Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

Embed Size (px)

Citation preview

Page 1: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

Nodal Program Update

Jason Iacobucci

Nodal Program Manager

Technical Advisory Committee

5 August 2010

Page 2: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

2 Technical Advisory Committee5 August 2010

Agenda

• Program Status

• Full System Market and Reliability Test Overview

• NMMS Update

• Cut-Over Overview

• Cut-Over Certification – Outage Scheduler & CRR

• Market Readiness

• Follow-Up Discussion

Page 3: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

3

Integrated Nodal Timeline – Go-Live December 1, 2010

Technical Advisory Committee5 August 2010

Page 4: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

4

2010 Market Trials Timeline – Go-Live December 1, 2010

Technical Advisory Committee5 August 2010

Page 5: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

5

2010 Cut Over Timeline – 4 month outlook

5 August 2010 Technical Advisory Committee

Page 6: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

6

117 Days to Go-Live

Technical Advisory Committee5 August 2010

Market Trials has been running for 26 weeks Market Quality Testing and Operational Readiness

Achievements within Market Trials: • CRR

• Six monthly CRR auctions and one Balance of the Year auction have been completed and invoiced

• Real Time Markets• Real Time settlements

– Occurring daily for 15 weeks

• DAM / RUC / WRUC• DRUC has been running in conjunction with DAM for 13 weeks• DAM Settlements are being executed• Settlement and extract data has been available since Mid-May• 12 Operational scenarios were successfully run in June• WRUC has been running twice a week for 3 weeks

• Ancillary Services• Procured in every DAM for production quantities• Supplemental AS Market tested as needed

• Full System Market and Reliability Test • 8 hour test occurred on June 17th • 5 hour test occurred on July 21st

• Credit• Credit Module went into effect on May 14th

• Cut-Over• Market Readiness Seminar #5 was held on July 28 th

Page 7: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

7

117 Days to Go-Live

Technical Advisory Committee5 August 2010

Market Trials has been running for 26 weeks Upcoming Milestones for Market Trials:

• Full System Market Reliability Tests

• 24 hour test scheduled for the week of August 2nd • Additional Full System Market and Reliability Test – Duration will be based on results of 24-Hour Tests• Week of August 30th, 168 hour Full System Market and Reliability Test• Additional Market Readiness Assessment / Market Simulation will take place, including a multiday test in

early Sept

• DAM/RUC/SASM Scenarios• Planning more operational scenarios for August• DAM will run continuously for 7 consecutive days starting on 8/9/2010 through 8/16/2010

• DRUC, WRUC, and HRUC will run 24x7 all 7 days• Reduce the number of DAMs to create more resource availability to support additional Full System Market

and Reliability Tests

• Market Changes in trials for August / September• NPRR206- Change in Credit Management Collateral calculations for Day-Ahead Market• NPRR202- Posting of ERCOT network model (redacted version for all MPs)• NPRR169- Posting Real-Time Prices after every SCED run• QSEs and TSPs begin maintaining outages for September and post Go-Live

System Cut-Over / Go-Live• Sept/Oct 2010– Network Modeling, Outage Scheduling• November 2010- Go-Live CRR Auction • November 30th DAM• December 1st – First Operating Day

Page 8: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

8

Upcoming Dates for Go-Live Sign Off

System (Protocol)

TAC Approval Board of Directors Approval

Congestion Revenue Rights (CRR) August 5th August 17th

Outage Scheduling (OS) August 5th August 17th

Full Nodal Operations October 7th October 19th

5 August 2010

The table below outlines key approval dates for TAC and Board Signoff

Technical Advisory Committee

Page 9: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

9

Test Activities CRRRTM DAMOSEMS COMSNMMS CMM REG REPORTS

Functional Stability

System Stability

Business Stability

Go-Live

Functional Completeness

Solution/ Data Completeness

Solution/ Data Quality

FA/SA TEST

INTEGRATION TEST

BUSINESS PROCESS TEST

PERFORMANCE & LOAD TEST

Model Load /Validation Processes

MARKET TEST

UI Performance

Improvements

Contingencies

ICCP Quality

SE Quality

DRUCDAMRTM

HRUCSASM

SCED

Model Baseline

ICCP Point Checkout

Technical Advisory Committee5 August 2010

Business Quality

Integration

1 Day Dual Entry

May Auction

Integrated Credit

Management

Phase 5:Full Functionality

Phase 5:Full

Functionality

RARF

SEM MT 2.1

MT 3.0MT 4.0 MT 5.0

NPRR 206 Integration

Page 10: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

10

Nodal Program Risks & Issues

Technical Advisory Committee5 August 2010

Risk/Issue Impacted Milestone

Target Category Probability Severity Status

Network Model ManagementPerformance and availability issues around the NMMS.

Program July 2010

Schedule / Budget

Med High • Working closely with vendor to correct all issues

• Working through issues list with NDSWG and NATF

Market Design AssessmentRisk around the protocol traceability project and the market results as each phase of market trials becomes active.

