MSP Document 2013

Embed Size (px)

Citation preview

  • 8/13/2019 MSP Document 2013

    1/33

    Livelihood Support and Promotion of Community Infrastructure Project (LACI-P)

    Integrated Development Planning at Village and Union Level

    Embarking on practical methodology

    Dr. Arjumand Nizami

    Mehmood Hemani

    Roshan Ara

    Nadeem Bukhari

    Islamabad

    2013

  • 8/13/2019 MSP Document 2013

    2/33

    2

    Final draft June 5th

    , 2013

  • 8/13/2019 MSP Document 2013

    3/33

    3

    Acknowledgement

    PPAF is Pakistans leading organization in terms of taking innovative initiatives

    for poverty reduction. This organization is highly committed to propel a large

    scale impact from its work in the field and a consistent emphasis on MSP is

    one step in achieving this direction.

    The consultants team is highly grateful to Qazi Azmat Isa, the CEO of PPAF in

    providing a conceptual outline on MSP and encouraging a process that is built on

    earlier knowledge and experiences. Mr. Masood Khalid and his team have been

    instrumental in extending all the cooperation and guidance in this process. We

    also thank Mr. Nasurullah and Mr. Taimur Jahangir and several other colleagues

    (who also attended the kick-off workshop on 17th

    of April at PPAF) for theirpunctual support in providing relevant material for our work. We thank Herman

    Mulder from Intercooperationfor peer reading this document and providing his

    valuable comments. Thanks are also due to our LACIP colleagues Rana Sarwar,

    Hayatullah and Mubashar for their day to day help during the mission and

    finalization of this report.

    We sincerely hope that this document will provide a useful framework for piloting

    MSP in PPAF project areas and will generate learning for further improvement

    into the process for the future.

    The MSP Methodology Team,Islamabad, April 2013

  • 8/13/2019 MSP Document 2013

    4/33

    4

    Table of Contents

    Chapter 01 ............................................................................................................................................................................................................................................ 6

    Introduction and background of this report ........................................................................... ............................................................................... .............................. 6

    Chapter 02 ............................................................................................................................................................................................................................................. 8

    The Concept of Multi-Sector Planning (MSP) ......................................................................... ............................................................................... .............................. 8

    Chapter 03 ........................................................................................................................................................................................................................................... 10

    The process and steps to conduct MSP ................................................................................................................................................................................................. 10

    Chapter 04 ........................................................................................................................................................................................................................................... 20

    Piloting in the fieldproposed outline ................................................................................................................................................................................................. 20

    Annex 1-7 ........................................................................................................................................................................................................................................23-32

  • 8/13/2019 MSP Document 2013

    5/33

    5

    Acronyms

    ADP Annual Development Plan (Government) LSO Local Support Organization

    AHO Asian Humanitarian Organisation MER Monitoring, Evaluation and Research

    AKRSP Aga Khan Rural Support Programme MDP Members Development Plan

    APO Associate Partner Organization MIP Members Investment Plan

    CIG Common Interest Groups MSP Multi-sector Plan

    CPI Community Physical Infrastructure NRSP National Rural Support Programme

    CO Community Organization OPM Operational Planning Manual

    CMST Community Management Skill Training PO Partner Organization

    DDF District Development Forum PPAF Pakistan Poverty Alleviation Fund

    DRR Disaster Risk Reduction PSC Poverty Score CardFFO Farmers Friend Organization SDP Settlement Development Plan

    GBIs Grant-Based Intervention SO Social Organizer

    HH Household TNA Training Needs Assessment

    KP Khyber Pukhtunkhwa UC Union Council

    LACIP Livelihood And Community based Infrastructure support Programme UCDO Union Council based Development Organization

    LEP Livelihood Enhancement and Protection UCDP Union Council Development Plan

    LIP Livelihood investment Plan VDP Village Development Plan

    LMST Leadership and Management Skill Training VO Village Organization

  • 8/13/2019 MSP Document 2013

    6/33

    6

    Chapter 1

    Introduction and background of this report

    PPAF as an organization believes in holistic approach in poverty alleviation and

    therefore is striving for integrated development through building strong

    institutions in the field. For PPAF, institutional strengthening in the field is the key

    to ensuring sustainability of development effects in poverty stricken areas.

    Therefore an idea of establishing community / village organizations for delivering

    development services does not stop there it needs to be further accompanied

    to achieve a wider understanding on development vision within a community for

    inclusive development and a living plan identifying how to achieve this

    development beyond interventions that are limited at individual household and

    neighborhood levels. MSP is an idea in this direction encompassing village and

    Union Council levels, taking multiple sectors into account, and ensuring that the

    idea will be eventually supported by the measures provided in LG Act when

    implemented.

    A workshop was called by LACIP for further fine tuning the MSP concept and bring

    all the concerned at PPAF on one page. This one day workshop was organized at

    PPAF (workshop programme Annex 1). The entire day strived to achieve the

    following objectives and expected outcomes:

    Objectives:

    - Collectively identify why MSP is neededwhat it isand what will be the

    methodological steps to achieve this at a village or a UC level

    - Understand the roles expected of various tiers (village, UC) for themselves

    and towards other development actors

    Expected outcome:

    - An outline for partners orientation on the concept and methodologywill be

    available as a result of the workshop

    - Internal clarity among the team to move on in the field through partners

    - Identification of the next steps

    In total 28 Participants contributed to the workshop discussion in a highly

    interactive manner. With pleasure we report, that all the relevant units were

    present in the workshop which helped in taking the MSP agenda forward through

    multiple inputs from experts in several development themes1. A list of

    participants is attached in Annex 2.

    1.1Workshop on 17thApril 2013 on MSP

    Fine-tuning methodological steps and roles of different tiers in MSP

    In his opening remarks, the CEO of PPAF highlighted the following as food for

    thought for identifying methodological aspects of MSP:

    - Often such plans are plagued by lack of ownership how to make sure that

    the ownership from community, government, us and civil society is acquired

    - Reality keeps changing, how to keep the flexibility in the plan to adjust to

    changing reality

    - To ground realities confronting us today:

    o Insecurity in KP therefore conflict sensitive / resolution mechanisms

    must be added in the plans

    o Most of the partner districts are disaster prone therefore there is a need

    to ensure that DRR remains integrated in the plan

    - It is essential to consider social and ecological heterogeneity in the districts or

    below since one plan doesnt fit to all

    - Material for desk review must be identified for secondary data- Important to look at practical dimension, local culture and heritage are rich,

    how to ensure that local knowledge, and indigenous systems may be

    integrated in the plan

    Followed by this, a presentation was made by GM special issues / file holder of

    LACIP on how LACIP works and why MSP was seen as an important subject. The

    1Including institutional development, health, Benazir Income Support Programme,

    Livelihood, rural Credit, Education, Environment, infrastructure, DRR and so on

  • 8/13/2019 MSP Document 2013

    7/33

    7

    ingredients from his presentation have been included in the methodological

    chapters of this document (the presentation is attached as Annex 3).

    The day continued with several interactive sessions on what processes are

    already undertaken by PPAF team and partners to found MSP process. This report

    provides the essence of the discussion and elaborates the key ingredients of MSP

    process identified during the workshop with the help of the participants in later

    chapters.

