Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
MS4 Permit Compliance, CIP
Development & Stormwater
Utilities as a Funding Mechanism
Presenters
Jaurice A. Schwartz, PE
Project Manager, Weston & Sampson
David M. Elmer, PE
Vice President, Weston & Sampson
Presentation Overview
• MS4 Permit Background
• MS4 Permit Requirements &
Cost Implications
• CIP Development
• Stormwater Funding
Mechanisms
What is an MS4?
Municipal Separate Storm Sewer System (MS4) All man-
made stormwater collection and conveyance infrastructure
owned by a municipality.
Drain Pipes
Drain Manholes
Catch basins
Outfalls
Culverts
Man-made Channels / Swales
Infiltration / Detention / Retention Basins
Treatment structures
MS4 Permit Background
• Phase 1 (1990) - Population > 100,000 – individual permits
• Phase 2 (1999) – Population < 100,000 in urbanized areas as defined by the Census Bureau – general permits
• MA/NH - EPA retains primacy
• Other New England states delegated to administer their programs.
MS4 Permit Intent
Permittees must develop, implement &
enforce a SWMP to reduce the discharge of
pollutants from the MS4 to the maximum
extent practicable, to protect water quality,
and to satisfy the Clean Water Act.
Best Management Practices (BMPs)
Best Management Practice (BMPs) – methods used to minimize pollutants discharged with stormwater into waterbodies and/or the peak rate at which stormwater discharges
Non-StructuralStreet sweeping
CB cleaning
Public education
Good housekeeping
Low impact development
StructuralInfiltration basins
Particle separators
CB sumps / hoods
Rain gardens
Detention ponds
Who is Regulated in New England?
State
Traditional
MS4s
Connecticut 121
Maine 30
Massachusetts 260
New Hampshire 61
Rhode Island 34
Vermont 13
MS4 Permit Status
State
Effective Date for Current/
Pending Permits
Connecticut July 1, 2017
Maine July 1, 2013
Massachusetts July 1, 2017
New Hampshire July 1, 2018
Rhode Island Draft Permit Pending
Vermont December 5, 2012
2003 vs. New MS4 Permit
• Greater accountability
• More detailed, required BMPs
• More stringent, designated timeframes for BMP
implementation
• Documentation in writing
• Increased reporting
• Extensive watershed-based
requirements
• More requirements = More $$
Minimum Control Measures
• Public Education and Outreach
• Public Participation/Involvement
• Illicit Discharge Detection & Elimination
• Construction Site Runoff Control
• Post-Construction Stormwater
Management
• Pollution Prevention/Good
Housekeeping
Watershed Based Permit
RequirementsImpaired Water - A waterbody or section of a waterbody with regular violations of water quality standards
Total Maximum Daily Load (TMDL) – Pollutant reductions set based how much of a given pollutant a waterbody can assimilate and still meet water quality standards
• Watershed Based Permit Requirements– Additional Requirements for Impaired Waters with
& without approved TMDLs
� Phosphorus
� Nitrogen
� Bacteria
� Chloride
� Metals
� Solids
� Oil/Grease
Minimum Control Measures &
Requirements
Cost Implications for MS4
Communities
Primary Cost Variables
• Size of MS4
• Location of MS4
• Amount of Urbanized Area
• Prior Accomplishments
• Watershed Based
Requirements
• Available In-House Staff
• Available Resources
Notice of Intent & SWMP
• What’s Required?– File a NOI for Coverage
– Identify Best Management Practices for Compliance
– Provide Schedule for Implementation
– Document in SWMP & Update Continually
• Cost Implications– Primary Variable: Watershed-Based Requirements
– Estimated Costs: Up to $30,000
Public Education/Participation
• What’s Required?
– Educational Messages to Targeted Audiences
• Residents
• Businesses, Institutions & Commercial Facilities
• Developers (construction)
• Industrial Facilities
– Evaluate Message Effectiveness
• Cost Implications
– Primary variables:• Existing/Available Resources vs. Develop New
• Assistance from Volunteer Organizations
– Estimated costs: Up to $5,000 annually
Illicit Discharge Detection & Elimination
Illicit Discharge – pollutants that enter the drainage system through direct and indirect sources
Improperly connected sewer services / floor drains
Cross connections between the sewer and drain
SSOs flowing into CBs/DMHs
Illegal dumping
Outside washing
Leaky dumpsters
Exfiltrating sewers
Failing septic systems
Contaminated soils or groundwater
Illicit Discharge Detection & Elimination
• What’s Required?– Written IDDE Plan
– Map the MS4 (Up to $250,000)
– Delineate/Rank/Prioritize MS4
Catchments for IDDE Potential
– Dry and Wet Weather Screening & Sampling
($100,000+)
– IDDE Field Investigations (Up to $ 1 million)
– Removal of Illicits (Budget $25,000 to
$50,000/yr.)
