Ms-project Training Jekale Cmc by Abinet

Embed Size (px)

Citation preview

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    1/128

     Microsoft Project Microsoft Project

    Tutorial Tutorial 

    Abinet D.Abinet D.

    16/10/13

    Ms-project training JekaleCMC by Abinet D.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    2/128

    Conceptual Parts

    •  Introduction

    • Processes

     Presentation Outline

    1:40 AM 2

     MS Project Application

     Introduction

    Scheduling Tasks

    Setting Resources

     Assigning Resources Assigning Costs

    Checking & Adjusting Project 

    Plan

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    3/128

     Introduction Introduction

    • Background

    • Definition, Purposes

    • Contractual Bases

    • Programming andPresentation Methods

    • Programming

    Approaches

     Presentation Outline

    1:40 AM 3

     Processes Processes

    Basic Planning

    Scope, Construction Methods &

    Crews

    Activities & ResourcesDependencies

    Constraints

    Activity Duration Estimating

    Construction Programs   C

      o  n  c  e  p   t  u  a   l   P  a  r   t

       C

      o  n  c  e  p   t  u  a   l   P  a  r   t

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    4/128

     Introduction Introduction

    • Background

    • Definition, Purposes

    • Contractual Bases

    • Programming andPresentation Methods

    • Programming

    Approaches

     Presentation Outline

    1:40 AM 4

     Processes Processes

    Basic Planning

    Scope, Construction Methods &

    Crews

    Activities & ResourcesDependencies

    Constraints

    Precedence Diagram

    Activity Duration Estimating

    Construction Works Program

    Construction Resources Program

    Construction Cash Flow Program

       C

      o  n  c  e  p   t  u  a   l   P  a  r   t

       C

      o  n  c  e  p   t  u  a   l   P  a  r   t

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    5/128

    • Time is one among the Performance Criteria for Construction Projects

    • Time is an important planning component• Time is expressed in Construction Works Program called Scheduling

    • Scheduling is for everyone and can be used for every process

    • Therefore; Construction Time need to be planned

    • Otherwise; Failing to plan is planning to fail; that is, projects will

    delay

    • Projects delay causes:

    – Contractors to pay Liquidated Damages and may loose expensesof idle resources, overhead costs, and escalated amounts

    – Employers miss target completion dates, consequential benefits

    and additional costs due to time related claims

     Introduction: Background 

    1:40 AM 5

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    6/128

    • Construction Time Management is a process of:

    – Identifying Scopes, Activities and Resources

    – Programming Works, Resources and Cash Flows

    – Tracking, Monitoring and Evaluation of Time related progresses

    – Re-Programming

    • Purposes include:

    – Ensuring the successful completion of projects within the

    Contractual agreed date

    – Administering Programs and Time related Claims such as

    Extension of Time, Prolongation Costs and Liquidated damages

     Introduction: Definition + Purpose

    1:40 AM 6

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    7/128

    • Bill of Quantities

    • Works, Resources and Costs Breakdown Structures for Scope

    Definition

    • Construction Methods definition and Crews assignment

    • Basic / Master, Detail and Updated Programs

    • Programming and Presentation Methods and Approaches

    selection

    • Activities and Resources Dependencies

    • Construction Works, Resources and Cash flow Programs

    • Administrative and Technological allowances

     Introduction: Contractual Bases

    1:40 AM 7

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    8/128

    • Bar Chart

    • Critical Path Method (CPM)

    • Program Evaluation and Review Technique (PERT)

    • Network Diagramming (AoA, AoN and PrecedenceDiagram)

    • Line of Balance Technique (LOB)

    • Critical Chain Method

     Introduction: Programming & Presentation Methods

    1:40 AM 8

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    9/128

    • Graphical presentations of Works against time

     Introduction: Bar Chart

    1:40 AM 9

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    10/128

    AdvantagesAdvantages

    • Ease of Preparation and Use

     Introduction: Bar Chart

    1:40 AM 10

    DisadvantagesDisadvantages

    Lack representations of activities

    dependencies

    Does not show Critical activities

    Provides insufficient information

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    11/128

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    12/128

    AdvantagesAdvantages

    • Considers Activities and Resources

    dependencies

    • Shows Critical and Non-Critical

    activities with their floats

    • Considers and Provides Sufficient

    Information

     Introduction: Critical Path Method 

    1:40 AM 12

    DisadvantagesDisadvantages

    Lacks considerations of

    uncertainties

    PERT solves thisdisadvantage

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    13/128

    • Three types of Network Diagramming

    – Activities on Arrows system

    – Activities on Nodes system later derived to Precedence Diagrams

    – Event or Milestones system

    • Precedence Diagram

    – A derivative method of Activity on Nodes network diagramming

    – The Nodes represent:

