Office of Facilities Development (OFD) Capital Projects Status Report
2nd
Quarter CY 2014
August 6, 2014 OFD is pleased to provide the second quarter Capital Projects Status Report for calendar year 2014. The report provides summary level information on all projects managed by OFD and more detailed information of select Capital Projects. The OFD team has been diligently supporting multiple County projects. Notable projects under construction include: Northside Library and Storage Facility, Crozet Streetscape, Seminole Trail Fire Station Addition/Renovation, and Agnor-Hurt Elementary School Addition/Renovation. The Belvedere Residential "Block" roads, drainage, water, sanitary sewer project from Free State Road bridge to the Village Green has reached substantial completion and punch list items are being addressed. The design of the Regional Firearms Training Center is in progress. The school summer maintenance projects are underway to ensure construction activities are complete prior to the August school opening.
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 1 of 11
CAPITAL PROJECTS Substantially Complete Scope Status Project Budget Key Milestone
Finance Department Teller Window Renovation
Remodel of teller window areas to include new electrical and
data outlets and various
upgrades to teller stations.
Substantially complete; final completion by end of
July.
$121,750 Substantial completion June 2014
In Construction Phase Scope Status Project Budget Key Milestone
Crozet Streetscape Phase II Relocation of overhead electric
and utility lines from Crozet Avenue, new stormwater
drainage system, first block of Main Street (Library Avenue),
and pedestrian, vehicular, and
streetscape enhancements along Crozet Avenue from The
Square to Tabor Street.
West side sidewalk
completed from Tabor Street to the connector
road at Library Ave, except pavers, lighting fixtures,
and landscaping.
East side of Crozet Avenue is substantially complete,
except light fixtures and landscaping.
Block 6 (west side to La
Cocina Del Sol) and Block 7 (west side to Post Office
entrance) to be completed July 2014.
Block 8 (west side to The
Square) to be completed August 2014.
$4,507,851
Streetscape –
Substantial completion November 2014
Utility relocation – completed January 2014
Tabor Street –
completed April 2014 Blocks 1-5 substantially
complete; Blocks 6-8 complete by August
2014.
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 2 of 11
Northside Library and Storage
Facility
Provide a permanent location
for the Northside Library and
long-term County warehouse/ storage space. The new facility
(repurposing of existing building) would provide
approximately 30,000 sq. ft. of
library space, and over 20,000 sq. ft. of warehouse space.
Construction approximately
30% complete as of June.
Albemarle Square Library lease extended for 3
months and move out of Seminole Trail storage
facility complete.
Work planned for July/August includes:
footings for additions, stairwells, and casework
pricing. Potential delay of 1 month
due to structural street
issue. Project Management Team
negotiating with contractor.
$11,844,833
Substantial completion
January 2015
Seminole Trail Volunteer Fire
Department (STVFD) Addition/Renovation
Addition (7,500 sq. ft.) to
STVFD and full renovation of the existing facilities (~7,500
sq. ft.). Includes 2-bay
addition, expansion of living quarters and full renovation of
existing facility to bring it to code and improve the facilities
to properly support the highest call volume station in the
County.
Construction approximately
65% complete as of June. Planned tasks include:
hang drywall in addition;
storefront window/door installation; finalize bay
floor coating selection; complete lower retaining
wall; plan parking lot work; and procure Personal
Protective Equipment (PPE)
lockers and floor finish for bays.
$4,047,403
Substantial Completion
September 2014
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 3 of 11
Belvedere Bond Default
Project
Complete the Belvedere
Boulevard and Residential
"Block" roads, drainage, water, sanitary sewer and related
construction according to the approved development plans.
Phase 1 of the work is
Belvedere Boulevard from Rio Road to Free State Road (RR
bridge); Phase 2 is the remaining Belvedere Boulevard
(Free State Rd. to the Village Green) and the residential
"Blocks" (3, 4A, 5A, 6B & 9A).
Funds for this project are from the developer’s performance
bonds.
Phase 1 Work:
Bond proceeds not
sufficient to cover work; project on hold pending
resolution of funding issues.
Phase 2 Work: comprised of
multiple development bonds necessitating dividing project
into individual Bid Items for each bond resulting in award
of four contracts. Schedule final VDOT and
County inspections.
Continue inspection/ monitoring of contracts.
A/E to complete as-built road & utility plans when
VDOT acknowledges
completion of punch list items.
Complete video inspection and cleaning of storm
sewer system.
Submit as-built plans and documentation for VDOT
and ACSA acceptance.
$3,675,790 Phase 1 Work – Resolve
funding issues
Phase 2 Work – Completion of all
contracted improvements and
submittals to VDOT and
ACSA for acceptance 3rd Quarter 2014
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 4 of 11
Lewis & Clark Exploratory
Center
Construction of an educational
building (including
transportation exhibits and river history), an access road
and parking area, and a connecting trail network, all
located at Darden Towe Park.
Funded by a grant through the VDOT Transportation
Enhancement Fund Program ($800,000) combined with
other funds raised by the Lewis & Clark Exploratory Center
(LCEC).
LCEC has obtained the
services of a project
manager to address items required to pass County
building and systems inspections.
