Obligations and Contract Cases

Embed Size (px)

Citation preview

  • 8/19/2019 Obligations and Contract Cases

    1/34

    THE METROPOLITAN BANK AND TRUST COMPANY v.

    ANA GRACE ROSALES AND YO YUK TO

    G.R. No. 183204

    FACTS:  Respondent Ana Grace Rosales (Rosales) is the owner of China Golden Bridge Travel

    Services, a travel agency. Respondent Yo Yuk To is the mother of respondent Rosales.

    In 2000, respondents opened a Joint Peso Account with Petitioner Metropolitan Bank and Trust

    Company. As of August 4, 2004, respondents’ Joint Peso Account showed a balance of

    P2,515,693.52.

    In May 2002, respondent Rosales accompanied her Taiwanese National client, Liu Chiu Fang, to

    petitioner’s branch in Escolta to open a savings account, as required by the Philippine Leisure and

    Retirement Authority (PLRA). Respondent Rosales acted as an interpreter for Liu Chiu Fang.

    Respondents opened with petitioner’s Pritil-Tondo branch a Joint Dollar Account with an initial

    deposit of US$14,000.00.

    On July 31, 2003, petitioner issued a “Hold Out” order against respondents’ accounts. On September 3, 2003, a criminal case for Estafa through False Pretences, Misrepresentation,

    Deceit, and Use of Falsified Documents, against respondent Rosales. Petitioner accused

    respondent Rosales and an unidentified woman as the ones responsible for the unauthorized and

    fraudulent withdrawal of US$75,000.00 from Liu Chiu Fang’s dollar account with petitioner’s

    Escolta branch. The Office of the City Prosecutor dismissed the complaint.

    Respondents filed a Complaint for Breach of Obligation and Contract with damages against

    petitioner. Respondents alleged that they attempted several times to withdraw their deposits

    but were unable to because petitioner had placed their accounts under “Hold Out” status.

    Petitioner alleged that respondents have no cause of action because it has a valid reason for

    issuing the “Hold Out” order. It averred that due to fraudulent scheme of respondent Rosales, itwas compelled to reimburse Liu Chiu Fang the amount of US$75,000.00 and to file a criminal

    complaint against respondent Rosales.

    While the criminal case was being tried, the City Prosecutor of Manila filed an Estafa case against

    respondent Rosales.

    The RTC rendered a decision finding petitioner liable for damages for breach of contract. It ruled

    that it is the duty of petitioner to release the deposit to respondents as the act of withdrawal of

    a bank deposit is an act of demand by the creditor.

    The CA affirmed the decision of the RTC.

    ISSUE: Whether or not petitioner is liable for breach of contract?

    HELD: Yes. The Court finds petitioner guilty of breach of contract when it unjustifiably refused to

    release respondents’ deposit despite demand. In cases of breach of contract, moral damages may

    be recovered only if the defendant acted fraudulently or in bad faith, or is guilty of gross

    negligence amounting to bad faith, or in wanton disregard of his contractual obligations.

  • 8/19/2019 Obligations and Contract Cases

    2/34

    In this case, a review of the circumstances surrounding the issuance of the “Hold Out” order

    reveals that petitioner issued a “Hold Out” order in bad faith. First of all, the order was issued

    without legal basis. Second, petitioner did not inform respondents of the reason for the “Hold

    Out.” Third, the order was issued prior to the filing of the criminal complaint.

    The Court finds that petitioner indeed acted in a wanton, fraudulent, reckless, oppressive or

    malevolent manner when it refused to release the deposits of respondent without any legal basis.

  • 8/19/2019 Obligations and Contract Cases

    3/34

    ARCO PULP AND PAPER CO., INC. VS.

    DAN T. LIM

    G.R. NO. 206806

    Facts:  Dan T. Lim works in the business of supplying scrap papers, cartons, and other raw

    materials, under the name Quality Paper and Plastic Products, Enterprises, to factories engaged

    in the paper mill business. From February 2007 to March 2007, he delivered scrap papers worth

    7,220,968.31 to Arco Pulp and Paper Company, Inc. (Arco Pulp and Paper) through its Chief

    Executive Officer and President, Candida A. Santos. The parties allegedly agreed that Arco Pulp

    and Paper would either pay Dan T. Lim the value of the raw materials or deliver to him their

    finished products of equivalent value.

    Dan T. Lim alleged that when he delivered the raw materials, Arco Pulp and Paper issued a post-

    dated check dated April 18, 2007 in the amount of 1,487,766.68 as partial payment, with the

    assurance that the check would not bounce. When he deposited the check on April 18, 2007, it

    was dishonoured for being drawn against a closed account.On the same day, Arco Pulp and Paper and a certain Eric Sy executed a memorandum of

    agreement where Arco Pulp and Paper bound themselves to deliver their finished products to

    Mega pack Container Corporation, owned by Eric Sy, for his account. According to the

    memorandum, the raw materials would be supplied by Dan T. Lim, through his company, Quality

    Paper and Plastic Products. The memorandum of agreement reads as follows:

    Per meeting held at ARCO, April 18, 2007, it has been mutually agreed between Mrs. Candida A.

    Santos and Mr. Eric Sy that ARCO will deliver 600 tons Test Liner 150/175 GSM, full width 76

    inches at the price of P18.50 per kg. to Megapack Container for Mr. Eric Sy’s account.

    It has been agreed further that the Local OCC materials to be used for the production of the

    above Test Liners will be supplied by Quality Paper & Plastic Products Ent., total of 600 MetricTons at P6.50 per kg. (Price subject to change per advance notice). Quantity of Local OCC delivery

    will be based on the quantity of Test Liner delivered to Megapack Container Corp. based on the

    above production schedule.

    On May 5, 2007, Dan T. Lim sent a letter to Arco Pulp and Paper demanding payment of the

    amount of 7,220,968.31, but no payment was made to him.

    Issue: Whether or not there was novation.

    Held:  Novation is a mode of extinguishing an obligation by changing its objects or principal

    obligations, by substituting a new debtor in place of the old one, or by subrogating a third person

    to the rights of the creditor. Article 1293 of the Civil Code defines novation as follows:

    "Art. 1293. Novation which consists in substituting a new debtor in the place of the original one,

    may be made even without the knowledge or against the will of the latter, but not without the

    consent of the creditor. Payment by the new debtor gives him rights mentioned in articles 1236

    and 1237."

  • 8/19/2019 Obligations and Contract Cases

    4/34

    In general, there are two modes of substituting the person of the debtor: (1) expromision and (2)

    delegacion. In expromision, the initiative for the change does not come from — and may even be

    made without the knowledge of — the debtor, since it consists of a third person’s assumption of

    the obligation. As such, it logically requires the consent of the third person and the creditor. In

    delegacion, the debtor offers, and the creditor accepts, a third person who consents to the

    substitution and assumes the obligation; thus, the consent of these three persons are necessary.

    Both modes of substitution by the debtor require the consent of the creditor.

    Novation may also be extinctive or modificatory. It is extinctive when an old obligation is

    terminated by the creation of a new one that takes the place of the former. It is merely

    modificatory when the old obligation subsists to the extent that it remains compatible with the

    amendatory agreement. Whether extinctive or modificatory, novation is made either by

    changing the object or the principal conditions, referred to as objective or real novation; or by

    substituting the person of the debtor or subrogating a third person to the rights of the creditor,

    an act known as subjective or personal novation. For novation to take place, the following

    requisites must concur: 1) There must be a previous valid obligation. 2) The parties concernedmust agree to a new contract. 3) The old contract must be extinguished. 4) There must be a valid

    new contract.

    Novation may also be express or implied. It is express when the new obligation declares in

    unequivocal terms that the old obligation is extinguished. It is implied when the new obligation

    is incompatible with the old one on every point. The test of incompatibility is whether the two

    obligations can stand together, each one with its own independent existence.

    Because novation requires that it be clear and unequivocal, it is never presumed, thus: In the civil

    law setting, novatio is literally construed as to make new. So it is deeply rooted in the Roman Law

     jurisprudence, the principle — novatio non praesumitur —that novation is never presumed. At

    bottom, for novation to be a jural reality, its animus must be ever present, debitum pro debito—  basically extinguishing the old obligation for the new one. There is nothing in the

    memorandum of agreement that states that with its execution, the obligation of petitioner Arco

    Pulp and Paper to respondent would be extinguished. It also does not state that Eric Sy somehow

    substituted petitioner Arco Pulp and Paper as respondent’s debtor. It merely shows that

    petitioner Arco Pulp and Paper opted to deliver the finished products to a third person instead.

    The consent of the creditor must also be secured for the novation to be valid: Novation must be

    expressly consented to. Moreover, the conflicting intention and acts of the parties underscore

    the absence of any express disclosure or circumstances with which to deduce a clear and

    unequivocal intent by the parties to novate the old agreement.

    In this case, respondent was not privy to the memorandum of agreement, thus, his conformity

    to the contract need not be secured.

    If the memorandum of agreement was intended to novate the original agreement between the

    parties, respondent must have first agreed to the substitution of Eric Sy as his new debtor. The

    memorandum of agreement must also state in clear and unequivocal terms that it has replaced

    the original obligation of petitioner Arco Pulp and Paper to respondent. Neither of these

    circumstances is present in this case.