     Introduction: Network Diagramming

    1:40 AM 13

    Earliest StartActivity

    Number

    Earliest

    Finish

    Latest Start Latest Finish

    Activity Description

    Total Float Duration

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    14/128

    • Precedence Diagram

    – The Arrow represents:

    • Four Type of Dependencies shown by the directions of the arrows; and

    • Lag or Lead times between activities.

     Introduction: Network Diagramming

    1:40 AM 14

    01

    5

    0 5

    Site

    Clearance

    0 5

    2

    3

    20

    7 25

    Bulk

    Excavation

    5 18

    SS = 2

    5 2 255 25

    Borrowed Fill

    0 20

    FS = 0

    25

    4

    10

    0

    25 10

    0

    Sub Base

    0 75FS = 0

    FS = 5

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    15/128

    • Precedence Diagram

    – The Four types of dependencies

     Introduction: Network Diagramming

    1:40 AM 15

     

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    16/128

    • LOB method is used to program / schedule recurrent activities

    • Recurrent activities include:

    – Sections in Transport, Communication and Electric Power Line related Projects

    – Construction Works on consecutive floors of buildings

     Introduction: Line of Balance Method 

    1:40 AM 16

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    17/128

    • Forward Pass Computations– Determines earliest starts and finishes

    – Saves Floats if adhered to earliest starts and finishes

    • Backward Pass Computations– Determines latest starts and finishes

    – Indicates floats to consume w/out affecting completion

    dates

     Introduction: Programming Approaches

    1:40 AM 17

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    18/128

     Introduction Introduction

    • Background

    • Definition, Purposes

    • Contractual Bases

    • Programming andPresentation Methods

    • Programming

    Approaches

     Presentation Outline

    1:40 AM 18

     Processes Processes

    Basic Planning for Programming

    Scope, Construction Methods &

    Crews

    Activities & ResourcesDependencies

    Constraints

    Activity Duration Estimating

    Construction Programs

       C  o  n  c  e  p   t  u  a   l   P  a  r   t

       C  o  n  c  e  p   t  u  a   l   P  a  r   t

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    19/128

     Processes: Basic Planning for Programming

    1:40 AM 19

    ItemsItems TasksTasks ApproachesApproaches

    Works

    Identifying & Knowing what is to be done

    Identifying the activities involved

    Identifying how the works can be done

    Studying Contract Document

    Developing WBSs

    Selecting Construction Methods

    Assignment of Crews

    Time

    Identifying When activities shall be done

    Whichactivities can be done in parallel?Which activities shall be done before or after thisactivity?

    Trade off between time and cost

    Identifying which ones require at most attentions

    Identifying where to provide buffers

    Network Analysis

    Critical Path

    Critical Chain

    ResourcesAssigning resources requirements MBSs, LBSs, EBSs & CBSs and their

    Schedules

    Controlling

    Developing Performance Targets / Milestones

    Identify how such targets to be measured

    Identify how to transform trends into impacts

    Communicate Performances

    Gantt Chart with Milestones

    Schedule and Cost Variances

    Cost & Schedule Performance Index

    Reporting Formats

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    20/128

    • Scope

    – BOQs of the Contract Document defines Scope of Works

    – WBSs is a tool to show the various classifications of Scopes for Construction

    Works Programming

     Processes: Scope, Construction Methods & Crews

    1:40 AM 20

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    21/128

    • Construction Methods considers

     –  Own Force Vs Outsourcing (Alliance / Sub Contracting)

     –  Equipment Vs Labour Intensive

     –  Own / Buy or Rent or Lease (Storage and Equipment)

