challenges: Completion of Bioengineering by December 2005 to take full advantage of the Whitaker Foundation Grant. Finalization of the Health and Human Services Grant. Completing the multi-phased design and procurement process with the objective of minimizing construction cost premiums. Expedite the building permit process.

CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number ValueChange Orders Approved 0 $0.00Change Order Proposals Pending 10 $161,683.00Change Order Requests Pending 0 $0.00Team Change Memos Approved 0 $0.00

Requests for Information to date Number Avg. TurnaroundRFI’s 25 2 days

Submittals to date Number Avg. TurnaroundSubmittals 9 6.45

14

Page 15: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNTCHART

15

Page 16: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.3

615

Pro

ject

:3615 B

ioengin

eering a

nd G

enom

e S

cience

s

PR

OJE

CT

CO

ST

RE

PO

RT

- L

evel 2

Origin

al

Budget

Com

mitt

ed

to D

ate

Act

ual

Cost

to

Date

Fore

cast

Tota

l C

osts

Variance

from

Late

st B

udget

Act

ual

Cost

this

P

eriod

Est

imate

of

Uncom

mitt

ed

Appro

ved

Changes

Pendin

g

Changes

AB

CD

EF

GH

(I-

C)

IJ

(B-I

)

Late

st

Appro

ved

Budget

B. C

onsultant S

erv

ices

1,4

51

,00

2

Pre

-De

sig

n S

erv

ice

s 1

,45

1,0

02

9

58

,55

3

94

6,3

80

1

6,6

57

9

75

,21

0

35

7,7

06

4

75

,79

2

0

41,5

86

11

,90

6,8

07

B

asi

c S

erv

ice

s 7

,33

7,5

66

5

,44

6,6

32

3

,87

6,1

16

1

,66

6,9

03

7

,11

3,5

35

0

2

24

,03

1

0

518,1

53

2,9

63

,82

7

Ext

ra S

erv

ice

s 7

,61

5,5

08

5

,03

9,6

01

3

,11

3,4

27

3

,39

6,5

12

8

,43

6,1

14

4

,52

7,5

54

(8

20

,60

6)

0

348,6

77

1,6

96

,59

7

Oth

er

Se

rvic

es

1,6

14

,15

6

32

3,5

63

5

,35

3

1,0

95

,99

1

1,4

19

,55

4

0

19

4,6

02

0

1

15

51

0,2

23

D

esi

gn

Se

rvic

es

Co

ntin

ge

ncy

51

0,2

23

0

0

5

10

,22

3

51

0,2

23

0

0

0

0

18,5

28,4

55

B.

Co

nsu

ltan

t S

erv

ice

s 1

8,5

28,4

55

11,7

68,3

50

7,9

41,2

76

6,6

86,2

86

18,4

54,6

36

4,8

85,2

61

To

tal

73,8

19

0

908,5

31

C. C

onst

ruct

ion

89

,50

7,4

44

P

rim

e C

on

tra

ct

90

,24

7,5

50

9

0,2

47

,55

0

0

0

90

,24

7,5

50

0

0

0

0

1

1,8

21

,88

0

GC

/CM

Ite

ms

11

,43

9,5

33

1

1,4

94

,25

3

33

6,3

89

(5

4,7

69

) 1

1,4

39

,48

4

54

,72

0

49

0

5

9,8

80

7,1

56

,61

5

Oth

er

Co

ntin

ge

ncy

7,8

07

,80

9

13

,68

3

0

7,6

89

,92

9

7,7

03

,61

2

13

,68

3

10

4,1

97

2

8,4

33

0

9

,77

1,5

05

C

on

stru

ctio

n S

ale

s T

ax

8,9

48

,46

3

8,9

79

,23

2

29

,60

2

(30

,76

9)

8,9

48

,46

3

0

0

0

5,2

69

2,6

14

,89

0

Ma

na

ge

me

nt

Re

se

rve

2,4

28

,97

9

0

0

2,2

77

,73

3

2,2

77

,73

3

0

15

1,2

46

0

0

120,8

72,3

34

C.

Co

nst

ruct

ion

1

20,8

72,3

34

110,7

34,7

18

365,9

92

9,8

82,1

24

120,6

16,8

42

68,4

03

To

tal

255,4

92

28,4

33

65,1

49

D. E

quip

ment

69

8,3

91

E

qu

ipm

en

t 6

98

,39

1

17

,08

4

10

,08

4

68

1,3

07

6

98

,39

1

0

0

0

1,2

19

2,6

80

,89

7

Fu

rnis

hin

gs

2,6

80

,89

7

0

0

2,6

26

,32

5

2,6

26

,32

5

0

54

,57

2

0

0

29

7,3

81

E

qu

ipm

en

t/F

urn

ish

ing

s S

ale

s T

ax

29

7,3

81

2

,75

8

1,1

59

2

94

,62

3

29

7,3

81

0

0

0

0

3,6

76,6

69

D.

Eq

uip

me

nt

3,6

76,6

69

19,8

42

11,2

43

3,6

02,2

55

3,6

22,0

97

0

To

tal

54,5

72

0

1,2

19

E. A

rtw

ork

64

,89

4

Art

wo

rk 6

4,8

94

0

0

1

45

,12

5

14

5,1

25

0

(8

0,2

31

) 0

0

64,8

94

E.

Art

wo

rk 6

4,8

94

0

0

145,1

25

145,1

25

0

To

tal

(80,2

31)

0

0

F. O

ther

Cost

s 5

45

,85

0

In-P

lan

t S

erv

ice

s 5

45

,85

0

6,4

39

6

,43

9

50

3,6

54

5

10

,09

3

0

35

,75

7

0

0

0

Util

itie

s/T

em

po

rary

Fa

cilit

ies

0

7,1

38

3

,89

0

92

,86

3

10

0,0

00

0

(1

00

,00

0)

0

0

66

5,9

95

P

erm

its 6

65

,99

5

97

,01

7

97

,01

7

49

6,9

98

5

94

,01

5

0

71

,98

0

0

0

11

8,1

97

B

uild

ers

Ris

k In

sura

nce

11

8,1

97

0

0

1

18

,66

2

11

8,6

62

0

(4

65

) 0

0

2

16

,36

9

Oth

er

Co

sts

21

6,3

69

5

0,6

15

3

3,8

19

4

16

,76

6

46

7,3

81

0

(2

51

,01

2)

0

92

1,5

46,4

11

F.

Oth

er

Co

sts

1,5

46,4

11

161,2

09

141,1

65

1,6

28,9

42

1,7

90,1

51

0

To

tal

(243,7

40)

0

92

G. P

roje

ct M

anagem

ent

3,5

33

,81

9

CP

O M

an

ag

em

en

t 3

,53

3,8

19

3

,53

3,8

19

2

55

,80

0

0

3,5

33

,81

9

0

0

0

0

1,7

77

,41

8

Oth

er

Ma

na

ge

me

nt

1,7

77

,41

8

76

2,0

51

7

6,4

08

1

,01

5,3

67

1

,77

7,4

18

4

,00

0

0

0

5,3

00

0

Oth

er

Co

sts

0

10

,57

9

10

,28

3

49

,33

3

59

,91

2

0

(59

,91

2)

0

0

5,3

11,2

37

G.

Pro

ject

Ma

na

ge

me

nt

5,3

11,2

37

4,3

06,4

49

342,4

91

1,0

64,7

00

5,3

71,1

49

4,0

00

To

tal

(59,9

12)

0

5,3

00

150,0

00,0

00

150,0

00,0

00

126,9

90,5

68

8,8

02,1

66

150,0

00,0

00

Pro

ject

Tota

ls 4

,957,6

63

0

28,4

33

23,0

09,4

33

980,2

92

Printe

d:1

1/1

4/2

003

16

Page 17: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Conibear Shellhouse Renovation & Addition

Project Number

1915

Monthly Report

October 2003

Prepared by the Capital Projects Office

Debra Born, Project Manager

17

Page 18: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Conibear Shellhouse Renovation & Addition

PROJECT DESCRIPTION The Conibear Shellhouse Renovation and Addition project will renovate and expand the existing facility from 27,866 gsf to 47,285 gsf. The Shellhouse contains shell storage, crew training facilities, student-athletic dining, tutoring, study and counseling programs for the Department of Intercollegiate Athletics. The west wing and upper floor of the original structure will be demolished to accommodate a new building on three levels. The remaining portions of the existing building will be extensively renovated to meet current building codes and to meet barrier-free requirements. The project Architect is Miller/Hull Partnership, Seattle, WA. The GC/CM is Sellen Construction, Seattle, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview The current schedule is based on the plan to complete bidding of sub-contractor packages before the end of the year and to mobilize for construction on January 13, 2004. Construction is expected to last thru mid-March 2005, and occupancy planned by Opening Day of Boating Season, May 7, 2005. Plans for Next 30 Days Advertisement for sub-contractor package bids is scheduled for November 3. Any addenda to the bidding documents will be issued prior to the end of the month. Shell racks needed for temporary crew facilities will be ordered thru Purchasing and Stores prior to the end of November. The Intercollegiate Department will finalize plans to temporarily relocate staff and building contents. Receipt of the building permit is anticipated. Design Status & Approvals Final revisions were made to the bid documents throughout the month. Sellen’s and Miller Hull’s final estimates were adjusted in early-October to account for costs associated with the University’s review of the bidding documents and the building permit application review. Subsequently the General Contractor/Construction Manger contract was finalized. In late October Capital Projects received PRB approval to proceed with bidding of sub-contractor packages. Construction Accomplishments This Period Sellen Construction presented the University with their final cost estimate based on the final bidding documents. This estimate is the basis for the Guaranteed Construction Cost

18

Page 19: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

(GCC) of $12,162,841. Throughout the rest of the month Sellen prepared the sub-contract package bidding documents for advertisement in early November. PROJECT BUDGET & COST The current project budget is $16,700,000. The current forecast, based on the aforementioned estimate, is $16,976,000. This figure represents all costs associated with the base bid, additive bid alternates, and the wetland mitigation work associated with project #3817. Depending on the outcome of the sub-contract package bids, alternates will be selected prior to sub-contract award so as not to exceed the current budget. CHANGES IN SCOPE Only minor adjustments in scope were made this month to the bidding documents related to comments made during the University’s final review of the construction documents. BUYOUT STATUS Not applicable at this time. SAFETY STATUS Subcontractors will be required to submit their work safety plans prior to the notice to proceed with construction. OPPORTUNITIES & CHALLENGES The challenge for November is to complete planning associated with relocation of programs and contents in the Shellhouse to temporary facilities. CONSTRUCTION CONTRACT ADMINISTRATION A construction manager from within the Capital Projects Office has been assigned to this project. The Capital Projects Office began negotiations with Miller Hull Partnership to identify the scope, costs, and players to be involved with construction management.

19

Page 20: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

1915

PRO

JEC

T C

OST

REP

OR

T - L

evel

2P

roje

ct:1

915

Con

ibea

r She

llhou

se R

enov

atio

n an

d A

dditi

on

Orig

inal

B

udge

tLa

test

App

rove

d B

udge

tC

omm

itted

to

Dat

eA

ctua

l Cos

t to

Dat

eA

ppro

ved

Cha

nges

Pen

ding

C

hang

esE

stim

ate

of U

ncom

mitt

edFo

reca

st T

otal

Cos

tsV

aria

nce

from

La

test

Bud

get

AB

CD

EF

G (H

-C)

HI (

B-H

)B

.

Con

sulta

nt S

ervi

ces

Pre

-Des

ign

Ser

vice

s14

3,76

113

3,92

916

1,12

815

6,62

24,

800

021

,884

183,

012

(49,

083)

Bas

ic S

ervi

ces

894,

410

968,

850

888,

392

608,

958

3,00

30

088

8,39

280

,458

Ext

ra S

ervi

ces

188,

485

599,

355

393,

438

311,

864

312,

510

023

4,65

562

8,09

3(2

8,73

8)O

ther

Ser

vice

s13

9,96

035

6,47

513

3,82

283

,381

11,4

400

245,

886

379,

708

(23,

233)

Des

ign

Ser

vice

s C

ontin

genc

y13

2,42

913

2,82

731

,000

28,2

1231

,000

076

,390

107,

390

25,4

37To

tal B

.

Con

sulta

nt S

ervi

ces

1,49

9,04

52,

191,

436

1,60

7,78

01,

189,

037

362,

753

057

8,81

52,

186,

595

4,84

1

C.

C

onst

ruct

ion

Prim

e C

ontra

ct8,

783,

001

9,75

0,00

00

00

09,

124,

326

9,12

4,32

662

5,67

4O

ther

00

00

00

017

9,68

4(1

79,6

84)

GC

/CM

Item

s11

2,52

31,

048,

334

630,

027

105,

124

00

1,21

7,97

71,

848,

004

(799

,670

)C

onst

ruct

ion

Con

tinge

ncy

511,

861

1,08

9,67

60

00

01,

121,

188

1,12

1,18

8(3

1,51

2)C

onst

ruct

ion

Sal

es T

ax84

1,51

61,

087,

055

13,2

697,

891

960

1,09

1,78

61,

105,

055

(18,

000)

Man

agem

ent R

eser

ve37

7,69

137

4,88

90

00

022

4,24

015

0,64

9To

tal C

.

Con

stru

ctio

n 10

,626

,592

13,3

49,9

5464

3,29

611

3,01

596

012

,555

,277

13,6

02,4

97(2

52,5

43)

F.

Oth

er C

osts

In-P

lant

Ser

vice

s15

,000

15,0

001,

577

827

00

13,4

2315

,000

0U

tiliti

es/T

empo

rary

Fac

ilitie

s50

,000

50,0

000

00

050

,000

50,0

000

Per

mits

59,0

5059

,763

61,2

6261

,262

00

21,8

5683

,118

(23,

355)

Bui

lder

s R

isk

Insu

ranc

e4,

000

4,00

00

00

04,

000

4,00

00

Oth

er C

osts

51,0

0093

,937

6,00

03,

000

3,00

00

64,0

0070

,000

23,9

37To

tal

F.

Oth

er C

osts

179,

050

222,

700

68,8

3965

,089

3,00

00

153,

279

222,

118

582

G.

P

roje

ct M

anag

emen

tC

PO

Man

agem

ent

695,

313

620,

910

620,

910

280,

060

00

062

0,91

00

Oth

er M

anag

emen

t0

225,

000

00

00

245,

000

245,

000

(20,

000)

Tota

l G

.

Pro

ject

Man

agem

ent

695,

313

845,

910

620,

910

280,

060

00

245,

000

865,

910

(20,

000)

Pro

ject

Tot

als

13,0

00,0

0016

,610

,000

2,94

0,82

51,

647,

201

365,

849

013

,532

,371

16,8

77,1

20(2

67,1

20)

H.

S

cope

Cha

nges

3817

Wet

land

s M

itiga

tion

090

,000

00

00

90,0

0090

,000

0To

tal

H.

