49
ODOT Manual of Bridge Inspection 2014 v8 Condition Rating Inspection Field Manual (Chapters 7 & 8)   

ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

ODOT Manual of Bridge Inspection 2014 v8 

Condition Rating Inspection 

Field Manual (Chapters 7 & 8) 

 

 

Page 2: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 107

Chapter7:FieldEvaluationThe importance of keeping public vehicular traffic safe and the inspector team safe in and around the 

bridge site and the speed of mitigating or reducing unsafe bridge conditions should not be diminished in 

light of assigning correct condition ratings or element level ratings.  The primary and first envelope of 

ascertaining bridge maintenance needs and condition ratings for the safety of the 

traveling public is through the inspectors’ visual assessment. Bridge inspectors who 

require prescription bifocals for driving or operating machinery shall use bifocals 

when performing bridge inspections.   

If an item is buried, hidden or is not visible, the condition shall be assessed based on 

destructive  and  nondestructive  testing  or  indicators  in  the materials  covering  the 

surfaces.  Allow the indicators to influence a lower condition rating when the unseen 

item is directly affected.  

 

When documenting deficiencies and assigning appropriate condition ratings the 

inspector must answer three important questions regarding the bridge: 

Public Safety? 

Bridge maintenance and repair needs must be effectively identified through early detection in 

order to safeguard the traveling public and minimize repair costs.   

What changed?  

The inspectors’ role is to provide thorough inspections identifying bridge conditions and defects.  

Ratings will be downgraded when the item changes from the original as‐built condition not only 

since the previous inspection but through the structures’ history.  Rapid degradation will require 

increased scrutiny.   

Is the structural capacity affected?   

The controlling structural elements primarily serve to transfer the bridges’ self‐weight and the 

traffic  live  load  into  the  earth.    The  load  path must  have  a  safe  and  predictable  route  and 

available  redundancy  through  the  entire  bridge.   When  this  load  path  is  compromised  the 

condition of the overall  item will be downgraded.   The fact that a bridge was designed for  less 

than current  legal  loads and may be posted will have no  influence upon condition ratings.   For 

Figure 60 ‐ Bifocals required 

Page 3: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 108

the purposes of this manual a Redundant load path will have more than three (3) primary beam 

or truss‐lines (i.e. four or more primary).  Load ratings on file must match field conditions. 

 

Figure 61 – Redundant Superstructure: 4 load paths 

 

Figure 62 – Non‐redundant Superstructure: 2 load paths 

In some instances the deficiency will occur in a single location.  If one deficiency reduces the load 

carrying capacity or serviceability of the component (Condition Rating inspections) then the element can 

be considered a weak link in the structure.  The entire item may be down‐rate based on one severe 

deficiency i.e. a 4” long crack will down‐rate the entire beam/girder rating. 

Page 4: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 109

Portions of bridges that are being supported or strengthened by temporary members will be rated 

based on their actual condition; that is, the temporary members are not considered in the rating of the 

item.  A temporary measure is an element installed that is generally in place no more than 7 years i.e. an 

initial temporary member may become permanent retrofit if there are no short term plans of a more 

thorough replacement.  Completed bridges not yet opened to traffic, if rated, will be coded as if open to 

traffic.   

Nomenclature 

Bridges shall be labeled looking upstation from the smallest to largest straight‐line‐mileage (SLM).  The 

intent  is to monitor, maintain and fix deficiencies and more than  likely these task will be peformed by 

different  people.    Communication  is  vitally  important  to  ensure  monitoring  and  repairing  remains 

consistent.  As‐built drawings may supersede these guidelines at the discretion of the Control Authority 

Program Manager (for example border bridges, major bridge construction labeling etc). 

1. Looking North on a North‐South route 

a. Rear abutment, or Abutment 1, is the South abutment, or smaller SLM 

b. Beams/Girders/Fascias/Truss  lines  are  counted  from  the  left  to  the  right  looking 

upstation. In other words the left fascia beam will be beam number 1. 

 

Figure 63‐ Beam Nomenclature 

 

2. Looking East on a East‐West route 

a. Rear abutment, or Abutment 1, is the West abutment, or smaller SLM 

b. Beams/Girders/Fascias/Truss  lines  are  increasing  from  the  left  to  the  right  looking 

upstation. In other words the left fascia beam will be beam number 1. 

Page 5: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 110

3. Pier number 1 will be the first pier looking upstation from the rear abutment.  

4. Left  and  Right  (parallel)  structures  will  follow  the 

naming  convention  dictated  by  the  increasing 

straight  line mileage.   This  includes  the noncardinal 

structure that has traffic flowing against the straight 

line mileage. 

 

 

5. Lanes should be labeled driving or slow, middle lane(s), and passing or fast lane(s).   

6. Span numbering increases with the SLM.  In other words, Span 1 will always be supported by the 

rear abutment. 

Left Right

Increasing SLM

Increasing SLM

Left Bridge

Right Bridge

Figure 64 ‐ Cardinal and Non‐Cardinal Nomenclature

Page 6: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 111

7. For  non‐highway  structures  (pedestrian,  railroads,  conveyor  belts,  etc.)  over  highways,  the 

south  or  the west  abutment  shall  be  the  rear  abutment.    For  example,  an  overhead  over  a 

Northbound Cardinal route would have the following designation: 

 

8. The differences  among  the  three:  Substructure  Slope Protection, Approach  Embankment  and 

Channel Protection   

a. Slope  protection  is  underneath  the  “shadow”  of  the  structure  protecting  the 

substructure slope. 

Figure 65 ‐ Span Numbering Over Mainline

Page 7: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 112

b. Channel  protection  is  the  protected  embankment  of  the  stream  both  upstream  and 

downstream. 

c. Approach  Embankment  is  the  sloped  earth  up  to  the  roadway  generally  behind  the 

wingwall.  For culverts it includes the portion of earth above the structure or “fill”. 

 

Inspection  Walking  Limits   

The Bridge Inspection includes all items within limits of the bridge and how the surrounding 

environment influences the structure, the maintenance needs and the safety of the traveling public.   

Upstation and Downstation  

 

Bridges not under fill:  

The walking limits, at a minimum, include portions of the approach on each end (forward and rear) of 

from the bridge to the furthest of:  

Twice the length of the Approach Slab 

Relief Joint 

Thirty feet 

 

Bridges under Fill i.e. Culverts:   

Walking limits and Approach ratings shall, at a minimum, include the furthest of the following distances 

on each side (forward and rear) of the culvert: 

Length Equivalent to the Clear span or 

Length Equivalent to the Depth of fill 

 

Additional distances may be included, on a case‐by‐case basis, at the discretion of the inspector in cases 

where fill, vaulted or embankment material was added that directly impacts the structure. 

   

Page 8: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

  

Page 113

Left and Right  

The minimum walking limits include a distance from a point upstream to a point downstream that shall 

include the following: 

Within the influence of the structure (a distance equal to the elevation difference between 

the stream bed and the roadway) 

One‐hundred feet Upstream and Downstream from the bridge centerline where a history 

of hydraulic concerns (scour, Channel misalignment, debris fields etc) exist 

 

Beyond the walking limits, visually sight a reasonable distance upstream and downstream to note any 

hazards or potential hazards in the maintenance needs and comments accordingly but inspectors 

need‐not include them in the numerical rating.  Observations during low‐flow periods, probing for 

signs of undermining or substructure deterioration or both should be done during all routine 

inspections.   

 

FieldReport

A completed Bridge Inspection Field Report is a legal document.  It may be used by an inspector to 

complete either an element level inspection or a condition rating inspection.  Each bridge, at a 

minimum, must be inspected in accordance with the procedures in this manual: 

A qualified Team Leader is at the bridge at all times during each initial, routine, in‐depth, 

fracture critical member and underwater inspection 

Condition codes are correctly assigned 

All notable bridge deficiencies are identified, and 

Condition codes are supported by narrative that appropriately justifies and documents the 

rating or condition state assignment. 

People, who sign inspection reports or forge SMS approvals without meeting the minimum NBIS 

qualifications or the minimum qualifications in this manual, may be subject to prosecution for 

forgery or fraud under section 2921.11 of the Ohio Revised Code or other applicable state or federal 

laws. 

 

Page 9: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 114

   

Figure 66 ‐ Bridge Inspection Field Report 

Page 10: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 115

Figure 67 ‐ Field Report

Page 11: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 116

CodingtheField Report

The  Summary  ratings,  Safety  Features  and 

Operating  Status  (orange  highlights  in 

adjacent  figure)  must  be  coded,  when  the 

item  exists  on  the  bridge,  when  collecting 

either Condition Rating or Element Level data.  

The  coding  of  these  orange  items  are 

discussed in the following sections.  

CodingtheSummaryItems

The  guidance  table  on  the  next  page  is  a 

succinct guide  for  the  Summary  ratings.   The 

worst  bold  box  1‐4  Individual  component 

Condition  Rating  or  Transition  rating  will 

influence the 9‐0 Summary rating.   

Generally, in coding the items, start at the top, 

“Excellent”,  and  read  down  the  9  rows  of 

condition ratings until you have moved down 

to  a  rating  that  is worse  than  the  actual  condition  item being  coded.   Choose  the  rating  above  that 

rating.  The vertical lines bordering the columns shall be treated as “or” conditions i.e. choose the lowest 

or worst column. 

Severity & Extent:  Condition codes are properly used when they provide an overall characterization of 

the general condition of the entire component being rated as it has degraded since its as‐built 

condition. Conversely, they are improperly used if they attempt to describe localized or nominally 

occurring instances of deterioration or disrepair.  An inspector may find materials or guidelines that are 

not defined during the course of their inspection.  The inspector should use discretion and the intent of 

the 9‐0 Guide in order to determine the appropriate condition.  Defects that are not visible for 

inspection shall be assessed based on the available visible surface.  Surfaces not visible shall be assessed 

based on destructive and nondestructive testing or indicators in the materials covering the surfaces.  

