  AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect. 15A. NAME AND TI TLE OF S IGNER (Type o r print ) 30-105-04 EXCEPTION TO SF 30 APPROVED BY OIRM 11-84 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA FAR (48 CFR) 53.243 The purpose for this am endm ent is to address preproposal questions. Off erors m ust ac knowledge amen dm ents in Block 19 of the SF1 442. The proposal due date remains 21 October 2013. 1. CONTRACT ID CODE PAGE OF PAGES J 1 4 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) 16C. DATE SIGNED BY 26-Sep-2013 16B. UNITED STATES OF AMERICA 15C. DATE SIGNED 15B. CONTRACTOR/OF FEROR (Signature of Contracting Officer) (Signature of person authorized to sign) 8. NAME AND ADDR ES S OF CO NTRACTOR (No., Street , County , State and Zip Code) X N33191-13-R-1240 X 9B. DATED (S EE IT EM 11) 05-Sep-2013 10B. DATED (S EE ITEM 13) 9A. AMENDMENT OF SOLICITATION NO. 11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS X The above numbered sol icitat ion is am ended as set forth in Item 14. The hour and date specified f or receipt of Off er is extended, X is not ex tended. Of f er must acknowledge receipt of this am endment prior to t he hour and date s pecif ied in the sol icitation or as amende d by one of the following m ethods: (a) By completing I tem s 8 and 15, and re turning copies of the am endment; (b) By a cknowle dging rec eipt of this am endm ent on eac h copy of the of f er subm itted; or (c) By separate letter or telegram which in cludes a refer ence to th e soli citation and am endment numbers. FAILURE OF YOUR ACKNOWL EDGMENT TO BE RECEIVED AT THE P LACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by vi rtue of this amendment you desi re to change an off er already su bmitted, such chan ge may be m ade by tel egram or lett er, provided each telegram or letter make s refe rence to the solicit ation and this am endm ent, and is received prior to the opening hour and date specified. 12. ACCOUNTING AND APPROPRIATION DATA (If required) 13. T HIS ITEM AP PLIES ONLY TO MODIFICATIONS O F CONTRACTS /ORDER S . IT MODIFIES T HE CONTRACT/ORDER NO. AS DES CRIB ED IN IT EM 14 . A. T HIS C HANG E ORDER IS IS S UED PURS UANT T O: (S pecify a uthor ity ) T HE CHANG ES S ET FOR T H IN IT EM 14 ARE MADE IN THE  CONTRACT ORDER NO. IN ITEM 10A. B. T HE ABOV E NUMBERED CONTRAC T /ORDER IS MODIFIED TO REFLECT T HE ADMINISTRATIVE CHANG ES (su ch as changes in p aying office, appropriation date, etc.) SET FOR TH IN IT EM 14, P URSUANT T O THE AUTHORITY OF FAR 43.103(B). C. THIS S UPP LEMENT AL AG REEMENT IS ENTERED INT O PURS UANT T O AUTHORIT Y OF: D. OTHER (S pecify typ e of mo di fication and au tho rity) E. IMPORT ANT: Co nt ractor is not, is re quired to sign this do cument and retu rn copies to the issuing of fi ce. 14. DESC RIPT ION OF AMENDMENT/MODIFICATION (Organized by UC F s ectio n headings , includ ing s olicitat ion/con tr act sub ject mat t er  where feasible.) 10A. MOD. OF CONTRACT/ORDER NO. 0002 2. AMENDMENT/MODIFICATION NO. 5. P ROJECT NO.(If applicabl e) 6. ISSUED BY 3. EFFECTIVE DATE 26-Sep-2013 CODE NAVFAC EUROPE AFRICA SOUTHWEST ASIA PSC 817 BOX 51 FPO AE 09622-0051 N33191 7. ADMINISTERED BY (If oth er than item 6) 4. REQUISITION/PURCHASE REQ. NO. CODE See Item 6 FACILITY CODE CODE EMAIL: TEL:

N33191-13-R-1240-0002

Embed Size (px)

DESCRIPTION

The work is divided into a BASE-BID and 4 CONTRACT OPTIONS. The Government reserves the right tounilaterally award, or not to award, the contract options. The contractor will provide separate pricing for theBase-Bid and the 4 contract options as required in the solicitation documents.3

Citation preview

  • AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

    Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

    15A. NAME AND TITLE OF SIGNER (Type or print)

    30-105-04EXCEPTION TO SF 30APPROVED BY OIRM 11-84

    STANDARD FORM 30 (Rev. 10-83)Prescribed by GSAFAR (48 CFR) 53.243

    The purpose for this amendment is to address preproposal questions.

    Offerors must acknow ledge amendments in Block 19 of the SF1442.

    The proposal due date remains 21 October 2013.

