    Implementation ofWeaker Sections Housing Programme

    byAndhra Pradesh State Housing Corporation

    Ltd

    (Status as on 30.11.10)

    Housing Department

    A P State Housing Corporation Limited, Hyderabad

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    2/45

    Implementation of Housing In Andhra Pradesh Government of AP has been according priority for providing

    Shelter to the poor .

    APSHCL is established in 1979 for taking up Rural

    Permanent Houses & Urban Permanent Houses besides

    Centrally Sponsored Schemes.

    State Sponsored Schemes

    INDIRAMMA Rural Housing

    INDIRAMMA Urban Housing

    Centrally Sponsored Schemes

    Indira Awaas Yojana

    Housing for Weavers, Fishermen, Beedi Workers

    JnNURM (BSUP & IHSDP) Schemes in Urban areas

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    3/45

    G M (Admn) CGM

    Organization Chart

    Managing Director

    Executive Director

    SOCGM CE

    Managing Director

    Executive Director

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    4/45

    District Collector / Executive Director

    Project Director

    EE (Revenue Division)

    DEE

    (Erstwhile Block)

    AE (per Mandal)

    WI

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    5/45

    Total Houses Constructed(as on 30.11.2010)

    Rural 90.58 lakhs

    Urban 7.87 lakhs

    Houses constructed

    up to 2004-05 52.65 Lakhs

    after 2004-05 45.80 Lakhs

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    6/45

    INDIRAMMA HousingIntegrated Novel Development In Rural Areas & Model Municipal Areas

    Launched in 2006 as a 3 yearprogramme

    1/3rd of State to be coveredeach year

    Saturation approach Drive for a hut free, slum free

    State

    In 60,000 habitations andurban wards

    Allocation of Rs. 5,000 Cr peryear through State budget upto 2008-09

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    7/45

    Eligibility Criteria

    Beneficiary living in kutcha houses as a single family.

    Beneficiary living in kutcha houses as a member of joint family. Beneficiary living as a single family in fully dilapidated Semi-

    Permanent House constructed with government assistance before1993-94.

    Beneficiary living as a member of joint family in fully dilapidated Semi-Permanent House constructed with government assistance before

    1993-94 Beneficiary living as a single family in fully dilapidated, own Semi-

    Permanent House constructed without any government assistance. Beneficiary living as a member of joint family in fully dilapidated, own

    Semi-Permanent House constructed without any governmentassistance.

    BPL Families living in rented accommodation in urban areas. Beneficiary living as a member of joint family in Rural Permanent

    Housing or Urban Permanent Housing Colonies constructed withgovernment assistance during the earlier years.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    8/45

    Over all Physical progress at a glance(as on 30.11.2010)

    Registered: 64.21 lakhs

    Completed: 33.24 lakhs

    Under progress: 13.62 lakhs

    BBL 1.56 lakhs

    BL 4.49 lakhs

    LL 2.39 lakhs

    RL 5.18 lakhs 7.57 Lakhs

    Not started: 17.35 lakhs Over all Expenditure

    under INDIRAMMA: Rs. 12,389 Cr

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    9/45

    Financial Pattern: Rural and Urban Permanent Housing

    (RPH & UPH)

    Unit Cost: RPH UPH

    GOAP Loan: Rs.17,500/- Rs 35,000/-GOAP Subsidy: Rs.13,200/- Rs 6,000/-Beneficiary Contribution: Rs. 500/- Rs 2,000/-Sub-Total Rs.31,200/- Rs 43,000/-

    Bath cum Toilet: Rs. 3,050/- ---Addl Loan: Rs.20,000/- Rs 30,000/-

    Grand Total: Rs.54,250 Rs 73,000/-

    Addl loan in respect of SC/ST beneficiaries provided as Govtloan.

    Rest Bridge Loan/Bank Loan.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    10/45

    Payment (per house Rs)

    Rural Urban

    Cement 50 bags 7,500 7,500

    Payment 26,750 35,500

    Supplementation 20,000 30,000

    Total 54,250 73,000

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    11/45

    INDIRAMMA - Stage wise Payments

    Stage Rural Urban

    Below Basement Level (BBL) 1500 1500

    Basement Level (BL) 8300 10600

    Lintel Level (LL) 6000 10000

    Roof Level (RL) 10400 17600Roof Caste (RC) 5000 3300

    Completion 3050 0

    Total 34,250 43,000

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    12/45

    (3.35M)

    (6.32 M)

    (3.65M X 2.9M)(2.1M X 2.9M)

    (1.9M X 1.1M)

    6'3"X3'6"

    7'0" X 9'6"

    BATH & WC

    ROOM MULTIPURPOSE ROOM

    PLAN

    12'0" X 9'6"

    D1

    D

    D1

    OA A'

    2.25M

    1.275M

    Type Design for Rural and Urban

    Evolved & adopted tworoomed pucca house withmultipurpose room,Kitchen and Bath cum WC

    The plan has provision forfuture expansion.