  • 8/19/2019 Obligations and Contract Cases

    5/34

    Petitioner Arco Pulp and Paper’s act of tendering partial payment to respondent also conflicts  

    with their alleged intent to pass on their obligation to Eric Sy. When respondent sent his letter of

    demand to petitioner Arco Pulp and Paper, and not to Eric Sy, it showed that the former neither

    acknowledged nor consented to the latter as his new debtor. These acts, when taken together,

    clearly show that novation did not take place. Since there was no novation, petitioner Arco Pulp

    and Paper’s obligation to respondent remains valid and existing. 

  • 8/19/2019 Obligations and Contract Cases

    6/34

    ROLANDO C. DE LA PAZ VS.

    L & J DEVELOPMENT COMPANY

    GR. NO. 183360.

    Facts: Petitioner lent P350,000 to respondent without a specified maturity date at 6% monthly

    interest. Respondent failed to pay, so petitioner filed a complaint for collection. Respondent

    claims the interest rate is unconscionable. Interest rate upheld by the RTC and increased by the

    CA to 12%

    Issue: Was the CA correct in increasing the interest?

    Held: The lack of a written stipulation to pay interest on the loaned amount disallows a creditor

    from charging monetary interest.

    Under Article 1956 of the Civil Code, no interest shall be due unless it has been expressly

    stipulated in writing. Jurisprudence on the matter also holds that for interest to be due andpayable, two conditions must concur: a) express stipulation for the payment of interest; and b)

    the agreement to pay interest is reduced in writing.

    Here, it is undisputed that the parties did not put down in writing their agreement. Thus, no

    interest is due. The collection of interest without any stipulation in writing is prohibited by law.

    Even if the payment of interest has been reduced in writing, a 6% monthly interest rate on a loan

    is unconscionable, regardless of who between the parties proposed the rate.

  • 8/19/2019 Obligations and Contract Cases

    7/34

    BPI EXPRESS VS.

    ARMOVIT

    G.R. NO. 163654

    (This case involves a credit card holder’s claim for damages arising from the suspension of her

    credit privileges due to her supposed failure to reapply for their reactivation. She has insisted

    that she was not informed of the condition for reactivation.)

    FACTS: Armovit, then a depositor of BPI, was issued a pre-approved credit card with a credit limit

    of P20k that was to expire at the end of March 1993.

    On Nov. 21, 1992, she treated her British friends from Hong Kong to lunch. As the host, she

    handed to the waiter her credit card to settle the bill, but the waiter soon returned to inform her

    that her credit card had been cancelled upon verification with BPI and would not be honoured.

    Hence, her guests were made to share the bill to her extreme embarrassment.

    Armovit called BPI to verify the status of her credit card. She learned that her credit card hadbeen summarily cancelled for failure to pay her outstanding obligations. She denied having

    defaulted on her payments. Thus, she demanded compensation for the shame, embarrassment

    and humiliation she had suffered in the amount of P2M.

    BPI Express Credit countered that her demand for monetary compensation had no basis; it

    claimed that it had sent Armovit a telegraphic message requesting her to pay her arrears for three

    consecutive months, and that she did not comply with the request, causing it to temporarily

    suspend her credit card; that while the obligation was settled, she failed to submit the required

    application form in order to reactivate her credit card privileges; that the temporary suspension

    of her credit card was in accordance with the terms and conditions of the credit card, since

    Armovit defaulted in her obligationsRTC: Ordered BPI to pay Armovit moral and exemplary damages; that BPI failed to furnish

    Armovit the application form, hence the latter could not be blamed for not complying.

    CA: assailed the decision of the RTC; since Armovit had not signed any application form in the

    issuance and renewals of her credit card from 1989 to 1992, she could not have known the terms

    and conditions embodied in the application form even if the credit card had specified that its use

    bound the holder to its terms and conditions. It did not see merit in BPI Express Credit’s

    contention that the submission of a new application form was a pre-requisite for the lifting of the

    suspension of her credit card, inasmuch as such condition was not stated in a clear and

    unequivocal manner.

    ISSUE: Whether or not the CA was correct in awarding damages in favour of Armovit for the

    temporary suspension of her credit card on the ground of her failure to submit a new application

    form.

    RULING:  The relationship between the credit card issuer and the credit card holder is a

    contractual one that is governed by the terms and conditions found in the card membership

  • 8/19/2019 Obligations and Contract Cases

    8/34

    agreement. Such terms and conditions constitute the law between the parties. In case of their

    breach, moral damages may be recovered where the defendant is shown to have acted

    fraudulently or in bad faith. Malice or bad faith implies a conscious and intentional design to do

    a wrongful act for a dishonest purpose or moral obliquity. However, a conscious or intentional

    design need not always be present because negligence may occasionally be so gross as to amount

    to malice or bad faith. Hence, bad faith in the context of Article 2220 of the Civil Code includes

    gross negligence.

    Such terms and conditions printed on the credit card application form spelled out the terms and

    conditions of the contract between BPI Express Credit and its card holders; it determined the

    rights and obligations of the parties. Yet, a review of such terms and conditions did not reveal

    that Armovit needed to submit her new application as the antecedent condition for her credit

    card to be taken out of the list of suspended cards.

    Considering that the terms and conditions nowhere stated that the card holder must submit the

    new application form in order to reactivate her credit card, to allow BPI Express Credit to impose

    the duty to submit the new application form in order to enable Armovit to reactivate the creditcard would contravene the Parole Evidence Rule. Indeed, there was no agreement between the

    parties to add the submission of the new application form as the means to reactivate the credit

    card.

    In the context of the contemporaneous and subsequent acts of the parties, the only condition

    for the reinstatement of her credit card was the payment of her outstanding obligation. Had it

    intended otherwise, BPI Express Credit would have surely informed her of the additional

    requirement in its letters of March 19, 1992 and March 31, 1992. That it did not do so confirmed

    that they did not agree on having her submit the new application form as the condition to

    reactivate her credit card.

    The letter of BPI Express Credit dated April 8, 1992 did not clearly and categorically informArmovit that the submission of the new application form was the pre-condition for the

    reactivation of her credit card. The statement in the letter merely raised doubt as to whether the

    requirement had really been a pre-condition or not. With BPI Express Credit being the party

    causing the confusion, the interpretation of the contract could not be done in its

    favour. Moreover, it cannot be denied that a credit card contract is considered as a contract of

    adhesion because its terms and conditions are solely prepared by the credit card issuer.

    Consequently, the terms and conditions have to be construed against BPI Express Credit as the

    party who drafted the contract.

  • 8/19/2019 Obligations and Contract Cases

    9/34

    SPS. JUICO VS.

    CHINA BANKING CORP

    G. R. NO. 187678

    FACTS: SPS Juico vs. CHINA BANK DOCTRINE: the escalation clause is void if it grants respondent

    the power to impose an increased rate of interest without a written notice to petitioners and

    their written consent. Concurring doctrine by CJ Sereno these points must be considered by

    creditors and debtors in the drafting of valid escalation clauses.

    Firstly, as a matter of equity and consistent with P.O. No. 1684, the escalation clause must be

    paired with a de-escalation clause.9 Secondly, so as not to violate the principle of mutuality, the

    escalation must be pegged to the prevailing market rates, and not merely make a generalized

    reference to "any increase or decrease in the interest rate" in the event a law or a Central Bank

    regulation is passed. Thirdly, consistent with the nature of contracts, the proposed modification

    must be the result of an agreement between the parties. In this way, our credit system would be

    facilitated by firm loan provisions that not only aid fiscal stability, but also avoid numerousdisputes and litigations between creditors and debtors. Spouses Ignacio F. Juico and Alice P.

    Juico (petitioners) obtained a loan from China Banking Corporation (respondent) as evidenced by

    two Promissory Notes both dated October 6, 1998 and numbered 507-001051-34and 507-

    001052-0,5 for the sums of !!6,216,000 and P4, 139,000, respectively. The loan was secured by a

    Real Estate Mortgage (REM) over petitioners’ property located at 49 Greensville St., White Plains,

    Quezon City respondent demanded the full payment of the outstanding balance with accrued

    monthly interests. As of February 23, 2001, the amount due on the two promissory notes totalled

    P19, 201,776. On the same day, the mortgaged property was sold at public auction, with

    respondent China bank as highest bidder for the amount of P10, 300,000. petitioners received 8a

    demand letter9 dated May 2, 2001 from respondent for the payment ofP8,901,776.63, theamount of deficiency after applying the proceeds of the foreclosure sale respondent prayed that

     judgment be rendered ordering the petitioners to pay jointly and severally: (1)P8,901,776.63

    representing the amount of deficiency, plus interests at the legal rate, from February 23, 2001

    until fully paid; (2) an additional amount equivalent to 1/10 of 1% per day of the total amount,

    until fully paid, as penalty; (3) an amount equivalent to 10% of the foregoing amounts as

    attorney’s fees; and (4) expenses of litigation and costs of suit. Ms. Annabelle Cokai Yu, its Senior

    Loans Assistant stated that as of now the outstanding balance of petitioners was P15, 190,961.48.

