NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Monthly Progress Report on
NTDCL Development Projects
forSeptember, 2013
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Ongoing Development Projects
Projects Ready for Implementation
Cross Border Interconnection Projects
1
ACTIVITIES
Ongoing Projects of NTDC
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
1- 220 kV GIS Bandala
220 kV substation with two 220/132 kV 160 MVA T/Fs along with allied equipment. 1,950
32 30-11-2006 ADB Tranche-I
Civil & electrical works in progress.
90 % October, 2013
In/Out of 220 kV Gatti-KSK Transmission Line at Bandala (5+5 km)
T/L Completed. 100 % Commissioned on
16-05-2012
2- 220 kV Rohri
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
4,84778 06-02-2008 ADB
Tranche-II
Civil and electrical works in progress.
86 % October, 2013
220 kV Dharki-Rohri New D/C T/L (115 km)
T/Ls Completed. 100 % Commissioned in
June, 2012
220kV D/C Rohri New-Shikarpur T/L (50km)
220kV D/C T/L for In/Out of Fauji Mari-Rohri New at Engro Chemical CCPP (5+5km)
3
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No. Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected Commissioning
3-220 kV Khuzdar & 220kV Dadu-Khuzdar D/C T/L
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,90050 27-07-2004 JICA
Civil and electrical works in progress.
82 % December, 2013
220 kV Dadu-Khuzdar D/C T/L (274 km)Lot-I= 135 KMLot-II=139 KM
Erection and stringing work in progress.
Lot-I=97%Lot-II=79% December, 2013
4- 220 kV Kassowal
220 kV substation with two 220/132 kV 160 MVA T/Fs and allied equipment
2,06736 02-02-2005 World Bank
Civil and electrical works in progress.
67 % March, 2014
Two 220 kV D/C T/L for In/out of 220 kV Vehari-Yousafwala D/C T/L at Kassowal (45+45km)
T/L Completed. 100 % T/L commissioned
on 06-08-2012
5- 220 kV GIS Shalamar
220 kV gas insulated substation with three 220/132 kV 160 MVA T/Fs and allied equipment
3,61759 22-10-2007 JICA
Civil and electrical works in progress.
80 % October, 2013
T/L Completed. 100 %
T/L commissioned on 20-11-2012
220 kV D/C T/L for In/Out of one circuit of 220 kV Ravi-KSK T/L at Shalamar (9 km) and under ground cable (3+3 km)
4
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNEC Financing Project
StatusOverall
ProgressExpected
Commissioning
6- 220 kV Okara
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,88431 06-02-2008 ADB Tranche-II
Civil and electrical works in progress.
90 % October, 2013
In/out of 220 kV Yousaf Wala-Sarfraz Nagar D/C T/L at Okara (5+5 km)
T/L Completed. 100 %
T/L Commissioned on 26.05.2012
.
7- 220 kV T.T. Singh
220 kV substation with three 220/132 kV 250 MVA T/Fs and allied equipment
1,75929 06-02-2008
ADB Tranche-II Installation in progress. 92 %
October, 2013
In/Out of 220 kV Faisalabad-Multan D/C T/L at T.T Singh (1+1 km)
NTDC own resources
Civil works completed.
Erection and Stringing in
progress
92 %
5
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
8- 220 kV Loralai
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
5,08883 06-02-2008
ADB Tranche-IICivil and electrical works in progress.
84 %
December, 2013
220 kV D.G Khan-Loralai D/C T/L (200 km) ADB Tranche-I
Erection and stringing in progress.
94 %
9-500 kV Rahim Yar Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment
4,93681 22-10-2007 JICA
Civil and electrical works in progress.
65 %
December, 2013
500 kV S/C T/L for In/Out of 500 kV Guddu-Multan 3rd Circuit at R.Y Khan (30+30 km)
Civil and Electrical works in progress.
59.95 %
6
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
10-Ext. at 500 kV Ghazi Barotha
Addition of one 500/220 kV 600MVA T/F with allied equipment.