S

cope

Cha

nges

090

,000

00

00

90,0

0090

,000

0P

roje

ct T

otal

s13

,000

,000

16,7

00,0

002,

940,

825

1,64

7,20

136

5,84

90

13,6

22,3

7116

,967

,120

(267

,120

)

20

Page 21: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

21

Page 22: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

22

Page 23: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Golf Driving Range

Project Number 2758

Monthly Report

October 2003

Prepared by the Capital Projects Office

Jon Lebo, Project Manager

23

Page 24: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Golf Driving Range

PROJECT DESCRIPTION The proposed project will replace the existing 37 foot high safety net with a safety net that will vary in height from 50 feet near the tee-line building to 80 feet along the west, north, and east sides. The tee-line building will be replaced to accommodate 68 tees of which 54 will be covered. Due to site constraints, the tee-line building will be a partial 2-story configuration with classrooms and 22 covered tees on the second level. The landing area will be contoured for better drainage and the installation of target greens. These improvements will improve public safety, access to address use demands, and allow for expanded instructional programs.

The architect is ARC Architects, Seattle, WA. . PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview The project design schedule continues to slip. Based upon the current reprogramming and design effort an additional seven months will be added to the design schedule. The Architect recommends given the scope of the project to increase the construction schedule from six to nine months. Accounting for the design delay and increased construction time, construction is anticipated to be from February 2005 to December 2005 with occupancy in January 2006. Plans for Next 30 Days The Recreational Sports Department will meet with ARC Architects in a series of workshops to develop a revised program and budget to meet the available funds. Shannon & Wilson is working to complete the supplemental Environmental Impact Statement information to be added to the overall EIS. This includes noise, light, and wildlife impacts caused by the improvements to the Golf Range. Design Status & Approvals The Montlake Landfill Oversight Committee on October 15, 2003 approved the recommendations of the subcommittee on the proposed grading plan. The recommendations established performance limits on the amount of lateral and vertical settlement as result of additional fill material added to the landfill to improve drainage and sightlines. Construction Accomplishments This Period Not applicable at this time.

24

Page 25: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT BUDGET & COST There is no change to the total project cost of $8.0 million or the construction budget of $5.69 million. The project team will perform value engineering and review the project scope to bring the project within budget. CHANGES IN SCOPE The project scope will be modified as necessary along with value engineering to help bring the project within budget. BUYOUT STATUS Not applicable at this time. SAFETY STATUS Not applicable at this time. Construction has not started on this project. OPPORTUNITIES & CHALLENGES The design and budget continue to be a challenge on the project. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time. The project is in design.

25

Page 26: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

26

Page 27: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.2

758

Pro

ject

:2758 G

OLF

DR

IVIN

G R

AN

GE

Golf

Drivi

ng R

ange -

Im

pro

vem

ents

PR

OJE

CT

CO

ST

RE

PO

RT

- L

evel 2

Origin

al

Budget

Com

mitt

ed

to D

ate

Act

ual C

ost

to

Date

Fore

cast

T

ota

l C

ost

s

Variance

from

Late

st B

udget

Est

imate

of

Uncom

mitt

ed

Appro

ved

Changes

Pendin

g

Changes

AB

CD

EF

G (

H-C

)H

I (B

-H)

Late

st

Appro

ved

Budget

B. C

onsultant S

erv

ices

35

0,0

00

P

re-D

esi

gn

Se

rvic

es

35

0,0

00

4

61

,91

6

41

1,6

37

0

4

61

,91

6

15

3,2

48

(1

11

,91

6)

0

49

1,8

92

B

asi

c S

erv

ice

s 4

91

,89

2

15

5,0

45

8

7,9

82

3

36

,84

7

49

1,8

92

0

0

0

42

1,8

10

E

xtra

Se

rvic

es

42

1,8

10

1

97

,08

5

16

8,0

35

2

57

,87

5

45

4,9

60

6

2,3

29

(3

3,1

50

) 0

11

5,4

64

O

the

r S

erv

ice

s 1

15

,46

4

40

,62

9

40

,62

9

11

3,9

99

1

54

,62

8

0

(39

,16

4)

0

97

,66

0

De

sig

n S

erv

ice

s C

on

ting

en

cy 9

7,6

60

0

0

4

8,4

71

4

8,4

71

0

4

9,1

89

0

1,4

76,8

26

B.

Co

nsu

ltan

t S

erv

ice

s 1

,476,8

26

854,6

75

708,2

83

757,1

92

1,6

11,8

67

215,5

77

To

tal

(135,0

41)

0

C. C

onst

ruct

ion

4,4

34

,04

7

Prim

e C

on

tra

ct

4,4

34

,04

7

0

0

4,4

34

,04

7

4,4

34

,04

7

0

0

0

13

1,4

98

O

the

r 1

31

,49

8

0

0

13

1,4

98

1

31

,49

8

0

0

0

44

7,1

43

C

on

stru

ctio

n C

on

ting

en

cy 4

47

,14

3

0

0

44

7,1

43

4

47

,14

3

0

0

0

45

2,4

68

C

on

stru

ctio

n S

ale

s T

ax

45

2,4

68

0

0

4

52

,46

8

45

2,4

68

0

0

0

22

5,5

50

M

an

ag

em

en

t R

ese

rve

22

5,5

50

0

0

9

0,5

09

9

0,5

09

0

1

35

,04

1

0

5,6

90,7

06

C.

Co

nst

ruct

ion

5

,690,7

06

0

0

5,5

55,6

65

5,5

55,6

65

0

To

tal

135,0

41

0

D. E

quip

ment

10

5,5

72

F

urn

ish

ing

s 1

05

,57

2

0

0

10

5,5

72

1

05

,57

2

0

0

0

9,2

91

E

qu

ipm

en

t/F

urn

ish

ing

s S

ale

s T

ax

9,2

91

0

0

9

,29

1

9,2

91

0

0

0

114,8

63

D.

Eq

uip

me

nt

114,8

63

0

0

114,8

63

114,8

63

0

To

tal

0

0

F. O

ther

Cost

s 1

5,8

36

In

-Pla

nt

Se

rvic

es

15

,83

6

10

,82

3

10

,73

4

5,0

13

1

5,8

36

0

0

0

34

,52

8

Pe

rmits

34

,52

8

1,9

26

1

,92

6

32

,60

2

34

,52

8

0

0

0

10

,55

7

Bu

ilde

rs R

isk

Insu

ran

ce 1

0,5

57

0

0

1

0,5

57

1

0,5

57

0

0

0

10

5,5

73

O

the

r C

ost

s 1

05

,57

3

0

0

10

5,5

73

1

05

,57

3

0

0

0

166,4

94

F.

Oth

er

Co

sts

166,4

94

12,7

50

12,6

60

153,7

44

166,4

94

0

To

tal

0

0

G. P

roje

ct M

anagem

ent

50

0,9

88

C

PO

Ma

na

ge

me

nt

50

0,9

88

5

00

,98

8

49

,19

8

0

50

0,9

88

0

0

0

50

,12

3

Oth

er

Co

sts

50

,12

3

0

0

50

,12

3

50

,12

3

0

0

0

551,1

11

G.

Pro

ject

Ma

na

ge

me

nt

551,1

11

500,9

88

49,1

98

50,1

23

551,1

11

0

To

tal

0

0

8,0

00,0

00

8,0

00,0

00

1,3

68,4

13

770,1

41

8,0

00,0

00

Pro

ject

Tota

ls 2

15,5

77

0

0

6,6

31,5

87

Printe

d:1

1/4

/2003

27

Page 28: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

28

Page 29: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Guggenheim Hall

Project Number 10419

Monthly Report

October 2003

Prepared by the Capital Projects Office

Lara Branigan, Project Manager

29

Page 30: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Guggenheim Hall

PROJECT DESCRIPTION This project is proposed as a renovation of Guggenheim Hall. Constructed in 1929, Guggenheim Hall occupies a central location on campus facing Drumheller Fountain. It currently houses the Department of Aeronautics and Astronautics, the Department of Applied Math and several general assignment classrooms including a major auditorium. The 56,200 gross square foot building has never had a significant renovation. This renovation would address seismic deficiencies, accessibility including providing an elevator, exterior shell renovation, upgrading all major building systems, asbestos abatement, and updates to the facility needed to improve instruction and research. . PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Contract negotiations with Bassetti Architects are nearly final with contract preparation underway. The Project Agreement has been reviewed by all parties and the final draft is being circulated for signature. Pre-design is expected to begin in November 2003 with completion of programming scheduled in April 2004. Design is expected to extend through summer 2005 with construction following immediately for approximately two years. Plans for Next 30 Days During the month of November a kick-off meeting will be held with Programming Committee and the Oversight Committee to set project priorities. The site programming Committee will hold their first meeting and the Programming Committee will begin their meetings with the consultant team. The Architects and Engineers will also begin their assessment of the building condition guided by reports prepared by Engineering Services for their use. Design Status & Approvals At the end of the programming phase, Capital Projects Office will report to the signatories of the Project Agreement the status of the project scope, budget, and schedule for approval to proceed with design. Construction is contingent upon funding by the Legislature.

Construction Accomplishments This Period Not applicable at this time.

30

Page 31: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT BUDGET & COST Funding for pre-design and design in the amount of $3,312,000 has been allocated by the State Legislature based on a project budget of $26,312,948. CHANGES IN SCOPE No changes in the project scope this month. BUYOUT STATUS Not applicable at this time. SAFETY STATUS Not applicable at this time. Construction has not started on this project. OPPORTUNITIES & CHALLENGES The challenge for the coming month is to set the priorities for the renovation and to set up a process for the committee to use in working to reflect these priorities in the study. The team has the opportunity to do an excellent evaluation of the building’s existing condition due to the information and assistance being provided by Engineering Services. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time. The project is in pre-design.

31

Page 32: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

32

Page 33: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Harborview Bond Program

Project Number 3927

Monthly Report

October 2003

Prepared by the Capital Projects Office

Joel Matulys, Project Manager

33

Page 34: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Harborview Bond Program

PROJECT DESCRIPTION As the premier Level-One Trauma Center serving a four-state region, Harborview Medical Center (HMC) is relied on to function during all states of emergencies. In order to ensure that the facility continues to meet the demands and responsibilities required, Harborview Medical Center has embarked on a long-range capital program for the period 2000 – 2010. The goals of the Program are to remedy significant seismic deficiencies, and address the need for expanded healthcare capacity. The project is under the joint oversight of King County, the University of Washington, and the Harborview Board of Trustees through the Bond Oversight Committee (BOC) with voting members from each of the three entities. Vanir Construction Management, Inc. provides independent technical oversight support to the BOC. The University’s Capital Projects Office is the project manager. Bond Program Projects include: Project 1: Ninth and Jefferson Building (NJB) New construction of a multi-purpose facility to house specialized services such as the King County Medical Examiners Office (KCME), research laboratories, dry labs, clinical services, Involuntary Treatment Act (ITA) Courtroom, retail, building lobby and five floors of underground parking. Project 2: Inpatient Expansion Building (IEB) and Seismic Upgrade Seismic improvements to the North Wing Trauma center tower. These improvements will meet FEMA Immediate Occupancy requirements after a code level seismic event, which exceeds the current seismic design for hospitals. New construction includes an inpatient building, adjoined to the existing facility by a bridge building. Project 3: Proposed Demolition of Harborview Hall and East Clinic (South Wing) Demolition of the seismically unsound East Clinic and potential demolition of Harborview Hall. The project architect is NBBJ West Limited Partnership, Seattle, WA. The GC/CM is Turner Construction, Seattle, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview The overall project is on schedule, based on the revised schedule that reflects the approved change in project scope for NJB. DD phase for Projects 2 and 3 is underway. Reprogramming for the NJB has taken longer than planned; however, it is anticipated that the delay will be mitigated and the DD phase for the NJB will be completed on time.

34

Page 35: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Plans for Next 30 Days Continue design meetings with client on all projects. Coordinate with utilities about size and location of steam and electrical service. Continue concrete panel testing at UW CE Lab. Work to mitigate schedule impacts. Design Status & Approvals Design Development for IEB, EC and HH Demolition projects are underway. The Acceptance Panel had also approved the SD submittal for NJB’s systems. These are being reviewed as we redesign the building for the approved scope increase. Construction Accomplishments This Period Construction has not started on this project. PROJECT BUDGET & COST This project has a fixed funding limit available from the sale of King County voter-approved bonds totaling $193 million. These plus the interest earnings and HMC reserves, created an original $263.2 million project budget. In August 2003, the King County Council approved the proposal to add one floor of parking and two finished floors to the NJB. This adds approximately 150 cars to the planned garage resulting in approximately 630 stalls; and increases the parking to 226,000 square feet. It also increases the above grade building to five floors totaling 190,000 square feet. This scope change is consistent with the Major Institution Master Plan, Environmental Impact Statement and the voter approved bond. The total cost of such additions is budgeted at $29.6 million. The overall project budget increased to $292.8 million. CHANGES IN SCOPE None this period. BUYOUT STATUS Not applicable at this time. SAFETY STATUS Not applicable. OPPORTUNITIES & CHALLENGES

• To mitigate the impact of the revised NJB programming and design work for the additional parking, shell space and tenant improvements and return to the original schedule by early DD without additional delay or expense.

• To mitigate the cost impact of the soils remediation effort at the NJB site.

35

Page 36: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

36

Page 37: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

3927

PRO

JEC

T C

OST

REP

OR

T - L

evel

2P

roje

ct:H

AR

BO

RV

IEW

BO

ND

PR

OG

RA

M

Orig

inal

B

udge

tLa

test

App

rove

d B

udge

tC

omm

itted

to

Dat

eA

ctua

l Cos

t to

Dat

eA

ppro

ved

Cha

nges

Pen

ding

C

hang

esE

stim

ate

of U

ncom

mitt

edFo

reca

st T

otal

Cos

tsV

aria

nce

from

La

test

Bud

get

AB

CD

EF

G (H

-C)

HI (

B-H

)A

.

Acq

uisi

tion

Acq

uisi

tion

Cos

t2,

000,

000

2,00

0,00

00

00

02,

000,

000

2,00

0,00

00

Tota

l A.

A

cqui

sitio

n2,

000,

000

2,00

0,00

00

00

02,

000,

000

2,00

0,00

00

B.

C

onsu

ltant

Ser

vice

sP

re-D

esig

n S

ervi

ces

2,93

2,00

02,

932,

000

4,13

8,69

03,

841,

775

3,72

3,36

70

(221

,995

)3,

916,

695

(984

,695

)B

asic

Ser

vice

s12

,144

,044

12,1

44,0

442,

981,

624

1,66

5,78

765

,118

08,

993,

857

11,9

75,4

8116

8,56

3E

xtra

Ser

vice

s11

,436

,971

11,4

36,9

714,

390,

909

2,10

4,67

73,

560,

700

07,

409,

655

11,8

00,5

64(3

63,5

93)

Oth

er S

ervi

ces

2,36

0,00

02,

360,

000

1,80

060

00

02,

360,

800

2,36

2,60

0(2

,600

)D

esig

n S

ervi

ces

Con

tinge

ncy

4,07

4,78

54,

074,

785

00

00

3,78

5,75

03,

785,

750

289,

035

Tota

l B.

C

onsu

ltant

Ser

vice

s32

,947

,800

32,9

47,8

0011

,513

,023

7,61

2,83

97,

349,

185

022

,328

,067

33,8

41,0

90(8

93,2

90)

C.

C

onst

ruct

ion

Prim

e C

ontra

ct13

3,07

4,17

313

3,07

4,17

30

00

013

3,07

4,17

313

3,07

4,17

30

Oth

er

24,2

93,6

9224

,293

,692

701,

751

130,

377

27,8

340

23,4

66,0

3424

,167

,785

125,

907

Con

stru

ctio

n C

ontin

genc

y13

,288

,189

13,2

88,1

890

00

013

,288

,189

13,2

88,1

890

Con

stru

ctio

n S

ales

Tax

15,4

95,8

7515

,495

,875

60,7

207,

918

00

15,4

24,1

0315

,484

,823

11,0

52M

anag

emen

t Res

erve

8,40

3,45

98,

403,

459

00

00

7,75

3,45

97,

753,

459

650,

000

Tota

l C.