     –  On site Vs Prefabrication and Assembly / Plant Based

     –  Temporary Vs Permanent Works

    • Construction Methods describes

     –  General description

     –  Scope and Tasks Involved

     –  Preparatory Works

     –  Resources involved

     –  Crew Designated and / or Assigned

     –  Productivities per Crew

     Processes: Scope, Construction Methods & Crews

    1:40 AM 21

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    22/128

    • Construction Methods: Example

     Processes: Scope, Construction Methods & Crews

    1:40 AM 22

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    23/128

    • Construction Methods

     Processes: Scope, Construction Methods & Crews

    1:40 AM 23

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    24/128

    • Construction Crews– Shows composition of Labor and Machineries for each trades of

    works

    – Serves as bases for determining productivities

    – Are either based on Organizational / National / International

    Standards

    – National Standards include:

    • EBCA / ETCA later BaTCoDA Standards

    • MoWaUD Pre - Output Norms

     Processes: Scope, Construction Methods & Crews

    1:40 AM 24

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    25/128

    • Activities Dependencies define

    – Which activity to Start / End

    – Which Activity to Precede / Follow

    – Which Activities to be executed in parallel

    – Which Activities diverge from Which Activity

    – Which Activities merge to which Activity

    • Resources Dependencies considers

    – Lead Time / Buffer for Resources Delivery

    – Storage Capacity for Resources Delivery

    – Scarcity for Resources Delivery

     Processes: Activities and Resources Dependencies

    1:40 AM 25

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    26/128

    • Constraints show Lead / Lag times in Network Diagrams and

    Work Programs• Constraints are considered for:

    Submittals which required for Engineer’s Initial & Intermediate reviews

    Shop Drawing Approvals

    Start up, Testing and Inspections Mockups for Local & Imported materials

    Procurement & Delivery for Local or Imported Materials, Machinery Rental or

    Import

    Procedural requirements for Sub Contracting

    Plant erection & Installations

    Productions

    Installation and Removal of Temporary Works

    Curing, etc

     Processes: Constraints

    1:40 AM 26

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    27/128

    • S – Curve can be the bases for Preliminary estimates of Time – Cost cut

    off points for its three Categories

     Processes: Estimating Activity Durations

    1:40 AM 27

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    28/128

    • For individual activities: di = qi / (pi x nci); where

    – di = duration of an activity i

    – qi = quantity of an activity i planned to be executed

    – pi = productivity of an activity i per a crew

    – nci = number of crews for an activity planned to be executed

    • numbers of crews are determined by apportioning the completion

    time and iteratively arriving to an optimum value

     Processes: Estimating Activity Durations

    1:40 AM 28

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    29/128

    • Construction Programs include

    – Construction Works Program• Activities from WBS & BOQs

    • Activity Quantities

    • Activity Durations

    • Lag Times• Precedence Diagrams

    – Construction Resources Program

    • Resources from LBSs, MBSs, EBSs & CBSs

    • Lead Times

    – Construction Cash flow Program

    • Cash Inflows from diversified financial sources

    • Cash Outflows including Direct and Indirect Costs

    • Cash Flow Balance

     Processes: Construction Programs

    1:40 AM 29

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    30/128

    Conceptual Parts

    •  Introduction

    • Processes

     Presentation Outline

    1:40 AM 30

     MS Project Application

     Introduction

    Scheduling Tasks

    Setting Resources

     Assigning Resources

     Assigning Costs

    Checking & Adjusting Project 

    Plan

       M   S   P  r  o   j  e  c   t   A  p  p   l   i  c  a   t   i  o  n

       M   S   P  r  o   j  e  c   t   A  p  p   l   i  c  a   t   i  o  n

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    31/128

    • MS Project

    – Is a Programming Software

    – Uses specialized databases internally

    – Defines Project and Task information

    – Stores and Presents many data such as Tasks, Durations, Links,

    Resources, Milestones, etc.

    – Undertakes computations to determine Early / Latest Starts /  

    Finishes; Floats / Slacks; Critical Activities / Path; Costs;

    Progresses; etc.

    – Presents results in different Views such as Gantt Chart;

    Precedence Diagram; Resources Graph; Cash flow; etc.

