53
Pulau Sambu Guntung Operational Cost Reduction Opportunity Analysis June 5th 2012

OA Final Pulau Sambu Guntung 120605

Embed Size (px)

DESCRIPTION

pulau sambu

Citation preview

  • Pulau Sambu Guntung

    Operational Cost ReductionOpportunity Analysis

    June 5th 2012June 5th 2012

  • Operational Cost ReductionOpportunity Analysis

    1. Introduction 10 minutes

    2. Review of the OCR methodology 20 minutes

    Presentation Cost mapping and 3. Presentation Cost mapping and Opportunity Analysis 90 minutes

    4. Next steps 20 minutes

    5. Discussion 40 minutes

  • Objectives and Introduction

    Operational Cost ReductionOpportunity AnalysisOpportunity Analysis

  • Purpose of this meeting

    To present the results of cost mapping exercise and opportunity analysis

    To agree the next steps in the Operating Cost Reduction project

  • Operational Cost ReductionProject phases Focused Improvement

    Map full operational cost structure in filling

    line operations

    Phase 1Cost Mapping

    Identify savings potential, prioritise

    based on operational cost impact

    Phase 2Opportunity Analysis

    Customer implements improvements (using

    WCM methodology) in chosen areas to gain

    savings

    Phase 3Implementation

    Systematic approach to:

    1) Establish operational cost baseline

    2) Identify the improvement activities returning the highest cost savings for your business

    3) Proven methodology to drive and secure improvements

    cost impact savings

  • Summary What we have done so farUsed the information provided by you into our system performance and economics model to generate a view of current operational cost structure

    Focus is to understand the economic impact of system performance improvements by line

    The cost structure has been assessed for direct production costs only current analysis do not include product and packaging (apart from waste), quality control department, logistics and inventory, sales and marketing expenses, etc.

    All analysis has been made on the operations in Pulau Samu Guntung plant

    Snap-shot assessment - based on actual performance data for Line D A3CFlex, for Snap-shot assessment - based on actual performance data for Line D A3CFlex, for period of Feb to Apr 2012 Information provided by you and PLMS that we have used: Actual line operations for the investigated month e.g. production time, CIP time, machine downtime

    and generated waste

    Current costs for: raw material, packaging material and staff

    We have also used general Tetra Pak assumptions for certain costs

    We have analysed opportunities for improvement

    The opportunities are based on the operational cost model and data gathered from PLMS and site based records

    They give indications of the type and size of savings available and will need to be confirmed within the first phase of the WCM initiative

  • Review of the Methodology

    Project scope

    Cost AnalysisCost Analysis

  • OCR Focused ImprovementScope Covered

    Total Conversion Cost

    Consumer

    Reception Processing Packaging Logistics$ $Customer

    Operational Cost Analysis

    Scope with adequate data

    Producer/Supplier

    Retailer

  • Review of the Methodology

    Project scope

    Cost AnalysisCost Analysis

  • OutputCost base

    Customer Operational Cost

    Fixed costs Variable costs Speed / CapacityOverall Equipment

    Cost/Unit

    Seeing everything in terms of costUnderstanding and allocating the data

    Cost Items Cost Drivers

    Fixed costs Variable costs Speed / CapacityEffectiveness

    Size/area

    Capital

    Operators

    Spare part cost

    Service cost

    Utilities

    Cost for waste

    Cleaning time

    Machine Mechanical Efficiency

    Set-up time

    Service time

    Waste

  • Spare part cost

    TP service work

    Customer service work

    Product waste cost

    Area cost

    Costs are analysed by Item and Driver

    60

    80

    100%

    Cost/'000

    Other time

    Service and maintenance (customer)

    Service and maintenance (TP)

    Area costProduct waste

    Utilities

    Capital cost

    Capital cost

    Labor cost

    Capital cost

    Capitalcost

    Laborcost

    Capit

    al cost

    Pro

    duct w

    ast

    e

    Labor

    cost

    TPservice

    cost

    Labor

    cost

    Capitalcost

    Packagewaste

    Product

    waste

    16.0 4.7 0.9 2.30.61.1

    2.5 2.6 3.3 1.5

    Total =

    35.4

    Value adding Non-Value adding

    Packmat waste cost

    Area cost

    Utilities

    Overhead

    Packer cost

    Operator cost

    Capital cost

    By Item By Driver

    0

    20

    40

    60Service and maintenance (TP)