    Yu reiterated that the interest rate changes every month based on the prevailing market rate.

    She notified petitioners of the prevailing rate by calling them monthly .It was increased

    unilaterally RTC: ordered Spouses to pay bank 9M plus the interest which amounted to 15M.CA

    AFFIRMED PETITIONER: They insist that the increase in interest rates were unilaterally imposed

    by the bank and thus violate the principle of mutuality of contracts.

    ISSUE: whether the increase in interest rates is void for violating the mutuality of contracts

  • 8/19/2019 Obligations and Contract Cases

    10/34

     HELD: Yes RATIO: Article 1308. The contract must bind both contracting parties; its validity or

    compliance cannot be left to the will of one of them. Article 1956 of the Civil Code likewise

    ordains that "no interest shall be due unless it has been expressly stipulated in writing." The

    binding effect of any agreement between parties to a contract is premised on xxx (2) that there

    must be mutuality between the parties based on their essential equality. Any contract which

    appears to be heavily weighted in favour of one of the parties so as to lead to an unconscionable

    result is void. Any stipulation regarding the validity or compliance of the contract which is left

    solely to the will of one of the parties, is likewise, invalid Escalation clauses refer to stipulations

    allowing an increase in the interest rate agreed upon by the contracting parties. This Court has

    long recognized that there is nothing inherently wrong with escalation clauses Nevertheless, an

    escalation clause "which grants the creditor an unbridled right to adjust the interest

    independently and upwardly, completely depriving the debtor of the right to assent to an

    important modification in the agreement" is void. A stipulation of such nature violates the

    principle of mutuality of contracts. In a case, SC said that petitioner’s assent to the modifications

    in the interest rates cannot be implied from their lack of response to the memos sent byrespondent It is now settled that an escalation clause is void where the creditor unilaterally

    determines and imposes an increase in the stipulated rate of interest without the express

    conformity of the debtor. Such unbridled right given to creditors to adjust the interest

    independently and upwardly would completely take away from the debtors the right to assent

    to an important modification in their agreement and would also negate the element of mutuality

    in their contracts. More recently in Solid bank Corporation v. Permanent Homes,

    Incorporated,39 we upheld as valid an escalation clause which required a written notice to and

    conformity by the borrower to the increased interest rate In Polotan, Sr. v. CA ,On petitioner’s

    contention that the interest rate was unilaterally imposed and based on the standards and rate

    formulated solely by respondent credit card company, we held: Cardholder hereby authorizesSecurity Diners to correspondingly increase the rate of such interest in the event of changes in

    prevailing market rates x x x" is an escalation clause. However, it cannot be said to be dependent

    solely on the will of private respondent as it is also dependent on the prevailing market rates.

    Thus, it was valid because it wasn’t  solely potestative as it was based on the market rates

    (something outside the control of respondent) here, the interest rates would vary as determined

    by prevailing market rates. Evidently, the parties intended the interest on petitioners’ loan,

    including any upward or downward adjustment, to be determined by the prevailing market rates

    and not dictated by respondent’s policy. HOWEVER, SC hold that the escalation clause here is still

    void because it grants respondent the power to impose an increased rate of interest without a

    written notice to petitioners and their written consent. Respondent’s monthly telephone calls to

    petitioners advising them of the prevailing interest rates would not suffice. A detailed billing

    statement based on the new imposed interest with corresponding computation of the total debt

    should have been provided by the respondent to enable petitioners to make an informed

    decision. An appropriate form must also be signed by the petitioners to indicate their conformity

    to the new rates. Compliance with these requisites is essential to preserve the mutuality of

    contracts. For indeed, one-sided impositions do not have the force of law between the parties,

  • 8/19/2019 Obligations and Contract Cases

    11/34

    because such impositions are not based on the parties’ essential equality. In the absence of

    consent on the part of the petitioners to the modifications in the interest rates, the adjusted

    rates cannot bind them. Hence, we consider as invalid the interest rates in excess of 15%, the

    rate charged for the first year. Based on the August 29, 2000 demand letter of China Bank,

    petitioners’ total principal obligation under the two promissory notes which they failed to settle

    is P10, 355,000. However, due to China Bank’s unilateral increases in the interest rates from 15%

    to as high as 24.50% and penalty charge of 1/10 of 1% per day or 36.5% per annum for the period

    November 4, 1999 to February 23, 2001, petitioners’ balance ballooned to P19,201,776.63. Note

    that the original amount of principal loan almost doubled in only 16 months. The Court also finds

    the penalty charges imposed excessive and arbitrary, hence the same is hereby reduced to 1%

    per month or 12% per annum. Concurring by CJ Sereno: not all escalation clauses in loan

    agreements are void per se .it is to maintain fiscal stability and to retain the value of money in

    long term contracts. However, a contract containing a provision that makes its fulfilment

    exclusively dependent upon the uncontrolled will of one of the contracting parties is void. Hence

    the provision on the promissory note: I/We hereby authorize the CHINA BANKING CORPORATIONto increase or decrease as the case may be, the interest rate/service charge presently stipulated

    in this note without any advance notice to me/us in the event a law or Central Bank regulation is

    passed or promulgated by the Central Bank of the Philippines or appropriate government

    entities, increasing or decreasing such interest rate or service charge. Is void. The floating rate

    of interest in the trust receipt agreement is also void. It reads: I, WE jointly and severally agree

    to any increase or decrease in the interest rate which may occur after July 1, 1981, when the

    Central Bank floated the interest rate, and to pay additionally the penalty of I% per month until

    the amount/s or installments/s due and unpaid under the trust receipt on the reverse side hereof

    is/are fully paid. It is ok, for banks to stipulate that interest rates on a loan not be fixed and instead

    be made dependent upon prevailing market conditions as long as there should always be areference rate upon which to peg such variable interest rates. An example of such a valid variable

    interest rate was found in Polotan, Sr. v. Court of Appeals.10 In that case, the contractual

    provision stating that "if there occurs any change in the prevailing market rates, the new interest

    rate shall be the guiding rate in computing the interest due on the outstanding obligation without

    need of serving notice to the Cardholder other than the required posting on the monthly

    statement served to the Cardholder" was considered valid. The aforequoted provision was

    upheld notwithstanding that it may partake of the nature of an escalation clause, because at the

    same time it provides for the decrease in the interest rate in case the prevailing market rates

    dictate its reduction. Here, the use of the phrase "any increase or decrease in the interest rate”

    is without reference to the prevailing market rate actually imposed by the regulations of the

    Central Bank.8 It is thus not enough to state, as akin to China Bank's provision, that the bank may

    increase or decrease the interest rate in the event a law or a Central Bank regulation is passed.

    To adopt that stance will necessarily involve a determination of the interest rate by the creditor

    since the provision spells a vague condition - it only requires that any change in the imposable

    interest must conform to the upward or downward movement of borrowing rates. And if that

    determination is not subjected to the mutual agreement of the contracting parties, then the

  • 8/19/2019 Obligations and Contract Cases

    12/34

    resulting interest rates to be imposed by the creditor would be unilaterally determined.

    Consequently, the escalation clause violates the principle of mutuality of contracts. Based on

     jurisprudence, therefore, these points must be considered by creditors and debtors in the

    drafting of valid escalation clauses. Firstly, as a matter of equity and consistent with P.O. No.

    1684, the escalation clause must be paired with a de-escalation clause.9 Secondly, so as not to

    violate the principle of mutuality, the escalation must be pegged to the prevailing market rates,

    and not merely make a generalized reference to "any increase or decrease in the interest rate"

    in the event a law or a Central Bank regulation is passed. Thirdly, consistent with the nature of

    contracts, the proposed modification must be the result of an agreement between the parties.

    In this way, our credit system would be facilitated by firm loan provisions that not only aid fiscal

    stability, but also avoid numerous disputes and litigations between creditors and debtors.

  • 8/19/2019 Obligations and Contract Cases

    13/34

    METROPOLITAN BANK VS.

    ABSOLUTE MANAGEMENT CORP.

    G.R. NO. 170498

    Facts: Metrobank deposited the AMC checks to Ayala Lumber and Hardware’s account; because

    of Chua’s control over AMC’s operations, Metrobank assumed that the checks payable to AMC

    could be deposited to Ayala Lumber and Hardware’s account. 

    Ayala Lumber and Hardware had no right to demand and receive the checks that were deposited

    to its account; despite Chua’s control over AMC and Ayala Lumber and Hardware, the two entities

    are distinct, and checks exclusively and expressly payable to one cannot be deposited in the

    account of the other.

    In its fourth-party complaint, Metrobank claims that Chua’s estate should reimburse it if it

    becomes liable on the checks that it deposited to Ayala Lumber and Hardware’s account. 

    Issue: Whether or not Ayala Lumber must return the amount of said checks to Metrobank.

    Held: Metrobank acted in a manner akin to a mistake when it deposited the AMC checks to Ayala

    Lumber and Hardware’s account because it assumed that the checks payable to AMC could be

    deposited to Ayala Lumber and Hardware’s account. This disjunct created an obligation on the

    part of Ayala Lumber and Hardware, through its sole proprietor, Chua, to return the amount of

    these checks to Metrobank.

