2
7650 InSite – Construction issues for the Middle East January 2015 – Issue No. 1 How ‘fixed’ are your Liquidated Damages? We all know that an employer’s entitlement to liquidated damages has a significant impact on contractors and the supply chain. If the contractor misses a contractual milestone, most contracts in Qatar and the UAE allow employers to levy liquidated damages. Liquidated damages permitted Liquidated damages are permitted under both the UAE and Qatari Civil Codes. As elsewhere in the world, the liquidated damages clause fixes a sum within the contract which is due on the occurrence of delay to an event or milestone. The often- stated purpose of such a clause is to provide certainty of risk at the contract negotiation stage if completion is delayed. However, in reality, liquidated damages primarily benefit an employer, as the clause removes the burden on the employer to prove it incurred those damages. In some jurisdictions liquidated damages cannot be so excessive that they ‘punish’ the contractor. In the UAE and Qatar this is not an issue. Freedom to contract The literal translation of “liquidated damages” in Arabic is “fines”. Both the UAE and Qatari Civil Codes allow parties to agree any level of future liquidated damages (or “fines”), even if the amount is arbitrary or excessive. This reflects both jurisdictions’ primary principle of freedom to contract. However, in both jurisdictions, this is subject to the discretion of the courts (and arbitrators applying the Civil Code). They may adjust the amount of liquidated damages to reflect the actual loss suffered in order to prevent one party obtaining an unjustified windfall. Assessing damages The UAE and Qatari Civil Codes differ in the way they assess liquidated damages. In the UAE, Article 390(1) of the Civil Code allows the parties to agree a fixed amount of damages in advance. Article 390(2) allows the court, when asked, to decrease or (importantly) increase the amount of damages to reflect the actual loss suffered. This discretion to increase the level of damages presents a serious risk for a contractor considering legal action. As the Code emphasises the parties’ freedom to contract, our experience is that the UAE courts require robust evidence to show a disparity between the actual loss suffered and the specified damages. However, it can happen. In the UAE Federal Supreme Court, case 103 of 2004, the court ruled that the rate of liquidated damages fixed by the contract was overestimated compared to the damage suffered by the party imposing the damages and therefore should be reduced. Unlike the UAE, the Qatari Civil Code does not allow a court to increase the rate of liquidated damages, except in the case of fraud. They may only maintain or reduce the level of damages. Welcome to the first issue of our bulletin focusing on construction industry issues in the Middle East. When your project is delayed do you know how the liquidated damages provisions work? How are liquidated damages assessed? In this issue, we consider these key contractual issues in the Qatari and UAE construction markets. Continued on next page >

nSite Construction issues for the Middle ast - Pinsent … Construction issues for the Middle ast ... 56 of Law No. 26 of 2005). In Qatar, ... + 971 4 373 9700 Dubai,

  • Upload
    vulien

  • View
    215

  • Download
    2

Embed Size (px)

Citation preview

Page 1: nSite Construction issues for the Middle ast - Pinsent … Construction issues for the Middle ast ... 56 of Law No. 26 of 2005). In Qatar, ... + 971 4 373 9700 Dubai,

7650

InSite – Construction issues for the Middle EastJanuary 2015 – Issue No. 1

How ‘fixed’ are your Liquidated Damages? We all know that an employer’s entitlement to liquidated damages has a significant impact on contractors and the supply chain. If the contractor misses a contractual milestone, most contracts in Qatar and the UAE allow employers to levy liquidated damages.

Liquidated damages permittedLiquidated damages are permitted under both the UAE and Qatari Civil Codes. As elsewhere in the world, the liquidated damages clause fixes a sum within the contract which is due on the occurrence of delay to an event or milestone. The often-stated purpose of such a clause is to provide certainty of risk at the contract negotiation stage if completion is delayed. However, in reality, liquidated damages primarily benefit an employer, as the clause removes the burden on the employer to prove it incurred those damages.

In some jurisdictions liquidated damages cannot be so excessive that they ‘punish’ the contractor. In the UAE and Qatar this is not an issue.

Freedom to contractThe literal translation of “liquidated damages” in Arabic is “fines”. Both the UAE and Qatari Civil Codes allow parties to agree any level of future liquidated damages (or “fines”), even if the amount is arbitrary or excessive. This reflects both jurisdictions’ primary principle of freedom to contract. However, in both jurisdictions, this is subject to the discretion of the courts (and arbitrators applying the Civil Code). They may adjust the amount of liquidated damages to reflect the actual loss suffered in order to prevent one party obtaining an unjustified windfall.

