MRP II+ +Chapter+4

Embed Size (px)

Citation preview

  • 8/8/2019 MRP II+ +Chapter+4

    1/38

    By:-

    Gaurav Goyal

    Assistant Prof,LMTSOM

    MRP-II

    12/01/101

  • 8/8/2019 MRP II+ +Chapter+4

    2/38

    MRP Works Best When...

    End Products are Standardized

    Batch Production

    End product is moderately complex and isassembled from a set of components andraw materials

    E.g automobiles, food processing and

    electronics items

    12/01/102

  • 8/8/2019 MRP II+ +Chapter+4

    3/38

    Limitations of MRP

    only looks at materials, ignores capacity,shop floor conditions

    requires user discipline

    requires accurate information/datarequires valid MPS

    12/01/103

  • 8/8/2019 MRP II+ +Chapter+4

    4/38

    WHAT IS MRP II??An information system that integrates all

    manufacturing and related applications includingdecision support, material requirement planning(MRP), accounting and distribution. Def given by APICS (Advancing Productivity,Innovation and Competitive Success)

    It is used to determine all resources of themanufacturing company related to manufacturing andnot only material requirement.

    Has a simulation capability to answer "what-if"questions.

    It is a total company management concept for usinghuman resources more productively.

    12/01/10

    4

  • 8/8/2019 MRP II+ +Chapter+4

    5/38

    Expanded MRP with emphasis placedon integration

    Financial planning

    Marketing

    Engineering

    Purchasing

    Manufacturing

    MRP II

    12/01/105

  • 8/8/2019 MRP II+ +Chapter+4

    6/38

    DIFFERENCE BETWEEN MRP,MRP II AND ERPMRP is simply about ensuring the materials are

    available to manufacture a specific part in aspecific volume

    MRP II takes care of all other aspects of a job

    including ordering, tracking inventory andensuring capacity.

    ERP is an integrated information system thatserves all the departments within an enterprise.

    ERP provides an integral coordination of theactivities that are carried out in all thedepartments of the enterprise.

    12/01/10

    6

  • 8/8/2019 MRP II+ +Chapter+4

    7/38

    just because MRP says

    produce X, are we able toproduce X?

    12/01/107

  • 8/8/2019 MRP II+ +Chapter+4

    8/38

    Capacity Requirements

    PlanningNo..Need to evaluate the capacity to see if it can meet

    planNeed all of MRP information plus:

    1. How much capacity a process requires to make 1unit of a product

    2. When does the process need the hours (time) ofcapacity

    12/01/108

  • 8/8/2019 MRP II+ +Chapter+4

    9/38

    CAPACITY REQUIREMENTPLANNING

    12/01/109

  • 8/8/2019 MRP II+ +Chapter+4

    10/38

    MarketMarket

    DemandDemand

    ProductionProductionplanplan

    Problems?Problems?

    Rough-cutRough-cut

    capacity planningcapacity planning

    YesYes NoNo YesYesNoNo

    FinanceFinance

    MarketingMarketing

    ManufacturingManufacturing

    AdjustAdjustproduction planproduction plan

    MasterMaster

    productionproduction

    scheduleschedule

    MRPMRP

    CapacityCapacity

    planningplanning

    Problems?Problems?RequirementsRequirements

    schedulesschedules

    Adju

    stmast e

    rsc

    hedule

    Adju

    stmast e

    rsc

    hedule

    MRP IIFigure 13.14

    12/01/1010

  • 8/8/2019 MRP II+ +Chapter+4

    11/38

    Capacity Planning

    Develop a tentativemaster production

    schedule

    Develop a tentativemaster production

    schedule

    Use MRP tosimulate material

    requirements

    Use MRP tosimulate material

    requirements

    Convert material

    requirements toresource requirements

    Firm up a portionof the MPS

    Is shopcapacity

    adequate?

    Cancapacity be

    changed to meet

    requirements

    Revise tentative

    master productionschedule

    Changecapacity

    Yes

    No

    Yes

    No

    Figure 13.15

    12/01/1011

  • 8/8/2019 MRP II+ +Chapter+4

    12/38

    Defining CapacityCapacity is the amount of work that can

    be done in a period of time

    It is usually stated in standard hours ofwork

    It must be determined at plant,department, and work center levels.

