Upload
v-a-khrustalev
View
212
Download
0
Embed Size (px)
Citation preview
S C I E N T I F I C - T E C H N I C A L P A P E R S
N U C L E A R P O W E R P L A N T S W I T H W A T E R - M O D E R A T E D
W A T E R - C O O L E D R E A C T O R S I N P O W E R S Y S T E M S :
A D A P T A T I O N M E T H O D S
V. A. Khrustalev UDC 621.311.25:621.039.524.44
In planned power systems with a probable high percentage of nuclear power plants (NPP), the problem arises of seeking
compromise methods for the control of daily, weekly, and seasonal load-schedule irregularities. In the examination of the various
modes of such NPP operation, it is necessary to observe optimal circuit-parameter characteristics and an equal energy effect as
well as engineering constraints. One of the determining constraints in the direct unloading of a multiunit NPP is the total
limiting control range, which is a function of the time and nature of the annual distribution of fuel recharging in the reactors.
According to the conditions of the 135Xe transient period, this factor is important for daily control, is less-important for weekly
control, and has practically no effect on loading when control is less-frequent. Analysis of the data of various organizations has
provided a basis for proposing a general-purpose approximation of the total control range of an NPP with a daily load cycle [1]:
A N Z = exp (a - b A t i) ~'ki(1 - "tki) c-dA t i 1, (I)
where At i is the time of smooth load variation of the i-th unit, in h; tki is the relative operating period (stationary fuel cycle);
and a, b, c, and d are coefficients, which are equal to 3.06, 0.132, 1.15, and 0.075 for the VVI~R-1000 water-moderated water-
cooled power reactor (WMWCPR).
Calculations by formula (I) have shown that with a conservative approach (alternate reloading in periods of maximum
inflow to hydroelectric plants in spring or minimal energy deficit in summer), NPP units with VVI~R-1000 reactors do not
provide even the moderate optimal control ranges established earlier [2]. This circumstance as well as the well-known economic
disadvantage of direct NPP unloading, owing to the smaller fuel component than that of a heat power plant, make it necessary
to investigate alternative methods for coverage of schedule irregularities. The main methods are listed in Table 1 and are well-
known in principle.
The initial conditions and formulas for the transmitted-energy balance in all power complexes follow from the methods
load-schedule coverage. Many of the proposed schedule-filling methods have been studied in detail - - for example, optimal
schemes, parameters, and realization methods for NPPs with WMWCPRs have been analyzed and generalized [1]. We shall
discuss method II, which is less-known in the literature and in which combines variation of the power of a unit by unloading at
valleys and spiking at peaks in the schedule. In this version, it is potentially possible to eliminate the shortcomings of direct
unloading. At the same time, along with reduction of capital outlays for NPPs due to the low power established in the power
system, additional expenditures for spiking of all elements of the unit are taken into account. The reduction of this version to a
single ecological effect consists of estimation of the additional cost of storage of excess enriched fuel in a cooling pond and the
isolation of a large area of land for a safety zone. More details on this version can be found elsewhere [I] or from the experience
of American NPPs with PWRs [3].
Versions I, It, and Ill combine an absence of generation of intermediate storable energy and, therefore, losses in its
transmission, as is observed in versions IV-VII. Losses are caused by energy dissipation (versions V and VI) as well as by losses
of potential performance due to lower efficiency of the peak circuit (version IV) or peak superstructure (version VII). In these
versions, the peak power is expressed in terms of the intermediate-generation power by means of the coefficients K/. in Table 1.
Saratov Polytechnic Institute. Translated from Atomnaya l~nergiya, Vol. 71, No. 6, pp. 551-555, December, 1991.
Original article submitted December 4, 1990.