Page 12: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 117

Condition Rating Guide  1‐4 

Individual 

Component 

9‐0 NBIS Summary 

Inspector Guidelines  (Quantitative comments include the Location, Extent & Severity of the 

deficiency) 

1‐GOOD  9 ‐ Excellent  No problems noted: no section loss, 

general deterioration. 

Make brief comments as necessary.  Communicate the predominant deficiency. 

 8 ‐ Very Good   

7 ‐ Good Some minor problems (ex. extent of concrete deterioration is up to 1% spalling or up to 5% saturation)  

 

2‐FAIR 

6 – Satisfactory 

Structural elements show some minor deterioration ( ex. extent of concrete deterioration is up to 5% spalling or up to 10% saturation) 

 

5 ‐Fair 

Structural elements show deterioration but are sound (ex. extent of concrete deterioration is up to 10% spalling or up to 20% saturation ) 

Document deficiencies quantitatively.  Consider taking photos or making sketches. 

 

3‐POOR 

4 ‐ Poor 

Advanced* (ex. extent of concrete deterioration is more than 10% spalling or more than 20% saturation).  Usually the load path appears to be affected for primary members or there are obvious structural changes since the as‐built condition that are advanced.  

Candidate to establish monitoring benchmarks to track the rate‐of ‐change.  Take photos, make sketches and document quantitatively in order to determine if a re‐load rating is possible.  Include in‐service conditions to verify capacity 

Poor  

Structurally Deficient** 

3 ‐ Serious  4‐Poor. . . And local failures possible. Above. . . And discuss the deficiency immediately with Control Authority. 

4‐CRITICAL 

2 ‐ Critical 

3‐Serious. . . And Unless closely monitored it may be necessary to close the bridge until corrective action is taken. 

Above. . . And the bridge is a candidate to dispatch road closure and/or immediate repairs and/or increased monitoring (Interim Inspections).  Confirm in writing, critical finding. 

1 ‐Imminent Failure 

2‐Critical. . . And Major deterioration is affecting stability.  Bridge or lane(s) shall be closed to traffic but corrective action may put bridge back into light service. 

Above. . . And Dispatch immediate lane or bridge closure.  Contact the Control Authority.  Stay at the bridge until the safety of the traveling public is achieved.  Confirm in writing. 

0 ‐ Failed 1‐Imm Failure. . . And Out of service ‐ beyond corrective action. 

* Advanced –widespread deficiencies or a likely reduction to capacity (more examples on following page).   ** Structurally Deficient (SD) –Bridge Deck, Superstructure, or Substructure Summary rated 4‐Poor or below.    A bridge can also be classified as structurally deficient if its load carrying capacity is significantly below current  design standards or if a waterway below frequently overtops the bridge during floods. 

Table 34 ‐ Condition  

Page 13: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 118

Common “Advanced” Deficiencies Settlement  ‐  Exceeds  tolerable  limits  depending  on  component,  activity  and  if  it  is measurable  or 

unstable  change.    Examples  include:  continued  unrepaired  settlement,  More  than  1”  vertical  for 

approach slab ends for high speed routes. 

Scour  ‐  Exceeds  tolerable  limits,  for  example  unprotected  sides  of  spread  footing,  loss  of  bearing 

capacity, undermining, 1/3 or more of the front row of piling exposed piling. 

Distortion ‐ Exceeds tolerable limits, for example distortion or buckling that is localized and warranting a 

structural review.  

Section Loss  

Flexure or Bending Members 

Steel Web –  

In  the  shear  zone:  Corrosion  hole  (in  any  interior  beam OR  fascia  beam  if  the  bridge  is 

horizontally  curved or  if  the  fascia  beam  is one of  2 or  3 beams  total).   Corrosion holes 

behind a web stiffener or behind the bearing are not considered “advanced” 

In  the  shear  zone: Deep  section  loss more  than 50% of web depth  for an area above  the 

bearing 8” high and 18 X the web thickness wide (in any interior beam OR fascia beam if the 

superstructure is non‐redundant or horizontally curved)  

  Steel Flange –  

Section loss of the flange cross section more than 1/4 of flange in the maximum negative or 

positive flexure zone (for “zone” longitudinal length use 1/3 of span length) 

Steel Axial Members 

Truss Members 

Corrosion holes OR section loss reducing any one cross section by more than 10% average  

Steel Bents (including bents with steel columns without reinforcing cages) 

Corrosion holes in 3 piles OR 

Missing steel sheath around ½ of one pile OR 

Overall thin metal in 3 consecutive piles  

Corrugated Metal Pipe  ‐Perforations or overall  thin metal which allows  for an easy puncture 

with chipping hammer throughout invert with roughly 20% of structure affected 

For Reinforced Concrete ‐ Exposed steel with more than 10% reduction in cross section or 360 exposure in at least four adjacent primary reinforcing bars in any maximum flexure zone. 

For Noncomposite Prestressed Concrete Box Beam ‐ More than ¼ prestressing strands exposed 

in one transverse plane (including strands not visible but adjacent to deteriorated concrete such 

as  saturated,  delaminated  or  cracked)  in  one  box  with  the  neighboring  beam  in  similar 

condition.   

Page 14: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 119

Inspection Comments 

The inspector must utilize sound judgment in assigning the appropriate numerical rating.  The rating an 

inspector assigns should be related to the actions required.  Quantitative Comments, sketches or photos 

are required and must be made available for future inspections for items coded with a Condition Rating 

of 5‐Fair or worse.   A different  inspector  in subsequent  inspections should be able to successfully find, 

quantify,  rate  and  determine  obvious  change  in  degradation  based  on  the  inspection  comments 

provided by the previous inspector.  Naturally expect the amount of comments, photos, documentation 

and  inspection time to  increase as the structure degrades.   All comments must be free of hearsay and 

generalities outside of objective justification for the numerical ratings 

CodingtheSafetyFeatures

Approach Safety Features If any one corner is not standard then the rating shall be not standard or “0”. 

Item ‐  Safety Feature  

Type –   N36B)‐Transition, N36C)‐Guardrail, N36D)‐Termination 

 

Code each of the three items with a 0, 1 or N appraisal item as it compares to current acceptable 

standards as established by ODOT or the most recent crash‐worthy standards.  See Appendix. Coding 

Safety Features (36.A, B, C & D) for additional guidance.   

0 ‐   Inspected feature does not meet current acceptable standards or a safety feature is required  

and none is provided. 

1 ‐   Inspected feature meets current acceptable standards (ODOT). 

N ‐   Not applicable or a safety feature is not required.

 

36B 36D 36C 

36A 

Page 15: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 120

36B: Transition ‐ The transition is required to change the safety feature from the relatively flexible 

guardrail system to the rigid bridge rail.  Methods to stiffen a transition include increased post spacing, 

nesting of guardrail, and embedding the post base in concrete. 

 

 Figure 68 ‐ Safety Feature Approach Rail and Transition 

36C: Guardrail –The guardrail system is designed to screen motorists from hazards beneath the bridge 

and hazardous roadside features on the approach to the bridge.  These hazards include the approach to 

the bridge if they are steeper than 4:1, trees larger than 4‐inches in diameter, large signs and other 

permanent structures.  Note that wood blocks are no longer allowed to meet the TL3 requirement and 

the height to the top of the guardrail is very important. 

 

36D: Termination – –The end treatment protects and shields the motorists from the guardrail itself.  

Most guardrail end treatments are designed to gate, meaning they will allow a vehicle to pass through if 

struck at an excessive angle.  Others include impact attenuators, sand filled barrels and non‐gating 

impact attenuators. 

 

 

Figure 69 ‐ Safety Features Approach Rail and Termination 

   

Page 16: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 121

Deck Safety Feature If any rail is not standard then the rating is not standard or “0”. 

Item ‐  Safety Feature  

Type –   36A) Bridge Rail 

 Code this item with a 0, 1 or N appraisal item as it compares to current acceptable standards.  All 

approved rails are tested in accordance with the Manual of Assessing Safety Hardware (MASH) and meet 

one of six Test Levels (TL) base on the speed and type of facility carried by the bridge.   

 

NHS routes are typically required to have a TL3 bridge barrier at minimum.   See Appendix. Coding 

Safety Features (36.A, B, C & D) for additional guidance 

 

Code   Description 

0 ‐   Inspected feature does not meet current acceptable standards or a safety feature is required  

  and none is provided 

1 ‐   Inspected feature meets current acceptable standards (ODOT) 

N ‐   Not applicable or a safety feature is not required (i.e. culverts) 

 

 

 

   

Page 17: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 122

Coding the Operational Status 

Item ‐  41. Operational Status 

The operational status of the bridge should be coded using the following: 

"A"   Open, no restriction 

"B"   Open, posting recommended but not legally implemented (all signs not in place) 

Inspectors shall verify that the restriction signing is clear at the bridge site and correctly 

represented in the inventory.  When the necessary signs are not in place or the posting 

recommended in the inventory by the load rating engineer is less than the actual field 

conditions i.e., no signs exist when a posting is recommended or the posting in the field 

does not match with the inventory (a B shall not be used if the sign is non‐compliant 

with the OMUTCD), the inspector shall ensure proper action is taken as soon as possible.  

Inspectors shall code the Operational Status “B” and the weight restriction signs shall be 

remedied at the bridge site no later than 90 days from the date of discovery.  It will be 

the responsibility of the Program Manager to verify that posting signs are in place and 

the inspector will update the Operational Status at the next regularly scheduled 

inspection. 