LCEC to work cooperatively
with contractor to coordinate project
completion. OFD will coordinate/
discuss with CDD some plan changes suggested
during the walk-thru with
LCEC and DIGs OFD to provide additional
information requested by VDOT for final
reimbursement (Note: final
reimbursement will not be issued until VDOT has
inspected and signed-off on the completed project).
$800,000
(Grant only)
Completion anticipated
3rd Quarter 2014
Western Albemarle High
School (WAHS) Stormwater Impacts
Design and construct a
stormwater management (SWM) facility and improve
head of channel at the back of WAHS. SWM facility will provide
storm water attenuation/
treatment in the form of a biofilter for the stormwater
runoff from the driver's education parking lot.
Rip-rap channel
construction complete. Biofilter mix installation,
forebay complete. Biofilter completed but not
draining. Contractor
working with Luck Stone to replace biofilter material
(at Luck Stone’s cost) which will consist of
excavating/hauling/
replacing the biofilter mix, mulching, and final
landscaping.
$183,589 Substantial Completion
Fall 2014
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 5 of 11
Agnor Hurt Elementary School
Addition & Renovations
Construction of 11,200 s.f.
addition consisting of seven (7)
classrooms, one (1) full-sized SPED classroom, faculty
workroom, offices and associated support spaces.
Renovations of 3,500 s.f.
consist of security improvements at front
entrance, upgrades to media center, and addition of air
conditioning to the kitchen. Replacement of existing chiller,
exhaust fans, roof top units
and boilers. Site improvements include additional parking and
modifications to student drop-off areas.
Notice to Proceed issued
for construction to
commence. Phase I Construction - site
work for new road and bus loop and relocated
playgrounds is underway.
$5,968,285 Construction to be
completed incrementally
in successive Phases: Ph. 1 – August 2014
Ph. 2 – November 2014 Ph. 3 – June 2015
Ph. 4 – August 2015
School Security
Improvements
Design and construction of
improved entrances at thirteen (13) schools to create a more
secure entrance. The project
was bid with four Base Bids: Base Bid A (5 schools); Base
Bid B (4 schools); Base Bid C (1 school); Base Bid D (3
schools).
Contracts awarded to 3
contractors and Notices to Proceed issued.
Construction underway at
all affected schools.
$500,000 Substantial completion
August 2014
In Bid/Award Phase Scope Status Project Budget Key Milestone
Church Road Basin
Stormwater Management
Facility Retrofit
Maintenance/enhancements to
existing regional stormwater
management facility including survey, design, and
construction. Project will help the County meet required
pollutant reductions mandated for the Chesapeake Bay
watershed.
“No Award” letter issued
since sole bid received
5/22/14 was over budget and negotiations with low
bidder were unsuccessful. Project being readvertised
with bid opening date scheduled for 7/17/14.
$424,739 Bid/Award 3rd Quarter
2014 ~ 6 months
construction
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 6 of 11
In Design/Planning Phase Scope Status Project Budget Key Milestone
Crozet North Safe Routes to
School (SRTS) Sidewalk
SRTS Grant provides pedestrian
improvements along west side of Crozet Avenue North
between Crozet Elementary
School and Ballard Drive. Construction work includes
erosion & sediment control, site grading, concrete curb &
sidewalk, ADA ramps, crosswalk striping & alert
system, asphalt paving,
stormwater system, waterline relocation, & site restoration.
Update construction cost
estimate based on proposed redesign and
obtain consultant fee to
revise the plans and project manual
Revise plans & specs; coordinate plan re-review
and approval Re-advertise 3rd quarter
2014
Proffer funds identified (~$85k) to fund const.
$190,000
(Current)
$275,000
(Projected)
Re-advertise 3rd
Quarter 2014 ~ 2-3 months construction
Crozet Avenue North Sidewalk Replacing or constructing
approximately 1100 feet of sidewalk and drainage
improvements along the west side of Crozet Avenue from
Saint George Avenue to Crozet
Elementary School. Partially funded with FY13 Revenue
Sharing (RS) Funds.
Working with County
Attorney Office to finalize deed for required
acquisitions from one property owner.
Obtain BOS approval of
acquisitions.
$735,787
Bid/award 4th Quarter
2014 ~ 6 months construction
South Pantops Drive/State
Farm Boulevard Sidewalk
Improvements
Construction of 3500 feet of
curb, gutter and sidewalk which
will serve several residential, business, and commercial
establishments. Partially funded with FY13 RS Funds.
Appraisals approx. 90%
complete and consultant
preparing determinations of just compensation.
Work with County Attorney Office to complete deeds for
required acquisitions.
Obtain BOS approval of acquisitions.
$995,570
Bid/award 4th Quarter
2014 ~ 6 months
construction
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 7 of 11
Hydraulic Road and Barracks
Road Sidewalk Improvements
Partially funded with revenue
sharing funds and supports
pedestrian safety by providing sidewalk improvements.
Hydraulic Road - construction of approx. 1700 feet of
sidewalk on the north side
between Commonwealth Drive and Georgetown Road.
Barracks Road: 1) construction of approx. 1000 feet of
sidewalk on the north side from Barracks West
apartments to existing
sidewalk west of Georgetown Road intersection;
2) construction of crosswalks and two segments of sidewalk
(650 ft total) on the south side
between Georgetown Road intersection & Westminster
Road, and between South Bennington Road & 29/250
Bypass ramps.
