NTPC’s Endeavors towards ESG Improvement18.03.2021

NTPC Kayamkulam NTPC Ramagundam NTPC Koldam NTPC Talcher Kaniha NTPC Dadri

NTPC Bhadla NTPC Simhadri NTPC Rojmal Touching Lives through CSR Promoting Safety

Page 2: NTPC’s Endeavors towards ESG Improvement

1• NTPC Overview

2• Key Business Growth Drivers

3• ESG Roadmap

Discussion Outline

Page 3: NTPC’s Endeavors towards ESG Improvement

NTPC Overview

1

Page 4: NTPC’s Endeavors towards ESG Improvement

NTPC: Vision, Mission and Core Values

Core Values

I C O I TM

To be the World’s Leading Power Company, Energizing

India’s Growth

Provide Reliable Power and Related Solutions in an Economical, Efficient and Environment friendly manner,

driven by Innovation and Agility

Vision Mission

Low cost, low emission and Highest Safety

Page 5: NTPC’s Endeavors towards ESG Improvement

About NTPC

Group installed capacity of 64,880 MW; generation of 295 BUs in FY21 (till date)

Total sales crossed $ 13 Bn (8% y-o-y) in 9MFY21

Registered 7 % of growth in generation vs -2 % of all India in FY21 (till date)

Added 2949 MW of commercial capacity in FY21 (till date)

7.25 % of generation fleet is carbon free, targets to cross 30% mark by 2032

Implementing “The Brighter Plan 2032” to improve ESG performance

Adjudged winner in CII-ITC Sustainability Awards for FY19 & FY20

Reliable electricity generator during COVID; provided food, PPE kits, hospital facilities

Ranked No.2 Independent Power Producer in the world by PLATTS in 2020

Page 6: NTPC’s Endeavors towards ESG Improvement

Expanding Presence across the Nation

Kerala 360MW

Tamil Nadu 1500 MW

Maharashtra 5607 MW

Gujarat

1363MW

A&N Islands

5 MW

Share of Electricity Generated

(as on Feb, 2021 )%

All India : 1115.5 BUs NTPC (Group) : 280 BUs

85%

15%

Share of Installed Capacity

(as on Feb, 2021)

All India : 3,79,130 MW

NTPC (Group) : 64,880 MW

78%

Telangana

2610 M+W1700MW

Andhra Pradesh 2250 MW+ 25MW

Karnataka2400MW

Assam

750MW

Rajasthan

679 MW

Bangladesh

1320 MW

eWst Bengal

Uttar Pradesh MW

Madhya Pradesh 5868 M+W2120 MW

Bihar5900 M+W4050MW

Jharkhand4380MW

Odisha

3590 M+W1850MW

Chhattisgarh 6954 M+W800MW

Present + Under Construction Capacity Leading Market Share

17%

83%

25 %

75%

Fuel MixNo. of Plants

Capacity (MW)

NTPC Owned

Coal 24 46,210

Gas/Liquid Fuel 7 4,017

Hydro 1 800

Renewables 13 1088

Sub-total 45 52,115

JVs/ Subsidiaries

Coal 9 7154

Gas 4 2,494

Hydro 8 2,625

Renewables 4 192

Sub-total 25 12765

Total 70 64,880

Present Capacity: 64.88 GW

Reduction of 17 paise in Coal ECR, Savings of Rs 3669 Cr to Discoms

Page 7: NTPC’s Endeavors towards ESG Improvement

Key Business Growth Drivers

2

Page 8: NTPC’s Endeavors towards ESG Improvement

Renewables: Enabling growth & ESG improvement

Highlights: FY 2021

143 270

1322

25873000 3000

FY2020 FY2021 FY2022 FY2023 FY2024 FY2025

RE Capacity Addition Plan in MW

NTPC RE Ltd, incorporated on 07.10.2020

Won 1360 MW under tariff based competitive bidding

160 MW of capacity commissioned

JV Company with ONGC for RE projects in India and abroad

Tender issued for acquisition of 1 GW Solar assets

MOU signed with NIIF for investment in RE

NTPC kayamkulam

128029540

Page 9: NTPC’s Endeavors towards ESG Improvement

Ultra Mega RE Power Parks-Ocean of RE generation

9

RajasthanGujarat

Maharashtra

MP

AP

Land allocated in Kutchh for 4.75 GW UMREPP

MOU to be signed for 5GW UMREPP

MOU signed for 2.5GW UMREPP

Another 140MW Floating Solar near Ujjani Dam

550MW UMREPP to be developed at NTPC Barethi

Application being filed for 4GW UMREPP

Page 10: NTPC’s Endeavors towards ESG Improvement

10

Biomass Co-firing: Game Changer in Sustainable Power Gen.