Program August2010

Scope / Budget

Low High • Performing risk assessment associated with four identified issues for August board meeting

Operational ReadinessOperational readiness of the Nodal systems and business processes are an increasing risk at this point in the program

Program September2010

Scope / Schedule/

Budget

Med High • Organizational capability assessments and improvement recommendations are under review by executive management

• The PMO has and will continue to identify critical deficiencies and implement mitigation strategies to ensure delivery

Page 11: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

11

Network Model Management System Update

• Improvement in stability since two patches installed on July 2nd and July 22nd – No unscheduled restarts since the July 22nd installation

• Navigation Performance:– Vendor delivered performance patch which is being tested in the

sandbox test environment– Initial results indicate navigation improvements but testing is ongoing

• The plan is to install this week if the patch continues to test well

• Validation Performance: – Programmers are assessing validation and testing potential

improvements

Technical Advisory Committee5 August 2010

Page 12: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

Kenneth RagsdaleMarket Trials

Full System Market and Reliability Test Overview

Page 13: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

13

5-Hour LFC Test Update

5-Hour LFC Test Update

Time Activity

0800 Hotline call was  made by the ERCOT Operator announcing the 1100 start time for the test

0929 ERCOT Operators activated an OC3 for solving congestion in Zonal

1100 Hotline call what made announcing the test was starting and the VDI was issued

1119 First participating QSE confirms switch over to Nodal control

1214 Final participating QSE confirms switch over to Nodal control

1218 Hotline call what made announcing that all participating QSEs on Nodal control

1531 Hotline call what made announcing that participating QSEs were being switched back to Zonal

1535 First participating QSE confirms switch back to Zonal control

1616 Final participating QSE confirms switch back to Zonal control

5 August 2010 Technical Advisory Committee

Page 14: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

14

5-Hour LFC Test Update

Constraints Encountered During the Test

Start Constraint Reason10:00 Roanoke Switch OC3 Loss of Roanoke Switch T1 345/138KV

autotransformer overloads West Denton - Fort Worth Substation 138KV - 108% of 218 MVA rating.

12:20 Jack County - Reno OC3 Loss of Jack County - Reno 138KV overloads Wise County - Bridgeport TU 138KV - 105% of 199 MVA rating.

5 August 2010 Technical Advisory Committee

Page 15: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

15

5-Hour LFC Test Update

• Completion Criteria:– The rolling CPS1 one minute average score must equal or exceed 100% during

the test period. • Note that CPS1 metric will not apply to periods during testing wherein

system tuning is being performed by either ERCOT or Market Participants– HE12-73, HE13-112, HE14-103, HE15-120, HE16-103

– Zonal Commercially Significant Constraints (CSCs) and Closely Related Elements (CREs) managed below thermal limits. The Zonal CSCs were not activated during the test

– Local Congestion managed below thermal limits. Two local constraints binding during the test

– Stability limits managed below transfer limits No stability limits were activated during the test

– No NERC Disturbance Control Standard (DCS) failure if applicable Not applicable during the test

– No LFC-SCED system issues that result in termination of the test. No issues– Procedural and software fixes have been verified to address lessons learned

from previous rounds of testing There were no shift factors transfer failures during the test.

5 August 2010 Technical Advisory Committee

Page 16: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

16

GREDP Performance Summary

• For this analysis; X=5%, Y=5, MW, and Z=10%

• Performance does not appear to have varied drastically from the 8-hour test

Percent of Non-IRR Generation Resources that Met the Protocol Criteria

All Resources 79.74%

Resources Providing Regulation 86.90%

Combined Cycle Resources 93.22%

Coal and Lignite Resources 97.50%

Diesel Resources 100.00%

Gas Steam (Non-Reheat Boiler) Resources 25.00%

Gas Steam (Reheat Boiler) Resources 72.22%

Gas Steam (Supercritical Boiler) Resources 33.33%

Hydro Resources 88.89%

Nuclear Resources 100.00%

Simple Cycle (Greater than 90 MW) Resources 100.00%

Simple Cycle (Less than 90 MW) Resources 34.04%

Percent of IRRs that Met the Protocol Criteria 33.33%

Number of IRRs that had an Interval for which

GREDP was scored9

5 August 2010 Technical Advisory Committee

Page 17: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

Nodal Go-Live UpdateReview of Outage Scheduler and CRR Go-Live Items

Kenneth RagsdaleMarket Trials

Page 18: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

18

Readiness Methodology

ERCOT will measure readiness by the following categories:• System Readiness – an evaluation of a particular system

needed to support identified market activities• Process Readiness – an evaluation of the Processes and

Procedures necessary to support identified market activities• People Readiness – an evaluation of ERCOT and Market

Participant capabilities to support identified market activities

ERCOT plans to review the Market Readiness Criteria at NATF and subsequently request a vote from TAC per Section 21.12.3, Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provision

5 August 2010 Technical Advisory Committee

Page 19: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

19

Protocol 21.12.3

21.12.3 Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provision

No part of the nodal market design may start operation until all the Market Readiness Criteria for that part of the nodal market design have been met. Certification that all Market Readiness Criteria have been met must be made at least by each of the following: the Technical Advisory Committee (TAC), ERCOT and the ERCOT Board. Upon such certification, ERCOT shall issue two Notices alerting Market Participants to the effective date of Nodal Protocol sections and the retirement of Zonal Protocol sections, as applicable. ERCOT shall issue the first Notice no less than thirty (30) days prior to the effective date or retirement date, as applicable, and the second Notice no less than ten (10) days prior to the effective date or retirement date, as applicable. The Notice shall include:

(1) The Nodal Protocol Sections to become effective; and

(2) The Zonal Protocol Sections to be retired, if any

5 August 2010 Technical Advisory Committee

Page 20: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

20

OS and OS UI (12 defects) as of 7-29-10

• All 12 are expected to be fixed in NPROD by 8-13-10.