“C”  Under construction with portions of the bridge open to traffic (ex. half‐width construction) 

"D"   Open, would be posted or closed except for temporary shoring, etc. to allow for unrestricted 

traffic 

"E"   Open, temporary structure in place to carry legal loads while original structure is closed and 

awaiting replacement or rehabilitation. 

"G"   New structure not yet open to traffic 

"K"   Bridge closed to all traffic 

"P"   Posted for load‐carrying capacity restriction (may include other restrictions) 

Load Posting Signs: Verify that the Load Rating Sign matches the posted signage.  

Bridges on State Routes are posted based any of the four Ohio Legal Loads Operating 

Rating is less than 100% (after rounding).  Inspectors are to compare with the inventory 

with the field conditions and ensure the inventory is the same as the field condition.    

"R"   Posted for other load‐carrying capacity restriction (ex.NO TRUCKS, Signage 

indicates a Speed reductions or the number of vehicles on the bridge to 

reduce impact to the structure).  

"X"   Bridge closed for reasons other than condition or load‐carrying capacity.   

Page 18: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

 

Page 123

Coding the General Appraisal 

Item ‐  General Appraisal 

 The GA is the lowest rating of either the  

 SUPERSTRUCTURE SUMMARY SUBSTRUCTURE SUMMARY SUPPLEMENTAL SUMMARY  

OR CULVERT SUMMARY 

 The general appraisal will be based on the existing condition of the bridge as compared to its as‐built 

condition.  The load carrying capacity will not be used in evaluating condition items. Portions of bridges 

that are being supported or strengthened by temporary members will be rated based on their actual 

condition, i.e. the temporary members are not considered in the rating of the item.  The fact a bridge 

was designed for less than current legal loads and may be posted will have no influence upon ratings.   

 Team Leaders: At least one NBIS Team Leader must be at the bridge for the duration of every field 

inspection and only qualified NBIS Team Leaders may sign an inspection form.  Inspections shall be 

performed on each bridge on an annual basis with the time between inspections no greater than 18 

months.  If the inspector is a registered professional engineer a review by another P.E. will not be 

necessary if the Inspector has a P.E. license and satisfies the definition of an NBIS Team Leader.  The 

inspector is to fill in the date of the inspection as the last day they were in the field.  It is imperative for 

the Team Leader to communicate findings that threaten the safety of the traveling public to the public 

entity who is responsible for maintaining the structure.  This may include communication above and 

beyond the normal inspection‐report review process. 

 

Reviewers: Only qualified NBIS Program Managers with a PE (Reviewers) may sign an inspection report 

as a reviewer.  Reports must be approved into SMS within 90 days after the field inspection for NHS and 

state structures, and within 180 days (except for NBIS NHS bridges) for county, municipal and local 

structures.   A reviewer must be a professional engineer registered in the State of Ohio and satisfy the 

minimum NBIS Program Manager qualifications.  The reviewed date must always be after the inspection 

date.  At a minimum reviews serve to:  

Maximize uniformity  

Delegate maintenance needs 

Communicate programming needs 

Establish items to monitor 

Ensure compliance  

Perform Quality Control 

Page 19: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 125

Chapter8:AssigningConditionRatingstothe1‐4ItemsThe Bridge Inspection Field Report is a document that may be used to complete either an element level 

inspection or a condition rating 

inspection.   The following report has 

the condition rating boxes highlighted 

blue.  All ratings in orange are 

required, when the item exists on the 

bridge, for both an element level and 

condition rating inspection.   

 

Condition Rating  Materials 

In order to expand upon the 9‐0 

“Condition Rating Guide” table and the 

“Advanced” definitions in Chapter 7 

the following Material Specific 

guidance shall be followed when 

coding either the 1‐4.  The worst 1‐4 

bold box should correlate with the 9‐0 

Summary rating.  Most deficiencies are 

material‐based and these tables will be 

beneficial.  Those components with 

non‐material deficiencies or more 

specific guidance are denoted with a “ded” on the field report.  The charted guidance for these items 

follows the material guidance.  The seven material types include: Reinforced Concrete, Wearing Surface, 

Structural Steel, Prestressed Concrete, Timber, Masonry & Mechanically Stabilized Earth. 

   

Page 20: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 126

Reinforced Concrete Cracking: Knowing the extent of cracking gives an indication of how much water and chlorides are able to 

penetrate into the concrete. On tined concrete decks or overlays, it may be difficult to see cracks. The best 

time to see cracks on tined decks is soon after a rain (though this is not always practical). As a deck dries out, 

cracks will remain wet longer than the deck surface and thus appear as dark lines against the lighter colored, 

dry deck.  Consideration may be used for raising a rating when a crack is retrofitted or dormant.  Types of 

cracks commonly encountered include the following: 

o Transverse flexural cracks (structural) due to negative bending will most likely appear over the piers of 

continuous superstructures or in the midspan of slabs.  

o Shear Cracks (structural) will most likely be adjacent to supports. 

o Longitudinal flexural cracks (structural). These are caused by negative bending of the deck over the girders 

or beams.  

o Longitudinal reflective cracks (structural) may appear along the joints of adjacent prestressed box beams. 

This cracking is caused by differential beam deflection.  

o Temperature and shrinkage cracks (non‐structural). This map/pattern will be apparent on most concrete 

decks and overlays.  

o Transverse reflective cracks (non‐structural) may appear adjacent to an expansion joint. These cracks 

suggest that the joint anchorage hardware is beginning to fail.  

Spalls and Delaminations: Delamination or spalling of the concrete is not necessarily an indication of poor 

concrete quality or of structural issues.  It usually indicates that chlorides and moisture have migrated through 

the concrete and attacked the reinforcing steel.  As the reinforcing steel corrodes, it increases in volume which 

tends to push the concrete away from the steel.  When the corrosion forces caused by this steel expansion 

exceed the tensile strengths of the concrete, the concrete starts to delaminate or separate from the surface.  A 

hollow sounding surface when tapped with a hammer or steel rod indicates a delamination which often results 

in a spall.  The amount of time for this to occur depends on the porosity or permeability of the concrete, the 

depth of resteel and the prevalence of moisture and chlorides.   

      

Page 21: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 127

Reinforced Concrete – Condition Rating Definitions 1‐4  9‐0 Summary   % Spalling,  

% Pothole or % Asphalt Patch % Saturation or % Delamination and Cracking 

1‐Good  9‐Excelent  No signs of distress, no discoloration 

8‐Very Good  Isolate, Minor  Minor, no rust staining 

7‐Good  Up to 1% *  Up to 5%, Minor, no rust staining Minor problems, hairline cracking with isolated leaking, isolated efflorescence.  

2‐Fair  6‐Satisfactory  Up to 5% *,  Stub Abutments: up to 4" deep spalling for less than 1/2 of the bridge width 

Up to 10% Minor cracking with leaking, efflorescence and isolated rust staining.   Map cracking combined with areas of saturation.  Minor differential settlement  

5‐Fair  Up to 10% with exposed steel,  Stub Abutments: may have up to 4” deep spall for more than ½ of bridge width.  

Up to 20%,  Stub Abutments: may have 100% saturation with full width delaminations with a few exposed vertical bars Cracking with moderate leaking and buildup of efflorescence and widespread rust staining.   Structural cracking with moderate, stable rotation or settlement  

3‐Poor  4‐Poor  More than 10%  Areas should include Advanced section loss to reinforcing  

More than 20%  Advanced cracking with heavy buildup, leaking, efflorescence and rust staining.    

3‐Serious  4‐Poor. . . And Local Failures Possible (ex. precursor to through‐hole 

4‐Crit ical 

2‐Critical  3‐Serious. . . And Unless closely monitored it may be necessary to close the bridge or lane(s) until corrective action is taken 

1‐Imm Failure  2‐Critical. . . And Major deterioration is affecting stability.  Bridge or lane(s) shall be closed to traffic but corrective action may put bridge back into light service 

0‐Failed  . . . And Out of service ‐ beyond corrective action 

*Slab‐Type Superstructures with one transverse section of more than 1/3 of the bridge width or primary bars exposed shall be coded no better than a "5‐Fair".   

Table 35 ‐ Condition Rating Material: Concrete   

Page 22: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 128

Wearing Surface – Condition Rating Definitions (Use steel material guidance for the Stay in place forms filled with asphalt)  

1‐4 Span. 

Distress Potholes, Cracks, Ruts, Delaminations (Asphalt patches in Concrete overlay) 

Rideability  

1‐Good 

None  Smooth   

Isolated, Minor cracking Minor isolated rutting 

Smooth 

1% distress, minor rutting   No bounce,  

2‐Fair 1‐10% distress   isolated traffic bouncing 

10‐15% distress (2‐5% asphalt patches on rigid concrete overlay) 

traffic bounce is not isolated but still subtle 

3‐Poor 

Advanced deficiencies:  

6‐10% asphalt patches on rigid concrete overlay 

More than 15% potholes (special attention should be given to areas with exposed structural superstructure elements), OR  

Widespread rutting deeper than 1”, OR  

Advanced cracking  

Traffic bouncing, impact to vehicles and/or bridge 

4‐Critical 

Serious. . . And Unless closely monitored it may be necessary to close the bridge or lane(s) until corrective action is taken 

 Critical. . . And Major deterioration is affecting stability.  Bridge or lane(s) shall be closed to traffic but corrective action may put bridge back into light service 

Imminent Failure. . . And Out of service ‐ beyond corrective action 

Table 36 ‐ Condition Rating Material: Wearing Surface 

  

 

 

 

   

Page 23: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 129

STEEL – Condition Rating Definitions 1‐4  9‐0 

Summary *Section Loss and Deterioration  **Cracks 

1‐Good 

9‐Excellent  None     

8‐V Good No measurable section loss or very minor section loss 

  

7‐Good  Insignificant section loss, minor    

2‐Fair 

6‐Satisfactory 

Minor Section Loss (ex. isolated pitting, corr. pin‐hole in redundant fascia web or any interior beam stiffener or behind a bearing)  

  

5‐Fair 

Sound with some deterioration, moderate section loss (ex. Some areas of heavy pitting, corrosion holes possible in fascia beams or outside of the load path, less than 1/4 loss in flanges in max bending regions) 

Compression zone: Minor cracking up to 2” long, stable cracks in base metal 

3‐Poor 

4‐Poor  Advanced (following page) 

Compression zone: Any longer than 2”, stable cracks in base metal.   Fracture Critical Member (FCM): any stable crack in the base metal of a FCM parallel to the primary stress.  Tension Zone: small stable crack(s) all less than 2" long in redundant load path.  