Biomass co-firing

status

22 KT of Biomass co-fired at 7 NTPC Plants

Order issued for 280 TPD for 4 years for Dadri Plant

Soon to start at another 7 plants

9 months tender issued for immediate supply for 17 Plants.

• Saved 11000 acres of farm fire• Saved around 25 K Tonnes of eq. CO2• Cost for 20 Mn T is Rs. 15165 Cr for 4 years

Page 11: NTPC’s Endeavors towards ESG Improvement

11

Transformation of Power plants to Hydrocarbon Complexes

H2 Generation Buffer Storage H2 Dispensing FCEV FleetGreen Energy

NTPC can become one of the the largest exporters of Green Hydrogen & Green Ammonia/Methanol in Asia due to its strategic location

Green Methanol

PilotAt MP &

Telangana

• H2 for mobility

• H2 Blending in Natural Gas

Page 12: NTPC’s Endeavors towards ESG Improvement

Integrated Energy Company: Diversification Plans

Diversification

Setting up 1000 charging stations (DHI FAME 2)across India, 141 chargers installed Complete e-bus solutions to STUs through NVVN; 40 e-buses in A&N; 90 in Bangalore Hydrogen based mobility in Leh (Intra-city) and on Delhi-Jaipur route based on FCEVs

200 Kw WtE (24 TPD) plant operational at Karsada, Varanasi JV with EDMC for setting up Integrated WtE project in East Delhi Plasma Gasification based WtE Pilot Plant for 50 TPD MSW jointly by NTPC, IOC and SDMC MoUs for WtE projects with municipalities of Varanasi, Indore, Hubli-Dharwad and Bhopal

Actively looking at East Asia,Middle East and Africa for business opportunities

Acquisition of Power Assets

Acquired entire GOI stake in THDC and NEEPCO with installed capacity of 3294 MW and under construction capacity of 3114 MW

EV Business Segment

Waste to Energy Projects

International Business Construction activities of a 1320MW project in Bangladesh are under progress Ten countries finalized with ISA to implement 1500MW solar projects Appointed as PMC by Govt. of Mali for 500 MW solar projects, Engagement with Republic of Togo for

development of 285-MW solar park

Page 13: NTPC’s Endeavors towards ESG Improvement

ESG Roadmap

3

Page 14: NTPC’s Endeavors towards ESG Improvement

Publishing Sustainability Reports as per the latest GRI frameworks since FY2012

Moved from Sustainability Report to Integrated Annual Report in FY2020 as per IIRC & GRI framework

Expanded the boundary of reporting with inclusion of all JVs & Subsidiaries since FY2020

Conducted Materiality Assessment at 20 NTPC locations with internal and external stakeholders

Timely responding to DJSI, CDP questionnaires and other queries of concerned stakeholders

Regular follow-ups and discussions with leading ESG Analysts

ESG: Disclosures & Engagements

FY20Integrated Annual Report

Page 15: NTPC’s Endeavors towards ESG Improvement

ESG: Strategy & Internal Controls

15

Water & Biodiversity Conservation Community Development

Strong Finance & Ethics

Decarbonisation & Air emissions control

Circular Economy Sustainable Supply Chain

Health and Safety

Aligned to core business strategy, 26 KPIs of 7 focus areas on Economic, Social and Environmental fronts

Page 16: NTPC’s Endeavors towards ESG Improvement

4

Lives

Touched

Frequency

Rate

32

Sp. CO2

Emission

1

-17%714 gm/kWh

-3%837 gm/kWh

2012

2022

2032

861gm/kWh 3.81 l/kWh

-34%2.5 l/kWh

-24%2.9 l/kWh

Sp. Water Consumption

.34

TBP 2032: Highlights

6 Mn*

+33%8 Mn

-65%.12

-47%.18

+200%18 Mn

*2020

Page 17: NTPC’s Endeavors towards ESG Improvement

Decarbonization

Efficiency Improvement

GHG Emission Trend

NTPC base load plants will play key role in taking care of RE integration through Flexibilization

Fuel Diversification CCUS R&D

7% of carbon free generation capacity

Decommissioned 705 MW of coal plants

No new green field thermal project

Bio-mass co-firing and WtE plants

Saved 1622 TJ of eq. heat and electrical energy

95% of coal capacity under construction is super/ ultra super critical tech

Earned 170653 of Escertsin PAT scheme

MoU with ONGC for CCU in Jhanor Gandhar

Carbon sink development through plantation of 35 million trees till date

Pilot project for 10 TPDCO2 to Methanol Plant

Development of GreenAmmonia and Urea

Floating solar Offset through fly ash use

232 240 226 252249 233 158 158 98

873876

871 870

868

870

872

874

876

878

0

100

200

300

FY2018 FY2019 FY2020 NTPC Group

Scope 1 (MMT) Scope 2 (00'MT) Scope 3 (0000' MT) Specific GHG Emission(g/kWh)NTPC Bhadla