    CIP stop

    Equipment stops

    Production time (normal functioning)

    Labor cost

    Product

    waste

    Packagewaste

    Labor cost

    Productwaste

    Pro

    duct w

    ast

    eLabor

    cost

    Spare

    parts

    Spare

    partsLabor

    cost

    Labor

    cost

    Production time

    (normal functioning)

    Filling

    machineD

    istr

    ibution

    equip

    ment

    Product

    change

    Paper

    change

    CIP

    Serv

    ice a

    nd

    main

    tenance (TP)

    Serv

    ice a

    nd

    main

    tenance

    (Em

    ig)

    Unschedule

    dtim

    e Other time(incl. Customer

    stops)

  • OEE Loss Analysis (Overall Equipment Effectiveness)Measures quality production against line capacity

    OEE = x 100A

    B

    WeekendShutdownHolidays

    Plant not scheduledScheduled downtime

    Breakdowns

    Set-up & adjustment

    Tools change

    Availability loss

    A

    Tools changeStart-up

    Others

    loss

    B

    Defect / ReworkQuality loss

    Minor stoppages

    Speed lossesPerformance

    loss

  • Performance and cost results

    Cost by item and by drivers

    OEE loss analysisOEE loss analysis

  • Key Data and Assumptions (1/5)Line D Feb-Apr 2012

    Product cost Primary Packaging material

    Secondary pack. mat.

    Information given by the customer Weighted average for all different PM: 55.10 /000

    Opening: 1.93 /000

    Cardboard: 14.14 /000

    Product cost

    0.30 / Litre

    57.03 / 000 packs 14.14 / 000 packs

  • Key Data and Assumptions (2/5)Line D Feb-Apr 2012

    Labor Waste Maintenance contract

    Filling Machine operators :1 xxxxx /month

    Distribution Equipment/FL Operators: 10xxxxxx /month

    Production leader:0.2per shiftxxxx /month

    QC personnel:0.33

    Product waste

    CIP : 1000 l/event

    Product change: 1000 l/event

    Paper change :0.75 l/event

    QC : 100% of QC waste

    Overfilling: 0.514 ml/pack

    Package waste

    QC:28/h (destructive)

    Service & maintenance

    Service employee cost: 1.16 /hour with 1924 hours service work per year on the line

    Total labor cost for the line per month: xxxx / month

    Package waste:

    2.083 / month

    Product waste:

    8.120 / month

    Maintenance contract:

    4.573 / month

    Customer Service

    186 / month

    QC personnel:0.33per shiftxxxx /month

    QC:28/h (destructive)

    CIP : 183/event

    Product change: 3/event

    Paper + strip change 3packs/event

    Line stops: 25.290 packs

  • Total Customer system CostLine D

    Op. CostFeb-Apr 2012

  • Line D A3 CFlex Cost/000

    Two ways of looking your cost Line D - Cost items, Cost drivers

    Period of analysis Feb- Apr 2012

  • Detailed operational cost structureLine D

    Period of analysis: Feb-Apr 12

  • Operational Cost Reduction Focussed Improvement Project Overview

    = On target (Within 0.5% of target)

    = Within 1.5% of target

    = More than 1.5% below target

    Objective:

    Operational Cost Reduction of 31.01 %

    Quantification

    Cost/1000 saved on focus lines 5.70

    Customer Project Manager: Tetra Pak Project Manager:

    Focus Improvement areas OCR Target %OCR

    Result %

    CIP time reductionCIP time reduction 13.79 55.304

    Filling Machine stop reduction 14.07 56.427

    Other stop time reduction 3.15 12.627

    Total 31.01 % 124.358

    HPBR/2012-05-18

    Highly Confidential

  • Performance and cost results

    Cost by item and by drivers

    OEE loss analysisOEE loss analysis

  • OEE Loss Analysis (Overall Equipment Effectiveness)Line D

    OEE = x 100 = 42.3 %A

    B

    Feb-Apr 2012

  • Improvement Opportunities

    Opportunities and sensitivity analysis

    Total potentials and impact on costTotal potentials and impact on cost

  • Set Up Time analysis

  • How Tetra Pak Lines are working?Set Up (CIP) time definition

    Production Stop,Set Up start

    Production starts at maximum speed

    ProductionProduction

    Set up is the sum of activities that has to be done in the machine in order to prepare it to produce