Assessing damagesThe UAE and Qatari Civil Codes differ in the way they assess liquidated damages. In the UAE, Article 390(1) of the Civil Code allows the parties to agree a fixed amount of damages in advance. Article 390(2) allows the court, when asked, to decrease or (importantly) increase the amount of damages to reflect the actual loss suffered. This discretion to increase the level of damages presents a serious risk for a contractor considering legal action.

As the Code emphasises the parties’ freedom to contract, our experience is that the UAE courts require robust evidence to show a disparity between the actual loss suffered and the specified damages. However, it can happen. In the UAE Federal Supreme Court, case 103 of 2004, the court ruled that the rate of liquidated damages fixed by the contract was overestimated compared to the damage suffered by the party imposing the damages and therefore should be reduced.

Unlike the UAE, the Qatari Civil Code does not allow a court to increase the rate of liquidated damages, except in the case of fraud. They may only maintain or reduce the level of damages.

Welcome to the first issue of our bulletin focusing on construction industry issues in the Middle East.When your project is delayed do you know how the liquidated damages provisions work? How are liquidated damages assessed? In this issue, we consider these key contractual issues in the Qatari and UAE construction markets.

Continued on next page >

Page 2: nSite Construction issues for the Middle ast - Pinsent … Construction issues for the Middle ast ... 56 of Law No. 26 of 2005). In Qatar, ... + 971 4 373 9700 Dubai,

InSite – Construction issues for the Middle EastJanuary 2015 – Issue No. 1

To successfully reduce the rate of liquidated damages in Qatar, the contractor must demonstrate that the pre-estimate of damages was “grossly excessive” to the harm actually suffered or that no loss was suffered at all. By contrast, according to the equivalent provision of the UAE Civil Code, the court may adjust the agreed amount of compensation “under any circumstances”, so that it is equal to the actual loss.

Qatar and extensions of timeIt is not all good news for contractors in Qatar. The Qatar Tenders Law entitles government entities who are employers to impose an additional penalty of up to 10% of the contract price in the event that an extension of time is granted to the contractor (see Article 56 of Law No. 26 of 2005).

In Qatar, in contrast to the UAE, parties can be assured that according to the Civil Code liquidated damages will not be increased by the court to reflect the actual loss suffered. While freedom to contract remains key in both jurisdictions, in reality the discretion of the courts in Qatar and, more particularly, in the UAE, may lead to uncertainty as to recovery of liquidated damages.

7650

“The discretion of the courts may lead to uncertainty as to recovery of liquidated damages.”Charlotte Holmes, Associate

This note does not constitute legal advice. Specific legal advice should be taken before acting on any of the topics covered.Pinsent Masons LLP is a limited liability partnership registered in England & Wales (registered number: OC333653) authorised and regulated by the Solicitors Regulation Authority and the appropriate regulatory body in the other jurisdictions in which it operates. The word ‘partner’, used in relation to the LLP, refers to a member of the LLP or an employee or consultant of the

LLP or any affiliated firm of equivalent standing. A list of the members of the LLP, and of those non-members who are designated as partners, is displayed at the LLP’s registered office: 30 Crown Place, London EC2A 4ES, United Kingdom. We use ‘Pinsent Masons’ to refer to Pinsent Masons LLP, its subsidiaries and any affiliates which it or its partners operate as separate

businesses for regulatory or other reasons. Reference to ‘Pinsent Masons’ is to Pinsent Masons LLP and/or one or more of those subsidiaries or affiliates as the context requires. © Pinsent Masons LLP 2015.

For a full list of our locations around the globe please visit our website: www.pinsentmasons.com

“Both Codes allow parties to agree any level of future liquidated damages, but beware that the level may be challenged in the local courts.”Matthew Heywood, Senior Associate

Pinsent Masons Dubai Level 8 The H Hotel, Office Tower,Sheikh Zayed Road, P.O. Box 115580,+ 971 4 373 9700Dubai, United Arab Emirates

Pinsent Masons Qatar QFC Branch,Tornado Tower,West Bay,PO Box 22758,+974 442 69200Doha, State of Qatar

Pinsent Masons have consistently won Global Construction Law Firm of the Year every year since 2008 including the award in 2014 (Who’s Who Legal Awards). For more information on the issues raised in this article and other enquiries about our services, please contact:

Upcoming regional events:

24 February 8:00 am – 9:30 am Construction Breakfast Briefing, Emirates Towers, Dubai, UAE

4 March 6:30 pm registration 7 pm start Unforeseeable Ground Conditions Seminar, La Cigal, Doha, Qatar