• 8 of the 12 are market facing.

5 August 2010 Technical Advisory Committee

Page 21: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

21

Outage Scheduling – Go Live

System Readiness Planned Completion

Status

Outage Scheduler released to Market Trials 2/01/10 Complete

Outages Scheduler Integrated with DAM, RUC 4/15/10 Complete

Outage Scheduler Qualification Connectivity Qualification (MP20) 4/01/10 Green

Process Readiness

Verify Outage Evaluation System Functionality (EMO3 #1) 6/23/10 Green

Outage Coordination Procedures 7/16/10 Complete

Nodal Protocol Transition Plan Updated for Outage Scheduling 7/29/10 Complete

Outage Scheduling Transition Plan Established 7/08/10 Complete

5 August 2010 Technical Advisory Committee

Page 22: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

22

Outage Scheduling – Go Live

People Readiness Planned Completion

Status

ERCOT Staff Support of Market Trials Ongoing Green

ERCOT Staff Trained on System and Processes 09/03/10 Green

Market Participant Training Delivered 7/15/10 NMMS/OS

class added

Overall Readiness

NATF Review7/08/10,

07/29/10 Complete

ERCOT Management Signoff 8/04/10

TAC Approval 8/05/10

BOD Approval 8/17/10

30 Day Market Notice 10/01/10

10 Day Market Notice 10/21/10

5 August 2010 Technical Advisory Committee

Page 23: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

23

Outage Scheduling

On July 8th, NATF approved a motion to recommend to TAC that the Outage Scheduling Market Readiness Criteria have been met.

ERCOT Management Sign-off in progress as of 7-29-10. It will be posted once signed.

5 August 2010 Technical Advisory Committee

Page 24: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

24 Technical Advisory Committee5 August 2010

• Outage Scheduler with Zonal Outage Transfer

• Delete all Outages and run Zonal to Nodal Transfer Tool Friday, 8/13 (Note that 80% to 85% of the outages are transferred)

• A Market Notice will be sent out once the purge and transfer is complete

• Email [email protected] by 8/9/10,1700 if the transfer is NOT desired

• Resource Outages will not be transferred by the Transfer tool

• The target is to make available for outage transfer validation and outage submissions Monday 8/16, 7:00 am, for the upcoming tests, optional months of October & November and for December and beyond

• Request list of Outages not transferred from [email protected]

• Send email to Market [email protected] confirming outages have been validated by 9/17 for all Outages December and beyond

• First production pull of OS data is scheduled for 10/2 for the first CRR Auction

• TSPs and QSEs are responsible to ensure that the outages in the Nodal Outage Scheduler are correct

• Outages previously approved in zonal will be automatically approved in Nodal

Outage Scheduler Transition Timeline

Page 25: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

25

TAC’s Outage Scheduler Certification Approval

WHEREAS, Protocols Section 21.12.3 (Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provisions) provides that before a “part of the nodal market design may start operation,” a vote of the Technical Advisory Committee (TAC) is required affirming that the “Market Readiness Criteria for that part of the nodal market design have been met”

WHEREAS, the Section 21.12.3 certification by TAC, Electric Reliability Council of Texas, Inc. (ERCOT) staff, and the ERCOT Board of Directors regarding the satisfaction of “Market Readiness Criteria” for a particular part of the nodal market design will result in ERCOT issuing “two Notices alerting Market Participants to the effective date of Nodal Protocol sections and the retirement of Zonal Protocol sections, as applicable”;

WHEREAS, the Protocols do not define the term “Market Readiness Criteria,” and ERCOT, in conjunction with Market Participants, has developed specific metrics and a Nodal Readiness Scorecard that are used to determine the progress of specific parts of the nodal market design in meeting the criteria necessary for implementing the Nodal Protocols and starting operations;

WHEREAS, the members of TAC recognize that there are issues that remain to be addressed regarding the implementation and operation of the Outage Scheduler before the Texas Nodal Market Implementation Date (TNMID), but that none of those issues should prevent the Outage Scheduler Go-Live on November 1, 2010, which is an integral occurrence in the progress toward meeting the TNMID on schedule;

WHEREAS, TAC has reviewed the market readiness metrics documentation underlying ERCOT staff’s recommendation regarding the Outage Scheduler part of the nodal market design, and has conducted due diligence on ERCOT staff’s conclusion that the Outage Scheduler has satisfied all of the steps necessary to make the declaration of market readiness required by Section 21.12.3, in order to authorize Outage Scheduler Go-Live on November 1, 2010;

THEREFORE be it RESOLVED, that this Resolution shall serve as the TAC certification that all Market Readiness Criteria have been met, for purposes of ERCOT Protocols Section 21.12.3, regarding Outage Scheduler Go-Live on November 1, 2010;

5 August 2010 Technical Advisory Committee

Page 26: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

26

CRR Allocation and Auction (5 defects) [as of 7-29-10]

1. Topology Processor (TP) cannot properly consume outage information. With TP version 8 delivered in early July it was identified that the outages were not properly consumed. Working with Siemens and also working on manual work-around.