    12/01/1012

  • 8/8/2019 MRP II+ +Chapter+4

    13/38

    Capacity Planning ProcessDetermine the capacity available

    Translate the released and planned

    orders into capacity requiredSum up capacities required for each

    work center

    Resolve differences between availablecapacity and required capacity

    12/01/1013

  • 8/8/2019 MRP II+ +Chapter+4

    14/38

    Determining Capacity

    AvailableCapacity available is the capability of a

    system or resource to produce a

    quantity of output in a particular timeperiod.

    Available (theoretical) capacity can becalculated or measured

    To calculate available capacity, oneneeds to knowAvailable timeUtilizationEfficiency

    12/01/1014

  • 8/8/2019 MRP II+ +Chapter+4

    15/38

    Capacity MeasurementsTheoretical capacityvolume of activity that could be attained

    under ideal operating conditions, with

    minimum allowance for inefficiency. It isthe largest volume of output possible;also called maximum capacity.

    Demonstrated capacityhighest activity level at which the

    factory can operate with an acceptabledegree of efficiency, taking intoconsideration unavoidable losses ofproductive time (i.e., vacations, holidays,repairs to equipment) 12/01/1015

  • 8/8/2019 MRP II+ +Chapter+4

    16/38

    End of Session 10

    12/01/1016

  • 8/8/2019 MRP II+ +Chapter+4

    17/38

    Utilization and Efficiency

    Actual Hours Charged

    Utilization =Scheduled Available Hours

    Standard Hours Earned

    Efficiency = Actual Hours Charged

    12/01/1017

  • 8/8/2019 MRP II+ +Chapter+4

    18/38

    Rated Capacity = Available time x Utilization xEfficiency

    Rated or Actual Capacity

    12/01/1018

  • 8/8/2019 MRP II+ +Chapter+4

    19/38

    CAPACITY REQUIREMENTPLANNINGThe technique that allows business to plan ahead to

    determine how large their future inventory capacityneeds to be in order to meet demand.

    Key elements of the CRP process areEstablishing

    Measuring

    adjusting the levels of the production capacity basedon the process of determining the amount of labor

    and machine resources required to accomplish thetasks of production

    12/01/1019

  • 8/8/2019 MRP II+ +Chapter+4

    20/38

    CAPACITYCapacity Lead Strategy

    It is done in anticipation of demand and thecapacity is increased.

    It is a very aggressive strategy and is used tolure customers away from competitors.

    Capacity Lag StrategyIt is done after demand has increased and the

    capacity is then increased.

    It is a conservative strategy and may result inloss of customers.

    It assumes that customers will return aftercapacity has been met which might not be true.

    12/01/1020

  • 8/8/2019 MRP II+ +Chapter+4

    21/38

    STRATEGIES FOR TIMINGCAPACITYAverage Capacity StrategyHere average expected demand is calculated

    and then capacity is increased accordingly.

    It is a moderate strategy.

    12/01/1021

  • 8/8/2019 MRP II+ +Chapter+4

    22/38

    Capacity Planning

    Load reports:Department or workcenter reports that compare knownand expected future capacityrequirements with projectedcapacity availability.

    Time fences: Series of time intervalsduring which order changes are

    allowed or restricted.

    12/01/1022

  • 8/8/2019 MRP II+ +Chapter+4

    23/38

    12/01/1023

    Rough Cut Capacity Planning

    Approximate calculation of the capacityrequired at critical work centers to meet thedemand in order to check the feasibility of aMaster Production Schedule.

    When the capacity required exceeds thecapacity available the MPS must be adjustedbefore proceeding to the MRP.