• Cost Variables:– MS4 Size/# of Outfalls/# of Illicits Identified
Construction Site Runoff Control (CSRC)
• What’s Required?
– Written Site Inspection/Enforcement Procedures
– Updated Construction Site Runoff Control
Ordinance
• Sediment and Erosion Control Program
• Control Wastes
– Written Site Plan Review Procedures
• Cost Implications:
– Combine with PCSWM
Post-Construction
Stormwater Management (PCSWM)
• What’s Required?
– Amend Existing Post-Construction Runoff Control
Ordinance
• MA Stormwater Management Standards
• Add procedures to minimize water quality impacts
• Require submission of as-builts
• Long-term O&M of stormwater management practices
– Assess Low Impact Design/Green Practices
– Identify Sites for BMP Retrofits
CSRC & PCSWM
Updates
• Cost Implications (CSRC & PCSWM)
– Extent of Existing Mechanisms
– Desire for New/Separate Mechanisms
– Legal Advice
– Up to $50,000
Pollution Prevention/
Good Housekeeping
• What’s Required?– Written O&M Procedures for
Municipal Activities
– Inventory of Municipal Facilities
– Optimize Catch Basin Cleaning
– Street and Lot Sweeping
– Develop/Implement SWPPPs
– Employee Training
• Cost Variables:– MS4 Size/# of Facilities/# of CBs
Watershed Based Requirements
• What’s Required?– TMDL/Impaired Waters
• Phosphorus– Phosphorus Control Plan
– Implement BMPs to Meet TMDL Wasteload Allocations & Percent Reductions
• Nitrogen– Identification of Nitrogen sources
– Implement Nitrogen reduction BMPs
• Bacteria/Chloride/Metals/Solids/Oil & Grease
• Cost Variables:– Dependent on Impairment &
Watershed Area
Summary of Estimated MS4
Compliance Costs*
Permit
Year
Estimated Cost
(Low End)
Estimated Cost
(High End)
Year 1 $150,000 $250,000
Year 2 $200,000 $600,000
Year 3 $150,000 $400,000
Year 4 $175,000 $425,000
Year 5 $200,000 $400,000
Years 6-10 (IDDE/Watershed
Based Requirements)
$100,000 annually $1 million+ annually
Years 10-20 (Watershed Based
Permit Requirements)
$1 million+ annually
* Estimates based on compliance costs developed for selected communities within MA & NH.
Big Picture Focus
MS4 Permit is the Driver
What about other Municipal
Stormwater Needs?
� Existing Capital Improvement
Plans for Water & Sewer Systems
– None for Stormwater
� Develop a Stormwater Infrastructure Improvement Plan to efficiently invest City resources
Capital Improvement Planning
CIP
Sewer
Water
Stormwater
• Existing CIPs for
Water & Sewer
Systems but what
about Stormwater?
• Develop a
Stormwater CIP to
efficiently invest
resources
• Comply with the MS4 Permit
• Reduce Localized Flooding
• Identify & Rehabilitate Failing
Drainage Infrastructure
• Predictive Maintenance
CIP Goals
Stormwater CIP Development
PlanPlan
Prioritization
Costs
Prioritization
Costs
Needs Assessment
Field Reconnaissance
Historical Data
Steering Committee
Needs Assessment
Field Reconnaissance
Historical Data
Steering Committee
Stormwater CIP
Components • MS4 Compliance
• Localized Flooding
• Stream Maintenance
• Culverts & Critical
Infrastructure
• Assessment for O&M
Needs
Project Prioritization
• Risk Based Approach
• Condition Assessment
• Consequence of Failure
• Risk Rating
Project Prioritization
Category of Consequence % of Weight
Public Health & Safety 22%
Property Damage 22%
Cost of Deferred Maintenance 20%
No. of People Impacted 13.5%
Traffic Impacts 13.5%
City Development Priorities 9%
Total 100.0%
Risk Rating
• Risk = Probability of Failure x
Consequence of Failure
• Risk Rating Calculated for each
Project
• Prioritized Stream Maintenance,
Localized Flooding & Culvert
Projects numerically based on
Risk Rating
• MS4 Compliance Work Federally
Mandated
High/LowHighest Priority
Lowest Priority
Low/High
Consequence of Failure
Pro
ba
bili
ty
of
Failu
re
Stormwater System – Newton, MA
• 320 miles of drain pipe
• 12,750 catch basins
• 2 Pump stations
• 183 exterior
outfalls/interconnections
• 201 interior outfalls
• 14 miles of streams
• Stormwater fee established in
2006 to partially fund stormwater
costs
Stormwater CIP
Newton, MA
• 20-Year Plan
• Annual Cost Ranges from
$1.35 to $2.94 million
• Total CIP Cost Estimated at $41 million
� MS4 Compliance - $11.3 million
� Localized Flooding - $3.0 million
� Stream Maintenance - $11.2 million
� Culverts - $15.7 million
Seek Funding
Stormwater Funding Mechanisms:
So How Do We Pay For All This?
