OHLONE COLLECE Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539 CHANGE ORDER (UNILATERAL) Project: BPO No.: 6105A - Academic Core Building B5901601 Date: DSA File No.: 3/25/2019 1-C3 The following parties agree to the terms of this Change Order: DSA Appl. No.: 01-114438 Owner: Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539 Contractor: Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 Architect: Cannon Design 202 Green Street San Francisco CA 94111 Reference Description Cost Days Ext. PCO#: 20 Requested By: Performed By: Reason: Provide all labor, material and equipment to complete the scope of work per ASI 003 (mechanical revisions) and ASI 018 (sequencing of controls). Architect Design Change $18,264.00 PCO#: 61 Requested By: Performed By: Reason: Provide all labor, material and equipment to remove and properly dispose of an existing asbestos pipe in conflict with new storm drain installation. Field Condition $1,893.00 PCO#: 144 Requested By: Performed By: Reason: Provide all labor, material and equipment to complete the scope of work per ASI 027 - revised bridge soffit between building 2 and 3. Architect Design Change $3,682.00 PCO#: 147 Requested By: Performed By: Reason: Provide all labor, material and equipment to complete the scope of work as noted in response to RFis 208R0-R3 and per scope of work per ASI 30Rl - revised restroom layout, wall types and mechanical pump room. Architect Design Change $107,039.00 PCO#: 166 Requested By: Performed By: Reason: Provide all labor, material and equipment to complete the scope of work per response to RFI 800 - demolition of unforeseen underground ductbank obstruction in path of the underground hydronic piping. Field Condition $4,973.00 PCO#: 172 Requested By: Performed By: Reason: Provide all labor, material and equipment to complete the scope of work per ASI 053 - revised and added casework in Chemistry labs, wire shelving units changed to solid shelving units with ledges. District Change $32,521.00 BPO #:B5901601 Change Order#: 19

OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

OHLONE COLLECE

Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

CHANGE ORDER (UNILATERAL) Project

BPO No

6105A - Academic Core Building

B5901601

Date

DSA File No

3252019

1-C3

The following parties agree to the terms of this Change Order DSA Appl No 01-114438

Owner Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

Contractor Balfour Beatty Construction 2335 Broadway Suite 300 Oakland CA 94612

Architect Cannon Design 202 Green Street San Francisco CA 94111

Reference Description Cost Days Ext

PCO 20

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 003 (mechanical revisions) and ASI 018 (sequencing of controls)

Architect Design Change

$1826400

PCO 61

Requested By

Performed By

Reason

Provide all labor material and equipment to remove and properly dispose of an existing asbestos pipe in conflict with new storm drain installation

Field Condition

$189300

PCO 144

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 027 -revised bridge soffit between building 2 and 3

Architect Design Change

$368200

PCO 147

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work as noted in response to RFis 208R0-R3 and per scope of work per ASI 30Rl - revised restroom layout wall types and mechanical pump room

Architect Design Change

$10703900

PCO 166

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 800 - demolition of unforeseen underground ductbank obstruction in path of the underground hydronic piping

Field Condition

$497300

PCO 172

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 053 -revised and added casework in Chemistry labs wire shelving units changed to solid shelving units with ledges

District Change

$3252100

BPO B5901601 Change Order 19

PCO 251

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1116 - schedule 10 piping not allowed per submitted 123 comments only schedule 40 to be used

Architect Design Change

$5660100

PCO 263

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 71 -commissioning agent comment to modify ductwork in building 1 restrooms 1306 and 1308

Architect Design Change

$1210800

PCO 268

Requested By

Performed By

Reason

Backcharge to the contractor for design teams assistance with additional submittal reviews nursery research and tagging of the substitution trees

Architect Design Change

($482500)

PCO 313

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1021 - fire piping new structural attachment at approximately 1045 locations

Architect Design Change

$24013700

PCO 352

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 076 -New air compressor added compressed air piping to spray booth and added acoustical caulking and firestopping

District Change

$2756200

PCO 375

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 83 -additional chemical water treatment for the geothermal bore field piping

Architect Design Change

$1432200

PCO 463

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per RFI 461 -added reinforcing at details 2S430 and 1S433

Architect Design Change

$155600

PCO 464

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 540 - added reinforcing at wall penetrations in the CUP