0038-531X/91/7106-1013512.50 �9 Plenum Publishing Corporation 1013
T A B L E 1. Ana lys i s o f Ve r s ions of C o v e r a g e of Schedu le I r r egu la r i t i e s Us ing a N u c l e a r P o w e r P l an t
Coverage method (type of 1 irregularity)
Formulas
I. Direct unloading
AN = ANse p
(daily, weekly, seasonal)
II. Unloading-spiking
AN= AN s RANsep Idaily, weekly, seasonal)
aN= ANGTP+ AN NPP
(daily, weekly, seasonal)
IV. Combinatio- of NPP and phase transition storage devices
( r-~ v ) "0 a N =ANpc; K- . t v t l p c q f
( daily )
V. Power complex: NPP and HSPP
T-t v ..MV = AN + cgAN-h~ K=
dis ~v ~IHSPP
Idailv)
Vl. NPP with off-peak su~p 1 y
T - x v K
r v rl f qelc
(daily)
VII. Power complex: NPP and system for hydrogen production and consump- tion
AN = ANHs " AN~PP " s '
T--T V K=
qel 7 dn
( d a i l y )
14B(Tj-Zv'A'%[) qv QO ZI(T:-~v~N)
24B(Tj- ~v j AN) 8 s . v qs ZI (T)- t v,i AN)
C.~v~ [1-n~ (D/rv)-i)(l-m~ c .248
24B(T]-t v j)AN q0 ns .C nQ~ rlGTP
• (~/tvj-i)(1-O-~)] +
+ k GTPk. (1-(x -A~)) ] sp
Ch~ v [ l - - a N
24s~24- ~d A~) n y v AN
+ (24/'l'dY "1) ~-='[- ] +
~f 8pc -
A.~" I , kPCk"
J sp k* 1
E+E~ [ k NPP(I-AN)+ sp
zjG-x v~at0
AN (24/'t v --i) 1 --
k*l § r
E+ E a
Zdy(24-~.. q A ~/) sp k*l
AN I -
B (24-T v &'~) n0
x 1 - + sp k§ k+l
+ " p
Z. (24-I vZ~g)(k+l) dy
C 2 v [ . I - A N
s 24B (24 -x v AN) rlav
( E + E a) [ k NPP x L sp
Z (24-t v AN) dy
§ .3 f i sh_ + sp L 24-x ~N (k + I
241T v -I ] § E§ a
q0 ~y (24--x v AN)
x k NPP sp * A3e.coEAZeco
CnXv ( l _ A N qo] * E*E~
24B (24-T v ATe) [" ~ ) / Zdy(24-Tv &~)
x ksp 1 - ksp - A 3 sep.
1014
pecks/ I- (kU-h)
1,1
1,o
Version i- i J
z '/,
I i I
0,05 0,/ o,15
l
i i / < ?"~ I
1
i I 1221 ousand fuel units
kc I __ I a
O.Z AN
Fig. 1. Specific reduced expenditures of versions I-III for coverage of variable load schedules at C n = 800 (1),
500 (2), and 300 rubles/kg UO 2 (3), spiking range AN s = 0.5AN (dashed curves), and NPP cost rise by 8%
(dot---dash curve).
E~ ko- pecks/ (kW' h)
Lq5 ,
i
i Lq~
/.55 .--
I,Y~-
1,2S t- 1 i
Version /V
TS;v ~Z ~,
/
o t ! i
. - ' ~ , ~ . ,§ 2/.
C
8 i Z,§
~-: f , ~ L- Z E
~ y
C a b q.21 . . . . . .
0.C5 0./ 8 : 5 .'LZ ,SV
Fig. 2. Specific reduced costs of versions IV, VI, and VII for coverage of variable load sched-
ules at ks PC = 100 (2') and 40 rubles/kW (2") and ~ e i ~ i = 15 rubles/thousand fuel units (la);
1, 3, 3) see Fig. 1.
We shall also discuss the generation and delivery of useful electrical energy according to a given schedule from a system
of NPPs and hydroelectric storage power plants (HSPP). This version involves reduced system expenditures, switching of the
NPP exclusively to the base part of the schedule, and the production of high (discharge) peak powers. Today, however, such one-
sided analysis is unacceptable: the ecological consequences of the HSPP must be taken into account. In addition, unsuitable
1015
E, kopecks/(kW'h)
J
bE,
Version_ / iii/v
j '
I I I a
$
i
O, 0g 0, I 0,15 0,2 zltr
lillion rub] es/yr
7
b I I
E. million rubles/year
f00 f
760
86'
~0
C
I I I
Fig. 3. Specific reduced expenditures of version V (a) and differences for versions I-II (b) and
I-V (c); 2', 2") without allowance tor ecological factors; I, 2, 3) see Fig. 1.
terrain and geological conditions increase the specific expenditures for the HSPP and the building of large high-head reservoirs
next to NPP sites whose safety is in doubt. The losses associated with the additional damage to soil (flooding) and fishing are
considerable in this case.
In versions VI and VII, in accordance with general principles of systems analysis, the closing costs for the production of
hydrogen, oxygen, and heat must be considered the most-favorable of the known individual methods. This refers chiefly to the
structure of the reduced costs of each of the versions. The initial data for today and for the future are calculated on their basis.
Qualitative analysis shows that, in principle, all versions could be competitive under conditions of daily irregularities but
only versions I, II, and III are suitable for weekly and seasonal irregularities, The following designations are used in the formulas
of Table 1: r/v, r/0, r/s and r/s are the efficiencies of NPP generation in the valley and base parts of the schedule and at minimum
and maximum loads under conditions of spiking; Zj is the annual number of load-variation cycles; and k NPP, k ~ k HsPP, k Pc sp ' sp , and ks PH are the specific capital outlays for an NPP, GTP, HSPP, a peak circuit n which an NPP is combined with phase-
transition storage devices, and a peak hydrogen superstructure.