2. HUB PNODES mismatch between TP and DSV model database. Defect resolved and currently being retested.

3. Incorrect Load Zone Designation from TP. (Possible data issue. Continue to investigate with Siemens.)

4. Resource Nodes missing from output file produced by TP. (Possible data issue. Continue to investigate with Siemens.)

5. Islanding in PSSE network model. (Possible data issue. Continue to investigate with Siemens.)

5 August 2010 Technical Advisory Committee

Page 27: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

27

CRR Allocation and Auction – Go Live

System Readiness Planned Completion

Status

CRR System released to Market Trials 2/01/10 Complete

CRR Integrated in Market Trials 5/01/10 Complete

CRR Account Holder Connectivity Qualification MP 15 (B) 9/17/10 Red**

Operation of CRR Auctions and Allocations (CRR3) Ongoing Green

Verify CRR Auction Invoices (CO8) Ongoing Green

Process Readiness

CRR Procedures 6/25/10 Complete

Nodal Protocol Transition Plan Updated for CRR 7/29/10 Complete

TCR to CRR Transition Plan (CRR4) 9/29/09 Complete

** Red due to MPs registering but not working to get qualified. (inflated denominator)

5 August 2010 Technical Advisory Committee

Page 28: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

28

CRR Allocation and Auction – Go Live

People Readiness Planned Completion

Status

ERCOT Staff Support of Market Trials Ongoing Green

ERCOT Staff Trained on System and Processes 06/25/10 Complete

Market Participant Training Delivered 07/15/09 Complete

Overall Readiness

ERCOT Management Signoff 08/04/10

NATF Review 07/08/10, 07/29/10

TAC Approval 08/05/10

BOD Approval 08/17/10

30 Day Market Notice 09/13/10

10 Day Market Notice 10/03/10

5 August 2010 Technical Advisory Committee

Page 29: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

29

CRR Allocation and Auction – Go Live (as of 7-29-10)

Scheduled to be reviewed again at 8-3-10 NATF meeting.

ERCOT Management Sign-off is in progress as of 7-29-10. It will be posted once signed.

5 August 2010 Technical Advisory Committee

Page 30: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

30

TAC’s Congestion Revenue Rights Certification Approval

WHEREAS, Protocols Section 21.12.3 (Notice to Market Participants of Effective Date for Nodal Protocol Provisions and Retirement of Zonal Protocol Provisions) provides that before a “part of the nodal market design may start operation,” a vote of the Technical Advisory Committee (TAC) is required affirming that the “Market Readiness Criteria for that part of the nodal market design have been met”

WHEREAS, the Section 21.12.3 certification by TAC, Electric Reliability Council of Texas, Inc. (ERCOT) staff, and the ERCOT Board of Directors regarding the satisfaction of “Market Readiness Criteria” for a particular part of the nodal market design will result in ERCOT issuing “two Notices alerting Market Participants to the effective date of Nodal Protocol sections and the retirement of Zonal Protocol sections, as applicable”;

WHEREAS, the Protocols do not define the term “Market Readiness Criteria,” and ERCOT, in conjunction with Market Participants, has developed specific metrics and a Nodal Readiness Scorecard that are used to determine the progress of specific parts of the nodal market design in meeting the criteria necessary for implementing the Nodal Protocols and starting operations;

WHEREAS, the members of TAC recognize that there are issues that remain to be addressed regarding the implementation and operation of the Congestion Revenue Rights before the Texas Nodal Market Implementation Date (TNMID), but that none of those issues should prevent the Congestion Revenue Rights Go-Live on October 13, 2010, which is an integral occurrence in the progress toward meeting the TNMID on schedule;

WHEREAS, TAC has reviewed the market readiness metrics documentation underlying ERCOT staff’s recommendation regarding the Congestion Revenue Rights part of the nodal market design, and has conducted due diligence on ERCOT staff’s conclusion that the Congestion Revenue Rights has satisfied all of the steps necessary to make the declaration of market readiness required by Section 21.12.3, in order to authorize Congestion Revenue Rights Go-Live on October 13, 2010;

THEREFORE be it RESOLVED, that this Resolution shall serve as the TAC certification that all Market Readiness Criteria have been met, for purposes of ERCOT Protocols Section 21.12.3, regarding Congestion Revenue Rights Go-Live on October 13, 2010;

5 August 2010 Technical Advisory Committee

Page 31: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

Brandon McElfreshReadiness & Transformation

Market Readiness

Page 32: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

32

Reminder – Nodal Registration Cutoff – QSEs and CRRAHs

Technical Advisory Committee

• Scope• What is the cutoff date for QSEs and CRRAHs to begin registration for Nodal Go-Live (based on ERCOT

resource availability)?• Registration must begin by these dates to be qualified for Nodal Go-Live

• August 13th, 2010• QSEs with Resources with a new WAN connection *• CRRAHs (to be qualified for the 10/13 PCRR nomination and for the 11/11 December 2010 CRR Auction) *

~

• October 1st, 2010• QSE with Resources using a Nodal qualified service provider *• QSEs without Resources *• Sub-QSEs using a Nodal qualified parent QSE *

• Mechanics• Qualification will follow the Nodal production qualification process and all testing will be done in the MOTE

environment• MPs that want to begin registration past these

deadlines will be examined on a case-by-case basis• Nodal Metric MP22 will measure progress of

new entrants

* QSE Application or CRRAH Application must be submitted, which includes Credit Application

~ Doesn’t include NOIE Allocation Eligibility Form, which must be submitted by 6/30 for CRRAHs eligible for PCRRs

QSERs (new wan),CRRAHs

QSERs (existing wan),Sub-QSERs,

QSEs w/o Resources

5 August 2010

Page 33: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

33

Next 60-days of Nodal Classes/Workshops

Course Start Date Location

Basic Training Program August 10 Calpine (Houston)