    This fulfills the requisites of solutio indebiti. Metrobank’s fourth-party complaint falls under the

    quasi-contracts enunciated in Article 2154 of the Civil Code. Article 2154 embodies the concept

    "solutio indebiti" which arises when something is delivered through mistake to a person who has

    no right to demand it. It obligates the latter to return what has been received through mistake.Solutio indebiti, as defined in Article 2154 of the Civil Code, has two indispensable requisites:

    first, that something has been unduly delivered through mistake; and second, that something

    was received when there was no right to demand it.

  • 8/19/2019 Obligations and Contract Cases

    14/34

    LILY LIM VS.

    KOU CO PING

    G.R. NO. 175256

    Principle: A single act or omission that cause damage to an offended party may gave rise to two

    separate civil liabilities on the part of the offender –(1)civil liability ex delicto, that is, civil liability

    arising from the criminal offense under Article 100 of the Revised Penal Code and (2) independent

    civil liability, that is civil liability that may be pursued independently of the criminal proceedings.

    The independent civil liability may be based on “an obligation not arising from the act or omission

    complained of as felony”. It may also be based on an act or omission that may constitute felony

    but, nevertheless, treated independently from the criminal action by specific provision of the

    Article 33 of the Civil Code.

    FACTS: FR Cement Corporation issued several withdrawal authorities for the account of cement

    dealers and traders, Fil-Cement and Tigerbilt. Each withdrawal authority contained provision thatit is valid for six months from its date of issuance, unless revoked by FRCC Marketing Department

    .Filcement and Tigerbilt sold their withdrawal authorities to Co. On February Co then sold these

    withdrawal authorities to Lim. Using the withdrawal authorities Lim withdrew cement bags from

    FRCC on a staggered basis. Sometime in April 1999, FRCC did not allow Lim to withdraw the

    remaining bags covered by the withdrawal authorities. Lim clarified the matter with Co and

    administrative manager of Fil-Cement, who explained that the plant implemented a price

    increase and would only release the goods once Lim pays the price difference or agrees to receive

    lesser quantity of cement. Lim filed case of Estafa through Misappropriation or Conversion

    against Co. The Regional Trial Court acquitted Co. After the trial on the civil aspect of the criminal

    case the court also found Co not civilly liable. Lim sought a reconsideration which the regionaltrial Court denied. On March 14, 2005 Lim filed her notice of appeal on the civil aspect of the

    criminal case. On April 19, 2005 Lim filed a complaint for specific performance and damages

    before the RTC.

    ISSUE: Whether or not there is no forum shopping for a private complainant to pursue a civil

    complaint for specific performance and damages while appealing the judgment on the civil aspect

    of a criminal case for estafa?

    HELD: A single act or omission that cause damage to an offended party may gave rise to two

    separate civil liabilities on the part of the offender – (1) civil liability ex delicto, that is, civil liability

    arising from the criminal offense under Article 100 of the Revised Penal Code and (2) independent

    civil liability, that is civil liability that may be pursued independently of the criminal proceedings.

    The independent civil liability may be based on “an obligation not arising from the act or omission

    complained of as felony”. It may also be based on an act or omission that may constitute felony

    but, nevertheless, treated independently from the criminal action by specific provision of the

    Article 33 of the Civil Code. Because of the distinct and independent nature of the two kinds of

  • 8/19/2019 Obligations and Contract Cases

    15/34

    civil liabilities, jurisprudence holds that the offended party may pursue two types of civil liabilities

    simultaneously or cumulatively, without offending the rules on forum shopping, litis pendentia

    or res judicata. The criminal cases of estafa are based on culpa criminal while the civil action for

    collection is anchored on culpa contractual. The first action is clearly a civil action ex delicto, it

    having been instituted together with criminal action. On the other hand, the second action,

     judging by the allegations contained in the complaint, is a civil action arising from contractual

    obligation and fortuitous conduct. The Civil Case involves only the obligation arising from

    contract and from tort, whereas the appeal in the estafa case involves only the civil obligations

    of Co arising from the offense charged.

  • 8/19/2019 Obligations and Contract Cases

    16/34

    GILAT SATELLITE VS.

    UCPB

    G.R. NO. 189563

    Facts:  One Virtual placed with Gilat Satellite Network (Gilat) a purchase order for various

    telecommunications equipment, promising to pay portions of the price according to a payment

    schedule. To ensure the prompt payment, it obtained a surety bond from defendant UCPB

    General Insurance Co., Inc. (UCPB) in favor of Gilat

    One Virtual failed to pay Gilat twice, prompting Gilat to write the surety UCPB two demand letters

    for payment. However, UCPB failed to settle the amount.

    Gilat filed a complaint against UCPB. The RTC, ruling in favor of Gilat, found that Gilat has already

    complied with its end of the obligation, i.e. delivery and installation of the purchased equipment.

    Demand notwithstanding, One Virtual and UCPB, as surety, failed to settle the obligation. The

    lower court reasoned that UCPB, as surety, bound itself to pay in accordance with the Payment

    Milestones. This obligation was not made dependent on any condition outside the terms andconditions of the Surety Bond and Payment Milestones.

    However, the RTC denied Gilat’s claim for interest on the premise that the interest shall only

    accrue when the delay or refusal to pay the principal obligation is without any justifiable cause.

    Here, UCPB failed to pay its surety obligation because of the advice of its principal (One Virtual)

    not to pay. The RTC then obligated UCPB to pay Gilat the principal debt (US $1.2 Million) under

    the Surety Bond, with legal interest at the rate of 12% per annum computed from the time the

     judgment becomes final and executory, plus attorney’s fees and litigation expenses. 

    The Court of Appeals (CA) dismissed the appeal of UCPB based on lack of jurisdiction. It ruled that

    in "enforcing a surety contract, the ‘complementary-contracts-construed-together’ doctrine

    finds application." In this case, the CA considered the arbitration clause contained in the PurchaseAgreement (principal contract) between Gilat and One Virtual as applicable and binding on the

    parties to the suretyship agreement (accessory contract). Hence, the trial court’s Decision was

    vacated. Gilat and One Virtual were ordered to proceed to arbitration.

    Subject:  Liability of a surety on the principal contract is direct, primary and absolute; The

    existence of a suretyship agreement does not give the surety the right to intervene in the

    principal contract, hence, surety cannot invoke the arbitration clause between the parties in the

    principal contract; Interest, as a form of indemnity, may be awarded to a creditor in case of

    inexcusable delay incurred by a debtor in the payment of his obligation

    Held: Liability of a surety on the principal contract is direct, primary and absolute 

    1. The failure of One Virtual, as the principal debtor, to fulfill its monetary obligation to petitioner

    Gilat gave the latter an immediate right to pursue UCPB as the surety.

    2. In suretyship, the oft-repeated rule is that a surety’s liability is joint and solidary with that of

    the principal debtor. This undertaking makes a surety agreement an ancillary contract, as it

    presupposes the existence of a principal contract. Nevertheless, although the contract of a surety

  • 8/19/2019 Obligations and Contract Cases

    17/34

    is in essence secondary only to a valid principal obligation, its liability to the creditor or "promise"

    of the principal is said to be direct, primary and absolute; in other words, a surety is directly and

    equally bound with the principal. He becomes liable for the debt and duty of the principal obligor,

    even without possessing a direct or personal interest in the obligations constituted by the latter.

    3. Thus, a surety is not entitled to a separate notice of default or to the benefit of excussion. It

    may in fact be sued separately or together with the principal debtor.

    4. Sureties do not insure the solvency of the debtor, but rather the debt itself. They are

    contracted precisely to mitigate risks of non-performance on the part of the obligor. This

    responsibility necessarily places a surety on the same level as that of the principal debtor. The

    effect is that the creditor is given the right to directly proceed against either principal debtor or

    surety. This is the reason why excussion cannot be invoked. To require the creditor to proceed

    to arbitration would render the very essence of suretyship nugatory and diminish its value in

    commerce. (See Palmares v. Court of Appeals)

    The existence of a suretyship agreement does not give the surety the right to intervene in the

    principal contract, hence, surety cannot invoke the arbitration clause between the parties in theprincipal contract

    5. UCPB’s claim that the Purchase Agreement, being the principal contract to which the

    Suretyship Agreement is accessory, must take precedence over arbitration as the preferred mode

    of settling disputes, cannot be sustained.

    6. The acceptance of a surety agreement does not change in any material way the creditor’s

    relationship with the principal debtor nor does it make the surety an active party to the principal

    creditor-debtor relationship. In other words, the acceptance [of the surety agreement] does not

    give the surety the right to intervene in the principal contract. The surety’s role arises only upon

    the debtor’s default, at which time, it can be directly held liable by the creditor for payment as a

    solidary obligor. Hence, the surety remains a stranger to the Purchase Agreement. (SeeStronghold Insurance Co. Inc. v. Tokyu Construction Co. Ltd.)

    7. UCPB cannot invoke in its favor the arbitration clause in the Purchase Agreement, because it

    is not a party to that contract. An arbitration agreement being contractual in nature, it is binding

    only on the parties thereto, as well as their assigns and heirs.

