NEW YORK STATE DEPARTMENT OF
TRANSPORTATIONRoute 146 Over the Mohawk River
Design-Build ProjectPIN 1085.42, Contract No. D900026
Town of Niskayuna, Schenectady CountyTown of Clifton Park, Saratoga County
RFP Informational Meeting
December 30, 2014
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42)Agenda
Project Overview Department’s Goals and Project Requirements Scope of Work Status of ROW and Utilities General Contract Information Alternative Technical Concepts Procurement Schedule One On One Meetings RFP Content Quality Control & Quality Assurance Evaluation and Selection Additional Information and Submission Guidelines Questions and Answers
2
Peter RussellAttn: SR 146 Over the Mohawk River
Design-Build ProjectOffice of Contract Management
New York State Department of Transportation50 Wolf Road, 6th Floor
Albany, New York 12232, [email protected]
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Rules of Contact
3
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) General Location
Route 146:
RM146-1603-3038 to RM 146-1504-1005BIN: 4-03836-0
Aqueduct Road to Riverview Road Town of Niskayuna, Schenectady County
Town of Clifton Park, Saratoga County0.7 Mi. Length
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Goals
Ensure a long-service life for all Project elements to satisfy long term preservation goals
Ensure the safety of the travelling public Maximize the benefit of the public investment
in the Project by: Providing cost-effective solutions that maximize value over
the lifespan of the bridge and approach roadway Sequencing construction to minimize effects on vehicular
traffic operations Reducing future maintenance requirements Minimizing impacts on the environment
5
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Goals (Continued)
Deliver the Project safely, on schedule and within budget
Ensure coordination with utility owners, third parties, Project stakeholders and any adjacent construction projects
Provide Best Value to the Department
6
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) General Scope of Work
Design and construct the replacement bridge over the Mohawk River
Design and construct the intersections of Route 146 with Aqueduct Road and Riverview Road
Design and construct/rehabilitate Route 146 between the intersections with four through travel lanes
Design and construct a multi-use path between Riverview Road and the Mohawk-Hudson Bike-Hike Trail
Maintain vehicular and pedestrian traffic on site throughout construction Canal/river navigation traffic must also be maintained
7
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) General Scope of Work (Continued)
Demolish existing structure and foundations Relocate and/or preserve existing utilities Perform public outreach and coordination with local
agencies (in coordination with NYSDOT) Coordinate with NYS Canal Corporation and NYS Office
of Parks Recreation and Historic Preservation Comply with existing environmental constraints:
Threatened and endangered species Historic Properties Wetlands
Acquire necessary permits (in coordination with NYSDOT)
8
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Indicative Plans
Indicative Plans represent the nature and type of work to be designed and constructed as part of the Project. They reflect items for which the Department has no particular view on specific configuration or Material used in the final product.
For this project, they include the following: Typical Sections Plan Sheets Profile Sheets
9
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Indicative Plans (Typical Sections)
10
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Indicative Plans (Typical Sections)
11
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Environmental Considerations
Issue Comments Wetlands Wetlands adjacent to Route 146 - Impacts
requiring mitigation are not expected. Surface Waters Mohawk River & Unnamed Perennial
Streams - All Designated Class A Streams; No In- stream Seasonal Work Restrictions; USACE
and Individual 401 WQC Stormwater Management SPDES permit > 1 acre disturbance
requires a Stormwater Pollution Prevention Plan
Ecology/Wildlife No Effect – Federal Endangered Species (FHWA Concurrence)
Cultural Resources NYSDOT has entered into a Programmatic Agreement (PA) with FHWA and SHPO. PA has detailed stipulations.
Asbestos/Hazardous Materials Testing Completed in Nov 2014. Bridge sheet packing material tested positive for ACM’s.
25
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Environmental Considerations (Continued)
Anticipated Permits/Authorizations Needed:USCG Bridge PermitUSACE Section 404/Section 10NYSDEC Section 401 Water Quality CertificationNYSDEC SPDES General Permit GP-0-10-001
No NYSDOT InvolvementNYSOPRHP Construction Use PermitCanal Corporation Use and Occupancy PermitFHWA EO 11990 Individual Wetland Finding
26
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Right of Way
All additional Right of Way required for the construction of the project has been acquired. ROW Maps will be included in Part 7 of the
Final RFP.
