Experiences with the construction of EPR at Flamanville and Taishan OECD/ Nuclear Energy Agency Workshop : ‘’Project and Logistics Management in Nuclear New Build’’ NEA Headquarters, Issy-les-Moulineaux March 11th, 2014

OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Experienceswith the construction of EPRat Flamanville and Taishan

OECD/ Nuclear Energy Agency

Workshop : ‘’Project and LogisticsManagement in Nuclear New Build’’

NEA Headquarters, Issy-les-Moulineaux March 11th, 2014

Page 2: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

oBackground

oEPR Projects Status• Flamanville 3• Taishan 1&2

Agenda

oLessons learned • Process• Examples• Early Contractor Involvement

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 2

Page 3: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

EDF’s NUCLEAR FLEETPowerful, competitive, low CO2 emissions

The demands of a zero error safety culture

� EDF Group: the world’s No. 1 nuclear power operator

□ 485.5 TWh generated

□ France: 58 PWRs* at 19 sites

• 404.9 TWh generated: 74.8% of production

• €2.7bn invested in maintenance

□ United Kingdom: 14 AGRs**, 1 PWR* at 8 sites

• 60 TWh generated

□ USA: 5 PWRs* via CENG (49.99% EDF stake) at 3 sites□ USA: 5 PWRs* via CENG (49.99% EDF stake) at 3 sites

� Building the future

□ 3 PWRs under construction

• 1 in France: Flamanville

• 2 in China: Taishan (30% EDF stake)

□ 1 PWR project in the United Kingdom:

• 2 reactors at Hinkley Point

• Authorizations granted

• Design approved by safety authorities

• Final Investment Decision not yet taken. * Pressurized water reactor

** Advanced gas-cooled reactor

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 3

Page 4: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Increase nuclear safety More competitive

EDF-Framatome N4 Siemens KONVOI

Design derived from French N4 and German Konvoi series.

EPR = European (Evolutionary) Pressurised water Reactor

EDF-Framatome N4 Siemens KONVOI

Feedbak of experienceFrom 58 + 17

reactors in operation

Evolutionarydesign concept

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 4

Page 5: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

4 independent safety trains

EPR : some design features to enhance safety

Air Plane Crash shelterMade with very thick concrete

structureOECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 5

Page 6: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Core melt stabilisation system

EPR : some design features to enhance safety

Digital Instrumentation & Control systemComputerised Man Machine Interface

In-containment water storage+ passive cooling system

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 6

Page 7: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

oBackground

oEPR Projects Status• Flamanville 3• Taishan 1&2

Agenda

oLessons learned • Process• Examples• Early Contractor Involvement

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 7

Page 8: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

FLAMANVILLE 3

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 8

Page 9: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

FLAMANVILLE 3

Civil engineering work almost completed.

Prestressing under prepartion.

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 9

Page 10: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

FLAMANVILLE 3

Electro – Mechanical work :more than 50 % completed

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 10

Page 11: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

FLAMANVILLE 3Conventional Island completed

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 11

Page 12: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

FLAMANVILLE 3

oCable puling ongoingoI&C cabinets ongoingoHV& LV switchboards completed

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 12

Page 13: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

FLAMANVILLE 3Commissioning under progress

On track to reach the 2016 target.

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 13

On track to reach the 2016 target.

Page 14: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

TAISHAN 1&2

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 14

Page 15: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

TAISHAN 1

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 15

Page 16: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

TAISHAN 1

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 16

Page 17: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

TAISHAN 1

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 17

Page 18: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

TAISHAN 2

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 18

Page 19: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

TAISHAN 1&2

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 19

Page 20: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

oBackground

oEPR Projects Status• Flamanville 3• Taishan 1&2

Agenda

oLessons learned • Process• Examples• Early Contractor Involvement

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 20

Page 21: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Lessons learned

Goal

Avoid repetition of problems encountered on in-progress EPR Projects

Informed about good practices

and engineering choices

Method Method

� Establish a continuous improvement culture across organizations

� Implement a process which quickly defines, assesses applicability and

implements Construction Lessons learned

Users All EPR Projects

Sharing for mutual benefit

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 21

Page 22: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Lessons learned : a continuous improvement process

Lessons learned process :

� Capture Lessons Learned• Launch investigation on critical topics (top-down process)• Encourage LL implementation in the database (bottom-up process)

� Analyze LL• Sorting of LL by leader entities, by impact (cost, schedule, constructability)• Analysis (relevance, applicability to other projects)

Process the LL� Process the LL• Appoint a pilot for each LL• Launch investigation & action plans• Follow-up of actions• Implement solution (best practices, issues, know-how)

� Communicate• Report• Share

Transforms experiences into valuable knowledge

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 22

Page 23: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Why ? � To prevent & eliminate difficulties for further projects, offers and ongoing

projects: Enhance constructability� To reduce and secure cost & time schedule

How ?� Implement Lessons Learned in the database

To improve the performance

By dedicating people to

Lessons learned : a continuous improvement process

� Implement Lessons Learned in the database� Redaction of reports, interviews,� Missions on site� With support of a LL network positioned in key entities

When ?� Day to day� Lessons Learned is an ongoing process

By dedicating people to this task

Every day

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 23

Page 24: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Examples

Flamanville 3

Taishan1 & 2

� Issue with the liner containment erection

� Liner le&ading to efficient welding

� Reactor raft poured in one step

� CW feedback in order to optimize construction methods 1

months

4.5months 10

weeks

47 weeks

TaishanTaishan

Flamanville 3 Flamanville 3

1 & 2

HinkleyPoint 1 & 2

� CW feedback in order to optimize construction methods

NI raft pouring

months

Liner cup on base slab

weeks

� Construction methods => prefabrications

� Early Contractor involvment

� Improvement of mechanicale and elevtrical erection

works

Page 24OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 24

Page 25: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

HINKLEY POINT C

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 25

Page 26: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Hinkley Point C project key strengths