    8. Section 24 of Republic Act No. 9285 is clear in stating that a referral to arbitration may only

    take place "if at least one party so requests not later than the pre-trial conference, or upon the

    request of both parties thereafter." UCPB has not presented evidence to show that either Gilat

    or One Virtual submitted its contesting claim for arbitration.

    Interest, by way of damages or indemnity, may be awarded to a creditor in case of inexcusable

    delay incurred by a debtor in the payment of his obligation

    9. Article 2209 of the Civil Code is clear: "[i]f an obligation consists in the payment of a sum of

    money, and the debtor incurs a delay, the indemnity for damages, there being no stipulation to

    the contrary, shall be the payment of the interest agreed upon, and in the absence of stipulation,

    the legal interest."

    10. Delay arises from the time the obligee judicially or extrajudicially demands from the obligor

    the performance of the obligation, and the latter fails to comply. Delay, as used in Article 1169,

  • 8/19/2019 Obligations and Contract Cases

    18/34

    is synonymous with default or mora, which means delay in the fulfilment of obligations. It is the

    nonfulfillment of an obligation with respect to time.

    11. In order for the debtor (in this case, the surety) to be in default, it is necessary that the

    following requisites be present:

    (1) That the obligation be demandable and already liquidated; (2) that the debtor delays

    performance; and (3) that the creditor requires the performance judicially or extrajudicially.

    12. If a surety, upon demand, fails to pay, it can be held liable for interest, even if in thus paying,

    its liability becomes more than the principal obligation. The increased liability is not because of

    the contract, but because of the default and the necessity of judicial collection.

    13. For delay to merit interest, it must be inexcusable in nature

    14. In culpa contractual x x x the mere proof of the existence of the contract and the failure of its

    compliance justify, prima facie, a corresponding right of relief. xxx A breach upon the contract

    confers upon the injured party a valid cause for recovering that which may have been lost or

    suffered. The remedy serves to preserve the interests of the promisee that may include his

    "expectation interest," which is his interest in having the benefit of his bargain by being put in asgood a position as he would have been in had the contract been performed, or his "reliance

    interest," which is his interest in being reimbursed for loss caused by reliance on the contract by

    being put in as good a position as he would have been in had the contract not been made; or his

    "restitution interest," which is his interest in having restored to him any benefit that he has

    conferred on the other party. Indeed, agreements can accomplish little, either for their makers

    or for society, unless they are made the basis for action. The effect of every infraction is to create

    a new duty, that is, to make recompense to the one who has been injured by the failure of

    another to observe his contractual obligation unless he can show extenuating circumstances, like

    proof of his exercise of due diligence x x x or of the attendance of fortuitous event, to excuse him

    from his ensuing liability. (See Guanio v. Makati-Shangri-la Hotel)15. Records are bereft of proof to show that UCPB’s delay was indeed justified by the

    circumstances – that is, One Virtual’s advice regarding Gilat’s alleged breach of obligations.

    16. As to the issue of when interest must accrue, our Civil Code is explicit in stating that it accrues

    from the time judicial or extrajudicial demand is made on the surety. This ruling is in accordance

    with the provisions of Article 1169 of the Civil Code and of the settled rule that where there has

    been an extra-judicial demand before an action for performance was filed, interest on the

    amount due begins to run, not from the date of the filing of the complaint, but from the date of

    that extra-judicial demand. Interest must start to run from the time petitioner sent its first

    demand letter (5 June 2000), because the obligation was already due and demandable at that

    time.

    17. Petitioner is rewarded legal interest at the rate of 6% per annum from 5 June 2000, its first

    date of extra judicial demand, until the satisfaction of the debt.

    18. "When the obligation is breached, and it consists in the payment of a sum of money, i.e., a

    loan or forbearance of money, the interest due should be that which may have been stipulated

    in writing. Furthermore, the interest due shall itself earn legal interest from the time it is judicially

    demanded. In the absence of stipulation, the rate of interest shall be 6% per annum to be

  • 8/19/2019 Obligations and Contract Cases

    19/34

    computed from default, i.e., from judicial or extrajudicial demand under and subject to the

    provisions of Article 1169 of the Civil Code. x x x When the judgment of the court awarding a sum

    of money becomes final and executory, the rate of legal interest...shall be 6% per annum from

    such finality until its satisfaction, this interim period being deemed to be by then an equivalent

    to a forbearance of credit." (See Nacar v. Gallery Frames, modifying Eastern Shipping Lines v. CA)

  • 8/19/2019 Obligations and Contract Cases

    20/34

    J PLUS ASIA DEVELOPMENT CORPORATION v.

    UTILITY ASSURANCE CORPORATION

    G.R. NO. 199650

    FACTS:  On December 24, 2007, petitioner and Martin E. Mabunay, doing business under the

    name and style of Seven Shades of Blue Trading and Services, entered into a Construction

    Agreement to build the former‘s 72-room condominium/hotel (Condotel Building 25). The

    project, costing P42,000,000.00, was to be completed within one year or 365 days reckoned from

    the first calendar day after signing of the Notice of Award and Notice to Proceed and receipt of

    down payment (20% of contract price). The P8, 400,000.00 down payment was fully paid on

    January 14, 2008. Payment of the balance of the contract price will be based on actual work

    finished within 15 days from receipt of the monthly progress billings. Per the agreed work

    schedule, the completion date of the project was December 2008. Mabunay also submitted the

    required Performance Bond issued by respondent Utility Assurance Corporation (UTASSCO) in

    the amount equivalent to 20% down payment or P8.4 million.The Construction Agreement provides for liquidated damages, as follows: ARTICLE 12  – 

    LIQUIDATED DAMAGES: 12.01 Time is of the essence in this Agreement. Should the

    CONTRACTOR fail to complete the PROJECT within the period stipulated herein or within the

    period of extension granted by the OWNER, plus One (1) Week grace period, without any

     justifiable reason, the CONTRACTOR hereby agrees – 

    a. The CONTRACTOR shall pay the OWNER liquidated damages equivalent to One Tenth of One

    Percent (1/10 of 1%) of the Contract Amount for each day of delay after any and all extensions

    and the One (1) week Grace Period until completed by the CONTRACTOR. b. The CONTRACTOR,

    even after paying for the liquidated damages due to unexecuted works and/or delays shall not

    relieve it of the obligation to complete and finish the construction.Any sum which may be payable to the OWNER for such loss may be deducted from the amounts

    retained under Article 9 or retained by the OWNER when the works called for under this

    Agreement have been finished and completed.

    Liquidated Damage[s] payable to the OWNER shall be automatically deducted from the

    contractors’ collectibles without prior consent and concurrence by the CONTRACTOR.

    12.02 To give full force and effect to the foregoing, the CONTRACTOR hereby, without necessity

    of any further act and deed, authorizes the OWNER to deduct any amount that may be due under

    Item (a) above, from any and all money or amounts due or which will become due to the

    CONTRACTOR by virtue of this Agreement and/or to collect such amounts from the Performance

    Bond filed by the CONTRACTOR in this Agreement.

    Mabunay commenced work at the project site on January 7, 2008. On November 14, 2008, after

    conducting a joint inspection and evaluation, the project was only thirty one point thirty nine

    percent (31.39 %) complete.

    On November 19, 2008, petitioner terminated the contract and sent demand letters to Mabunay

    and respondent surety. As its demands went unheeded, petitioner filed a Request for Arbitration

    before the Construction Industry Arbitration Commission (CIAC). Petitioner prayed that Mabunay

  • 8/19/2019 Obligations and Contract Cases

    21/34

    and respondent be ordered to pay the sums of P8,980,575.89 as liquidated damages and

    P2,379,441.53 corresponding to the unrecouped down payment or overpayment petitioner

    made to Mabunay.

    In his Answer, Mabunay claimed that the delay was caused by retrofitting and other revision

    works ordered by Joo Han Lee. He asserted that he actually had until April 30, 2009 to finish the

    project since the 365 days period of completion started only on May 2, 2008 after clearing the

    retrofitted old structure. Hence, the termination of the contract by petitioner was premature and

    the filing of the complaint against him was baseless, malicious and in bad faith.

    ISSUE: Whether or not Mabunay had incurred delay in the performance of his obligations under

    the Construction Agreement and is therefore liable.

    HELD: Indeed, resolution of the issue of delay was crucial upon which depends petitioner‘s right

    to the liquidated damages pursuant to the Construction Agreement.

    Default or mora on the part of the debtor is the delay in the fulfillment of the prestation by reasonof a cause imputable to the former. It is the non-fulfillment of an obligation with respect to time.

    Article 1169 of the Civil Code provides: ART. 1169. Those obliged to deliver or to do something

    incur in delay from the time the obligee judicially or extrajudicially demands from them the

    fulfillment of their obligation. It is a general rule that one who contracts to complete certain

    work within a certain time is liable for the damage for not completing it within such time, unless

    the delay is excused or waived. The Construction Agreement provides in Article 10 thereof the

    following conditions as to completion time for the project

    The CONTRACTOR shall complete the works called for under this Agreement within ONE (1)

    YEAR or 365 Days reckoned from the 1st calendar day after signing of the Notice of Award and

    Notice to proceed and receipt of down payment.In this regard the CONTRACTOR shall submit a detailed work schedule for approval by

    OWNER within Seven (7) days after signing of this Agreement and full payment of 20% of the

    agreed contract price. Said detailed work schedule shall follow the general schedule of activities

    and shall serve as basis for the evaluation of the progress of work by CONTRACTOR.