    Different type designs arebeing adopted depending

    upon the local conditions. Plinth area is ranging

    between 20 and 25 Sqm.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    13/45

    E-governance for total transparency

    All details in the public domain to maintain totaltransparency

    The execution, payment and monitoring of more than 60lakh houses done through:

    E- Governance system that

    Facilitates making payment

    Internet banking system

    Monitors house-wise progress

    Follows up complaints

    All details in the public domain to maintain totaltransparency

    Rs 12,389 Cr transferred to people using thise-governance system up to 30.11.2010

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    14/45

    IAY -2010-11

    GOI have enhanced the unit cost of house under IAY programmefrom Rs. 35,000/- to Rs. 45,000/-. (Central share - Rs 33,750/- and

    the State share - Rs. 11,250/-) Financial performance (Rs in Cr)

    Opening Balance 8.75

    Funds allocated to the State 1156.97

    Funds released ( CS- 433.86+ S.S-144.62 ) 578.48 Total available funds (including OB & state share) 587.24

    Funds utilized during the year 520.15

    Physical Performance:

    Annual physical target 2,57,104

    Houses completed

    SCs/STs 125725

    Minorities 3850

    Total 129575

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    15/45

    Additional amount for SC / ST beneficiaries

    SC/ST Beneficiaries - Permission accorded foradditional amount of Rs 20,000/- in Rural and Rs30,000/- in Urban areas

    SC/ST houses completed after issue of G.Os with

    additional loan (as on 21.11.2010)1 Phase I 1,49,783 30.11.2008 to till date

    2 Phase II 97,157 15.01.2010 to till date

    3 Phase III 98,547 15.01.2010 to till date

    Total 3,45,487

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    16/45

    Implementation strategy - Disbursement system

    AE visits all villages himself personally once a fortnight as per a pre-drawnProgramme. Fixed day in each village every fortnight.

    (No public contact for the outsourced staff)

    AE conducts verification of houses and records M Book.Announces the list/amount payable in the open.

    Dy EE cross checks at least 10% of M Books and confirms. There after,PDs confirm payment online.

    Beneficiaries Meeting.List and entitlements read out in open.

    Disbursement only through individual accounts. Transition period of 45 dayPay slips distributed in the village by AE.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    17/45

    Changes brought-in, to improve the deliverysystem in the implementation of INDIRAMMA

    Housing

    Payments only through individual accounts. Beneficiaries are givenoption to open their account either in bank or post office dependingupon their convenience.

    VO payments dispensed from December 2009.

    To make the system very transparent and make the beneficiaries aware

    of their total eligibility of amount and materials actually issued, apassbook with all the details have been given to each beneficiary.

    Pay slips are being given to beneficiaries for each payment.

    Fortnightly fixed tour programme by AEs.

    Payments released by the DEE, directly to the beneficiary account.

    24 Hour Call Centre with Toll Free No 1100 for Complaint Redressal.

    Established Monitoring Unit (SMU) for dealing exclusively with all thecases related to irregularities brought to the notice through call centre /Newspaper/ any other form.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    18/45

    Due to introduction of above steps the number of

    complaints have come down substantially.