Architect Design Change

$139900

PCO 465

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per changes made to reinforcing in submittals 220 and 221 (partial CCD 40) where grade beams intersect with concrete walls

Architect Design Change

$268800

PCO 466

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 547Rl - added reinforcing at building 1 level 1 wall penetrations

Architect Design Change

$287600

BPO 85901601 Change Order 19

PCO 467 Provide all labor material and equipment to complete the scope of work per response $619000 to RFI 815 - added HRC 670 T-heads on all boundary vertical reinforcing at building 1 CUP wall along gridline G

Requested By

Performed By

Reason Architect Design Change

PCO 468 Provide all labor material and equipment to complete the scope of work per response $230000 to RFI 920 - new block out and reinforcing at new storm drain pipe at south site wall at building 1

Requested By

Performed By

Reason Architect Design Change

PCO 472 Provide all labor material and equipment to complete the scope of work per response $131400 to RFI 1032 - added rebar at footing to accommodate revisions due to electrical conduit conflict

Requested By

Performed By

Reason Architect Design Change

Contract time will be adjusted as follows

Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $334102300

0 Calendar Days Extension (zero unless Amount of This Change Order $53260000 otherwise indicated)

Contract Amount $12995235000 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA __3 Oakland CA 94612

UNILATERAL

~~~-Name DateName

Architect

Cannon Design 202 Green Street San Francisco CA 94111

Digitally signed by Carey Woo Dale 2019 05 20 112009-0700

Name Date

END OF DOCUMENT

BPO B5901601 Change Order 19

OHLONE CO L LECE

Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

CHANGE ORDER (UNILATERAL) Project

BPO No

6105A -Academic Core Building

85901601

Date

DSA File No

582019

1-Cl

The following parties agree to the terms of this Change Order DSA Appl No 01-114438

Owner Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

Contractor Balfour Beatty Construction 2335 Broadway Suite 300 Oakland CA 94612

Architect Cannon Design 202 Green Street San Francisco CA 94111

Reference Description Cost Days Ext

PCO 113

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 299Rl - added drywall at the CUP level of elevator 1B to achieve the necessary 2hr wall rating

Architect Design Change

$520900

PCO 148

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to ASI 31 which deleted a large work bench with 3 power monuments but added two typical student work stations with power monuments (2 each - 4 total) gas and vacuum

District Change

$802000

PCO 164

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 032 -Added mechanical duct work and electrical infrastructure to accommodate the new video walls at both the medium and large tiered classrooms

District Change

$17825600

PCO 264

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 72Rl and response to RFI 1482 The flooring was revised from carpet to polished concrete in the corridor from gridline 2-1 to 2-7 cabinetry was added in the sculpture area as well as the glazing room the pottery wheel space was reconfigured the electrical was revised to all the electric kilns and retractable lighting was added in the sculpture area venting was added for the kilns a sink was added in the glazing room and the masonry wing walls were removed

District Change

$10450800

PCO 299

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1450 angle brace conflicted with exterior wall at bldg 2 lvl 2 and needed to be cut back and re-welded so exterior framing could be installed

Architect Design Change

$297300

BPO B5901601 Change Order 20

PCO 338

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1359 Rl - added stainless steel saddle flash fully soldered water tight and integrated into the wall waterproofing

Architect Design Change

$78700

PCO 391

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope work work per ASI 061 - added soffit to conceal fume hood supports and added lighting to accommodate the space where the soffit was added

Architect Design Change

$817700

PCO 418

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1495 Rl - remove horizontal HSS and plates at sunshade posts at levels 2 and 3 - gridline 2-D as they conflict with the window systems

Architect Design Change

$225800

PCO 474

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 997 Rl relocated rebar for equipment pad at building 2 roof that was in conflict with screen wall

Field Condition

$205500

PCO 483

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1129 - relocate door in room 3205 and reroute electrical feed due to pump equipment pad locations

Field Condition

$346300

BPO 85901601 Change Order 20

Contract time will be adjusted as follows Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $387362300

0 Calendar Days Extension (zero unless Amount of This Change Order $31570600 otherwise indicated)

Contract Amount $13026805600 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA _14~ Oakland CA 94612

UNILATERAL