    – Programs, Tracks and Update Programs

    – Provides reports

     Introduction

    1:40 AM 31

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    32/128

     Microsoft Project 2007 

    • Just a tool; which helps to manage

    actives

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    33/128

    What do we need to work with MS-Project

    • Worked resource breakdown.

    • Duration to each activity (Start date, finish

    date, calendar, etc…)

    • Relation of activities

    • Generally Understanding your Project

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    34/128

    What to Expect /Ms-Project output/ 

    Automate repeated tasks: If you havetasks that repeat throughout the life of a

    project, such as weekly meetings or regular

    reviews, you can create a single repeating

    task, and Project duplicates it for you.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    35/128

    What to Expect /Ms-Project output/ 

    Project templates: If you often do similar typesof projects, you can create project templates with

    typical project tasks already in place; you can

    then modify the templates for individual projects.

    Project comes with templates to help you get

    started.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    36/128

    What to Expect /Ms-Project output/ 

    Import existing task lists: You can createprojects from tasks that you’ve set up in

    Outlook, or you can use Excel to start your

    project and then easily import the

    spreadsheet into Project.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    37/128

    What to Expect /Ms-Project output/ 

    Macros: You can take advantage ofMicrosoft Visual Basic to build macros that

    automate repetitive tasks, such as

    generating weekly reports. (advanced

    option)

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    38/128

    What to Expect /Ms-Project output/ 

    Advanced reporting and analyticalcapabilities: In addition to the reports

    Project provides, you can easily use Project

    data to prepare reports in Visio and Excel,

    providing you with additional analytical

    capabilities.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    39/128

    What to Expect /Ms-Project output/ 

    • Visual reports

    • Cost /financial reports/ 

    •  Activity assignment•  List of tasks in different categories

    • A Gantt Chart

    • Critical path

    • Easy summary tasks

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    40/128

     Defining the Project 

    • The objective of the project should bedefined by the person/group that is going to

    manage the project.

    • Tasks, start times, and deadlines should be

    clearly established.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    41/128

    Using MS Project 

    • Define the Project• Build the Plan

    – Set a start date

    – Enter tasks/durations

    – Assign resources

    – Link tasks– Fine tune the plan

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    42/128

    Using MS Project (cont’d)

    • Track and Manage– Set a baseline

    – Enter actual

    – Adjust plan

    • Close Project

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    43/128

    Start working with MS-Project 

    • Click start on Windows 7– Click on start

    – All Programs

    – Microsoft Office

    – “Microsoft office 2007”

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    44/128

    Start working with MS-Project 

    • For windows 8- Type “Microsoft office 2007” in search box or

    look @ on recent items

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    45/128

     Default View of Ms Project 

    Table areaChart area

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    46/128

    • Two Options to open an MS Project file:

    – Open MS Project from MS Office Drop Down Menu– From Existing File using “OPEN” from “File” Menu

    – Creating a New File using “NEW” from “File” Menu

    Start => MS-Project

    1:40 AM 46

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    47/128

    Setup a Project information

    1:40 AM 47

    ((To be scheduled from project startTo be scheduled from project start

    date)date)

    1. Click Project > Project

    Information.

    2. In the Start Date box,.

    ––  By default, the Start Date By default, the Start Date

    box shows today’s date.box shows today’s date.3. Click OK.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    48/128

    Setup a Project information

    1:40 AM 48

    SETUP A PROJECT(To be scheduled from project(To be scheduled from project finish finishdate)date)

    1. Click Project, Project

    Information.

    2. In the Schedule From box,

    click Project Finish Date.

    3. In the Finish Date box,enter the project finish

    date.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    49/128

    Setting Your Project Calendar 

    1:40 AM 49

    Working with Base Calendars in Microsoft Project Working with Base Calendars in Microsoft Project 

    Microsoft Project comes with four base calendars. These base calendars are like

    calendar templates that you can apply to a set of resources,resources, aa setset of of tasks,tasks, oror thethe projectproject

    asas aa wholewhole.