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10

    739

    1736

    764

    499

    429

    279

    187 195 208 186

    112 120 9976 92 80 72

    TOTAL COMPLAINTS

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    19/45

    Budget Allocation and Releases during the year 2010-11

    State Budget Allocation (for schemes) Rs 1340.00 Cr

    Releases made so far

    1st & 2nd Qtr Rs 707.64 Cr

    Amount pending adjustment Rs 135.10 CrNet Amount adjusted to APSHCL a/c Rs 572.84 Cr

    BROs issued but not released for 3rd Qtr Rs 295.31 Cr

    GoI Allocation for IAY 2010-11Allocation Rs 867.73 Cr

    Released so far (50%) Rs 433.86 Cr

    Balance to be released Rs 433.87 Cr

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    20/45

    2010 - 11 - Targets and Achievements(Up to 30.11.2010)

    3.24 lakh houses completed (Target : 6.92 lakhs and

    Proportionate Target : 4.61 lakhs )

    Expenditure : Rs 1112.36 Crs

    1,54,818 SC/ST houses completed (Target : 2,18,540 Houses and

    Proportionate Target 1,45,693 Houses )

    Houses under Progress as on 30.11.2010 13.62 Lakhs Houses at RL/LL level 7.57 Lakhs

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    21/45

    2010 -11 - Balance houses as on 30.11.2010(Houses in Lakhs)

    Stage as on1.4.2010

    as on30.11.2010

    Roof Level 5.80 5.17

    Lintel Level 2.77 2.39

    Basement Level 5.23 4.49

    Below BasementLevel 1.86 1.56

    Not Started 18.81 17.35

    Houses Completed in 8 months 3.24 Lakhs

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    22/45

    Houseless families who do not

    possess site for construction areprovided with house sites inGovernment land or in landsacquired under Social WelfareDepartment Budget.

    14,09,599 beneficiariesbelonging to the above Categorywere identified in INDIRAMMASurveys.

    Government decided to provide

    basic infrastructural facilitiesi.e approach road, internal roads,water and Electrification fortaking up of construction in newlayouts / Relocation colonies.

    INDIRAMMA Infrastructure

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    23/45

    Infrastructure contd.,

    Government sanctioned Rs.429.99 Crores from out of the Budget allocated forINDIRAMMA Housing to provide the above basic infrastructural facilities innew layouts / Relocation colonies.

    A total of 10410 works have been sanctioned in 5786 layouts at district level.The physical progress of the above works is as follows:

    100 % completion -- 6,058 works

    75 % completion -- 493 works

    50 % completion -- 521 works

    25 % completion -- 315 works

    Just Grounded -- 884 works

    Not started -- 2,139 works

    10,410 works

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    24/45

    Cement

    160 lakh MTs of cement is approximately required forabout 65 lakh houses.

    Negotiations with cement companies were held at thehighest level in the Government i.e Honble ChiefMinister/Honble Minister and the rates were approvedfor WSHP.

    The Present rates of procurement is as follows: SKLM,VZM Rs155.50 per bag VSP,CTR Rs153.50 per bag KMM,NLG Rs133.50 per bag

    EG Rs143.50 per bag NLR Rs148.50 per bag KNL,ATP and KDP Rs145.00 per bag Other districts Rs145.00 per bag

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    25/45

    Additional Proposals

    Government have issued orders vide

    G O Rt No 171 Housing (RH A1) Dept,

    Dt 6.7.2010, to send proposals for considering

    sanction in respect of houses which were startedbefore last General Elections without anysanction.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    26/45

    Proposals submitted to Govtin accordance with G O 171.

    4.71 lakh houses are proposed.

    Of these, 3.72 lakh houses are at BBL to RL,

    1 lakh houses are at RC.

    Includes 1.63 lakh SC/ST houses.

    Beneficiaries details placed in the housing

    website.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    27/45

    Financial requirement for 4.71 lakh houses

    Rs 1853 Cr for 4.71 lakh houses

    Rs 768 Cr is requirement as per the presentstages

    Rs 130 Cr is required from RWS Dept

    towards ISL amount

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    28/45

    Instructions given to District Collectors

    To scrutinise the lists with other data bases under the supervision ofAddl Joint Collector in-charge of Housing with respect to G O 171guidelines

    ration card numbers are not repeated in the list now submitted

    beneficiaries under INDIRAMMA three phases are not covered

    againensure that the ration card number is a valid white ration card as

    per Civil Supplies Depts key register data

    In 9 districts, (VSP, EG, PKM, CTR, KNL, MBNR, MDK, ADL , WGL)

    the lists are more than 20,000 and are requested to be appropriatelyre-verified to ensure only eligible are covered.

    Submit soft copy lists for RC houses in SKL,VZM,GNT,YSR,ANTPand balance lists in NLG, MBNR, ADL and KMM.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    29/45

    Integrated Survey

    Government have taken up integrated Survey of individualbenefit schemes of Ration Cards, Pensions and Housing.

    The Survey is undertaken by Civil Supplies Department.

