21
MIKE DEWINE, OHIO GOVERNOR | JACK MARCHBANKS, ODOT DIRECTOR | MIKE DOMBROWSKI, DISTRICT DEPUTY DIRECTOR ODOT DISTRICT 9 2020 CONSTRUCTION PROGRAM SERVING ADAMS, BROWN, HIGHLAND, JACKSON, LAWRENCE, PIKE, ROSS AND SCIOTO COUNTIES

ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

MIKE DEWINE, OHIO GOVERNOR | JACK MARCHBANKS, ODOT DIRECTOR | MIKE DOMBROWSKI, DISTRICT DEPUTY DIRECTOR

ODOT DISTRICT 9 2020 CONSTRUCTION PROGRAM

SERVING ADAMS, BROWN, HIGHLAND, JACKSON, LAWRENCE, PIKE, ROSS AND SCIOTO COUNTIES

Page 2: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Ohio Department of Transportation - District 9

2020 DRAFT CONSTRUCTION PROGRAM hio’s highways are essential to keeping and creating new jobs. With a mission to provide safe and easy movement of people and goods from place to place, the Ohio Department of Transportation (ODOT) is responsible for maintaining one of the largest transportation networks in the nation. Guided by ethical principles and accountability, ODOT works to improve safety, enhance travel and advance economic development.

The following draft summary outlines those projects which are programmed for the 2020 construction season in ODOT District 9. With an estimated cost of over $57 million, the construction program will consist of 81 new and ongoing preservation, maintenance and safety improvement projects to be sold and/or constructed through FY2020 and the first quarter of FY2021, and included in these are projects in which the department is partnering with the respective county engineer’s office.

Due to production and planning variables, however, not all projects may be sold as proposed, and projects are subject to funding availability. Any cost estimates, sale dates or schedules cited in this document are subject to change, and estimated costs are the construction cost estimates established by District 9’s Planning & Design staff prior to bid letting; these do not include any preliminary engineering or right of way acquisition costs as applicable to the project. Projects listed as Local Government are those which are being administered by the Department of Transportation; additional information about these and other local projects can be obtained from the respective local agency.

Additional information about these projects will be released as they are scheduled or awarded. For more information, please contact the District 9 Public Information Office at 740-774-8834 or email [email protected].

The environmental review, consultation, and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried-out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.

O

PID = Project Identification Number CRS = County, Route, Section

Page 3: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

$-

$2,000,000

$4,000,000

$6,000,000

$8,000,000

$10,000,000

$12,000,000

$14,000,000

ADAMS BROWN HIGHLAND JACKSON LAWRENCE PIKE ROSS SCIOTO DISTRICT-WIDE

$1,448,075

$6,505,643

$7,152,930

$3,535,622

$12,496,765

$7,020,105

$8,180,789

$7,437,158

$3,396,987

2020 Construction Program Cost Summary

Page 4: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

ADAMS COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

100843 ADA-136-20.40/ADA-247-

18.17

Resurfacing SR 247 from the Seaman corp. limit to the Highland County Line, and SR 136 from the Winchester corp. limit to the Highland County Line. Traffic will be maintained using flaggers as needed.

AWARDED 11/27/2019

$655,575

101808 ADA SR 73 10.43

Roadway Widening

CARRYOVER: Primary construction complete. Traffic will be maintained using flaggers as needed. AWARDED 3/15/2019

$2,686,481

LOCAL GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 101867 ADA CR VAR

Guardrail FY21 Guardrail

Replacement (Safety)

Repair and replace guardrail on various county roads. Traffic will be maintained using flaggers as needed.

10/2/2020 $288,500

103779 ADA-CR 6B/9B-15.72/30.40

Bridge Replacement

Replace the existing structures on Fawcett Rd. between Hope Ridge Rd. & Steam Furnace Rd. (completed), and Mineral Springs Rd. between Davis Memorial Rd. & Cedar Fork Rd. The road will be closed for this construction.