Application approved by
VDOT for additional
revenue sharing funds in FY15 to fully fund
construction. Agreement under review for approval
by County Executive.
Survey and plan design underway.
$1,588,600
Bid/award 3rd Quarter
2015 ~ 5 months
construction
Fontaine Avenue Sidewalk Construction of a short sidewalk (~160') from the end
of the Fontaine Research Park paved path to the end of
sidewalk at the City line. This
project closes the walkway gap which may create safety issues
if left unconnected.
Staff will provide a "sketch plan" and detail since
proposed sidewalk is within existing right-of-way; sketch
plan and detail is about
95% complete. Staff providing the Project
Manual which is presently 95% complete.
Submit sketch and detail to
VDOT (permit section) to assure it's acceptable prior
to bidding.
$102,189 Bid 3rd Quarter 2014 ~ 2 months construction
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 8 of 11
Hollymead-Powell Creek Drive
Sidewalk
Completion of the sidewalk
connection from Hollymead to
Sutherland Schools. The required right-of-way has been
donated.
Survey and base map
completed.
Since proposed sidewalk is within existing right-of-way,
staff will provide a “minimal design plan” for use with
the standard sidewalk
"technical specification".
$209,164 Bid 3nd Quarter 2014
~ 2 months construction
FY14 Revenue Sharing
Projects - Pedestrian/Sidewalk Improvements
1. Old Lynchburg Road
Walkway Upgrade 2. Avon Street Walkway/
Crosswalks Phase 1
3. Rio Road (Meadowcreek Pkwy to Stonehenge)
4. US Rte 250 West, Crozet (Harris Teeter)
Working with VDOT to split
projects into at least 2 separate UPCs.
Secure services of a
consultant to provide support for administration
of VDOT’s Local Administration Program
(LAP) requirements.
$1,500,000 Work with VDOT to
establish needed UPCs. Secure consultant
services for LAP support
services.
Regional Firearms Training Center
Design and construction of a regional indoor firearms
training facility, which includes a 50-yard qualification range
and 50-yard tactical range, 16
shooting lanes (original scope 20-24 shooting lanes),
classroom, office, bathrooms and storage areas (control
platforms eliminated from
original scope). The range will be located on property owned
by UVA on Milton Road.
Schematic Design completed and delivered
to team on 6/27/14. Memo/report provided to
BOS indicating status of
design and schematic cost estimate on 7/8/14.
Current construction cost estimate showing ~$2Mil
over budget. Working with
partners on potential phasing and Value
Engineering options. Completed second public
meeting on 7/17/14. Presentation to the BOS
anticipated on 8/13/14.
Final drafting of Regional Operating Agreement
underway & lease terms expected to be approved
by UVA in August.
$4,865,422
Agreement in place for operations & funding –
3rd Quarter 2014 Complete design/site
plan approval – 4th
Quarter 2014 Bid/award – 1st Quarter
2015 ~ 6-9 months construction
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 9 of 11
MAINTENANCE PROJECTS
In Construction Phase Scope Status Project Budget Key Milestone
Stormwater Multi-Facility Maintenance Projects
Includes maintenance (sediment removal/dredging)
and upgrades to existing
regional stormwater management facilities and
channel (Four Seasons Lower Basin dredging, Four Seasons
Upper channel improvements,
and the Greenbrier Road forebay sediment removal).
Phase 1 scope is complete and included surveying and
analysis of existing facilities to determine required
improvements and possible
enhancements. Phase 2 scope includes design and
construction of recommended improvements/enhancements.
Four Seasons Upper Pond Dredging:
Muck removal now
completed. Cleanup and punch list inspection to occur
end of July. Four Seasons Channel and
Branchlands (Hillsdale Road)
Forebay: Contracts awarded and
routing for execution by County.
$373,404 Substantial Completion 3rd Quarter 2014 for all
three projects
Yancey Elementary School
Roof Replacement
Replace existing ballasted roof
systems at Yancey Elementary School main building and 1990
addition (29,320 SF). New
roofing system will be adhered EPDM roofing system with
new insulation.
Notice to Proceed issued for
construction to commence. Stone roof ballast removal
completed.
Tear off to continue sections at a time.
$470,000 Substantial completion
August 2014
Stone-Robinson Elementary
School Roof Replacement
Replace existing ballasted roof
at Stone Robinson Elementary
School. New EPDM roof system (23,295 SF).
Notice to Proceed issued for
construction to commence.
Removal of roof stone began and stone being delivered to
Darden Towe Park for repurposing.
Roof tear-off underway.
$253,650 Substantial completion
August 2014
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 10 of 11
Cale Elementary School Roof
Replacement, Phase II
Replace 2nd half of ballasted
school roof. New roof system
will be same as Phase 1, insulation self adhering EPDM
roof.
Notice to Proceed issued for
construction to commence.
Completion of gym roof, walk pads and detailing by
July 2014. Credit to be evaluated for
cricket/slope change. Credit
amount is $4,400
$357,600 Substantial completion
August 2014
Cale Elementary School
Parking Lot Expansion
Design and construction of an
additional twenty-five (25) parking spaces on the
southeast side of the school.
Notice to Proceed issued for
construction to commence. Contractor has all E&S in
place, has started
stormwater piping, and graded most of the site.