C

onst

ruct

ion

194,

555,

388

194,

555,

388

762,

471

138,

295

27,8

340

193,

005,

958

193,

768,

429

786,

959

D.

E

quip

men

t0

Furn

iush

ings

14,5

00,0

0014

,500

,000

00

00

14,5

00,0

0014

,500

,000

0E

quip

men

t/Fur

nish

ings

Sal

es T

ax1,

276,

000

1,27

6,00

00

00

01,

276,

000

1,27

6,00

00

Tota

l D.

E

quip

men

t15

,776

,000

15,7

76,0

000

00

015

,776

,000

15,7

76,0

000

E.

A

rtwor

kA

rtwor

k2,

000,

000

2,00

0,00

00

00

02,

000,

000

2,00

0,00

00

Tota

l E.

A

rtwor

k2,

000,

000

2,00

0,00

00

00

02,

000,

000

2,00

0,00

00

F.

Oth

er C

osts

In-P

lant

Ser

vice

s30

0,00

030

0,00

00

00

030

0,00

030

0,00

00

Per

mits

1,56

0,00

01,

560,

000

38,9

0738

,907

00

1,52

1,09

31,

560,

000

0B

uild

ers

Ris

k In

sura

nce

2,68

5,00

02,

685,

000

00

00

2,68

5,00

02,

685,

000

0O

ther

Cos

ts2,

653,

000

2,65

3,00

00

00

02,

621,

030

2,62

1,03

031

,970

Tota

l F.

O

ther

Cos

ts7,

198,

000

7,19

8,00

038

,907

38,9

070

07,

127,

123

7,16

6,03

031

,970

G.

P

roje

ct M

anag

emen

tC

PO

Man

agem

ent

8,04

0,81

28,

040,

812

8,04

0,81

20

00

08,

040,

812

0O

ther

Man

agem

ent

682,

000

682,

000

686,

976

362,

572

(3,0

25)

0(1

49,1

09)

537,

867

144,

133

Tota

l G

.

Pro

ject

Man

agem

ent

8,72

2,81

28,

722,

812

8,72

7,78

836

2,57

2(3

,025

)0

(149

,109

)8,

578,

679

144,

133

Pro

ject

Tot

als

263,

200,

000

263,

200,

000

21,0

42,1

898,

152,

613

7,37

3,99

40

242,

088,

039

263,

130,

228

69,7

72

H.

S

cope

Cha

nges

NJB

Add

ition

s0

29,6

00,0

000

00

029

,600

,000

29,6

00,0

000

Tota

l H

.

Sco

pe C

hang

es0

29,6

00,0

000

00

029

,600

,000

29,6

00,0

000

Pro

ject

Tot

als

263,

200,

000

292,

800,

000

21,0

42,1

898,

152,

613

7,37

3,99

40

271,

688,

039

292,

730,

228

69,7

72

37

Page 38: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

38

Page 39: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

IMA Expansion Recreational Sports-Fitness Facility

Project Number

2120

Monthly Report

October 2003

Prepared by the Capital Projects Office

Jon Lebo, Project Manager

39

Page 40: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY IMA Expansion

Recreational Sports-Fitness Facility PROJECT DESCRIPTION The scope of this project is to expand and renovate a portion of the existing Intramural Activities Building (IMA). Approximately 40,000 gross square feet is being renovated; the building’s structural system is being upgraded to increase seismic resistance, and air conditioning is being added. An addition of approximately 95,000 gross square feet is being constructed. The project to convert the natural grass field north of the IMA into a lighted artificial turf field is now part of the IMA project and has been completed. The project architect is BOORA Architects, Portland OR. The GC/CM is Hoffman Construction, Seattle, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Change order work is still being finished and due to late design changes, the lobby glass wall and gates/turnstile are not yet complete. With the exception of the lobby glass wall, which may not be complete until January, as the manufacturer can only produce at the rate of two panels a week (15 total panels), the University is negotiating an extension of the contract for substantial completion to approximately November 15, 2003. The University took beneficial occupancy of the addition on September 29. The landscape work is nearing completion, it was delayed when the first subcontractor defaulted on its work and had to be replaced. Plans for Next 30 Days Hoffman Construction is working to complete the landscaping. Work has started on the glass lobby wall with the first glass panel installed and approved for further production. Minor work and punch list items are being completed. The turnstiles arrived and will be installed, still awaiting exit gates. Design Status & Approvals Construction Administration tasks by BOORA are ongoing. Construction Accomplishments This Period Work continued on interior finishes for change order work and completion of punch list items. Housing and Food Services opened café/deli operations on October 27th. Installation of vinyl stair treads and risers is complete. Finish work in the lounge area (temporary IMA office area) was completed. Site work continued at the entry plaza, E6 parking area and landscape areas. Asphalt paving at walkways and parking area was completed and striped. Back-punch and verification of completed punch list items is

40

Page 41: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

progressing well. Commissioning is complete. The HVAC system has been balanced. Change order work on the fire alarm system for the existing air handler units is progressing well. PROJECT BUDGET & COST No changes in project costs or budget this period. CHANGES IN SCOPE Approximately $840,000 in additional work for upgrades to the women’s locker room; conduit and wire to plaza outlets; revised handrails; additional magnetic hold opens for activity spaces and other minor improvements have been identified. It is proposed that this additional work be completed as a change order to Hoffman’s contract. The funding for this work will come from additional interest on the bonds that paid for the project. Approval of the Executive Vice President is required before this work may begin. BUYOUT STATUS The buyout is 100% complete with savings of $3,195,860. SAFETY STATUS There was one recordable incident this last month.

Safety Statistics This Month Project To DateAverage Daily Work Force 28Lost Time Incidents 0 2Recordable Incidents 0 12Total Hours Worked All Crafts 4,375 276,445Project Total Incidence Rate * 0 10.1* Incidence Rate = (# of Incidents x 200,000 hrs) / (# of hours worked)

OPPORTUNITIES & CHALLENGES Negotiating the project time extension and overhead costs from Hoffman and its subcontractors is an ongoing issue. CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number ValueChange Orders Approved 566 $3,869,702Change Order Proposals Pending* 83 $1,191,013Change Order Requests Pending 0 $0Team Change Memos Approved 102 $774,847

*includes open field work orders Requests for Information to date Number Avg. TurnaroundRFI’s 1272 7 daysSubmittals to date Number Avg. TurnaroundSubmittals 485 10 days

Disputes Review Board Status There are no issues under consideration or anticipated for the DRB.

41

Page 42: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

42

Page 43: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

2120

PRO

JEC

T C

OST

REP

OR

T - L

evel

2P

roje

ct:2

120

IMA

Exp

ansi

on R

ecre

atio

nal S

ports

Pro

gram

Orig

inal

B

udge

tLa

test

App

rove

d B

udge

tC

omm

itted

to D

ate

Act

ual C

ost t

o D

ate

App

rove

d C

hang

esP

endi

ng C

hang

esE

stim

ate

of U

ncom

mitt

edFo

reca

st T

otal

Cos

tsV

aria

nce

from

La

test

Bud

get

AB

CD

FG

H (I

-C)

IJ

(B-I)

B.

C

onsu

ltant

Ser

vice

sP

re-D

esig

n S

ervi

ces

340,

000

575,

000

579,

406

579,

406

00

057

9,40

6(4

,406

)B

asic

Ser

vice

s1,

724,

000

2,20

3,75

02,

075,

119

2,12

8,22

3(6

4,48

9)0

02,

075,

119

128,

631

Ext

ra S

ervi

ces

790,

795

702,

000

723,

168

653,

984

177,

947

141

141

723,

309

(21,

309)

Oth

er S

ervi

ces

501,

250

619,

911

646,

461

585,

846

110,

698

010

6,30

475

2,76

5(1

32,8

54)

Des

ign

Ser

vice

s C

ontin

genc

y96

,640

97,6

871,

006,

012

961,

964

1,00

6,01

20

01,

006,

012

(908

,325

)To

tal

B.

C

onsu

ltant

Ser

vice

s3,

452,

685

4,19

8,34

85,

030,

166

4,90

9,42

31,

230,

168

141

106,

445

5,13

6,61

1(9

38,2

63)

C.

C

onst

ruct

ion

Prim

e C

ontra

ct20

,062

,000

20,4

55,7

2619

,065

,986

18,5

95,5

720

00

19,0

65,9

861,

389,

740

Oth

er

027

5,15

027

4,43

722

8,14

30

00

274,

437

713

GC

/CM

Item

s25

0,00

04,

131,

002

5,14

3,60

14,

614,

715

00

100,

000

5,14

3,60

1(1

,012

,599

)C

onst

ruct

ion

Con

tinge

ncy

2,17

3,30

72,

138,

262

3,04

5,37

02,

597,

859

1,65

5,63

01,

827,

201

2,35

4,63

05,

400,

000

(3,2

61,7

38)

Con

stru

ctio

n S

ales

Tax

1,74

6,83

22,

322,

012

2,51

6,23

02,

386,

821

266,

601

131,

973

131,

973

2,64

8,20

3(3

26,1

91)

Tota

lC

.

Con

stru

ctio

n 24

,232

,139

29,3

22,1

5230

,045

,624

28,4

23,1

101,

922,

231

1,95

9,17

42,

586,

603

32,5

32,2

27(3

,210

,075

)

D.

E

quip

men

tE

quip

men

t0

060

2,08

539

5,90

30

097

,915

700,

000

(700

,000

)Fu

rnis

hing

s0

025

4,45

411

4,77

254

20

145,

546

400,

000

(400

,000

)E

quip

men

t/Fur

nish

ings

Sal

es T

ax0

068

,600

29,9

3470

024

,006

92,6

06(9

2,60

6)To

tal

D.

E

quip

men

t0

092

5,13

954

0,60

961

20

267,

467

1,19

2,60

6(1

,192

,606

)

F.

Oth

er C

osts

In-P

lant

Ser

vice

s74

,638

134,

000

173,

038

164,

189

00

76,9

6225

0,00

0(1

16,0

00)

Util

ities

/Tem

pora

ry F

acili

ties

00

252,

933

252,

933

00

025

2,93

3(2

52,9

33)

Per

mits

85,7

2885

,728

110,

239

110,

031

00

011

0,23

9(2

4,51

1)B

uild

ers

Ris

k In

sura

nce

17,0

0017

,000

34,3

4234

,342

00

034

,342

(17,

342)

Oth

er C

osts

51,0

007,

220,

000

35,2

8232

,678

26,1

000

035

,282

7,18

4,71

8To

tal

F.

Oth

er C

osts

228,

366

7,45

6,72

860

5,83

459

4,17

326

,100

076

,962

682,

796

6,77

3,93

2

G.

P

roje

ct M

anag

emen

tC

PO

Man

agem

ent

885,

906

1,32

2,77

21,

345,

276

1,18

3,84

30

00

1,34

5,27

6(2

2,50

4)O

ther

Man

agem

ent

00

438,

320

376,

360

00

043

8,32

0(4

38,3

20)

Tota

lG

.

Pro

ject

Man

agem

ent

885,

906

1,32

2,77

21,

783,

596

1,56

0,20

30

00

1,78

3,59

6(4

60,8

24)

Pro

ject

Tot

als

28,7

99,0

9642

,300

,000

38,3

90,3

5836

,027

,518

3,17

9,11

11,

959,

315

3,03

7,47

741

,327

,835

972,

165

H.

S

cope

Cha

nges

Fund

ed S

cope

Cha

nges

033

9,70

033

9,70

033

9,70

033

9,70

00

033

9,70

00

SC

L C

ontri

butio

n0

77,8

750

00

00

077

,875

Unf

unde

d S

cope

Cha

nges

00

1,05

0,04

01,

050,

040

1,05

0,04

00

01,

050,

040

(1,0

50,0

40)

Tota

lH

. S

cope

Cha

nges

041

7,57

51,

389,

740

1,38

9,74

01,

389,

740

00

1,38

9,74

0(9

72,1

65)

Pro

ject

Tot

als

28,7

99,0

9642

,717

,575

39,7

80,0

9837

,417

,258

4,56

8,85

11,

959,

315

3,03

7,47

742

,717

,575

(0)

43

Page 44: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT PHOTOS

East Elevation West Elevation

Third floor multi purpose room West Elevation at entry

Café Deli at entry Entry way Terrazzo and glass wall construction

44

Page 45: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Johnson Hall Renovation

Project Number 10106

Monthly Report

October 2003

Prepared by the Capital Projects Office

Jon Lebo, Project Manager

45

Page 46: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Johnson Hall Renovation

PROJECT DESCRIPTION The Johnson Hall laboratory building was constructed in 1930; in 1948 an addition to the building was constructed resulting in the approximately 121,500 gross square feet facility. Johnson Hall currently houses programs in Earth and Space Sciences, Biology, and approximately 8,500 square feet of general assignment classrooms totaling approximately 635 seats. The renovation will include upgrading all major building systems, correcting accessibility, seismic, and life and safety code conditions, performing hazardous materials abatement, and providing updated facilities for instruction and research programs. The project architect is Arai/Jackson Architects and Planners, Seattle, WA. The GC/CM is Skanska USA, Seattle, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview The 100% Construction Documents for the demolition and hazardous material phase of the work were submitted a week late. Fortunately this work is not on the critical path. The University made a preliminary review of the Design Development (DD) submission due on October 27 and asked the design team to continue working as the submission was incomplete. Arai/Jackson proposes that the DD package will be ready for submission on November 17; a three week delay. Coupled with the previous 2 week delay of the project the overall schedule is 5 weeks behind. Two of these weeks might be mitigated by starting the Construction Document phase when the DD package is submitted. Arai/Jackson also proposed to reduce the necessary design time for the Construction Document phase to offset another week. To test the cost of accelerating the construction phase to offset the design delays we requested Skanska to develop a construction schedule that allows the University to occupy Johnson Hall for the start of fall quarter 2005 and determine the cost impacts of a shortened schedule. Skanska should be able to complete their analysis by the end of November. Plans for Next 30 Days Review the 100% CD demolition and hazardous materials drawings. Begin the review of the Design Development submission. Skanska and Arai/Jackson will perform costs estimates of these packages. Skanska’s reconciled estimate will be the basis for the Guaranteed Construction Cost (GCC). Skanska will perform more investigations of the brick tie conditions, and do a mock-up of the abatement, repair, and painting of a couple of existing windows to better define the scope and cost of the work. Skanska is also

46

Page 47: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

working with the UW’s abatement contractor to investigate other possible locations of asbestos. Design Status & Approvals The Design Development (DD) phase is nearing completion. The DD submittal was postponed 3 weeks to allow the design team to complete the required design elements and is now scheduled for submission on November 17. The building interior design is lagging and may be another 6 – 8 weeks until it is complete. The demolition and hazardous materials package was completed and submitted for review. The Design Review Board approved the proposed new southeast entry from Rainier Vista without comment. Construction Accomplishments This Period Skanska USA (GC/CM) preformed additional exploratory investigations. Skanska performed mapping of brick ties on the 1930 building to determine if the brick ties were uniformly and closely spaced to meet current codes. Preliminary indications show that the brick ties are spaced to meet code. Further investigations will be performed to determine the condition and adequacy of the ties. Additional, asbestos investigations were performed to determine their locations and condition. Skanska located additional site utilities and assisted the surveyors in mapping their locations. Skanska is working with a painting subcontractor and asbestos abatement contractor to determine the cost and scope of retaining the existing windows. PROJECT BUDGET & COST

No changes to the project budget or cost, awaiting the new cost estimates from Arai/Jackson and Skanska. CHANGES IN SCOPE At the request of Facilities Services an additive alternate was identified and incorporated into the design to clean and seal all of the building masonry and replace a brick ledger angle and repair some cast stone on the west side at the 4th floor near the auditorium. Funding for this work will be provided by Facilities Services. This work is estimated to be approximately $400,000. CASPO has approved the addition of the Quaternary Research Center (QRC) cooling tower replacement as part of the Johnson Hall project. The cooling tower will replace the existing cooling tower in the courtyard space. The new location will be on the roof of Johnson Hall. The current estimated cost of the tower is $450,000 - $500,000. We anticipate the cost will be reduced due to the design change to eliminate the new roof well. The tower in its new location will not require a well. Based upon the next cost estimate this work and the masonry cleaning will be added to the project budget.