The results of the comparative analysis are shown in Figs. 1-3. Typical irregularities, which are determined by the ratio
Tj/Tvj , are as follows: 2.4-4 daily, 4-6 weekly, and 6-10 seasonally. Version I (the worst) and version II (the best) were found to
be polar opposites. Version II is the most-efficient when the entire control range AN (up to 20%) is covered by an NPP without
additional expenditures for its support (curve 1 of Fig. 1, version II).
In the compound process of irregularity coverage partially by unloading and spiking (AN s = 0.5AN) with allowance for
the increased NPP cost (A,~sp = 8%), the E value is increased appreciably. For example, it is apparent from Fig. 1 (version II)
that the rise is up to 13-15% in the first case and up to 4-6% in the second at C n = 300 rubles/kg UO 2 and AN = 0.2. The
method is most-efficient at 7)/r v = 6-10, which corresponds to weekly and seasonal irregularities. For all versions except for V,
the specific expenditures are typically reduced by 10-12% or more when C n is reduced from 800 to 300 rubles/kg UO 2.
In version III with a GTP that uses costly organic fuel, the dependence of Tj/T v on expenditures is reversed: the shorter
the peak period, the higher the efficiency of combining NPPs and GTPs. At Cf < 25 rubles/thousand fuel units, however, the
effect of lower GTP costs prevails, the effect of the ratio 7)/r v is the same as in versions I and II, and the efficiency is increased
by 11-12%. It is apparent from Fig. 1 that Cf = 35-40 rubles/thousand fuel units, versions III and I are economically equivalent,
but an NPP with a GTP is more-efficient that direct unloading with daily and weekly irregularities (but less-efficient with
seasonal irregularities).
Versions IV-VII are economically justified only for the control of daily irregularities, since the capital outlays for storage
devices rise sharply with prolonged load cycles. Version IV, in which an NPP is combined with a peak circuit of phase-transition
storage devices, is situated economically between direct unloading and spiking. In the case of daily cycling, a reduction in the
specific cost for a peak circuit from i00 to 40 rubles/kW (zones 2 and 2' at C n = 500 rubles/kg UO2) corresponds to an
efficiency increase by 1.5-2% for this method.
1016
Versions VI and VlI are in many ways dependent on the costs of separate replacement production. In version VI, for ,- AEv el example, a reduction ol - - s e p from 30 to 15 rubles/thousand fuel units impairs the efficiency of the method by 1.3-1.5% at ~ =
0.2 and ~:v = 10 h. If more-costly fuel is used, the saving from replacement of solid fuel, even at Cf = 30-40 rubles/thousand fuel
units and T j # v = 4-6, raises the competitiveness of version VI over that of version IV (Fig. 2a).
Version VII (Fig. 2c) for off-peak supply is more-efficient than direct unloading as well as an NPP with GTP when
costly organic fuel is used but is inferior to all other versions except V (Fig. 3a). Here, as in version VI (Fig. 2b), the costs refer
to the initial given desired delivery of energy to the consumer.
The specific costs of version V with HSPP with allowance for ecological factors (Fig. 3, curve 3 ') are increased by a
factor of 3.2-3.3 at ~ = 0.2, which attests to the total inefficiency of this version. Ground rent for the additional alienated
territory and direct annual expenses for the fishing industry are proportional to the energy consumed and distributed by the
HSPP.
The cost savings in the operation of an NPP with WMWCPR with the load schedules for versions II and I are compared
in Fig. 3b. For 0 _< C n < 800 rubles/kg UO 2 and 0.05 _< AN _< 0.2, the saving is from 2.8 to 14 million rubles per year for a unit
power of 1000 MW. In Fig. 3c, the expected loss for HSPP construction is compared with that direct unloading of the NPP. At
0.05 < AN _< 0.2 and 2.4 _< T/ t v <__ 6, the annual cost overrun can rise from 22 to 210 million rubles for a 1000-MW system.
Analysis of the possible versions with NPP participation in the control of load schedules allows versions II and IV and
sometimes I to be recommended for more-detailed development. The timely preparation for typical NPP load situations will
make it possible to develop most efficiently and optimally and operate safely and reliable plant equipment and power systems in
the future.
LITERATURE CITED
1.
2.
3.
R. Z. Aminov, V. A. Khrustalev, A. S. Dukhovenskii, and A. I. Osadchii, Nuclear Power Plants with Water-Cooled
Water-Moderated Reactors: Operating Conditions, Characteristics, Efficiency [in Russian], l~..nergoatomizdat, Moscow
(1989).
V. A. Khrustalev, "On optimal participation of heat and nuclear power plants in the coverage of variable load sched-
ules," in: Use of Low-Grade Solid Fuel in Energy Technology and Protection of the Environment [in Russian], Saratov
Polytechnic Inst. (1988), pp. 1(}4-107.
V. A. Khrustalev, "Increasing the power of nuclear power plant units with pressurized-water reactors in the United
States," At. Tekh. Rubezh., No. 5, 10-13 (1988).
1017