Well Integrity Programme, Strengthening of 5 Conductors, (NOJ-023)
Client: Petronas Carigali through PetroUsaha Offshore S/B
Status: Ongoing, 2012
Grouting of Skirt Piles and Pile Sleeves for New Platform Installation (NOJ-021)
Client: Heerema Marine Contractors Ned. B.V.
Status: Ongoing, 2012
Strengthening of Jacket Braces and Piles for Platform Retrofitting, (NOJ-019)
Client: Dragon Oil (Turkmenistan) Ltd.
Status: Ongoing, 2012
Grouting of Skirt Piles for new Platform Installation, (NOJ-016)
Client: Murphy Sarawak Oil through PetroUsaha Offshore S/B
Status: Completed, 2012
Grouting of Leg Brace Clamps, Indonesia (NOJ-014)
Client: PT Radiant Utama Interinsco
Status: Completed, 2012
TSW Well Integrity Campaign 2012, (NOJ-012)
Client: Brunei Shell Petroleum through Joffren Omar S/B
Status: On-going since 2006
TSW4 Well Integrity Campaign 2012 (AMDP11), 6 Wells, Brunei (NOJ-011)
Client : Shell Brunei through Joffren Omar s/b
Status : Completed
TSW4 Well Integrity Campaign (CPDP 33), 6 Wells, Brunei (NOJ-010) Client : Brunei Shell through Joffren Omar s/b
Status : Completed
Cape Lambert Dolphin Installations, Australia (NOJ-009)
Client : Rio Tinto through John Holland
Status : Completed, 2012
Grouting Works for Pile Sleeves Connection, Panna SBM (NOJ-008)
Client: Dolphin Offshore Enterprises Ltd., India
Status: On-going, March 2012
Page 2 of 2
Na
utic
Gro
up
Pte
Ltd
Well Integrity Campaign, Shell Malaysia (NOJ-007)
Client : Shell Malaysia through PetroUsaha Offshore s/b
Status : Completed, 2012
Strengthening of N4 Jacket, Persian Gulf (NOJ-006)
Client : Dulam, UAE
Status : Completed, 2012
Strengthening of MNP & MNW Jackets (NOJ-005)
Client : Larsen and Toubro, India
Status : Complete
KNPG-B Jacket Installation, Malaysia (NOJ004)
Client : Petronas Carigali through PetroUsaha Offshore s/b
Status : Completed
LAM-4 Platform, Jacket Installation, Turkmenistan (NOJ-003)
Client : Dragon Oil (Turkmenistan) Ltd
Status : Completed
Grouting of 8 Skirt Piles, Yetagun, Ph. 4 development project, Myanmar (NOJ-002)
Client : TL Offshore Ltd trough PetroUsaha Offshore s/b
Status : Completed
Analysis and Design of Strengthening for Offshore Flare Tower (NOJ-001)
Client : Woodside Engineering Ltd, Australia
Status : Completed