Upload
tiffany-criste
View
217
Download
0
Embed Size (px)
Citation preview
Neutrino Town MeetingNeutrino Town MeetingCERN – May 14-16, 2012CERN – May 14-16, 2012
SPL R&D and Potential SPL R&D and Potential ApplicationsApplications
R. Garoby for the SPL team*
O. Brunner, S. Calatroni, O. Capatina, E. Ciapala, F. Gerigk, E. Montesinos,V. Parma, K.M. Schirm,+ I. Aviles Santillana **, R. Bonomi **, J. Chambrillon, P. Coelho Azevedo**, K. Liao, N. Valverde Alonso**
** supported by ESS
HP-SPL:HP-SPL:R&D ManagementR&D Management
R. G. – 15/05/2012 3
• R & D for a High Power SPL formally supported at CERN in view of multiple future potential applications
~1.7 MCHF and 6 FTEs / year
• Collaboration with ESS Fellows and procurement of klystron modulator for SM18
• French in-kind contribution Tuners, Helium tanks, use of Saclay 704 MHz high power test place…
• EC-supported programmes• EuCARD (WP10)
Development and test of beta=1 (CEA) and beta=0.65 (IN2P3) 5 cells cavities• CRISP (WP4)
Joint work with ESS and DESY EC-supported manpower for upgrading and exploiting the SM18 test place
• LAGUNA-LBNO EC-supported fellow for studying proton drivers at CERN using LP- or HP-SPL
• DOE-supported programme• BNL Development and test of a =1 cavity
ResourcesResources
SPL documentation in EDMS [ https://edms.cern.ch/nav/SLHC-000008 ] SPL meetings in Indico [ http://indico.cern.ch/categoryDisplay.py?categId=1893 ]
SPL documentation in EDMS [ https://edms.cern.ch/nav/SLHC-000008 ] SPL meetings in Indico [ http://indico.cern.ch/categoryDisplay.py?categId=1893 ]
R. G. – 15/05/2012 4
Organization (at CERN)Organization (at CERN)GuidelineGuideline
«Project-like» structure aimed at meeting the objectives of the HP-SPL R&D:• Building and testing a prototype cryomodule with 4 cavities• Updating CERN infrastructure and competence in superconducting RF technology• Preparing submission of future subjects of R&D [design and construction of a full-size cryomodule,
high power RF sources, HIPIMS (High Power Impulse Magnetron Sputtering)…]
Work UnitsWork Units-Design, construction and test of the prototype cryomodule (Leader: V. Parma)
- Components: Cryomodule, Cavities, RF items (Couplers, tuners, …), cryogenics equipment…- Assembly (with adequate tools): cavities string in clean room, inclusion in cryomodule- Tests: cavities in vertical cryostat, assembled cryomodule in bunker.- Upgrade of the SM18 infrastructure (Leader: O. Brunner)- HP water rinsing system and upgraded clean roon- Cryogenics for efficient operation at 2K- High power RF at 704 MHz (klystron, modulator, high power distribution)- Low Level RF and controls
-SC RF cavities technology (Leader: E. Ciapala)- Fabrication and processing- Test, diagnostics and analysis
HP-SPL:HP-SPL:Baseline Design ParametersBaseline Design Parameters
R. G. – 15/05/2012 6
Option 1 Option 2
Energy (GeV) 2.5 or 5 2.5 and 5
Beam power (MW)2.25 MW (2.5 GeV)
or
4.5 MW (5 GeV)
5 MW (2.5 GeV)
and
4 MW (5 GeV)
Protons/pulse (x 1014) 1.1 2 (2.5 GeV) + 1 (5 GeV)
Av. Pulse current (mA) 20 40
Pulse duration (ms) 0.9 1 (2.5 GeV) + 0.4 (5 GeV)
2 beam current 2 nb. of klystrons etc .