    1.2Documents / background material available and reviewed

    In pursuit to prepare for the workshop and ensure that the methodological steps

    are built on earlier knowledge, the following material was consulted by thefacilitating team of Intercooperation. This helped in founding a base of MSP:

    1. An example of Village/ Settlement Development Plan (VDP/SDP), Farmers

    Friend Organization (FFO) Sargodha

    2. An example Village Development Plan: Mara Khurd, 4thJuly 2010

    3. Checklist for assessing the quality of Community Organizations, Human and

    Institutional Development Unit, PPAF

    4. District Census report DI Khan, Chitral and Haripur

    5. Draft Strategy Livelihood Enhancement & Protection Unit (August 30th

    , 2012)

    6. Integrated Development Visions (2008) DI Khan and Chitral, IUCN Pakistan

    7. List of LACIPs partner Districts, project locations and Partner O rgnizations

    8. Livelihood Investment Plan (LIP) PPAFPart 1

    9. Local Government Act 2012, KP

    10.Member Development Plan format, PPAF

    11.MSP Approaches (KFW), proceedings of workshop (6thMay 2012)

    12.Multi-sectoral Planning LACIP. Mission report Martin Dietz (23rd

    January4th

    February 2013), Helvetas Swiss Intercooperation

    13.Operational Polices Manual for Grant-Based Intervention (GBIs), PPAF

    14.Poverty Score Card, PPAF

    15.Situation Analysis form, PPAF

    16.Village Development Planning Manual (2012), Intercooperation and Forests

    Department KP

    1.3Major challenge encountered while defining MSP process

    The facilitating team encountered the following challenges while elaborating the

    processand would like to remind the PPAF team that similar challenges may be

    faced by them in the field. It is therefore essential to remain aware of these while

    making MSP a reality on ground:

    1. MSP must capitalize on existing practices, experiences and tools that are

    being used by Partner Organizations and other development partners in the

    field. A process defining all the processes from scratch will never take off and

    will not yield results.

    2. There is a large range among Partner Organizations in terms of their capacityand history of working in a specific geographical region. The MSP process

    however was defined keeping in view a lower denominator in view, which

    means the organizations with lower capacity, little field experience and brief

    history of presence in a specific district.

    3. There was a varying understanding of the PPAFs internal processes, planning

    tools and their linkages within the team the MSP methodological exercise

    served an opportunity to clarify these elements within the team. A similar

    challenge may be encountered at the field level with POs. An orientation

    session for POs may be helpful at this stage.

    Two examples of processes were presented during the workshop for inspiration

    and discussion:

    1. Recommendations on MSP process from Martin Dietzs report (January

    2013): Annex 4

    2. Village Integrated Development Planning process introduced by KP Forests

    Department: summary Annex 5

    MSP process explained in this document includes the elements of both the

    examples.

  • 8/13/2019 MSP Document 2013

    8/33

    8

    Chapter 2

    The Concept of Multi-Sector Planning (MSP)

    2.1Why Multi-Sector Planning?

    This question is closely connected to the discussion on what PPAF as an

    organization is willing to achieve:

    The PPAF aims to promote a holistic approach to poverty alleviation, which is

    aligned closely with Pakistans commitment to the Millennium Development

    Goals. It emphasizes multi-sector programmes that generate broad and deepimpacts at the community level.(Operational Policies Manual for GBIs, 2011).

    PPAF is out in the field with its agenda for an inclusive development for poverty

    alleviation. It is aimed at supplementing development actors in their effort to

    enable communities in harnessing their potential for their self-development.

    PPAF is highly committed to strengthen community based organizations at

    various levels (including the ones visualized at apex level hopefully driving Union

    Council development along with other development actors at that level).

    MSP is a vehicle to effectively realize holistic development. So far, PPAF has been

    successful in realizing community based development through COs, organized

    within a village at a Mohalla or settlement level. However most of the

    interventions had impact for individual households, or a neighborhood or a village

    at the most. There is a need now to identify interventions at another scale that

    may have consequences for a larger population, such as a village or a group of

    villages or ideally a union council. This, however, is to be done without losingconnection with what is earlier done with the COs and individual households. The

    MSP therefore serves as an umbrella for a partner UC and strives to bring synergy

    among various development players, helps up-scaling PPAFs earlier experience,

    and inculcate a longer-term development vision at community level. MSP is a

    journey from a need based development to a potential based development

    leaving enough room for multiple actors in development to play their due role in

    the field.

    The overall Goalfor Multi-sector Planning was identified as follows2:

    Equitable and resilient socio-economic opportunities are identified and promoted

    while ensuring ownership of stakeholders

    Two objectives were identified for conducting MSP process:

    Communities develop an inclusive area development vision / road-map

    Institutions pro-actively mobilize resources for addressing socio-economicinterests and solidarity

    These two objectives promote the idea of inclusive, long term, proactive

    development however at the core of this are institutions, which own and

    carry development plans at certain levels and collectively mobilize resources for

    their realization. The MSP process has been perceived to realize this ambitious

    vision of multi-sectoral planning. The key here would lie in selection of the

    partners having base in the selected UCs incase capacities lack, a principal PO

    shall be charged with strengthening the local organization within stipulated time

    and handover the lead to them.

    2.2MSP initially as a process internal to PPAF

    It is highly encouraging that PPAF has started the process of multi-sectoral

    planning through first achieving an internal integration within the organization.

    Partner Organizations used to submit isolated proposals to PPAF for funding. Itwas often that these proposals maintained an independent relationship with

    various units within PPAF and did not relate to each other. Similarly, each unit

    approached potential Partner Organization rather independently for separate

    projects and did not synergize on these efforts neither administratively nor

    thematically. Now, with the restructuring within PPAF, the proposals are made in

    a manner that all the Units sit together to appraise them and award funding. This

    2Workshop 17

    thApril 2013, LACIP, PPAF

  • 8/13/2019 MSP Document 2013

    9/33

    9

    has helped achieving integration within PPAF and at NGO partner level. This will

    however not be complete till it is also achieved at the field level. E.g. various

    partners or non partner development actors strive to achieve a shared vision in

    development, and PPAF comes in as one of the contributors.

    2.3MSP for whom?

    It is essential to understand that MSP is not a panacea for achieving all

    development aims at the field level; it does however contribute to enhancing:

    - Acquiring a long term development vision

    - Efficient delivery of development services in collaboration with community

    - Inculcating a good reason to create / strengthen home-grown local

    institutions that carry the development forward- Ensuring interventions at all possible scales (household, neighborhood, village

    and union council) without duplication.

    It is therefore, MSP is for all the development actors involved in a district / UC

    such as:

    Who? What

    PPAF Inclusive development, larger impact, efficient delivery

    PO A good platform to attract other donors (than PPAF) to become

    part of development agenda not funded by PPAF

    Local

    Institutions

    HH, CO, VO and UCDO have development interventions in a longer

    term perspective; UCDO particularly have a tool to knock the door

    of relevant development actors rather than passively wait for

    someone to come for communitys aid

    Government

    actors at

    local level

    Government departments at UC / District levels will have a good

    base to collaborate with the UCDO and meet their annual targets

    possibly align their planning practices with MSP.

  • 8/13/2019 MSP Document 2013

    10/33

    10

    Dist

    DDFA

    CO +

    Chapter 3

    The process and steps to conduct MSP

    The MSP at Union Council is the end result of a regenerative process that begins

    from COs organized by POs of PPAF. It is important to understand that in this

    process, we not only achieve a well thought multi-sectoral VDP and MSP at UC

    levels but also the respective social organizations which own and contribute to

    the preparation and realization of these plans.

    1. Situation Analysis

    This step is crucial for correctly preparing the MSP process in the field. The

    situation analysis will be conducted at two levels in parallel:

    - District / UC level using secondary information as well as primary

    assessment on market / value chains

    - Village level in close collaboration with the villagers based on PPAFs

    exiting procedures.

    The following table provides the detail to conduct this step. In short it is

    summarized as follows:

    1. As a first step, try to collect all necessary documents which are already

    available and can provide secondary data regarding the district. The

    examples include:

    a. District census reports

    b. District gazetteers produced by British government

    c. Integrated development visions produced by IUCN or othersd. Any baselines / studies conducted by PO or other development

    organization in the district

    e. District plans / Annual Development Plans of various departments

    (P&D Department)

    2. The PO will engage an Associate Partner Organization already at this level

    and support them to conduct a broader consultation within the villages

    and identify key development issues.

    3. Further down in the process, the PO or APO conducts Poverty Score Card

    and wealth ranking, and based on data, identify potential clients for LIP at

    household level.