47

Page 48: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

CASPO also approved funding to assist the Department of Earth & Space Sciences to develop design concepts and preliminary cost estimates for proposed donor improvements to the building. BUYOUT STATUS Not applicable. SAFETY STATUS Not applicable OPPORTUNITIES & CHALLENGES The investigations of the brick ties on the 1930 building may afford an opportunity to greatly reduce the amount of additional anchors required to secure the brick and stone to the building. Performing a painting mock-up of the window will better define the scope and cost. Maintaining the project schedule continues to be a major challenge. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time.

48

Page 49: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

49

Page 50: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

1010

6PR

OJE

CT

CO

ST R

EPO

RT

- Lev

el 2

Pro

ject

:101

06 J

ohns

on H

all R

enov

atio

n

Orig

inal

B

udge

tLa

test

App

rove

d B

udge

tC

omm

itted

to

Dat

eA

ctua

l Cos

t to

Dat

eA

ppro

ved

Cha

nges

Pen

ding

C

hang

esE

stim

ate

of U

ncom

mitt

edFo

reca

st T

otal

Cos

tsV

aria

nce

from

La

test

Bud

get

AB

CD

EF

G (H

-C)

HI (

B-H

)B

.

Con

sulta

nt S

ervi

ces

Pre

-Des

ign

Ser

vice

s66

2,91

866

2,91

862

7,61

461

1,83

323

0,41

70

062

7,61

435

,304

Bas

ic S

ervi

ces

2,70

5,87

62,

783,

426

869,

945

558,

235

44,9

990

1,91

3,48

12,

783,

426

0E

xtra

Ser

vice

s1,

091,

030

1,19

9,69

277

2,00

013

2,42

473

0,35

50

506,

972

1,27

8,97

2(7

9,28

0)O

ther

Ser

vice

s1,

015,

143

1,02

7,26

476

076

00

01,

026,

504

1,02

7,26

40

Des

ign

Ser

vice

s C

ontin

genc

y99

5,54

492

2,17

90

00

082

2,10

082

2,10

010

0,07

9To

tal B

.

Con

sulta

nt S

ervi

ces

6,47

0,51

16,

595,

479

2,27

0,31

91,

303,

252

1,00

5,77

10

4,26

9,05

76,

539,

376

56,1

03

C.

C

onst

ruct

ion

Prim

e C

ontra

ct31

,462

,184

28,9

19,5

262,

585

2,58

50

028

,916

,941

28,9

19,5

260

GC

/CM

Item

s26

7,70

73,

127,

391

249,

828

67,0

4560

,188

03,

027,

563

3,27

7,39

1(1

50,0

00)

Con

stru

ctio

n S

ales

Tax

3,33

2,12

13,

296,

559

16,6

685,

900

00

3,27

9,89

13,

296,

559

0M

anag

emen

t Res

erve

2,35

9,66

463

6,93

80

00

01,

009,

703

1,00

9,70

3(3

72,7

65)

Oth

er C

osts

3,77

5,46

24,

777,

038

00

00

4,77

7,03

84,

777,

038

0To

tal C

.

Con

stru

ctio

n 41

,197

,138

40,7

57,4

5226

9,08

175

,530

60,1

880

41,0

11,1

3641

,280

,217

(522

,765

)

D.

E

quip

men

tE

quip

men

t0

428,

917

00

00

00

428,

917

Furn

ishi

ngs

1,39

2,07

496

5,07

50

00

096

5,07

596

5,07

50

Equ

ipm

ent /

Furn

ishi

ngs

Sal

es T

ax12

2,50

312

2,67

20

00

084

,927

84,9

2737

,745

Tota

l D.

E

quip

men

t1,

514,

577

1,51

6,66

40

00

01,

050,

002

1,05

0,00

246

6,66

2

E.

A

rtwor

kA

rtwor

k14

6,90

627

0,67

30

00

027

0,67

327

0,67

30

Tota

l E.

A

rtwor

k14

6,90

627

0,67

30

00

027

0,67

327

0,67

30

F.

Oth

er C

osts

In-P

lant

Ser

vice

s13

0,83

120

4,06

96,

214

214

00

197,

855

204,

069

0U

tiliti

es/T

empo

rary

Fac

ilitie

s20

,933

74,4

030

00

074

,403

74,4

030

Per

mits

146,

531

146,

828

450

450

00

146,

378

146,

828

0B

uild

ers

Ris

k In

sura

nce

57,5

6657

,682

00

00

57,6

8257

,682

0O

ther

Cos

ts1,

653,

705

1,62

2,96

50

00

01,

622,

261

1,62

2,96

50

Tota

l F.

O

ther

Cos

ts2,

009,

566

2,10

5,94

76,

664

664

00

2,09

8,57

92,

105,

947

0

G.

P

roje

ct M

anag

emen

tC

PO

Man

agem

ent

2,61

6,88

32,

659,

070

2,65

9,07

013

4,19

4(2

4,80

6)0

02,

659,

070

0O

ther

Man

agem

ent

350,

000

400,

000

00

00

400,

000

400,

000

0O

ther

Cos

ts10

0,00

010

0,00

00

00

010

0,00

010

0,00

00

Tota

l G

.

Pro

ject

Man

agem

ent

3,06

6,88

33,

159,

070

2,65

9,07

013

4,19

4(2

4,80

6)0

500,

000

3,15

9,07

00

Pro

ject

Tot

als

54,4

05,5

8154

,405

,285

5,20

5,13

41,

513,

640

1,04

1,15

30

49,1

99,4

4754

,405

,285

0

H.

S

cope

Cha

nges

Mas

onry

Cle

anin

g R

epai

rs0

400,

000

00

00

400,

000

400,

000

0Q

RC

Coo

ling

Tow

er0

500,

000

00

00

500,

000

500,

000

0To

tal

H.

S

cope

Cha

nges

050

0,00

00

00

050

0,00

050

0,00

00

Pro

ject

Tot

als

54,4

05,5

8154

,905

,285

5,20

5,13

41,

513,

640

1,04

1,15

30

49,6

99,4

4754

,905

,285

0

50

Page 51: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Merrill Hall Replacement Project

Project Number 3757

Monthly Report October 2003

Prepared by the Capital Projects Office

Norm Menter, Project Manager

51

Page 52: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Merrill Hall Replacement Project

PROJECT DESCRIPTION This project provides for replacement of Merrill Hall, the keystone facility for the Center for Urban Horticulture (CUH), within the College of Forest Resources. The Center is an applied research and teaching facility. The facility houses outreach programs, administrative offices, the Elizabeth C. Miller Horticultural Library, student study space, and ecological research labs. The structure was a 17,022-sf, two-story, wood framed construction that was extensively damaged in an arson fire. 70% of the structure required demolition. In the area not demolished, the structure was smoke sealed. Temporary enclosures were erected to protect the facility from weather. This work was complete by July 24, 2001 under an emergency public works contract. This project will replace the structure and upgrade the facility to current program and building/fire/safety code requirements. A notable element of the project is enhanced security and access control. Private donations are being sought to fund potential additive or future program elements. The project architect is Miller/Hull Partnership, Seattle, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview The construction process started as planned with owner notice to proceed given to CDK Construction on September 15. Substantial Completion of construction has been set by contract as August 16, 2004. As of November 1, 47 days of the 335 day construction have elapsed or slightly less than 14% of the construction time. Design Status & Approvals The design process is complete. All required approvals have been received by the project. Construction Accomplishments This Period The site excavation is 30% complete, site utilities 80%, plumbing slab rough-in 70%, electrical slab rough-in 10%, concrete & steel associated with the mechanical plenum are 30%, general building excavation for structural footings has just begun. Submittals are being executed. The site is secure. Plans for Next 30 Days Excavation, forming, reinforcement and placement of concrete for foundations will dominate the construction activity plans for the next month. Installation of underground building and site utilities will be mainly completed with the exception of the storm water collection vault. The vault will not be installed until demolition of the existing electrical room at the southeast corner of the building is complete. This is scheduled for February 2004.

52

Page 53: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT BUDGET & COST On September 18, 2003, the Capital Assets Committee of the Board of Regents approved a budget adjustment to the project. The current approved project budget was increased to $7,052,000. CHANGES IN SCOPE The construction contract has been amended to add alternate #3 Miller Library Reading Room Skylight and alternate #4 WSU/MGF Classroom 150 operable partition. BUYOUT STATUS Not applicable. This project was bid as a public works project. SAFETY STATUS

Safety Statistics This Month Project To DateAverage Daily Work Force 9 N/ALost Time Incidents 0 0Recordable Incidents 0 0Total Hours Worked All Crafts 1520.5 1760.5Project Total Incidence Rate * 0 0

OPPORTUNITIES & CHALLENGES The utilities have been challenging since there have been several incidents of unknown utilities that have been discovered. Puget Sound Energy has struggled to locate the gas service to the complex of buildings. PSE and UW as-builts for this utility are not accurate. The project team is working hard to overcome these unforeseen complications. The structural qualities of the soils underlying footing excavations in the southwest corner of the site have been poor. Over-excavation and import of suitable structural is required based on the Geo-technical Engineers field reports for these excavations. The cost to the project is not yet known. The team has been working hard to figure out the best means and methods to execute the switch over from existing electrical, communication, and fire alarm system to new services that will be provided as part of this project. The shutdowns will impact the staff, students and faculty of CUH. Several brainstorming sessions have been held to minimize these impacts. The tentative schedule calls for the majority of the switch over work will occur early in February 2004.

53

Page 54: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number Value Change Orders Approved 0 0 Change Order Proposals Pending 7 $39,916 Change Order Requests Pending 0 0

Requests for Information to date Number Avg. Turnaround RFI’s 45 2 days

Submittals to date Number Avg. Turnaround Submittals 65 8 days

Disputes Review Board Status Not applicable on this project.

54

Page 55: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

55

Page 56: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.3

757

Pro

ject

:3757 M

err

ill H

all

Urb

an H

ort

icultu

re

PR

OJE

CT

CO

ST

RE

PO

RT

- L

evel 2

Origin

al

Budget

Com

mitt

ed

to D

ate

Act

ual C

ost

to

Date

Fore

cast

T

ota

l C

ost

s

Variance

from

Late

st B

udget

Est

imate

of

Uncom

mitt

ed

Appro

ved

Changes

Pendin

g

Changes

AB

CD

EF

G (

H-C

)H

I (B

-H)

Late

st

Appro

ved

Budget

B. C

onsultant S

erv

ices

10

1,1

71

P

re-D

esi

gn

Se

rvic

es

11

2,4

09

0

3

6,2

65

1

12

,40

9

11

2,4

09

0

0

0

28

4,4

65

B

asi

c S

erv

ice

s 3

33

,07

9

32

6,5

75

2

16

,68

1

(1)

32

6,5

74

(3

,05

9)

6,5

05

0

20

2,9

97

E

xtra

Se

rvic

es

40

0,0

77

3

24

,50

5

24

5,9

48

8

2,4

23

4

06

,92

7

24

9,4

08

(6

,85

0)

0

14

9,2

48

O

the

r S

erv

ice

s 8

7,5

74

2

2,7

48

6

,70

0

64

,82

6

87

,57

4

0

0

0

44

,77

2

De

sig

n S

erv

ice

s C

on

ting

en

cy 6

2,1

25

0

0

5

9,1

25

5

9,1

25

0

3

,00

0

0

782,6

53

B.

Co

nsu

ltan

t S

erv

ice

s 9

95,2

64

673,8

28

505,5

94

318,7

81

992,6

09

246,3

49

To

tal

2,6

55

0

C. C

onst

ruct

ion

3,1

73

,67

7

Prim

e C

on

tra

ct

4,3

73

,40

8

4,2

81

,32

0

0

32

3,0

88

4

,60

4,4

08

0

(2

31

,00

0)

0

26

,93

7

Oth

er

23

,98

0

23

,97

5

23

,97

5

5

23

,98

0

0

0

0

27

1,7

16

C

on

stru

ctio

n C

on

ting

en

cy 4

16

,33

2

0

0

41

6,3

32

4

16

,33

2

0

0

0

32

8,9

72

C

on

stru

ctio

n S

ale

s T

ax

45

1,0

05

4

07

,29

8

2,1

10

4

3,7

07

4

51

,00

5

0

0

0

67

,96

9

Ma

na

ge

me

nt

Re

se

rve

80

,33

6

0

0

80

,33

6

80

,33

6

0

0

0

3,8

69,2

71

C.

Co

nst

ruct

ion

5

,345,0

61

4,7

12,5

93

26,0

85

863,4

68

5,5

76,0

61

0

To

tal

(231,0

00)

0

D. E

quip

ment

0

Eq

uip

me

nt

57

,00

0

7,0

00

0

4

3,0

00

5

0,0

00

0

7

,00

0

0

21

,55

0

Fu

rnis

hin

gs

26

6,7

50

2

24

,00

0

0

(18

1,2

50

) 4

2,7

50

0

2

24

,00

0

0

1,8

96

E

qu

ipm

en

t/F

urn

ish

ing

s S

ale

s T

ax

8,1

62

0

0

8

,16

2

8,1

62

0

0

0

23,4

46

D.

Eq

uip

me

nt

331,9

12

231,0

00

0

(130,0

88)

100,9

12

0

To

tal

231,0

00

0

E. A

rtw

ork

0

Art

wo

rk 1

8,8

83

0

0

1

8,8

83

1

8,8

83

0

0

0

0

E.

Art

wo

rk 1

8,8

83

0

0

18,8

83

18,8

83

0

To

tal

0

0

F. O

ther

Cost

s 1

2,9

30

In

-Pla

nt

Se

rvic

es

13

,00

1

0

0

13

,00

1

13

,00

1

0

0

0

0

Util

itie

s/T

em

po

rary

Fa

cilit

ies

10

,83

5

0

0

10

,83

5

10

,83

5

0

0

0

33

,44

6

Pe

rmits

31

,64

2

15

,45

3

15

,45

3

16

,18

9

31

,64

2

0

0

0

3,2

32

B

uild

ers

Ris

k In

sura

nce

3,2

50

0

0

3

,25

0

3,2

50

0

0

0

26

,93

7

Oth

er

Co

sts

47

,88

2

4,7

24

0

4

3,1

58

4

7,8

82

0

0

0

76,5

45

F.

