20
ORNL is managed by UT-Battelle, LLC for the US Department of Energy Oak Ridge Spallation Neutron Source Proton Power Upgrade Project and Second Target Station Project Workshop on the future and next generation capabilities of accelerator driven neutron and muon sources STFC Rutherford Appleton Laboratory August 14, 2018 by Mike Plum Proton Power Upgrade Project Ring Systems Group Leader

Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

ORNL is managed by UT-Battelle, LLC for the US Department of Energy

Oak Ridge Spallation Neutron SourceProton Power Upgrade Project and Second Target Station Project

Workshop on the future and next generation capabilities of accelerator driven neutron and muon sources

STFC Rutherford Appleton LaboratoryAugust 14, 2018

by Mike Plum

Proton Power Upgrade Project

Ring Systems Group Leader

Page 2: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

2

SNS Accelerator Complex Today

Front-End:

Produce a 1-ms

long, chopped,

H− beam

1 GeV

LINAC

Accumulator Ring: Compress 1 ms long

pulse to 700 ns

2.5 MeV

DTLFE

Accumulator

Ring

RTBT

HEBT

Injection

Extraction

RF

Collimators

945 ns

1 ms macropulse

Cu

rre

nt

mini-pulse

Chopper system

makes gaps

Cu

rre

nt

1ms

Liquid Hg

Target

1000 MeV

Design parameters: 60 Hz, 1.4 MW

CCL SCL

87 MeV 186 MeV

Page 3: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

3

SNS beam power history

Availability for latest run cycle is 94%Plan to operate at 1.4 MW starting September 2018

1.4 MW

Beam power administratively limited by target most of this time

Page 4: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

4

SNS Upgrade Plans

• Proton Power Upgrade project doubles accelerator power capability

– Near term, ~$240 M. CD-1 awarded April 2018. FY18 budget $36M.

– Increases FTS capability+ capacity and provides accelerator basis for STS

• Second Target Station provides new instrument hall with world class cold neutron brightness

– Delayed from PPU start, ~$1.5B

After PPU Upgrade

STS• 22 instrument slots• 8 initial instruments

FTS• 24 instrument positions• 19 instruments built

Now

FTS• 24 instrument positions• 19 instruments built

After STS Upgrade

1.4

MW

Accelerator today

0.8

MW

2 M

W

Accelerator after PPU

Page 5: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

5

Second Target Station: world class cold neutron performance

• STS will be the highest peak brightness long wavelength neutron source

(5 MW)

(1 MW)

(0.8 MW)

5 Å – long wavelength comparison

Page 6: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

6

PPU Parameters: power increase with energy and current

SNS

1.4 MW

PPU full

upgrade

capability

PPU FTS 60

Hz operation

Proton beam power capability (MW) 1.4 2.8 2.0

Beam energy (GeV) 1.0 1.3 1.3

RFQ output peak beam current (mA) 33 46 46

Average linac chopping fraction (%) 22 18 41

Average macropulse beam current (mA) 25 38 27

Energy per pulse (kJ) 23 47 33

Pulse repetition rate (Hz) 60 60 60

Macro-pulse length (ms) 1 1 1

FTS decoupled moderator brightness/pulse (AU) 1 2.04 1.43

FTS coupled moderator brightness/pulse (AU) 1 2.16 1.51

• PPU delivers 2.8 MW capable accelerator

• Prior to STS, accelerator will run at 2 MW to FTS

50% current increase

33% energy increase

No change

Page 7: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

7

PPU system upgrades

WARM LINAC KLYSTRONS

• Upgrade DTL klystrons 3, 4, and 5

from 2.5 MW to 3.0 MW

RING EXTRACTION

• Add 2 more kickers to the existing 14

kickers.

• But there is another way: to upgrade

the voltage capability of the existing

14 kickers -- prototype testing is in

progress.