    1. CONTRACT ID CODE PAGE OF PAGES

    J 1 4

    16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

    16C. DATE SIGNED

    BY 26-Sep-2013

    16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

    (Signature of Contracting Officer)(Signature of person authorized to sign)

    8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N33191-13-R-1240X 9B. DATED (SEE ITEM 11)05-Sep-2013

    10B. DATED (SEE ITEM 13)

    9A. AMENDMENT OF SOLICITATION NO.

    11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONSX The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

    Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods: (a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

    12. ACCOUNTING AND APPROPRIATION DATA (If required)

    13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

    A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

    B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

    C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

    D. OTHER (Specify type of modification and authority)

    E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

    14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

    10A. MOD. OF CONTRACT/ORDER NO.

    00022. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

    6. ISSUED BY

    3. EFFECTIVE DATE

    26-Sep-2013CODE

    NAVFAC EUROPE AFRICA SOUTHWEST ASIAPSC 817 BOX 51FPO AE 09622-0051

    N33191 7. ADMINISTERED BY (If other than item 6)

    4. REQUISITION/PURCHASE REQ. NO.

    CODE

    See Item 6

    FACILITY CODECODE

    EMAIL:TEL:

  • N33191-13-R-1240 0002

    Page 2 of 4

    SECTION SF 30 BLOCK 14 CONTINUATION PAGE

    SUMMARY OF CHANGES

    SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

    The following have been added by full text: AMENDMENT 0002

    N33191-13-R-1240 Renovation of Sevastopol School #5, Ukraine

    Questions and Answers

    QUESTION: With regards to picture #108: In page 43 (technical specifications ver.002) write: Red: Additional area requiring roof repair included in Option-4. Red: actually roof repairs?

    ANSWER: This is a mistake in the contract specifications. Red corresponds to complete faade restoration, described in paragraph 1.7.1 and clarified in picture#108-b of the Technical Specifications. It does not correspond to roof repair.

    QUESTION: With regards to picture #108: Blue: Area requiring only faade restoration - it`s actually only requiring faade?

    ANSWER: Yes, this is described in paragraph 1.7.2 of the Technical Specifications. It does not include new windows or doors, but includes faade restoration and painting the windows and doors.

    QUESTION: With regards to picture #108: Blue - I understand correctly: the blue area to repair the faade is different from a green area. Green area - it`s full renovation and Blue area - repair of individual regions.

    ANSWER: The green area corresponds to the area included under contract option -2. Contract option-4 does not include any work in the green area. The blue areas include the work described in paragraph 1.7.2 of the Technical Specifications. Under this contract option, it is not required to replace the doors or windows. It must be noted that the blue areas in the central building include areas within contract option-3. Therefore, if contract option 3 and 4 are awarded, the blue section in the contract wing will require faade restoration and window replacement. If only contract option 3 is awarded, only the windows in the central wing will require replacement, but no faade restoration. If only option 4 is awarded,

  • N33191-13-R-1240 0002

    Page 3 of 4

    the blue areas of the central wing would have the faade restored, but the windows and doors only painted.

    QUESTION: With regards to picture #107: In this picture #107: In the green belt must be replaced only the window? Provided in this Green area renovation in faade?

    ANSWER: Under contract option-3 only the window replacement is included. No work on the faade is included under this contract option.

    QUESTION: Past Performance Questionnaire - This document must be completed by the client of our company?

    ANSWER: The Past Performance Questionnaire should be completed by the client(s) of the design and construction projects that were completed by your company.

    QUESTION: The Technical Proposal shall include the following 3 factors: Factor 1, Corporate Experience -it`s documents Contract Data Sheet

    Factor 2, Safety - it`s document drawn up on two pages about the safety of this project Factor 3, Past Performance - it`s document on the past project that is signed by the client of my company

    These three factors are sufficient for the technical proposal?

    ANSWER: Yes, as stated in the solicitation, the Technical Proposal includes the following 3 factors:

    Factor 1, Corporate Experience: Contract Data Sheet is provided as Attachment 2 of the solicitation for offerors to fill out for their submitted relevant projects. Factor 2, Safety: Offerors must provide their narrative within two (2) single-sided pages, 8.5 X 11, with a minimum of 12 font. If more than two (2) pages are submitted, only the first two (2) pages will be evaluated. Factor 3, Past Performance: Past Performance Questionnaire is provided as Attachment 3 of the solicitation for offerors to have their clients of relevant projects to fill out.

  • N33191-13-R-1240 0002

    Page 4 of 4

    QUESTION: In checklist for submittals N33191-13-R-1240 includes : safety narrative. I understand this document as Factor 2. Safety - it`s correct?

    ANSWER: Correct. The checklist is provided to assist offerors in ensuring they have met all of the solicitation submittal requirements. For Factor 2, Safety, a safety narrative is required.

    QUESTION: Section 00600 - Representations & Certifications - it`s document includes in N33191-13-R-1240.pdf . In this documents I must to put the date and signature. It`s correct?

    ANSWER: Offerors MUST sign and date the highlighted area in Section 00600 Representations and Certifications on page 14 of the solicitation.

    (End of Summary of Changes)