AWARDED 9/3/2019

$504,000

TOTAL: $1,448,075

Page 5: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 6: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

BROWN COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

92014 BRO-SR 353-0.00 Resurfacing From Red Oak to SR 125. Traffic will be maintained using flaggers as needed AWARDED 12/19/2019

$589,549

93796 BRO SR 125 7.10 Brdg Replace

Bridge Replacement

CARRYOVER: Located immediately west of the village of Georgetown. Traffic will be maintained in one lane in each direction.

AWARDED 3/15/2019

$8,213,769

102849 BRO-221-3.91 & VAR

Bridge Preservation

Erosion control work at three locations along SR 221. Traffic will be maintained using flaggers as needed.

5/4/2020 $750,000

102888 BRO SR 763 0.62 Culvert

Culvert Replacement

Between Stringtown Rd. and Lawwill Rd. Traffic will be maintained in one lane using temporary signals.

6/1/2020 $665,619

105099 BRO-505-5.50 Culvert Replacement

Between Love Rd. and SR 756. The road will be closed for 60 days. Traffic will be detoured using SR 125, SR 221, and US 52.

4/20/2020 $171,490

105667 BRO/ROS-32/35-7.43/9.28

Culvert Replacement

On SR 32 between Klein Rd. and US 68 in Brown County, and on US 35 east of Westfall Rd. in Ross County. Trafficl will be maintained using one lane, temporary closures as needed.

3/23/2020 $267,548

109635 BRO SR 41 4.18 OH18-02

Geologic Maintenance / Slide Repair

Located between Ellis Run Rd. and the Adams County Line. Traffic will be maintained in one lane using temporary signals.

9/28/2020 $472,222

110309 BRO SR 32 11.93 Turn Lane

Intersection Improvement

(Safety)

Realignment of existing turn lanes on SR 32 at Sardinia-Mowrystown Rd. Traffic will be maintained in one lane in each direction.

6/1/2020 $500,000

110787 BRO US 52 16.46 OH19-01

Geologic Maintenance / Slide Repair

Between Chief Logan Gap Rd. and 3-Mile Rd. Traffic will be maintained in one lane using temporary signals.

6/1/2020 $1,200,000

LOCAL GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 78609 BRO CR 42A 0.28 Bridge

Replacement Replace the existing structure on Skiffsville Rd. near the Clermont County Line. The road will be closed for 90 days. Traffic will be detoured via SR 505, SR 756, and Felicity-Higginsport Rd.

6/15/2020 $390,900

105313 BRO CR 76 5.52 Brdg Replace

Bridge Replacement

Replace the existing structure on Purdy Rd. over White Oak Creek in Sardinia. The road will be closed for 120 days. Traffic will be detoured via SR 32 and Sardinia-Mowrystown Rd.

AWARDED 12/19/2019

$1,498,314

TOTAL: $6,505,643

Page 7: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 8: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

HIGHLAND COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

91995 HIG US 62 17.32

Resurfacing From the Hillsboro corp. limit to the Fayette County Line. Traffic will be maintained using flaggers as needed.

AWARDED 10/3/2019

$1,577,524

100426 HIG 321 0.00

Resurfacing Between Buford and US 62. Traffic will be maintained using flaggers as needed. AWARDED 10/3/2019

$826,766

100504 HIG US 62 10.38

Resurfacing From Warlamount Rd. to the Hillsboro corp. limit. Traffic will be maintained using flaggers as needed.

8/10/2020 $944,443

105095 HIG-41-2.02 Culvert Replacement Between Sinking Spring and Pin Hook Rd. Traffic will be maintained using flaggers as needed. 4/6/2020 $350,000 110310 HIG SR 72

0.00 Resurface

Resurfacing From US 62 to the Clinton County Line. Traffic will be maintained using flaggers as needed. 6/1/2020 $1,063,739

110364 HIG-134-5.18

Smoothseal

Resurfacing Between SR 138 and Murtland Rd. Traffic will be maintained using flaggers as needed. 7/27/2020 $835,220

LOCAL GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 99192 HIG

CR4/VAR Guardrail

FY20

Guardrail / Roadside Maintenance

New guardrail installed on various county roads. Traffic will be maintained using flaggers as needed.

