Pipeline Material Selection Study Report PL- 31

1Prepared by Corrigo Technical Services Sdn Bhd

Content1.0: Project Background2.0: Pipeline Paramaters3.0: Material Candidates 4.0: Result Summary

2

1.0 Project Background3SKO currently produces about 91.1 kblpd of net oil to MCOT, BCOT and MLNG in addition to about 702 mmscf/d of natural gas.

Current operating pipeline assets arising from integrity risk assessment / premature failures/degradations have been confirmed with high internal corrosion risk suspected arising from Microbially Influenced Corrosion (MIC)

For Pipeline Rehabilation Program, PCSB has awarded Petrofac RNZ to perform Pipeline Material Selection Study (PMSR) for PL-31

This study will determine the most optimum material to be used for the SKO pipeline rejuvenation for these pipeline.

42.0 Pipeline Parameters PL-31PL IDSERVICETotal LengthNominal Pipeline SizeOriginating PlatformLanding PlatformPL - 31FWS1.559 km 6 inBNJT-C BNJT-F

3.0 Material Candidates5 Material candidates based on DDBM study :

Stand alone (PVDF)

In-Field Liner using (PVDF)

4.0 Result Summary6ItemStand Alone (PVDF)In Field Liner (PVDF)1. Pipeline Hydraulic Analysis Report6 inch6 inch2. Fluid Material Compatibility StudyAs per PTS 30.10.02.13. However PTS does not have much verification for PVDF. Need further study.As per PTS 30.10.02.13 However PTS does not have much verification for PVDF. Need further study.3. Degradation Design Basis MemorandumResist to common corrosive corrosion (MIC,CO2,H2S, Seawater etc.). Resist to common corrosive corrosion (MIC,CO2,H2S, Seawater etc.). 4. Failure Mode Effects AnalysisTechnically feasibleTechnically feasible5. Life Cycle Cost AnalysisCAPEX = $16,582,344CAPEX = $18,965,770OPEX = $16,568,158OPEX = $16,038,005Material Selection : In Field Liner due to lowest cost