~~~ lt -23 - I I Name Date Name Date

Architect ~ Cannon Design 202 Green Street San Francisco CA 94111

L A - Dlgitally signed by Carey WOO 7 W fV Date 20190520

ia_ ~ailelampgt-1~-11e~rooJe------ ---D-a-te___ ~ END OF DOCUMENT

BPO 85901601 Change Order 20

Page 2: OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

PCO 251

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1116 - schedule 10 piping not allowed per submitted 123 comments only schedule 40 to be used

Architect Design Change

$5660100

PCO 263

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 71 -commissioning agent comment to modify ductwork in building 1 restrooms 1306 and 1308

Architect Design Change

$1210800

PCO 268

Requested By

Performed By

Reason

Backcharge to the contractor for design teams assistance with additional submittal reviews nursery research and tagging of the substitution trees

Architect Design Change

($482500)

PCO 313

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1021 - fire piping new structural attachment at approximately 1045 locations

Architect Design Change

$24013700

PCO 352

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 076 -New air compressor added compressed air piping to spray booth and added acoustical caulking and firestopping

District Change

$2756200

PCO 375

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 83 -additional chemical water treatment for the geothermal bore field piping

Architect Design Change

$1432200

PCO 463

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per RFI 461 -added reinforcing at details 2S430 and 1S433

Architect Design Change

$155600

PCO 464

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 540 - added reinforcing at wall penetrations in the CUP

Architect Design Change

$139900

PCO 465

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per changes made to reinforcing in submittals 220 and 221 (partial CCD 40) where grade beams intersect with concrete walls

Architect Design Change

$268800

PCO 466

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 547Rl - added reinforcing at building 1 level 1 wall penetrations

Architect Design Change

$287600

BPO 85901601 Change Order 19

PCO 467 Provide all labor material and equipment to complete the scope of work per response $619000 to RFI 815 - added HRC 670 T-heads on all boundary vertical reinforcing at building 1 CUP wall along gridline G

Requested By

Performed By

Reason Architect Design Change

PCO 468 Provide all labor material and equipment to complete the scope of work per response $230000 to RFI 920 - new block out and reinforcing at new storm drain pipe at south site wall at building 1

Requested By

Performed By

Reason Architect Design Change

PCO 472 Provide all labor material and equipment to complete the scope of work per response $131400 to RFI 1032 - added rebar at footing to accommodate revisions due to electrical conduit conflict

Requested By

Performed By

Reason Architect Design Change

Contract time will be adjusted as follows

Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $334102300

0 Calendar Days Extension (zero unless Amount of This Change Order $53260000 otherwise indicated)

Contract Amount $12995235000 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA __3 Oakland CA 94612

UNILATERAL

~~~-Name DateName

Architect

Cannon Design 202 Green Street San Francisco CA 94111

Digitally signed by Carey Woo Dale 2019 05 20 112009-0700

Name Date

END OF DOCUMENT

BPO B5901601 Change Order 19

OHLONE CO L LECE

Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

CHANGE ORDER (UNILATERAL) Project

BPO No

6105A -Academic Core Building

85901601

Date

DSA File No

582019

1-Cl

The following parties agree to the terms of this Change Order DSA Appl No 01-114438

Owner Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

Contractor Balfour Beatty Construction 2335 Broadway Suite 300 Oakland CA 94612

Architect Cannon Design 202 Green Street San Francisco CA 94111

Reference Description Cost Days Ext

PCO 113

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 299Rl - added drywall at the CUP level of elevator 1B to achieve the necessary 2hr wall rating

Architect Design Change

$520900

PCO 148

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to ASI 31 which deleted a large work bench with 3 power monuments but added two typical student work stations with power monuments (2 each - 4 total) gas and vacuum

District Change

$802000

PCO 164

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 032 -Added mechanical duct work and electrical infrastructure to accommodate the new video walls at both the medium and large tiered classrooms

District Change

$17825600

PCO 264

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 72Rl and response to RFI 1482 The flooring was revised from carpet to polished concrete in the corridor from gridline 2-1 to 2-7 cabinetry was added in the sculpture area as well as the glazing room the pottery wheel space was reconfigured the electrical was revised to all the electric kilns and retractable lighting was added in the sculpture area venting was added for the kilns a sink was added in the glazing room and the masonry wing walls were removed

District Change

$10450800

PCO 299

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1450 angle brace conflicted with exterior wall at bldg 2 lvl 2 and needed to be cut back and re-welded so exterior framing could be installed

Architect Design Change

$297300

BPO B5901601 Change Order 20

PCO 338

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1359 Rl - added stainless steel saddle flash fully soldered water tight and integrated into the wall waterproofing

Architect Design Change

$78700

PCO 391

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope work work per ASI 061 - added soffit to conceal fume hood supports and added lighting to accommodate the space where the soffit was added

Architect Design Change

$817700

PCO 418

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1495 Rl - remove horizontal HSS and plates at sunshade posts at levels 2 and 3 - gridline 2-D as they conflict with the window systems

Architect Design Change

$225800

PCO 474

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 997 Rl relocated rebar for equipment pad at building 2 roof that was in conflict with screen wall

Field Condition

$205500

PCO 483

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1129 - relocate door in room 3205 and reroute electrical feed due to pump equipment pad locations

Field Condition

$346300

BPO 85901601 Change Order 20

Contract time will be adjusted as follows Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $387362300

0 Calendar Days Extension (zero unless Amount of This Change Order $31570600 otherwise indicated)

Contract Amount $13026805600 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA _14~ Oakland CA 94612

UNILATERAL