27
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Utility Coordination
In accordance with Part 4 – Utility Requirements, Design-Builder is responsible for: Verifying utility locations Indentifying and resolving any conflicts not yet
documented Coordinating with utility owners for utility
relocations Providing stakeout and final layout of utility
relocations Protecting existing utilities Repairing damages to utilities caused by the
Design-Builder
28
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Utility Coordination (Continued)
Informing the Department of all meetings and correspondence with utility owners
Known utilities located in the Project area: National Grid (Electric) Verizon Communications Time Warner Cable Town of Niskayuna Water Department Clifton Park Water Authority Fibertech
29
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Utility Coordination (Continued)
Impact on the utilities is dependent on the approach taken by the Design-Builder.
A meeting will be scheduled in the next two weeks between the utilities and the shortlisted firms. The Department will invite the shortlisted firms and the utilities within the project limits to this meeting.
30
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Contract Information
Lump Sum Design-Build Contract Best Value Selection Process (50% Price, 50%
Quality) Project Completion Date shall be the earlier of:
December 31, 2017 or The number of days past NTP proposed by the successful
Proposer on Form SCD in ITP Appendix E
Stipend to unsuccessful proposers – 50% of qualified costs up to $90K max. (Must satisfy criteria in ITP General Instructions)
Payment Schedule included in the RFP
31
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Contract Information (Continued)
32
(1) Percent of Lump Sum Price to be completed by Proposer. Total percent for all Work Items shall equal 100%
(2) Intersections and roadways shall, for purposes of payment, be considered complete when built to binder course pavement. Final top course pavement and final striping shall be paid for under Construct Final Top Course Pavement, Signage and Striping.
(3) Aqueduct Road intersection drainage shall, for purposes of payment, be considered complete when drainage structures and associated piping are installed. Payment for setting inlet frames and grates to finish grade shall be paid for under Construct Final Top Course Pavement, Signage and Striping.
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Contract Information (Continued)
DBE Participation Goal – 12% Special Provision 6 –
Liquidated Damages will be imposed for not meeting the Project completion date and for days in excess of the number of calendar days indicated to complete the milestones shown on Form SCD.
Escrow Submission of Bid Documents for Successful Proposer
Buy America Clause Iran Divestment Act Clause
33
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) ATCs
Alternate Technical Concepts (ATCs) are proposals from the Proposer to design and construct the Project in a manner that is different than the Contract Requirements and which: are submitted to the Department for review,
consideration and approval prior to Proposal submittal have significant savings in time, and/or reduction of
traffic impacts, and/or community disruption, and/or project costs, and/or environmental impacts, and/or other beneficial impacts to Project parameters
are , in the Department’s judgment, equal to or better than the Work product described in the Contract Documents.
34
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) ATCs (Continued)
Proposers may submit, on a confidential basis, up to three (3) ATCs, using Form ATC, for the Department’s pre-approval.
The proposed end product of each alternative must, in the Department’s judgment, be equal to or better than the Work product described in the Contract Documents.
Department may provide ‘Conditional Approval’ of an ATC. Proposers must respond to Conditional Approvals by the established date.
The Design-Builder is solely responsible for obtaining approvals from any local municipality, public agency or permit-issuing agency for ATC concepts which would affect their facilities, operations or issued permit.
35
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Procurement Schedule (*These dates will be reflected in the Final RFP)
Activity Due Date *Final RFP to Shortlisted Firms January 22, 2015
Date Proposers may start submitting ATCs for review January 23, 2015
Proposal period One-on-One Meetings with all ProposersFebruary 17, 2015 –
March 11, 2015
Final date for Proposers to submit ATCs for review March 18, 2015
Final date for requests for changes to Proposers’ organization and personnel March 20, 2015
Final date for Department’s responses to ATCs submitted for review March 27, 2015
Final date for receipt of Proposers’ questions March 31, 2015
Final date for Proposers to respond to conditional approval of ATCs April 6, 2015
Issue date for Final Addendum and/or answers to Proposers’ questions April 7, 2015
Proposals due April 21, 2015
Post Proposal Meetings (if required) TBD
Selection of Best Value proposal May 2015
Limited negotiations (if required) TBD
Contract Award June 2015
Notice to Proceed July 2015
36
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) One-On-One Meetings
If One-On-One Meetings are held, at least one meeting will be held with each Proposer.
One-on-One Meetings will be recorded. The Department reserves the right to disclose to all
Proposers any issues raised during the meetings that may materially affect the Project.