3‐Serious 

Section loss is seriously affecting the load path, local failures are possible  (ex. Extensive perforations or loss through member, perforations through many members, buckle in compression zone) 

Compression zone: Any longer than 2” and unstable or working cracks.   Fracture Critical Member (FCM): any stable crack in the base metal of a FCM perpendicular to the primary stress.   Tension Zone: Stable cracks, one may be 2” or longer in redundant load path.  

4‐Crit ical 

2‐Critical 

Advanced deterioration (ex. Active crushing or buckling) lane should be closed or closely monitored.  Distortion in a load path of a redundant member 

Cracks have removed support or eliminated load path distribution.  Working or unstable cracks in the tension zone perpendicular to the primary stress. 

1‐Imminent Failure 

Major section loss, deterioration or cracking that is worse than above (ex. Beams are crushing, or buckling) and closed to traffic. Distortion in a load path of a compression zone of a non‐redundant member 

0‐Failed  Beyond corrective action 

Table 37 ‐ Condition Rating Material: Steel 

*Section loss is dependent on location, extent and severity. **Cracking: Minor versus advanced cracking depends on the probability of propagation, location & length and may be given to the judgment of the Team Leader taking into consideration brittle fracture.  For dormant cracks, consideration shall be given in improving the condition rating 

 

Page 24: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 130

Common “Advanced” Deficiencies  

Settlement  ‐  Exceeds  tolerable  limits  depending  on  component,  activity  and  if  it  is measurable  or 

unstable change 

Scour  ‐  Exceeds  tolerable  limits,  for  example  unprotected  sides  of  spread  footing,  loss  of  bearing 

capacity, undermining, 1/3 or more of the front row of piling exposed piling. 

Distortion ‐ Exceeds tolerable limits, for example distortion or buckling that is localized and warranting a 

structural review.  

Section Loss  

Flexure or Bending Members 

Steel Web –  

In  the  shear  zone:  Corrosion  hole  (in  any  interior  beam OR  fascia  beam  if  the  bridge  is 

horizontally  curved or  if  the  fascia  beam  is one of  2 or  3 beams  total).   Corrosion holes 

behind a web stiffener or behind the bearing are not considered “advanced” 

In  the  shear  zone: Deep  section  loss more  than 50% of web depth  for an area above  the 

bearing 8” high and 18 X the web thickness wide (in any interior beam OR fascia beam if the 

superstructure is non‐redundant or horizontally curved)  

  Steel Flange –  

Section loss of the flange cross section more than 1/4 of flange in the maximum negative or 

positive flexure zone (for “zone” longitudinal length use 1/3 of span length) 

Steel Axial Members 

Truss Members 

Corrosion holes OR section loss reducing any one cross section by more than 10% average  

Steel Bents (including bents with steel columns without reinforcing cages) 

Corrosion holes in 3 piles OR 

Missing steel sheath around ½ of one pile OR 

Overall thin metal in 3 consecutive piles  

Corrugated Metal Pipe  ‐Perforations or overall  thin metal which allows  for an easy puncture 

with chipping hammer throughout invert with roughly 20% of structure affected 

   

Page 25: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 131

 

Prestressed Concrete – Condition Rating Definitions 1‐4 Span 

9‐0 Sum  General Deficiencies   Longitudinal Joints  Strand Exposure in worst transverse plane of a  Non Composite Box Beam* 

1‐Good  9‐Ex  No notable deficiencies        

8‐VGood  Minor deficiencies   Isolated leaking  Up to 1% of strands 

7‐Good  Up to 1%, exposed strand in fascia or spalling along edge 

Leaking up to 10% of span with light efflorescence 

2‐ 10% with neighboring beam in similar condition or better. 

2‐Fair  6‐Satis factory 

Up to 5%, minor exposed strands, efflorescence, spalling  

Leaking at joints with no efflorescence 

11‐15% with neighboring beam in good condition or in similar condition 

5‐Fair  Up to 10%, no transverse cracks in bottom of beams 

Leaking at joints with light efflorescence and isolated rust stains 

16‐25% with neighboring beam in satisfactory condition or in similar condition 

3‐Poor  4‐Poor  More than 10%  Leaking at joints with heavy efflorescence and rust staining 

26‐40% with neighboring beam in fair condition or in similar condition.  Fascia beam(s) are saturated 

3‐Serious  Open flexure cracks, sagging or loss of camber 

Broken or missing transverse tendons  

41‐50% with neighboring beam in poor condition or in similar condition  

4‐Critical 

2‐Critical  3‐Serious. . . And Unless closely monitored it may be necessary to close the bridge or lane(s) until corrective action is taken 

1‐Imm F  2‐Critical. . . And Major deterioration is affecting stability.  Bridge or lane(s) shall be closed to traffic but corrective action may put bridge back into light service 

0‐Failed  . . . And Out of service ‐ beyond corrective action 

Table 38 ‐ Condition Rating Material: Prestressed Concrete 

*This seems to be the most common deficiency for PSBB Noncomposite bridges.  Beams carrying a 

sidewalk should not control the condition rating.  Beam ratings shall consider beams immediately 

adjacent. 

General Deficiencies – includes imperfection in the concrete (i.e. spalls, cracking, mottled area, 

efflorescence, honeycombing, water in beams, damaged concrete around railing connection) and 

general beam alignment (i.e. loss of upward camber, twists) 

Longitudinal Joints  –staining or wetted areas from runoff infiltration.   

Strand Exposure – discount all strands visible and those strands not visible located:  

1) Above a longitudinal cracks located in the bottom flange 

2) Above a delamination  

3) Above a spall with unsound or mottled concrete.  

4) Consideration should also be given to those strands neighboring and above a corroded stirrup. 

Only count the same strand exposed once per span.  Divide those strands that are exposed over the 

total number of strands existing per beam (Plans will need to be reviewed for determining the number 

Page 26: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 132

of strands, should no plans be available the inspector should use design data sheets from the era of the 

bridge located on the ODOT website for an approximation).   

Prestressed Box Beam (PSBB)     

    

       

  Non‐Composite               Composite  

 

Structural Cracks in Prestressed Concrete – shear cracks are at a 45 degree angle sloping down near 

supports.  Flexure cracks are transverse to the load path near high moment regions.  Crack comparator 

cards and crack monitoring gauges are useful in quantifying and tracking crack widths especially for 

prestressed concrete.  For structural cracks consider recording widths and locations in the comments 

and on the bridge.  Note the crack width descriptions below from the BIRM 2002 for prestressed 

concrete:          Hairline (HL)     < 0.004"  

          Narrow (N)     0.004 to 0.009"  

          Medium (M)     0.010 to 0.030"  

          Wide (W)     > 0.030 

 

   

Figure 71 ‐ Composite and Noncomposite PSBB

Page 27: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 133

TIMBER – Condition Rating Definitions  

Timber should be examined for decay especially when bearing on sources of moisture, or between 

layers of planking or laminate pieces.  Note loose connections and differential bending.  The majority of 

timber members exists on local agency structures decks.  Therefore the guidance primarily describes 

timber planks and deck components. 

 

Abrasion due to stones on the top surface of floors will abrade into the timber floor in the wheel path.  

This is where moisture tends to pond and promotes accelerated rot.  Where the timbers span the 

distance between abutments the floor rating must be the same as the Superstructure: beam/girder/slab 

rating. 

 

Noticeable deflection, under traffic, of the timber floor between stringers may be a strong indicator of 

deficiency. 

 

1‐4 Indiv. 

9‐0 Summary Description 

1‐Good 

9‐Excellent  No noticeable or noteworthy deficiencies which affect the condition of the deck.   

8‐Very Good  No crushing, rotting, or splitting. Tightly secured to floor system. Very few minor deficiencies.   

7‐Good  Minor checking or splitting with a few loose planks. 

2‐Fair 

6‐Satisfactory  Several planks are checked or split but sound. Some loose planks. Fire damage limited to surface scorching with no measurable section loss. Some wet areas noted. A few planks (under 5%) are in need of replacement. 

5‐Fair  Numerous planks checked or split. Majority of planks are loose. Fire damage limited to surface charring with minor, measurable section loss. Some planks (5 ‐ 10%) are in need of replacement. 

3‐Poor 

4‐Poor  Majority of the planks are checked or split. Fire damage with significant section loss which may reduce the load carrying capacity of the member. Over 10% of the planks are in need of replacement. 

3‐Serious  Local failures possible.  Severe signs of structural distress are visible. Major decay or fire damage is present which has substantially reduced the load carrying capacity of the deck.  

4‐Critical 

2‐Critical  Advanced deterioration with partial deck failure. May be necessary to close bridge until corrective action is taken. 

1‐Imminent Failure 

Bridge closed, corrective action will put it back in light service   

0‐Failed  Bridge closed, replacement necessary 

Table 39 ‐ Condition Rating Material: Timber   

Page 28: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 134

MASONRY – Condition Rating Definitions  

1‐4 Indiv.  9‐0 Summary  General  Displacement 

1‐Good  

9‐Excellent No signs of distress, Minor spalling of stone surface.  