~~~ lt -23 - I I Name Date Name Date

Architect ~ Cannon Design 202 Green Street San Francisco CA 94111

L A - Dlgitally signed by Carey WOO 7 W fV Date 20190520

ia_ ~ailelampgt-1~-11e~rooJe------ ---D-a-te___ ~ END OF DOCUMENT

BPO 85901601 Change Order 20

Page 3: OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

PCO 467 Provide all labor material and equipment to complete the scope of work per response $619000 to RFI 815 - added HRC 670 T-heads on all boundary vertical reinforcing at building 1 CUP wall along gridline G

Requested By

Performed By

Reason Architect Design Change

PCO 468 Provide all labor material and equipment to complete the scope of work per response $230000 to RFI 920 - new block out and reinforcing at new storm drain pipe at south site wall at building 1

Requested By

Performed By

Reason Architect Design Change

PCO 472 Provide all labor material and equipment to complete the scope of work per response $131400 to RFI 1032 - added rebar at footing to accommodate revisions due to electrical conduit conflict

Requested By

Performed By

Reason Architect Design Change

Contract time will be adjusted as follows

Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $334102300

0 Calendar Days Extension (zero unless Amount of This Change Order $53260000 otherwise indicated)

Contract Amount $12995235000 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA __3 Oakland CA 94612

UNILATERAL

~~~-Name DateName

Architect

Cannon Design 202 Green Street San Francisco CA 94111

Digitally signed by Carey Woo Dale 2019 05 20 112009-0700

Name Date

END OF DOCUMENT

BPO B5901601 Change Order 19

OHLONE CO L LECE

Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

CHANGE ORDER (UNILATERAL) Project

BPO No

6105A -Academic Core Building

85901601

Date

DSA File No

582019

1-Cl

The following parties agree to the terms of this Change Order DSA Appl No 01-114438

Owner Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

Contractor Balfour Beatty Construction 2335 Broadway Suite 300 Oakland CA 94612

Architect Cannon Design 202 Green Street San Francisco CA 94111

Reference Description Cost Days Ext

PCO 113

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 299Rl - added drywall at the CUP level of elevator 1B to achieve the necessary 2hr wall rating

Architect Design Change

$520900

PCO 148

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to ASI 31 which deleted a large work bench with 3 power monuments but added two typical student work stations with power monuments (2 each - 4 total) gas and vacuum

District Change

$802000

PCO 164

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 032 -Added mechanical duct work and electrical infrastructure to accommodate the new video walls at both the medium and large tiered classrooms

District Change

$17825600

PCO 264

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 72Rl and response to RFI 1482 The flooring was revised from carpet to polished concrete in the corridor from gridline 2-1 to 2-7 cabinetry was added in the sculpture area as well as the glazing room the pottery wheel space was reconfigured the electrical was revised to all the electric kilns and retractable lighting was added in the sculpture area venting was added for the kilns a sink was added in the glazing room and the masonry wing walls were removed

District Change

$10450800

PCO 299

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1450 angle brace conflicted with exterior wall at bldg 2 lvl 2 and needed to be cut back and re-welded so exterior framing could be installed

Architect Design Change

$297300

BPO B5901601 Change Order 20

PCO 338

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1359 Rl - added stainless steel saddle flash fully soldered water tight and integrated into the wall waterproofing

Architect Design Change

$78700

PCO 391

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope work work per ASI 061 - added soffit to conceal fume hood supports and added lighting to accommodate the space where the soffit was added

Architect Design Change

$817700

PCO 418

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1495 Rl - remove horizontal HSS and plates at sunshade posts at levels 2 and 3 - gridline 2-D as they conflict with the window systems

Architect Design Change

$225800

PCO 474

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 997 Rl relocated rebar for equipment pad at building 2 roof that was in conflict with screen wall

Field Condition

$205500

PCO 483

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1129 - relocate door in room 3205 and reroute electrical feed due to pump equipment pad locations

Field Condition

$346300

BPO 85901601 Change Order 20

Contract time will be adjusted as follows Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $387362300

0 Calendar Days Extension (zero unless Amount of This Change Order $31570600 otherwise indicated)

Contract Amount $13026805600 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA _14~ Oakland CA 94612

UNILATERAL