1,65427 06-02-2008 ADB
Tranche-IICivil works in
progress. 65 % December, 2013
11- 220 kV Gujrat
220 kV substation with three 220/132 kV 250 MVA T/Fs with allied equipment.
1,96632 22-10-2007 JICA
Construction of boundary wall is in
progress and contractor is
preparing design submittals for
approval.
5 % July, 2015220 kV D/C T/L for In/Out of 220kV Mangla-Ghakkar D/C T/L at Gujrat (2+2 km)
12-220 kV Ghazi Road, Lahore
220 kV substation with three 220/132 kV 160 MVA T/Fs and allied equipment.
2,59243 25-02-2005
KfW
Bidding documents vetted by M/S Lahmayer and sent to KfW for concurrence.Land acquired.
5 % December, 2014
220 kV D/C T/L for In/Out of 220 kV NKLP-S/Nagar S/C at Ghazi Road (30 km) Korean Exim
BankT/Ls ready for commissioning 100 %
Work completed and ready for
commissioning220 kV D/C T/L for In/Out of 220 kV Ravi-KSK S/C at Ghazi Road (50 km)
7
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
13- 220 kV Chishtian
220 kV substation with two 220/132 kV 250 MVA T/Fs and allied equipment
2,63343 22-10-2007 JICA
Civil work in progress. 49%
December, 2013
220 kV Chishtian-Vehari D/C T/L (65 km) Civil and
Erection work in progress.
51%
49%Extension at 220 kV Vehari Grid Station
14- 500 kV D.G Khan
500 kV substation with two 500/220 kV 600 MVA & two 220/132 kV 250 MVA T/Fs and allied equipment
4,46773 06-02-2008 ADB
Tranche-II
Civil and erection works
in progress. 39.09 %
December, 2013
Erection and stringing in progress
78.37 %In/Out of 500 kV Guddu-Multan 2nd Circuit at D.G Khan (20+20 km)
8
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Expected
Commissioning
15-Augmentationof existing Grid Stations
Name of Grid Stations
No. of
T/FsVoltage
(kV)Capacity
(MVA)
3,90046
21-01-2010 ADB Tranche-II
i) Contract agreement for 13
T/Fs has been signed with M/S SUNIR and are expected to be
delivered in December 2013.
ii)Bidding document for 5 T/Fs has been sent to ADB for concurrence.
December, 2013
500 kV Rewat 1 500/220 750
500 kV Sheikh Muhammadi
4 220/132 250
220 kV Mardan 2 220/132 250
220 kV Burhan 4 220/132 250
220kV Bund Road 4 220/132 250
220 kV Bahawalpur 2 220/132 250
220 kV Quetta Industrial
2 220/132 250
9
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
16- SVC at NKLPStatic Var Compensators with T/F of 450 MVA Capacity
2,08734 30-11-2006 ADB
Tranche-I
Basic design has been
agreed upon and project will be completed on schedule.
26 % May, 2014
17- 220 kV Dera Murad Jamali
220 kV substation with 220/132 kV 1x160 MVA & 1x100 MVA T/Fs and allied equipment
88011
PC-I approved by CDWP on
07-04-2011NTDC own resources
Contractor mobilized and civil works in
progress.10 %
December, 2014
220 kV D/C single conductor T/L for In/Out of 220 kV Uch-Guddu S/C at Dera Murad Jamali (5 km)
Re-survey work in
progress. 5 %
10
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project Status Overall
ProgressExpected
Commissioning
18-500 kV Lahore New
500 kV substation with two 500/220 kV 750 MVA T/Fs and allied equipment
12,664147 09-12-10 JICA
Work is delayed due to non availability
of land.
5 % 2014-15
Two 500 kV S/C T/Ls for In/Out of 500 kV Sahiwal-Lahore S/C at Lahore New (15+15km)
T/L route survey is in progress.