    • Standard Working time is set to Monday through Friday, 8:00 A.M. until 5:00 P.M.,

    with an hour off for lunch from noon until 1:00 P.M. each day. ThisThis isis thethe default default 

    basebase calendar calendar used used for  for thethe project, project, for  for tasks,tasks, and and for  for resourcesresources..• Night Shift Working time is set to an 11:00 P.M. until 8:00 A.M. night shift, five

    days a week, with an hour off for lunch from 3:00 A.M. until 4:00 A.M. each

    morning.

    • 24 Hours Working time is set to midnight until midnight seven days a week; that is,work never stops. This base calendar is typically used for projects in a manufacturing

    situation.

    • Customs (next topic)

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    50/128

     MODIFYING A CALENDAR

    1:40 AM 50

    Click Tools, Change WorkingTime.

    Dialog box will open with the

    name “Change Working Time”

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    51/128

     MODIFYING A CALENDAR (CONT’D)

    1:40 AM 51

    Click on “crate New Calendar” tab

    and rename your project calendar In the For box, click the name of  

    the base calendar you want to

    modify

    To change the working time of a

    single day, click that day.

    In the Exceptions field, write the

    holiday. AutomaticallyAutomatically thethe selectedselected

    dayday willwill bebe setset asas nonnon workingworking timetime

    Example: Select January 20 and write

    “Ethiopian Epiphany” at the Exceptions

    Field. Do to the same for 13 nation

    holyday

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    52/128

     MODIFYING A CALENDAR (CONT’D)

    1:40 AM 52

    To change the working time of a

    particular day of each week,Select the workweeks field.

    For example, to change the

    working time of Saturday, Select

    Details button. Select the day (example Saturday)

    and Mark the “Set day(s) to these

    specific working time”

    then change the times in the From

    and To boxes as needed.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    53/128

     MODIFYING A CALENDAR (CONT’D)

    1:40 AM 53

    To add or change the working time of a

    day in another month. In the Change Working Time dialog

    box, select the calendar from the

    “For calendar” drop-down list, and

    then click the Exceptions tab.

    TheThe ExceptionsExceptions tabtab appearsappears..

    Enter the name, start date, and finish

    date as you would for a regular

    exception.

    Recurring exceptions tend to span

    longer periods of time than

    exceptions for holidays or training

    classes.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    54/128

    Working with Ms-project views

    •  It vital of ms-project 

    • We use frequently now and then

    • Its adjustable

    • Have five main views

    • Calendar view

    • Gantt Chart

    • Network Diagram

    • Task Usage

    • Tracking Gantt Chart

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    55/128

    Working with Ms-project views

    • Calendar view

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    56/128

    Calendar View

    • Keeps tabs on whentasks occur.

    • Quickly see how long

    tasks take, when theystart and finish, and

    how they occur in

    relation to other tasks.

    • To view, click the

    Calendar icon

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    57/128

    Working with Ms-project views

    • Gantt Chart

    • Very common view of Ms-Project

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    58/128

    Working with Ms-project views

    • Network Diagram

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    59/128

    Working with Ms-project views

    • Task Usage

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    60/128

    Task Usage View

    • Work with task andresource information

    side by side.

    • Easily create usefulreports about when a

    resource is scheduled

    to work on a task.

    • To view, click the

    Task Usage icon

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    61/128

    Working with Ms-project views

    • Tracking Gantt Chart

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    62/128

     Resource Graph View

    • See whether resourcesare over allocated,

    what capacity they're

    working at, and how

    much they cost in a

    timescale graph

    • To view, click the

     Resource Graph icon

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    63/128

     More Views

    •  Resource Sheet View– Easy way to review, add, edit data about

    resources

    •  Resource Usage View

    – Work with resource and task information side

    by side

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    64/128

    Working with ==>>Tools ==>>Option

    View tab; Point to

    focus

    •Default view•Calendar type•Date format•Currency symbol

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    65/128

    Changing Date formats

    •It is possible to change date formats by clicking:•Tools => Option => View

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    66/128

    Working with ==>>Tools ==>>Option

    General Tab;

    •User name

    •Rate /hr or /day

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    67/128

    Working with ==>>Tools ==>>Option

    Edit Tab;

    •View option

    •Minutes, Hrs, day..

