33
NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Embed Size (px)

Citation preview

Page 1: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED Status Report

Arnaud DevredCEA/DSM/DAPNIA/SACM

& CERN/AT/MAS

CARE Steering Committee MeetingLPNHE

11 April 2006

Page 2: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

CARE/NED JRA

• The Activity is articulated around four Work Packages and

one Working Group

1 Management & Communication (M&C),

2 Thermal Studies and Quench Protection (TSQP),

3 Conductor Development (CD),

4 Insulation Development and Implementation (IDI),

5 Magnet Design and Optimization (MDO) Working

Group.

• It involves 7 institutes (8 laboratories)

• Total budget: ~2 M€; EU grant: 979 k€ (over 3 years).

Page 3: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Management & Communication (1/2)

• Steering Committee meetings– 23 February at CERN

1 June at CIEMAT

• HHH/AMT meeting– WAMDO: 3-6 April at CERN

• ESAC meeting next fall, at the end of Step 2 of Conductor

Development.

Page 4: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Management & Communication (2/2)

• 4 papers at ICEC 21/ICMC '06 (17–21 July, Prague,

Czech Republic) – NED cryostat– Nano- and micro-hardness measurements– 2 papers on conventional insulation

• 6 papers at ASC (27 August–1 September, Seattle,

WA)– Overview– Heat-transfer measurements– Quench computation on slot design– Wire FE model– NED reference design V2– WGMDO comparison

Page 5: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/TSQP Work Package

• The TSQ Work Package includes two main Tasks

– development and operation of a test facility

to measure heat transfer to helium through

Nb3Sn conductor insulation

(CEA and WUT; Task Leader: B. Baudouy, CEA),

– quench protection computation

(INFN-Mi; Task Leader: G. Volpini).

Page 6: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Heat Transfer Measurement Task (1/2)

• The first part of the Task was to

design and build a new He-II,

double-bath cryostat.

• The cryostat was built by

Kriosystem in Poland under the

supervision of Wroclaw University

according to specifications written

by CEA.

• The cryostat was delivered to

CEA on 20 September 2005 and

has been rprepared for

commissioning.Miscellaneous views of NED cryostat

(Courtesy M. Chorowski, WUT)

Page 7: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Heat Transfer Measurement Task (2/2)

• The first cooldown was carried out on 14 February 2006 and

it took ~7 hours to reach 1.5 K in the He II pressurized

bath.

First cooldown of NED cryostat at CEA

(Courtesy B. Baudouy, CEA)

• The test was suspended

due to a problem with a LHe

level sensor that is a critical

element of the control

system.

• A new sensor has been

ordered and the test is

expected to resume in June

2006.

• Extensive measurement

campaigns will follow.

08 AM 09 AM 10 AM 12 PM 01 PM 02 PM 03 PM 04 PM 06 PM 07 PM

0

50

100

150

200

250

300

TT1 TT3 TT5bis TT2bis TT5 TT6 TT7 TT4 TT2

Temperature (K)

Time

February 14th first cooldown, 9:20 AM

Page 8: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED Quench Computation Task

• INFN-Mi has carried a detailed

analysis of the thermal and

electrical behaviors of NED-like

magnets during a quench.

• The computations were

focused on the Reference 88-

mm-aperture, cos, layer design

and show that, magnets up to 10

m long can be operated safely,

thereby justifying the choice of

conductor parameters made

early on.

• The Task is completed and a

final report has been issued.