Ion species H−
Output Energy 5 GeVBunch Frequency 352.2 MHzRepetition Rate 50 HzHigh speed chopper < 2 ns(rise & fall times)
Required for muon production
Required for flexibility and low loss in accumulator
Required for low loss in accumulator
HP-SPL: Beam CharacteristicsHP-SPL: Beam Characteristics
R. G. – 15/05/2012 7
Medium cryomodule
High cryomodules
Ejec
tion
9 x 6=0.65 cavities
11 x 8=1 cavities
13 x 8=1 cavitiesto
EURI
SOL
Debunchers
To H
P-PS
and
/or A
ccum
ulat
or
High cryomodules
From
Lin
ac4
0 m0.16 GeV
110 m0.73 GeV
291 m2.5 GeV
500 m5 GeV
Segmented cryogenics / separate cryo-line / room temperature quadrupoles:-Medium (0.65) – 3 cavities / cryomodule-High (1) – 8 cavities / cryomodule
Low energy
Intermediate energy
High energy
HP-SPL: Block DiagramHP-SPL: Block Diagram
R. G. – 15/05/2012 8
Medium Medium cryomodule cryomodule
High High cryomodule cryomodule
Energy range: 160 MeV – 732 MeV5 cell cavitiesGeometrical : 0.65Maximum energy gain: 19.4 MeV/m54 cavities (9 cryomodules)Length of medium section: ~110.35 m
Energy range: 732 MeV – 5 GeV5 cell cavitiesGeometrical : 1Maximum energy gain: 25 MeV/m192 cavities (24 cryomodules)Length of high section: ~360 m
Energy gain (MeV/m)
1
5
1
0
1
5
Position (m)
100 200 300 400
HP-SPL: Cavities & CromodulesHP-SPL: Cavities & Cromodules
Status and Plans of R&DStatus and Plans of R&D
R. G. – 15/05/2012 10
CavitiesCavities (1/4)(1/4)
R. G. – 15/05/2012 11
CavitiesCavities (2/4)(2/4)
R. G. – 15/05/2012 12
CavitiesCavities (3/4)(3/4)
R. G. – 15/05/2012 13
CavitiesCavities (4/4)(4/4)
R. G. – 15/05/2012 14
SPL coupler: requirementsSPL coupler: requirements
Technical Choices
Single window coupler
Fixed coupler
With a Double Walled Tube
Mounted in clean room with its double walled tube horizontally in only one operation
Vertically below the cavity and will be a support for the cavity (first time worldwide)
With a HV DC biasing capacitor
Air cooled
14
RF Characteristics
f0 704.4 MHz
Power levels
1000 kW pulsed0.4 + 1.2 + 0.4 = 2.0 ms50 Hz (20 ms)100 kW average
Cavity design gradient 19-25 MV/m
Qext of input coupler 1.2 x 106
Input line Ø 100 / 43.5 mm = 50 Ω(from the cavity design)
Waveguides WR 1150
R. G. – 15/05/2012 15
15
SPL coupler: 2 designsSPL coupler: 2 designs
LHC-derivedSPS-derived
Doubled-wall tube
Ceramicwindow
Air cooling
R. G. – 15/05/2012 16
SPL coupler: test assemblySPL coupler: test assembly
• Four ‘vacuum lines’:– 4 cylindrical window
couplers– 4 planar disk window
couplers– 8 Double walled Tubes– 4 test boxes
• DESY clean process assembly– (Jlab also proposed to help)
• CERN LLRF measurements
• CEA RF power tests– (BNL also proposed to help)
16
R. G. – 15/05/2012 17
• Test box assembly not easy because of specific surfaces roughness needed for helicoflex
• Couplers assembly was also not easy because :– Couplers are heavy– Last connection has to be
done manually– Ok for few prototypes, not
for a large series
SPL coupler: clean room assembly SPL coupler: clean room assembly (DESY)(DESY)
R. G. – 15/05/2012 18
• Tests started with cylindrical window couplers
• Not baked out, static vacuum~ 2 x 10 -7 mbar– Wanted to check RF– Size of the test box 250 mm x 600 mm– Helicoflex
• Pulse mode process
• Reached > 1MW – 25 Hz – 2 ms (limited by heating due to lack of Cu platting)
SPL coupler: RF high power tests SPL coupler: RF high power tests (CEA)(CEA)
R. G. – 15/05/2012 19
System/Component/Activity Person(s) in charge Lab
Cavities/He vessel/tuner construction O.Brunner, O.Capatina, Th.Renaglia, F.Pillon, N.Valverde, M.Esposito, I.Aviles,G.Devanz
CERN
CEA-Saclay
SRF, magnetic shielding, Clean-Room activities, RF test stations (SM18)
E.Ciapala, T.Junginger, K.Shirm, J.Chambrillon, O.Brunner
CERN
RF Coupler E.Montesinos, G.Devanz
CERNCEA Saclay
Vacuum systems G.Vandoni CERN
Cryogenics, (cryo infrastructure SM18) U.Wagner, (O.Pirotte) CERN
Survey and alignment P.Bestman CERN
Cryo-module conceptual design R.Bonomi, D.Caparros, O.Capatina, P.Coelho, V.Parma,Th.Renaglia, A.Vande Craen, L.R.Williams
CERN
Cryo-module detailed design & Integration & Cryostat assembly tooling
Ph.Dambre, P.Duthil, P.Duchesne, S.Rousselot, D.Reynet
CNRS/IPNO-Orsay
SPL Machine architecture F.Gerigk CERN
ESS Cryomodule developments Ch.Darve ESS, Lund
Cryo-module Technical Coordination V.Parma CERN
ESS/CERN Fellow
ESS/CERN Fellow
ESS/CERN Fellow
ESS/CERN Fellow
Short cryomodule: the actorsShort cryomodule: the actors
R. G. – 15/05/2012 20
Short cryomodule: schematic layout Short cryomodule: schematic layout
Connection to cryo distribution line
CW transition
RF coupler, bottom left sideCavity additional support
1.7% Slope (adjustable 0-2%)
Cryo fill line (Y), top left Technical Service Module
EndModule
Phase sep.