Page 18: NTPC’s Endeavors towards ESG Improvement

SOx, NOx & PM Emissions

SOx Reduction

FGD/DSI system implemented at 1.3 GW Under implementation at ~59 GW and under tendering at ~5 GW FGD Contracts amounting ~ ₹29,000 crore have been awarded

De NOx Combustion Modification Implemented at 2.5 GW Combustion Modification awarded/under execution for 18GW Inbuilt design for Combustion Modification in 25 GW Combustion Tuning after overhaul for 18 GW Cost of Combustion Modification Awarded ~ ₹ 370 Cr

Firm Action Plan in place to comply with New Environment Norms

Major Initiatives Specific Emissions trend

FGD at NTPC Vindhyachal

SPM Reduction

ESP already modified (R&M) for 10+ GW, Work in advanced stage for 5 + GW; to be completed by 2022

89 89 84

0.27 0.260.22

0

0.1

0.2

0.3

80

82

84

86

88

90

FY2018 FY2019 FY2020

Absolute PM (000' MT) Specific PM (gm/Kwh)

Page 19: NTPC’s Endeavors towards ESG Improvement

Policies

Water Conservation

Water Policy

Rainwater Harvesting Policy

Major Initiatives

Water Accounting

Wastewater Reuse

Process Innovations

Alternate Sources

• Air Cooled Condenser in place of conventional• Higher Cycle of Concentration (COC >5)• Zero Liquid Discharge• Taking cooling water blow down from hot side• Rain Water Harvesting Systems• Dry Bottom Ash Handling System instead of

conventional Wet Bottom Ash Handling System• High Concentration Slurry Disposal• Flue gas based Sea Water Desalination• Regular third party water audit

Trend

ACC Prototype, North Karanpura

561 593 559849

3.063.04 3.15

2.93

2.8

2.9

3

3.1

3.2

0

500

1000

FY 2018 FY 2019 FY 2020 NTPC Group

Total Freshwater Consumption (MCM) Sp. Water Consumption (l/kWh)

Page 20: NTPC’s Endeavors towards ESG Improvement

NTPC Projects

Biodiversity: Green belts & Afforestation

Species

Cassia seamea

Cassia fistula

Dalbergia sisoo

Pongamia pinnata

Azadirachta indica

Syzygium cumini

Prunus dulcis

Terminalia arjuna

Melia azedarach

Annona squamosa

Mangifera indica

Saraca indica

Rihand Singrauli Farakka

Kahalgaon Simhadri Talcher K

NTPC is transforming Badarpur Ash Dyke (884 acres) into an eco Park

Page 21: NTPC’s Endeavors towards ESG Improvement

Coal Power Station Ongoing Hydro Power Projects Gas Power Stations

Ongoing Thermal Projects Solar PV

Map not to scale. Includes capacity of under construction plants

Hydro Power Projects Wind

Sipat 2,980MW

Lara 1600MW

Durgapur(120MW)

Kayamkulam(350MW)

Vallur(1,500MW)

Kudgi(2,400MW)

Ratnagiri(1,940MW)

Solapur(660+660 MW)

Simhadri(2,000MW)

Ramagundam(2,600MW) + (10MW solar)

Mouda (2,320MW)

Kawas(645MW)

Gandhar(648MW)

Talcher Thermal(460MW)

Talcher Kaniha(3,000MW) + 10MW Solar

Bhilai 574MW

Rourkela(120MW)

Korba(2,600MW)

Kahalgaon (2,340MW)

Kanti(610MW)Barh 3,300MW

Nabinagar(1980 MW)

Tanda (1760 MW)

Unchahar (1,550MW) &(10 MW Solar)

Meja (1,320MW)

Vindhyachal (4,760MW)

Singrauli (2,023MW)Incld.15 MW Solar, 8MW Hydro)

Auraiya (652MW)

Anta(413MW)

Jhajjar (1,500MW)

NCTPP (1,820MW)

Faridabad (430MW +5MW Solar)

Dadri (817MW)

Dadri SolarPV (5MW)

Lata Tapovan (171MW)

Koldam (800MW)

A&N Solar PV (5MW)

Rihand 3,000MWFarakka 2,100MW

Bongaigaon (750MW)

Tapovan Vishnugad (520MW)

Gadarwara (1600 MW)

Rajgarh Solar PV, 50 MW

Daralipali(1600MW)

NKP 1980MW

Rammam (120MW)

Khargone 1320 MW

Anantpur Solar(250MW)

BRBCL 1000MW

PVUNL (325MW)

Rourkela Exp. (250MW)

Rojmal40+10 MW

Bhadla(260 MW)

Durgapur(40MW)

Mandsaur Solar PV, 250 MW

Telangana 1000MW

Patratu 2,400MW

Species IUCN Red List Picture

Sloth bear (Melursusursinus)