0

50

100

150

200

250

300

Rd=15 mOhmRd=25 mOhmRd=35 mOhmRd=45 mOhmDelay=30 msDelay=40 msDelay=50 ms

I=15 kAI=22 kAI=29 kA

Hot spot temperature (K)

QLASA

QUABER

0

200

400

600

800

1000

1200

1400

Rd=15 mOhmRd=25 mOhmRd=35 mOhmRd=45 mOhmDelay=30 msDelay=40 msDelay=50 ms

I=15 kAI=22 kAI=29 kA

Total voltage (V)

QLASA

QUABER

Quench simulations for 10-m-long, 88-mm-aperture, cos, layer design

(Courtesy M. Sorbi, INFN-Mi)

Page 9: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Complementary NED/TSQP Efforts

• Since the start of NED, two complementary efforts have been

launched at CERN

– Analysis of available LHC magnet test data at high

ramp rate to determine how well the heat-transfer

measurements at CEA correlate with actual magnet data,

– Review of magnet cooling modes to estimate, on the

cryogenics system point of view, what are the limitations

on power extraction and to provide guidance on how to

improve cooling of magnet coils

(preliminary conclusions indicates that NED-like magnets

may have to be operated in superfluid helium).

Page 10: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/CD Work Package

• The CD Work Package includes three main Tasks

– conductor development

(under CERN supervision; Task Leader: L. Oberli),

– conductor characterization

(CEA, INFN-Ge, INFN-Mi, and TEU; Task Leader: A. den

Ouden, TEU),

– FE wire model (to simulate cabling effects)

(CERN and INFN-Mi; Task Leader: S. Farinon, INFN-Mi).

• It is the core of the Program and absorbs about 70% of the

EU-allocated funding.

Page 11: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Conductor Development (1/2)

• Conductor specifications were derived from preliminary

design studies carried out in 2003-2004 at CERN; salient wire

parameters are

– diameter 1.250 mm,

– eff. filament diameter < 50 m,

– Cu-to-non-Cu ratio 1.25 ± 0.10,

– filament twist pitch 30 mm,

– non-Cu JC 1500 A/mm2 @4.2 K & 15

T,

– minimum critical current 1636 A at 12 T,

818 A at 15 T,

– N-value > 30 at 4.2 K and 15 T,

– RRR (after heat treatment)> 200.

(It is also requested that the billet weight be higher than

50 kg.)

Page 12: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Conductor Development (2/2)

• Based on these specifications, a call for tender was issued by

CERN in June 2004 and two contracts (funded by CARE/NED)

were awarded in November to 2004 to

– SMI in The Netherlands (“Powder in Tube” Process) for

290 m of 40-strand cable,

– Alstom/MSA in France (“Enhanced Internal Tin”

process) for 580 m of 40-strand cable.

• After discussion with CERN, the two companies have agreed

to work out their development program into two successive RD

Steps (referred to as STEP 1 and STEP 2) followed by final cable

production.

• Note that, since then, CERN has awarded in April 2005 a third

contract for 580 m of 40-strand cable to Outokumpu OY (which

is internally funded by CERN).

Page 13: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

SMI Status (1/6)

• SMI STEP 1 was devoted to iterations on an existing 1-mm-ø

strand design with 192 (NbTa)3Sn filaments.

• Several billets were produced with different powder

compositions (B179 & B201) or outer Ta tubes around the Nb

tubes to act as on anti-diffusion barrier.

• The best critical current

results were obtained on

B179Diameter: 1.00 mmFilaments: 192 (50 m)

Cu-to-non-Cu ratio = 0.73IC = 1105 A at 12T (with 84 h at 675

°C)

Non/Cu JC = 2410 A/mm2 at 12 T

Page 14: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

SMI Status (2/6)

• Following STEP 1, it was decided to produce another billet

(B207), aimed at NED diameter, but keeping the same NbTa

tubes and the same powder composition as for B179.

• The resulting wire is pretty good in terms of overall critical

current but Cu-to-no-Cu ratio and critical current density are

below expectations.

Diameter: 1.255 mmFilaments: 288 (50 m)

Cu-to-non-Cu ratio = 0.955IC = 1313 A at 12T (with 84 h at 675

°C)

Non/Cu JC = 2077 A/mm2 at 12 T

Page 15: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

SMI Status (3/6)

• The critical current of wire B207 has been fully characterized

at INFN-Mi (7-13 T) and University of Geneva (15-19 T).