NPRR206 E-Factors Workshop August 10 Hilton Austin Airport (Austin)

ERCOT Nodal 101 August 10 ERCOT Met Center (Austin)

Basic Training Program August 10 Calpine (Houston)

Network Model/Outage Scheduler Workshop (new)

August 10 ERCOT (Taylor)

Load Serving Entity 201 August 16 Reliant Energy (Houston)

Market Settlements 301 August 17 City of Garland Fire Administration Building (Dallas)

Network Model/Outage Scheduler Workshop (new)

August 18 ERCOT (Taylor)

GCPA Retail Workshop August 19 Centerpoint (Houston)

5 August 2010

Enrollment at: http://nodal.ercot.com/training/courses/index.html

Technical Advisory Committee

Page 34: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

34

Next 60-days of Nodal Classes/Workshops - continued

Course Start Date Location

NOIE QSE Operations August 20 City of Garland Fire Administration Building (Dallas)

Congestion Revenue Rights August 24 University of Delaware (Newark, DE)

Generation 201 August 25 University of Delaware (Newark, DE)

Congestion Revenue Rights August 31 ERCOT Met Center (Austin)

Generation 201 September 1 Hilton Austin Airport (Austin)

Economics of LMP September 13 ERCOT Met Center (Austin)

ERCOT 101 for Wind Generation September 13 Optim Energy (Dallas)

ERCOT Nodal 101 September 14 StarTex Power (Houston)

Generation 101 September 15 Hilton Austin Airport (Austin)

Basic Training Program September 20 LCRA (Austin)

Load Serving Entity 201 September 27 ERCOT Met Center (Austin)

Enrollment at: http://nodal.ercot.com/training/courses/index.html

5 August 2010 Technical Advisory Committee

Page 35: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

35

RED/AMBER Metrics Summary

ERCOT Metrics

Market Participant Metrics

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

Market Participant MetricsMP15(B) CRR Connectivity Qualification

Red CRRAHsEven

weighting94.2% 0.0% 0.0% 5.8%

Successful submission CRR transactions

66/74 CRRAHs qualified. Greater than

5% RED.

MP16 DAM Participation

Amber QSEsEven

Weighting78.6% 6.6% 12.6% 1.1%

Participation in 50% of the Day-Ahead Market

runs

143/182 QSEs w/o Resources

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

ERCOT Metrics

EMO9(A) State Estimator Convergence

Amber ERCOT N/A N/A 95.44 N/A N/A

State Estimator converges 97% of runs during a monthly test

period.

95.44% Convergence for State Estimator for

the month of May.

EMO9(B) RTCA Modeling Differences

Red ERCOT N/A N/A N/A 84.33% N/A95% of load tap setting

values matched between Zonal/Nodal

84.33% Match for transformer tap settings.

1430 transformers in Nodal.

Technical Advisory Committee5 August 2010

Page 36: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

36

Questions ?

5 August 2010 Technical Advisory Committee

Page 37: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

37

Appendix

5 August 2010 Technical Advisory Committee

Page 38: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

38

Nodal Program Risks & Issues: Definitions

5 August 2010

Definitions for Category, Probability and Severity of Risks & Issues:

• Category– Scope : Will require a scope change– Schedule: Will require a schedule change– Budget: Will require a budget change

• Probability– High : Probability to occur is ≥ 90%; perceived impact would require a Change

Request over the next 1-3 months– Medium: Probability to occur is between 31 – 89%; perceived impact would

require a Change Request over the next 4 -10 months– Low: Probability to occur is ≤ 30 %; not expected to require a Change Request

• Severity – High: Milestone impact, or budget impact >$250,000 – Medium: Milestone impact - but expected to be mitigated, or budget impact

between $0 - $250,000 – Low: No milestone impact, or no budget impact

Technical Advisory Committee

Page 39: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

39

60 Day Outlook : August Market Activities

Functional Area Real-Time Market

Congestion Revenue Rights

Day-Ahead Market

Reliability Unit Commitment

Outage Scheduler

COMS/Settlements

Network Modeling

Nodal Reports

Credit

Full Integration

Targeted Activities for August 2010• August is reserved for focusing on any

issues or scenarios encountered in the first 3 months of Phase 5

• Real time submission continue• ERCOT executes August Monthly CRR

Auction• SASM executed as needed

Jan Feb Mar Apr May June July Aug

5 August 2010 Technical Advisory Committee

Page 40: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

40

DAM/RUC/SASM Operational Scenarios

5 August 2010 Technical Advisory Committee

Page 41: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

41

DAM/RUC/SASM Operational Scenarios

5 August 2010 Technical Advisory Committee

Page 42: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

42

ACTIVE NODAL METRICSMetric # Metrics Name Category ERCOT QSERs QSEs TSPs CRRAHs REs