8‐Very Good  Scaling on of stone surface less than 1/2 inch. 

7‐Good  Diagonal or vertical shear crack in isolated stones. Fracture of stone surface less than 2 inches. 

2‐Fair 

6‐Satisfactory  Diagonal or vertical shear crack through several courses of stone.  Removable stone face for less than 1/2 of bridge width less than ¼ stone depth. 

Minor  

5‐Fair  Diagonal or vertical shear crack through several courses of stone.  Removable stone less than ¼ of stone depth for more than 1/2 of bridge 

Displacement may be bulge or leaning stones. Total displacement is less than 1/4 of stone depth. 

3‐Poor 

4‐Poor Settlement causing diagonal or vertical shear crack through several courses of stone with displacement.  Large fractures or erosion of stone surfaces up to 1/3 stone depth on several adjacent stones.   

Total displacement is less than 1/3 of stone depth. 

3‐Serious  Large unsound areas.  Misalignment of mortar joints. Large fractures or erosion of stone surfaces greater than 1/3 stone depth.  

Several stones are displaced or missing. 

4‐Critical 

2‐Critical  Numerous missing or displaced stones. Displacements greater than 1/3 of stone depth.  Keying (vertical separation between compression stones), or measurable displacement between adjacent stones, exists on at least 3 stones in one longitudinal load‐line. 

1‐Imminent Failure 

Partially collapsed abutment 

0‐Failed  Total failure of abutment 

Table 40 ‐ Condition Rating Material: Masonry 

      

Page 29: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 135

Mechanically Stabilized Earth (MSE) – Condition Rating Definitions    

1‐4 Indiv. 

9‐0 Summary 

Panels  Joints  Erosion  Bowed  

1‐Good 

9‐Excellent  No Cracking or Spalls 

Uniform joint spacing       

8‐Very Good 

No Cracking or Spalls, cracks may exist in coping 

minor variation in joint spacing 

   None 

7‐Good  Hairline cracking or spalls 

Moderate variation in joint spacing, minor sand in joints 

   Minor 

2‐Fair 

6‐Satisfactory 

Cracks <1/4" on a few panels 

Moderate sand in joints but no exposed fabric nor sand piles below joints 

Minor erosion along panels, max 1’ deep 

Moderate 

5‐Fair  Cracks <1/4" many panels, global, minor spalling 

Exposed fabric at a few isolated joints, small sand pile, moisture around a few joint(s) 

Moderate erosion along panels, max 2' deep 

Moderate change since as built 

3‐Poor 

4‐Poor  Cracks >1/4", global, moderate spalling 

Exposed fabric at many joints, sand pile(s) below at least one joint, trees growing between joints.  Moisture through joint(s) 

Erosion >2' deep along panels 

Major change since as built 

3‐Serious 

Spalling exposes backfill 

Exposed fabric and active sand piles below many joints.  Active moisture through joint(s) 

Erosion exposing the top of the leveling pad and pad is not on rock, exposed straps or mesh 

Major, changing, global 

4‐Critical 

2‐Critical Any worse than above 

Major leaking of sand from joints 

erosion undermining leveling pads 

Major, changing, systemic and global 

1‐Imm Failure     0‐Failed 

Table 41 ‐ Condition Rating Material: MSE   

Page 30: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 136

Coding  Condition  ratings  with dedicated Charts 

Approach Embankment – “ded” CONDITION RATING 

Item ‐  4. Embankment  

  Description 

1‐Good Moderate rutting from drainage. Minor bare soil exposed. 

2‐Fair 

Erosion caused by drainage or channel;  Erosion to embankment impacting guardrail performance or encroaching on shoulder. Evidence of minor or stable foundation settlement. 

3‐Poor 

Major erosion caused by drainage or channel;  Erosion to embankment impacting guardrail performance or encroaching on shoulder. Evidence of foundation settlement. 

4‐Critical Several guardrail posts are hanging due to major erosion. A lane of traffic is closed, tension cracks in asphalt due to embankment movement. 

Table 42 ‐ Condition Rating: Approach Embankment 

Deck Drainage – “ded”  CONDITION RATING 

Item ‐  12. Drainage   

Worst Span   Clogging  Ponding 

1‐Good  No clogging  No ponding 

2‐Fair  Up to a 25% of scuppers/grates continually clog. Minor ponding may exist in the shoulder or outside of the traveling lanes. 

3‐Poor  More than 25% of the scuppers/grating continually clog. Ponding is beginning to cross into the traveling lane.   

4‐Critical Local flooding, hydroplaning or icing due to improper drainage system.  Unless closely monitored it may be necessary to close the lane(s) until corrective action is taken.   

Table 43 ‐ Condition Rating: Deck Drainage 

 

 

 

 

   

Page 31: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 137

Table 44 ‐ Condition Rating: Deck Expansion Joints 

 

 

 

 

Deck Expansion Joint –  “ded” CONDITION RATING Item 13. Expansion Joint 

1‐4   9‐0 Summary 

Leaking Expansion and Contraction 

Opening Armor and Anchorage 

1‐Good 

9‐Excellent  No leakage     

8‐Very Good Minor isolated leakage, debris may be present    

Minor surface delaminations in header  

7‐Good Localized leakage along the joint may be present, debris  

Measurements exhibit normal expansion and contraction within ¼” on any one joint 

A few delaminations or spalls or cracking in the header 

2‐Fair 

6‐Satisfactory 

Leakage in several places.   Gland is partially separated from the armor or has minor tears.  Significant debris  

Minor abnormalities in the longitudinal measurements may exist (1/4”‐1/2” difference on any one joint) 

Spalls or cracking in the deck and/or header may be present adjacent to the joint.  Gouges in armor. 

5‐Fair 

Any Joint paved over, Leakage along the joint in many locations.  Gland may be partially pulled out of the armor.   

Abnormalities in measurements.  Bent or misaligned fingers may be observed.  Minor vertical offset.  Closed in warmer temperatures. 

'Clanking' under heavy truck traffic only with small spalls or cracking.  Gouges in armor 

3‐Poor 

4‐Poor 

Gland has been pulled completely out of the armor.   

Significant abnormalities in the measurements.  Missing or broken fingers.  More than ½” difference in any one joint.  Up to 1” vertical misalignment Closed in coldest temperatures. 

Clanking in one lane under truck traffic.  Major spalls or significant cracking.   

3‐Serious Major abnormalities in the measurements, up to 2” misalignment 

Visible movement and clanking under all traffic loads in one lane, major spalls .   

4‐Critical 

2‐Critical  Major abnormalities in the longitudinal, vertical and/or horizontal measurements, greater than 2” misalignment.  Tight on one side and open in the other.  Visible movement and clanking under all traffic loads in all lanes, major spalls. Anchorage separation on multiple beams. 

1‐ImmFailure 

0‐Failed 

Page 32: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 138

Superstructure Alignment –  “ded” CONDITION RATING 

Item ‐  14.  Alignment (of members) 

Worst Span: 

Condition Rating 

Primary Members  Dimensions 

1‐Good Minor misalignment or distortion due to construction 

 

2‐Fair Out of plane distortion of tension zones/members 

 

3‐Poor 

Vertical deflection (sag) due to deteriorations or excessive dead loads  Major misalignment or distortion due to impact  

Highly skewed bridges with Beam webs having less than 1/8” horizontal bow for every 1 vertical foot  

4‐Critical 

Global racking, large distortion, vertical sag of the span due to distortion   Any out of plane distortion of compression zones/ members.  

More than 2‐inch sag for a 100’ span   Highly skewed bridges: More than 1/4” horizontal movement for every 1‐foot vertical on a steel beam web 

Table 45 ‐ Condition Rating: Superstructure Alignment 

 

 

 

 

 

 

 

 

 

 

 

Page 33: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 139

Superstructure Truss Gusset Plates –  “ded” CONDITION RATING   

Item ‐  23. Truss Gusset Plates  

Condition  Bowing Section Loss (SL), Connectivity and General 

Deterioration 

1‐Good  9‐Exclnt  Like new condition  Isolated SL up to 1/10 depth of plate thickness 

(ex. 1/16” loss for a 5/8” plate) not in primary line 

8‐Vr Good  No problems noted 

7‐Good 

2‐Fair 

6‐Satis factory 

Bowing up to half the thickness of the plate due to inadequate fill plates, misalignment of truss members or pack rust (not free‐edge bowing)  

Minor deterioration  Widespread SL up to 1/10 depth of plate thickness (ex. 1/16” for a 5/8” plate) along the primary load path,  Localized pitting up to 1/10 depth of plate thickness up to 5% of plate area 

5‐Fair  Bowing due to inadequate fill plates, misalignment of truss members or pack rust (no free edge bowing between compression members) 

Minor section loss  Widespread SL up to 1/4 depth of plate thickness (ex. 1/8” for a 1/2” plate) along the primary load path,  Localized pitting up to 1/4 depth of plate thickness up to 25% of plate area, may have a corrosion hole up to ½” diameter NOT in the primary load path 

3‐Poor 

4‐Poor  Free edge bowing or distortion behind a compression member 

Advanced section loss  Widespread SL up to 1/3 depth of plate thickness (ex. 1/4” for a 3/4” plate) along the primary load path,  Localized corrosion hole may exist up to ½” in length or diameter in the primary load path 

3‐Serious  Any changed free edge bowing or distortion behind a compression member   

Deficiencies that seriously affect the structural integrity of the bridge, large corrosion hole or pinholes interconnected with advanced section loss in the primary load path 

4‐Critical 

2‐Critical  Unless closely monitored it may be necessary to close the bridge.  Immediate action is required, Any plastic deformation in primary load path 

Deficiencies that seriously affect the structural integrity of the bridge.  Stress cracks in the gusset plate in areas of advanced section loss, broken or missing bolt or rivets since as‐built condition, fatigue cracks in gusset welded connection or gusset base metal 

1‐Imm F  Bridge closed to vehicular traffic  

0‐Failed  Out of service, beyond corrective action Table 46 ‐ Condition Rating: Superstructure Gusset Plates 

Special attention shall be placed on gusset plates with corrosion holes or widespread loss of section 1/3 the plate thickness in the primary load path & Special attention shall be placed on gusset plates with bowing at the free edge. 