Oth

er

Co

sts

106,6

10

20,1

77

15,4

53

86,4

33

106,6

10

0

To

tal

0

0

G. P

roje

ct M

anagem

ent

24

3,9

45

C

PO

Ma

na

ge

me

nt

25

4,2

70

2

54

,27

0

25

4,2

70

0

2

54

,27

0

0

0

0

243,9

45

G.

Pro

ject

Ma

na

ge

me

nt

254,2

70

254,2

70

254,2

70

0

254,2

70

0

To

tal

0

0

4,9

95,8

60

7,0

52,0

00

5,8

91,8

68

801,4

02

7,0

49,3

45

Pro

ject

Tota

ls 2

46,3

49

2,6

55

0

1,1

57,4

77

Printe

d:1

1/4

/2003

56

Page 57: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT PHOTOS

Merrill Pre-Groundbreaking Meeting

Merrill Stairway – From the Past

Merrill Ground Floor Excavation Mechanical Plenum Formwork

Merrill Ground Floor – Looking North Merrill Electrical Under Slab Work

57

Page 58: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

58

Page 59: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Paul G. Allen Center for Computer Science & Engineering

Project Number

2507

Monthly Report

October 2003

Prepared by the Capital Projects Office

Lara Branigan, Project Manager

59

Page 60: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY

Paul G. Allen Center for Computer Science & Engineering PROJECT DESCRIPTION This project adds 160,000 gross square foot of additional new space for the departments of Computer Science & Engineering and Electrical Engineering. The new facility houses computer research and teaching laboratories, faculty and staff offices, and associated support space. This project also completed the unfinished portion of the Electrical Engineering Building and connects the two facilities. The project architect is LMN Architects, Seattle, WA. The GC/CM is M.A. Mortenson Company, Bellevue, WA. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Work toward Final Acceptance and Close-out continues. The Audio/Visual equipment punch list is complete, and the final training session is scheduled during the first week in November. Building signage punch list work is in progress. The furniture package punch list work is nearing completion. Commissioning work on the building equipment heating and cooling systems is in the functional performance testing stage, and scheduled to be complete in November. The Reboot espresso bar is busy serving lattes. Plans for Next 30 Days Completion of all remaining punch list and known warranty items should be achieved. All outstanding change order proposals should be reviewed and approved if justified. Miscellaneous landscape punch list work should be complete by November 14th. Building interior and exterior signage punch list work should completed by November 21st. Commissioning of all mechanical and electrical systems should be completed. LMN Architects will begin production of record drawings of the project. The team will continue to track and complete project closeout requirements. Design Status & Approvals The LMN Architects continues to support the punchlist effort and are engaged in the punchlist backcheck, which started during the last week in September. Construction Accomplishments This Period The building grand opening celebrations took place on the eighth and ninth of October, with a dinner on one day and a luncheon the next. The punch list and warranty item list are down to less than 100 items combined. Site work is complete, and the 60 day maintenance period for the landscape ends on 11/14/03. PROJECT BUDGET & COST The construction change order rate remains below the amount in the original budget, as are the furniture and audiovisual packages. The GC/CM has notified the University that Western Partitions, the framing, drywall, painting and acoustical ceilings subcontractor has submitted a letter notifying Mortenson of their intent of submitting a request for equitable adjustment for impacts and inefficiencies resulting from changes to their work.

60

Page 61: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

The formal request with documentation has yet to be submitted. Based on preliminary discussions, we have incorporated this possibility in our latest cost forecast. CHANGES IN SCOPE None to report this period. BUYOUT STATUS

Buyout Statistics Awarded Remaining Total

Percent Complete

Number of Packages 18 0 18 100%Dollar Value of Pkgs $37,331,071 $0 $37,331,071 100% Savings to Date (+ ahead or – behind) +$1,331,071

SAFETY STATUS

Safety Statistics This Month Project To DateAverage Daily Work Force 5Lost Time Incidents 0 1Recordable Incidents 0 13Total Hours Worked All Crafts 1,200 389,994Project Total Incident Rate * N/A 6.7* Incident Rate = (# of Incidents x 200,000 hrs) / (# of hours worked)

OPPORTUNITIES & CHALLENGES The project team remains committed to achieving complete project close-out as early as possible. CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number ValueChange Orders Approved 181 $2,987,467Change Order Proposals Pending 46 $239,965Change Order Requests Pending 9 $130,261Team Change Memos Approved Team Change Memos Pending

466

$721,284$188,716

Claims -Western Partitions $1.5M - Netversant $ 75K - Holiday Parks $ 75K

3 $1,650,000

Requests for Information to date Number Avg. TurnaroundRFI’s 1361 3 days Submittals to date Number Avg. TurnaroundSubmittals 511 10 days

Dispute Review Board Status The DRB has not met since August 18, 2003. It is anticipated that they will be involved in 2 of the 3 pending claims.

61

Page 62: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

This will be the last time this report is included in the monthly reports since it has achieved occupancy.

PROJECT SCHEDULE / GANNT CHART

62

Page 63: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.2

507

Pro

ject

:2507 A

LLE

N C

EN

TE

R F

OR

CS

E P

aul G

. A

llen C

ente

r fo

r C

om

pute

r S

cience

and E

ngin

eering

PR

OJE

CT

CO

ST

RE

PO

RT

- L

evel 2

Origin

al

Budget

Com

mitt

ed

to D

ate

Act

ual C

ost

to

Date

Fore

cast

T

ota

l C

ost

s

Variance

from

Late

st B

udget

Est

imate

of

Uncom

mitt

ed

Appro

ved

Changes

Pendin

g

Changes

AB

CD

EF

G (

H-C

)H

I (B

-H)

Late

st

Appro

ved

Budget

B. C

onsultant S

erv

ices

46

7,4

74

P

re-D

esi

gn

Se

rvic

es

46

7,4

74

3

72

,63

9

35

5,5

03

(4

,11

0)

36

8,5

29

0

9

8,9

45

0

3,0

21

,54

1

Ba

sic

Se

rvic

es

3,0

21

,54

1

3,2

47

,40

4

3,2

00

,17

2

0

3,2

47

,40

4

32

,97

9

(22

5,8

63

) 0

1,0

11

,92

0

Ext

ra S

erv

ice

s 1

,01

1,9

20

1

,04

5,8

21

9

88

,96

3

53

,32

5

1,0

99

,14

6

82

9,2

01

(8

7,2

26

) 0

65

7,0

99

O

the

r S

erv

ice

s 6

57

,09

9

1,0

36

,81

9

90

6,7

82

1

00

,00

0

1,1

36

,81

9

63

8,4

18

(4

79

,72

0)

0

1,0

67

,51

0

De

sig

n S

erv

ice

s C

on

ting

en

cy 1

,06

7,5

10

8

00

7

21

5

10

,44

7

51

1,2

47

8

00

5

56

,26

3

0

6,2

25,5

44

B.

Co

nsu

ltan

t S

erv

ice

s 6

,225,5

44

5,7

03,4

83

5,4

52,1

41

659,6

62

6,3

63,1

45

1,5

01,3

98

To

tal

(137,6

01)

0

C. C

onst

ruct

ion

38

,84

7,2

16

P

rim

e C

on

tra

ct

38

,84

7,2

16

3

8,6

15

,74

0

38

,54

7,4

72

0

3

8,6

15

,74

0

3,7

25

,54

5

23

1,4

76

0

0

Oth

er

0

18

2,4

70

1

69

,12

8

(15

5,8

47

) 2

6,6

24

0

(2

6,6

24

) 0

3,6

92

,42

1

GC

/CM

Ite

ms

3,6

92

,42

1

5,8

69

,73

1

4,0

19

,37

1

(20

0,6

33

) 5

,66

9,0

98

(1

,04

2,1

97

)(1

,97

6,6

77

) 2

80

,16

4

5,9

31

,79

7

Co

nst

ruct

ion

Co

ntin

ge

ncy

5,9

31

,79

7

2,8

78

,74

1

2,8

63

,09

7

1,7

21

,36

2

4,6

00

,10

3

2,8

78

,74

1

1,3

31

,69

4

11

4,9

12

4,4

79

,07

7

Co

nst

ruct

ion

Sa

les

Ta

x 4

,47

9,0

77

3

,91

1,8

85

3

,74

0,9

70

3

46

,14

5

4,2

58

,03

0

(12

1,5

34

) 2

21

,04

7

0

2,0

35

,88

0

Ma

na

ge

me

nt

Re

se

rve

3,7

35

,88

0

0

0

0

0

0

3,7

35

,88

0

0

54,9

86,3

91

C.

Co

nst

ruct

ion

5

6,6

86,3

91

51,4

58,5

67

49

,34

0,0

37

1

,711,0

27

53,1

69,5

95

5,4

40,5

55

To

tal

3,5

16,7

97

395,0

76

D. E

quip

ment

0

Eq

uip

me

nt

0

57

1,2

94

3

57

,03

5

(27

,55

7)

54

3,7

37

0

(5

43

,73

7)

0

5,1

00

,00

0

Fu

rnis

hin

gs

5,1

00

,00

0

3,7

25

,69

7

1,8

09

,19

0

29

,12

1

3,7

54

,81

8

33

,16

0

1,3

45

,18

2

0

44

8,8

00

E

qu

ipm

en

t/F

urn

ish

ing

s S

ale

s T

ax

44

8,8

00

3

32

,42

4

96

,72

6

5,0

31

3

37

,45

4

0

11

1,3

46

0

5,5

48,8

00

D.

Eq

uip

me

nt

5,5

48,8

00

4,6

29,4

14

2,2

62,9

51

6,5

95

4,6

36,0

09

33,1

60

To

tal

912,7

91

0

E. A

rtw

ork

15

7,2

45

A

rtw

ork

15

7,2

45

1

57

,24

5

15

7,2

45

0

1

57

,24

5

0

0

0

157,2

45

E.

Art

wo

rk 1

57,2

45

157,2

45

157,2

45

0

157,2

45

0

To

tal

0

0

F. O

ther

Cost

s 0

In

-Pla

nt

Se

rvic

es

0

12

2,7

77

1

22

,77

7

82

,11

0

20

4,8

87

0

(2

04

,88

7)

0

0

Util

itie

s/T

em

po

rary

Fa

cilit

ies

0

10

,34

0

3

0

10

,33

9

0

(10

,33

9)

0

0

Pe

rmits

0

95

,72

7

92

,00

2

0

95

,72

7

70

,44

0

(95

,72

7)

0

0

Bu

ilde

rs R

isk

Insu

ran

ce 0

6

2,0

20

6

2,0

20

1

2,9

80

7

5,0

00

0

(7

5,0

00

) 0

1,1

82

,91

7

Oth

er

Co

sts

1,1

82

,91

7

31

4,5

40

5

4,6

11

(2

,49

3)

31

2,0

47

0

8

70

,87

0

0

1,1

82,9

17

F.

Oth

er

Co

sts

1,1

82,9

17

605,4

03

331,4

13

92,5

97

698,0

00

70,4

40

To

tal

484,9

17

0

G. P

roje

ct M

anagem

ent

1,2

68

,26

1

CP

O M

an

ag

em

en

t 1

,26

8,2

61

1

,26

8,2

61

1

,15

9,6

71

0

1

,26

8,2

61

0

0

0

63

0,8

42

O

the

r M

an

ag

em

en

t 6

30

,84

2

70

1,1

20

6

38

,75

6

0

70

1,1

20

1

13

,60

0

(70

,27

8)

0

1,8

99,1

03

G.

Pro

ject

Ma

na

ge

me

nt

1,8

99,1

03

1,9

69,3

81

1,7

98,4

27

0

1,9

69,3

81

113,6

00

To

tal

(70,2

78)

0

70,0

00,0

00

71,7

00,0

00

64,5

23,4

94

59

,34

2,2

13

6

6,9

93,3

75

Pro

ject

Tota

ls 7

,159,1

53

4,7

06,6

25

395,0

76

2,4

69,8

81

Printe

d:1

1/4

/2003

63

Page 64: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

64

Page 65: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Research & Technology Building

Project Number 10297

Monthly Report

October 2003

Prepared by the Capital Projects Office

Andy Casillas, Project Manager

65

Page 66: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Research & Technology Building

PROJECT DESCRIPTION The lack of available research space is the constraining factor to expanding and remaining nationally competitive in research. Preparing additional Seattle campus space will provide an opportunity to expand multi-disciplinary research initiatives in high growth areas that need to be located near the campus. The Administration proposes to meet this need in a similar fashion to the private sector, by providing a competitively priced, highly flexible and adaptable research building core and shell, in which UW research entities would build out their required spaces. The building will be approximately 115,000 gross square feet. The selected site for the new building is the existing surface parking lot W44, west of the Publications Services building, on NE Northlake Place. The Administration proposes to procure the core and shell research building using the design-build-operate-maintain (DBOM) alternative public works procurement process, as authorized by RCW 39.10.051. This procurement method is envisioned to provide the much-needed additional research space in a shorter amount of time and in a more cost-competitive manner than other, more traditional methods. In addition to design and construction, the procurement will likely include a building operation component. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview As the DBOM RFP advertised in late September, most of October was used in answering questions and assembling Addenda. All project documents continued to be issued via the CPO web site. On October 28th, five teams replied to the RFP and presented proposals for our review. Hard copies and/or CD’s were distributed to the Jury, Technical Evaluation Committee and Consultants the next day. As the RFP’s were rather extensive, it will take two weeks to fully review and analyze all of the proposals. Initial reviews indicate cost projections are tight but achievable. All schedules presented indicate 2005 occupancy is probably not attainable with initial schedules reflecting closer to a January 2003occupancy date. Long term dewatering issues for garage parking also appears to be a concern. A full report will be presented to the Selection Jury on November 17th. Coordination with King County Metro continued in efforts to send a survey crew inside the 108” sewer line for as-built measurements with the current target date set for November 5th to perform this work. The overall project remains on track with the Request for Proposals (RFP) received on October 28, 2003.

66

Page 67: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Plans for Next 30 Days The month of November will be utilized to evaluate the five teams to determine the extent of the Best & Final round of competition. The consultant will also update the RFP as necessary for the Best & Final round. As the proposed budget of $31.4M currently appears attainable, a formal project work plan will be submitted. Consultant Services Accomplishments this Period All submitted questions by the RFP respondents were answered and distributed as Addendum 1 & 2. Design Status & Approvals Based on preliminary assessments of proposals, we may need to keep our parking options open pending further analysis on garage parking under the water table. Construction Accomplishments This Period Construction has not started on this project. PROJECT BUDGET & COST A conceptual budget was prepared for the core & shell and established at $31,400,000. Based on assumed layouts the core & shell bare costs MACC estimate is projected to be around $20,119,000. This estimate does not include the impact of the 108” sewer line. Parking Services continues to evaluate parking options and alternates to minimize underground parking. A preliminary project budget of $600,000 has been established to proceed with planning, programming and preparation of the design/build/operate solicitation which is included in the Core & Shell budget. The cost of tenant improvements will depend on the type and occupancy of these improvements and will be determined when the requirements are better defined. CHANGES IN SCOPE The overall budget for the Core and Shell construction will be prepared for the projected $31.4M. BUYOUT STATUS Not applicable at this time.