AWARDED 11/1/2019

$341,233

99193 HIG CR3 Various PM

FY 2020

Traffic Control (Safety) New pavement markings on various county roads. Traffic will be maintained using flaggers as needed.

AWARDED 8/15/2019

$313,000

101388 HIG CR 10 1.62 Brdg Replace

Bridge Replacement At Careytown Rd. over Clear Creek, north of Hillsboro. The road will be closed for 90 days. 2/3/2020 $901,004

TOTAL: $7,152,930

Page 9: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 10: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

JACKSON COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

96292 JAC-139-12.45 Bridge Replacement

Replace the existing structure just south of the intersection with SR 32. Traffic will be maintained in one lane using temporary signals.

6/15/2020 $480,000

100443 JAC-32-VAR Bridge Preservation

Bridge sealing various structures between SR 35 and the Pike County Line. Traffic will be maintained using one lane temporary closures as needed.

3/23/2020 $400,000

100887 JAC-279-10.13 Bridge Replacement

CARRYOVER: Replace the existing structure over Jackson Lake between Tommy Been Rd. and W. Main St. in Oak Hill. Traffic maintained in one lane using temporary signals.

AWARDED 9/20/2019

$1,644,899

102448 JAC-35-26.10 Bridge / Culvert Maintenance

Repair the existing structure over Indian Creek, between the Centerville Rd. intersections. Traffic will be maintained in one lane in each direction.

AWARDED 10/3/2019

$930,852

107587 JAC-124-17.55 Resurfacing From SR 327 to the Vinton County Line. Traffic maintained using flaggers as needed. AWARDED 11/27/2019

$858,001

LOCAL GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 97347 JAC TR 221 2.33

Brdg Replace Bridge

Replacement CARRYOVER: Replace the existing structure on Roberts Rd., immediately south of US 35. Traffic will be detoured locally via Oakland Rd.

AWARDED 8/15/2019

$821,329

98668 JAC CR 29 8.73 Bridge Replacement

Replace the existing structure on Raysville Rd. between SR 327 and Borland Rd. near Ray, Ohio. The road will be closed for this construction.

2/24/2020 $866,769

TOTAL: $3,535,622

Page 11: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 12: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

LAWRENCE COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

10374 LAW-93-22.71

Bridge Replacement

Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flaggers as needed until April, at which point one lane will be closed for the remainder of the project. Traffic will then be maintained in one lane using temporary signals.

AWARDED 11/27/2019

$587,814

20617 LAW-243-9.45

Bridge Preservation

Repalce the existing structure at the intersection of SR 243 and Deering-Middle Leatherwood Rd. with a box culvert. Traffic will be maintained in one lane using temporary signals.

2/24/2020 $574,478

96285 LAW-141-12.98

Bridge Replacement

South of SR 378 in Aid. Traffic will be maintained in one lane using temporary signals 5/4/2020 $1,354,184

100587 LAW SR 522 0.00

Resurfacing Chip/Seal SR 522 from the Scioto County Line to SR 93. Traffic will be maintained using flaggers as needed.

AWARDED 11/1/2019

$719,624

100849 LAW-217-13.59

Resurfacing Chip/Seal SR 217 between SR 218 and SR 7. Traffic will be maintained using flaggers as needed.

5/18/2020 $563,980

100888 LAW-775-14.36

Bridge Replacement

At the intersection of SR 775 and Long Creek Rd., south of Wilgus. SR 775 will be closed for 14 days as part of the project. At all other times, traffic will be maintained in one lane using temporary signals

2/3/2020 $487,433

102043 LAW SR 7 0.66 Rockfall

Geologic Maintenance /

Slide Repair

Benching and layback of existing hillside on SR 7 between Buffalo Creek Rd. and Tallow Ridge Rd. Southbound traffic will be maintained in one lane in each direction

3/9/2020 $7,004,542

102889 LAW-378-2.25

Culvert Replacement

Located between Drift Creek Rd. and McKinney Creek-Symmes Church Rd. Traffic will be maintained using flaggers as needed.