    Housing beneficiaries data of 64.42 lakhs was sent for

    survey, out of which, 12.60 lakhs Housing beneficiariesidentified as doubtful during preliminary survey.

    Their details have been placed before Gram Sabha.

    District Collectors have furnished the final list of ineligible

    beneficiaries after verification of the details in the Grama Sabha.

    Final lists of ineligible beneficiaries received from all districtsand disabled.

    Fi l i d f C ll d

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    30/45

    Final reports received from Collectors andBeneficiary data blocked

    Sl.No

    District Number of doubtfulbeneficiaries as per

    Preliminary Survey

    Final number of beneficiaries blockedIneligible Still pending as

    doubtful

    Total data

    blocked1 Srikakulam 45019 2320 28045 303652 Vizianagaram 61148 7411 0 74113 Visakhapatnam 89826 30562 0 305624 East Godavari 53500 8427 0 84275 West Godavari 41801 17652 0 176526 Krishna 23969 6206 0 62067 Guntur 29467 12930 0 12930

    8 Prakasam 65484 25631 0 256319 SPSR Nellore 49481 19138 0 1913810 Chittoor 83273 17013 18633 3564611 Kadapa 49605 11506 0 1150612 Anantapur 129547 32736 0 3273613 Kurnool 84317 33285 4290 3757514 Mahabubnagar 123788 14204 37480 51684

    15 Ranga Reddy 38907 6627 0 662716 Medak 57133 4723 29772 3449517 Nizamabad 18189 4073 0 407318 Adilabad 30593 4277 13517 1779419 Karimnagar 22821 7182 0 718220 Warangal 84623 8466 14877 2334321 Khammam 39775 4468 0 446822 Nalgonda 37859 8318 0 8318

    Total 1260125 287155 146614 433769

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    31/45

    Instructions issued to District Collectors/PDs

    To initiate the process for recovery of amount mis-utilised in respect of the ineligible beneficiaries, asper the directions issued in G.O Rt No. 266

    Dt. 19.12.2009.

    Time frame to be fixed for recovery of the amount.

    To issue cancellation orders in respect of all ineligiblebeneficiaries as per the orders issued vide

    G O Rt No 266 dt. 19.12.2009

    To furnish proposal for deletion of not started houses,as the beneficiaries are confirmed as ineligible.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    32/45

    INDIRAMMA URBAN HOUSINGin small towns

    Houses considered under INDIRAMMA 5,09,234

    Ph-I 1,46,078

    Ph-II 1,98,390

    Ph- III 1,64,766

    Houses taken up in Layouts : 2,97,006

    No of Colonies : 359

    Houses tagged to IHSDP 36,753

    Municipalities 26 (47 colonies)

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    33/45

    JnNURM HOUSING

    Govt of India have sanctioned Housing andinfrastructure projects for improvement ofSlums in the selected cities and towns

    with the financial participation of State Govt andhe Local bodies.

    Housing in Mission Cities of Hyderabad,Visakhapatnam and Vijayawada is coveredunder Basic Services for Urban Poor (BSUP)

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    34/45

    Government of India has sanctioned 1,31,321 houses in the 3 cities. The

    concerned Municipal Corporations are executing the programme and part of

    the programme (10,255 houses) in Vijayawada and Visakhapatnam are

    executed by APSHCL

    Hyderabad 78,746 by GHMC

    Vijayawada 27,000 by VMC1,152 by APSHCL

    Visakhapatnam 15,320 by GVMC9,103 by APSHCL

    Financing Pattern is GOI - 50%, GOAP - 30% & ULB - 20%.

    Dwelling Unit cost at Visakhapatnam is Rs 1.96 lakhsat Vijayawada is Rs 1.60 lakhs

    JnNURM BSUP - In Mission Cities

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    35/45

    JnNURM- BSUP

    No of houses

    sanctioned

    Houses

    completed

    Houses in

    progress

    Cost of

    Infrastructure Rs inCrs in thecolonies(underprogress)

    Visakhapatnam 9,103 7,536 1,567 50.98

    Vijayawada 1,152 1,056 96 Being doneby VMC

    Total 10, 255 8,592 1,663 50.98

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    36/45

    Govt have sanctioned 36,753 houses along with

    Infrastructure for 30 projects in 26 Municipalities in 2Phases. The financing Pattern is, GOI 80%, GOAP 10%& ULB 10%. The Unit cost of the dwelling Unit is @Rs40,00o/- and 80,000/- in case of independent houses

    and Rs 1.31 lakhs to Rs 2.00 lakhs for G+ housesdepending upon the site conditions.