67

Page 68: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

SAFETY STATUS Not applicable. Construction has not started on this project.

OPPORTUNITIES & CHALLENGES As garage parking will need to be below the water level and lake elevation, the challenge remains to economically accommodate the needed parking. To assure the best value, the operations and maintenance details need to be finalized before issuance of the Best and Final round. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time.

68

Page 69: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

69

Page 70: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.1

0297

Pro

ject

:10297 S

EA

TT

LE

CA

MP

US

Specu

lativ

e R

ese

arc

h B

ldg P

hase

I

PR

OJE

CT

CO

ST

RE

PO

RT

- L

evel 2

Origin

al

Budget

Com

mitt

ed

to D

ate

Act

ual C

ost

to

Date

Fore

cast

T

ota

l C

ost

s

Variance

from

Late

st B

udget

Est

imate

of

Uncom

mitt

ed

Appro

ved

Changes

Pendin

g

Changes

AB

CD

EF

G (

H-C

)H

I (B

-H)

Late

st

Appro

ved

Budget

B. C

onsultant S

erv

ices

44

4,7

29

P

re-D

esi

gn

Se

rvic

es

44

4,7

29

4

42

,42

4

27

2,6

67

2

,30

5

44

4,7

29

1

5,5

86

0

0

41

2,8

81

B

asi

c S

erv

ice

s 4

12

,88

1

0

0

41

2,8

81

4

12

,88

1

0

0

0

51

,04

8

Ext

ra S

erv

ice

s 5

1,0

48

1

8

18

5

1,0

30

5

1,0

48

0

0

0

24

,22

1

Oth

er

Se

rvic

es

24

,22

1

0

0

24

,22

1

24

,22

1

0

0

0

48

,07

4

De

sig

n S

erv

ice

s C

on

ting

en

cy 4

8,0

74

0

0

4

8,0

74

4

8,0

74

0

0

0

980,9

53

B.

Co

nsu

ltan

t S

erv

ice

s 9

80,9

53

442,4

42

272,6

85

538,5

11

980,9

53

15,5

86

To

tal

0

0

C. C

onst

ruct

ion

20

,11

9,2

80

P

rim

e C

on

tra

ct

20

,11

9,2

80

0

0

2

0,1

19

,28

0

20

,11

9,2

80

0

0

0

3,6

69

,58

1

GC

/CM

Ite

ms

3,6

69

,58

1

0

0

3,6

69

,58

1

3,6

69

,58

1

0

0

0

1,0

05

,96

4

Co

nst

ruct

ion

Co

ntin

ge

ncy

1,0

05

,96

4

0

0

1,0

05

,96

4

1,0

05

,96

4

0

0

0

2,2

35

,06

0

Co

nst

ruct

ion

Sa

les

Ta

x 2

,23

5,0

60

0

0

2

,23

5,0

60

2

,23

5,0

60

0

0

0

60

3,5

79

M

an

ag

em

en

t R

ese

rve

60

3,5

79

0

0

6

03

,57

9

60

3,5

79

0

0

0

27,6

33,4

64

C.

Co

nst

ruct

ion

2

7,6

33,4

64

0

0

27,6

33,4

64

27,6

33,4

64

0

To

tal

0

0

E. A

rtw

ork

95

,52

3

Art

wo

rk 9

5,5

23

0

0

9

5,5

23

9

5,5

23

0

0

0

95,5

23

E.

Art

wo

rk 9

5,5

23

0

0

95,5

23

95,5

23

0

To

tal

0

0

F. O

ther

Cost

s 3

0,9

83

In

-Pla

nt

Se

rvic

es

30

,98

3

38

7

38

7

30

,59

6

30

,98

3

0

0

0

22

7,8

04

P

erm

its 2

27

,80

4

0

0

22

7,8

04

2

27

,80

4

0

0

0

25

,81

3

Bu

ilde

rs R

isk

Insu

ran

ce 2

5,8

13

0

0

2

5,8

13

2

5,8

13

0

0

0

82

0,8

42

O

the

r C

ost

s 8

20

,84

2

0

0

82

0,8

42

8

20

,84

2

0

0

0

1,1

05,4

42

F.

Oth

er

Co

sts

1,1

05,4

42

387

387

1,1

05,0

55

1,1

05,4

42

0

To

tal

0

0

G. P

roje

ct M

anagem

ent

1,1

46

,61

8

CP

O M

an

ag

em

en

t 1

,14

6,6

18

5

0,0

00

3

,50

0

1,0

96

,61

8

1,1

46

,61

8

0

0

0

43

8,0

00

O

the

r M

an

ag

em

en

t 4

38

,00

0

78

,00

0

0

36

0,0

00

4

38

,00

0

0

0

0

1,5

84,6

18

G.

Pro

ject

Ma

na

ge

me

nt

1,5

84,6

18

128,0

00

3,5

00

1,4

56,6

18

1,5

84,6

18

0

To

tal

0

0

31,4

00,0

00

31,4

00,0

00

570,8

29

276,5

72

31,4

00,0

00

Pro

ject

Tota

ls 1

5,5

86

0

0

30,8

29,1

71

Printe

d:1

1/4

/2003

70

Page 71: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Soccer/Baseball Stadium

Project Number 3682

Monthly Report

October 2003

Prepared by the Capital Projects Office

Debra Born, Project Manager

71

Page 72: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Soccer/Baseball Stadium

PROJECT DESCRIPTION Last of the "Campaign for the Student Athlete" projects to be designed, this project will replace the temporary grandstands and support facilities with a permanent venue for Intercollegiate Athletic soccer and baseball programs. This stadium will be comparable to other PAC-10 Conference facilities and may serve as an NCAA tournament site. The goal is to develop a shared facility located between the existing soccer and baseball fields to take advantage of different playing seasons and back-to-back field locations. The concept features back-to-back seating for the two sports separated by a concourse with spectator amenities located on either side and with team support and facilities maintenance spaces below. The complex is planned to be completed in two or more phases due to the anticipated need to rely on incremental funding. The site is situated in the East Campus over the Montlake Landfill and just outside the 200 foot shoreline setback for Lake Washington. The site is bounded on the north by recreational fields and Wahkiakum Lane, by Canal Road and the University slough to the east, by E-1 parking and recreational sports fields, and E-8 parking on the west, and the Conibear Shellhouse to the south. LMN Architects in association with CDFM2 Architecture Inc. are the design consultants. Current departmental expectations include these project components: 1) Permanent soccer grandstands with a seating capacity of approximately 2,500. 2) Permanent baseball grandstands with a seating capacity of approximately 1,800. 3) New main gate and ticketing area including concessions and public restrooms. 4) On-site team support facilities. 5) On-site field maintenance facilities. 6) Sidewalk and landscape improvements along Walla Walla Road edge of site. 7) Grandstands location to allow future track around the soccer field. 8) Soccer field to shift slightly northward and existing soccer stands to be relocated.

PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Submittal of the draft Program for University review is scheduled for early December. Approval of the Program is anticipated to be by the end of 2003 pending departmental approval of the draft program and concept drawings at a meeting scheduled for mid-November.

72

Page 73: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Design Status & Approvals Programming phase tasks are 80% complete. A meeting to review the Architect’s concept for the stadium and updated cost model occurred between the Architect and the Department of Intercollegiate Athletics in late October. Plans for Next 30 Days A final programming meeting with the Department is planned for mid-November to finalize decisions prior to submittal of the Program document for final University review in December. Construction Accomplishments This Period Not applicable at this time. PROJECT BUDGET & COST LMN Architects presented an updated cost estimate for incremental construction. Project cost for the initial phase is estimated at $12.5 million including 2,500 new soccer seats and 1,500 new baseball seats. Project cost to build 1,000 additional soccer seats and 1,500 additional baseball seats including team support facilities and additional public amenities is $5.1 million. Project cost to add a future track around the soccer field including necessary revisions to the field and surrounding areas is an additional $5 million. Approximate project costs for all proposed work escalated to 2005 is $22.6 million. CHANGES IN SCOPE Not applicable at this time. BUYOUT STATUS Not applicable at this time. SAFETY STATUS Not applicable at this time. OPPORTUNITIES & CHALLENGES To develop an organizational concept that maximizes shared services, utilizes existing field layouts, and allows for future development options that meet fund-raising realities. To identify impacts to existing facilities and the required upgrades to existing utilities. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time.

73

Page 74: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

74

Page 75: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Terry Hall Improvements

Project Number 3948

Monthly Report

October 2003

Prepared by the Capital Projects Office

JR Fulton, Project Manager

75

Page 76: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY Terry Hall Improvements

PROJECT DESCRIPTION The Terry Hall Improvements Project will replace the existing kitchen and dining room in Terry Hall with a market style food court, including: four food concepts - Asian, Euro Kitchen, Deli, and Salads, plus a Convenience Store. This is the third and final food court identified in the Housing and Food Service Strategic Master Plan and is intended to serve the west campus. Renovated area on the first floor is approximately 18,000 gross square feet (gsf) with an additional 4000 gsf in storage areas adjacent the loading dock on the ground floor. URS Corporation is architect for the project. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Design Development documents have been reviewed by UW and Consultants are responding to comments. In order to meet scheduled opening fall quarter 2004, schematic and design development phases have been accelerated with no change to the delivery date for bid documents. Plans for Next 30 Days The consultant is responding to Design Development review comments, proceeding on construction documents and modifying documents based on revised alternates. Mid CD review is planned for November 13, 2003. Design Status & Approvals The Project Review Board (PRB) approved the consultant to proceed with construction documents in mid October. A modified process is being used for internal review based on increased communications with review team. The modified process allows the consultant to proceed with design during the UW review process. Design Development is complete. The “look and feel” of the restaurant has been significantly resolved with the exception of some finishes in the large dining room and public corridor. Alternates were partially revised. There are three alternates currently included in the project, but they are outside of the MACC, including: public restroom upgrade, patio dining and improved exterior entrances and upgrade of Terry Desk. The freight elevator upgrade has been moved to the base project and elevator security vestibules have been eliminated. Construction Accomplishments This Period Not applicable at this time.

76

Page 77: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT BUDGET & COST The project budget remains at $8,000,000 and construction budget (MACC) is unchanged at $4,200,000. Design Development cost estimate identified MACC at $4,231,327 with three alternates totaling $425,659 above the MACC. Following this cost estimate, Alternates were revised to meet $4.2M MACC. CHANGES IN SCOPE Alternates were modified at Design Development based on cost estimates, eliminating elevator vestibule, moving freight elevator upgrade into base contract and moving Terry desk upgrade into Alternates. BUYOUT STATUS Not applicable. SAFETY STATUS Not applicable. OPPORTUNITIES & CHALLENGES The project continues to target being completed and ready for use for the Fall Quarter 2004. CONSTRUCTION CONTRACT ADMINISTRATION Not applicable at this time.

77

Page 78: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

78

Page 79: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.3

948

Pro

ject

:3948 L

AN

DE

R-T

ER

RY

HA

LLS

Terr

y H

all

Din

ing a

nd Im

pro

vem

ents

PR

OJE

CT

CO

ST

RE

PO

RT

- L

evel 2

Origin

al

Budget

Com

mitt

ed

to D

ate

Act

ual C

ost

to

Date

Fore

cast

T

ota

l C

ost

s

Variance

from

Late

st B

udget

Est

imate

of

Uncom

mitt

ed

Appro

ved

Changes

Pendin

g

Changes

AB

CD

EF

G (

H-C

)H

I (B

-H)

Late

st

Appro

ved

Budget

B. C

onsultant S

erv

ices

33

4,3

11

P

re-D

esi

gn

Se

rvic

es

33

4,3

11

3

41

,61

1

28

8,1

56

0

3

41

,61

1

68

,61

9

(7,3

00

) 0

47

4,9

08

B

asi

c S

erv

ice

s 4

74

,90

8

34

0,9

94

1

26

,55

5

13

3,9

14

4

74

,90

8

0

0

0

43

2,1

01

E

xtra

Se

rvic

es

43

2,1

01

1

67

,16

6

8,0

92

2

65

,44

1

43

2,6

07

1

33

,15

1

(50

6)

0

13

7,4

82

O

the

r S

erv

ice

s 1

37

,48

2

0

0

13

7,4

82

1

37

,48

2

0

0

0

78

,11

5

De

sig

n S

erv

ice

s C

on

ting

en

cy 7

8,1

15

0

0

7

0,3

09

7

0,3

09

0

7

,80

6

0

1,4

56,9

17

B.

Co

nsu

ltan

t S

erv

ice

s 1

,456,9

17

849,7

71

422,8

02

607,1

46

1,4

56,9

17

201,7

70

To

tal

0

0

C. C

onst

ruct

ion

4,3

74

,44

0

Prim

e C

on

tra

ct

4,3

74

,44

0

0

0

4,3

74

,44

0

4,3

74

,44

0

0

0

0

52

4,9

32

C

on

stru

ctio

n C

on

ting

en

cy 5

24

,93

2

0

0

52

4,9

32

5

24

,93

2

0

0

0

43

8,8

44

C

on

stru

ctio

n S

ale

s T

ax

43

8,8

44

0

0

4

38

,84

4

43

8,8

44

0

0

0

87

,48

9

Ma

na

ge

me

nt

Re

se

rve

87

,48

9

0

0

87

,48

9

87

,48

9

0

0

0

5,4

25,7

05

C.

Co

nst

ruct

ion

5

,425,7

05

0

0

5,4

25,7

05

5,4

25,7

05

0

To

tal

0

0

D. E

quip

ment

34

6,8

30

F

urn

ish

ing

s 3

46

,83

0

0

0

34

6,8

30

3

46

,83

0

0

0

0

30

,52

2

Eq

uip

me

nt/

Fu

rnis

hin

gs

Sa

les

Ta

x 3

0,5

22

0

0

3

0,5

22

3

0,5

22

0

0

0

377,3

52

D.

Eq

uip

me

nt

377,3

52

0

0

377,3

52

377,3

52

0

To

tal

0

0

E. A

rtw

ork

21

,00

0

Art

wo

rk 2

1,0

00

0

0

2

1,0

00

2

1,0

00

0

0

0

21,0

00

E.

Art

wo

rk 2

1,0

00

0

0

21,0

00

21,0

00

0

To

tal

0

0

F. O

ther

Cost

s 5

1,5

04

In

-Pla

nt

Se

rvic

es

51

,50

4

0

0

51

,50

4

51

,50

4

0

0

0

58

,11

2

Pe

rmits

58

,11

2

22

5

22

5

57

,88

7

58

,11

2

0

0

0

15

,45

1

Bu

ilde

rs R

isk

Insu

ran

ce 1

5,4

51

0

0

1

5,4

51

1

5,4

51

0

0

0

15

,45

1

Oth

er

Co

sts

15

,45

1

0

0

15

,45

1

15

,45

1

0

0

0

140,5

18

F.

Oth

er

Co

sts

140,5

18

225

225

140,2

93

140,5

18

0

To

tal

0

0

G. P

roje

ct M

anagem

ent

54

8,4

78

C

PO

Ma

na

ge

me

nt

54

8,4

78

5

48

,47

8

0

0

54

8,4

78

0

0

0

30

,03

0

Oth

er

Ma

na

ge

me

nt

30

,03

0

30

,00

0

1,5

00

3

0

30

,03

0

0

0

0

578,5

08

G.

