No. Brief Description Client Value Delivery
1 Kikeh FPSO UPV (15 units) MMHE/ MDFT RM10.800m July 2006
2 Bunga Raya E UPV (2 units) Talisman RM 0.284m June 2006
3 SFK-A/SJP-A L/R (2 units) Sabah Shell RM 0.463m May 2006
4 F13 SCDR-A UPV (1 unit) Ramunia/ SSB RM 0.340m Nov 2006
5 Sumandak UPV (18 units) Carigali RM 6.635m May 2007
6 Sumandak Skids (2 units) Carigali RM 7.300m May 2007
7 MG3 PPMSB UPV (13 units) Larsen & Toubro RM 1.200m March 2007
8 Chermingat UPV (2 units) Oilfab/ Newfield RM 0.380m March 2007
9 MCOT P2 Rej UPV (4 units) Carigali RM 1.500m March 2007
10 West Lutong L/R (4 units) Carigali RM 0.578m Feb 2007
11 SCDR-A FDP UPV ( 2 units) MMHE/ SSB RM 0.618m April 2007
12 Puteri FDP UPV (3 units) Kencana/Carigali RM 1.011m May 2007
13 BOA Misc. UPV (3 units) Sime Eng./ Talisman RM 2.650m Aug 2007
No. Brief Description Client Value Delivery
1 BO-A Misc. UPV (10 units) Sime Eng./ Talisman RM 2.650m Sept 2007
2 Chloride Remover (1 unit) Penapisan Melaka RM 0.430m May 2007
3 JeB UPV (1 unit) Brooke Dockyard RM 0.235m Sept 2007
4 Air Buffer UPV (1 unit) L&T/Penapisan Melaka RM 0.083m Sept 2007
5 Betty-4 L/R (2 units) Carigali RM 0.480m Sept 2007
6 MCOT UPV (1 unit) Carigali RM 0.100m March 2008
7 Polisher Vessel (2 units) Ethylene Malaysia RM 0.390m Nov 2007
8 MOQ L/R (5 units) Maersk Oil Qatar RM 1.400m Sept 2008
9 B11-KA 2 Gas Skids/ 1 GTCCoalescer Skid
OTEC Kemajuan/ Sarawak Shell Bhd
RM23.200m Dec 2008
10 MG#3 Tank (2 units) L&T/Penapisan Melaka RM 0.104m Aug 2007
11 <32mm UPVs(28 units) Murphy Oil RM 5.120m Feb 2009
12 >32mm UPVs (6 units) Murphy Oil RM 3.575m Feb 2009
13 PTLE Top Cones (12 units) Ethylene Malaysia RM 0.480m Nov 2007
14 J4 UPV (2 units) Kencana HL RM 0.575m Feb 2008
15 J4 L/R (2 units) Kencana HL RM 0.405m Feb 2008
No. Brief Description Client Value Delivery
16 PC4 2 units L/R (MMHE Kuantan) Carigali RM 0.518m March 2008
17 PSR2 UPV (1 unit) MMC Engineering RM 0.165m Feb 2008
18 PC4 FG Skid (1 unit) Carigali RM 5.500m April 2008
19 PSR2 UPV (17 units) Foster Wheeler E&C RM 6.885m Nov 2008
20 PSR1 UPV (1 unit) MITCO RM 0.119m March 2008
21 Bokor L/R (2 units) Vastalux/ Carigali RM 0.938m March 2008
22 Bokor UPV Skid (1 unit) Carigali RM 1.612m June 2008
23 Angsi-D FG Skid (1 unit) Carigali RM 4.900m July 2008
24 PSR2 Sulfur Lock UPV (4 units) Foster Wheeler E&C RM 0.440m Sept 2008
25 SMP-A/C L/R (8 units) Shapadu/ Carigali RM 3.489m April 2008
26 TEJT-W Scrubber UPV Skid (1unit)
Carigali RM 0.325m April 2008
27 PSR2 KO Drum UPV (1 unit) Foster Wheeler E&C RM 0.228m Dec 2008
No. Brief Description Client Value Delivery
1 Repair of Heat Exchanger RWNA /MTBE RM 0.058m April 2008