Inter-cavity supportNow suppressed
Now suppressed
R. G. – 15/05/2012 21
1054
1021
• General concept and dimensions (not latest design)
7400
SSS
Courtesy P.Duthil (IPNO)(views S.Rousselot, IPN-Orsay)
Transport,dressing and alignment frame
Short cryomodule: vacuum vesselShort cryomodule: vacuum vessel
R. G. – 15/05/2012 22
4.5 K vapor generatorreservoir (with elect.heater)
standard support
Last cavity IC support
Ph.Separator pot
DN80 gate valve (single valve)
CWT 50 K heat intercept
(views S.Rousselot, IPN-Orsay)
Short cryomodule: technical service Short cryomodule: technical service modulemodule
Courtesy P.Duthil (IPNO)
R. G. – 15/05/2012 23
Courtesy W. Hofle @ 5th SPL collaboration Meeting
D. Valuch
LLRF under developmentLLRF under development
R. G. – 15/05/2012 24
Upgraded installation in SM18Upgraded installation in SM18
R. G. – 15/05/2012 25
Delivery of 704 MHz klystron and modulator
Preparation of SM18 infrastructure (cryogenics, RF, clean-room)
Cavities production
Cavities processing/RF testing
RF couplers
Clean room assembly of string
Cryomodule (& assy tooling) design
Cryomodule fabrication
Cryomodule assembly
Start cryomodule RF testing
Short cryomodule: master scheduleShort cryomodule: master schedule
R. G. – 15/05/2012 26
Related R & DRelated R & D
Nb coating of Cu cavities, using the HIPIMS (High Power Nb coating of Cu cavities, using the HIPIMS (High Power Impulse Magnetron Sputtering) technologyImpulse Magnetron Sputtering) technology
– In collaboration with Sheffield Hallam University (UK).– Supported in the context of the construction of LHC spare cavities.– Potentially very attractive technology for the SPL (raw material cost, mechanical Potentially very attractive technology for the SPL (raw material cost, mechanical
stiffness).stiffness).– First results on low beta 704 MHz cavity: end 2012First results on low beta 704 MHz cavity: end 2012
SPL ApplicationsSPL Applicationsto Proton Driversto Proton Drivers
R. G. – 15/05/2012 28
• New High Power PS (30-50 GeV, 2MW beam power) using the Low Power SPL (LP-SPL) Low Power SPL (LP-SPL) as injector.
• Feasibility Study based on the work for SPL and PS2 supported within the LAGUNA-LBNO DS.