Pro

ject

Ma

na

ge

me

nt

578,5

08

578,4

78

1,5

00

30

578,5

08

0

To

tal

0

0

8,0

00,0

00

8,0

00,0

00

1,4

28,4

74

424,5

27

8,0

00,0

00

Pro

ject

Tota

ls 2

01,7

70

0

0

6,5

71,5

26

Printe

d:1

1/4

/2003

79

Page 80: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

80

Page 81: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

UWMC Surgery Pavilion

Project Number 2731

Monthly Report

October 2003

Prepared by the Capital Projects Office

Dick Owen, Project Manager

81

Page 82: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY UWMC Surgery Pavilion

PROJECT DESCRIPTION The UWMC Surgery Pavilion project is a 160,000 gross square foot facility to house short stay surgery and treatment areas, and diagnostic and ancillary services on the site of the S10 and S11 parking lots to the east of the University Of Washington Medical Center. The project will be constructed above approximately 300 parking spaces housed in a new underground parking garage. The parking square footage is not included in the 160,000 gsf. The last major addition to the hospital was in 1984-86, and many clinical areas are operating today in less than optimal spaces. The most severe space shortages are in the operating rooms, outpatient procedure areas, diagnostic and ancillary services, clinic areas, and offices for the clinically active faculty of the School of Medicine. Major changes are occurring in the patterns of medical care delivery as more and more services are being provided in the outpatient setting, and incentives in the health care system are encouraging this trend. As a result, there is an increasing need to teach health sciences students how to provide care on an ambulatory basis in facilities appropriately designed for ambulatory care. The project architect is NBBJ with the firm Destafano Keating acting as the collaborating architect. The GC/CM is Hoffman Construction Company. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Substantial completion is being established as September 12, 2003. Contractor is working on completion of the punch list. The UWMC gala event occurred on October 10, 2003. The Medical Center started seeing patients on Level 1 on October 14, 2003. Occupancy for Level 2 is scheduled for November 4, 2003 and Level 3 on November 13, 2003. Plans for Next 30 Days Design Status & Approvals Design is complete. NBBJ continues in its support of construction. Construction Accomplishments This Period

1. Correcting punch list items 2. Completing change order work 3. Completed equipment installation 4. Completed transplant cleaning

82

Page 83: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT BUDGET & COST Total project costs are currently anticipated to remain at $87.8 million, about $2 million below the project budget. Some of the buyout savings was used to increase the scope of work. CHANGES IN SCOPE None this period. BUYOUT STATUS The buyout is complete

Buyout Statistics Awarded Remaining Total

Percent Complete

Number of Packages 45 0 45 100%Dollar Value of Pkgs $48,413,426 0 $48,413,426 100% Savings to Date (+ ahead or – behind) $4.935 M

Calculated before Conformance Change Order #107

SAFETY STATUS

Safety Statistics This Month Project To DateAverage Daily Work Force 25Lost Time Incidents 0 7Recordable Incidents 0 14Total Hours Worked All Crafts 4570 567,623Project Total Incidence Rate * 0 7.40 * Incidence Rate = (# of Incidents x 200,000 hrs) / (# of hours worked)

OPPORTUNITIES & CHALLENGES 1) Settle Outstanding Cost Issues CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number ValueChange Orders Approved 567 $1,911,864Change Order Proposals Pending 39 -$44,563Change Order Requests Pending 13 $193,055Team Change Memos Approved 139 $1,304,310

83

Page 84: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Requests for Information to date Number Avg. TurnaroundRFI’s 1970 7 days

Submittals to date Number Avg. TurnaroundSubmittals 760 25 days

Disputes Review Board Status There are currently no issues being reviewed by the DRB.

84

Page 85: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

85

Page 86: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

2731

PRO

JEC

T C

OST

REP

OR

T - L

evel

2P

roje

ct:2

731

UW

MC

Sur

gery

Pav

ilion

Orig

inal

B

udge

tLa

test

App

rove

d B

udge

tC

omm

itted

to

Dat

eA

ctua

l Cos

t to

Dat

eA

ppro

ved

Cha

nges

Pen

ding

C

hang

esE

stim

ate

of U

ncom

mitt

edFo

reca

st T

otal

Cos

tsV

aria

nce

from

La

test

Bud

get

AB

CD

EF

G (H

-C)

HI (

B-H

)B

.

Con

sulta

nt S

ervi

ces

Pre

-Des

ign

Ser

vice

s1,

080,

000

1,08

0,00

01,

058,

208

1,03

1,75

074

1,23

50

(11,

260)

1,04

6,94

833

,052

Bas

ic S

ervi

ces

4,72

7,64

84,

727,

648

5,20

4,10

54,

927,

343

478,

195

00

5,20

4,10

5(4

76,4

57)

Ext

ra S

ervi

ces

2,30

5,17

02,

305,

170

4,34

2,52

24,

222,

104

3,77

2,95

40

50,9

784,

393,

500

(2,0

88,3

30)

Oth

er S

ervi

ces

1,79

4,38

41,

794,

384

1,12

3,99

41,

097,

336

891,

614

0(2

,027

)1,

121,

967

672,

417

Des

ign

Ser

vice

s C

ontin

genc

y35

2,68

135

2,68

158

,705

58,7

0510

8,77

10

058

,705

293,

976

Tota

l B.

C

onsu

ltant

Ser

vice

s10

,259

,883

10,2

59,8

8311

,787

,534

11,3

37,2

385,

992,

769

037

,691

11,8

25,2

25(1

,565

,342

)

C.

C

onst

ruct

ion

Prim

e C

ontra

ct56

,022

,047

56,0

22,0

4754

,150

,833

51,3

14,6

866,

776,

702

1,14

5,07

51,

375,

993

55,5

26,8

2649

5,22

1O

ther

13

5,05

813

5,05

82,

857

2,63

70

053

,893

56,7

5078

,308

GC

/CM

Item

s7,

865,

777

7,86

5,77

78,

416,

783

5,49

9,26

4(4

,934

,919

)(3

3,17

8)(9

91,9

17)

7,42

4,86

644

0,91

1O

ther

Con

tinge

ncy

00

00

00

00

0C

onst

ruct

ion

Con

tinge

ncy

4,48

1,78

24,

481,

782

00

00

00

4,48

1,78

2C

onst

ruct

ion

Sal

es T

ax6,

001,

520

6,00

1,52

05,

632,

099

5,19

1,96

80

00

5,63

2,09

936

9,42

1M

anag

emen

t Res

erve

1,28

0,45

81,

280,

458

00

00

00

1,28

0,45

8To

tal C

.

Con

stru

ctio

n 75

,786

,642

75,7

86,6

4268

,202

,572

62,0

08,5

551,

841,

783

1,11

1,89

743

7,96

968

,640

,541

7,14

6,10

1

D.

E

quip

men

t0

Equ

ipm

ent

00

45,4

5845

,458

45,3

670

(1,4

85)

43,9

73(4

3,97

3)Fu

rnis

hing

s0

054

354

30

00

543

(543

)To

tal D

.

Equ

ipm

ent

00

46,0

0146

,001

45,3

670

(1,4

85)

44,5

16(4

4,51

6)

E.

A

rtwor

kA

rtwor

k31

3,40

031

3,40

027

2,65

20

00

38,9

3431

1,58

61,

814

Tota

l E.

A

rtwor

k31

3,40

031

3,40

027

2,65

20

00

38,9

3431

1,58

61,

814

F.

Oth

er C

osts

In-P

lant

Ser

vice

s54

,023

54,0

2323

8,56

723

8,56

70

021

7,44

645

6,01

3(4

01,9

90)

Util

ities

/Tem

pora

ry F

acili

ties

00

10,9

0011

,859

00

010

,900

(10,

900)

Per

mits

417,

326

417,

326

298,

061

50,6

290

00

298,

061

119,

265

Bui

lder

s R

isk

Insu

ranc

e70

,230

70,2

300

00

00

070

,230

Oth

er C

osts

135,

058

135,

058

93,0

2568

,688

12,1

190

(4,3

79)

88,6

4646

,412

Tota

l F.

O

ther

Cos

ts67

6,63

767

6,63

764

0,55

336

9,74

312

,119

021

3,06

785

3,62

0(1

76,9

83)

G.

P

roje

ct M

anag

emen

t0

CP

O M

anag

emen

t1,

800,

005

1,80

0,00

51,

800,

005

1,38

0,00

00

(1,3

50)

255,

586

2,05

5,59

1(2

55,5

86)

Oth

er M

anag

emen

t88

8,43

388

8,43

396

6,23

186

6,45

50

00

966,

231

(77,

798)

Oth

er C

osts

00

47,0

0224

,858

00

(0)

47,0

02(4

7,00

2)To

tal

G.

P

roje

ct M

anag

emen

t2,

688,

438

2,68

8,43

82,

813,

239

2,27

1,31

30

(1,3

50)

255,

586

3,06

8,82

4(3

80,3

86)

Pro

ject

Tot

als

89,7

25,0

0089

,725

,000

83,7

62,5

5076

,032

,850

7,89

2,03

81,

110,

547

981,

761

84,7

44,3

124,

980,

688

H.

S

cope

Cha

nges

Pne

umat

ic T

ube

Sys

tem

00

1,99

4,68

51,

994,

685

00

01,

994,

685

(1,9

94,6

85)

Sur

gery

Wai

ting

00

759,

459

759,

459

00

075

9,45

9(7

59,4

59)

Oth

er C

lient

Cha

nges

00

324,

334

324,

334

00

032

4,33

4(3

24,3

34)

Tota

l H

.

Sco

pe C

hang

es0

03,

078,

478

3,07

8,47

80

00

3,07

8,47

8(3

,078

,478

)P

roje

ct T

otal

s89

,725

,000

89,7

25,0

0086

,841

,028

79,1

11,3

287,

892,

038

1,11

0,54

798

1,76

187

,822

,790

1,90

2,21

0

86

Page 87: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

UW Tacoma Campus Phase 2b Cherry Parkes & Mattress Factory

Project Number

2608

Monthly Report

October 2003

Prepared by the Capital Projects Office

Catherine Vogt, Project Manager

87

Page 88: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY UW Tacoma Campus Phase 2b

PROJECT DESCRIPTION This project renovates five 19th century warehouses to provide space for classrooms, computer labs, faculty offices, group study, staff offices, campus support, and various student services. Three connected warehouses on Pacific Avenue will become one large, interconnected building named Cherry Parkes and will total apprx. 42,000 gross square feet for academic uses plus 30,000 gross square feet of retail and shell space. Two connected buildings on Commerce Street, named the Mattress Factory, will total apprx. 61,000 gross square feet. The capacity of the campus will increase by 600 FTE, bringing the total to 2,007 FTE. The prime architect is the McGranahan Partnership with design architects: BOLA Architects and Miller/Hull. The GC/CM is Lease Crutcher Lewis. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Substantial Completion is currently scheduled for December 1, 2003. As of October 31 2003, the construction time of 487 days is 94% complete. Plans for Next 30 Days A pair of boilers and an emergency generator will be installed into the UWT Science Building to handle the additional load that will come on line when the Phase 2b buildings are occupied. A bid package is being prepared, which is expected to be bid out during the month of November as a new project. Design Status & Approvals Design is complete. The Design Team continues in its support of construction. Construction Accomplishments This Period Cherry Parkes

Pacific Ave storefront installed, trimmed & glazed, doors installed. Commerce St storefront installed & glazed, doors to install this week.

Doors, hardware, & casework 90% complete. Carpet, vinyl flooring, & cable tray installed through 2nd floor. Ceiling grid 98% complete. Skylights installed. Projector screens, tackboards, & whiteboards installed. Heating hot water pipe connection complete. ATB’s & AHU’s powered up & point-to-point testing completed. Toilet fixtures & accessories completed, drinking fountains tested & activated. Mattress Factory Storefronts installed on three sides, door install this week. All walls taped & painted except 2nd floor of South Building. All handrails installed. Ceiling grid installed on 3 floors North & 2 floors South.

88

Page 89: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Parapet cap installed & flashing complete. Skylights installed. Toilet fixtures & accessories installed Ground & 1st floors. Stair tower elevator platform built & cab construction started. Sitework Sidewalk, curbs, & gutters complete. Final paving complete. Irrigation system completed & tested, landscaping under way. Fire lane pavers reinstalled. PROJECT BUDGET & COST The total project budget for UWT Phase 2b is $44,349,000. Currently project costs remain within budget. The tenant improvements added by change order to this project are being funded by sources other than the State. The Board of Regents recently approved the public/private housing/parking project for which $1.2 million has been on hold. CHANGES IN SCOPE UW Tacoma has provided additional funding and directed the team to complete the relocation of the dumpster/compactor from the Library to the Commerce Street site. BUYOUT STATUS

Buyout Statistics Awarded Remaining Total

Percent Complete

Number of Packages 23 0 23 100%Dollar Value of Pkgs $24,101,332 $0 $24,101,332 100%Savings to Date (+ ahead or – behind) $1,293,408

The buyout savings was used to replenish the Owner’s Construction Contingency and the GC/CM Reimbursables Account. SAFETY STATUS

Safety Statistics This Month Project To DateAverage Daily Work Force 182Lost Time Incidents 1 4Recordable Incidents 0 3Total Hours Worked All Crafts 36,248 298,185Project Total Incidence Rate * 5.5 4.7 * Incidence Rate = (# of Incidents x 200,000 hrs) / (# of hours worked)

OPPORTUNITIES & CHALLENGES The project has the opportunity to achieve Silver LEEDS Certification. The primary challenge at this stage will be to reach Substantial Completion by December 1.

89

Page 90: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number ValueChange Orders Approved * 189 $5,968,811Change Order Proposals Pending 54 $613,565Change Order Requests Pending 0 $0.00Team Change Memos Approved 3 $126,764

* Change Order amount includes added scope for Audio Visual and Communications Cable Packages, as well as a Conformance Change Order that included additional funds from other sources for tenant improvements.

Requests for Information to date Number Avg. TurnaroundRFI’s 460 5 days

Submittals to date Number Avg. TurnaroundSubmittals 255 18 days Disputes Review Board Status The most recent Disputes Review Board meeting was held October 1. There are currently no outstanding disputes.

90

Page 91: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

91

Page 92: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

2608

PRO

JEC

T C

OST

REP

OR

T - L

evel

2P

roje

ct:2

608T

acom

a P

hase

2B O

rigin

al

Bud

get

Late

st A

ppro

ved

Bud

get

Com

mitt

ed to

Dat

eA

ctua

l Cos

t to

Dat

eA

ppro

ved

Cha

nges

Pen

ding

Cha

nges

Est

imat

e o

f Unc

omm

itted

Fore

cast

Tot

al C

osts

Var

ianc

e fro

m

Late

st B

udge

t

AB

CD

FG

H (I

-C)

IJ

(B-I)

B.

C

onsu

ltant

Ser

vice

sP

re-D

esig

n S

ervi

ces

275,

000

275,

000

500,

498

485,

291

18,5

160

(15,

207)

485,

291

(210

,291

)B

asic

Ser

vice

s2,

307,

459

2,30

7,45

92,

321,

787

2,19

3,77

629

,071

00

2,32

1,78

7(1

4,32

8)E

xtra

Ser

vice

s1,

243,

551

1,24

3,55

11,

677,

787

1,39

8,04

81,

304,

888

3,90

63,

906

1,68

1,69

3(4

38,1

42)

Oth

er S

ervi

ces

526,

947

526,

947

724,

229

476,

578

517,

488

011

6,51

884

0,74

7(3

13,8

00)

Des

ign

Ser

vice

s C

ontin

genc

y35

9,48

535

9,48

50

00

019

2,29

719

2,29

716

7,18

8To

tal

B.