MO4 Verify SCED Execution Quality RT Green N/A N/A N/A N/A N/AMO5 Generate LMPs for 6 months RT Green N/A N/A N/A N/A N/ACRR3 (ERCOT) Operation of CRR Auctions and Allocations CRR Green N/A N/A N/A N/A N/AMO9 Generate Day-Ahead LMPs DAM Green N/A N/A N/A N/A N/AMO10 DRUC Execution DAM Green N/A N/A N/A N/A N/ACO8 Verify CRR Auction Invoices COMS Green N/A N/A N/A N/A N/AEMO9(A) State Estimator Convergence NM Amber N/A N/A N/A N/A N/AEMO9(B) RTCA Modeling Differences NM Red N/A N/A N/A N/A N/AEMO10 Anomalous/Auto-Disabled Telemeted Points NM Green N/A N/A N/A N/A N/AE1 ERCOT Internal Training READ Green N/A N/A N/A N/A N/AE9 Develop Nodal Procedures READ Green N/A N/A N/A N/A N/AMP3 Market Submissions Connectivity Qualification CONN Green Green Green N/A N/A N/AMP15B CRR Connectivity Qualification CONN Red N/A N/A N/A Red N/AMP20 Outage Scheduler Connectivity Qualification CONN Green Green N/A Green N/A N/AEMO6 Individual LFC Testing RT N/A Green N/A N/A N/A N/AMP15A Real-Time Market Daily Participation RT N/A Green N/A N/A N/A N/AEMO6 Individual LFC Testing RT N/A Green N/A N/A N/A N/ACRR3 Operation of CRR Auctions and Allocations CRR N/A N/A N/A N/A Green N/AMP16 DAM Participation DAM N/A Green Amber N/A N/A N/AMP20 Outage Scheduler Connectivity Qualification OS N/A Green N/A Green N/A N/AN2 Telemetry/ICCP System Failover NM N/A Green N/A N/A N/A N/AMP6(SE) Telemetry Compliance 3.10.7.5 NM N/A Green N/A N/A N/A N/AMP6(SCED) Telemetry Compliance 3.10.7.5 NM N/A Green N/A N/A N/A N/AMP6 (TSP) Telemetry Compliance 3.10.7.5 NM N/A N/A N/A Green N/A N/AMP14B Participation in NOMCR Trials NM N/A N/A N/A Green N/A N/AMP14C Network Model Validation NM N/A N/A N/A Green N/A N/AMP11 Resource Registration RES N/A N/A N/A N/A N/A Green

Active Nodal Metrics

Technical Advisory Committee5 August 2010

Page 43: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

43

Metrics RoadmapPURPLE

ORANGE

Timing and Design Confirmed

Timing subject to change, design in progress

MP15A

MP16

MP20

MP3

MP6

MP11 MP14C

E9

E1

N2 EMO9(B)

CRR3

EMO6

MO4 MO5

CO1

CO2

CO3

CO4

CO5

CO6 CO7

CO8 CO9

C10

E7

E11

E12

C1-C10

EMO13

MO7

CRR4

E5

IMM1

R0

R2

R3

MP15B

MP3

N1

E3

E10

R1

MP22

EMO9(D)

MO9

MO8MO3MO10

EMO10 EMO9(C) EMO7EMO9(A)

New Metric

MP23

EMO2

EMO8

Technical Advisory Committee5 August 2010

Page 44: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

44

CRR Metrics

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

Market Participant MetricsMP15(B) CRR Connectivity Qualification

Red CRRAHsEven

weighting90.7% 0.0% 9.3% 0.0%

Successful submission CRR transactions

68/75 CRRAHs qualified. Greater than

5% RED.

CRR3 Operation of CRR Auctions and

AllocationsGreen CRRAHs

Even weighting

87.8% 0% 12.2% 0.0%

Participation in at least 1of the last 2 auctions or allocations. > 80%

total participating

58/66 CRRAHs with adequate participation in June or July auction or

allocationERCOT Metrics

CRR3 Operation of CRR Auctions and

Allocations

Green ERCOT N/A N/A N/A N/A N/A

Auction results distributed to

participants per schedule in CRR

Handbook

6/21 2010 June Monthly Auction results posted to

market.

TBD ERCOT N/A 100% 0% 0% 0%

Allocated Revenue Rights in statistical

sample = 100% accurate

Source – Sink prices = CRR Clearing prices for

obligations for BOY auction. ERCOT working on similar

validation process for options.

CO8 Verify CRR Auction Invoices

GreenERCOT N/A 100% 0% 0% 0%

CRR Auction Result for MP(n) – CRR Auction

Invoices for MP(n) = 0$

S&B validated invoices reflected awards for each CRRAH in the

March, April, May, June, and July auctions, .

GreenERCOT N/A 100% 0% 0% 0%

System Generated CRR Auction Invoices

not posted = 0

6/22 July CRR auction invoices submitted to all 48 CRRAHs who participated

Technical Advisory Committee5 August 2010

Page 45: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

45

Real-Time Metrics

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

Market Participant MetricsMP3 Market Submissions Connectivity Qualification

Green QSERsGeneration Ratio Share

99.0% 1.0% 0.0% 0.0% Successful submission of RT and DAM

transactions

79/81 QSERS qualified

Green QSEsEven

weighting98.9% 1.1% 0.0% 0.0% 178/182 QSEs qualified.

EMO6 Individual LFC Testing

Green QSERsGeneration Ratio Share

96.9% 0% 0% 3.1%

80% of system-wide generation has

completed individual QSE tests for LFC

70/73 QSERs completed their individual LFC test or provided attestation

MP15-A Real-time Market Participation

Green QSERsGeneration Ratio Share

100.0% 0.0% 0.0% 0.0%Weekly average of

daily SCED submissions

79/79 QSERs above 95% weekly average for

SCED submissions. ERCOT Metrics

MO3 Verify SASM Green ERCOT N/A 100% N/A N/A N/A

Multiple SASMs are successfully executed during Market Trials

and the 168 hour test.