~~~ lt -23 - I I Name Date Name Date

Architect ~ Cannon Design 202 Green Street San Francisco CA 94111

L A - Dlgitally signed by Carey WOO 7 W fV Date 20190520

ia_ ~ailelampgt-1~-11e~rooJe------ ---D-a-te___ ~ END OF DOCUMENT

BPO 85901601 Change Order 20

Page 4: OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

OHLONE CO L LECE

Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

CHANGE ORDER (UNILATERAL) Project

BPO No

6105A -Academic Core Building

85901601

Date

DSA File No

582019

1-Cl

The following parties agree to the terms of this Change Order DSA Appl No 01-114438

Owner Ohlone Community College District 43600 Mission Boulevard Fremont CA 94539

Contractor Balfour Beatty Construction 2335 Broadway Suite 300 Oakland CA 94612

Architect Cannon Design 202 Green Street San Francisco CA 94111

Reference Description Cost Days Ext

PCO 113

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 299Rl - added drywall at the CUP level of elevator 1B to achieve the necessary 2hr wall rating

Architect Design Change

$520900

PCO 148

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to ASI 31 which deleted a large work bench with 3 power monuments but added two typical student work stations with power monuments (2 each - 4 total) gas and vacuum

District Change

$802000

PCO 164

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 032 -Added mechanical duct work and electrical infrastructure to accommodate the new video walls at both the medium and large tiered classrooms

District Change

$17825600

PCO 264

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per ASI 72Rl and response to RFI 1482 The flooring was revised from carpet to polished concrete in the corridor from gridline 2-1 to 2-7 cabinetry was added in the sculpture area as well as the glazing room the pottery wheel space was reconfigured the electrical was revised to all the electric kilns and retractable lighting was added in the sculpture area venting was added for the kilns a sink was added in the glazing room and the masonry wing walls were removed

District Change

$10450800

PCO 299

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1450 angle brace conflicted with exterior wall at bldg 2 lvl 2 and needed to be cut back and re-welded so exterior framing could be installed

Architect Design Change

$297300

BPO B5901601 Change Order 20

PCO 338

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1359 Rl - added stainless steel saddle flash fully soldered water tight and integrated into the wall waterproofing

Architect Design Change

$78700

PCO 391

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope work work per ASI 061 - added soffit to conceal fume hood supports and added lighting to accommodate the space where the soffit was added

Architect Design Change

$817700

PCO 418

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1495 Rl - remove horizontal HSS and plates at sunshade posts at levels 2 and 3 - gridline 2-D as they conflict with the window systems

Architect Design Change

$225800

PCO 474

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 997 Rl relocated rebar for equipment pad at building 2 roof that was in conflict with screen wall

Field Condition

$205500

PCO 483

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1129 - relocate door in room 3205 and reroute electrical feed due to pump equipment pad locations

Field Condition

$346300

BPO 85901601 Change Order 20

Contract time will be adjusted as follows Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $387362300

0 Calendar Days Extension (zero unless Amount of This Change Order $31570600 otherwise indicated)

Contract Amount $13026805600 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA _14~ Oakland CA 94612