2 PC-4 FDP / 4 unit PVs MMHE / Carigali RM 3.140m April 2008
3 Off Spec Blinds EMSB RM 0.041m April 2008
4 PSR-2 / 1 unit PV (V-31207) Foster Wheeler RM 0.383m Sept 2008
5 VAT Vessel ExxonMobil RM 0.215m Aug 2008
6 Sampling Chambers EMSB RM 0.169m June 2008
7 LLP Furious / Scrubber Skid Shell RM 2.815m Jan 2009
8 Angsi-D / 1 unit PVs Ramunia /Carigali RM 0.323m Aug 2008
9 B11 KA / 4 units PVs MMHE / Shell RM 1.197m Sept 2008
10 MLTTB/ 18 unit PVs Carigali RM14.441m Sept 2009
11 Kumang Cluster / 16 unit PVs Carigali RM 7.371m Sept 2009
12 Kumang Cluster / Skid Carigali RM15.450m Sept 2009
13 Cili Padi/ 15 PVs, 2 Gas Skids & 2Launcher/Receiver
Sarawak Shell Bhd RM43.850m Sept 2009
14 Gumusut Kakap/ 9 units UPVs MMHE RM1.600m April 2009
15 Semarang Field - 10 units L/Rs PBJV Group RM 0.785m April 2009
No. Brief Description Client Value Delivery
16 Bokor - L/Rs & Tanks Package Dayang Enterprise RM 2.935m Nov 2009
17 Dulang Field / 6 PVs Kencana HL RM 3.874m July 2009
18 Kumang Field / 1 unit PV Sime Darby RM 0.150m Jan 2009
19 Kumang Field / 6 units Launcher& Receiver
Sime Darby RM 5.050m Feb 2009
20 MLTTB/ 2 units Launcher & 1 unitReceiver
Sime Darby RM 2.05m August & Dec 2009
21 Dulang Field/ 1 unit Receiver forCompressed Gas Capacity
Kencana HL RM 0.538m March 2009
22 1 unit PIG Signaller for LPLauncher
Dayang Enterprise RM 0.090m April 2009
23 LHDP-A MLDP-A FWS & TanggaBarat/ 1 Gas Receiver & 1 GasCondensate Receiver
Kencana HL RM 1.493m August 2009
24 D1 Cluster Dev/ 1 Closed DrainVessel & 1 Closed Drain c/wHeater & PIG Receiver
PCPP Operating Company
RM 1.100m August 2009
No. Brief Description Client Value Delivery
1 Baronia Water Injection / FlangedEnd Enclosure
Carigali SKO RM 0.175m August 2009
2 Kumang Field / Inlet Gas FilterCoalescer, Accumulator, Dry Filtersfor Acid Removal System
Scomi NTC / Carigali
RM 6.181m Dec 2009
3 Fairley Baram / 6” Gaslift pipelineLauncher & Receiver
Carigali RM 1.800m March 2010
4 Dulang Pipeline / Launcher &Receiver + Spools
Carigali RM 0.400m August 2009
5 Pressure Vessel & Column for AFC Online Column Chemical Cleaning
MTBE RM0.680m Sept 2009
6 Air Receiver Tanks for Crane ME-150 & ME-590
ExxonMobil RM0.185m Feb 2010
7 ST Joseph Dev. Project / Fuel Gas Skid/Pressure Vessel/L&R
Sabah Shell RM9.172m Feb 2010
8 Baronia / Cyclone Separator S-6200 Tanjong Offshore RM0.250m Aug 2009
9 Lawit-A / Stripping Columns ExxonMobil RM0.706m Nov 2009
10 Baronia BNDP-A / Receiver Carigali RM0.170m Jan 2010
No. Brief Description Client Value Delivery
11 SBO / Instrument Gas Scrubber S-1& S-2
Carigali RM0.311m March 2010
12 Launcher & Receiver and Deck Extension (Pig Trap)
Carigali
SKO
RM11.321m Dec 2010