    10 projects in 7 municipalities where land is scarce are

    taken up in G+ pattern through Contractors/Deptexecution and in the balance 19 municipalities housesare taken up in Independent pattern throughbeneficiaries.

    JnNURM- IHSDP

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    37/45

    JnNURM- IHSDP

    No ofhousessanctioned

    Housescompleted Houses inprogress Cost ofInfrastructureRs in Crs inthe colonies

    (underprogress)

    Phase-I25 projects

    25,170 19,075 6,095 86.99

    Phase-II5 projects

    11,583 2,056 9,527 31.62

    Total 36,753 21,131 15,622 118.61

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    38/45

    RAJIV AWAAS YOJANA

    The Government of India has launched Rajiv AwasYojana (RAY), which envisage making India Slum-free by 2014.It aims to upgrade housing and civic infrastructure

    for the settlement of the poor in urban areas, andmake adequate urban land households in the urbanareas.

    Slum-free Plan of Action There are 125 ULBs in the State including

    Secunderabad Cantonment Board (SCB). The Statehas proposed to take up 25ULBs during 2010-11, 63ULBs in 2011-12 and 37 ULBs in 2012-13.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    39/45

    Flood Housing - Introduction

    Heavy rains and floods in Krishna

    & Tungabhadra rivers occurred duringSeptember/ October 2009.

    Temporary Shelters provided - 19,810

    Kurnool 9,988Mahabubnagar 9,822

    Proposed to relocate families from severely

    affected villages duly acquiring land.

    Insitu up gradation is permitted where ever landis suitable for living.

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    40/45

    Permanent Housing

    Unit Cost Rs. 68,450/-

    Govt. of India Subsidy (IAY)Rs.26,500/-

    Govt. of AP Subsidy (IAY+INDIRAMMA ) Rs.21,700/-

    Govt. of AP Loan (INDIRAMMA ) Rs.17,500/-

    Toilet ( PR Dept) Rs. 2,750/-

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    41/45

    Status of land acquisition

    DistrictColonies

    beingRelocated

    No. of plotsin the

    layouts

    Amountreleased in

    Crores

    Kurnool 27 10472 17.29

    Mahabubnagar 10 5930 10.07

    Krishna 1 0 0.55

    Guntur 1 0 0.08

    Total: 39 16402 27.99

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    42/45

    Status of Relocation

    Work commenced

    No. of Colonies 34 No. of Houses 9,374 Houses Completed 965 Houses in progress 4,353

    Targeted to be completed by Dec-2010 Work being commenced (Rajole): 01 Work to be commenced : 04(Thimmanadoddi, Mamidalapadu- Kurnool District - Land Acquisition

    problemThotlavallur, Krishna Districtand KV Palem, Guntur District - Land yet to be handed

    over

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    43/45

    Progress on Flood Housing

    Category/District

    TAKENUP

    COMPLETED

    Progress of Houses

    BBL BL LL RLNS to

    beStarted

    RELOCATION

    KURNOOL 7695 855 1744 1014 349 345 3388MAHABOOBNAGAR

    1679 110 519 236 96 50 668

    TOTAL: 9374 965 2263 1250 445 395 4056

    INSITU

    KURNOOL 12240 1177 1516 1405 1094 942 6106MAHABOOBNAGAR

    3259 22 181 273 142 110 2531

    KRISHNA 1189 212 70 206 160 141 400

    GUNTUR 530 216 47 40 53 57 117

    TOTAL: 17218 1627 1814 1924 1449 1250 9154

  • 8/3/2019 New Microsoft Office Power Point Presentation 3011

    44/45

    Infrastructure Facilities sanctioned

    Amount Sanctioned by the APSHCL

    Approach Roads : Rs. 24.60 lakhs

    Water Supply : Rs.142.40 lakhs

    Electrification : Rs.390.85 lakhs

    T O T A L : Rs.557.85 lakhs

    Amount sanctioned by other Departments

    Approach & Internal Roads : Rs.364.10 lakhs

    Water Supply : Rs.195.50 lakhsT O T A L : Rs.559.60 lakhs

    Grand Total : Rs.1117.45 lakhs