Planned tasks include: bio-retention pond; complete
storm drainage piping; install
asphalt.
$155,969 Substantial completion
August 2014
Monticello High School Track
Replacement
Design and construction
services to demolish and
replace existing track at Monticello High School football
stadium.
Notice to Proceed issued for
construction to commence.
Contractor completed demo of existing top coat at long
jump and triple jump runways.
Planned tasks include: removal of existing track
surface material; place new
track material; painting of track lanes and symbols.
$165,000 Substantial completion
July 2014
Vehicle Maintenance Facility
(VMF) Lift Replacement Phase III
Phase III of multi-year phased
replacement of bus and vehicle lifts originally installed
with the construction of the VMF in the early 1980’s. This
phase replaces one (1) bus lift.
Notice to Proceed issued for
construction to commence. Construction underway -
concrete work completed. Lift delivery and installation
is pending.
$198,000 Substantial completion
August 2014
Office of Facilities Development Capital Projects Status Report – 2nd Quarter, CY 2014
Page 11 of 11
Ivy Creek School Exterior
Masonry Wall Repairs
Evaluate cracking and
deterioration of exterior c.m.u.
walls at various areas around perimeter of school, prepare
plan for repair, and initiate construction to remedy the
situation.
Notice to Proceed issued for
construction to commence.
Masonry repairs completed. Paint touch-up is pending.
$35,750
Substantial completion
August 2014
In Bid/Award Phase Scope Status Project Budget Key Milestone
Court Square Air Handling
Units (AHU) and Controls
Replacement
Replace existing AHU’s with
new and replace pneumatic
controls with digital.
Notice of Intent to Award
issued and contract
forwarded to Contractor for execution.
Expect to issue Notice to Proceed by end of July.
$410,249 Substantial completion
October 2014
In Design/Planning Phase Scope Status Project Budget Key Milestone
COB-McIntire AHU
Replacement
Replace existing air handling
units along with main duct cleaning. Humidity control to
be included.
A/E Project Order issued for
design and construction administration services.
Expecting final design documents 3rd quarter 2014
$691,275 Bid 3rd Quarter 2014
Project start Feb. 2015
Page 1 of 2 August 6, 2014
Project: Crozet Streetscape Enhancements Phase II
Phase 2 (Crozet Avenue) and 2A (Main Street and Alleys)
Description: Phase 2 and 2A of the Crozet Streetscape Enhancements includes relocation of overhead electric and
utility lines from Crozet Avenue, new stormwater drainage system, first block of Main Street (Library
Avenue), and pedestrian, vehicular, and streetscape enhancements along Crozet Avenue from The
Square to Tabor Street.
Status:
Phase 2 – Crozet Avenue:
Project web page maintained to provide project information and construction updates. West side
sidewalk completed from Tabor Street to the connector road at Library Avenue, except pavers, lighting
fixtures, and landscaping. East side of Crozet Avenue is substantially complete, except light fixtures
and landscaping. Block 6 (west side to La Cocina Del Sol) and Block 7 (west side to Post Office
entrance) to be completed July 2014. Block 8 (west side to The Square) to be completed August 2014.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Design Complete 08/30/12 02/28/13 182
Right-of-Way / Easements Complete 08/30/12 07/31/13 335
VDOT Approval to Advertise 09/30/12 09/04/13 339
Utility Relocation Complete 10/30/12 10/25/13 360
Advertise 09/30/12 09/11/13 346
Bid Opening Date 10/30/12 10/16/13 351
VDOT "Authorize to Award" 11/30/12 11/13/13 348
Pre-construction Meeting 11/30/12 12/11/13 376
Sign Contract; Issue NTP 11/30/12 01/16/14 412
Community Meeting 11/30/12 12/03/13 368
Groundbreaking Ceremony 04/01/14 04/01/14 0
Ph-A Curb, Drainage & Sidewalk Complete 06/01/13 06/27/14 391
Ph-B Curb, Drainage & Sidewalk Complete 11/01/13 09/22/14 325
Paving Complete 12/01/13 10/31/14 334
Substantial Completion 01/30/14 11/20/14 294
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[March 2007]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 3,700,000 $ 4,507,851 $ (807,851)
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 3,700,000 $ 4,507,851 $ (807,851)
Use of Funds
Soft Costs $ 590,000 $ 917,759 $ (327,759)
Hard Costs $ 2,770,000 $ 3,555,668 $ (785,668)
Contingency $ 340,000 $ 34,423 $ 305,577
Total $ 3,700,000 $ 4,507,851 $ (807,851)
Balance = Funding - Costs $ - $ -
Encumbered: $ 895,456
Paid to Date: $ 3,531,124
A/E Contract (Kimley-Horn & Associates) Construction Contract (Ph 2A – Library Ave)
Original Agreement $379,000 Piedmont Concrete Contractors
Approved Changes $163,761 COMPLETE (FY11) $780,168
Pending Changes $0
TOTAL
A/E Change Orders:
$542,761 Construction Contract (Ph 2 – Crozet Ave)
Linco, Inc.