Special attention shall be placed on gusset plates with loose, cracked or missing connections.  

The procedures for measuring bowing in gusset plates shall be clearly documented and quantitatively repeatable at future inspections by different inspectors in order to monitor bowing change within a tolerance of 1/16”.    

Page 34: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 140

Superstructure Bearing Devices –  “ded” CONDITION RATING 

Item ‐  26.  Bearing Devices  

Type ‐   General 

1‐4   9‐0 Summary  Function 

1‐Good  

9‐Excellent 

Minor or aesthetic deficiencies. Bearings are free to move, slide, roll or rock back and forth longitudinally and rotate as designed.  Bearings have not moved or shifted vertically or transversely from its intended position.  Elastomeric pads: the horizontal bulge is less than 15% of the  height 

8‐Very Good 

7‐Good 

2‐Fair 

6‐Satisfactory Section loss, pack rust, bearings may have shifted vertically or horizontally but still within the design tolerance.  Keeper bars or anchor bars are bent or showing signs of bending or loose when tapped with hammer.    Elastomeric pads: the horizontal bulge is less than 25% of the  height 

5‐Fair 

3‐Poor 

4‐Poor Outside of design tolerance. Any two or more adjacent bearings are frozen, floating, excessively tilted or deficient that is directly impacting other elements (i.e. beam, deck, cross‐frames).  Advanced section loss, advanced pack rust, bearings are frozen and no longer free to move or tilted in excessively wrong directions for the temperature or shifted to expose the underside of the masonry plate**.  Keeper bars or anchors are broken from transverse movement.  Elastomeric pads: the horizontal bulge is MORE than 25% of the  height 

3‐Serious 

4‐Critical 

2‐Critical  Multiple adjacent are rocked beyond recall* or walked out of position 

Table 47 ‐ Condition Rating: Superstructure Bearing Devices 

*Beyond Recall – Rocker(s) measured with a plumb‐line whose horizontal distance is greater than 1/4 of 

H (Vertical height difference between the bottom face of the sole plate (top plate) and the top face of 

the masonry plate or bottom plate).  Often the rocker will pinch and slide rather than rock. 

 

**Masonry Plate Undermining:  

The bearings shall be downgraded for any undermining of a masonry plate when the Superstructure has 

shifted or moved the bearing.  The substructure unit will be downgraded when the root cause is within 

the substructure, i.e. when settlement, deep spalling, crushing or delaminations occur.   

Page 35: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 141

Superstructure Protective Coating System –  “ded” CONDITION RATING 

Item ‐  30.  Protective Coating System (PCS) 

1‐4 Rating  Degradation Problems Workmanship Problems 

Candidate for Recoating  

% Surface Area (SA) Failed  

Issues Surface Corrosion 

1‐Good  0 to 5%   Light 

Up to 10% failed SA, Multiple minor issues, Up to 10% finish 

coat failed 

 

2‐Fair  6 to 15% 

Not effective at Beam ends under joints 

Prevalent  Up to 20% 

Candidate for zone painting (fascias and under joints) 

3‐Poor  16‐30%  Not effective  

Prevalent Large areas of old Paint Painted over  

Candidate for total recoating 

4‐Failed  More than 30% 

Table 48 ‐ Condition Rating: Superstructure Protective Coating System 

Page 36: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 142

Superstructure Pins/Hangers/Hinges –  “ded” CONDITION RATING 

Item ‐  31.  Pins/Hangers/Hinges 

Type ‐   Steel 

1‐4   9‐0 Summary 

Functional Movement Corrosion & Cleanliness 

Bearing Integrity/Hinge 

1‐Good 

9‐Excelent  Aesthetic deficiencies only 

8‐V Good 

7‐Good  All in proper contact 

2‐Fair 

6‐Satisfact. 

Movement not restricted; shallow wear grooves (up to 1/8”) 

Minor pack rust or debris, some dry spots in lubricated parts. 

One pin/hanger/hinge slightly misaligned with others or missing not more than one anchor bolt per hanger line 

5‐Fair 

Movement restricted only at extreme operating limits.  Minor misalignment. At least 1/8” deep wear grooves 

Moderate pack rust or accumulated debris.  Moderate abrasion up to 1/8” deep with no lubricant on parts.   

One not in proper contact or somewhat misaligned with others.  Missing not more than one anchor bolt per bearing.   

3‐Poor 

4‐Poor 

Movement restricted within normal operating limits; seized.  Up to 1” misalignment 

Major pack rust or accumulated debris limiting normal operation.  Lack of normal operation.  Abrasion >1/8” deep of hanger sides with no lubrication. 

Multiple not in proper contact or multiple adjacent pin/hanger/hinges misaligned on one unit or multiple not aligned  

3‐Serious Seized due to corrosion or debris, preventing movement.  Up to 2” misalignment 

Pin/hanger/hinges leaning beyond recall or jammed significantly  

4‐Critical 

2‐Critical 

ANY SIZE fatigue crack in primary load path base metal in the hanger, hinge, pin or vicinity (within 4‐feet of pin).  Unless closely monitored it may be necessary to close bridge due to advanced deterioration.  Crushing.  More than 2” misalignment.   

1‐Imm Failure 

0‐Failed Table 49 ‐ Condition Rating: Superstructure Pins/Hangers/Hinges 

   

Page 37: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 143

Superstructure Fatigue –  “ded” CONDITION RATING Item ‐  32.  Fatigue  Type –   Steel  

Table 50 ‐ Condition Rating: Superstructure Fatigue 

Cracks should be carefully measured and their location and length documented. 

Typically the first time a fatigue crack is identified it is CS 3 in the Compression zone and CS4 in 

the Tension zone. 

Truss: the quantity is the sum of all of the lengths of each truss panel measured longitudinal to 

the travel way and the worst part in the vertical one‐foot controls the rating i.e. include all 

truss members by rating each vertical linear foot of truss as if it were an open‐webbed beam or 

girder 

1‐4   9‐0 Summary  Cracks 

1‐Good 

9‐Excellent    

8‐V Good    

7‐Good  Any arrested or retrofitted crack 

2‐Fair 6‐Satisfactory  Compression zone: Minor cracking up to 2” long, stable cracks in 

base metal 5‐Fair 

3‐Poor 

4‐Poor 

Compression zone: Any longer than 2”, stable cracks in base metal.   Fracture Critical Member (FCM): any stable crack in the base metal of a FCM parallel to the primary stress.  Tension Zone: small stable crack(s) all less than 2" long in redundant load path.  

3‐Serious 

Compression zone: Any longer than 2” and unstable or working cracks.   Fracture Critical Member (FCM): any stable crack in the base metal of a FCM perpendicular to the primary stress.   Tension Zone: Stable cracks, one may be 2” or longer in redundant load path.  

4‐Critical 

2‐Critical 

Any Crack in the base metal at or adjacent to a pin and hanger or hinge assembly shall be “Critical” or less.   Cracks have removed support or eliminated load path distribution.  Working or unstable cracks in the tension zone perpendicular to the primary stress. 

1‐Imminent Failure 

Major section loss, deterioration or cracking that is worse than above (ex. Beams are crushing) and closed to traffic. Distortion in a load path of a compression zone of a non‐redundant member 

0‐Failed Beyond corrective action   

Page 38: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 144

Substructure Scour, Spread or Unknown foundations –  “ded” CONDITION RATING 

Item ‐  42.  Scour  

Type –   Spread Footing on Soil OR Unknown Foundations 

1‐4  9‐0 Description* 

Exposed Spread or Unknown Foundation* 

1‐Good 

9‐Excellent  No Problems noted.   

8‐Very Good  Minor scour holes developing, scour protection placed.   

 

7‐Good  Some minor problems.  Minor scour holes exist; probing indicated soft material in scour hole.   

top of footing exposed 

2‐Fair 

6‐Satisfactory 

Damage to scour countermeasures, probing indicates soft material in scour hole. 

Sides of footings exposed less than 6 inches. 

5‐Fair Minor scour, damage to scour countermeasures, probing indicates soft material in scour hole.   

Unprotected footings along the vertical sides are exposed less than 12‐inches high, corner of footing may have minor undermining. 

3‐Poor 

4‐Poor 

Advanced scour.   

Unprotected vertical side of footing exposed, full height, less than 1/3 the horizontal length of the footing. 

3‐Serious  Scour has seriously affected the primary structural components Local failures are possible.   

Undermining exposing the underside less than 1/3 the horizontal length of the footing. 

4‐Critical 

  2‐Critical 

Scour may have removed substructure support.   Local failures are possible.  Any substructure unit with more than 20% of bearing capacity removed.   

Underside of footing exposed more than 1/3 the horizontal length of the footing. 

1‐Imminent Failure 

Obvious vertical or horizontal movement due to scour that is affecting the structure stability.  Bridge is closed to traffic but corrective action may put bridge back in to light service. 

 

0‐Failed  Out of service ‐ beyond corrective action.   Table 51 ‐ Condition Rating: Substructure Shallow Foundations Scour 

*Condition shall be adjusted based on the rate of change since the as‐built condition.  This item may be 

rated higher, for example, if the as‐built condition had the top face of the spread footing exposed and it 

has not changed.  Also, due to the dynamic nature of the waterway the ratings may be coded lower if a 

dramatic change occurred since the previous inspection.  Unknown foundations on soil shall be rated 

the same as a spread footing on soil.  Those spread footings on rock shall be rated as deep foundations.  