    4. It is important to use data (point 3) analyzed from PSC / wealth rankingfor conducting vulnerability context analysis of each socio-economic

    group since this will lead us to activities that have significance for the

    entire village or even at Union Council level, in case the vulnerability

    trend is maintained in several villages of the same UC.

  • 8/13/2019 MSP Document 2013

    11/33

    11

    Stage Level Steps (major actions) Instrument / Output Remarks / Notes Who CapacityChange

    required

    Situation

    Analysis

    District / UC1. Market / Value Chain Assessment

    UC level

    Market actors and potential for

    products / services (skills demand) in

    UC

    Ideally this is done at the time

    of UC / District selection.

    Subject

    matter

    specialist

    on value

    chain

    New

    Special TORs

    to do this

    and

    supervision

    District / UC

    2. Collect and go through secondary

    documents (census report,

    gazetteers, met data, ADPs, other

    documents etc.)

    A broader view of the UC extracted

    from the documents

    Try to analyze trend - what

    comes out as a key

    development challenge?

    UC / group of

    villages

    3. Identify and engage APOs

    (specialized) and capacity building

    Village /

    Mohallah

    4. Broader consultation / discussion

    with Mohalla / Village with wider set

    of stakeholders on development

    context of the village

    - Socio-economic and disaster

    vulnerability context (Situation

    Analysis Form) - including references

    with secondary data

    - Participatory Wealth Ranking

    (ill/well being analysis)

    - vulnerability assessment (e.g. SWOT)

    with each socio-economic category

    - mapping of major development

    actors at UC level

    Context built for activities that

    go beyond village boundaries

    (e.g. at UC level)

    PO (SO,

    MER)

    Conducting

    situation

    analysis in

    a holistic

    manner

    Budget for

    pre-

    interventions

    Village for

    each HH

    5. Interviews with HH - Poverty Profile through Poverty

    Score Card

    However the VDP process

    (next steps) move on based

    on ill/well being analysis. PSC

    is more for LIP / CIGsIndividual HH 6. Desk review of data- Identification of potential

    beneficiaries for LIP

    Existing processes - In case of large PO identifying APO

    - Conducting vi llage consultation

    - Poverty Score Card and Wealth Ranking

    - Identifying potential beneficiaries for LIP but conduct LIP and provide assets in the next step

    What is new - A strong emphasis on desk review of existing documents

    - Conducting Market / Value Chain assessment and link identified economic potentials with other identified interventions

    - Vulnerability assessment must be conducted within socio-economic categories

  • 8/13/2019 MSP Document 2013

    12/33

    12

    2. Social Mobilization

    Primary data collection and analysis results in situational analysis report which

    documents a detail profile of the area including its market / value chain

    potentials. Based on these analyses social organization of the village is initiated in

    order to carry out planning and interventions. An inclusive social mobilization is

    closely connected with a good quality situation analysis, particularly Poverty

    Score Card and wealth Ranking. At the moment two things happen at this step:

    - The formation of Community Organizations (COs) is conducted based on

    PPAFs existing procedures with due flexibility given to the Partner

    Organization to allow CO process as per their geographical vicinity,

    commonality of issues and their cultural bounds.

    - Based on economic potentials, Common Interest Groups (CIGs) are formed

    that mainly look into market based / value chain activities. CIGs are not

    essentially organized on the basis of geographical contiguity (e.g. Mohallah).

    Followed by CO / CIG formation, it is important to catalyze VO formation at village

    level. A VO is supposed to be an all inclusive body of the villagers where all COs

    are represented through their office bearers. There are three tiers of

    organizations that lead to MSP process at Union Council level. Community

    Organizations (COs), Village Organizations (VOs) and Union Council Development

    Organizations (e.g. LSOs). Moreover, other management committees for specific

    projects such as School Management Committees, operation and maintenance

    committees in case of infrastructure projects and Common Interest Group (CIGs)

    are also formed at operational level for the smooth running of the activities.

    The geographical jurisdiction of a CO is a Mohallah (settlement) of a village/town.

    COs in a large number already exist or had existed in most of the target villages,

    which will be utilized largely after some structural review and refining if needed.

    Where there are no existing COs, field teams of POs will facilitate the formation

    of COs ensuring a democratic process have been followed. After the registration

    of the COs, a joint bank account between COs and Partner Organizations (POs)

    will be opened in the local banks according to the PPAF guidelines.

    COs registration is mandatory for funds release by the POs for CIPs, LIPs and

    MDPs. Once the COs have been formed and/or notified, different trainings such

    as CMST, LMST, organizational record keeping and others will be carried out. A

    Training Need Assessment (TNA) will also be conducted with the COs to identify

    any other human & institutional development needs. It is necessary to identify all

    the members of COs as General Body of the village before the next step of Village

    Organization (VO) is undertaken.

    In the next step VO will be constituted by COs. Office Bearers (President, GeneralSecretary, and Treasurer) of the COs will become members of the VO and

    elect/select office bearers of VO among themselves. Constitution of VO is a pre-

    requisite for developing a Village Development Plan (VDP) which includes

    interventions of collective benefit. VDP process calls for participation of all

    stakeholders (both internal & external) of the village and encompasses broader

    population and long term activities. VO acts as custodian of VDP and ensures

    equitable distribution of benefits, transparency and self accountability. VO shall

    also formulate its Rules of Business during this phase.

    Stage 1: CO Formation and Registration

    (LIP, CIP, CIG at this stage)

    Stage 2: VO formation

    CO Members form a General Body while the

    office bearers form membership

    Joint Bank Account

    (VDP and CIP / DRR activities at this stage)

  • 8/13/2019 MSP Document 2013

    13/33

    13

    Eventually at a later stage a support organizations at UC level will emerge which

    will act as an advocacy group ensuring service delivery and community

    leadership. Such an organization will anchor, lead and uphold the Multi Sector

    Plan (MSP) process. It will serve as a platform for knowledge sharing, adoption,

    replication and integration of development activities in other parts of the UC.

    Stage Level Steps (major actions) Instrument / Output Remarks / Notes Who CapacityChange

    required

    Social

    Mobilization

    Mohalla: CO

    Village: VO7. Constitution of COs (CIG), VOs Registration, bank account, etc.

    Registration of CO required for

    funds release by POs (OpM)

    PO (SO)

    Fund

    transfer

    subject to

    registration8. Training of COs and VOs - Institutional Checklist

    Registration VO is mandatory

    to receive benefits of LG Act

    (as an umbrella of COs)

    - Organizational record keeping, CMST,

    LMST, etc.

    Existing processes - CO formation at Mohallah / settlement level

    - CIG establishment based on common interests

    - Registration of CO, administrative procedures such as opening of bank account

    What is new - VO formation at village level (with an intention to do Village Development Planning)

    - Essential for VO to have close links with CIG and CO as an umbrella organization of the village

    - Registration of VO and opening of bank account

    3. Village Development PlanningIn a number of consultative sessions, the VOs identify their key planning priorities

    which are aimed at the overall development of the village. It is important at this

    stage that they leave aside the individual household priorities which are already

    being taken care of by LIPs prepared with the support of COs. All other CIP

    activities and other village related development interventions need to be enlistedin this process. The expertise of Partner Organization in the consultative

    processes with the VO is expected to yield a plan that is not a wish list but a

    logical set of interventions that connects with the overall development vision for

    the village. The village Development Plan is multi-sectoral in nature and envisages

    contribution from multiple actors. Therefore MSP realization already starts at this

    stage, albeit only at village level (village based MSPs). Our observation is that as

    oppose to the current practice of conducting MIP/MDP preparation for the non-ultra-poor members in the community, their interests will be adequately address

    in CIGs.

    Stage Level Steps (major actions) Instrument / Output Remarks / Notes Who CapacityChange

    required

    Individual HH 9. Conduct LIP with ultra poor Use Poverty Score Card Results Immediate implementation PO/CO

  • 8/13/2019 MSP Document 2013

    14/33

    14

    VDP (xIPs)

    Village

    10. Village General body discussion on

    potential interventions for Mohalla /

    village.