    Machine cooling down

    CleaningWater

    circulation

    Machine preparation

    Machine preparation

    Machine sterilization

  • 3.50

    4.00

    4.50

    Set Up AIC timeLine D Actual Average 2:52 hrs

    Specification: 2 hoursActual average: 2:9

    Target: Average = 2.1 hrsTarget-30%

    1.00

    1.50

    2.00

    2.50

    3.00

    3.50

    Actual Average

    Target Average

    Specification

  • 200

    300h

    Hours per month and line

    2027 209

    Set Up time reduction: what happensLine D, AIC reduction

    Time saved Additional productionTransfer at 50 % OEE

    to additional production time

    0

    100

    Production

    time

    Additional

    production

    time from CIP

    time reduction

    New total

    production

    time

    Line D Target -30% for AICSet Up reduction: 0:51 hours (Monthly frequency 8)Total potential saving monthly: 6.36 hoursYearly Extra Capacity (@ 50% OEE) = 0,36 Mio Packs

  • 6.00

    7.00

    8.00

    9.00

    Set Up Final CIP timeLine D Actual Average 6:10 hrs

    Specification: 4 hoursActual average: 6:10

    Target: Average = 4:15 hrs

    Target-30%

    Actual Average

    1.00

    2.00

    3.00

    4.00

    5.00

    6.00

    Target Average

    Specification

  • 200

    300h

    Hours per month and line

    202

    26 228

    Set Up time reduction: what happensLine D, Final CIP reduction

    Time saved Additional productionTransfer at 50 % OEE

    to additional production time

    0

    100

    Production

    time

    Additional

    production

    time from CIP

    time reduction

    New total

    production

    time

    Line D Target -30% for final CIPSet Up reduction: 1.2 hours (Monthly frequency 15)Total potential saving monthly: 26.06 hoursYearly Extra Capacity (@ 50% OEE) = 1.4 Mio Packs

  • Set Up time reduction: potential savingLine D Final CIP + AIC

    Line Line D D Target - 30% for CIPTotal OCR = Total OCR = 13.23% (2.44 13.23% (2.44 /000)/000)Yearly potential saving* = Yearly potential saving* = 55.300 55.300

    *Assuming 21.8 Mio packages produced yearly

  • Line Equipment Downtime analysis

  • Stop Reduction: what happens Line D excluding Set Up

    Actual Lost Time Target Situation

    300

    330h

    Hours per month

    320.9

    -40.1

    -27.8

    253.0

    -30%

    - 50%

    Target = Stop Reduction by 50% Monthly savings : 51 hours Yearly Extra Capacity (@ 50% OEE) = 2.754.000 Packs

    100

    200

    Actual FM OE

    -27.8

    New total

    production

    time

  • 200

    250h

    Hours per month and line

    202.0

    39.0 241.0

    Stop Reduction: what happens Filling machine line D

    Time saved Additional productionTransfer at 50 % OEE

    to additional production time

    - 50%

    100Production

    time

    Additional

    production

    time from CIP

    time reduction

    New total

    production

    time

    Target = Stop Reduction by 50% Total potential saving monthly: 39 hours Yearly Extra Capacity (@ 50% OEE) = 2.100.000 Packs

  • Stop reduction: potential savingFilling machine line D

    Line DActivity Target = Short Stop Reduction by 50%OCR =14.7% (2.59 )Yearly potential saving* = 56.427

    *Assuming 21.8 mio packages produced yearly

  • Stop Reduction: what happens Other Equipment stops reduction

    Time saved Additional productionTransfer at 50 % OEE

    to additional production time

    - 30%

    Activity Target = Stop Reduction by 30% Total potential saving monthly: 12 hours Yearly Extra Capacity (@ 50% OEE) = 648.000 Packs

  • Stop reduction: potential savingOther equipment stop reduction

    *Assuming 21.8 mio packages produced yearly

    Line DActivity Target = Short Stop Reduction by 30%OCR = 3.15% (0.58 )Yearly potential saving* = 12.627