SCL

• Add 7 cryomodules

(28 cavities)

• Add 28 klystrons and

3 modulators

RING INJECTION

• Replace 2 chicane magnets

• Replace inj. dump septum magnet

• Upgrade 8 inj. kickers

• Add quad magnet to inj. dump beam line

TARGET

• Increase power capability from

1.4 to 2.0 MW

STS STUB

• Build first part of beam

tunnel to future second

target

Future beam line to second target station

INJECTION DUMP

• Re-assess 150 kW power rating

• Add view screen imaging system

RING UTILITIES

• Increase water cooling capacity

Page 8: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

88

PPU notional schedule

• Holding 6-month

outage/early finish firm

• Includes a pre-6 month

outage PPU target demo,

possibly at > 1.4 MW

Page 9: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

9

Front end

• The new RFQ installed in 2018 allows higher peak currents

• 48 – 50 mA is easy to achieve. PPU requirement is 46 mA.

Screen shot of BCM in MEBT on July 2, 2018

50 mA

40 mA

Page 10: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

1010

RF Progress

• RF task force conducted measurements to determine required warm linac upgrades

– 3 of 6 DTL klystrons require upgrades from 2.5 to 3.0 MW

– CCL RF is OK

• Initiated testing of new high voltage convertor modulator (HVCM) design proposed to power new RF systems

Test load for DTL klystron testing

RF task force report

New alternate topology HVCM

Page 11: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

11

SRF progress

• SRF / M. Howell

– Initiate cavity long lead procurements (Nb, cavity qualification equipment, cavities)

– With J-Lab, initiate cryo-module engineering baseline activities

Spare cryomodule in production since 2012 demonstrates PPU gradient

Page 12: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

1212

Ring progress

• Injection region

– FNAL selected to design the magnets and oversee fabrication

– Beam measurements made to verify final design requirements

• Extraction region

– Baseline plan: add additional kickers in provided space

– A prototype resonant charging supply is being tested now. We hope this can be used to increase the voltage on the existing kickers instead of installing new ones.

Kicker magnets

Injection chicane

Page 13: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

1313

Target Progress: gas bubble injection implemented in operations Nov. 2017

• Measured vessel strain from pressure pulse reduced 10-70% with gas on

Gas off

Gas on

str

ain

(me)

time (ms)

• Core samples from target nose indicate erosion mitigation with gas on

Gas off: Target 17

Gas on: Target 18

Page 14: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

1414

Target Progress: target design

• 2 MW target design developed

– Simplified flow deployment in corners (tapered shape)

– Eliminated unnecessary feature (center baffle)

– Includes a gas-wall “curtain” in the nose regionPPU target vessel

CFD thermal analysis

Finite element stress analysis

Page 15: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

15

Conventional Facilities Progress

• A/E contract issued for design work (Cannon Design)

– CF + technical equipment layout

– Uses BIM (Building Information Modeling) approach

– Kick-off meeting held July 18-19

July 2017 Mar 2018

• Klystron gallery building cleared out, prepared for PPU activities

– Waveguide and cable conduit inserts assembled and inserted in chases to the tunnel

Assembled chase

insert

Relocated

magnet cables

Page 16: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

16

PPU Challenges

• The ring injection chicane is very complicated and crowded

– The new design will build on the tools and experience we’ve already developed to address the past issues we’ve had in this area

– Particle tracking simulations with 3D fields will be used to verify design

• The 2 MW target requires a lot of development

– We’ve only recently built targets that can operate at 1.4 MW

– Mercury flow, gas bubbles, and gas curtains are key

Page 17: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

17

Summary and conclusions

• CD-1 for PPU awarded April 2018. The project is making good progress.

– We’re aiming for completion in 2024 – 2025

• CD-0 for the STS project was awarded in 2009, but then put on hold

– We’re optimistic that it will be restarted soon

Page 18: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

18

Thank you for your attention!

Page 19: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

19

Backup slides

Page 20: Oak Ridge Spallation Neutron Source Proton Power Upgrade … - SNS PPU and STS... · 2018-09-10 · 4 SNS Upgrade Plans • Proton Power Upgrade project doubles accelerator power

2020

R2T2 beam line and stub• Initial R2T2 beam line layout complete

• Conceptual design of R2T2 stub in progress

(Courtesy J. Eckroth)

(Courtesy Survey and Alignment Team)