    Overview / Holistic VDP (more than

    LACI-P/ PPAF mandate) - inform about

    market finding

    3-5 yrs vision

    1 year priority planCO / VO

    VO / CO / CIG

    11. Economic intervention planning

    with CIGs, prioritization of activities

    related to collective vulnerabilities

    MDP/Sectoral/sub-sectoral income

    enhancement plan (CIG), etc.Training

    of CIG members in related topics

    CO/ VO/

    POVO

    12.If VO already exists, look into

    restructuring of VO if needed

    All inclusive VO that represents CO

    interests

    VO / CO / CIG

    13. Social sector (CPI, soft elements)

    Intervention planning with COs and

    VO, prioritization

    VDP format to be developed VDP is owned by VO

    Existing processes - LIP is retained independent of VDP planning due to its nature to address immediate needs at HH level and upgrade ultra

    poor to contribute to social organization and planning processes- CIP projects conducted at CO level

    What is new - Village development planning that encompasses activities at CO and HH level and provides an umbrella for all the

    interventions including those that are beyond CO level

    - MIP dropped

    4. Resource MobilizationAs said in the preceding section, the VDP envisages a multi-actor support for the

    realization of interventions. This suggests that linkages and resource mobilization

    are crucial for the realization of the village plan. These resources (financial or

    non-financial) may be internally raised within the village or attracted from

    outside, but are deployed for achieving the plan over a period of time.It is

    important to note that the village plans in all the villages are prepared in a

    parallel process to save time and ensure connectivity in the activities. An example

    may be a DRR scheme in one village that may affect another downstream. A

    parallel process for VDP preparation will ensure that such mutual issues may be

    dealt with carefully through a dialogue.

    Stage Level Steps (major actions) Instrument / Output Remarks / Notes Who CapacityChange

    required

    Resource

    Mobilization

    Village14. Implementation of Village Plans- begin funding PPAF/LACI-P mandate

    Proposals by PO/APOCO / VO

    PO

    Village15. Establish relevant Scheme

    committees.Community groups CO/ PO

    Village /

    district

    16. Linkage Development (Networking

    - DDF, Dev. Partners, Line Dept.)

  • 8/13/2019 MSP Document 2013

    15/33

    15

    Existing processes - POs submit project proposals to PPAF for funding

    - In few cases, POs approach government line agencies to create service linkages with the COs

    What is new - A rather systematic identification of development actors at Village / UC level

    - Establishment of linkages with development actors and reflect into the plan document

    5. Networking / ClusteringOnce a number of village organizations have been established in the village and

    village development plans prepared by them, it is time to cluster VOs into a union

    council based organization. Only in few cases in which the Partner Organizations

    have taken the initiative to organize village member based Local Support

    Organizations at UC level. In most of the cases however there are no such

    umbrella organizations on ground. In a few cases there may be apex organizations

    for specific sectors such as Water Users Associations, Production or Market

    Associations, or Seed Growers Associations and so on. Such organizations must

    be included in the process as an entry point for forming such a cluster at UC level.

    Stage Level Steps (major actions) Instrument / Output Remarks / Notes Who CapacityChange

    required

    Networking /

    ClusteringVillage / UC

    17. Constitute LSO/UCDO (if does not

    exist)

    UC overview / oversight / advocacy

    groupRegistration

    Existing processes - In some cases, POs have established Local Support Organizations

    What is new - In several cases an apex / UC based development organization does not exist. The best is to make an apex of member

    villages and form one.

    - Ensure that existing LSO (which act more as an APO or NGO at the UC level) and the intended UCDO of villages whose

    development plan is in question do not have conflict of interest3

    3Mostly the existing LSOs offer themselves as project implementers and therefore a risk lies that an LSO has perceived a multi-sector project for donors funding that they

    themselves implement. An apex body of the villagers however perceives such a plan with a clear vision that it is the service that is important for them, and not from where it isfunded (e.g. a donor, government line agency, collective funding e.g. chanda, etc.)

  • 8/13/2019 MSP Document 2013

    16/33

    16

    6. MSP formation at UC levelWith the formation of a cluster organization, we are very close to identifying

    multi-sector priorities at UC level. These development priorities are funneled

    down from VDPsbut at the same time, take account of an overall development

    trend in the UC such as vulnerability to a specific disaster, drought, water scarcity

    or abundance, a specific agriculture product, etc. Like in case of VDP, UC multi-

    sectoral plan needs to take into account the overall vision for UC development in

    a longer term and must provide space for multi-actors in development to extend

    support.The UC level development organization is the custodian of this plan and

    needs to be trained to act as an advocacy body to pursue major targets given in

    the plan with relevant development actors.

    Stage Level Steps (major actions) Instrument / Output Remarks / Notes Who CapacityChange

    required

    UC (Multi-

    sectoral) Plan

    16. Collate key elements of VDPs in UC Ownership is with UCDO/LSO LSO17. Trend Analysis regardinghealth,

    education, disasters, conflicts, etc.LSO +

    expertUnion Council

    18. Augment Strategic elements -

    secondary data, mapping other

    initiatives, other players (L/Dep)

    Mapping other initiatives, other players

    (Line departments)

    19. Disseminate and follow-up MSP LSO

    Use / follow-

    up of UC Plan

    (MSP)

    21. Constitute District Development

    Forum (pilot in a few cases)LACI-P

    Union

    Council

    22. Collate UC Plans (MSP) at District

    Levels

    - Strategic Adjustments by PPAF /

    Projects / Line Depts.PPAF?

    23. Advocacy in DDF and with L/Dep.,

    other actors for inclusion of MSP/VDP

    elements in ADP

    LSOs

    Existing processes - Not at the moment

    What is new - Several VDPs at UC level and the overall trends found during situation analysis lead to a living MSP plan / priorities

    - Linkages with MSP, dissemination of document

    - Hopefully DDF (at least first one or two examples) will give impetus to MSP implementation

    - Local support organization of member villages take the plan implementation forward

  • 8/13/2019 MSP Document 2013

    17/33

    17

    Frequently Asked Questions

    Questions Deliberation / Answers / Potential Solutions

    How do you ensure consensus building? How

    to ensure that all possible social groups

    including deprived have a voice during

    consultationon development priorities

    reflected in the VDP?

    - A major entry point to achieve this is the CO formation. If CO is formed in an inclusive manner and participation of all

    the members has been ensured, there is a chance that they will respect each other.

    - VDP preparation does not entail a one-time consultation. Consultation can be conducted in smaller groups and where

    necessary, triangulation of priorities may be achieved though consulting with men and women, and in repeated

    sessions.

    - If consensus building is problematic, a Plan B must entail a consultation with only a relevant group.

    What is it in these steps that PPAF does not

    do?

    - The entire process up to the CO formation is already institutionalized by PPAF through partners agreements.

    - However at this stage, vulnerability assessment is not taken into accountas well as value chain / market assessment

    are not conducted- It is more about the depth of process and linking every activity to the next higher level at least up to the UC level.

    Is MSP need based or? The term need is self defying and is against the entire philosophy of PPAF as well as MSP concept. MSP must be based on

    existing potentials within the community and therefore is a mix of community aspirations and strategic elements that are

    identified based on development potentials.

    The idea is to work on causes of poverty and pull people out of poverty cycle rather than giving a temporary relief.

    How to ensure that the plans are built on

    long term development objectives?

    - Since the plans are aimed at harnessing community potential, there is a vision that guides the identification of

    interventions as oppose to an existing offer for a project / service / charity.

    - The social organization is the keycommunity institutions set and own the plan priorities and essential synergies for

    their relevant constituency (e.g. village or UC) and not an external expert.

    - However, the facilitating experts knowledge counts they are the one to guide communities in this process.

    Does this promote a specific model for

    replication in all the partner districts?

