Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
1 nrrnrrni 0000073620
EXPERIMENTAL~-~~ ... ~·· ~----· ............. ~ ........ RACKED CONCRETE
COLUMN REPAIRED BY JACKETING METHOD
MUHAMMAD ZULIIlLMI BIN ALI
A report submitted in partial f ulf'dment of the
Requirements for the award of the degree of
Bachelor of Civil Engineering
Faculty of Civil Engineering and Earth of Resources
University Malaysia Pahang
JUNE2012
ii
vi
ABSTRACT
This study is to investigate the strength, crack pattern, and failure pattern in
crack concrete colmnn repair by jacketing method. The scope of this research is
limited to overloading load and the sample is made using concrete G25. The
reinforcement concrete has been design and analyse according to BS5950 with T12
for main bar and R6 for shear link. Two samples with colmnn size of 125 mm x 125
mm x 1500 mm was prepared for repair method, and the structural test is carried out
after reach 28 days strength using strong floor machine with rate 0.55 mm per
minute. The samples were preloaded under axial compression to its ultimate load;
repair using jacketing method in grouting mortar and then retested to failure. The
result show that the original maximum load indicate highest value compare to
maximum load after repaired by jacketing method. Diagonal crack is observed in
original colmnn and transverse crack is observed in colmnn after repaired. As
conclusion, the jacketing method used in this study failed to restore the strength of
cracked concrete colmnn.
vii
ABSTRAK
Kajian ini adalah untuk menyiasat kekuatan, corak retak, dan corak kegagalan
untuk tiang konkrit yang retak menggunakan kaedah jacketing. Skop untuk: kajian ini
adalah terhad disebabkan beban muatan yang berlebihan dan sampel itu dibuat
menggunakan konkrit 025. Konkrit tetulang telah direka bentuk dan dianalisa
berdasarkan kepada BS5950 dengan Tl2 bar utama dan R6 bar ricih. Dua sampel
dengan saiz 125 mm x 125 mm x 1500 mm telah disediakan bagi kaedah pembaikan,
dan ujian struktur dijalankan selepas kekuatan 28 hari jangkauan yang menggunakan
mesin lantai yang kukuh dengan kadar 0.55 mm seminit. Sampel yang telah dimuat
mampatan paksi kepada beban muktama; pembaikan jacketing dengan menggunakan
kaedah Grouting mortar dan kemudian diuji semula sehingga kegagalan. Hasilnya
menunjukkan bahawa beban maksimum asal menunjukkan nilai tertinggi berbanding
dengan beban maksimum selepas dibaiki oleh kaedah jacketing. Retak pepenjuru
diperhatikan dalam ruang asal dan retak melintang diperhatikan dalam ruang selepas
dibaiki. Sebagai kesimpulan, kaedah jacketing yang digunakan dalam kajian ini
gagal untuk mengembalikan kekuatan konkrit tiang yang retak.
I
viii
TABLE OF CONTENTS
CHAPTER TITLE PAGE
CERTIFICATION OF THESIS CERTIFICATION BY SUPERVISOR I
TITLE PAGE 11
AUTHOR'S DECLARATION lll
DEDICATION IV
ACKNOWLEDGEMENTS v ABSTRACT VI
ABSTRAK Vll
TABLE OF CONTENTS viii LIST OF TABLES IX
LIST OF FIGURES x LIST OF ABBREVIATIONS XI
LIST OF SYSBOLS Xll
CHAPTER I INTRODUCTION
1.1 Introduction 1 1.2 Problem statement 2 1.3 objective 3 1.4 Scope of study 3 1.5 Significance of study 3
CHAPTER2 LITERITURE REVIEW
2.1 Introduction 4 2.2 Type of repair column 5 2.3 Crack 5 2.4 Method of concrete repair 6
2.4.1 Jacketing technique 6 2.4.2 Epoxy resin injection technique 6
CHAPTER3 METHODOLOGY
3.1 Introduction 7 3.2 Analysis of reinforcement concrete column 7
3.2.1 Introduction 7 3.2.2 Design column specimen 8
I
3.3 Concrete 9 3.3.1 Introduction 9 3.3.2 Aggregate 9 3.3.3 Cement 9 3.3.4 Water 10 3.3.5 Steel Bar 10
3.4 Formwork 11 3.5 Concrete mix design 12
3.5.1 Mixing concrete process 12 3.6 Curing 14 3.7 Column crack 14 3.8 Repair method 15
3.8.1 Jacketing technique 15 3.9 Quality control of concrete 16
3.9.1 Introduction 16 3.9.2 Workability 16 3.9.3 Slump test 16 3.9.4 Concrete compression test 17
3.10 Test for column crack 19 3. I l Analysis of data 20
3. I I . I .Analysis crack pattern 20 3.I 1.2.Strength of column crack 20
CHAPTER4 RESULT AND DISCUSSION
4.1 Introduction 21 4.2 Cube test result 2I 4.3 Expected result 22 4.4 Maximum load for structure test 22
4.4.1 Original column specimen l 22 4.4.2 Specimen 1 repair using jacketing 23
method 4.4.3 Original column specimen 2 25 4.4.4 Specimen 2 repair using jacketing 26
method 4.4.5 Maximum loading result comparison and 28
analysis
4.5 Crack pattern 30 4.5.1 Original column specimen 1 & 2 30 4.5.2 Specimen 1 & 2 repair using jacketing 31
method 4.5.3 Crack pattern comparison and analysis 32
CHAPTERS CONCLUTION AND RECOMMENDATION