13 Kinabalu NAG / 9 units PVs Carigali RM9.890m Sept 2010
14 West Belumut /4 units PVs KHL / Newfield RM 0.805m Nov 2009
15 West Belumut / 4 units L&R KHL/Newfield RM0.520m Nov 2009
16 MTBE / 1 unit Stabilizer Receiver MTBE RM0.340m Dec 2009
17 Pipeline PL347 / 2 units L&R KHL / Carigali RM0.682m Dec 2009
18 Eccentric Reducer for 3 units L&R Carigali RM0.493m Dec 2009
19 Pig Trap for 2 units L&R Carigali RM0.355m Feb 2010
20 KNJT-C / 1 unit Launcher KHL / Carigali RM0.510m Feb 2010
21 Seligi & Semangkok / Launcher &Receiver
ExxonMobil RM8.939m Sept 2010
22 Betty Re-visit / Fuel Gas Skid Carigali RM0.680m July 2010
No. Brief Description Client Value Delivery
23 St. Joseph / 1 unit Daerator Package Edwards Pte Ltd RM0.910m April 2010
24 Onshore Slug Catcher / 1 unit Air Receiver
Carigali / PMO RM0.360m Feb 2010
25 MRU / 4 units Condensate Coalescer Peco Facet / Talisman
RM2.600m Aug 2010
26 Tukau / 1 unit Air Receiver Carigali RM0.235m March 2010
27 East Belumut / 1 unit KO Drum Newfield RM1.775m April 2010
No. Brief Description Client Value Delivery
1. FPSO Perintis / 3 units WaterInjection Fine Filter Replacement
M3Nergy RM1.446m July 2010
2 SSGP / 6 units Air Receivers & Drain Tanks
Punj Lloyd / Carigali
RM2.000m Jan 2011
3 ABF / 4 units Rubber Lined PVs Asean Bintulu Fertilizer
RM1.665m Aug 2011
4 Jerneh / 1 unit Glycol Flash Vessel PRW / EMEPMI RM0.638m Dec 2010
5 Guntong E / 1 unit Air ReceivingVessel
PRW / EMEPMI RM1.200m Jan 2011
6 East Piatu / 1 unit Test Separator KHL / NFX RM1.232m Jan 2011
7 F28DR / 1 unit Knock Out Vessel KHL / Shell RM0.560m Jan 2011
8 East Piatu / 1 unit Closed Drain Vessel
KHL / NFX RM0.305m Jan 2011
9 PMO / 1 unit Instrument Gas Scrubber
Carigali RM0.430m Jan 2011
10 1 unit Pressure Vessels EMEPMI RM0.218m Jan 2011
11 East Piatu / 5 units Pressure Vessels KHL / NFX RM3.350m Feb 2011
No. Brief Description Client Value Delivery
12 Guntong D / 1 unit Fuel Gassuperheater
PRW / EMEPMI RM0.286m Feb 2011
13 F28 / 7 units Pressure Vessels for Produced Water Treatment Unit
Tanjong Offshore / Shell
RM3.500m Oct 2011
14 KPOC / 5 nos Pressure Vessel (Glycol) for KPOC Project
Prosep AP RM1.870m Oct 2011
15 PFK / 1 Unit Mix-Bed Exchanger Petronas Fertilizer
RM0.44m Sept 2011
16 KPOC / 18 Units of Pressure Vessels Kebabangan Petroleum Operation
RM23.542m Oct 2011
17 KNPG-B / 2 units Launcher & Receivers
MMHE / Carigali RM0.840m Nov 2010
18 F28DR-A / 1 unit Launcher KHL / Shell RM0.795m Jan 2011
19 F28 / 1 unit Receiver Shell RM0.638m May 2011
20 PL 353, 357, 383 SKO / 6 units Launcher & Receiver
Carigali RM1.893m Jan 2011
21 KNPG-B / 1 units Fuel Gas Skid MMHE / Carigali RM8.535m Feb 2011
No. Brief Description Client Value Delivery