    - It is not a blue print for the districts to follow. It is however essential to provide an outline of the process that is sized

    according to the situation.

    - The process in this document give major building blocks essential to design MSP

    - The name multi-sectorsuggests that we are not stuck to a model with pre-defined sectorsbut are open to complex

    phenomenon of poverty and multiple options.

    Resource mobilization how shall we dothat?

    - It is essential to first look within the village and then within the union council. Make an inventory of actors available andthe services they can extend.

    - The next is to look into various development agencies (including NGOs, development projects and funding agencies as

    the PO may know)and pursue them

    - A factually correct mapping of actors (ideally done before a proposal is moved by a PO or at least at situation analysis

    stage)leads to proper follow up. While one member of the UC development organization feels comfortable engaging

    with the government line agencies, another may knock the door of a development project to present the plan priorities.

    - Once the plan is there and the organization is ready with its basic administrative settings (including training on LMST,

    etc.), it may be worthwhile to train them on how to prepare development proposals and manage to raise funds.

  • 8/13/2019 MSP Document 2013

    18/33

    18

    What is the core inspiration for MSP? MSP provides a longer term vision for development planning and interventions at certain level. For PPAF, MSP is an effective

    entry point to promote holistic development in pursuit to achieve Millennium Development Goals and eventually post MDG

    development agenda (Sustainable Development Goals)

    How much time it is going to take MSP - This is subject to the situationkey question: How much ground experience already exists?

    - Roughly 4-5 months with three parallel teams in a new district,where number of selected villages within a UC remain

    within 10 or below. This is a district where nothing exists on ground (including PSC, and organized CO)

    - In an existing district with existing COs and PSC data available, it may take about 4months (with about 10 VDPs, 1 UC

    plan) with three parallel teams.

    - It is important to keep in mind that this is the minimum investment before we have in our hand a long term,

    comprehensive development agenda to continue. During this process, LIP and some of the CIP activities at CO level will

    not stop.

    How much staff is required? - Each team comprises at least 1 female and 1 male SO. This intensity is needed for 6 months only till the MSP and VDPs

    are achieved.- In addition, during the MSP process, 1 office based support is needed for data analysis

    - 1 mentor / manager with multi-sector orientation is essential during this period to guide the process

    - One team who conducts rapid market / value chain appraisal in the beginning

    - It is essential to understand that the VDP and MSP preparation will be an intensive task spread over 6 months. Once the

    plans are there, try to shift most of the burden to the social organizations

    Who will own the plans? CO: LIP with ultra poor

    VO: VDP. It is however necessary that the UC administration recognizes this plan

    LSO / UC development organization: UC MSP. It is however necessary that this plan is also recognized by district authorities

    Funding level and funds flowsfrom PPAF now

    and late?

    - Currently the funds flow to registered COs for LIP and CIP

    - In case of VDPfor larger schemes the funds will flow to the registered VOs as well

    - In case PPAF is keen to also fund part of UC plan, the funds will flow to a registered union council based organization for

    a particular scheme

    Legal status of community organizations? All the three tiers of organizations are to be registered under the existing laws in Pakistan. They must put together their

    Rules of Business at relevant level (what will be the role of CO, VO and LSO and responsibilities / obligations towards each

    other in a downward accountability system).

    Who will conduct rapid market / value chainappraisal

    Needs to be carefully defined who will conduct this technical task (PO? A special team of PPAF or consultants engaged byPPAF or PO)

    What are major risks / concerns? Mitigation strategy?

    Concerns / Risks Mitigation Strategy

    At union council level, it is essential to have a Local Support

    Organization or a similar institution as an umbrella

    representative of the villages. However they do not exist

    In such cases initiate organizing such organizations, drawing strength and membership from Village

    Organizations

    Sector focused organizations (e.g. WUA on a watershed level) could also be an entry point to form

  • 8/13/2019 MSP Document 2013

    19/33

    19

    everywhere such an umbrella institution

    PO often donot encourage LSOs formation since they may fear

    being replaced by them

    Administrative strategy: Make POs contractually obliged and organize funds flow with a necessary

    frame condition

    Development strategy: It is essential for PO to help LSO in identifying its Rules of Business whereby

    an LSO and PO complement each other and do not overlap each other in their roles.

    POs have to acquire an understanding that their role must change in a longer run (see Annex 5, SRSP

    LSO concept).

    LSO may see LG bodies with fear after the implementation of

    LG Act 2012

    Perhaps initially but it is a misnomer; they need LG bodies for effective advocacy of MSP implementation

    When one PO is expected to facilitate for a number of VDPs

    within a UC say 10), there is a fear to Cut and Paste from one

    VDP document

    Active supervision by mentors, participatory monitoring, regular feedback meetings with teams will

    help understand that specificities among villages have been understood and addressed in the VDP

    process

    A review at UC MSP level will require that all the VDPs will also be reviewed to funnel key activities.The Cut and Paste dynamics will be caught at that stage

    PO: COs are mine: Stamped COs / VOs attitude confronting

    multi-actor support

    COs are owned by the people. The POs must understand how COs are embedded in the VO and not

    the PO organization set up

    It is imperative that multiple-actors may count on POs earlier presence and understanding on

    development issuesthe PO will be happy to attract them for support in the UCs where they

    function.

    Disbursement pressure vs quality of process what if

    compromises are made

    We insist that LIP and CIP activities limited to CO must continue during the process of MSP

    preparation.

    Even if done before VDP / UC MSP materialize, it is essential though to reflect CIP activities in the

    documents (past progress etc.). Once the MSPs (Village and UC) are final and priorities are set, field

    implementation at various scales (CO, VO, UC) has a potential to pace up dramatically.

    Security impediments It is essential to remain in close coordination with the district authorities and community influential.

    We assume that the POs are mostly from within the district and therefore are well connected to the

    information sources leading to asses risks for the teams (which is relatively less intensive for local

    staff due to their social acceptance).In case the POs come from outside, we consider it highly essential to engage local APOs at an early

    stage

    Monitoring of progress in the field by PPAF / LACIP may suffer due to security impediments; it may

    be worthwhile to engage consultants hailing from relevant districts to provide such services to the

    projects

  • 8/13/2019 MSP Document 2013

    20/33

    20

    Chapter 4

    Piloting in the fieldproposed outline

    Following the agreement on the major steps for developing the MSP, the

    participants, while discussing the next steps, suggested to pilot it in few places.

    Some of the criteria for choosing a UC/District put forth are:

    a) Strength/maturity of the POweak and strong/experienced partner

    b) Social capitalUC where CO/VO exists and new area to build from scratch

    c) Securitystable work conditions and less secure district

    No prior agreement was made on final number or locations for piloting, however,

    it was agreed in the workshop that LACIP-PMU shall do the piloting first and makerecommendations.

    Since LACIP is in its 2nd

    year of a 4-year phase/life (including one year extension)

    it is envisaged that coverage will further expand from current 36 UCs in 5 districts.

    The overall outreach is forecasted to reach to 60 UCs in KP through LACIP. At

    present PPAF has contracted 19 POs with varying levels of capacities, coverage,

    and progress (Annex 6, list of POs and locations). With such a diverse set of

    engagement parameters, piloting in many locations would thinly spread the

    energies of the technical support team who would not only devise/improvise

    processes and instruments but also build enhance practical skills of the

    stakeholders to ensure realization of the conceptual benefits of MSP at all level.

    The chief among multifold purposes of MSP is to define practice guide and distill

    lessons for up-scaling.

    Though the OPM (para 3.6-a) states that 50% HHs in the UC shall be addressed

    under the MSP but in terms of % of villages in a UC, the OPM is silent. A certainminimum village coverage in a UC would be essential for aadequately

    representative MSP (UCDP). It is understood that as yet the current modalities

    both contractual and policy/operational guidelines, do not clearly delineate the

    minimum coverage the PO shall/must strive to develop first draft representative

    MSP at UC level. It is suggested that PMU shall have a detailed look into the

    current contracts and clarify the current and intended coverage to ascertain a

    certain (adequate) minimum coverage for piloting MSP.