The Department will not disclose information pertaining to an individual Proposer’s technical concepts, proposal or ATCs.
Additional One-on-One Meetings may be held if required to review ATCs or if the Department believes they are warranted.
37
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Request for Proposals (RFP) Documents
RFP Documents: Instructions to Proposers
General Instructions Appendix A – Project Information Appendix B – Administrative Submittal
Requirements Appendix C – Technical Submittal Requirements Appendix D – Price Proposal Submittal
Requirements Appendix E – Forms Appendix F – Conflict of Interest Policy Appendix G – Abbreviations and Definitions
38
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Request for Proposals (RFP) Documents (Continued)
Part 1: D-B Agreement Part 2: General Provisions, Sect. DB 100 &
Appendices Part 3: Project Requirements (Scope of Work) Part 4: Utility Requirements Part 5: Special Provisions Part 6: RFP Plans Part 7: Engineering Data Part 8: Special Specifications (Including New
DB Specifications)
39
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Request for Proposals (RFP) Documents (Continued)
Part 9: Design-Builder’s Proposal Part 10: RFP Addenda (If Any)
Reference Documents on Department’s website (not part of the Contract Documents)
40
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Quality Control (QC)
QC is the Design-Builder’s Responsibility. The Design-Builder shall appoint a QC Manager responsible for the
QC Plans for both design and construction. Design QC may be by the Designer in accordance with the QC
Plan. Construction Inspection shall be performed by an Independent
Engineering Firm hired by the Design-Builder. Materials Testing shall be performed by an Independent Materials
Testing Firm or Laboratory hired by the Design-Builder. The Materials Testing Firm shall report to the Construction
Inspection Firm. Offsite Plant Quality Control shall be performed by the
Department.
41
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Quality Assurance (QA)
Design & Construction QA is the Department’s responsibility.
The Department may perform QA on any of the Design-Builder’s design and construction activities.
The Department will utilize an independent Consultant to perform QA of the Design-Builder’s designs.
Department Staff will perform Construction QA. Offsite Plant Quality Assurance will be performed by the
Department.
42
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) RFP Evaluation and Selection
Pass/Fail Evaluation Factors Legal – Financial – Administrative – DBE Compliance - Price Proposal
(Bond/Conformance)
Quality Evaluation Factors (50%) Key Personnel (10 points) Management Approach (30 points)
Overall Design-Build Team Organization (8 points) Design Management Plan (7 points) Construction Management Plan (7 points) Quality Control Plan (8 points)
Technical Solutions (35 points) Design Approach (13 points) Construction Approach (15 points) Schedule (7 points)
Project Support (5 points) Proposal Format(5 points)
Price (50%)
Design-Builder must obtain a minimum score of 60 points on Quality Evaluation factors in
order to be considered for Best Value determination.
43
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Additional Information – Submission Guidelines
All proposals must be self-contained. Proposals should not have links to external
websites. Proposals should contain all information
needed for evaluation. Do not assume that the Department
“knows” your firm and its experience/qualifications.
44
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Additional Information – Submission Guidelines (Continued)
Submit ALL Forms required. Do not alter any form unless indicated on the
form. Do not add any appendices or attachments to the
forms. Do not include photographs or illustrations unless
specifically indicated. Do not submit:
Form SA (Stipend Agreement) Form BDEA (Bid Document Escrow Agreement) PAB (Payment Bond (Labor and Material Bond)) PEB (Performance Bond (Faithful Performance Bond))
45
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Additional Information
Responses to Proposer Questions will be posted on the Department’s Project Web Site.
Reference Information which has been posted on the Project Web Site (https://www.dot.ny.gov/main/business-center/designbuildproject13): Design Report/Environmental Assessment Existing ROW and/or Acquisition Maps Survey Data Record Plans of roadways and structures within the Project limits Bridge Inspection Reports Geotechnical Investigations and Design Information Preliminary Design Microstation files Traffic data and analysis Environmental Guidance and Information
Preliminary USCG Permit Application
46
Peter RussellAttn: SR 146 Over the Mohawk River
Design-Build ProjectOffice of Contract Management
New York State Department of Transportation50 Wolf Road, 6th Floor
Albany, New York [email protected]
Route 146 Over the Mohawk RiverDesign-Build Project (PIN 1085.42) Project Contact
47