No. & Brief Description Amount
1 – Jarmans Gap Road interim storm
system & historic resources (FY09)
$41,500
2 – Additional plats & transportation
planning services (FY09)
$12,625
3 – Main Street extension to proposed
Library entrance (FY09)
$24,000
4 – Conceptual Downtown Plaza
improvements (FY09)
$ 9,750
5 – Additional plats (FY10) $ 2,750
6 – Temporary tie-in of new Main
Street (FY10)
$21,000
7 – Water & sewer relocation design
(FY10)
$ 7,300
8 – Library storm sewer advance
work (FY12)
$ 5,961
9 – Finalize const. documents (FY13) $38,875
Bid Award $1,474,350
Approved Changes $ 17,248
Pending Changes $ 51,910
TOTAL $1,543,508
Construction Change Orders:
No. & Brief Description Amount
1 – Retaining wall construction;
storm piping changes
$17,248
Pending 2 and 3 – various changes
due to unforeseen site/field
conditions, owner requested, or
VDOT required
$51,910
Page 1 of 2 August 6, 2014
Project: Northside Library and Storage Facility
Description: Provide a permanent location for the Northside Library and long-term County warehouse/storage space
by repurposing an existing building located on property recently purchased at 705 Rio Road West
(formerly Phillips Building Supply). The new facility would provide approximately 30,000 square feet
of library space, and over 20,000 square feet of warehouse space. The Northside Library is currently
located in leased space at Albemarle Square, and the County warehouse/storage space is currently
located in leased space at the former Comdial building on Seminole Trail. The new facility will
eliminate the need for those two leased spaces.
Status: Construction work underway and approximately 30% complete as of June 30. Albemarle Square
Library lease extended for 3 months and move out of Seminole Trail storage facility complete. Schools
ESOL space not included presently, but might be added. Work planned for July/August includes:
footings for additions, stairwells, and casework pricing. Potential delay of one month and change order
due to structural steel change of approximately $60-$100k. Project Management Team meeting with
contractor to resolve.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Schematic design Complete 09/15/13 09/15/13 0
Design Complete 12/31/13 12/31/13 0
Bid Opening Date 01/31/14 02/12/14 12
Notice to Proceed 02/15/14 03/31/14 44
Demolition Complete 03/01/14 05/07/14 67
Site Work Complete 05/01/14 10/01/14 153
Substantial Completion:
Basement Storage Area 05/01/14 10/15/14 167
Library 09/30/14 01/15/15 107
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[May 2013]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 11,820,373 $ 11,844,833 $ (24,460)
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 11,820,373 $ 11,844,833 $ (24,460)
Use of Funds
Soft Costs $ 3,764,625 $ 4,033,384 $ (268,759)
Hard Costs $ 7,402,498 $ 7,585,171 $ (182,673)
Contingency $ 653,250 $ 226,278 $ 426,972
Total $ 11,820,373 $ 11,844,833 $ (24,460)
Balance = Funding - Costs $ 0 $ -
Encumbered: $ 5,141,012
Paid to Date: $ 5,576,728
A/E Contract (HB+M Architects) Construction Contract (Kenbridge Construction)
Original Agreement $736,500 Bid Award $6,773,500
Approved Changes $ 14,100 Approved Changes $ (29,379)
Pending Changes $ 0 Pending Changes $ 111,086
TOTAL $750,600 TOTAL $6,855,207
A/E Change Orders:
No. & Brief Description Amount
1 – Traffic & access analysis $ 3,450
2 – Extended bid phase assistance $10,650
1 – Delete re-roofing scope;
delete sprinkler system standpipe
$(73,100)
2 – Mezz duct frame, stair walls,
VA Power conduits
$ 43,721
Pending – Structural steel
changes; various changes due to
unforeseen site/field conditions
$111,086
Page 1 of 2 August 6, 2014
Project: Seminole Trail Volunteer Fire Department Addition/Renovation
Description: Addition (7,500 sq. ft.) to Seminole Trail Volunteer Fire Department (STVFD) and full renovation of
the existing facilities (~7,500 sq. ft.). Total scope includes a 2-bay addition, an expansion of living
quarters and full renovation of the existing facility to bring it to code and improve the facilities to
properly support the highest call volume station in the County.