� World-class team with significant experience in

nuclear projects and large infrastructure projects

(2012 Olympics, Heathrow Terminal 5)

� Lessons from other EPR projects fully included

� Involvement of strategic industrial partners,

sharing construction risk

Leverage from nuclear

and large

infrastructure projects

� Strong project organisation and clear processes

� Basic design agreed with UK regulator together with

Alignment through

contractual framework

� Supply chain aligned to delivery and management of

risk

� Early contractor involvement improves

constructability and interface management

� Basic design agreed with UK regulator together with

strict change management process

� Robust cost model and schedule developed

� Constructability and interface management

improved by 4D modeling

Specific project

strengths

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 26

Page 27: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

4D Construction Planning Model

HPC ProjectExamples of benefits – pre construction

Detailed on site / off site logistics planning:• Monthly time slice• Cranes; scaffold & access• Welfare & facilities• Temporary roads, utilities & works• Materials handling; lay down & traffic control• Interfaces between other contracts

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 27

Page 28: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

New build contracts - Major lessons learned

� Analysis of FA3 main contracts and their

management

� Significant increase in initial quotation, mostly

due to many configuration changes

� Insufficient control of contractual milestones

• Major areas of improvement, in particular:

– A more precise definition of technical scope : engi neering studies, equipment/system list, BoQ, erection, etc

– The right moment to sign the final contract: some c ontracts signed too early compared to detailed design status and works

– Setting up of contractual milestones : notice dates , contract steps (studies, qualification, procurement, manufacturing, erection, tests)

– Cost firming up

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 28

Page 29: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Early contract Involvement (ECI)

• ECI phase : a firming-up phase to conduct early and limited works to get a better level of certainty of contract scope, costs and scheduleThrough an Early Work Agreement (EWA)

Selection of

contractor

Full Notice

To Proceed

Final contract

signature

ECI phase : Early Work Agreement (EWA)

First

Concrete

Date

EWA

signat

ure

Through an Early Work Agreement (EWA)

• Early Work Agreement may cover the following activities (depending on the Contractor’s activities)

– Critical engineering activities

– Technical configuration and interface management

– Project management activities ramp-up

– Plot plan finalisation / optimisation

– Site Preparatory work

– Support to licensing

– Schedule

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 29

Page 30: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Interests of ECI – project & construction aspects

– Risk management: engineering studies performed before FNTP allowing to reduce critical risks (with high probability and high impact), optimise design and secure planning

• Reduction and management of changes in configuration with contractor: No

work shall be started on construction until specifications, drawings sufficient

and configuration enough stable. Freeze of a design reference.

• Anticipation and clarification of interfaces between lots/contracts

– Appropriation of contractor methods, common development of process and procedures

Win-Win approach: an

integrated team to set

the environment for

success

• Entering in a smooth

and simplified dialogue

with the contractor,

working together to

prepare the execution • Consider constructor methods at the very beginning of the detailed

design phase

• Integrate innovative methods and tools from contractors mastering their construction specialty (civil works, etc)

• Improve constructability (pre-fabrication, etc) by considering it in the early engineering phase

• Optimise delivery process

– Implementation of project management organisation in line with contractors’ one and associated preliminary activities to be ready to start construction just after the FNTP

prepare the execution

of the final contract

• Collaborative work

with the contractor to

develop a common

solution and approach

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 30

Page 31: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Interests of ECI – contractual aspects

– Improvement of contract management system and process applying international best practices:

• Formalisation: contractual exchanges, precise definition of milestones, deliverables, interfaces

• Tools for contract managers

– Contractual integration of an agreed number of

Win-Win approach: an

integrated team to set

the environment for

success

• Entering in a smooth

and simplified dialogue

with the contractor,

working together to

prepare the execution – Contractual integration of an agreed number of configurations and associated key milestones (in the final contract)

– Cost firm up : from an estimated target price to a final target price. Reduction of contingencies level

– Common work on schedule

prepare the execution

of the final contract

• Collaborative work

with the contractor to

develop a common

solution and approach

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 31

Page 32: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Heavy prefabrication of the pools has been studied in detail.

The pools will be prefabricated and lifted into to position

Significant improvement in schedule

ECI - HPC Main Civils ContractExamples of benefits – pools optimisation

Significant improvement in schedule

Improvement in safety

Improvement in quality

ECI has identified and developed specific details to enable the prefabrication of the pools

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 32

Page 33: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

ECI - Main Civils ContractExamples of benefits – design to build

Problems detected and resolved during the design phase giving better certainty on construction programme due to:

� Clash detection of rebar, plates and cast in items

� Construction sequencing and coordination

� Material control on site – lean processes using manufacturing techniques

� Improved quality and productivityOECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 33

Page 34: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Precast concrete roof slab components with structural topping:�Increases productivity,�Improved quality with cast in items to be fitted in a factory environment,�Avoids requirement for false work & propping pus early backfilling,

ECI - HPC Main Civils ContractExamples of benefits – gallery optimisation

propping pus early backfilling,�Improves safety / reduced working at height.

It’s important to carry on the ECI through the key contracts

OECD – NEA – 2014/03/11 – Experiences with construction of EPR in Flamanville & Taishan 34

Page 35: OECD/ Nuclear Energy Agency Workshop : ‘’Project …...New build contracts - Major lessons learned Analysis of FA3 main contracts and their management Significant increase in initial

Thanks for your attention