ONLINE EOT PROCESSING – WORK FLOW
Contractor submits EOT proposal to
EE
EE evaluates proposal
Does the Proposal need modification?
Modifies Proposal
Submit Proposal to
SE
SE evaluates proposal
Modify Proposal
Submit Proposal to
CE
Modify Proposal
Modify Proposal
Update Proposal in Portal and
submit to SLSC
Coordinate Proposal approval between SLSC and Govt.
CE updates Portal with Final EOT Date once
approved by Govt.
YES
YES
YESYES
Offline Processing Online Processing
NO
Does the Proposal need modification?
NO
NO
Does the Proposal need modification?
Submit Proposal to CE
NO
Does the Proposal need modification?
Contractor Role
LEGEND
Enter User ID and Password obtained
from SE/EE
Login Page in the PPMS Portal
Portal Address:http://
irrigation.ap.gov.in/ppms/jsp/login/
login.jsp
First Page after Login for Contractor
Click on the Tab for EOT Proposal
Submission
Link for downloading the Excel formats of EOT proposal to be
filled
Page on clicking EOT Status
Select relevant Project from dropdown menu for uploading proposal
Select the relevant Package for uploading
Proposal
EOT Status page view of selected Package
Keep this unchecked till all files are finally uploaded & ready for final submission. After submission with this box checked, contractor will not be able to make any
edits
Input the proposed EOT date
Input remarks, if any
Click Submit/Update
Page view on Submitting EOT date
Select the relevant Package
Select the relevant Project
Click View to see EOT Status of Package and
Upload Files
EOT Status page for uploading filled in Formats
Click to Upload the filled Excel Files
Proposed EOT date visible
Draft Status to continue till all files
are uploaded correctly
Page view for Uploading filled in Formats
Select the relevant Package
Select the relevant Project
Click to select the relevant File to upload
Browse to select the relevant filled in excel file
Page view for Uploading filled in Formats
Sample Selected Details for Uploading Click Submit after
attaching the file above
Confirmation of File Upload
Similarly, upload all 8 files for the EOT Proposal
Page view for Uploading filled in Formats
Page for Viewing Uploaded Project Status File
All columns need to be filled in with
appropriate details
Page for Viewing Uploaded Bottleneck Report file
All columns need to be filled in with
appropriate details
All columns need to be filled in with
appropriate details
Page for Viewing Uploaded Schedule of Drawings file
Page for Viewing Uploaded Schedule of Land Plan file
All columns need to be filled in with
appropriate details
Page for Viewing Uploaded Schedule of Manpower file
All columns need to be filled in with
appropriate details
Page for Viewing Uploaded Schedule of Materials file
All columns need to be filled in with
appropriate details
Page for Viewing Uploaded Schedule of P&M file
All columns need to be filled in with
appropriate details
Page for Final Submission
After uploading all correct files, check
the final submission
tickbox
Once the OK is clicked, it is considered the final submission. After Final
submission, no change can be made and the proposal
is with the Department for processing.
On Final Submission by Contractor,
Status changes to “Reviewed and
Submitted to EE”
EOT Status Page after Final submission by Contractor