    In this jurisdiction, the following requisites must be present in order that the debtor may be in

    default: (1) that the obligation be demandable and already liquidated; (2) that the debtor delays

    performance; and (3) that the creditor requires the performance judicially or extrajudicially.

    In holding that Mabunay has not at all incurred delay, the CA pointed out that the obligation to

    perform or complete the project was not yet demandable as of November 19, 2008 when

    petitioner terminated the contract, because the agreed completion date was still more than one

    month away (December 24, 2008). Since the parties contemplated delay in the completion of the

    entire project, the CA concluded that the failure of the contractor to catch up with schedule of

    work activities did not constitute delay giving rise to the contractor‘s liability for damages.

    Records showed that as early as April 2008, or within four months after Mabunay commenced

    work activities, the project was already behind schedule for reasons not attributable to

  • 8/19/2019 Obligations and Contract Cases

    22/34

    petitioner. In the succeeding months, Mabunay was still unable to catch up with his

    accomplishment even as petitioner constantly advised him of the delays,xxx .

    Liability for liquidated damages is governed by Articles 2226 to 2228 of the Civil Code, which

    provide:

    ART. 2226. Liquidated damages are those agreed upon by the parties to a contract, to be paid

    in case of breach thereof.

    ART. 2227. Liquidated damages, whether intended as an indemnity or a penalty, shall be

    equitably reduced if they are iniquitous or unconscionable.

    ART. 2228. When the breach of the contract committed by the defendant is not the one

    contemplated by the parties in agreeing upon the liquidated damages, the law shall determine

    the measure of damages, and not the stipulation.

    A stipulation for liquidated damages is attached to an obligation in order to ensure performance

    and has a double function: (1) to provide for liquidated damages, and (2) to strengthen the

    coercive force of the obligation by the threat of greater responsibility in the event of breach. The

    amount agreed upon answers for damages suffered by the owner due to delays in the completionof the project. As a precondition to such award, however, there must be proof of the fact of delay

    in the performance of the obligation.

    As already demonstrated, the contractor‘s default in this case pertains to his failure to

    substantially perform the work on account of tremendous delays in executing the scheduled work

    activities. Where a party to a building construction contract fails to comply with the duty imposed

    by the terms of the contract, a breach results for which an action may be maintained to recover

    the damages sustained thereby, and of course, a breach occurs where the contractor inexcusably

    fails to perform substantially in accordance with the terms of the contract.

  • 8/19/2019 Obligations and Contract Cases

    23/34

    GOLDEN VALLEY EXPLORATION, INC. (GVEI) VS.

    PINKIAN MINING COMPANY (PMC) AND COPPER VALLEY, INC. (CVI).

    G.R. NO. 190080

    Facts: PMC is the owner of 81 mining claims 15 of which were covered by Mining Lease Contract

    (MLC) while the remaining 66 had pending applications for lease. PMC entered into an Operating

    Agreement (OA) with GVEI, granting the latter "full, exclusive and irrevocable possession, use,

    occupancy, and control over the mining claims for a period of 25 years, with a stipulation that

    GVEI’s non-payment of royalties would give PMC sufficient cause to cancel or rescind the OA, In

    a letter, PMC extra- judicially rescinded the OA upon GVEI’s violations of thereof. GVEI contested

    PMC’s extra-judicial rescission of the OA through a Letter.

    PMC no longer responded to GVEI’s letter. Instead, it entered into a Memorandum of Agreement

    (MOA) with CVI, whereby the latter was granted the right to enter, possess, occupy and control

    the mining claims and to explore and develop the mining claims, among others, for a period of

    25 years. Due to the foregoing, GVEI filed a Complaint Annulment of Contract and Damagesagainst PMC and CVI. The RTC declared the rescission of the OA void and the execution of the

    MOA between PMC and CVI without force and effect. On appeal, the CA reversed the RTC ruling

    and upheld the validity of PMC’s rescission of the OA and its subsequent execution of the MOA

    with CVI.

    Issue: Whether there was a valid rescission of the OA.

    Held:  Yes. In reciprocal obligations, either party may rescind the contract upon the other’s

    substantial breach of the obligation/s he had assumed thereunder. Article 1191 of the Civil Code

    which states that “the power to rescind obligations is implied in reciprocal ones, in case one ofthe obligors should not comply with what is incumbent upon him. The injured party may choose

    between the fulfilment and the rescission of the obligation, with the payment of damages in

    either case. He may also seek rescission, even after he has chosen fulfilment, if the latter should

    become impossible”. As a general rule, the power to rescind an obligation must be invoked

     judicially and cannot be exercised solely on a party’s own judgment that the other has committed

    a breach of the obligation. This is so because rescission of a contract will not be permitted for a

    slight or casual breach, but only for such substantial and fundamental violations as would defeat

    the very object of the parties in making the agreement. As a well-established exception,

    however, an injured party need not resort to court action in order to rescind a contract when the

    contract itself provides that it may be revoked or cancelled upon violation of its terms and

    conditions. By expressly stipulating in the OA that GVEI’s non -payment of royalties would give

    PMC sufficient cause to cancel or rescind the OA, the parties clearly had considered such violation

    to be a substantial breach of their agreement. Thus, in view of the above-stated jurisprudence

    on the matter, PMC’s extra-judicial rescission of the OA based on the said ground was valid.

  • 8/19/2019 Obligations and Contract Cases

    24/34

    EDS MANUFACTURING INC vs.

    HEALTHCHECK INT’L INC

    G.R. NO: 162802

    FACTS:  -lcalth Maintenance Organization HMO) entered into a one-year

    contract with DLSUMC in which HCI was to provide the employees of EMI and their dependents

    as host of medical services and benefits

    gan. HCI notified EMI that its accreditation

    with DLSUMC was suspended and advised it to avail of the services of nearby accredited

    institutions.

    SUMC resumed services. Despite this

    commitment, HCI failed to preserve its credit standing with DLSUMC prompting the latter to

    suspend its accreditation for a second time. A third suspension was still to follow on and

    remained in force until the end of the contract period.

    s were notbeing honoured by the DLSUMC and other hospitals and physicians. EMI formally notified HCI

    that it was rescinding their April 1998 Agreement on account of

    HCI’s serious and repeated breach of its undertaking including but not limited to the unjustified

    non-availability of services. It demanded a return of premium for the unused period in the cost

    of P6 million.

    the failure of EMI to collect all the

    HMO cards of the employees and surrender them to HCI as stipulated in the Agreement. HCI had

    to tell EMI on that its employees were still utilizing the cards even beyond the pretermination

    date set by EMI. It asked for the surrender of the cards so that it could process the pretermination

    of the contract and finalize the reconciliation of accounts.two letters demanding for the payment

    ofP5,884,205 as the 2/3 portion of the premium that remained unutilized after the Agreement

    was rescinded in the previous September.

    -empted EMI’s threat of legal action by instituting the present case before the

    Regional Trial Court of Pasig. The cause of action it presented was the unlawful pretermination

    of the contract and failure of EMI to submit to a joint reconciliation of accounts and deliver such

    assets as properly belonged to HCI.

    an answer alleging that HCI reneged on its duty to provide adequate

    medical coverage after EMI paid the premium in full. Having rescinded the contract, it claimed

    that it was entitled to the unutilized portion of the premium, and that the accounting required

    by HCI could not be undertaken until it submitted the monthly utilization reports mentioned in

    the Agreement.

    escission of the Agreement was not

    done through court action or by a notarial act and was based on casual or slight breaches of the

    contract. Moreover, despite the announced rescission, the employees of EMI continued to avail

    of HCI’s services. 

  • 8/19/2019 Obligations and Contract Cases

    25/34

    ional, (HCI)

    substantially breached their agreement, it also appears that Eds Manufacturing, Inc. (EMI) did

    not validly rescind the contract between them. Thus, the CA dismissed the complaint filed by HCI,

    while at the same time dismissing the counterclaim filed by EMI.

    id decision. However, the same was

    denied in a Resolution dated March 16, 2004.

    ISSUE: W/O/N There was a valid rescission of the agreement of the parties

    RULING: We rule in the negative.

    First, Article 1191 of the Civil Code states:

    The power to rescind obligations is implied in reciprocal ones, in case one of the obligors should

    not comply with what is incumbent upon him.

    The injured party may choose between the fulfillment and the rescission of the obligation, with

    the payment of damages in either case. He may also seek rescission, even after he has chosenfulfillment, if the latter should become impossible.

    The court shall decree the rescission claimed, unless there be just cause authorizing the fixing of

    a period.

    This is understood to be without prejudice to the rights of third persons who have acquired the

    thing, in accordance with Articles 1385 and 1388 and the Mortgage Law.

    The general rule is that rescission (more appropriately, resolution ) of a contract will not be

    permitted for a slight or casual breach, but only for such substantial and fundamental violations

    as would defeat the very object of the parties in making the agreement.