    On the basis of the preliminary review of documents (a couple of proposals /

    contracts) and discussion with the existing partners it is proposed that the pilot

    should be carried out in Khot and ParowaUCs in districts of Chitral and Dera

    Ismail Khan respectively. In addition, an area in the newly selected district of

    Haripur is proposed for trying out the approach from scratch. Thus in total, pilot

    in 3 UC would greatly aid in drawing learning for various categories of target

    areas and partners. This piloting envisages all the VDPs in the UC, collating

    these into a UC level MSP and in parallel work on the social organizations that

    will serve as pre-requisite to arrive at such plans.

    Irrespective of the final decision about UC/District, defining the complete process

    leading up to MSP as per the OPM guideline is MSP submitted to PPAF for

    approval and funding within six months of signing the contract. While this

    condition would remain intact for all current and future PPOs the challenge in

    essence is to figure out the process for existing and new areas.The OPM also use

    the term batches of MSPsonce every month which is somewhat misleading

    and requires clarification. The interpretation used for piloting is that a multi-

    sectoral sense in planning is already reflected at VDP level and thus we take that

    it is actually a Village MSPwhere all discussions on MSP have been understood

    to be a UC level planthat might be called UCDP or MSP at UC level. Terminology

    therefore needs to be well defined.

    This required that the steps defined in Chapter 3 a re viewed from action lens to

    determine the sequencing and feasible timeframe as well as the personnel

    requirements from start to end. Final decisions with regard to the concerns raised

    above would have bearing on the number of teams (described in FAQs, chapter 3)to be deployed in the field by the partners.

    Overall, the table in Annex 7 depicts the key processes for a new UC/District laid

    out on weekly basis ensuring that 1st draft MSPs are ready by the end of 4

    th

    month. The suggested approach relies on working on multiple processes in

    parallel, maximally utilizing the staff of the PO. This saves nearly 2 months from

    the 6 month timeframe defined in the OPM.

  • 8/13/2019 MSP Document 2013

    21/33

    21

    Use at

    Use at

    Use

    Use

    While preparing the scheduling chart, special attention was given to separate the

    steps of planning from implementation, however, where time and staffing

    permit parallel actions have been planned for both domains.

    For instance, the rapid market assessment (step-1), analysis of secondary data

    (2a), PO+APO staff orientation (2b), distilling broad potential opportunities and

    investment needs (2d) would be carried out in parallel to the situation analysis at

    villages (3).

    The next block of steps related to the VDP development (4), community

    institutions building (5) would be carried out in parallel to the filling of the PSCs

    and identification of potential beneficiaries for LIP (7). Followed by LIPs

    development (7a), LSO/UCDO constitution (6a) and collation of the VDPs (6b)

    would be done in parallel.

    At this stage the POs would be in position to start making the proposals for

    funding of HH and collective benefit interventions/investments. In parallel to this

    the trend analysis of VDPs (6c) and further augmentation of the UC level

    information from the secondary & market data (6d) would be taken up,

    culminating in the Draft MSP/UCDP (6e).

    In order to add value and enhance the ownership of all involved (esp. line

    department, other NGO and development actors) a series of steps are suggested.

    These include a joint workshop to validate the MSP (6e) followed by alignment of

    the VDPs (6f), if major strategic elements are added by other actors. At this stagethe MSP is technically ready, but to promote its use second joint sitting is

    suggested to develop annual priority list (6e) for various resource (services)

    providers. This would aid in follow-up of the MSP with various actors.

    Moreover, the process attempts to ensure use of the learning in the subsequent

    steps, this is shown by means of arrows showing flow of information. For instance

    in both the VDP and LIP making the market potential would enrich the

    communitys / HHs understanding to evaluate their aspirations. Thus,

    classical/typical requests being made would be replaced with more meaningful

    and lasting interventions is expected. In the existing/current UCs the pilot would

    not revisit the PSCs and LIPs already implemented.

    The detailed snapshot of piloting is given in the following. The diversity among

    piloting regions poses a challenge, albeit essential to build a case for up-scaling in

    a confident manner:

  • 8/13/2019 MSP Document 2013

    22/33

    22

    Chitral D.I. Khan Haripur

    Union Council Khot Union Council Parowa Union Council: open

    Number of villages: 09 Number of villages: 20 Number of villages: open

    PO: AKRSP PO: AHO PO: NRSP

    Population: Population: 28,216

    We recommend moving on with the support of an APO right

    from the start. There is an organized and registered LSO

    called MID in this Union Council. We anticipate that a Union

    Council based Development Organization may already be

    present in the UC. The AKRSP is active in all the villages, has

    organized a number of COs however village organizations

    are not active in the area. With mature experience of AKRSP,

    a convenient access to secondary data, we anticipate that the

    process of 9 VDPs,UC MSP and cross checking of VDPs

    alignment with the MSP will be completed within 4 months.

    This is taking the account of long distances and remote

    locations of the villages and weather factor.

    Team requirement:

    - 1 rapid market / VC appraisal will be conducted in the UC

    at the beginning (consultant Helvetas / Intercooperation)

    - Three teams are required including 2 social organizers: 1

    male and 1 female. (PO)

    - 1 lead facilitator will be provided by the consultant to

    guide social organizers (Helvetas / Intercooperation)

    - Support for data entry and analysis (PO)

    - 1 person (manager level) will go through the existing

    documents and suggest development trends at the stage

    of VO/UC planning. The same person + teammates will

    help in networking with other development actors (PO).

    We strongly recommend engaging an APO from the

    locality since AHO does not have local roots in the

    district. Parowa is a rather large scale UC and a piloting

    exercise can be a real challenge due to a large expected

    coverage by LACIP. AHO is not active in all the villages,

    therefore it is a question whether or not to include all

    the villages in the process. The process of 20 villages will

    have to begin from scratch with hardly any social

    capital on ground. We therefore anticipate that the

    entire process may take a little over 4 months before a

    UC plan can be furnished. One should notice that at the

    moment DI Khan is also not the easiest in terms of

    security of NGO staff.

    Team requirement

    - Six teams are required including 2 social organizers:

    1 male and 1 female- only if all 20 villages are to be

    covered (PO)

    - 1 lead facilitator will be provided by the consultant

    to guide social organizers

    (Helvetas/Intercooperation)

    - Support for data entry and analysis (PO or APO)

    - 1 person (manager level) will go through the existing

    documents and suggest development trends at the

    stage of VO/UC planning. The same person +

    teammates will help in networking with other

    development actors (PO).

    Haripur is a new addition in the LACIP districts, therefore

    PPAF procedures may be new for the district. Our experience

    however, suggests that Haripur is a highly organized and

    enterprising district, with aware and outgoing communities

    who received ample exposure from various development

    agencies including Intercooperation and RSPs. Therefore we

    count on an existing social capital and prior exposure of NRSP

    to PPAFs way of holistic working. We anticipate that the

    entire process of VDP and MSP planning will be accomplished

    in 4 months.

    Team requirement

    - 1 rapid market / VC appraisal will be conducted in the UC

    at the beginning (consultant Helvetas /

    Intercooperation)

    - Three teams are required including 2 social organizers: 1

    male and 1 female (PO)

    - 1 lead facilitator will be provided by the consultant to

    guide social organizers (Helvetas/Intercooperation)

    - Support for data entry and analysis (PO /APO)

    - 1 person (manager level) will go through the existing

    documents and suggest development trends at the stage

    of VO/UC planning. The same person + teammates will

    help in networking with other development actors (PO).