22 Jernih / 2 units Foam Skid System PRW / EMEPMI RM1.800m Dec 2010
23 E8 & F13 / 2 units Seal Gas Conditioning Skids
Shell RM3.615m Aug 2011
24 E8 & F13 / 5 units Pressure Vessels and 2 units Fuel Gas Skid
Shell RM28.222m Aug 2011
25 F28 / 2 units Fuel Gas Skids Shell RM16.638m Dec 2010
TOTAL RM105.658
No. Brief Description Client Value Delivery
1. Angsi-B / 1 unit Closed Drain Vessel Carigali RM0.790m Oct 2011
2 BCOT / 1 unit Degassing Boots Dialog / Carigali RM0.550m Aug 2011
3 PRR-2 / 7 units Pressure Vessels Hyundai / GPP RM2.739m Dec 2012
4 SOGT / 15 units Pressure Vessel Samsung / Carigali
RM3.038m July 2012
5 Tapis EOR / 13 units Pressure Vessel EMEPMI RM24.790m July 2012
6 PFK / 1 unit Mix Bed Polisher PetronasFertilizer
RM0.420m Dec 2011
7 Cendor / 1 unit Instrument Gas Receiver
KHL / Petrofac RM0.180m Dec 2011
8 Cendor / 1 unit Closed Drain Vessel KHL / Petrofac RM0.245m Dec 2011
9 SKO / 1 Unit Pig Trap PL 291 – 22” Carigali RM0.245m Aug 2011
10 SKO / 1 Unit Pig Trap PL 184 – 14” Carigali RM0.170m July 2011
11 SKO / 1 Unit Pig Receiver ANDR-A Petrofac RM0.282m July 2011
No. Brief Description Client Value Delivery
12 FPSO / 1 Unit Pig Launcher Petrofac RM0.298m July 2011
13 SKO / 1 Unit Pig Trap PL 26 BNDP-A Carigali RM0.240m May 2011
14 SKO / 2 Units Pig Trap PL 47 & PL 270
Carigali RM0.235m Oct 2011
15 SKO / 1 Unit Pig Trap PL 326 MLNG Carigali RM0.400m Oct 2011
16 SKO / 1 Unit Pig Trap PL 29 BNDP-A Carigali RM0.230m Nov 2011
17 SKO / 1 Unit Pig Trap PL 232 WLP-A Carigali RM0.170m Nov 2011
18 SKO / 1 Unit Pig Trap PL 325 MLNG Carigali RM0.400m Oct 2011
19 SKO / 1 Unit Pig Trap PL 355 BEP-A Carigali RM0.220m Sept 2011
20 SKO / 1 Unit Pig Trap PL 271 BYDP-B Carigali RM0.170m Sept 2011
21 Tinggi / 1 Unit Launcher & Receiver Newfield / Carigali
RM0.410m Sept 2011
22 SOGT / 8 Units Launcher & Receiver Samsung / Carigali
RM2.280m Jan 2012
No. Brief Description Client Value Delivery
23 Cendor / 4 Units Launcher & Receiver
Kencana / Petrofac
RM0.810m Dec 2011
24 Tukau / 1 Units each Launcher & Receiver
Carigali RM0.590m Dec 2011
25 SKO / 1 Unit Pig Trap PL 282 Baronia Carigali RM0.230m Nov 2011
26 SKO / 3 Units Launcher & 3 Units Receiver
Carigali RM1.475m Nov 2011
27 SKO / 1 Unit Reducer PL 341 MCOT Carigali RM0.117m Nov 2011
28 Polyethylene / 1 Unit New Condensate Drum & 6 Units Withdrawal Hopper
Polyethylene RM0.496m June 2012
29 EMEPMI / 1 Unit Air Accumulator ExxonMobil RM0.030m Jan 2012
30 KPOC / 1 Unit Nitrogen Buffer Vessels
Tanjung New Energy
RM0.118m March 2012
31 KPOC – Produce Water Treatment / 12 Units Pressure Vessels for
Prosep AP RM3.444m June 2012
32 FPSO Chendor / 1 Unit Pressure Vessel
MMHE RM0.640m April 2012
