Mollie MahoneyProject Manager20 June 2019
NEW SOO LOCK QUARTERLY UPDATE STAKEHOLDERS
2
AGENDA
1. Soo Locks Overview
2. Maintenance of Existing Facility
3. Schedule
4. Cost
5. Upstream Channel Deepening
6. Upstream Approach Walls
7. New Lock Chamber
SOO LOCKS LOCATION & IMPORTANCE 3
Soo Locks
The New Soo Lock would eliminate the single point of failure in our Nation’s iron ore supply chain
Routine O&M $8M - $15M annually
MAINTAINING EXISTING SOO LOCK
02468
101214161820
FY08 FY10 FY12 FY14 FY16 FY18
Asset Renewal Routine O&M
Funding, $M
Major Rehabilitation Construction
Asset Renewal Plan Maximize reliability and reduce risk $75M of $190M remaining for:
• Poe Lock Gate 1 Replacement• Poe Gate 4 anchorages• Center Dike Rehab• Emergency Power System
Dav
is L
ock
(Inac
tive)
Sabi
n Lo
ck (I
nact
ive)
Poe Stop Logs
Mac Tainter Valve Machinery
Davis & Poe Pump Wells
Poe Ship Arrestors
NEW SOO LOCK PROPOSED PROJECT CONDITION 5
Sabin (Inactive)
New lock will have same dimensions as existing Poe Lock (1200 ft. length by 110 ft. width and a depth of 32 ft.)
Existing Proposed
Major Milestones in Last 12 Months• June 2018 – Economic Validation Study completed establishing new benefit cost ratio of 2.42• Oct 2018 - WRDA 2018 increased authorized cost $1.03B• Nov 2018 – Funds for New Soo Lock construction included in FY19 Work Plan• Dec 2018 – State of Michigan provided $52M to New Soo Lock• Mar 2019 – New Soo Lock included in FY20 PBud Request
NEW SOO LOCK CONSTRUCTION PHASES
Upstream Channel
Deepening
Design
Contract Procurement
Construction
FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30
*
* Early completion could be realized with efficient funding and favorable weather conditions
Completed Work: Downstream Deepening & Sabin Lock Cofferdam
Remaining Work:
Upstream Approach
Walls
New Lock Chamber
Phase 1
Phase 2
Phase 3
NEW SOO LOCK FUNDING HISTORY AND CAPABILITIESFiscal Year
Allocation/ (Capability)
Activities Funded/Capabilities
Prior to 2018 $32.0M
• Design and planning efforts• Downstream Channel Deepening construction completed• Sabin Lock Cofferdam construction completed
2019$69.2M
$32.3MFed$36.9M State of
MI
• Upstream Channel Deepening: complete design & award construction contract
• Upstream Approach Walls: complete design• New Lock Chamber: resume design
2020($89.7M)*
$75.3M in PbudRequest
• Upstream Channel Deepening: complete and manage construction• Upstream Approach Walls: complete design, AOA, award and manage
construction contract • New Lock: continue design $14.4M remaining capability identified in fiscal year 2020
2021 ($173.1M) *• Upstream Channel Deepening – manage construction• Upstream Approach Walls – complete and manage construction• New Lock - complete design and advertise construction contract
2022 ($129.3M)*• Upstream Approach Walls – manage construction • New Lock – year 2 of construction contract
2023-2028 ($536.4M) * • New Lock - Manage and complete construction
7
Remaining $15M in State of MI Funds to be used for future needs*Fully funded costs escalated through midpoint of construction
8
Channel Deepening LimitsBedrock & Overburden Removal LimitsOverburden Removal LimitsMaterial Placement Area
NEW SOO LOCK UPSTREAM CHANNEL DEEPENING
Scope: Deepen upstream approach channel to depth of 30 feetSolicitation Number: W911XK-19-B-0004Design Status: In Progress – Advertisement expected in July 2019Construction Status: Construction award expected in Sep 2019 ($4.946M included in FY20 Pbud Request to complete and manage construction)Total Project Cost: $68M
9NEW SOO LOCK UPSTREAM CHANNEL DEEPENING
• Channel to be deepened to 30’ + 1’ Allowable Over depth• 200,000 CY – 300,000 CY bedrock removal • 100,000 CY of overburden material removal
REQ’D OVERDEPTH (-30’ LWD)
ALLOWABLEOVERDEPTH (-31’ LWD)
REQUIRED DEEPENING(-29’ LWD)
NEW SOO LOCK UPSTREAM CHANNEL DEEPENING 10
Jacobsville Sandstone removed during downstream channel deepening
NEW SOO LOCK UPSTREAM CHANNEL DEEPENING CONTRACTOR ENGAGEMENT
11
• Upstream Channel Deepening Industry Day was held on site on 1 May 2019
• Upstream Channel Deepening Pre-Bid Conference will be held on 9 July 2019 in Sault Ste Marie
12NEW SOO LOCK UPSTREAM APPROACH WALLS
New 34 ft diameter Circular SSP CellsNew SSP FacingExisting Wall Treatment is TBD
Scope: Rehabilitate approach walls upstream of New Soo Lock-Install 1,900’ of 34’ diameter SSP Cells-Install 2,600’ of SSP facing-1,500’ of existing wall to be stabilized-Install new mooring bollards
Design Status: In Progress (funded by State of MI)Construction Status: Funding Capability Identified in FY20 Budget ($62.03M of $74.9M capability included in FY20 Pbud Request)Total Project Cost: $83M Estimated Performance Period: 24 Months
NEW SOO LOCK UPSTREAM APPROACH WALLS 13
Majority of Existing Approach Wall over 100 years old and in need of rehabilitation
NEW SOO LOCK UPSTREAM APPROACH WALLS 14
NEW SOO LOCK UPSTREAM APPROACH WALL CONTRACTOR ENGAGEMENT
• Industry Day will be held for the Upstream Approach Wall contract on 8 July 2019 in Sault Ste. Marie, MI.
• Contractors will have opportunity to ask questions about draft contract documents and visit the project site
NEW SOO LOCK UPSTREAM APPROACH WALL INDUSTRY ENGAGEMENT
• New Soo Lock Ship Simulation Study was held on May 7-10 at USACE’s Engineering Research and Development Center
• Vessel Captains navigated upstream and downstream approaches to the New Soo Lock to evaluate approach wall design scenarios
NEW SOO LOCK CHAMBER 17
New Lock Chamber Contract Construction Limits
Scope: Construct new 1,200’ long by 110’ wide by 32’ deep chamber and rehabilitate downstream approach wallsDesign Status: In Progress ($8.355M included in FY20 Pbud Req)Construction Status: Funding capability identified in FY21 BudgetTotal Project Cost: $848M Estimated Performance Period: 5-8 Years
18NEW SOO LOCK CHAMBER
SOO LOCKS PROJECTS UPCOMING DATES:• Upstream Channel Deepening Contract Advertisement: 03 Jul 19• Upstream Approach Walls Industry Day: 8 Jul 19• Upstream Channel Deepening Pre-Bid Conference: 9 Jul 19• Soo Locks Facility Steam Plant Advertisement: 05 Aug 19• Upstream Channel Deepening Contract Award: Sep 2019• New Soo Lock Fiscal Year 20 1st Quarter Update: 03 Oct 19
19
CONTACT INFO:Mollie Mahoney, Project Manager, (313) 226-2033