3/9/2020 $334,846

104167 LAW US 52 11.75 Phase II OH15-01

Geologic Maintenance /

Slide Repair

CARRYOVER: Phase II of a rock fall remediation project between SR 652 at the Ashland twin bridges and Crabtree Hollow Rd. Traffic will be maintained in a minimum of one lane in each direction

AWARDED 6/27/2019

$14,546,779

109600 LAW US 52 20.45 Safety

Intersection Improvement

(Safety)

Install continuous thru-lane on US 52 Westbound through the intersection with Wal-Mart Way. US 52 traffic will be maintained in two lanes in each direction by shifting lanes onto the shoulders. The US 52 median will close for 14 days, meaning there will be no access to or from US 52 Westbound and Walmart Way. Walmart Way and US 52 Eastbound will function as a right-in right-out intersection during this time.

4/20/2020 $692,258

111327 LAW SR 7 0.66 Tree Removal

Vegetative Maintenance

Tree clearing on SR 7 between Buffalo Creek Rd. and Tallow Ridge Rd. Southbound traffic will be maintained using shoulder closures or single lane closures as needed.

AWARDED 12/19/2019

$177,605

TOTAL: $12,496,765

Page 13: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 14: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

PIKE COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

93829 PIK-124-9.46 Bridge Replacement

Located between Lathom Hill Rd. and Spicy Run Rd. Traffic will be maintained in one lane using temporary signals

AWARDED 10/18/2019

$597,864

103852 PIK CR 50 1.95 OH16-01

Geologic Maintenance /

Slide Repair

Located on Watson Rd. between Mutton Run Rd. and Hay Hollow Rd. Traffic is being maintained in one lane using temporary signals.

AWARDED 11/1/2019

$1,791,299

105666 PIK-104-3.16 Culvert Replacement

Located between Loys Run Rd. and Ganderhook Rd. Traffic will be maintained in one lane using temporary signals

AWARDED 12/23/2019

$288,820

106088 PIK SR 220 12.24 OH17-01

Geologic Maintenance /

Slide Repair

Located between Miller Lane and Industrial Park Dr. Traffic will be maintained in one lane using temporary signals.

AWARDED 10/18/2019

$145,594

108734 PIK SR 32 15.77 Safety

Intersection Improvement

(Safety)

RCUT intersection project at SR 32 and Shyville Rd. The existing signal will be removed and the median closed, and specialized U-turn lanes will be installed. One lane in each direction will be maintained on SR 32 throughout construction.

5/4/2020 $2,319,655

110731 PIK-SR 32-12.54 Landslide

Geologic Maintenance /

Slide Repair

Located between SR 104 and Smokey Hollow Rd. Traffic on SR 32 Westbound will be maintained in one lane throughout construction. SR 32 Eastbound traffic unaffected

5/18/2020 $748,775

111089 PIK-23-8.37 Bridge / Culvert Maintenance

Bridge Maintenance on the structure on the north side of Piketon. US 23 northbound traffic will be maintained in one lane.

AWARDED 12/19/2019

$94,000

LOCAL GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 99194 PIK CR 5/VAR

Guardrail FY 2020

Guardrail / Roadside

Maintenance

Repair and replace guardrail at various locations on county roads. Traffic will be maintained using flaggers as needed.

2/3/2020 $433,113

107076 PIK CR4/VAR PM FY20

Traffic Control (Safety)

Pavement marking work on various county roads. Traffic will be maintained using flaggers as needed.

6/1/2020 $96,200

108262 PIK CR 66 2.12 OH18-01

Geologic Maintenance /

Slide Repair

Located on Germany Rd. between Owl Creek Rd. and Gravel Hill Rd. Traffic will be maintained in one lane using temporary signals.