No. Brief Description Client Value Delivery
33 HESS / 1 Unit Utility Gas Heater Intergrity RM0.640m Dec 2011
34 Bekok-C / 1 Unit Instrument Air Receiver
Petrofac RM0.045m Feb 2012
35 KPCO / 1 Unit Pressure Vessel for Fuel Gas System
MMHE RM1.324m June 2012
36 KPOC / 7 Units Filter Vessels PECO Facet RM1.413m July 2012
37 Tapis-Q / 7 Units Tote Tanks MMHE RM0.420m April 2012
38 GPP / 18 Units of Pressure Vessels TOYO RM2.500m July 2012
39 Telok A&B / 2 Units of Tote Tank MMHE RM0.455 June 2012
40 SKO / 1 Unit Pig Trap PL 174 TEDP-E Carigali RM0.310m Dec 2011
41 KPOC / 4 Units Launcher & Receiver MMHE RM1.225m April 2012
42 Tapis & GuE / 5 Units Launcher & Receiver / 10 nos of QOC
Shapadu RM2.202m May 2012
43 SKO / Supply QOC Premier Viable RM2,245m April 2012
44 Resak / 1 Unit FG Skid PCSB - PMO RM0.705m March 2012
No. Brief Description Client Value Delivery
1. KPOC / 2 Units Fresh Water Filter & 2 Units Potable Water Filter
VME Technical RM0228m June 2012
2. F14 / 2 Units of Pressure Vessels & 2 Units of Launcher & Receiver
Sarawak Shell RM1.744m Aug 2012
3. Resak / 4 Units of Air Accumulator PCSB - PMO RM0.060m April 2012
4. D12 / 1 Unit of Pressure Vessel & 2 Units of Condensate Pot
Sarawak Shell RM0.476m Nov 2012
5. Laila / 4 Units of Pressure Vessels Sarawak Shell RM1.003m Oct 2012
6. HESS / 1 Unit FG Superheater & 1 Units FG Filter Separator
Highbase RM0.325m June 2012
7. Resak / 22 Units Air Accumulator PCSB PMO RM0.742m July 2012
8. Serendah / 2 Units of Pressure Vessels
Kencana RM1.276m Oct 2012
9. FGRU / 2 Units Pressure Vessel TOYO RM0.196m Nov 2012
10. Tapis r / 2 Unit Corrugated Plate Interceptor & 1 Unit Induced Gas Floatation Vessel
CETCO RM5.220m Dec 2012
11. Patricia / 3 Units of Pressure Vessels and 1 Unit Launcher
Kencana RM0.513m Oct 2012
No. Brief Description Client Value Delivery
12. Siakap / 1 Unit SNP Separator & 1 Unit Suction Scrubber
MDFT Kikeh RM1.984m Dec 2012
13. Damar / 1 Unit Closed Drain Vessel MMHE RM1.215m May 2012
14. MLNG / 14 Units of Pressure Vessels Envipure, Spore RM1.750m Jan 2013
15. SAPA / 7 Units of Pressure Vessels Brooke RM1.750m Feb 2013
16. Bekok-C / 1 Unit Air Receiver Petrofac RM0.200m Dec 2012
17. Kongsberg / Fuel Gas Filter Separator
Ranhill Worley RM0.170m Jan 2013
18. MTBE / 1 Unit Vent Gas Wash Tower MTBE RM0.250m March2013
19. PMO / 12 Units of Pressure Vessels PCSB RM1.838m Feb 2013
20. 1 Unit of Nitrogen Gen skid Intergrity RM0.315m March 2013
21. Laila / 1 Unit of Pig Receiver Sarawak Shell RM0.372m Oct 2012
22. D35A / 1 Unit of Pig Receiver Kencana RM0.257m July 2012
23. SKO / 14 Units of Launcher & Receiver
Carimin RM4.700m July 2012
No. Brief Description Client Value Delivery