Non-Cu JC = 2077 A/mm2 at 12 T

= 1118 A/mm2 at 15 T

• INFN-Mi also performed stability current measurement, which

did not show any instability up to 1800 A (14 to 18 mT/s).

Page 16: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

SMI Status (4/6)

• INF-Mi also performed measurements on 2 deformed samples

(0.35-mm deformation) yielding ~15-17% IC degradation.

(Courtesy G. Volpini, INFN-Mi)

Page 17: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

øNb = 55 m øNb3Sn = 44 mm

• Shielded volumes derived from m(T)

4.5 K, transverse field

SMI Status (5/6)

• Magnetization measurements performed at INFN/Ge have

confirmed the expected filament outer diameter.

(Courtesy M. Greco, INFN-

Ge)

Page 18: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

SMI Status (6/6)

• The next step agreed upon by CERN is to produce a 10-kg

billet similar to B207 (which was only 3 kg) with proper Cu-to-

non-Cu ratio and a proper powder preparation (aimed at

achieving a non-Cu critical current density greater than 2500

A/mm2 at 4.2 K and 12 T)

should be ready by mid-June.

Page 19: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Alstom/MSA Status

• Alstom/MSA is developing the so-called enhanced internal-tin

process based on a double-stacking billet design and cold

drawing.

• STEP 1 has been devoted on optimizing billet design and

assembly to obtain good workability.

• Workability problems have appeared more severe than

anticipated and require a systematic study of main design and

assembly parameters.

• Good progress, no show stoppers.

Page 20: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED Conductor Characterization

• NED conductors are characterized by performing

critical current and magnetization measurements.

• Critical current measurements represent a real

challenge, given the expected performances (e.g.,

~1600 A at 4.2 K and 12 T on a 1.25-mm-Ø wire,

compared to ~200 A presently achieved on 0.8-mm-

Ø ITER wires).

• To validate sample preparation and measurement

processes, CEA, INFN-Mi and Twente University have

carried out an extensive cross-calibration program

and have now achieved a reasonable convergence.

Page 21: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

FE Wire Model

• INFN-Ge has been working on

a mechanical FE model (based

on ANSYS®) to simulate the

effects of cabling on un-reacted,

Nb-Sn wires.

• To feed the model, CERN has

supervised and/or carried out a

series of nano-indentation and

micro-hardness measurements

to determine the mechanical

properties of the materials

making up the wire in the cold-

work state where they are prior

to cabling.

Micro-hardness measurements on a X-cut of internal tin wire

(courtesy C. Scheuerlein, CERN)

FE model of internal tin wire(courtesy S. Farinon, INFN-Ge

Page 22: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/IDI Work Package (1/2)

• The IDI Work Package includes two main Tasks

– studies on “conventional” insulation systems

relying on ceramic or glass fiber tape and

vacuum-impregnation by epoxy resin

(CCLRC/RAL; Task Leader: S. Canfer),

– studies on “innovative” insulation systems

relying on pre-impregnated fiber tapes and

eliminating the need for a vacuum

impregnation

(CEA; Task Leader: F. Rondeaux).

Page 23: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/IDI Work Package (2/2)

• CCLRC/RAL is evaluating a polyimide-sized glass

fiber tape that is able to sustain the required Nb3Sn

heat treatment without degradation and which

seems a promising solution to conventional

insulation.

• The Innovative Insulation Task is built upon an

ongoing R&D program at CEA which has

demonstrated the feasibility of such a system, but

which has been on hold for a year due to a lack of

human resources; the program has now restarted

and is gearing up to speed.

Page 24: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/MDO Working Group (1/4)

• The MDO Working Group is made up of representatives from

CCLRC, CEA, CERN and CIEMAT

(Chairman: F. Toral, CIEMAT).