2/24/2020 $59,956

110036 PIK CR 84 4.60 Brdg

Replacement

Bridge Replacement

Located on Wakefield-Mound Rd. between Grove Rd. and Seif Rd. The road will be closed for this construction.

4/20/2020 $444,828

TOTAL: $7,020,105

Page 15: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 16: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

ROSS COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

93744 ROS SR 207 0.00 New Roadway CARRYOVER: Extension of SR 207 from the US 23 interchange to SR 159, north of Delano Rd., with roundabouts at SR 207-SR 159 and at SR 159-SR 180 intersections.

AWARDED 8/15/2019

$6,668,143

97178 ROS US 50 21.91 Safety

Intersection Improvement

(Safety)

CARRYOVER: Turn lane construction and signalization at Plyleys Ln. in Chillicothe. Traffic will be maintained in one lane in each direction.

AWARDED 5/31/2019

$2,354,243

100575 ROS SR 41 3.69 Resurfacing Located between US 50 and SR 28. Traffic maintained using flaggers as needed. AWARDED 2/3/2020

$1,656,011

100846 ROS-138/207-0.27/3.08

Resurfacing Chip/Seal SR 138 between SR 28 and Austin Rd. Chip/Seal SR 207 from SR 104 to the Pickaway County Line. Traffic will be maintained using flaggers as needed.

4/20/2020 $1,370,667

100863 ROS US 35 25.02 / JAC US 35 1.79

Resurfacing Resurface US 35 in Ross County between US 50 and Vigo Rd. Resurface US 35 in Jackson County between Springer Rd. and Brohard Rd. Traffic will be maintained in one lane in each direction throughout.

AWARDED 10/18/2019

$2,722,253

102851 ROS-35/104-(13.40)(18.12)/25.45

Bridge Preservation Perform maintenance and repairs on the existing structures on Biers Run Rd. and Adena Rd. over US 35. Traffic on US 35 will be maintained in one lane in each direction. Biers Run Rd. and Adena Rd. will close for 30 days. Perform maintenance and repairs on the existing structure on SR 104 at Yellow Bud. Traffic will be maintained in one lane using temporary signals.

AWARDED 11/27/2019

$452,792

106089 ROS US 23 2.50 OH17-01

Geologic Maintenance /

Slide Repair

Located at SR 327/Scioto Trails. US 23 Northbound will be reduced to one lane. Access to SR 327 will be maintained during construction.

3/23/2020 $892,927

107179 ROS-207-13.55 Culvert Replacement

Located south of the village of Clarksburg. Traffic will be maintained using flaggers as needed.

AWARDED 10/3/2019

$236,666

GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 99195 ROS CR127/ VAR

Guardrail FY 2020 Guardrail / Roadside

Maintenance

Replace and repair guardrail on various county roads. Traffic maintained using flaggers as needed.

AWARDED 10/3/2019

$269,474

109348 ROS Tar Hollow Resurf ODNR FY20

Roadway Minor Rehab

Chip/Seal various Forest Roads. Traffic maintained using flaggers and other traffic control devices as needed.

4/6/2020 $580,000

TOTAL: $8,180,789

Page 17: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 18: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

SCIOTO COUNTY - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

20742 SCI-73-4.25 Bridge Replacement

Replace the existing structure between Dry Run Rd. and Laurel Fork Rd. (Old SR 73). Traffic will be maintained in one lane using temporary signals.

AWARDED 6/11/2019

$1,032,750

76461 SCI-US 23-11.48

Resurfacing From the Pike County Line to SR 348. Traffic will be maintained in one lane in each direction. AWARDED 11/27/2019

$2,551,589

96959 SCI-73-11.81 Bridge Replacement

Replace two existing structures between Big Spruce-Little Bear Rd. and Arion Rd. Traffic will be maintained in one lane using temporary signals. Big Spruce-Little Bear Rd. will also close for 5 days as part of this construction.

3/9/2020 $2,312,548

98005 SCI-335-8.63 Bridge Replacement

Replace the existing structure south of the intersection of SR 335/Bennett School House Rd./High St. in Minford. Traffic will be maintained on SR 335 in one lane using temporary traffic signals.