SASMs successfully run on 4/28, 4/30, 5/4, 5/6, 5/7, 5/12, 5/14, 6/9, and

6/10. No issues reported.

MO4 Verify SCED Execution Quality

Green ERCOT N/A 100% 0% 0% 0%

All successful SCED executions passed the post-execution price

validations.

6/1 - 6/14 period - 4,035 Price Validation runs with no rule violations

MO5 Generate 6 Months of LMPs

Green ERCOT N/A 98.1%. 0% 1.9% 0%

95% of SCED executions completed with LMPs posted on

MIS.

6/1 - 6/14 period, 3,971 out of 4,031 SCED runs

with LMPs posted.

CO5 Verify RTM Settlement

Statements/CO6 Verify RTM Settlement

Invoices

Green ERCOT N/A 100% 0% 0% 0%

System Generated RT Statement Dollars-

Independently Generated RT

Calculation Dollars =$0

6660 RTM Statements;1609 RTM InvoicesAll validated $$ =

system generated (with some rounding differences)

Green ERCOT N/A 100% 0% 0% 0%System Generated RT Statements/Invoices

not posted = 0

6660 RTM Statements;1609 RTM InvoicesAll posted on time

Technical Advisory Committee5 August 2010

Page 46: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

46

Day-Ahead Market Metrics

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

Market Participant Metrics

MP16 DAM Participation

Green QSERsGeneration Ratio Share

99.0% 1.0% 0.0% 0.0% Participation in 50% of the Day-Ahead Market

runs

78/79 QSEs with Resources

Amber QSEsEven

Weighting78.6% 6.6% 12.6% 1.1%

143/182 QSEs w/o Resources

CO10 Credit Calculations

6/30/2010QSERs, QSEs

Gen Ratio Share, Even Weighting

N/A N/A N/A N/A<= 25% of MPs credit limits inconsistent with

protocolsTo be determined

ERCOT Metrics

MO8 Verify DAM Execution Quality

Report in Progress

ERCOT N/A N/A N/A N/A RedDAM executions pass

the post-execution price validations

Report in progress

MO9 Generate DAM LMPs

Green ERCOT N/A N/A N/A N/A N/A95 percent DAM

execution as evidenced by DAM LMP postings

6/1 – 6/14 – 7/7 DAM runs execute(doesn’t

measure quality)

MO10 DRUC Execution

Green ERCOT N/A N/A N/A N/A N/A95 percent DRUC

execution

6/1 – 6/14 - 7 out of 7 DRUC runs executed

(doesn’t measure quality)

CO3 Verify DAM Settlement

Statements/CO7 Verify DAM Invoices

Green ERCOT N/A 100% 0% 0% 0%

System Generated RT Statement Dollars-

Independently Generated RT

Calculation Dollars =$0

4715 DAM Statements and Invoices

All validated $$ = system generated (with

some rounding differences)

Green ERCOT N/A 100% 0% 0% 0%System Generated RT Statements/Invoices

not posted = 0

4715 DAM Statements and Invoices

All posted on time

CO10 Credit Calculations

6/30/2010ERCOT N/A N/A N/A N/A N/A

ERCOT performs credit calcs for a stat. sample

of MPsTo be determined

1. MP16 – Metric is based on a 2 week rolling average (6/7 – 6/18 – 9 runs).2. MP16 – 97% Load participating.

Technical Advisory Committee5 August 2010

Page 47: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

47

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

Market Participant Metrics

MP14-C TSP Model Validation

Green TSPsOwnership Ratio Share

99.9% .1% 0.0% 0.0%Network Model data

validated by TSP

24/28 TSPs have submitted model

validation e-mail to ERCOT.

MP6 Telemetry Compliance with Nodal

Protocols 3.10.7.5

Green QSERsGeneration Ratio Share

100% 0.0% 0.0% 0.0%Expected State

Estimator telemetry submitted.

78/78 complete. 3502 total SE points provided

Green QSERsGeneration Ratio Share

100% 0.0% 0.0% 0.0%Expected SCED

telemetry submitted.78/78 complete. 7629 SCED points provided

Green TSPsOwnership Ratio Share

99.3% 0.0% 0.0% .7%Expected TSP

telemetry per ICCP Handbook submitted

14/17 TSPs above 98% threshold for GREEN. 143 points outstanding

N2 Telemetry ICCP System Failover

Green/White only

QSERsGeneration Ratio Share

68.9% 0% 0% 31.1%

ICCP Failover test completed successfully prior to the 8-hour LFC 

test.

37/78 QSERs completed ICCP telemetry failover

test.

MP18 Mapping of Resources and Loads

in Private Use Networks

6/30/2010 QSERsGeneration Ratio Share

N/A N/A N/A N/A

# of QSE(n) PUN Points Provided / # of QSE(n) PUN Points

Expected

306 points across 7 QSEs with Resources. 15 points still assigned

to TSP.MP21 WGRs ICCP

Meteorological Telemetry

6/30/2010REs (only

WGRs)

Registered MW Capacity Ratio Share

N/A N/A N/A N/AWGRs must meet

reasonability tests for MET ICCP

To be determined

MP23 Telemetry Quality (MP to ICCP

server)

6/30/2010 TSPsOwnership Ratio Share N/A N/A N/A N/A

# of TSP(n) Suspect/Bad points

provided / # of TSP(n) points total

1077 Suspect/Bad points (98.3% good

quality).