Page 39: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 145

Substructure Scour, deep foundations –  “ded” CONDITION RATING 

Item ‐  42.  Scour  

Type –   Deep Foundations: Piles, Drilled Shafts, including Spread Footing on Rock 

1‐4  9‐0 Total Bridge  Description*  Exposed Deep Foundation* 

1‐Good 

9‐Excellent  No Problems noted.   

8‐Very Good  Minor scour holes developing, scour protection placed.   

 

7‐Good  Some minor problems.  Minor scour holes exist; probing indicated soft material in scour hole.   

top of footing and first 6‐inches exposed  

2‐Fair 

6‐Satisfactory  Damage to scour countermeasures, probing indicates soft material in scour hole. 

Full height side of footing exposed  

5‐Fair  Minor scour, damage to scour countermeasures, probing indicates soft material in scour hole.   

One or two pilings are visible less than 10% of piling height** 

3‐Poor 

4‐Poor Advanced scour.   

1/3 of the front row of piling exposed less 10% of piling height** 

3‐Serious 

Scour has seriously affected the primary structural components Local failures are possible.   

Any one piling exposed above or below water more than 3‐feet high, more than 1/3 of the front row of piling exposed less than 10% of piling height** 

4‐Critical 

2‐Critical Scour may have removed substructure support.   Local failures are possible  

Any substructure unit with more than 20% of bearing capacity removed.   

1‐Imminent Failure 

Obvious vertical or horizontal movement due to scour that is affecting the structure stability.  Bridge is closed to traffic but corrective action may put bridge back in to light service. 

0‐Failed  Out of service ‐ beyond corrective action. Table 52 ‐ Condition Rating: Substructure Deep Foundations Scour 

*Condition shall be adjusted based on the rate of change since the as‐built condition.  This item may be 

rated higher, for example, if the as‐built condition had the top face of the spread footing exposed and it 

has not changed.  Also, due to the dynamic nature of the waterway the ratings may be coded lower if a 

dramatic change occurred since the previous inspection.  Unknown foundations on soil shall be rated 

the same as a spread footing on soil.  Those spread footings on rock shall be rated as deep foundations.  

**Use 10‐foot deep piling when the foundation plans do not exist.   

As a general guideline a bridge may warrant a scour analysis if any of the following occur: o Undermining for a spread footing  o Water flowing beneath a culvert 

Monitoring scour related problems should include periodic stream profile measurements. 

Page 40: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 146

Substructure Slope Protection ‐  “ded” CONDITION RATING 

Item ‐  43.  Slope Protection  

Type –   Generic / Sloped 

1‐4  Erosion  Adequacy 

1‐Good Minor Erosion not affecting substructure unit(s), beginning to slump. 

Minor deficiencies, minor repairs recommended. 

2‐Fair Small erosion channels/failure, up to 6" deep, erosion ruts exist.  

Moderate deficiencies, sloughing or sliding of protection however still functioning as designed. 

3‐Poor Significant erosion, up to 2' deep, erosion ruts.   

Moderate and active slope protection failure.  Slight Undermining, No longer stabilizing the slope, collapsing rip rap.    Sand pile below at least one MSE wall joint 

4‐Critical Major erosion, greater than 2' deep/wide ruts that are directly affecting substructure units, example 5’ of one piling is exposed. 

Serious undermining, evidence of obvious global movement, no longer stabilizing the slope. 

Table 53 ‐ Condition Rating: Substructure Slope Protection 

Page 41: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 147

Culvert Alignment –  “ded” CONDITION RATING 

Item ‐  45.  Alignment 

1‐4   9‐0   Description 

1‐Good  9‐Excellent  Straight line between sections. 

8‐Very Good Minor settlement or misalignment.  

7‐Good  Minor misalignment at joints; off sets less than 1/2 inch no fill settlement. Minor settlement or misalignment, ponding less than 3 inches.   

2‐Fair  6‐Satisfactory 

Fair, minor misalignment and settlement at isolated locations. Moderate settlement or misalignment, ponding between 3 and 5 inches deep. 

5‐Fair  Minor misalignment or settlement throughout culvert. Ponding (depths less than 5 inches) of water due to sagging or misalignment of pipe sections, end sections dislocated and about to drop off. Four or more sections with offset less than 3 inches. 

3‐Poor  4‐Poor  Considerable settlement and misalignment of pipe. Significant ponding (depths less than 6 inches) of water due to sagging or misalignment of pipes sections, end sections dislocated about to drop off. Four or more sections with offset less than 4 inches. Rotation of foundation. 

3‐Serious  Any condition described in “Poor” but is excessive in scope.  Severe movement or differential settlement of the segments or loss of fill.  Metal culverts have extreme distortion and deflection in one section.  Significant ponding (depths greater than 6 inches) of water due to sagging or misalignment of pipes sections, end‐section drop‐off has occurred.  Significant ponding of water due to sagging or misaligned masonry units; end section drop off has occurred.  Four or more sections with off sets greater than 4 inches. 

4‐Critical  2‐Critical  Culvert not functioning due to alignment problems throughout.  Metal culverts have extreme distortion and deflection throughout. 

1‐ImmFailure 

Culvert partially collapsed or collapse is imminent. 

0‐Failed  Culvert collapsed. Table 54 ‐ Condition Rating: Culvert Alignment 

Page 42: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 148

Culvert Shape –  “ded” CONDITION RATING 

Item ‐  46.  Shape 

Type –   Flexible Culverts Only 

1‐4  9‐0 Summary 

Description % Change of Cross Section* under influence of 

traffic 

1‐Good 9‐Excellent 

New Condition.  May exhibit minor damage along edge of inlet or outlet due to construction 

8‐Very Good 

Smooth curvature in barrel Span dimension within 1 percent of design. 

7‐Good Top half of pipe smooth but minor flattening of bottom 

Span dimension within 3 percent of design.  Very minor distortion 

2‐Fair 

6‐Satisfactory 

Smooth curvature in top half, bottom flat 

Span dimension within 5 percent of design.  Very minor distortion  

5‐Fair 

Generally fair, significant distortion in top in one location; bottom has slight reverse curvature in one location but generally fair  

Span dimension up to 7 percent greater than design. Non‐symmetric shape. 

3‐Poor 

4‐Poor Marginal significant distortion throughout length of pipe, lower third may be kinked 

Span dimension more than 7 percent greater than design, noticeable dip in guardrail over pipe. 

3‐Serious 

Poor, extreme deflection at isolated locations, flattening at top of arch or crown; bottom has reverse curvature throughout;  

Extreme non‐symmetric shape. 

4‐Critical 

2‐Critical  Critical, extreme distortion and deflection throughout pipe  

1‐Imm Fail  Structure partially collapsed with crown in reverse curve. 

0‐Failed  Structure collapsed. Table 55 ‐ Condition Rating: Culvert Shape 

*This may include any straight measurement through the center of the cross section, i.e. perpendicular 

to the longitudinal axis.  Refer to Appendix. for a chart for recording the shape changes/flattening in 

corrugated metal culverts. 

   

Page 43: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 149

Culvert Seams –  “ded” CONDITION RATING 

Item ‐  47.  Seams 

Type –   Corrugated Metal / Multi‐Plate 

 

1‐4  9‐0  Seam   Bolts  Backfill 

1‐Good 

9‐Excellent  Minor amounts of efflorescence or staining. 

8‐Very Good Light surface rust on bolts due to loss of galvanizing, efflorescence staining, tight with no openings along seams. 

7‐Good 

Metal has cracking on each side of the bolt hole less than 3 instances in a seam section.  Minor seam openings less than 1/8 inch.   

More than 2 consecutive missing bolts in a row. Rust scale around bolts. 

Potential for backfill infiltration.

2‐Fair 

6‐Satisfactory 

Metal has cracking on each side of the bolt hole less than 6, more than 3 instances in a seam section.  Minor seam openings less than 1/8 inch.  

More than 3 consecutive missing bolts in a row. Rust scale around bolts. 

Evidence of minor backfill infiltration through seams.  

5‐Fair Moderate cracking at bolt holes along a seam in one section.    

More than 6 consecutive missing bolts in a row or 20% along the seam. 

Backfill being lost through seam causing slight deflection. 

3‐Poor 

4‐Poor Major cracking of seam near crown.   Partial cocked and cusped seams.   

Advanced section loss to bolt heads along seams.  Missing several bolts in a row 

Infiltration of backfill causing major deflection. 

3‐Serious 

Longitudinal cocked and cusped seams and/or metal has 3 inch crack on each side of the bolt hole run total length of culvert.   

Numerous missing or tipping bolts. 

Infiltration of backfill causing major deflection. 

4‐Critical 

2‐Critical Seam cracked from bolt to bolt. 

Missing or tipping bolts. 

Significant amounts of backfill infiltration.

1‐Imminent Failure 

Pipe partially collapsed or collapse is imminent. 

0‐Failed  Total failure of pipe. Table 56 ‐ Condition Rating: Culvert Metal Seams 

    

Page 44: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 150

Culvert Seams –  “ded” CONDITION RATING 

Item ‐  47.  Seams 

Type –   Concrete  

1‐4  9‐0 Summary 

General  Alignment  Backfill 

1‐Good  9‐Excellent  Straight line between sections. 

8‐Very Good No settlement or misalignment; Tight with no defects apparent. 

7‐Good  Minor distress to pipe material adjacent to joint.  Shallow mortar deterioration at isolated locations. 

Minor misalignment at joints; off sets less than 1/2 inch. 

Possible minor infiltration of fills no settlement. 