Status: Construction underway and approximately 65% complete as of June 2014. Planned tasks include: hang
drywall in addition; storefront window/door installation; finalize bay floor coating selection; complete
lower retaining wall; plan parking lot work; and procure Personal Protective Equipment (PPE) lockers
and floor finish for bays.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Pre-design Complete 01/11/13 01/18/13 7
Design Complete 03/22/13 04/26/13 35
Bid Opening Date 04/11/13 05/31/13 50
Notice of Intent to Award 04/18/13 07/23/13 96
Notice to Proceed 04/29/13 08/26/13 119
Renovation Demo Complete 06/14/13 10/13/13 121
Excavation - Addition Complete 07/05/13 10/04/13 91
Structural Elements Complete 09/06/13 05/22/14 258
Building Dried-In 11/29/13 06/13/14 196
Finishes Complete 02/28/14 09/05/14 189
Site Work Complete 03/21/14 09/05/14 168
Substantial Completion 04/04/14 09/22/14 171
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[May 2012]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 3,836,670 $ 4,033,298 $ (196,628)
Future Appropriations $ - $ 14,105 $ (14,105)
Additional Source $ - $ - $ -
Total $ 3,836,670 $ 4,047,403 $ (210,733)
Use of Funds
Soft Costs $ 426,320 $ 567,600 $ (141,280)
Hard Costs $ 3,126,500 $ 3,376,743 $ (250,243)
Contingency $ 283,850 $ 103,060 $ 180,790
Total $ 3,836,670 $ 4,047,403 $ (210,733)
Balance = Funding - Costs $ - $ -
Encumbered: $ 1,232,234
Paid to Date: $ 2,385,878
A/E Contract (DJG, Inc. – includes Add. & Renov.) Construction Contract (Kenbridge Construction)
Original Agreement $428,444 Bid Award $3,001,754
Approved Changes $ 10,946 Approved Changes $ 27,678
Pending Changes $ 0 Pending Changes $ 221,884
TOTAL $439,390 TOTAL $3,251,316
A/E Change Orders:
Construction Change Orders:
No. & Brief Description Amount No. & Brief Description Amount
1 – MEP redesign for Value
Engineering changes
$10,946 1 – Underground sewer lines under
engine bay floor; sanitary pipe to tie-
in washer boxes to sewer line in
laundry room 114; add mop sink in
room 016
2 – Replace doors and hardware at
several locations to comply with
code requirements for fire rating
3 – Dumpster rental for demo by
volunteers; add section of concrete
footing to CMU wall
4 – Underground water line to riser
room 008; adding an energy
recovery ventilator to redesigned
HVAC system
Pending Future – Civil/structural
drawing discrepancies; various
changes due to unforeseen site/field
conditions, design errors, or owner
requested; PPE lockers and concrete
bay floors
$ 10,882
$ 4,330
$ 2,386
$ 10,080
$221,884
Page 1 of 2 August 6, 2014
Project: Crozet North Sidewalk
Description: Provide for pedestrian safety by replacing or constructing approximately 1100 feet of sidewalk and drainage
improvements along the west side of Crozet Avenue from Saint George Avenue to Crozet Elementary
School. County and Revenue Sharing funds are being used to provide the sidewalk from St. George Avenue
to Crozet Elementary School. A Safe Routes to School (SRTS) Grant provides improved pedestrian crossing
at the school and extends sidewalk to Ballard Drive.
Status: Crozet Avenue North Sidewalk: Working with County Attorney’s office to finalize deed for required
acquisitions from one property owner. Board approval of acquisitions is required and will be scheduled for a
Board meeting in the very near future. Obtain VDOT approval of Final Plans & Project Manual and
authorization to advertise - target 3rd quarter 2014; approximately 6 months construction.
Safe Routes to School Sidewalk: Update construction cost estimate based on proposed redesign and obtain
consultant fee to revise the plans and project manual. Revise plans & specs; coordinate plan re-review and
approval. Proffer funds have been identified to allocate to the project. Targeting re-advertisement 3rd
quarter 2014; approximately 3 months is estimated for construction.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Revenue Sharing Project
(St. George to Crozet ES)
Design Complete 02/14/13 02/28/14 379
Right-of-Way / Easements Complete 03/15/13 09/30/14 564
VDOT Approval to Advertise 04/15/13 10/30/14 563
Bid Opening Date 05/31/13 12/15/14 563
Notice to Proceed / VDOT Approval of Contract 06/30/13 01/10/15 559
Curb & Drainage Complete 08/31/13 04/01/15 578
Sidewalks Complete 09/30/13 05/30/15 607
Paving Complete 10/15/13 06/20/15 613
Substantial Completion 10/15/13 06/30/15 623
SRTS Grant Project
(Crozet ES to Ballard Dr.)
Design Complete 04/30/12 02/20/13 296
Right-of-Way / Easements Complete 05/31/12 12/30/12 213
VDOT Approval to Advertise 06/30/12 07/30/13 395
Bid Opening Date 08/15/12 10/28/13 439
Re-advertise Project 01/08/14 08/30/14 234
Notice to Proceed / VDOT Approval of Contract 09/15/12 09/30/14 745
Waterline Relocation Complete 04/15/14 06/15/14 61
Curb & Drainage Complete 11/15/12 10/30/14 714
Sidewalks Complete 11/30/12 11/30/14 730
Paving Complete 12/15/12 12/15/14 730
Substantial Completion 12/15/12 12/15/14 730
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 661,400 $ 985,787 $ (324,387)
Future Appropriations $ - $ (60,000) $ 60,000
Additional Source $ - $ - $ -
Total $ 661,400 $ 925,787 $ (264,387)
Use of Funds
Soft Costs $ 104,200 $ 278,329 $ (174,129)
Hard Costs $ 497,200 $ 578,789 $ (81,589)
Contingency $ 60,000 $ 68,669 $ (8,669)
Total $ 661,400 $ 925,787 $ (264,387)
Balance = Funding - Costs $ - $ -
Encumbered: $ 17,249
Paid to Date: $ 159,531
* Future transfer to South Pantops Drive/Sate Farm Boulevard revenue sharing sidewalk project
A/E Contract (Kimley-Horn & Assoc.) – RS Sidewalk Construction Contract Original Agreement $40,000 Bid Award $
Approved Changes $ 1,600 Approved Changes $
Additional Agreement $31,596 Pending Changes $
TOTAL $73,196 TOTAL $
A/E Change Orders:
No. & Brief Description Amount
1 - Eliminate bid/construction
observation; add plats & final
engineering services.