Stormwater Management
Funding Sources• Operational Funds:
� Taxes
� Fees / User Charges
• Capital Funds:
� Taxes
� Betterments / Special Assessments
� Fees / User Charges
� Grants / Loans
� District Financing (e.g. DIF, TIF)
Stormwater Funding Assistance
• Transportation Funding Programs
– Chapter 90 funds, TIP, TEG, TIGER
• Water Quality Grants (Section 319/604b)
• Community Development Grants
(CDBG/CDAG)
• State Revolving Fund (SRF)
• Rural Development Funding (Grant/Loan)
• Hazard Mitigation / FEMA Grants
Stormwater Utilities
What is a Stormwater Utility (SWU)?
“A Stormwater Utility, operating much like an
electric or water utility, may collect fees
related to the control and treatment of
stormwater that can be used to fund a
municipal stormwater management program.”
- U.S. EPA, Funding Stormwater Programs, April 2009
Stormwater Utilities
Legal Basis for SWU:
• All New England states have provided
authority for the creation of stormwater
utilities.
• In Massachusetts, M.G.L. Chapter 83,
Section 1 (amended 2006) addresses
establishment of stormwater utility programs.
Stormwater Utilities
Forms of SWU:
• Stormwater Fee Programs
– Often Revenue Generation Only
• Revenues Dedicated to SW Management
– Separate Use of Funds for SW Management
• True Enterprise Funded SWU
– Separate Accounting
– All funds for SW Management from SWU Fees
• Separate Utility Entity
– Your local Stormwater Company
Stormwater Utilities
SWU Fee Systems:
• Commonly an Area Based Method
– Calculate Impervious Area
– Establish a Common Unit: An Equivalent Residential Unit (ERU) is the amount of impervious area on a typical single family residential parcel.
– Flat Fees or Variable Fees Based on ERU increments • Small, Medium or Large Residential
• Commercial/Industrial Scale
• Rates Based on Actual Costs
for SW Management
Stormwater Fees in MA
MunicipalityResidential Fee
Structure
“Non-Residential”
Fee Structure
Chicopee Single Family Homes
$100/yr.
Up to $160/yr.
Fall River $140/yr.
$140/yr for every
2,800 SF of IA
Milton4 Residential Tiers
Range from $28 to $156/yr. $1.56 x 100 SF of IA
Newton Residential (1 to 4 Family Dwellings)
$75/yr.
Tiered System based on IA
$250 - $5,000/yr.
NorthamptonResidential (1 to 3 Family Dwellings)
4 Tiers - $63.94 to$259.07/yr. Based on IA
Reading 1 or 2-Family - $40/yr.
$40/yr. for every
3,210 SF of IA
Westfield $20/yr.
$0.045 per SF of IA
Min. Fee = $100/yr.
Max. Fee = $640/yr.
Stormwater Funding
Where to Start
• Understand your local costs for stormwater management – start tracking.
• Learn more about options (e.g. SWU training).
• Engage people - establish interdepartmental support and use public forums.
• Municipal/Agency Budget –Identify costs in your budget and discuss with Town Meeting/City Council.
QUESTIONS?
Contact Us:
Weston & Sampson(978) 532-1900
www.westonandsampson.com
David E. Elmer, P.E.
Jaurice A. Schwartz, P.E.
thank youwestonandsampson.com