C

onsu

ltant

Ser

vice

s4,

712,

442

4,71

2,44

25,

224,

301

4,55

3,69

31,

869,

963

3,90

629

7,51

45,

521,

815

(809

,373

)

C.

C

onst

ruct

ion

Prim

e C

ontra

ct22

,976

,234

22,9

76,2

3423

,673

,988

23,2

85,3

4713

,370

00

23,6

73,9

88(6

97,7

54)

Oth

er

2,31

0,16

12,

310,

161

442,

842

366,

293

182,

193

00

442,

842

1,86

7,31

9G

C/C

M It

ems

3,49

8,78

03,

498,

780

4,82

5,49

94,

798,

922

1,17

4,28

025

8,10

125

8,10

15,

083,

600

(1,5

84,8

20)

Con

stru

ctio

n C

ontin

genc

y2,

126,

755

2,12

6,75

54,

311,

759

1,74

7,87

94,

311,

759

335,

837

335,

837

4,64

7,59

6(2

,520

,841

)C

onst

ruct

ion

Sal

es T

ax2,

485,

422

2,48

5,42

22,

890,

249

2,62

8,70

149

3,92

151

,799

51,7

992,

942,

048

(456

,626

)M

anag

emen

t Res

erve

531,

637

531,

637

00

00

398,

902

398,

902

132,

735

Tota

lC

.

Con

stru

ctio

n 33

,928

,989

33,9

28,9

8936

,144

,337

32,8

27,1

426,

175,

523

645,

737

1,04

4,63

937

,188

,976

(3,2

59,9

87)

D.

E

quip

men

tE

quip

men

t92

4,32

592

4,32

527

,218

11,2

010

070

2,51

572

9,73

319

4,59

2Fu

rnis

hing

s90

8,29

790

8,29

746

,517

17,6

1922

086

1,78

090

8,29

70

Equ

ipm

ent/F

urni

shin

gs S

ales

Tax

189,

834

189,

834

5,41

51,

464

00

184,

419

189,

834

0To

tal

D.

E

quip

men

t2,

022,

456

2,02

2,45

679

,150

30,2

8422

01,

748,

714

1,82

7,86

419

4,59

2

E.

A

rtwor

kA

rtwor

k13

8,60

813

8,60

813

8,60

80

00

013

8,60

80

Tota

lE

.

Artw

ork

138,

608

138,

608

138,

608

00

00

138,

608

0

F.

Oth

er C

osts

In-P

lant

Ser

vice

s10

7,92

710

7,92

710

,790

10,7

900

097

,137

107,

927

0U

tiliti

es/T

empo

rary

Fac

ilitie

s49

,155

49,1

5515

,988

14,4

400

033

,167

49,1

550

Per

mits

112,

020

112,

020

114,

362

6,64

30

00

114,

362

(2,3

42)

Bui

lder

s R

isk

Insu

ranc

e58

,772

58,7

7284

,605

84,6

050

00

84,6

05(2

5,83

3)P

arki

ng1,

200,

000

1,20

0,00

00

00

032

6,54

232

6,54

287

3,45

8O

ther

Cos

ts20

7,07

820

7,07

821

7,10

664

,472

12,0

001,

210

021

7,10

6(1

0,02

8)To

tal

F.

Oth

er C

osts

1,73

4,95

21,

734,

952

442,

851

180,

950

12,0

001,

210

456,

846

899,

697

835,

255

G.

P

roje

ct M

anag

emen

tC

PO

Man

agem

ent

1,49

9,71

71,

499,

717

1,49

9,71

795

9,81

90

00

1,49

9,71

70

Oth

er M

anag

emen

t31

1,83

631

1,83

626

6,43

018

0,21

30

045

,406

311,

836

0To

tal

G.

P

roje

ct M

anag

emen

t1,

811,

553

1,81

1,55

31,

766,

147

1,14

0,03

20

045

,406

1,81

1,55

30

Pro

ject

Tot

als

44,3

49,0

0044

,349

,000

43,7

95,3

9438

,732

,101

8,05

7,50

865

0,85

33,

593,

119

47,3

88,5

13(3

,039

,513

)

H.

S

cope

Cha

nges

Fund

ed S

cope

Cha

nges

G

ener

ator

010

0,00

00

00

00

010

0,00

0

Fenc

ing

and

Gro

wth

CO

022

,000

00

00

00

22,0

00

Inst

itute

of T

echn

olog

y0

867,

513

00

00

00

867,

513

S

tude

nt S

ervi

ces

095

0,00

00

00

00

095

0,00

0

Ret

ail

01,

100,

000

00

00

00

1,10

0,00

0To

tal

H.

Sco

pe C

hang

es0

3,03

9,51

30

00

00

03,

039,

513

Pro

ject

Tot

als

44,3

49,0

0047

,388

,513

43,7

95,3

9438

,732

,101

8,05

7,50

865

0,85

33,

593,

119

47,3

88,5

130

92

Page 93: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT PHOTOS

Cherry Parkes

Commerce Street side Mattress Factory Stair Tower

Commerce Street side

Mattress Factory North

C Street side Mattress Factory South

21st Street side

Final paving on C Street

Cherry Parkes Pacific Avenue storefront

93

Page 94: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

94

Page 95: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

William H. Gates Hall

Project Number 1846

Monthly Report

October 2003

Prepared by the Capital Projects Office

Thomas Ryan, Project Manager

95

Page 96: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT EXECUTIVE SUMMARY

William H. Gates Hall PROJECT DESCRIPTION William H. Gates Hall includes space for the Law Library, instructional spaces for the Law School, offices for faculty, administration, staff, graduate programs and centers, clinics, student activities and Continuing Legal Education programs. The site is located at the northwest corner of the main campus, south of the Burke Museum. The William H. Gates Hall building is programmed at 196,000 gross square feet. The 43rd Street Right-of-Way Pedestrian Improvements, including site improvements to separate vehicle and pedestrian access at the major campus entry, was approved to be included in this project by the Capital Facilities Committee, with additional funding allocated from the University. The project architect is Mahlum Architects in collaboration with Kohn Pederson Fox Associates. The General Contractor/Construction Manager is Lease Crutcher Lewis of Seattle. PROJECT MANAGER’S STATEMENT ON PROJECT STATUS Schedule Overview Correction of both construction and FF&E punch list is on-going. The Capital Projects team is coordinating these activities with the Law School to minimize impact to operations of the Law School. Our goal is to complete all punch list work, with few exceptions, by November 30, 2003. The most significant installation not yet complete are student lockers. Lockers are scheduled to be installed by November 17. Design Status & Approvals All construction and FF&E (furniture, fixtures and equipment) design work is completed with the exception of electronic building directory and information board (FF&E add service). Construction Accomplishments This Period Final commissioning activities proceeded. Punchlist and warranty work continued. The Architect began the process of “back-punching” to verify punchlist item completion. Various issues arose as the building occupants settled into their new environment. Determinations were made as to whether these items necessitated design or construction team action.

96

Page 97: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT BUDGET & COST Total project costs are forecast at $82,564,852. Total project funding is $81,529500. We forecast a net project overage of $1,053,352. This is lower than the September projection, due to ongoing resolution of cost and analysis of projected construction costs. CHANGES IN SCOPE There have been no scope changes this month. BUYOUT STATUS Buyout is complete. SAFETY STATUS

Safety Statistics This Month Project To DateAverage Daily Work Force 2Lost Time Incidents 0 2Recordable Incidents 0 19Total Hours Worked All Crafts 250 493,657Project Total Incidence Rate * 0 8.52 * Incidence Rate = (# of Incidents x 200,000 hrs) / (# of hours worked)

CONSTRUCTION CONTRACT ADMINISTRATION

Change Documents to date Number ValueChange Orders Approved 589 $7,763,295.07Change Order Proposals Pending 6 $224,969.00Change Order Requests Pending 6 $291,663.00Team Change Memos Approved 90 $1,307,590

Requests for Information to date Number Avg. TurnaroundRFI’s 2114 5 days

Submittals to date Number Avg. TurnaroundSubmittals 892 14 days

OPPORTUNITIES & CHALLENGES The primary challenge facing the construction team continues to be the completion of the punchlist. The project team is working to evaluate and conclude all remaining construction change requests in a timely manner. Only a handful of items remain. The large roofing change request was resolved. In addition to the Disputes Review Board (DRB) item noted below, issues remaining unresolved include several electrical issues and a request for compensation for extended general conditions.

97

Page 98: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Disputes Review Board Status An informal DRB process has started with regard to a handful of change requests from the mechanical subcontractor. This will be the last time this report is included in the monthly reports since it has achieved occupancy.

98

Page 99: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

PROJECT SCHEDULE / GANNT CHART

99

Page 100: Monthly Major Projects Report for October 2003cpd.uw.edu/cpo/sites/default/files/file/management-reports/03... · Lara Branigan Jon Lebo Andy Casillas Joel Matulys Lou Castino Jeraldine

Pro

ject

No.

1846

PRO

JEC

T C

OST

REP

OR

T - L

evel

2P

roje

ct:1

846

Will

iam

J. G

ates

Hal

l

Orig

inal

B

udge

tLa

test

App

rove

d B

udge

tC

omm

itted

to D

ate

Act

ual C

ost t

o D

ate

App

rove

d C

hang

esP

endi

ng C

hang

esE

stim

ate

of U

ncom

mitt

edFo

reca

st T

otal

Cos

tsV

aria

nce

from

La

test

Bud

get

AB

CD

FG

H (I

-C)

IJ

(B-I)

B.

C

onsu

ltant

Ser

vice

sP

re-D

esig

n S

ervi

ces

1,64

7,18

461

7,50

043

4,36

242

3,16

20

00

434,

362

183,

138

Bas

ic S

ervi

ces

3,83

1,13

33,

831,

133

3,83

1,03

33,

794,

115

00

100

3,83

1,13

30

Ext

ra S

ervi

ces

1,49

0,58

51,

490,

585

1,85

5,90

61,

505,

383

1,34

9,32

60

29,6

681,

885,

574

(394

,989

)O

ther

Ser

vice

s82

3,61

11,

849,

847

1,98

9,50

61,

888,

971

461,

309

043

1,35

42,

420,

860

(571

,013

)D

esig

n S

ervi

ces

Con

tinge

ncy

256,

676

260,

124

00

00

40,1

0140

,101

220,

023

Tota

lB

.

Con

sulta

nt S

ervi

ces

8,04

9,18

98,

049,

189

8,11

0,80

77,

611,

631

1,81

0,63

50

501,

223

8,61

2,03

0(5

62,8

41)

C.

C

onst

ruct

ion

Prim

e C

ontra

ct48

,591

,192

48,5

91,1

9253

,335

,370

52,0

75,0

506,

066,

710

1,37

4,53

640

,469

53,3

75,8

39(4

,784

,647

)O

ther

0

072

,440

72,4

400

00

72,4

40(7

2,44

0)G

C/C

M It

ems

5,32

2,15

85,

322,

158

5,30

6,78

06,

448,

129

(1,0

41,1

85)

1,02

4(4

0,12

2)5,

266,

658

55,5

00O

ther

Con

tinge

ncy

00

00

00

00

0C

onst

ruct

ion

Con

tinge

ncy

2,71

6,06

42,

716,

064

00

00

00

2,71

6,06

4C

onst

ruct

ion

Sal

es T

ax5,

062,

350

5,06

2,35

04,

502,

558

4,47

5,84

1(2

42,5

74)

00

4,50

2,55

855

9,79

2M

anag

emen

t Res

erve

897,

288

897,

288

00

00

00

897,

288

Tota

lC

.

Con

stru

ctio

n 62

,589

,052

62,5

89,0

5263

,217

,148

63,0

71,4

604,

782,

951

1,37

5,56

034

763

,217

,495

(628

,443

)

D.

E

quip

men

tE

quip

men

t0

019

9,64

312

8,34

90

0(1

99,6

43)

00

Furn

ishi

ngs

1,51

0,04

01,

510,

040

8,39

9,15

43,

800,

423

(11,

760)

0(1

,048

,736

)7,

350,

418

(5,8

40,3

78)

Equ

ipm

ent/F

urni

shin

gs S

ales

Tax

132,

884

132,

884

615,

642

212,

421

00

(38,

949)

576,

693

(443

,809

)To

tal

D.

E

quip

men

t1,

642,

924

1,64

2,92

49,

214,

439

4,14

1,19

3(1

1,76

0)0

(1,2

87,3

28)

7,92

7,11

1(6

,284

,187

)

E.

A

rtwor

kA

rtwor

k19

0,19

419

0,19

419

0,19

40

00

019

0,19

40

Tota

lE

.

Artw

ork

190,

194

190,

194

190,

194

00

00

190,

194

0

F.

Oth

er C

osts

In-P

lant

Ser

vice

s75

,000

75,0

0018

3,63

618

3,50

60

00

183,

636

(108

,636

)U

tiliti

es/T

empo

rary

Fac

ilitie

s24

,000

24,0

000

00

00

024

,000

Per

mits

270,

204

270,

204

129,

362

25,3

470

00

129,

362

140,

842

Bui

lder

s R

isk

Insu

ranc

e80

,664

80,6

6481

,244

580

00

081

,244

(580

)O

ther

Cos

ts40

5,00

040

5,00

041

6,66

619

5,84

36,

750

00

416,

666

(11,

666)

Tota

lF.

O

ther

Cos

ts85

4,86

885

4,86

881

0,90

840

5,27

66,

750

00

810,

908

43,9

60

G.

P

roje

ct M

anag

emen

tC

PO

Man

agem

ent

1,21

3,81

81,

213,

818

1,35

4,21

81,

188,

772

140,

400

00

1,35

4,21

8(1

40,4

00)

Oth

er M

anag

emen

t31

5,45

531

5,45

543

2,89

641

4,30

10

020

,000

452,

896

(137

,441

)To

tal

G.

P

roje

ct M

anag

emen

t1,

529,

273

1,52

9,27

31,

787,

114

1,60

3,07

314

0,40

00

20,0

001,

807,

114

(277

,841

)

Pro

ject

Tot

als

74,8

55,5

0074

,855

,500

83,3

30,6

1076

,832

,633

6,72

8,97

61,

375,

560

(765

,758

)82

,564

,852

(7,7

09,3

52)

H.

S

cope

Cha

nges

Fund

ed S

cope

Cha

nges

:

Tunn

el Im

prov

emen

ts0

80,0

000

00

00

080

,000

S

ound

Tra

nsit

43rd

Stre

et R

OW

054

0,00

00

00

00

054

0,00

0

Furn

iture

06,

054,

000

00

00

00

6,05

4,00

0U

nfun

ded

Sco

pe C

hang

es:

M

isc

Ow

ner D

irect

ed C

hang

es0

029

7,55

40

00

00

0To

tal

H.

Sco

pe C

hang

es0

6,67

4,00

029

7,55

40

00

00

6,67

4,00

0

Pro

ject

Tot

als

74,8

55,5

0081

,529

,500

83,6

28,1

6476

,832

,633

6,72

8,97

61,

375,

560

(765

,758

)82

,564

,852

(1,0

35,3

52)

100