2‐Fair 

6‐Satisfactory 

Extensive areas of shallow deterioration; missing mortar at isolated locations; possible infiltration or exfiltration; minor cracking. 

Dislocated end section.  

Minor backfill infiltration due to slight opening at joints; minor cracking or spalling at joints allowing exfiltration. 

5‐Fair  Significant cracking, spalling, buckling of pipe material, loose or missing mortar at isolated locations.  

Joint offset less than 3 inches. End sections dislocated about to drop off mortar generally deteriorated. 

Joint open and allowing backfill to infiltrate, infiltration staining apparent. 

3‐Poor 

4‐Poor  Voids seen in fill through offset joints. End sections dropped off at inlet. Mortar severely deteriorated, significant loss of mortar.  

Differential movement and separation of joints. Joint offset less than 4 inches.  

Significant infiltration or exfiltration between masonry units. 

3‐Serious Large voids seen in fill through offset joints.  Extensive areas of missing mortar. 

Significant openings, dislocated joints in several locations exposing fill material with joint offsets greater than 4 inches.  

Infiltration or exfiltration causing misalignment of pipe and settlement or depressions in roadway. 

4‐Critical  

2‐Critical  Culvert not functioning due to alignment problems throughout. Large voids seen in fill through offset joints. 

1‐Imminent Failure 

Pipe partially collapsed or collapse is imminent. 

Table 57 ‐ Condition Rating: Culvert Concrete Seams 

Page 45: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 151

Culvert Scour –  “ded” CONDITION RATING 

Item ‐           49.  Scour  

Type –          Culvert 

1‐4  9‐0  General*  Conduit‐Type Open Bottom‐Type (no floor/invert) 

1‐Good 

9‐Excellent 

No Problems noted.    

8‐Very Good 

Minor scour holes developing, scour protection placed.   

  

7‐Good  Some minor problems.  Minor scour holes exist; probing indicated soft material in scour hole.   

Scour holes at inlet or outlet but are not affecting structure. 

top of footing exposed 

2‐Fair 

6‐Satisfactory 

Damage to scour countermeasures, probing indicates soft material in scour hole. 

Minor scour holes developing at inlet or outlet.  

Sides of footing exposed less than 6 inches. 

5‐Fair Minor scour, damage to scour countermeasures, probing indicates soft material in scour hole.   

Scour holes at inlet or outlet.   

Unprotected footing along the vertical sides are exposed less than 12‐inches high, corner of footing may have minor undermining. 

3‐Poor 

4‐Poor 

Advanced scour.   

Significant scour holes developing at inlet or outlet. Major stream erosion behind headwall that threatens to undermine culvert. 

Unprotected vertical side of footing exposed, full height, less than 1/3 the horizontal length of the footing. 

3‐Serious  Scour has seriously affected the primary structural components Local failures are possible.   

Undermined cutoff walls or headwalls.  

Undermining exposing the underside less than 1/3 the horizontal length of the footing. 

4‐Critical 

2‐Critical Scour may have removed substructure support.   Local failures are possible.   

Streambed degradation causing severe settlement. 

Underside of footing exposed more than 1/3 the horizontal length of the footing. Any substructure unit with more than 20% of bearing capacity removed.   

1‐Imminent Failure 

Obvious vertical or horizontal movement due to scour that is affecting the structure stability.  Bridge is closed to traffic but corrective action may put bridge back in to light service. 

0‐Failed  Out of service ‐ beyond corrective action. Table 58 ‐ Condition Rating: Culvert Scour 

   

Page 46: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 152

Channel Alignment –  “ded” CONDITION RATING 

Item ‐  51.  Alignment 

Type –   All 

1‐4  9‐0  Channel Flow 

1‐Good 

9‐Excellent  Channel flow is causing no adverse conditions to channel protection bridge.   

8‐Very Good  Channel has straight alignment for more than 100 feet upstream. Flow hits protective materials placed to protect structure. 

7‐Good  Silt and gravel buildup restricts half of the channel; Tree or bush growing in the channel. 

2‐Fair  6‐Satisfactory  Minor streambed movement evident.  Not desirable: Flows through 1 out of 2 pipes; Flows along one abut.  Doesn’t flow under center of the structure; minor curve (20o‐40o angle change from as‐built); Deposits causing channel to split into 2 or more small channels.  

5‐Fair  Flow hits outside wingwall/endwall into unprotected embankment. Stream has meandered or has deposited sediment diverting flow causing erosion to embankment (Flow angle between 40o‐50o change from as‐built) Trees and brush restrict the channel.   

3‐Poor 

4‐Poor  Flows into or along wall to expose footing. Stream has meandered or has deposited sediment diverting flow causing erosion to embankment (Flow angle between 50o‐70o change from as‐built) Flow enters pipe by other means than designed opening. Beginning to undercut substructure. 

3‐Serious  Stream bed aggradation, degradation or lateral movement has changed the channel to now threaten the bridge and/or approach roadway.  80o‐90o (change from as‐built) turns at the bridge causing erosion behind wingwall. Loss of embankment material. Erosion to embankment encroaching on roadway.  

4‐Critical 

2‐Critical  Flow is piping around culvert. Erosion to embankment impacting roadway. The waterway has changed to the extent the bridge is near a state of collapse.  

1‐Imminent Failure 

No flow enters culvert. All of the flow pipes around culvert barrel. Bridge closed because of channel failure.   

0‐Failed  Total failure of pipe. Table 59 ‐ Condition Rating: Channel Alignment 

Page 47: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 153

Channel Protection –  “ded” CONDITION RATING 

Item ‐  52.  Protection 

1‐4  9‐0  Channel Protection 

1‐Good 

9‐Excellent  Embankment protection is not required or is in a stable condition. 

8‐Very Good  Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition.  No noteworthy deficiencies, which affect the condition of the channel protection 100 feet upstream. 

7‐Good  Bank protection is in need of minor repairs.  River control devices and embankment protection have a little minor damage.   

2‐Fair  6‐Satisfactory Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. Riprap starting to wash away.  Minor erosion. Cracked concrete channel protection at inlet of a culvert. 

5‐Fair  Bank protection is being eroded.  River control devices and/or embankment have major damage. Broken up concrete channel protection.  

3‐Poor 

4‐Poor  Bank and embankment protection is severely undermined.  River control devices have severe damage; stone is completely washed away; Major erosion; Failed concrete channel protection.  

3‐Serious  Bank protection has failed and no threatens the structure.  River control devices have been destroyed. 

4‐Critical 

2‐Critical  The channel has changed to the extent the bridge is near a state of collapse. 

1‐Imminent Failure 

Bridge closed because of channel failure. Corrective action may put back in light service. 

0‐Failed  Bridge closed because of channel failure. Replacement necessary. 

Table 60 ‐ Condition Rating: Channel Protection 

Page 48: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 154

Channel Hydraulic Opening –  “ded” CONDITION RATING 

Item ‐  53.  Hydraulic Opening 

Type –   All 

 

1‐4  9‐0   % Debris Buildup/Blockage* Blockage/Overtopping  Scour Critical 

Bridge Non‐Scour 

Critical Bridge

1‐Good 

9‐Excellent 

0  Up to 5% 

No blockage or as designed condition. 

8‐Very Good  Minor amounts of sediment build‐up with no appreciable loss of opening. 

7‐Good  Banks and/or channel have minor amounts of drift. 

2‐Fair  6‐Satisfactory 

0  Up to 10% Debris is restricting the channel slightly.  Fence placed at inlet or outlet;  

5‐Fair  Up to 5%,  non that may cause scour 

Up to 20% Trees and brush restrict the channel; Fence placed at inlet or outlet.  Debris in cross frames from more than 10 years. 

3‐Poor 

4‐Poor 5‐10%,  

none that may cause scour 

Up to 30% 

Large deposits of debris are in the waterway.  Occasional (ex. every 3‐10 years) overtopping of roadway. Minor inconvenience to traffic, passable in within a couple hours.  Continual debris in crossframes, every 3‐10 years 

3‐Serious ANY that MAY cause scour 

ANY that IS causing scour

Overtopping of roadway (ex. every 3‐10 years with long term traffic delays). 

4‐Critical 

2‐Critical  The channel has changed to the extent the bridge is near a state of collapse. 

1‐Imminent Failure 

Bridge closed because of channel failure. Corrective action may put back in light service. 

0‐Failed  Bridge closed because of channel failure. Replacement necessary. 

*% blockage area below the ordinary high water elevation of any span OR of the span length  Table 61 ‐ Condition Rating: Channel Hydraulic Opening 

Page 49: ODOT Manual of Bridge Inspection 2014 v8 Inspection operations... · available redundancy through the entire bridge. ... Page 110 3. Pier number 1 will be the first pier looking upstation

Manual of Bridge Inspection 2014 

Page 155

Channel Navigation Lights –  “ded” CONDITION RATING 

Item ‐  54.  Navigation Lights 

  Lighting 

1‐Good  All lights operating, no repairs necessary to system.  

2‐Fair  All lights operating, however, mounting brackets may need attention or wiring conduit may be partially disconnected.  

3‐Poor  All lights operating, however lenses may be broken, connections not secure.  

4‐Critical  Some lights burnt out or wiring circuitry non‐functioning or both, connections not secure with imminent or permanent failure. 

Table 62 ‐ Condition Rating: Navigation Lights 

Signs/Utilities – “ded”  CONDITION RATING 

Item ‐  55.  Signs, 56. Sign Supports, 57. Utilities 

Type –   All 

  Description 

1‐Good  All signs legible. 

2‐Fair  Minor damage. 

3‐Poor At least one sign is ineffective.  Signs barely legible due to vandalism or fading or partial obstructions. 

4‐Critical  Signs are ineffective   Table 63 ‐ Condition Rating: Signs, Sign Supports and Utilities