  • 8/8/2019 MRP II+ +Chapter+4

    24/38

  • 8/8/2019 MRP II+ +Chapter+4

    25/38

    Lead-Time ElementsQueuetime waiting before operation begins

    Setup

    time getting ready for operation

    Run time performing operation

    Wait time waiting after operation ends

    Move

    time physically moving between operations

    12/01/1025

  • 8/8/2019 MRP II+ +Chapter+4

    26/38

    Adjustments to Capacity orLoad Increasing CapacityAdd extra shifts

    Schedule overtime or weekends

    Add equipment and/or personnel

    Reducing Load

    Subcontract work to outside suppliers Reduce lot sizes

    Hold work in production control

    Reduce the MPS

    Reducing Capacity

    Eliminate shifts or reduce length of shifts worked Reassign personnel temporarily

    12/01/1026

  • 8/8/2019 MRP II+ +Chapter+4

    27/38

    Continued Increasing Load Make items normally purchased or subcontracted

    Release orders early

    Increase lot sizes

    Increase the MPS

    Redistributing the Load Use alternate work centers

    Use alternate routings

    Adjust operation start dates forward or backward in time

    Revise the MPS

    12/01/1027

  • 8/8/2019 MRP II+ +Chapter+4

    28/38

    Load Sources

    Open OrdersMRP - Planned Order Releases

    Other SourcesReworkExcess scrapQuality problems

    12/01/1028

  • 8/8/2019 MRP II+ +Chapter+4

    29/38

    Routing Data

    Operation identification codeOperation description

    Planned work center

    Standard setup timeStandard run time per unit

    Tooling requirements

    12/01/1029

  • 8/8/2019 MRP II+ +Chapter+4

    30/38

    CRP ILLUSTRATION

    12/01/1030

    http://crp%20illustration.ppt/http://crp%20illustration.ppt/
  • 8/8/2019 MRP II+ +Chapter+4

    31/38

    MGT 651 - IV DR. OZATALAY31

    Scheduling

    ObjectivesMeet delivery datesEffectively use manufacturing resources

    InvolvesEstablishing start and finish dates for each

    operation needed to complete an order

    S h d li d L di

  • 8/8/2019 MRP II+ +Chapter+4

    32/38

    MGT 651 - IV DR. OZATALAY32

    Scheduling and LoadingTechniquesForward scheduling:Activity starts as soon as the order is received

    .regardless of due date

    Backward scheduling

    Activities are scheduled back from the due dateInfinite loadingAssumes capacity is infinite at any work center

    Finite loading

    Assumes there is a definite limit to capacity at anywork center

  • 8/8/2019 MRP II+ +Chapter+4

    33/38

    MGT 651 - IV DR. OZATALAY33

    Bottlenecks ManagementBottlenecks control the throughput of all

    products processed by them

    Work centers feeding bottlenecks should bescheduled at the rate the bottlenecks can

    processA time buffer inventory should be established

    before the bottleneck

    Work centers fed by the bottleneck have their

    throughput controlled by the bottleneck

  • 8/8/2019 MRP II+ +Chapter+4

    34/38

    MGT 651 - IV DR. OZATALAY34

    Input, Output, Queue, and Capacity

    Queue

    Capacity

    Input Input Input

  • 8/8/2019 MRP II+ +Chapter+4

    35/38

    MGT 651 - IV DR. OZATALAY35

    Actual Output Less Than Planned Output

    Queue

    Capacity

    Input Input Input

    Not enough input?

    Queues and lead

    times increase

    Insufficient Capacity?

  • 8/8/2019 MRP II+ +Chapter+4

    36/38

    MGT 651 - IV DR. OZATALAY36

    Actual Input Less Than Planned Output

    Queue

    Capacity

    Input Input Input

    Feeding work centers

    behind schedule

    Work released late

    Late ordersMay run out of work

  • 8/8/2019 MRP II+ +Chapter+4

    37/38

    MGT 651 - IV DR. OZATALAY37

    Actual Output Greater Than Planned Output

    Queue

    Capacity

    Input Input Input

    May run out of work

    Excess Capacity

  • 8/8/2019 MRP II+ +Chapter+4

    38/38

    MGT 651 IV DR OZATALAY38

    Actual Input Greater Than Planned Input

    Queue

    Capacity

    Input Input Input

    Feeding work centers

    ahead of schedule

    Work released early

    Queues and lead times

    will increase