UNILATERAL

~~~ lt -23 - I I Name Date Name Date

Architect ~ Cannon Design 202 Green Street San Francisco CA 94111

L A - Dlgitally signed by Carey WOO 7 W fV Date 20190520

ia_ ~ailelampgt-1~-11e~rooJe------ ---D-a-te___ ~ END OF DOCUMENT

BPO 85901601 Change Order 20

Page 5: OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

PCO 338

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1359 Rl - added stainless steel saddle flash fully soldered water tight and integrated into the wall waterproofing

Architect Design Change

$78700

PCO 391

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope work work per ASI 061 - added soffit to conceal fume hood supports and added lighting to accommodate the space where the soffit was added

Architect Design Change

$817700

PCO 418

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1495 Rl - remove horizontal HSS and plates at sunshade posts at levels 2 and 3 - gridline 2-D as they conflict with the window systems

Architect Design Change

$225800

PCO 474

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 997 Rl relocated rebar for equipment pad at building 2 roof that was in conflict with screen wall

Field Condition

$205500

PCO 483

Requested By

Performed By

Reason

Provide all labor material and equipment to complete the scope of work per response to RFI 1129 - relocate door in room 3205 and reroute electrical feed due to pump equipment pad locations

Field Condition

$346300

BPO 85901601 Change Order 20

Contract time will be adjusted as follows Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $387362300

0 Calendar Days Extension (zero unless Amount of This Change Order $31570600 otherwise indicated)

Contract Amount $13026805600 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA _14~ Oakland CA 94612

UNILATERAL

~~~ lt -23 - I I Name Date Name Date

Architect ~ Cannon Design 202 Green Street San Francisco CA 94111

L A - Dlgitally signed by Carey WOO 7 W fV Date 20190520

ia_ ~ailelampgt-1~-11e~rooJe------ ---D-a-te___ ~ END OF DOCUMENT

BPO 85901601 Change Order 20

Page 6: OHLONE€¦ · Balfour Beatty Construction 2335 Broadway, Suite 300 Oakland CA 94612 : Architect: Cannon Design 202 Green Street San Francisco CA 94111 : Reference ; Description :

Contract time will be adjusted as follows Original Contract Amount $12607872700

Previous Completion Date 1082018 Amount of Previously Approved Change Order(s) $387362300

0 Calendar Days Extension (zero unless Amount of This Change Order $31570600 otherwise indicated)

Contract Amount $13026805600 Current Completion Date 1082018

The undersigned Contractor approves the foregoing as to the changes if any to the Contract Price specified for each item and as to the extension of time allowed if any for completion of the entire work as stated therein and agrees to furnish all labor materials and services and perform all work necessary to complete any additional work specified for the consideration stated therein Submission of sums which have no basis in fact or which Contractor knows are false are at the sole risk of Contractor and may be in violation of the False Claims Act set forth under Government Code section 12650 et seq

This change order is subject to approval by the governing board of this District and must be signed by the District Until such time as this change order is approved by the Districts governing board and executed by a duly authorized District representativethis change order is not effective and not binding

It is expressly understood that the compensation and time if any granted herein represent a full accord and satisfaction for any and all time and cost impacts of the items herein and Contractor waives any and all further compensation or time extension based on the items herein The value of the extra work or changes expressly includes any and all of the Contractors costs and expenses both direct and indirect resulting from additional time required on the project or resulting from delay to the project Any costs expenses damages or time extensions not included are deemed waived

This unilateral change order shall not constitute a waiver by the District of any right or remedy under the Contract THE DISTRICT HEREBY RESERVES ALL RIGHTS AND REMEDIES UNDER THE CONTRACT IN LAW OR IN EQUITY

Signatures

District Contractor

Ohlone Community College District Balfour Beatty Construction 43600 Mission Boulevard 2335 Broadway Suite 300 Fremont CA _14~ Oakland CA 94612

UNILATERAL

~~~ lt -23 - I I Name Date Name Date

Architect ~ Cannon Design 202 Green Street San Francisco CA 94111

L A - Dlgitally signed by Carey WOO 7 W fV Date 20190520

ia_ ~ailelampgt-1~-11e~rooJe------ ---D-a-te___ ~ END OF DOCUMENT

BPO 85901601 Change Order 20