50 GeV synchrotron-based proton 50 GeV synchrotron-based proton driverdriver
Long baseline experiment (2300 km)CERN-Pyhasalmi (Finland)
R. G. – 15/05/2012 29
PS2 parameters: reminder…PS2 parameters: reminder…
Parameter unit PS2 PS
Injection energy kinetic GeV 4.0 1.4
Extraction energy kinetic GeV 20 - 50 13 - 25
Circumference m 1346 628
Max. bunch intensity LHC (25ns) ppb 4.0 x 1011 1.7 x 1011
Max. pulse intensity LHC (25ns) ppp 6.7 x 1013 1.2 x 1013
Max. pulse intensity FT ppp 1.0 x 1014 3.3 x 1013
Linear ramp rate T/s 1.5 2.2
Repetition time (50 GeV) s ~ 2.5 1.2/2.4
Max. stored energy kJ 800 70
Max. effective beam power kW 320 60
29
R. G. – 15/05/2012 30
PS2 integration at CERN: reminderPS2 integration at CERN: reminder
30PAC 2009 Vancouver PS2 Design Optimization, M.Benedikt
PS2
SPL
Linac4
SPL to PS2
PS
PS/LEIR to SPS / PS2
SPS
PS2 to SPS
– “Straight” H- inj. line SPL PS2 avoiding large bending radii to minimise Lorentz stripping of H-.
– Minimum length of inj. line TT10 PS2 for ions and protons from PS complex.
– Minimum length HE line PS2 SPS.
R. G. – 15/05/2012 31
SPL-based 5 GeV – 4 MW proton drivers have been designed [SPL + 2 fixed energy rings (accumulator & compressor)] which meet these requirements
References:– SPL based proton driver/ R. Garoby, talk at NuFact06,
http://nufact06.physics.uci.edu/Workshop/Slides/RGaroby_SPL3_Pdriver.ppt– Feasibility Study of Accumulator and Compressor for the 6-bunches SPL-based Proton Driver / M. Aiba,
CERN-AB-2008-060– A first analysis of 3-bunches and 1-bunch scenario for the SPL-based Proton Driver / M. Aiba, CERN-AB-
Note-2008-048-BI– Beam Stability in the SPL Proton Driver Accumulator for a Neutrino Factory at CERN / E. Benedetto,
http://nufact09.iit.edu/wg3/wg3_benedetto-splstability.ppt, to be published– SPL-based Proton Driver for a Neutrino Factory at CERN, M. Aiba, E. Benedetto, R. Garoby, M. Meddahi,
poster nb.25 (this workshop)
Parameter Basic value Range
Beam energy [GeV] 10 5 - 15
Burst repetition rate [Hz] 50 ?
Number of bunches per burst (n) 4 1 – 6 ?
Total duration of the burst [s] ~ 50 40 - 60
Time interval between bunches [s] (tint)
16 ~ 50/(n-1)
Bunch length [ns] 2 1 - 3
Specifications(from ISS report)
HP-SPL based proton driver: principle HP-SPL based proton driver: principle (1/2)(1/2)
R. G. – 15/05/2012 32
1. Beam accumulation– Accumulator ring
» Charge exchange injection» n x 100s accumulation time» Isochronous (=0): beam frozen longitudinally to preserve p/p » No RF (=> minimum impedance)» 1-6 bunches of ~120 ns length
2. Bunch compression- Compressor ring
» Large RF voltage (large stored energy & minimum RF power) (=> bunch rotation on stored energy)
» Large slippage factor => rapid phase rotation in few x10s, » ~2ns rms bunch length @ extraction to the target (=> moderate Q
because of dispersion)
• Synchronization between rings- Ratio of circumferences guaranteeing correct positioning of successive bunches inside the compressor without energy change in any ring
HP-SPL based proton driver: principle HP-SPL based proton driver: principle (2/2)(2/2)
R. G. – 15/05/2012 33
Accumulation Duration = 400 s
Compression t = 0 s
t = 12 s
t = 24 s
t = 36 s
etc. until t = 96 s
Accumulator[120 ns pulses
-60 ns gaps]
SPL beam[42 bunches -
21 gaps]Compressor
[120 ns bunch -V(h=3) = 4 MV]
Target[2 ns bunches
– 6 times]
Generation of 6 bunchesGeneration of 6 bunches
R. G. – 15/05/2012 34
-40 -20 0 20 40-2
-1
0
1
2
x' (
mra
d)
x (mm)
Injection Rotated
-10 -5 0 5 10-0.6
-0.4
-0.2
0.0
0.2
0.4
0.6 Injection Rotated
y' (
mra
d)
y (mm)
-40 -20 0 20 40-0.15
-0.10
-0.05
0.00
0.05
0.10
0.15 Injection Rotated
dE (
GeV
)
RF phase/3 (deg.)