Two 500 kV S/C T/Ls for In/Out of 500 kV Lahore – Gujranwala S/C at Lahore New (50+50 km)
220 kV D/C T/L for In/Out of 220 kV NKLP- Ghazi Road S/C at Lahore New (50km)
220kV D/C T/L for In/Out of 220 kV NKLP- Wapda Town S/C at Lahore New (45 km)
11
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval
by ECNECFinancing Project
StatusOverall
ProgressExpected
Commissioning
19-
Installation of SVS at 220/132 kV Quetta Industrial
SVS (SVC of -50/+300 MVAR & MSC of 300 MVAR)
2,08734 06-02-08 ADB Tranche-II Not yet
started. NIL December, 2014
20- 500 kV Shikarpur
500 kV substation with two 500/220 kV 600 MVA T/Fs and allied equipment
8,08594 09-12-10 JICA
Contract agreement signed, L/C opened and contractor mobilized.
Land acquired.
21.25 % August, 2014
Two 500 kV S/C T/Ls for In/out of 500 kV Dadu -Guddu Cct # 1 (20+20 km)
1.25% June, 2015Two 500 kV S/C T/Ls for In/out of 500 kV Dadu – Guddu Cct # 2 (22+22 km)
220 kV D/C T/L for In/out of 220 kV Guddu – Sibbi S/C at Shikarpur (50 km)
12
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the
ProjectsScope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project Status Overall
ProgressExpected
Completion
21-
Power Dispersal from 747 MW CCPP Guddu
500kV Guddu-Muzaffargarh S/C T/L (256 km)
7,85691 29.07.2011
Buyer’s Credit Basis
Tender opened on 08.10.2012 evaluated and sent to BOD for
approval.NIL
2014-15500 kV T/L for In/Out of 500 kV D.G Khan-Multan S/C T/L at 500 kV Muzaffargarh (10 +10 km)
Three 500 kV line bays at Muzaffargarh substation
500 kV T/L for In/Out of existing Guddu-Multan (R.Y.Khan) T/L at 500 kV Guddu New substation (2+2 km)
Deposit work of
GENCO-IICivil works in progress. Dec. 2013
22-Power Dispersal from Uch-II
220 kV Uch-II – Sibbi D/C T/L (125km)
2,50830 16.08.2012 ADB
Tranche-III
Bid evaluation report finalized. ADB has been requested for allowing price negotiation with
single bidder. Response from ADB is awaited.
5 % Dec. 2014
Extension at 220kV Sibbi substation Work in progress from NTDC own resources. 50% April, 2014
220 kV D/C T/L for In/Out of 220kV existing Uch-I to Shikarpur New S/C T/L at Uch-II (0.5 km) Reconductoring of 1km
T/L and In/Out of 0.5km completed.
100 % Commissioned on 25.04.2013
Reconductoring of 220kV T/L Uch-I to Uch-II (1 km)
13
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRs/ MUS$)
Date of Approval by
ECNECFinancing Project
StatusOverall
ProgressExpected
Completion
23-Power Dispersal from Neelum Jhelum HPP
Package-I500 kV D/C T/L from Neelum Jhelum to Gujranwala (270km)
22,582251
Approved by ECNEC on 26.08.2013
Buyer’s Credit Basis
LOA issued on
12.09.2013.NIL 2015-16
500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Azad Pattan (5km)
500 kV D/C T/L for In/out of 500 kV Neelum Jhelum Gujranwala S/C at Karot (5 km)
Package- IIExtension at 500 kV Gujranwala
Bidding not yet initiated
24-
Power Dispersal Arrangements from Duber Khwar Power House
220 kV D/C T/Line from Duber Khwar to Khan Khwar Power House (33km)
249428
(For Lot-I & II)
Approved under PC-I of Hydel Power Project
Deposit work of G.M (Hydel)
Erection and stringing work in progress.
90 %
Oct. 2013(Subject to
clearance of ROW problems from Tower No. 2 to 10 during Jirga Meeting
on 18.08.2013)
14
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER 15
Sr. No.