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    68/128

    Working with ==>>Tools ==>>Option

    Calendar Tab;

    •Week/yr stats on

    •Working hr/day …

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    69/128

    69

    Constraints

    Definition and Types of ConstraintsEight types of constraints available in Ms Project. By default all tasks are assigned As Soon

    As Possible constraint.

    •  As Soon As Possible (ASAP) Starts the as soon as possiblebased on links to other tasks. allow schedule changes tostart tasks earlier or later .– Used for Starting a task as soon as possible with predecessor

    tasks, if any, allow. Do not enter a date with this constraint ..

    •  As Late As Possible (ALAP) Starts the as late as possiblebased on links to other tasks. allow schedule changes to

    start tasks earlier or later.– Used for Starting a task as late as possible with out delaying the

     project end date or the finish date of a successor task .do no entera date with this constraint.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    70/128

    70

    •  Finish No Earlier Than (FNET) Finishes thetask on or after the day you enter. allowsschedule changes to start tasks later .

    – Used for Tasks that perhaps can but shouldn’t finishbefore a specific date. Ms Project automatically

    assigns this constraint when you enter a task finishdate.

    • Start No Earlier Than (SNET) Starts the taskon or after the day you enter. allows schedule

    changes to start tasks later.– Used for Tasks that must start on or after a specific

    date. Ms Project automatically assigns this constraintwhen you enter a task start date.

    Constraints cnt’d 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    71/128

    71

    •  Finish No Later Than (FNLT) Finishes thetask on or before the day you enter. Allowsschedule changes to move the finish date up to.But not later than the specified start date.

    – Used for Tasks that must finish by a specific date• Start No Later Than (SNLT) Starts the task on

    or before the day you enter. Allows schedule

    changes to move the finish date up to. But notlater than the specified start date.

    – Used for tasks that must start by a specific date.

    Constraints cnt’d 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    72/128

    72

    Constraints cnt’d 

    •  Must Finish On (MFO) Finishes the taskon a specific date. schedule changes don’taffect the finish date.

    – Used for Tasks that must finish on a specificdate.

    •  Must Start On (MSO) Starts the task on aspecific date. schedule changes don’t affectthe start date.

    – Used for Tasks that must start on a specific date

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    73/128

     Entering Tasks and Durations

    • Tasks are entered in the “Task Name”column

    • Subtasks are created by indenting a task.

    • Durations may be entered in number of

    working days or start and finish dates may

    be used

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    74/128

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    75/128

     Entering Tasks and Durations

    Inking Duration with Excel• Copy duration column from excel and “past

    special” in ms-project duration column

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    76/128

    • Recurring tasks like weekly meeting• Click on Insert (main menu) recurring

    task

     Entering Tasks and Durations

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    77/128

    Standard Markers

    • Normal Task 

    – designates ordinary task duration

    • Summary Bar

    – designates the duration of a group of sub-tasks

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    78/128

    Special Markers

    • Milestones– A reference point marking a major event in a

    project and used to monitor the project's

    progress– To create a milestone, Enter “0” in the duration

    field

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    79/128

    Changing Marker Styles

    • Double-click on the Marker you want to change

    and format accordingly or from main menu

    forma=> Bar style (for the project)

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    80/128

     Assigning Resources

    • A resource can be a single person, anequipment, or it can represent a group, such

    as Plumbers

    • Information on resources includeAvailability, Costs, and Working Time

    • Resources are very important in accurate

    scheduling

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    81/128

    • Copy all list of resources and past @ resource sheet

    • View => Resource Sheet

     Assigning Resources

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    82/128

     Assigning Resources

    • Enter pertinent information and click OK.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    83/128

     Assigning Resources

    • To Assign a Resource:

    – Select the task to which you want to assign the resource

    – Click the Assign Resources button on the toolbar Or from

    tools main menu bar “Assign Resource” or select task

    and Alt+F10

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    84/128

     Assigning Resources

    • If resources are not already set up, doubleclick on the name box

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    85/128

     Entering Cost (BOQ)

    • We need this when we do planning forcontractor side (or not earned value) after

    award of contract. In this scenario even if

    we assign project resource we have to satevalue as zero, and to follow our financial as

    of our BOQ.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    86/128

    • Setting View for cost

     Entering Cost (BOQ)

    • The copy your data on excel and

    pate here the amount should be

    at “fixed price”

    C l

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    87/128

    Crating Financial Report view

    • Again we need this when we do planningfor contractor .