    Thus, the rescission referred to in Article 1191, more appropriately referred to as resolution, is

    on the breach of faith by one of the parties which is violative of the reciprocity between them.In the present case, it is apparent that HCI violated its contract with EMI to provide medical

    service to its employees in a substantial way. As aptly found by the CA, the various reports made

    by the EMI employees from July to August 1998 are living testaments to the gross denial of

    services to them at a time when the delivery was crucial to their health and lives.

    However, although a ground exists to validly rescind the contract between the parties, it appears

    that EMI failed to judicially rescind the same. In Iringan v. Court of Appeals, this Court reiterated

    the rule that in the absence of a stipulation, a party cannot unilaterally and extrajudicially rescind

    a contract. A judicial or notarial act is necessary before a valid rescission (or resolution) can take

    place. Thus – Clearly, a judicial or notarial act is necessary before a valid rescission can take place,

    whether or not automatic rescission has been stipulated. It is to be noted that the law uses the

    phrase "even though" emphasizing that when no stipulation is found on automatic rescission, the

     judicial or notarial requirement still applies. x x x x

    But in our view, even if Article 1191 were applicable, petitioner would still not be entitled to

    automatic rescission. In Escueta v. Pando, we ruled that under Article 1124 (now Article 1191) of

    the Civil Code, the right to resolve reciprocal obligations, is deemed implied in case one of the

    obligors shall fail to comply with what is incumbent upon him. But that right must be invoked

  • 8/19/2019 Obligations and Contract Cases

    26/34

     judicially. The same article also provides: "The Court shall decree the resolution demanded,

    unless there should be grounds which justify the allowance of a term for the performance of the

    obligation."

    This requirement has been retained in the third paragraph of Article 1191, which states that "the

    court shall decree the rescission claimed, unless there be just cause authorizing the fixing of a

    period."

    Consequently, even if the right to rescind is made available to the injured party, the obligation is

    not ipso facto erased by the failure of the other party to comply with what is incumbent upon

    him.

    The party entitled to rescind should apply to the court for a decree of rescission. The right cannot

    be exercised solely on a party’s own judgment that  the other committed a breach of the

    obligation. The operative act which produces the resolution of the contract is the decree of the

    court and not the mere act of the vendor. Since a judicial or notarial act is required by law for a

    valid rescission to take place, the letter written by respondent declaring his intention to rescind

    did not operate to validly rescind the contract. What is more, it is evident that EMI had notrescinded the contract at all. As observed by the CA, despite EMI s pronouncement, it failed to

    surrender the HMO cards of its employees although this was required by the Agreement, and

    allowed them to continue using them beyond the date of the rescission. The in-patient and the

    out-patient utilization reports submitted by 1 ICI shows entries as late as March 1999, signifying

    that EMI employees 1 were availing of the services until the contract period were almost over.

    The continued use by them of their privileges under the contract, with the apparent consent of

    EMI, belies any intention to cancel or rescind it, even as they felt that they ought to have received

    more than what they got.

  • 8/19/2019 Obligations and Contract Cases

    27/34

    OSCAR AND THELMA CACAYORIN VS.

    ARMED FORCES AND POLICE MUTUAL BENEFIT ASSOCIATION, INC. (AFPMBAI)

    G.R. NO. 171298

    Facts:  Oscar Cacayorin filed an application with AFPMBAI to purchase a property which the latter

    owned through a loan facility. Oscar and his wife, Thelma, and the Rural Bank of San Teodoro

    executed a Loan and Mortgage Agreement with the former as borrowers and the Rural Bank as

    lender, under the auspices of PAG-IBIG. On the basis of the Rural Bank's letter of guaranty,

    AFPMBAI executed in petitioners' favor a Deed of Absolute Sale, and a new title was issued in

    their name. Then, the PAG-IBIG loan facility did not push through and the Rural Bank closed.

    Meanwhile, AFPMBAI somehow was able to take possession of petitioners' loan documents and

    the TCT, while petitioners were unable to pay the loan for the property. AFPMBAI made written

    demands for petitioners to pay the loan for the property. Then, petitioners filed with the RTC a

    complaint for consignation of loan payment, recovery of title and cancellation of mortgage

    annotation against AFPMBAI, PDIC and the Register of Deeds of Puerto Princesa City. AFPMBAIfiled a motion to dismiss claiming that petitioners' Complaint falls within the jurisdiction of the

    Housing and Land Use Regulatory Board (HLURB), as it was filed by petitioners in their capacity

    as buyers of a subdivision lot and it prays for specific performance of contractual and legal

    obligations decreed under Presidential Decree No. 957(PD 957). It added that since no prior valid

    tender of payment was made by petitioners, the consignation case was fatally defective and

    susceptible to dismissal.

    Issue: Whether or not the case falls within the exclusive jurisdiction of the HLURB.

    Ruling:  No. Unlike tender of payment which is extrajudicial, consignation is necessarily judicial;hence, jurisdiction lies with the RTC, not with the HLURB. Under Article 1256 of the Civil Code,

    the debtor shall be released from responsibility by the consignation of the thing or sum due,

    without need of prior tender of payment, when the creditor is absent or unknown, or when he is

    incapacitated to receive the payment at the time it is due, or when two or more persons claim

    the same right to collect, or when the title to the obligation has been lost. The said provision

    clearly precludes consignation in venues other than the courts.

  • 8/19/2019 Obligations and Contract Cases

    28/34

    ADELAIDA SORIANO V.

    PEOPLE OF THE PHILIPPINES

    G.R. NO. 181692

    Facts: Evelyn Alagao (Evelyn), daughter of private complainant Consolacion Alagao(Alagao), as

    borrower-mortgagor, executed a “Contract of Loan Secured by Real Estate Mortgage with Special

    Power to Sell Mortgage Property without Judicial Proceedings “in favour of petitioner as lender-

    mortgagee. The instrument provides for a P40, 000 loan secured by a parcel of land registered in

    Evelyn’s name. It likewise provides that the loan was to be paid two years from the date of

    execution of the contract and that Evelyn agrees to give petitioner¼ of every harvest from her

    corn land until the full amount of the loan has been paid, starting from the first harvest. Based

    on Alagao’s testimony, the first harvest was made only in September 1994. Petitioner on the

    other hand claims that from the time the loan was obtained until September 1994, there were

    already four harvests. During pre-trial, it was admitted by Alagao that she did not only receive

    P40,000 as provided in the contract of loan but P51,730 in the form of fertilizers and cashadvances. Alagao and some companions delivered 398 sacks of corn grains to petitioner.

    Petitioner prepared a voucher indicating that Alagao had received the amount of P85,607 as full

    payment for the 398 sacks of corn grains. Alagao signed said voucher even if she only received

    P3,000. According to Alagao, 64 of the 398 sacks will serve as partial payment of her P40,000 loan

    with petitioner while the remaining balance will come from theP85,607 cash she was supposed

    to receive as payment for the corn grains delivered so she can redeem her daughter’s land title.

    The Regional Trial Court (RTC) of Misamis Oriental, Branch 40, rendered a decision finding

    petitioner guilty beyond reasonable doubt of the crime of estafa. However, the CA set

    petitioner’s conviction aside in the assailed decision. The CA ruled that the prosecution failed to

    establish that petitioner made false pretenses, fraudulent acts or fraudulent means to induceAlagao to deliver to her the 398 sacks of corn grains. In fact, in Alagao’s testimony, she admitted

    that she delivered the corn grains to petitioner because the latter was demanding payment from

    her and she wanted to pay her obligation of P40,000 to petitioner so that she could get back the

    title of her daughter’s mortgaged property and the balance of the total cash value of the 398

    sacks of corn. Thus, the CA held, in the absence of deceit, petitioner’s liability is only civil.

    Unsatisfied, petitioner is now before the Supreme Court questioning her civil liability.

    Issue: Whether legal compensation is proper.

    Held:  Yes. Compensation is a mode of extinguishing to the concurrent amount, the debts of

    persons who in their own right are creditors and debtors of each other. The object of

    compensation is the prevention of unnecessary suits and payments through the mutual

    extinction by operation of law of concurring debts. Article 1279 of the Civil Code provides for the

    requisites for compensation to take effect and the Court ruled that all the requisites for

    compensation are present in the instant case. First, petitioner and Alagao are debtors and

    creditors of each other. It is undisputable that petitioner and Alagao owe each other sums of

  • 8/19/2019 Obligations and Contract Cases

    29/34

    money. Petitioner owes P85,607 for the value of the corn grains delivered to her by Alagao in

    September 1994 while Alagao owes petitioner P51,730 by virtue of a loan extended by the latter

    in February 1994.Second, both debts consist in a sum of money. There is no issue as to the

    P85,607 debt by petitioner that it consists a sum of money. As to the P51,730 received by Alagao

    from petitioner, though what was extended by petitioner consists of cash advances and

    fertilizers, there is no dispute that said amount is payable in money. Third, both debts are due.