5.1 Introduction 33 5.2 Brief conclusion 33
5.2.l Comparison the Strength Produce 33 Between Original Column Specimen and
after Repairing using Jacketing Method 5 .2.2 The Type of Crack Due to Load between 34
Original Specimen and After Repair Using Jacketing Method
5 .3 Recommendation 34
REFERENCES 36
APPENDIX A B c D
Column design calculation Mix design Compression test Result
37 38 39 40
TABLE NO. 3.1 4.1 5.1
LIST OFT ABLES
Ratio of concrete Cube test result Result
TITLE
ix
PAGE 12 39 40
x
LIST OF FIGURES
FIGURE NO TITLE PAGE 1.1 Column crack on site 2 3.1 Square section of column 8 3.2 Dimension of column 8 3.3 Cross section column 10 3.4 Side view of column 11 3.5 Formwork 12 3.6 Concrete mixer 13 3.7 Curing process 14 3.8 Additional of reinforcement 15 3.9 Pour grouting mortar into formwork 15 3.10 Slump test apparatus 17 3.11 Compression test machine 18 3.12 Strong floor 19 3.13 Loading arrangement 20 4.1 Arrangement of column inside the strong floor specimen 22
1 4.2 Load versus displacement specimen 1 23 4.3 Situation of the column after the maximum load is 24
applied specimen 1 4.4 Load versus displacement after re-test specimen 1 24 4.5 Arrangement of column inside the strong floor specimen 25
2 4.6 Load versus displacement specimen 2 26 4.7 Situation of column after the maximum load is applied 27
specimen2 4.8 Load versus displacement after re-test specimen 2 27 4.9 Load versus displacement for specimen 1 29 4.10 Load versus displacement for specimen 2 29 4.11 The crack pattern at top of column 30 4.12 The crack pattern at bottom of column 30 4.13 The pattern crack at top of column after repair 31 4.14 The pattern crack at bottom of column after repair 31 5.1 Enlargement column 34 5.2 Jacketing with steel plate 35
RC
C35
G25
ACI
BS
ASTM
MS
LIST OF ABBREVIATIONS
Reinforcement concrete
Column 35
Grade 25
American concrete institute
British Standard
America Society for Testing and Material
Malaysia Standard
xi
xii
LIST OF SYMBOLS
% Percent
0 Degree
mm Millimetre
N Newton
fy Reinforcement characteristic strength
kN Kilo Newton
Po Ultimate strength
fc Concrete characteristic strength
Ac Area of concrete
Ast Area of steel
1
CHAPTER I
INTRODUCTION
1.1 Introduction
Industrial training is a valuable expenence for every student. Whether
consultant, contractor or developer, the experience only have in industrial training.
I 00% experience on site will be having in contractor. Experience on site different
from what we learn in university. In site, we exposed more toward on installation of
every each structure element such as slab precast, RC beam, and enlargement
column.
Various problems occur at site whether problem in architect drawing not
same with structure drawing. This entire problem can disturb the project progress.
The major problem that gives the critical problem on site is crack in structure
element. Many damaged concrete structure with various types of crack were
repaired. For economic concern, this damage was repaired with some technique and '
method better than construct new building. This technique can restore strength of the
structure that applies.
2
1.2 Problem statement
In my industrial training, there is one problem that occurs during
construction. One of column C35 was crack during construction. Because of this
column, some activity cannot run as schedule. It gives us problem to complete that
project as planning before.
As solution on this problem, the contractor comes out with their solution to
rectification this problem. There are methods that were suggested from contractor is
jacketing technique. This method can restore the strength the column.
Figure 1.1: column crack on site
3
1.3 Objective
The objectives of the study are:
I. To compare the strength produce between original column specimen
and after repair using jacketing method.
2. To study the type of crack due to load between original specimen and
after repair using jacketing.
1.4 Scope of study
The scope of this research is the column crack due to overloading load. There
is one type of rectification that used to restore the strength of column cracked. The
maximum loading after repair using the jacketing technique will compare with the
maximum loading for the column without repair using jacketing method. This
method just for study there effect of strength to that column crack. The concrete
grade which will be used to make the sample for testing to be carried out is concrete
G25. This sample must create a crack after 28 day. Cube test will be carried out on 7,
14 and 28 day age of concrete.