• Its main charge is to address the following questions

– How far can we push the conventional, cos, layer

design in the aperture-central-field parameter space

(especially when relying on strain-sensitive conductors)?

– What are the most efficient alternatives, in terms of

performance, manufacturability and cost?

• A number of magnetic configurations have been selected and

are presently being evaluated.

Page 25: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/MDO Working Group (2/4)

Common coil(CIEMAT)

Ellipse-type(CEA/Saclay)

Double helix(RAL)Cos layer

(CERN & RAL)

Motor-type(CIEMAT)

Cos slot(CERN)

(Courtesy F. Toral, CIEMAT)

Page 26: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/MDO Working Group (3/4)

(Courtesy N. Schwerg, CERN)

• CERN has pursued the electromagnetic optimization of the

baseline, 88-mm-aperture, cos layer design with respect to

– conductor geometry,

– iron shape (to reduce saturation effects),

– ferromagnetic shims (to compensate magnetization

effects).

Page 27: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

NED/MDO Working Group (4/4)

(Courtesy P. Loveridge, CCLRC/RAL)

• CCLRC/RAL is developing a comprehensive (ANSYS®-based)

mechanical model of the baseline, 88-mm-aperture, cos layer

design throughout the various steps of manufacturing,

cooldown and energization.

STAINLESS-STEEL COLLAR LAMINATION LOWER COIL

UPPER COIL

IRON YOKE

STAINLESS-STEEL SHRINKING CYLINDER

Page 28: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

INFN/CANDIA Project (1/2)

• INFN has approved on 30 November 2004 a

research project called CANDIA (Italian acronym for

CAvi in Niobio-stagno per DIpoli ad Alto campo or

niobium-tin cables for high field dipoles), involving

teams from INFN-Frascati (LNF), INFN-Genova and

INFN-Milano (LASA).

• The main goal of CANDIA is the development of a

Nb3Sn conductor according to NED-like

specifications.

• A call for tender was issued in the Fall of 2005 and

a contract for the manufacture of 1500 m of wires

was awarded on 15 December 2005 to Outokumpu

Copper Superconductor Italy (OCSI).

Page 29: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

INFN/CANDIA Project (2/2)

• The chosen technology is Internal Tin process.

• The expected delivery is Fall of 2006.

• Of course, close ties are maintained between

CANDIA and NED.

Page 30: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

What’s next? (1/2)

• 10 European Group Leaders/Managers and 2 US-

LARP Managers have cosigned a contribution to the

CERN Council Strategy Grouphttp://council-strategygroup.web.cern.ch/council-strategygroup/

• This document outlines a strategy for European

superconducting accelerator magnet R&D aimed at

LHC luminosity upgrade, promoting the

manufacturing of NED (in complement to LARP) and

some well-focused R&D on cycled NbTi accelerator

magnets.

Page 31: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

What’s next? (2/2)

• The document will be extended to outline a world-

wide strategy (with US and Japanese partners)

should be ready by mid-June.

• The strategy document will serve as a basis for a

letter of intent to the European Strategy Group on

Accelerator R&D (ESGARD) for FP7 proposals (due on

28 April 2006).

Page 32: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Letter of Intent for FP7

• Transnational Access

Test facilities for conductor characterization.

• Topics for JRA

– NED manufacturing and test,

– focused R&D on cycled NbTi accelerator

magnets (conductor, supercritical helium

study, quench protection study, extended test

of FAIR-type prototype).

• Strategy on one or two JRA’s to be determined

when the details of the call for proposal will be

known.

Page 33: NED Status Report Arnaud Devred CEA/DSM/DAPNIA/SACM & CERN/AT/MAS CARE Steering Committee Meeting LPNHE 11 April 2006

Conclusion

• All NED Tasks are making good progress.

• The Activity will come to an end at the end of the

year (first semester of 2007?).

• How to bridge the gap with FP7?