nTof Civil engineering Status -5 July 2013 • EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 • CERN preparatory works (antennas removal, radio club barrack removal, asbestos removal B559, deviation of the optical fibre, power and water temporary supply for the worksite) finished on 30/04/2013 • Contractor’s main works started on 13/05/2013: Done : – Worksite installation – Demolition of barrack 559 – Deviation of the existing networks – Earthworks – Beam shaft and opening ɸ80 in the roof of the nTOF technical gallery – Piles Ongoing: – Concreting of the building foundations on the ISR slab L.A.Lopez

NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Embed Size (px)

Citation preview

Page 1: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

nTof Civil engineeringStatus -5 July 2013

• EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013

• CERN preparatory works (antennas removal, radio club barrack removal, asbestos removal B559, deviation of the optical fibre, power and water temporary supply for the worksite) finished on 30/04/2013

• Contractor’s main works started on 13/05/2013:

Done:– Worksite installation– Demolition of barrack 559– Deviation of the existing networks– Earthworks– Beam shaft and opening ɸ80 in the roof of the nTOF technical gallery – Piles

Ongoing:– Concreting of the building foundations on the ISR slab

L.A.Lopez

Page 2: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Désamiantage

Dépose baraque du Radio-club

Page 3: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Démolition B559

Page 4: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Terrassement

Cérémonie 1er

coup de pelle

Page 5: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Puits du faisceau

Carottage faisceaudans galerie nTOF

Page 6: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Puits fini du faisceau

Déviation des réseaux

Page 7: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Réalisation des pieux

Page 8: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Planning “objectif”

Page 9: NTof Civil engineering Status -5 July 2013 EDMS approval procedure for « Execution drawings » launched on 24/05/2013. Drawings approved on 10/06/2013 CERN

Next steps

• Concreting works → September 2013

• Finishing works (waterproofing, insulation, doors, « chape », painting) → October-November 2013

• Landscaping → November 2013