  • Overfilling Analysis

  • TPA3Flex 2000ml Line 7 packs > 200 packs

    0.06

    0.07

    0.08

    0.09

    0.1

    Cream Mean

    Skim Mean

    Overfilling ReductionLine X

    Achieve 3 Gr mean with 0.7 STD

    0

    0.01

    0.02

    0.03

    0.04

    0.05

    -1.0 0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    12.0

    13.0

    14.0

    15.0

    16.0

    17.0

    18.0

    19.0

    20.0

    21.0

    22.0

    23.0

    24.0

    25.0

    26.0

    27.0

    Skim Mean

    Cust Min

    Cust Max

    Skim

    Cream

  • Overfilling reductionLine X sensitivity analysis

    Activity target: Activity target: Reduce from 13.8 Gr. (weighted average between cream and skim) to 3 Gr. Reduce from 13.8 Gr. (weighted average between cream and skim) to 3 Gr. (78 % reduction) reducing the standard deviation from 6 (average between (78 % reduction) reducing the standard deviation from 6 (average between cream and Skim) to 0.7.cream and Skim) to 0.7.

    5.4% OCR representing 7.7 5.4% OCR representing 7.7 Yearly potential saving* = 77 000 Yearly potential saving* = 77 000

    Over capacity = 51 500 packs

    *Assuming 10 Mio packages produced yearly

  • Improvement Opportunities

    Opportunities and sensitivity analysis

    Total potentials and impact on costTotal potentials and impact on cost

  • Scenarios showing impact of implementingrealizable initiatives on Line DPotential 31.01% reduction in operational

    Operational cost base Potential saving

    31.01 %

    124.358 /year

  • Product Loss Analysis

  • Operational Cost Reduction Focussed ImprovementAdditional Potential Benefits ( not included on calculated savings)

    Overfilling (*) CIP ProductWaste

    Target 4 ml / pack 300 lts

    Total Monthly 7.271 lts 6.900 lts

    Total Monthly 14171 lts

    Total savings / month 4251

    Total savings / Year 55.266

    HPBR/2012-05-18

    Highly Confidential

    (*) Assuming an underfilling aprox 4 ml of the 261 ml of the nominal full pack isachievable without forming problems

  • Project Deliverables

  • OCR FI Hard Deliverables

    Operational Cost reduction 31.01 %

    Pilot line savings 124.358

    OEE Improvement from 42.3 % 51.41 %OEE Improvement from 42.3 % 51.41 %

    An additional capacity of packs/year 4.559.000

    An additional potential saving of product loss 55. 266

  • OCR FI Soft Deliverables

    A group of people trained in WCM methodologies

    An additional capacity of packs/year 4.559.000

    Potential to expand methodology to the rest of theTetra Pak lines

    Potential to expand methodology to the rest of the plant

  • Questions ?Questions ?

  • Thank you Thank you

  • Next Steps

  • Focused improvement team training and kick off

    Execute projectsPrioritisation & Master Plan

    Operational Cost Reduction road mapDriving Focused Improvements

    Close individualprojects

    Regular follow-up

    Opportunity Analysis

    Operational Cost Analysis

    OEE Loss Analysis

  • Propose and define Team table/matrix

    OCR manager OCR Central Team

    Steering CommitteeCustomer:

    Technical Service:KAM:

    Operational Team

    Project coordinatorname OCR manager

    (Tetra Pak Indonesia)

    OCR Central Team(Technical service)name

    (Customer)

    Team 1 CIP time reduction 1 leader + 4 members

    Team 2 FM short stop reduction 1 leader + 4 members

    Team 3 Other equipment stop Reduction 1 leader + 4 members

  • Identify Team Leaders and members - 1 Team Leader/Team - 4 members/Team

    Running the Teams: From Middle of October 2007 till End of February 2008

    it visit week

    Next Steps

    Steering group meeting from week to review results from the teams

    Monthly regular meeting to update Prod. manager.

    Training and Kick off of the teams

  • The End

  • Training proposed

    World Class Manufacturing Concept - WCM big picture, infinite loop - From Pillar to teams (definitions) - Team work

    Method and tools applied at customer - analyse Data and decide the route to take - analyse Data and decide the route to take

    Standards for visualisation to be used (team boards)