Name of the Projects Scope of work
Approved Cost
(MRS/MUS$)
Date of Approval
by ECNEC Financing Project Status
Overall Progress
Expected Completion
25-
Dispersal of power from 2x50MW Wind Power Plants at Mirpur Sakro
132kV D/C T/L on Greeley conductor from WPP#1 to 132kV Thatta G/S (64km)
81614 22-04-2006
NTDC own resources
Tender opened,
evaluated and case is being prepared for
getting approval of competent
authority for award of work
NIL June 2014Construction of two 132kV line bays each at Thatta G/S
26-
Interconnection arrangement for dispersal of power from TGF & WPP#4 at Jhimpir
132kV D/C T/L for looping I/O of Jhimpir-Nooriabad 2nd 132kV at TGF & WPP#4 at Jhimpir (7 km)
2072 _
NTDC own resources
Procurement of material initiated.
NIL 2014-15Conversion of 2 Nos. 132kV iso bays to line bays at Nooriabad substation for Kalu Kahar and Jamshoro old S/C T/Ls.
132kV T/L approx 4km from Nooriabad to the nearby Jamshoro-KDA T/L
Total108,526
1,479
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 500kV Projects
Sr. No. Description Addition in T/L & T/F Capacity
1- 500 kV S/C Transmission Lines Length 1150 km
2- 500/220 kV Transformation Capacity (New Projects) 5100 MVA
3- 500/220 kV Transformation Capacity (Extension) 600 MVA
4- 500/220 kV Transformation Capacity(Augmentation) 300 MVA
500/220 kV Transformation Capacity(Grand Total) 6000 MVA
16
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Ongoing 220kV Projects
Sr. No. Description Addition in T/L & T/F
Capacity1- 220 kV D/C Transmission Line 1227.5 km
2- 220/132 kV Transformation Capacity(New Projects) 6930 MVA
3- 220/132 kV Transformation Capacity(Extension) ----
4- 220/132 kV Transformation Capacity(Augmentation) 1620 MVA
220/132 kV Transformation Capacity(Grand Total) 8550 MVA
18
Projects Ready for Implementation
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of Approval by
ECNECFinancing Project Status Expected
Completion
1-
3rd Circuit from Jamshoro to Rahim Yar Khan (For power evacuation from 2x660 MW Coal Power Plant at Jamshoro & WPPs)
500 kV Jamshoro-Moro-R.Y.K S/C T/L (535 km)
24,214269
Approved by ECNEC on 26.08.2013
ADBTranche-III
Rebidding in process. 2015-16
500 kV Moro-Dadu S/C T/L (55 km)
500 kV Switching Station at Moro
Extension at 500 kV Jamshoro, Dadu & R.Y.K Grid Stations.
2-Power Dispersal from Chashma Nuclear (C3 & C4)
220 kV Chashma Nuclear – Bannu D/C T/L (125 km)
3,10335
Approved by ECNEC on 26.08.2013
Proposed under ADB Tranche-IV
Route under checking. 2015-16
220kV D/C T/L for In/Out of existing C1 &C2 at C3 & C4 (2 km)
Extension at 220kV Bannu
20
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for ImplementationSr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of Approval by
ECNECFinancing Project
StatusExpected
Completion
3-
Power Dispersal from 1200 MW Thar Coal Based Power Plant
500 kV Thar – Matiari D/C T/L (250 km)
22,306237 16.08.2012
JICA has shown interest
to fund the project.
T/L Plan and Profile
Drawings completed. Execution is linked with
installation of Coal Fired
Power Plants at Thar.
2015-16
500 kV Switching Station at Matiari
4- 220 kV Nowshera
220kV sub station with 220/132kV 3x250 MVA T/Fs along with allied equipment
1,87631 06.02.2008
Proposed in ADB
Tranche-IV
Site for Grid Station
selected. Acquisition of
land in progress.