    • We need to have financial report view left

    side actives on right side monthly cashflow.

    C i Fi i l R i

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    88/128

    Crating Financial Report view

    • Click on view• More views

    • Select task usage

    • Click copy

    • Rename as cash flow

    • Select table; cost• Click ok 

    C i Fi i l R i

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    89/128

    Crating Financial Report view

    C i Fi i l R i

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    90/128

    Crating Financial Report view

    You will have normal cash flow view (BOQ) or duration

    on the left and monthly executed/planned monetary

    value on right side

    Li ki T k

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    91/128

     Linking Tasks

    • Some tasks require that another task becompleted before it can begin. These tasks

    must be linked.

    • Tasks and subtasks are linked by assigningPredecessors.

    Li ki T k

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    92/128

     Linking Tasks

    • Predecessor– A task that must start or finish before anothertask can start or finish

    • Successor– A task that cannot start or finish until another

    task starts or finishes

    – A task becomes a successor when a rownumber is entered in the predecessor column

    Li ki T k

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    93/128

     Linking Tasks

    There are four types of relationships between tasks:

    Finish-to-Start; The default link between tasks and what you

    get when you press the Link Tasks button on the Standard

    toolbar. This is sometimes called a “stair step” or “waterfall”plan when tasks are linked using this relationship type. Tasks

    happen in serial fashion, one after the other. Task 1 finishes and

    then Task 2 begins.

    Li ki T k

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    94/128

     Linking Tasks

    Start-to-Start; Tasks begin at the same time. Tasks are

    linked in a parallel fashion, happening at the sametime. Task 1 and Task 2 begin at the same time.

    Microsoft Project 2007 Level 1Creating Project Tasks

    Linking Tasks

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    95/128

     Linking Tasks

    Finish-to-Finish; Tasks end at the same time. Again

    tasks are parallel, happening at the same time. Task 1

    and Task 2 finish at the same time.

    Linking Tasks

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    96/128

     Linking Tasks

    Start-to-Finish; Tasks are not listed in chronological

    order, or tasks from one category of your project plan

    affect tasks in another category. Tasks are happening in

    a serial fashion; Task 1 starts after Task 2 finishes.

    Linking Tasks

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    97/128

     Linking Tasks

    Adding Lags; in any of previous links you can also

    add lag .

    Linking Tasks

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    98/128

     Linking Tasks

    Fine Tune the Plan

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    99/128

    Fine Tune the Plan

    • When all resources have been assigned and

    appropriate tasks are linked, the original

    Gantt chart will be complete

    • Check to make sure tasks have been linkedcorrectly and task durations are correct

    • The project is now ready to begin

    Set a Baseline

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    100/128

    Set a Baseline

    • A baseline compares your original plan for

    the project with the actual course of the

    project.

    • You can see which tasks started earlier orlater than planned, exceeded their original

    budget, took longer than planned, and so on.

    Set a Baseline

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    101/128

    Set a Baseline

    • Create a baseline after you've polished it

    and just before you actually start work on

    the project

    • To track costs, be sure to enter costinformation before you create the baseline

    • Updates can easily be made to the baseline

    if information is missing

    Set a Baseline

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    102/128

    Set a Baseline

    • The Baseline plan includes:

    – Tasks (start and finish dates, duration, work,

    cost, splits, time phased work, and time phased

    cost)

    – Resources (work, cost, time phased work, and

    time phased cost)

    – Assignments (start and finish dates, work, cost,time phased work, and time phased cost)

    Set a Baseline

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    103/128

    Set a Baseline

    • To set a baseline:

    – Point to Tracking on the Tools menu

    – Click Save Baseline

    Entering Progress

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    104/128

     Entering Progress

    • Update actual start and finish dates for a task.