1.5 Significance of study
This study is to investigate type of method use to rectification the column
crack until their strength restore. For technical and financial reason, these methods
which are times saving, have more simple procedure to carry out and required lower
cost are more appealing to the industry.
4
CHAPTER2
LITERATURE REVIEW
2.1 Introduction
Reinforcement concrete is one of the most widely used modem buildings.
Concrete is combination by mixing cement, sand, and aggregates with water.
Reinforcement concrete is a strong building material that is formed into many shapes
and sizes ranging. It almost common used in construction work compare to the
reinforcing steel in worldwide. Reinforcing steel require expensive manufacturing
mills compare to the concrete production. The extensive use of reinforced concrete
construction its relatively low cost compare to other materials such as steel.
5
2.2 Type of repair column
The main cause for RC column with the need to undergo rectification are
large spacing of tie in columns, the use of 90° hooks, close tie spacing, and to meet
stringent existing building code requirement. (Abdullah, and K.Takiguchi, 2011)
Column which need to undergo rectification usually have insufficient ductility due to
improper transverse confinement, and insufficient shear strength. (Abdullah, and co,
2011). There is various type of rectification method for RC column. Some of the
method use to rectify RC column is: (a) Ferrocement jacket, (b) high performance
fibre-reinforce concrete jacket.
2.3 Crack
Crack in concrete have many causes. They may affect appearance only, or
they may indicate significant structural distress or lack of durability (Camille A. Issa,
Pauls Debs.2005). Crack always occurs before a concrete structure achieves their
strength or fails. Crack an important role in concrete response to load in both tension
and compression. It very important to first identify the location and extent of
cracking when anticipating repair of crack in concrete (reported by ACI committee
224, ACI 224.lR-93). Crack can be categorized in three groups: cracks due to
inadequate structural performance, cracks due to inadequate material performance,
and acceptable cracks (Tsiatas, 2002). Structural cracks are caused primarily by
overloading; material related cracks are due to shrinkage and chemical reaction; and
acceptable cracks are those that develop due to service level for tensile stresses to be
distributed properly along the length of the material (Tsiatas, 2002).
6
2.4 Method of concrete repair
There many researchers about concrete repair such as seismic performance of
repaired RC column (K.-S. Yown, H.-E. Lee and S.choi, 2006). The restoration of
the strength of cracked concrete was measured for various conditions of the concrete
surfaces (Hindo, K. R., 1990). Repair and rehabilitation work for concrete structures
can broadly be classified into two main categories: (i) repair in which the damage
due to deterioration and cracking is corrected to restore the original structural
capacity and (ii) repair that is necessary to strengthen the structural capacity of a
member whose load carrying capacity has either been inadequate or whose strength
has been severely impaired (Al-Gadhib AH,2003).
2.4.1 Jacketing technique
Jacketing is the most popularly used method for strengthening of building
columns. The common types of jackets are steel jacket, reinforced concrete jacket,
fibre reinforced polymer composite jacket, jacket with high tension materials like
carbon fibre. Jacketing serves to improve the lateral strength and ductility by
confinement of compression concrete. The jacketing of columns is generally carried
out by two methods (i) reinforced concrete column jacketing and (ii) steel jacketing
(Shri, Pravin B, W aghmare, 2011 ).
2.4.2 Epoxy resin injection technique
Epoxy resin is a common used in rehabilitation work. According to ACI
224.lR-93, epoxy resins are commonly used repair materials that generally have very
good bonding and durability characteristics. Structural performance of RC slabs
repaired using epoxy resin injection performed best compared to other repair material
(Calder and Thompson, 1998). The bond between concrete and the injection material
is very critical; a good bond may restore the original stiffuess of the repaired material
and prevent further penetration of chloride ions and water (Minoru et al, 2001). The
crack must be clean and dry prior if not the epoxy resin not applicable.
7
CHAPTER3
METHODOLOGY
3.1 Introduction
In this chapter, vanous aspect of preparation of material, apparatus and
testing sample will be explained. All the aspect will be follow according to the
specification.
3.2 Analysis of Reinforcement Concrete Column
3.2.1 Introduction
Analysis of RC column is an important in this research. It is important to
analysis the strength of RC column before construct the column. It is to ensure that
the design of the column is follow the specification required according to BS 8110-
1 : 1997. The column design calculations refer in appendix A.
8
3.2.2 Design column specimen
For this research, the analysis based on short column with square section. The
column is single reinforcement column.