Additional Agreement: Waterline
relocation design, right-of-way
acquisition and construction phase
services
$ 1,600
$31,596
A/E Contract (Anhold Associates) – SRTS
Original Agreement $20,697
Approved Changes $ 2,524
Pending Changes $ 0
TOTAL $23,221
A/E Change Orders:
No. & Brief Description Amount
1 – Prepare documents to relocate
existing waterline conflicting with
proposed stormwater utilities
$2,524
Construction Contract
Bid Award $
Approved Changes $
Pending Changes $
TOTAL $
Page 1 of 2 August 6, 2014
Project: South Pantops Drive/State Farm Boulevard Sidewalk Improvements
Description: Provide for pedestrian safety along the north side of South Pantops Drive and west side of State Farm
Boulevard by constructing 3500 feet of curb, gutter and sidewalk which will serve several residential,
business, and commercial establishments. Construction will be partially funded with FY13 Revenue
Sharing Funds.
Status: Appraisals approximately 90% and consultant preparing determinations of just compensation. Board approval
of acquisitions is required. Obtain VDOT approval of Final Plans & Project Manual and authorization to
advertise - target 3rd quarter 2014; approximately 6 months construction.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Design Complete 12/31/12 10/01/13 274
Right-of-Way/Easements Complete 03/15/13 09/30/14 564
VDOT Approval to Advertise 04/15/13 10/30/14 563
Bid Opening Date 06/01/13 12/15/14 562
Notice to Proceed/VDOT Approval of
Contract 07/01/13 01/10/15 558
Curb & Drainage Complete 09/01/13 04/01/15 577
Sidewalks Complete 10/01/13 05/30/15 606
Paving Complete 10/15/13 06/20/15 613
Substantial Completion 10/31/13 06/30/15 607
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[July 2008]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 512,000 $ 935,570 $ (423,570)
Future Appropriations $ - $ 60,000 $ (60,000)
Additional Source $ - $ - $ -
Total $ 512,000 $ 995,570 $ (483,570)
Use of Funds
Soft Costs $ 60,000 $ 276,305 $ (216,305)
Hard Costs $ 410,000 $ 645,424 $ (235,424)
Contingency $ 42,000 $ 73,841 $ (31,841)
Total $ 512,000 $ 995,570 $ (483,570)
Balance = Funding - Costs $ - $ -
Encumbered: $ 20,297
Paid to Date: $ 122,380
* Future transfer from Crozet Ave North revenue sharing sidewalk project.
A/E Contract (Kimley-Horn & Associates) Construction Contract Original Agreement $ 39,116 Bid Award $
Approved Changes $ 9,369 Approved Changes $
Additional Agreement $ 58,483 Pending Changes $
TOTAL $106,968 TOTAL $
A/E Change Orders:
No. & Brief Description Amount
1 – Update survey (FY09) $ 600
2 – Additional survey (FY09) $ 6,950
3 – Add topo survey, plats & final
engineering; eliminate bidding/
construction observation (FY12)
$ 1,819
Additional Agreement (RS funds):
Bidding/construction phase;
easement acquisition services
$58,483
Page 1 of 2 August 6, 2014
Project: Regional Firearms Training Center
Description: Design and construction of a regional indoor firearms training facility, which includes a 50-yard
qualification range and 50-yard tactical range, 16 shooting lanes (original scope 20-24 shooting lanes),
classroom, office, bathrooms and storage areas (control platforms eliminated from original scope). The
range will be located on property owned by UVA on Milton Road.
Status: Schematic design completed and delivered to team on 6/27/14. Schematic footprint includes the site,
two 8 lane ranges, and 3,200 sq. ft. administration building. Memo/report provided to Board indicating
status of design and schematic cost estimate on 7/8/14. Current Cost estimate showing construction cost
~ $2Mil over budget. Working with partners on potential phasing options to bring project in at existing
budget and Value Engineering options. Presentation to the Board anticipated on 8/13/14. Final drafting
of Regional Operating Agreement underway and lease terms expected to be approved by UVA in
August. Project team presented second round of public meetings on 7/17/14. No issues identified by
public during that meeting.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
A/E Procurement Complete 04/07/14 04/21/14 14
Pre-design Complete 05/26/14 07/10/14 45
Design Complete 09/29/14 12/17/14 79
Bid Opening Date 10/30/14 01/19/15 81
Notice to Proceed 11/27/14 02/16/15 81
Excavation Complete 0
Site Work Complete 0
Substantial Completion 08/25/15 11/25/15 92
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[January 2014]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 4,865,422 $ 4,865,422 $ -
Future Appropriations $ - $ - $ -
Additional Source $ - $ - $ -
Total $ 4,865,422 $ 4,865,422 $ -
Use of Funds
Soft Costs $ 509,191 $ 669,965 $ (160,774)
Hard Costs $ 4,024,824 $ 5,889,315 $ (1,864,491)
Contingency $ 331,407 $ 279,398 $ 52,009
Total $ 4,865,422 $ 6,838,678 $ (1,973,256)
Balance = Funding - Costs $ - $ (1,973,256)
Encumbered: $ 496,005
Paid to Date: $ 64,769
A/E Contract (Clark Nexsen) Construction Contract
Original Agreement $514,137 Bid Award $
Approved Changes $ 42,276 Approved Changes $
Pending Changes $ Pending Changes $
TOTAL $556,413 TOTAL $
CO History:
No. & Brief Description Amount
Pending - Well and septic design
and analysis
$42,276
Page 1 of 2 August 6, 2014
Project: Church Road Basin Stormwater Management Facility Retrofit
Description: The Church Road Basin project includes maintenance and enhancements to the existing regional
stormwater management facility. The project scope includes survey, design, and construction. The
County is required (through the DCR-issued stormwater permit) to reduce pollutant discharges
(nitrogen, phosphorus and sediment) to impaired waters having approved TMDLs, or pollution diets.