    – On the Tools menu, point to Tracking and then click

    Update Task 

    – Under Actual, type Start and Finish dates

    Entering Progress

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    105/128

     Entering Progress

    • Update progress on a task 

    – Double-click on the task to be updated

    – Enter a percentage

    – On the Gantt chart, a progress bar appears in the task

    bar

    Tracking Gantt Chart

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    106/128

    Tracking Gantt Chart 

    • Tracks the progress of the project

    • Shows what tasks are overdue and what has

    been completed on time

    • Click on the view Tracking Gantt (as wediscussed in previous PPT)

    Tracking Gantt Chart 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    107/128

    Tracking Progress

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    108/128

    Tracking Progress

    • Determining if tasks are starting and

    finishing according to plan:

    – In the Tracking Gantt, point to Table (View

    menu) and click Variance– Drag the Divider bar to the right to view

    variance.

    – Variance is shown in Days

    Tracking Progress

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    109/128

    Tracking Progress

    • Determine if tasks cost more or less than

    budgeted

    – In the Tracking Gantt, point to Table (View

    menu) and click Cost – Drag the Divider bar to the right to view Total

    Cost and Baseline fields

    PERT Chart 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    110/128

    C

    • You have many ways to gather information to

    estimate durations. However, most of these methodsdon't enable you the flexibility of analyzing best-case

    and worst-case scenarios. A Program, Evaluation, and

    Review Technique (PERT) analysis• (PERT analysis: PERT [Program, Evaluation, and

    Review Technique] analysis is a process by which you

    evaluate a probable outcome based on three scenarios:best-case, expected-case, and worst-case.) gives you

    this flexibility

    PERT Chart 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    111/128

    • Shows a flowchart of

    the project.

    • Each box represents a

    task in the project.

    • Connecting arrows

    show dependencies

    between tasks.

    • To view, click the

    PERT chart icon

    PERT in MS-project 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    112/128

    p j

    1 2 3 4 5 6 7

    PERT in MS-project

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    113/128

    p j

    • 1. Optimistic Gantt

    • 2. Expected Gantt

    • 3. Pessimistic Gantt

    • 4. Calculate PERT

    • 5. PERT Entry form

    • 6. PERT weight• 7. PERT Entry sheet

    PERT in MS-project 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    114/128

    p j• Start with no. 7

    • Click (PERT Entry sheet)• Feed optimistic duration, Expected Duration and

    Pessimistic Duration.

    • And click no. 4 (calculate PERT) to find duration.

    PERT in MS-project 

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    115/128

    p j

    • No.6 (PERT weight) use to adjust weight of

    each duration (1:4:1) to any other special

    condition for the common left default.

    • No 5 (PERT Entry form) to input data foreach activity one by one.

    • The others (no. 1,2 and 3) click on them to

    view the graph.

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    116/128

    j p p

    • Overview

    • Current Activates

    • Costs

    • Assignments

    • Work load

    • Custom

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    117/128

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    118/128

    • To edit click on “Edit” and work with font

    formatting for project summary and Milestone.But for others different

    dialog box will appear

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    119/128

    • Current Activity Reports; incorporates reportsrelated to tasks;

    • Unstated task 

    • Tasks Starting soon

    • Tasks in Progress

    • Completed tasks

    • Should have stared tasks

    • Slopping tasks

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    120/128

    • Cost Report• Cash Flow

    • Budget• Overbudget Tasks

    • Overbudget Resources

    • Earned Value

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    121/128

    • Assignment Reports; to find reports in

    relation to resources

    • Who Does what

    • Who does what when• To-do-List

    • Overallocated Resources

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    122/128

    • Work Loads;

    – Task Usage and

    – Resource Usage

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    123/128

    • Work Loads; to customize and to create

    your own report– Can edit from exiting reports.

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    124/128

    • Export Reports to Excel (you have to have

    knowledge of Excel pivot table)

    • Click Report => Visual Reports

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    125/128

    • Cont..

    • Visual Report

    – Dialog box

    – Select one– Click on view

     Ms-Project Reports/Out puts

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    126/128

    The Project is Now Complete !!

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    127/128

    • MS Project is a very powerful tool if it is

    used correctly

    • This program can save a lot of time for

    engineers who are interested in time, cost,etc.

    • Automatically keeps your project organized.

  • 8/19/2019 Ms-project Training Jekale Cmc by Abinet

    128/128

    Thank you !!

    visitwww.constructionproxy.comwww.constructionproxy.com

    for more short and clear softwaremanuals