-3 -2 -1 0 1 2 30
5
10
15
Cou
nts/
bin
(%, b
in=
0.2
deg)
RF phase/3 (deg)
Rotated=1.98 ns
from M. Aiba
Bunch rotation before ejectionBunch rotation before ejection
R. G. – 15/05/2012 35
SPL for proton driver Output beam Parameters Values Parameters Values
Kinetic beam energy 5 GeV Kinetic beam energy 5 GeV Repetition rate 50 Hz Repetition rate 50 Hz Average current during the burst 40 mA No. of bunches per cycle 6 Beam power 4 MW Bunch length (r.m.s.) ~2 ns Bunch spacing ~12 s
Transverse emittance (r.m.s., physical) 3 mm-mrad
Accumulator Compressor Parameters Values Parameters Values
Circumference 318.5 m Circumference 314.2 m Transition gamma 6.33 Transition gamma 2.3 RF voltage - RF voltage 4 MV Harmonics number - Harmonic number 3 No. of arc cells 24 No. of arc cells 6 Super periodicity 2 Super periodicity 2 Nominal transverse tune 7.77/ 7.67 Nominal transverse tune 10.79/5.77 No. of turns for accum. 400 No. of turns for comp. 36 Maximum no. of bunches 6 Maximum no. of bunches 3
Main quadrupole Bore radius Field gradient Magnetic length
56 mm 5.5 T/m 1.2 m
Main quadrupole Bore radius Field gradient Magnetic length
148 mm 7.1 T/m 1.9 m
Main bending Full gap Full width Field stength Magnetic length
103 mm 162 mm
1.7 T 1.5 m
Main bending Full gap Full width Field strength Magnetic length
125 mm 379 mm
5.1 T 3 m
from M. Aiba
Main parametersMain parameters
R. G. – 15/05/2012 36
K1
K2
D1
D2
D3
D4
T1
T2
T3
T4
p z
Beam delivery on 4 targets & hornsBeam delivery on 4 targets & horns
Principle:• Use of 2 bipolar kickers (or bipolar pulsed magnets): ± 45˚ rotation wrt the z axis• K1 (K2) deflects to D1 and D3 (D2 and D4)• Need of 1 compensating dipole per beam line (1 angle for each target):
Apply a symmetry in the system
keff
EL
B
2998.0
)sin(Angle of deflection (rad)
Kinetic energy(GeV)Magnetic length (m)
Magnetic field (T)2000mm
T1 T2
T4 T3
z
K1 K2
D1 D2
D3 D4
T1 T2
T3 T4
zp
3D view
side view
E. Bouquerel – IPHC, EUROnu meeting, March 27, 2012
>>KEY PARAMETER<<
SummarySummary
R. G. – 15/05/2012 38
Technology (1/2)Technology (1/2)
Presently, the HP-SPL R&D:Presently, the HP-SPL R&D:
•progresses at a good pace, leading to the high power test of a short 4 cavities cryomodule in 2014.•allows testing the validity of new concepts that should result in significant savings (RF couplers, SS He tanks, Cryomodule design…)•can potentially be used in multiple projects at CERN as well as outside (ESS, MYRRHA) and benefits from external support (ESS and EU programmes)•is a means for CERN to embed inside the network of labs involved in superconducting RF technology (CEA, IN2P3, DESY, JLAB, FNAL, ANL…) and re-establish in-house competence in that field at the state-of-the-art level•drives infrastructural upgrades (e.g. electro-polishing facility, clean room, high power RF at 704 MHz…) which will be beneficial for other development (LHC main RF, Crab cavities, HIE IDOLDE…)
R. G. – 15/05/2012 39
Technology (2/2)Technology (2/2)
Important future R&D subjectsImportant future R&D subjects
•HOM damper for beam stability at high current•Cavities in view of reaching the expected performance/simplifying fabrication/evaluating alternative solutions (Nb on Cu)•Cryomodule towards a full size prototype•RF amplifiers for reducing cost•Power supply for high power amplifier for reducing cost
R. G. – 15/05/2012 40
Accelerator designAccelerator design
• The SPL accelerator design is «mature» and stable
• In the context of the LAGUNA-LBNO:– The LP-SPL design will be adapted to the requirements of the HP-PS– The HP-SPL design will be briefly revisited and completed with the design of the
accumulation ring
• Other applications may require resuming/refining accelerator design:– e+/e- acceleration in the ERL of the Linac-Ring option of LHeC– LEP-3– LP-SPL remains a back-up option for the LHC injector complex…