Vulnerable

Black Buck (Antilope cervicapra)

Near Threatened

Gangetic Dolphin (Platanista gangetica)

Endangered

Cheer Pheasant(Catereus wallichii)

Threatened

Elephant(Elephas maximus)

Endangered

Great Indian Bustard (Ardeotis nigriceps)

Critically endangered

Olive Ridley Turtles(Lepidochelysolivacea)

Vulnerable

Biodiversity: Wildlife Conservation Plans

NTPC with US-AID developing Biodiversity Project "Narmada Landscape Restoration Project" along River Narmada

Page 22: NTPC’s Endeavors towards ESG Improvement

NTPC consistently featured as a great workplace for last 12 years by Great Place to Work and The Economic Times

Employee Development

Major Initiatives

Top employee benefits, Lowest attrition (<1%) rate as per industry standards

Mandatory Job rotation, global training and exposure and career linked planned interventions

Leadership programs and digital learning platforms from elite academic institutions (Harvard, Wharton)

CLIMS in place at all NTPC locations enabling payment of labour wages on 1st day of month

Trend

0.44 0.40 0.35

0.00

0.20

0.40

0.60

FY 2018 FY 2019 FY 2020

Man-MW ratio

32 35 39

0

50

FY 2018 FY 2019 FY 2020

Average Training hours (Hr / Emp/ Year)

Page 23: NTPC’s Endeavors towards ESG Improvement

Health & Safety

Policy

Safety Policy

Major Initiatives

Enabling & Monitoring System• Upgradation of safety standards from OHSAS 18001 to ISO 45001• Adherence to specific safety guidelines for Gas, Hydro, Mining• Strengthening of Safety MIS (leading & lagging indicators)• Safety App & Tracking safe-man hours on daily basis• Implementation of CLIMS

Culture Building• Peer-to-peer coaching to address unsafe behaviours• Uniform training system• NTPC Zero Deviation Plans (NZDP)- Life saving Rules• Safety Academy at NTPC Unchahar• Safety weightage in Performance Appraisal

Capacity Building• Skill based process trainings, handholding by international consultants• Safety park with practical exposure to safety gears and equipment

Trend

0.3 0.31

0.18

0

0.2

0.4

FY 2019 FY 2020 FY 2021 (Till Feb)

Frequency Rate (FR)

In Our objective is to ensure “Zero Incidents” at work

Page 24: NTPC’s Endeavors towards ESG Improvement

Ash Utilisation

Ash Policy

Grand Challenge for Ash Utilization: Nano Concrete aggregates, artificial sand and fly ash-gypsum plaster based AU

Bulk Transportation of Fly Ash through Railways, 3 BTAP wagon racks procured

Ash park established at Varanasi and Rewa, under process Raipur, Bhubaneshwar & Pune

Ash back filling in Mines: Started from Korba , Talcher Thermal, Ramagundam; starting soon at other 2 places

Pond Ash: Being supplied to NHAI road projects, 17 MMT issued in FY21 (till feb 28)

PolicyTrends

Major Initiatives

amended to incentivize usage by cement industries

6566

67

55%65%

76%

0%

50%

100%

64

65

66

67

68

FY18 FY19 FY20

Ash Produced (MMT) Ash Utilisation (%)

In FY’20, 15 stations achieved 100 % Ash utilisation

Page 25: NTPC’s Endeavors towards ESG Improvement

Community Development

Policies

CSR Policy

R&R Policy

ICD Policy

Major Initiatives

4 major thrust areas- Health, Sanitation, Education and Water

Girl Empowerment Mission (GEM) at 23 locations in FY 2020, covering 1800+ school girls

Enhanced agricultural incomes by improving farm productivity, more than 2000 farmers benefitted

Integrated Livestock Development programme, more than 6000 farmers benefitted

Special Burn Centre at AIIMS Patna, Bhubaneshwar and KGMC, Lucknow

Adopted 18 Industrial Training Institutes (ITIs), setting up of 8 new ones

MoU with National Skill Development Corporation (NSDC) to develop the skills of 30000 youth over 5 years in 12 states

Trends

Overall CSR expenditure in FY20: Rs. 305 Cr, (2.41% of PAT)

15 1262 3231 15

701823 12

119

110

200

Health Water Education Sanitation

CSR Expenditure (Rs. Cr.)

FY2018 FY2019 FY2020

Page 26: NTPC’s Endeavors towards ESG Improvement

Partial list of Recent Awards

CII-ITC Sustainability Award 2020

Among top 50 best companies in 2020 by “Great Place to Work”

Awarded with National Safety Award

Awarded as Best Performing Power Generation Company

Won 7th CSR INDIA Awards 2020 by Greentech foundation

Awarded in ATD Global BEST Award 2020

Won double honor at the Governance Now 7th PSU Awards