24. Serendah / 3 Units of Launcher & Receiver
Kencana RM0.655m Oct 2012
25. Cendor / 1 Unit Receiver Kencana RM0.125m Aug 2012
26. Tapis / 3 Units Launcher & Receiver Shapadu RM0.246m Sept 2012
27. Siakap / 2 Units Launcher & Receiver
MDFT Kikeh RM0.387m Nov 2012
28. West Desaru / 1 Unit Launcher Aquaterra, UK RM0.170m Sept 2012
29. Patricia / 1 Unit Receiver Kencana RM0.145m Dec 2012
30. SKO / 2 Unit Launcher & Receiver for PL11 and PL12
PCSB RM0.980m June 2013
31. SKO / Removal, Install & Leak Test for Launcher & Receiver PL11, PL12 & PL341 Kicker Line Modification
PCSB RM0.970m June 2013
32. Baram / 1 Unit Scrubber Skid Carimin RM0.650m Aug 2012
33. Tapis / 1 Lot Piping & Structural Works
Cetco RM2.430m Jan 2013
34. Tapis / 2 Units Chemical Injection SKid
Shapadu RM1.094m March 2013
No. Brief Description Client Value Delivery
1. UDTP / 9 Units Tanks Package Petrofac RM0.590m May 2013
2. Damar / 1 Unit Diesel Fuel & Coalescing Filter
MMHE RM0.240m June 2013
3. UDTP / 48 Units of Pressure Vessels & Columns
Petrofac RM2.513m June 2013
4. UDTP / 1 Unit Oil Stabilization Reboiler
Petrofac RM0.485m June 2013
5. UDTP / 4 Units of Launcher & Receiver
Petrofac RM0.332m June 2013
6. PRR-4 / 3 Units of Pressure Vessels TOYO RM1.400m July 2014
7. BASF / 1 Unit Separator Drum BASF RM0.195m Oct 2013
8. Permas / 4 Units of Pressure Vessels THHE RM0.795m Nov 2013
9. Tapis / 1 Unit Hot Water Heater MMHE RM0.455m Nov 2013
10. Malikai / 4 Units Multimedia Backwasher Fine Filter
Prosep RM1.000m Sept 2014
11. Eva / 1 Unit Knock Out Drum Kencana RM0.365m May 2014
No. Brief Description Client Value Delivery
12. Malikai / 1 Unit Daerator Vessel ETA RM1.120m May 2014
13. Malikai / 3 Units Hulls Storage Tank & 2 Unit Potable Tank & GTG Tank
Technip Malikai RM3.170m June 2014
14. Tapis / 2 Units Launcher & Receiver Shapadu RM0.169m Dec 2013
15. Guntong / 1 Unit Receiver Petrofac RM0.239m July 2013
16. Chendor / 8 Units Pigging Devices for Receiver
Petrofac RM1.091m Aug 2013
17. SKO / Removal, Install & Leak Test for PL67
PCSB RM0.301m Nov 2013
18. SKO / 1 Units Launcher & Receiver for PL67
PCSB RM0.995m Nov 2013
19. Malikai / 1 Unit Launcher Technip MMHE RM0.323m Jan 2014
20. Permas / 1 Unit Launcher THHE RM0.160m Feb 2014
21. JDA-EVA / 1 Unit Launcher Kencana RM0.415m March 2014
No. Brief Description Client Value Delivery
22. SKO-Baronia / 1 Unit Scrubber Skid Shapadu RM0.620m June 2013
23. SKO -Tukau/ 1 Unit Scrubber PCSB RM0.770m Dec 2013
24. Canada / 1 Unit Sugar Concentration Skid
Petrosep RM0.528m Sept 2013
25. SKO-West Lutong / 1 Unit Scrubber Skid
PCSB RM0.850m Dec 2013
26. Bekok-C / FSS Vessel Repair Petrofac RM2.250m March 2013