Figure 3.1: Square section of column
L
Figure 3.2: 3 dimension of column
Dimension of column
b= 125 mm
h= 125 mm
L= 1500 mm
9
3.3 Concrete
3.3.1 Introduction
Concrete is a composed mainly of three materials, namely, cement, water
aggregate, and an additional material, known as an admixture. The selection of
concrete proportions involves a balance between economy and requirements of
placeability, strength, durability, density, and appearance.
3.3.2 Aggregate
The coarse and fine aggregate will be used in this research. There are between
ranging from 10 mm to 20 mm for coarse and less than 5 mm for fine aggregate. The
standard specification for concrete aggregate is described in ASTM C33-03 (ASTM
2003).the aggregate will be air dried to ensure that are no moisture content in
aggregate. This is because the moisture content of the aggregate can affect the
performance of the concrete. Aggregate also considerably improves both the volume
stability and the durability of the resulting concrete.
3.3.3 Cement
Cement is a material that has adhesive and cohesive properties enabling it to
bond mineral fragments into a solid mass. The different cements used for making
concrete are finely ground powders and all have the important property that when
mixed with water a chemical reaction take place which, in time, produces a very hard
and strong binding medium for the aggregate particles. The cement used in this study
is ordinary Portland cement. Type 1 Portland cement as in ASTM C150-05 (ASTM
2005c) was used throughout the study.
10
3.3.4 Water
Water used in concrete in addition to reacting with cement and thus causing it
to set and harden, also facilitates mixing, placing and compacting of the fresh
concrete. It is also used for washing the aggregates and for curing purposes. The
clean water in accordance to MS 28 is used.
3.3.5 Steel bar
Both mild steel (fy = 250 N mm2) and high strength steel (fy = 460 Nmm2
) will
be used in this research. The high strength steel will be used as main bar whereas the
mild steel will be used as bent-up links. The dimension of steel are selected while
design the reinforcement according to BS 8110.
Ill .. 125 mm
• •
125mm
Figure 3.3: Cross section column
11
2T12 ii\
1 ~ -, ..... R 6 - 200
_, 125mm
~ -'
~,.
1500 mm \ ,,
2T12
Figure 3.4: Side view of column
3.4 Formwork
In this research, timber formworks were used to mould the column having
size of 125 x 125 x 1500 mm. The advantage of using plywood formwork over other
type is that it can mould bigger and produce smooth surface concrete. So that, the
timber formwork is the best choice due to its flexibility and cost.
Prepare formwork
a) Determine and calculate the quantity of plywood required for the
structure.
b) Measured and draw line or mark on the plywood according to the
required dimension. This step is repeated for supporting member and
braces.
c) Using sawing cut the plywood based on the line done in step 2.
d) Using sand paper, clean the plywood to ensure that the plywood is free of
dust and other debris.
e) Nails the plywood together using hammer.
f) Place supporting member and braces to secure the formwork.
12
Figure 3.5: form.work
3.5 Concrete Mix Design
The column were used concrete grade 25 will be used for column in this
research. The dimension of the column is the same as the design that is 125 x 125 x
1500 mm. The column casting in horizontal same as beam casting. Mix design table
refer appendix B.
Cement Water Fine agg. Coarse agg.
I column 11.76 kg 5.88 kg 19.32 kg 30.24 kg
Table 3.1: Ratio of concrete
3.5.1 Mixing Concrete Process
Procedure for mixing concrete is followed by BS 1881: Part 125-1989
(Testing concrete. Methods for mixing and sampling fresh concrete in the
laboratory). Procedures for mixing concrete are as below:
13
a) Prepare the mixer before mixing concrete. be sure the surface of the mixer is
wet.
b) Put the coarse and fine aggregate in the mixer.
c) Star the mixer. Let it mix for 15 minutes.
d) Add about haft of the water in the mixer and mix it for 2 minutes.
e) Carefully add all the cement with the mixer running and mix it for 30 seconds
until all the cement is blended in.
f) Add enough water from the final half of the water to produce a workable mix
and mix it for 2 minutes.
g) Perform a slump test (BS 1881: Part 102, method of determination of slump).
h) Cast the cube in order to determine the compressive strength of the concrete
and out of the mix or column casting.
i) After 24 hours, the cube and column should be stripped and cured in the
water tank (BS 1881: Part 111: 1983, method of normal curing of test
specimen.
Figure 3.6: Concrete mixer
14
3.6 Curing
The purpose of curing is to promote the hydration of cement, thus the
development of strength and durability of concrete. It also controls the temperature
and moisture movement from and into the concrete. While the column samples it
take 28 days to achieve good strength for concrete. Cure the sample by cover it with
jute and water is spray at the interval of 1 hour.
Figure 3.7: Curing process
3. 7 Column crack
Column crack for this research is due to overloading load. The crack of
column was using strong floor equipment.
Step of produce column crack:
a) Setup the column on the equipment.