  • 8/13/2019 MSP Document 2013

    23/33

    23

    Annex 1

    One-Day workshop

    Livelihood and Community physical Infrastructure support Project (LACIP)

    Fine-tuning methodological steps and roles of different tiers in Multi-Sectoral Planning (MSP)

    S. No. Content Lead

    09:30 Opening- Welcome note and Workshop Objectives- Round of introduction- Further understanding in the plenary on why this workshop?- Opening remarks

    Masood KhalidFacilitatorFacilitatorQazi Azmat Isa

    10:00 What is LACIP, key targets, implementation challenges Masood Khalid

    10:30 What is MSP and why? Ideas / Considerations Plenary

    10:45 Martins report major recommendations (recap) Dr. Arjumand Nizami

    11:30 Coffee / tea break

    11:45 An example of VDP process Syed Nadeem Bukhari

    12:15 Synthesisplenary brainstorming on MSP outlines Facilitator

    13:15 Lunch / Prayers

    14:00 How to go about MSP process in the field (options) 3 groups

    15:00 Summarizingkey conclusions Facilitator / participants

    15:30 Next steps Participants16:30 Closing remarks Qazi Azmat Isa

    The background of the workshop:

    PPAF as an organization believes in holistic approach in development and therefore is striving for integrated

    development through building strong institutions in the field. For PPAF, institutional strengthening in the field is the key

    to ensuring sustainability of development effects in poverty stricken areas. Therefore an idea of establishing

    community / village organizations for delivering development services does not stop there it needs to be further

    accompanied to achieve a wider understanding on development vision within a community for their development

    and a living plan identifying how to achieve this development. MSP is an idea in this direction encompassing village

    and Union Council levels, taking multiple sectors into account, and ensuring that the idea will be eventually supported

    by the measures provided in LG Act when implemented. This workshop was identified for further fine tuning the MSP

    concept and bring all the concerned at PPAF on one page.

    Objectives:

    - Collectively identify why MSPwhat it isand what will be the methodological steps to achieve a plan in a

    village or a UC

    - Understand the roles expected of various tiers (village, UC) for themselves and towards other development

    actors

    Expected outcome:

    - An outline for partners orientation on the concept and methodology will be available as a result of theworkshop

    - Internal clarity among the team to move on in the field through partners

    - Identification of the next steps

    Participants:

    - LACIP PMU

    - Dr. Allah Nawaz

    - 2 members, LEP

    - 1 member, health

    - 1 member energy

    - 1 member, MER

    - Two members from Helvetas

    - Facilitator MahmoodHemani supported by Roshan Ara

  • 8/13/2019 MSP Document 2013

    24/33

    24

    Annex 2

    Fine Tuning Methodology Steps & Roles in Different Tiers in MSP

    Jinnah Hall, PPAF Office, Islamabad

    17th April 2013

    S

    # Name Designation Organization

    1 Qazi Azmat Isa CEO PPAF PPAF

    2 Masood Khalid GM-LACIP PPAF

    3 Taimur Jehangir SME-LACIP PPAF

    4 Fahd Usman SME-Kfw (PMU) PPAF

    5 Zeeshan Azam Consultant-Kfw (PMU) PPAF

    6 Muhammad Ayaz ME-PMU PPAF

    7 Engr. Hayatullah Khan SNE-LACIP (PMU) PPAF

    8 Zaheer-ud-Din Taj ME-WECC PPAF

    9 Khurram Shahzad SM-MER PPAF

    10 Ahsan UllahBaig ME-EHN PPAF

    11 Waqas Nazir ME-EHN PPAF

    12 Nasrullah Khan Consultant-LACIP PPAF

    13 Ms. Tehseen Rafi Manager-LEP PPAF

    14 Muhammad Shahid Khan SME-ID PPAF

    15 Dr. Anwar Butt Consultant PPAF

    16 Muhammad Riaz Manager-LEP PPAF

    17 Ms. Anila Naimat ME-ID PPAF

    18 Ms. SumairaGul ME-ID PPAF

    19 Ms. Farzana Nadeem ME (GIS)-WEU PPAF20 Dr. Rubina Ashfaq SME-LACIP PPAF

    21 Muhammad Shahbaz Shafique Manager-BISP PPAF

    22 Anwar Mahmood Consultant PPAF

    23 Ms. Roshan Ara Consultant Intercooperation

    24 Dr. Arjumand Nizami Consultant Intercooperation

    25 Nadeem Bukhari Consultant Intercooperation

    26 Mahmood Hemani Consultant Intercooperation

    27 Lt. Col. Zeeshan NLC

    28 Maj. Humayun NLC

  • 8/13/2019 MSP Document 2013

    25/33

    25

    Annex 3

    LIVELIHOOD SUPPORT & PROMOTION OF SMALL

    COMMUNITY INFRASTRUCTURE PROJECT

    (LACIP)

    LACI-P

    Total Project Amount is EUR 31.56 Million

    Commencement of Project Implementation: April 2012

    Completion of Project Implementation: Dec 2015

    Project Districts: 6 (Charsadda, Buner, Swabi, Chitral, D.I.

    Khan and Haripur)

    Number of Union Councils: 60

    The Project will benefit approximately 600,000 people

    Per Person Average investment Cost is PKR 6,000

    PROJECT OBJECTIVES

    Increased access to sustainable

    social, economic and physical infrastructure

    Increased employment and income

    opportunities, especially for the poor

    Development / Strengthening of local civil

    society institutions

    Enhanced participation of the population in

    decision making

    PROJECT COMPONENTS

    Small and Medium Scale community infrastructure

    Improvement and renovation of existing Health and

    Education Units

    Asset Transfers to the Vulnerable and Ultra Poor's

    TARGETS

    Activities TargetSmall and M edium Scale Infrastructureprojects

    2,000

    kill trainings for transitory poors 6,000Livelihood support for ultra poors 7,000Health and edu cation projects 120

    ACHIEVEMENTS

    Sr. No Project Type

    Progress Up till

    March 2013

    1 Smalland Medium Scale Infrastructure Projects Initiated 378

    2 Smalland Medium ScaleInfrastructure Projects Completed 113

    3 Community Organizations 1177

    5 Village Organizations formed 61

    6 Livelihood Investment Plans completed 2819

    7 Sk ill T ra in ings 1817

    8 Assets Transferred 1427

  • 8/13/2019 MSP Document 2013

    26/33

    26

    CHALLENGES

    Poor planning

    security situation in KPK

    Repercussions of Afghanistan after

    2014

    Disaster Prone target areas

    Issues of Female Representation

    CONTINUED

    COs Bank account opening issues

    POs/POs staff capacity, TNA

    required

    Pressure to increase utilization

    CONTINUED

    Anticipating Political Pressures after the May 11,

    2013 Elections in Pakistan

    LACIP PMU Field Monitoring issues due to

    security risks Value Chain tools needed at PO level to enhance

    their vision to create linkages and further

    growth in respective markets

    CONTINUED

    Anticipating Political Pressures after the May 11,

    2013 Elections in Pakistan

    LACIP PMU Field Monitoring issues due to

    security risks Value Chain tools needed at PO level to enhance

    their vision to create linkages and further

    growth in respective markets

    WHY MSPWhere are you goingHow w ill you get there

    hat will tell you that youvearrived

    A MSP m odel is your program ROAD MAP

  • 8/13/2019 MSP Document 2013

    27/33

  • 8/13/2019 MSP Document 2013

    28/33

    28

    Annex 4:

    Summary of recommendations on steps for village development planning and towards MSP

    Martin Dietz Mission (collectively prepared with Dr.Robina Ashraf, Mr.FahadUsman, Mr.TaimurJehangir,

    Mr. Martin Dietz, Mr. Klaus Euler)

    1. Consult with key stakeholders at village, union council and district level to inform and get consent

    It will be important to inform stakeholders from local government bodies and other local bodies of the MSP

    processes right at the outset and get their consent.

    2. Formation of inclusive planning group from within the LSO at UC level

    LSOs should form an inclusive planning group at UC level. This group will initiate inclusive planning groups at

    village level.