    Upon delivery of the 398 sacks to petitioner, she was under the obligation to pay for the value

    thereof as buyer. As to Alagao’s debt, the contract of loan provided that it is payable in February

    1996. Though it was not yet due in September 1994 when she delivered the 398 sacks of corn

    grains to petitioner, it eventually became due at the time of trial of the instant case. Fourth, both

    debts are liquidated and demandable. A debt is liquidated when the amount is known or is

    determinable by inspection of the terms and conditions of relevant documents. There is no

    dispute that the value of the 398 sacks of corn grains is P85,607. And lastly, neither of the debts

    are subject of a controversy commenced by a third person. There are no third-party claims with

    respect to Alagao’sP51,730 loan. As to petitioner’s P85,607 debt representing the 398 sacks ofcorn grains, the alleged other owners have not commenced any action to protect their claim over

    it. Thus, the P85, 607 debt cannot be considered subject of a controversy by a third person. With

    respect to the 1/4 share in the harvest due to petitioner as provided in the contract of loan, the

    same cannot be considered in the legal compensation of the debts of the parties since it does

    not consist in a sum of money, said share being in the form of harvests. More importantly, it is

    not yet liquidated. There is still a dispute as to how many harvests were made from the time of

    the execution of contract of loan up to the time the action was commenced against petitioner

    and even when the principal obligation became due in February 1996. Thus, the harvests due

    petitioner is not capable of determination.

  • 8/19/2019 Obligations and Contract Cases

    30/34

    DAVID VS.

    DAVID

    G.R.NO.162365 

    FACTS: On July 7, 1995, Respondent Eduardo C. David (Eduardo), and his brother Edwin C. David

    (Edwin), acting on their own and in behalf of their co-heirs, sold their inherited properties to

    Petitioner Roberto R. David (Roberto), specifically: (a) a 1,231 square meters parcel of land,

    together with all the improvements thereon, located in Baguio City (Baguio City lot); and (b) 2

    units International CO 967- Truck Tractor with two Mi-Bed Trailers. A deed of sale with

    assumption of mortgage (deed of sale) embodied the terms of their agreement, stipulating that

    the consideration for the sale was P6,000,000.00, of which P2,000,000.00 was to be paid to

    Eduardo and Edwin, and the remaining P4,000,000.00 to be paid to Development Bank of the

    Philippines (DBP) in Baguio City to settle the outstanding obligation secured by a mortgage on

    such properties. Eduardo and Edwin was given the right to repurchase within 3 years from the

    execution of the deed of sale based on the purchase price agreed upon, plus 12% interest perannum.

    A memorandum of agreement (MOA) was executed by Roberto and Edwin in April 1997, with

    spouses Marquez and Soledad Go, by which they agreed to sell the Baguio City lot to the latter

    for P10,000,000.00. The Spouses Go then deposited the amount of P10,000,000.00 to Robertos

    account. Thereafter, Roberto gave Eduardo P2,800,00.00 and returned to him one of the truck

    tractors and trailers subject of the deed of sale.

    When Eduardo demanded for the return of the other truck tractor and trailer but Roberto

    refused, he initiated a replevin suit again the latter, alleging that he was exercising his right torepurchase under the deed of sale. Roberto then denied that Eduardo could repurchase the

    properties in question; and insisted that the MOA had extinguished their deed of sale by

    novation.

    The RTC rendered a judgment in favor of Eduardo on December 5, 2001. RTC opined that the

    stipulation giving Eduardo the right to repurchase had made the deed of sale a conditional sale;

    that Eduardo had fulfilled the conditions for the exercise of the right to repurchase; that the

    ownership of the properties had reverted to Eduardo; that Robertos defense of novation had no

    merit; and that due to Roberto's bad faith in refusing to satisfy Eduardos claim.

    Roberto appealed to the CA.

    The CA affirmed the decision of RTC. It opined that although there was no express exercise of the

    right to repurchase, the sum of all the relevant circumstances indicated that there was an

    exercise of the right to repurchase pursuant to the deed of sale, that the findings of the RTC to

    the effect that the conditions for the exercise of the right to repurchase had been adequately

    satisfied by Eduardo, and that no novation as claimed by Roberto had intervened.

  • 8/19/2019 Obligations and Contract Cases

    31/34

    The CA denied Robert's motion for reconsideration. Hence, Roberto filed a petition for review on

    certiorari.

    ISSUE:  Whether or not Respondent Eduardo exercised his right to repurchase?

    HELD:  Respondent Eduardo exercised his right to repurchase.

    CIVIL LAW: right to repurchase

    A sale with right to repurchase is governed by Article 1601 of the Civil Code, which provides that:

    Conventional redemption shall take place when the vendor reserves the right to repurchase the

    thing sold, with the obligation to comply with the provisions of Article 1616 and other stipulations

    which may have been agreed upon. Conformably with Article 1616, the seller given the right to

    repurchase may exercise his right of redemption by paying the buyer: (a) the price of the sale, (b)

    the expenses of the contract, (c) legitimate payments made by reason of the sale, and (d) thenecessary and useful expenses made on the thing sold.

    The CA and the RTC both found and held that Eduardo had complied with the conditions

    stipulated in the deed of sale and prescribed by Article 1616 of the Civil Code. From the testimony

    of the defendant himself, the preconditions for the exercise of the plaintiffs right to repurchase

    were adequately satisfied by the latter. The alleged repurchase was exercised within the

    stipulated period of 3 years from the time the Deed of Sale was executed. Moreover, the

    defendant returned to plaintiff the amount of P2,800,000.00 from the total purchase price of

    P10,000,000.00. This only means that this is the excess amount pertaining to plaintiff and co-

    heirs after the defendant deducted the repurchase price of P2,000,000.00 plus interests and hisexpenses. Add to that is the fact that defendant returned one of the trucks and trailers subject

    of the Deed of Sale.

    In Metropolitan Bank and Trust Company v. Tan, the court ruled that a redemption within the

    period allowed by law is not a matter of intent but of payment or valid tender of the full

    redemption price within the period. Verily, the tender of payment is the sellers manifestation of

    his desire to repurchase the property with the offer of immediate performance.

    In the present case, Eduardo paid the repurchase price to Roberto by depositing the proceeds of

    the sale of the Baguio City lot in the latter's account. Such payment was an effective exercise of

    the right to repurchase. On the other hand, the court dismissed as devoid of merit Roberto's

    insistence that the MOA had extinguished the obligations established under the deed of sale by

    novation. In sales with the right to repurchase, the title and ownership of the property sold are

    immediately vested in the vendee, subject to the resolutory condition of repurchase by the

    vendor within the stipulated period. Accordingly, the ownership of the affected properties

  • 8/19/2019 Obligations and Contract Cases

    32/34

    reverted to Eduardo once he complied with the condition for the repurchase, thereby entitling

    him to the possession of the other motor vehicle with trailer.

  • 8/19/2019 Obligations and Contract Cases

    33/34

    NARCISO DEGAÑOS v

    PEOPLE

    G.R. No. 162826

    FACTS: In an amended information, the Office of the Provincial Prosecutor charged Aida Luz, and

    Narciso Degaños in the RTC with estafa under Article 315 of the RPC allegedly committed as

    follows: That they received from Sps Atty. Bordador gold and pieces of jewelry worth almost 500k

    under express obligation to sell the same on commission and remit the proceeds thereof or

    return the unsold gold and pieces of jewelry, but the said accused, once in possession of the said

    merchandise and far from complying with their obligation, in spite of repeated demands for

    compliance therewith, wilfully, unlawfully and feloniously, with intent of gain and grave abuse of

    confidence misapply, misappropriate and convert to their own use and benefit the said

    merchandise and/or the proceeds thereof, to the damage and prejudice of said Sps. Atty.

    Bordador in the said amount of almost 500k.Prior to the institution of the instant case, a separate

    civil action for the recovery of sum of money was filed by the Sps. Bordador against accused Aidaand Narciso. In an amended complaint Ernesto Luz, husband of Aida, was impleaded as party

    defendant. RTC found Narciso liable and ordered him to pay the sum of P725,463,98 as actual

    and consequential damages plus interest and attorney’s fees in the amount of P10,000.00. On

    the other hand, Aida was ordered to pay the amount of P21,483.00, representing interest on her

    personal loan. The case against Ernesto Luz was dismissed for insufficiency of evidence. Both

    parties appealed to the CA which affirmed the aforesaid decision. On further appeal, the SC

    sustained the CA. While the said civil case was pending, the private complainants instituted the

    present case against the accused. Narciso and Aida Luz are brother and sister. Lydia knew them

    because they are the relatives of her husband. The usual business practice of Sps. Atty Bordador

    with the accused was for Narciso to receive the jewelry and gold items for and in behalf of Aidaand for Narciso to sign the "Kasunduan at Katibayan" receipts while Aida will pay for the price

    later on. The subject items were usually given to Narciso only upon instruction from Aida through

    telephone calls or letters. Said business arrangement went on for quite some time since Narciso

    and Aida Luz had been paying religiously. When the accused defaulted in their payment, they

    sent demand letters Aida sent a letter to Lydia Bordador requesting for an accounting of her

    indebtedness. Lydia made an accounting which contained the amount of P122,673.00 as principal

    and P21,483.00 as interest. Thereafter, she paid the principal amount through checks. She did

    not pay the interest because the same was allegedly excessive. Atty. Jose Bordador brought a

    ledger to her and asked her to sign the same. The said ledger contains a list of her supposed

    indebtedness to the private complainants. She refused to sign the same because the contents