This project will help the County meet required pollutant reductions mandated for the Cheasapeake Bay
watershed.
Status: Project was advertised and one bid received on May 22, 2014. The sole bid was over budget and
negotiations with the low bidder were unsuccessful; therefore, a “no award” letter was issued by the
Purchasing office on June 10, 2014. The project is currently being readvertised with a bid receipt date of
July 17, 2014. Award 3rd
quarter 2014, approximately 6 months construction.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Charrette Mtg 05/31/13 06/12/13 12
60%-design Complete 07/26/13 10/25/13 91
100% Design Complete 11/08/13 02/28/14 112
Project Out-to-bid 01/10/14 06/15/14 156
Bid Opening Date 02/28/14 07/19/14 141
Notice to Proceed 04/01/14 08/20/14 141
Substantial Completion 12/14/14 02/20/15 68
Grading Plan
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[April 2013]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 449,739 $ 403,847 $ 45,892
Future Appropriations $ - $ 20,892 $ (20,892)
Additional Source $ - $ - $ -
Total $ 449,739 $ 424,739 $ 25,000
Use of Funds
Soft Costs $ 98,739 $ 99,001 $ (262)
Hard Costs $ 265,000 $ 240,000 $ 25,000
Contingency $ 86,000 $ 85,738 $ 262
Total $ 449,739 $ 424,739 $ 25,000
Balance = Funding - Costs $ - $ -
Encumbered: $ 14,413
Paid to Date: $ 69,059
A/E Contract (Kimley-Horn & Associates) Construction Contract
Original Agreement $72,772 Bid Award $
Approved Changes $ 2,310 Approved Changes $
Pending Changes $ Pending Changes $
TOTAL $75,082 TOTAL $
A/E Change Orders:
No. & Brief Description Amount
1 – Easement plat preparation &
grant application assistance
$2,310
Page 1 of 2 August 6, 2014
Project: Agnor-Hurt Elementary Additions & Renovations
Description: Construction of an 11,200 sq. ft. addition consisting of seven (7) classrooms, one (1) full-sized SPED
classroom, faculty workroom, offices and associated support spaces. Renovations of 3,500 sq. ft. consist
of security improvements at front entrance, upgrades to media center, and addition of air conditioning to
the kitchen. Replacement of existing chiller, exhaust fans, roof top units and boilers. Site improvements
include additional parking and modifications to student drop-off areas.
Status: Notice to Proceed issued for construction work to commence. Phase I Construction (site work for new
road and bus loop and relocated playgrounds) underway.
Project Schedule:
Phase Baseline Schedule Actual/Forecast Variance (days)
Schematics Complete 11/14/13 11/14/13 0
Construction Docs Complete 03/31/14 04/02/14 2
Bid Opening Date 04/30/14 05/08/14 8
Notice to Proceed 06/05/14 06/18/14 13
Start Construction 06/16/14 06/19/14 3
Phase 1 - Start 06/16/14 06/19/14 3
Phase 1 - Finish 08/18/14 08/18/14 0
Phase 2 - Start 08/19/14 08/19/14 0
Phase 2 - Finish 11/26/14 11/26/14 0
Phase 3 - Start 12/20/14 12/20/14 0
Phase 3 - Finish 06/12/15 06/12/15 0
Phase 4 - Start 06/13/15 06/13/15 0
Phase 4 - Finish 08/01/15 08/01/15 0
Substantial Completion 07/01/15 07/01/15 0
Final Completion 08/01/15 08/01/15 0
Page 2 of 2 August 6, 2014
Project Budget:
Baseline
[January 2014]
Current
Estimate At Completion Variance
Funding
Appropriated to Date $ 5,868,285 $ 5,918,663 $ (50,378)
Future Appropriations $ 49,622 $ (49,622)
Additional Source $ - $ - $ -
Total $ 5,868,285 $ 5,968,285 $ (100,000)
Use of Funds
Soft Costs $ 616,772 $ 583,526 $ 33,246
Hard Costs $ 4,913,694 $ 5,248,850 $ (335,156)
Contingency $ 337,819 $ 135,909 $ 201,910
Total $ 5,868,285 $ 5,968,285 $ (100,000)
Balance = Funding - Costs $ - $ - $ -
Encumbered: $ 5,062,941
Paid to Date: $ 322,250
Appropriation includes schools maintenance money for HVAC, paving. Future appropriation represents
estimate of reallocation of project management funds from maintenance account.
A/E Contract (SHW Group) Construction Contract (Haley Builders)
Original Agreement $400,500 Bid Award $4,947,000
Approved Changes $ Approved Changes $
Pending Changes $ Pending Changes $
TOTAL $400,500 TOTAL $4,947,000
CO History:
No. & Brief Description Amount