6/30/2010 QSERsGeneration Ratio Share

N/A N/A N/A N/A

# of QSER(n) Suspect/Bad points

provides / # of QSER(n) points total

277 Suspect/Bad points (98% good quality)

Network Modeling Metrics

1. MP6 does not include 405 QSE CB and DSC points from TSP outreach. ERCOT is determining whether these rollback into the QSER MP6 measurement.

Technical Advisory Committee5 August 2010

Page 48: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

48

Network Model Metrics

Network Modeling Metrics

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red %Not

Scored %Primary Criteria Notes

ERCOT MetricsEMO9(A) State

Estimator Standards Performance

Amber ERCOT N/A N/A N/A N/A N/AState Estimator

converges 97% during monthly test period

95.44% Convergence for State Estimator for

the month of May.

EMO9(B) RTCA Modeling Differences

Green ERCOT N/A 96.8% N/A N/A N/A95% of impedance

values matched between Zonal/Nodal

97.9% match for impedances for lines

and transformers. 6718 lines and transformers in

Nodal.

Green ERCOT N/A 96.8% N/A N/A N/A95% of dynamic line

ratings matched between Zonal/Nodal

97.5% match for ratings for lines. 5288 lines in

Nodal.

Red ERCOT N/A N/A N/A 84.33 N/A95% of load tap setting

values matched between Zonal/Nodal

84.3% Match for transformer tap settings.

1430 xfrms in Nodal.

EMO10 Anomalous / Auto-Disabled

Telemetered PointsGreen ERCOT N/A 1.91% N/A N/A N/A

The % of Anomalous and Auto-Disabled

Measurements < 2% of Total Measurements

April Nodal 2.58%May Nodal 1.92%June Nodal 1.91%

EMO9(C) RTCA CSC Comparison

7/14/2010 ERCOT N/A N/A N/A N/A N/ACSC Pre-contingency SE Flows within 5% (Hourly snapshot)

Measurement establishes baseline flows on Commercial lines to indicate the

significance of Psuedo modeling and multi-

section lines on the SE flows.

EMO9(D) Validate Zonal and Nodal Security Analysis

Results

9/8/2010 ERCOT N/A N/A N/A N/A N/A

90% of active constraints in Zonal

RTCA are also detected in Nodal

RTCA

To be determined

Technical Advisory Committee5 August 2010

Page 49: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

49

Other Readiness Metrics

Metric NameCurrent Score

Applies to

Weight Green % Yellow % Red % Not Scored % Primary Criteria Notes

Market Participant MetricsMP20 Outage

Scheduler Connectivity Qualification

Green QSERsGeneration Ratio Share

98.9% 0.0% 0.0% 1.1% Successful submission of OS

transactions

78/79 QSERS qualified.

Green TSPsOwnership Ratio Share

99.7% 0% 0% .3% 20/23 TSPs qualified.

MP11 Resource Registration

Green REsRegistered

MW Capacity Ratio Share

99.6% 0.0% .4% 0.0%

Decision Making Authority form submitted, and

GENMAP validated

154/157 Resources completed.

CO2 Verify Dispute Process

7/14/2010QSERs, QSEs

Generation Ratio Share,

Even Weighting

N/A N/A N/A N/A

>=1 dispute submit per MP. # of unprocessed

disputes by 168 = 0

To be determined

ERCOT Metrics

E1 ERCOT Staff Completes Training

Green ERCOT N/A 100% N/A N/A N/A

Training plans must be adhered

to for highly impacted

departments

15 out of 15 highly impacted departments are up to date with their

training plans.

E9 Develop Nodal Procedures

Green ERCOT N/A 100% N/A N/A N/A

Procedures developed 1

month prior an exercised in the

appropriate Market Trials Phase

All MT4 and MT5 are developed and the MT4 procedures exercised as scheduled in MT4.

EMO3 Verify Outage Evaluation System

FunctionalityGreen ERCOT N/A N/A N/A N/A N/A

A test of the Outage

Management Process is completed

OS to OE integration tested throughout Market Trials and

reviewed at 6/23 NATF

Technical Advisory Committee5 August 2010

Page 50: Nodal Program Update Jason Iacobucci Nodal Program Manager Technical Advisory Committee 5 August 2010

50

Participant Readiness Touch Points

20102010

Meetings

Training

Outreach

Market trials

SeptemberAugustJuly

• NATF 7/8

• MRS #5 168 Hour Test (Tentative)

• Dispute & Reports Metrics

• Standby site visits

• Weekly Trials calls• 48 hr system-wide

LFC test• Verifiable costs

loaded into N-Prod

• Nodal 101• Transmission 101• Generation 101, 201• Basic Training

Program• NOIE QSE Operations• Settlements 301

• Weekly Trials calls• Prepare for 168 hr

test

• NATF 8/19

• Nodal 101• Transmission 101• Generation 101, 201• Basic Training

Program• NOIE QSE Operations• Settlements 301

• Standby site visits

• Weekly Trials calls• Execute 168 hr test

• NATF 9/14

• Nodal 101• Transmission 101• Generation 101, 201• NOIE QSE Operations• Settlements 301• MMS & MIS GUI

(Online only)

• Standby site visits

October

• Preparation for Nodal Go-Live

• NATF 10/5

• TBD

• TBD

Technical Advisory Committee5 August 2010