3/9/2020 $1,139,280

100496 SCI-US 52-31.24

Resurfacing From SR 522 to the Greenup Dam. Traffic will be maintained in one lane in each direction. 3/9/2020 $1,906,627

100892 SCI-139-15.00

Culvert Replacement

Replace the existing structure at Salem Rd. and SR 139. Salem Rd. will be closed for 30 days as part of this project. Traffic will be maintained on SR 139 with flaggers as needed.

6/15/2020 $720,000

103708 SCI SR 140 2.16 Safety

Intersection Improvement

(Safety)

Remove existing site obstructions to improve visibility between Lang-Slocum Rd. and Dixon Mill Rd. Traffic will be maintained using flaggers as needed.

3/23/2020 $243,155

106651 SCI-73-23.01 Culvert Replacement

Located between Poole St. and Galena Pike. Galena Pike will be closed south of Briggs Rd. for this construction. Traffic on Briggs Rd. and SR 73 will be maintained in one lane.

AWARDED 11/27/2019

$279,670

110473 SCI US 23 11.43 Safety

Traffic Control (Safety)

Upgrade existing signal at US 23/SR 728/SR 348 intersection, install additional signal head for US 23 Southbound traffic, install additional lighting. Traffic will be maintained in one lane in each direction.

7/13/2020 $200,000

STATE GOVERNMENT PROJECTS PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated

Cost 101880 SCI CR VAR

Guardrail FY 2021

Roadside / Median

Improvement (Safety)

Repair and replace guardrail on various country roads. Traffic will be maintained using flaggers as needed.

7/2/2020 $288,500

107284 SCI Shawnee State Forest

Bridges

Bridge Preservation

Rehabilitate six bridges at various locations on Rehabilitate six bridges at various locations on Forest Roads in Shawnee State Forest. The affected roads will be closed during each rehab. orestry roads in Shawnee State Forest. The affected roads will be closed during each rehab.

6/1/2020 $347,379

TOTAL: $7,437,158

Page 19: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

Page 20: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9

DISTRICT-WIDE PROJECTS - 2020 CONSTRUCTION PROGRAM STATE GOVERNMENT PROJECTS

PID CRS Project Type Location Description and Maintenance of Traffic Sale Date Estimated Cost

97978 D09 PM FY2020 (A)

Traffic Control (Safety)

District-wide auxiliary striping project. Traffic will be maintained using flaggers or other traffic control devices as needed.

AWARDED 11/27/2019

$140,121

97979 D09 RPM FY2020

Traffic Control Maintenance

District-wide Reflective Pavement Marker (RPM) replacement. Traffic will be maintained using flaggers as needed.

2/24/2020 $238,660

97980 D09 PM FY2020 (B)

Traffic Control (Safety)

District-wide long line striping project. Traffic will be maintained using flaggers or other traffic control devices as needed.

AWARDED 10/3/2019

$1,919,092

102522 D09-CR-FY2020

Culvert Preservation

Various locations. Traffic will be maintained using flaggers and other traffic control devices as needed.

AWARDED 11/1/2019

$363,249

109297 D09 HS FY2020

Vegetative Maintenance

District-wide Herbicidal Spraying. Traffic will be maintained using flaggers as needed. AWARDED 12/19/2019

$110,865

111407 D09 HS FY2021

Vegetative Maintenance

District-wide Herbicidal Spraying. Traffic will be maintained using flaggers as needed. 12/14/2020 $125,000

112237 D09-Tree Removal

Vegetative Maintenance

District-wide tree cutting. Traffic will be maintained using flaggers as needed 6/1/2020 $500,000

TOTAL: $3,396,987

Page 21: ODOT DISTRICT 9 · 10374 LAW-93-22.71 Bridge Replacement Just south of the intersection of SR 93 and Telegraph Hill Rd. Traffic will be maintained using flagger s as needed until

Ohio Department of Transportation – District 9