2015-16In/Out of 220 kV Ghazi Barotha – Shahi Bagh D/C T/L at Nowshera (5+5 km)
21
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of Approval by
ECNECFinancing Project Status Expected
Completion
5- 220 kV Lalian New
220kV sub station with 220/132kV 3x250 MVA T/Fs along with allied equipment
1,58118 11.11.2011
Proposed in ADB
Tranche-IV
Hiring of project preparatory
consultants in process.
Land not yet acquired
2015-16In/Out of 220 kV Gatti – Ludewala D/C T/L at Lalian New (4+4 km)
6- 220 kV Mansehra
220kV sub station with 220/132kV 2x250 MVA T/Fs along with allied equipment
90511
07.04.2011
ADBTranche-III
Bids opened on 26-02-2013
evaluated & sent to competent authority
for approval.Land acquired.
2015-16Two 220 kV D/C T/L for In/Out of 220 kV Alai Khawar – Islamabad Peshawar Road D/C at Mansehra (0.5+0.5 km)
22
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
NTDC Development Projects Ready for Implementation
Sr. No.
Name of the Projects Scope of work
Est. Cost (MRs/MUS$)
Date of approval by
ECNECFinancing Project Status Expected
Completion
7- 220/132 kV D.I.Khan
220kV sub station with 220/132kV 2x250 MVA T/Fs along with allied equipment
3,77944
09.12.2010Proposed in ADB
Tranche-IV
Land for G/S acquired.
Boundary wall completed.
2015-16220 kV D/C T/L for In/Out of 220 kV Chashma Nuclear-Ludewala S/C T/L at D.I Khan (100km)
Total 57,764
645
23
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Summary of Projects Ready for Implementation
Sr. No. Description Addition in T/L & T/F Capacity
1- 500kV S/C Transmission Lines Length 1090 km
2- 220kV Transmission Line 246 km
3- 220/132 kV Transformation Capacity 2500 MVA
24
Cross Border Interconnection Projects
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection ProjectsSr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
1-Import of 100MW Power from Iran.
220 kV Pak Iran Border-Gwadar D/C T/L (100km)
44
Work of profile & plan tabling is in
progress. 70% by Export
Development Bank of Iran and 30% by
NTDC.
August, 2014Work awarded to
contractor and contractor mobilized.
220 kV GIS at Gwadar with 2x160MVA T/Fs
2-Import of 1000MW Power from Iran.
500 kV HVDC Bipolar Transmission Line from Pak - Iran Border to Quetta (585km).
508
MoU signed between Pakistan & Iran on 31.05. 2012
to implement the project.
Not yet committed 2015-16
500 kV Convertor Station at Quetta.
220 kV Quetta-Quetta Ind.D/C T/L (5 km)
220 kV Quetta-Loralai D/C T/L (170km)
220 kV Quetta-Mastung D/C T/L (50km)
26
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
Cross Border Interconnection ProjectsSr. No.
Name of the Projects Scope of work Est. Cost
(MUS$) Project Status Financing Expected Completion
3-Import of 1000MW Power from Tajikistan (CASA-1000)
500 kV HVDC Bipolar Transmission line from Pak-Afghan Border to Peshawar (71km).
200 Feasibility Study completed.
Positive response from
World Bank and IDB
2015-16500 kV Converter Station at Peshawar
220 kV D/C T/L for interconnection of 220 kV Peshawar- ShahiBagh (10 km)
500 kV D/C T/L for interconnection of 500 kV Peshawar- Tarbela (5 km)
4-Import of 200-500 MW Power from India.
Different options for Interconnection are under study. -
World Bank has offered to sponsor pre-feasibility study
for the project
Positive response from
World Bank-
Total 752
27
NATIONAL TRANSMISSION AND DESPATCH COMPANY LIMITED
PLANNING POWER
Report Prepared by: Designation Contact No.
Maqsood Ahmad Qureshi
ManagerProjects Planning
0347-4447720 042-99202609
Fahmeeda Shafi Dy. Manager Projects Planning
042-99202609
28