    3. Capacity building of community facilitators (village development plan facilitator)

    Planning should be seen as an ongoing activity. Plans need to be updated and further detailed. Therefore, local

    expertise is required to accompany the planning process in future. For this purpose, it is proposed to train

    community facilitators to accompany, support and facilitate the process. It is suggested to train at least two

    persons per union council area.

    4. Conduct a situation analysis / develop village profile

    Planning has to be based on a good situation analysis. Attention needs to be given to a sound analysis of the

    social and economic situation of a village. In an initial step data from secondary sources can be used; they

    need to be verified through FGDs and / or key informants. The community facilitator and PO staff will take a lead

    role for this step.

    This baseline exercise will also include identification of ongoing and planned development initiatives and

    resources. Use a simple data base format and mechanisms for its regular update.

    The situation analysis should consider the following sectors: agriculture, forestry, education,

    employment & enterprise, health, irrigation, drinking water, transport, infrastructure and OD/ID.

    PPAF already has a guideline / list for conducting a situation analysis. This should be reviewed to ensure that it

    will suit the actual purpose of MSP.

    4. Identifying priority sectors of the village

    The situation analysis must provide a good insight to the importance of the different sectors, considered in the

    situation analysis, for the economy and livelihood of the population in the village. Taking on all sectors for detailed

    planning may be a task that is beyond the capacities of a community. It is therefore proposed to select 3 to 4 sectors

    for detailed planning while the remaining sectors will be touched in the planning process with less depth. The main

    criterion for the selection of the priority sectors will be their role and contributions to the livelihood of the majority

    of the population, specifically of disadvantaged communities and the economy of the village.

    5. Development Goals to be achieved long-term (vision)

    At the outset of the process the inclusive planning group with the support of the facilitator will identify long term

    goals for their village. These goals should be cross-sectoral and relate to the envisaged overall changes of the village

    over the coming 5 to 7 years.

    6. Drawing up strategic (periodic) plans

    For the identified priority sectors the Planning Group will develop simple, and as far as possible SMART medium term

    goals (3 years). The goal statement should be complemented by describing the strategies which will outline how

    these goals will be achieved. Setting the strategies should be based on an analysis of the problems that were

    identified earlier. Jumping from problems to solutions should be avoided.

    7. Drawing up annual plans and budgets

  • 8/13/2019 MSP Document 2013

    29/33

    29

    The strategic, medium term plan will be the base for drawing up an annual plan for the village. Projects / activities

    will be planned for the coming year that contributes towards achieving the medium term goals of the village / UC.

    These interventions should be selected by using criteria such as for instance:

    High impact in short time;

    Large number of people to benefit, completion with in one year;

    Benefits for economically and socially disadvantaged are to be given high priority.

    UCs / VOs should be supported to develop budgets for the planned projects and activities. This will be the realitycheck for the community planning.

    8. Collating key elements of village development plans into a MSP of the Union Council

    The LSO/APO will collate village development plans (periodic and annual) to develop a UC MSP. Such an MSP should

    feed into district planning and be used to seek funding for UC projects identified through the MSP.

    9. Interactions of UC with development actors

    Link LSOs with development agencies (government, bilateral, INGOs and NGOs) in appropriate forums to present

    their periodic and annual plans. Such interactions will provide opportunities for UCs to communicate their

    development priorities and invite development actors to take up opportunities for development.

    The recently approved legislation on Local Government by the KP Provincial Parliament may provide opportunity for

    PPAF to embed MSP into a legal framework and promote this approach as mainstream throughout in KP.

    Next steps towards preparing MSP

    1. Discuss and further elaborate the issue within PPAF / LACI-P and finalized the concept

    2. Identify a small working group within PPAF / LACIP and HELVETAS which will accompany field testing / piloting

    3. Assess the details of the recently approved Local Government legislation to assess how MSP can fit best into this

    legislation

    4. Briefly assess and summarize ongoing village level planning work by some POs. Identify good practices that can be

    incorporated into MSP

    5. Identify potential and competent POs for piloting

    6. Get feedback from POs on the concept

    7. Consider to involve relevant officials from the KP Provincial Government early in the process

    8. Develop details of the planning process, train PO staff and community facilitators (HELVETAS will be able to

    support this part and share experience from other countries)

    9. Identify one or two UCs

    10. Get consensus from local stakeholders, including stakeholders at district level

    11. Develop a monitoring system to ensure that learnings can be drawn from the pilots

    12. Run the pilot

    13. Evaluate, upscale, mainstream

  • 8/13/2019 MSP Document 2013

    30/33

    30

    Annex 5

    Table 1: Guiding Principles of Integrated Village Planning (Government of KP, Forests Department)

    Guiding Principles Check list

    Participation All owners and users of NRs have been approached for initial information and in the rest of

    the process

    Rights of households from all village sections are knownVDC and WO include representatives from all community sections and hamlets

    The VDC reaches consensus on objectives, division into management units and

    interventions

    Women, landless, poor in the community contribute in the village planning and decision

    making

    Poor and remotely located sections are also represented in management committees

    All sections have a chance to participate in the monitoring committees established from

    time to time

    Integrated

    approach

    Initial information is collected about all land uses

    A land use map is prepared with the consensus of the villagers

    Representatives from forests and other line agencies participate in planning process

    Interventions identified in the plan for all land uses and social services

    Responsibilities for forest and other line agencies identified in the plan as per interventions

    Responsibilities for the VDC, JFMC, WO and other management committees identified

    Responsibilities of the beneficiaries identified

    Sustainable use of

    natural resources

    Management plans include village regulations for controlled use (e.g. nagha)

    Use intensities and timing compatible with growing cycles of vegetation

    Use intensities and timing compatible with the needs of the people

    Timber is not the only valued resource indicated in the plan there are interventions for

    other sources of livelihoods as well

    Pro-poor Household typology conducted in the village to identify different socio-economic groups in

    the village

    Poor and poorest identified through household typology are alsorepresented and

    participate in VDC/WO as members

    Contributions / benefit sharing of different sections agreed upon between themselves

    Interventions are included in the plan which specially benefit the poorest / poor

    Self accountability

    and transparency

    The entire planning process was inclusive and consultative

    All sections of communities were involved in identifying interventions

    Responsibilities are clearly identified in the plan (e.g. community, service providers)The plan document is villagers property, is open and accessible to all in the village

    VDC identifies beneficiaries / locations of interventions in open meeting

    Periodically the plans implementation progress is presented in general body by AMC

  • 8/13/2019 MSP Document 2013

    31/33

    31

    Annex 6:

    List of partner NGOs and respective Union CouncilsLACIP

    District- Wise PO's, PO's Funding and UCs Information

    # District PO's Name of UC's Funding (Rs) In

    Million

    Total

    1 Swabi SWWS Checknodha, Anbar 230.14 702.21

    NRSP Asota, Bachai, Parmolai 207.1

    SDF Sara Cheena, Yaqobi 128.63

    GBTI Kohata, Batakra 136.34

    2 Chitral AKRSP Yarkhoon, Khot, Oveer, Koh, Mulkhow, Chitral II 293.71 477.59

    SRSP Arandu, Ashurait, Shishikoh 160.3

    MIED Yarkhoon, Khot, Oveer, Koh, Mulkhow, Chitral II 23.58

    3 Charsadda SRSP HisaraNehri, Hassanzai, Madani 201.19 234.47

    SPADO Prang 33.28

    4 Buner HADAF Mukhranai, Amazai 138.64 525.59

    MGPO Chagalai, Ghorghosto 156.6

    RDP Gulbandi 63.87

    CGN-P Chaghlai,Mukharani, Gulbandi 30.14

    EPS Koga, Nawagai 136.34

    5 D.I Khan SERVE Shorekot 56.87 369.88

    CUP Korai, Yarik 125.2

    SABAWON Daraban, Chaudhwan 114.58

    AHO Mehra 33.86

    CIE Korai, Yarik, Daraban 39.37

    Total 2309.74

  • 8/13/2019 MSP Document 2013

    32/33

  • 8/13/2019 MSP Document 2013

    33/33