658

Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

Embed Size (px)

Citation preview

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    1/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    2/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    3/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    4/726

    Table of Contents

    Prefaceyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    18&/($532:(53/$17618&/($532:(55($&725)$&,/,7,(6,17+(5(6($5&+$1''(9(/230(1767$*(

    OVERVIEW OF NUCLEAR POWER PLANTSyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Status of Operation, Construction and Decommissioning of Nuclear Power Plants

    Status of Operation and Construction of Nuclear Power Plantsyyyyyyyyyyyyyyy

    Nuclear Power Plant Site Map (as of the End of FY2009)yyyyyyyyyyyyyyyyyyy

    Dates When Nuclear Power Plants Attained the First Criticality and

    Became Synchronized to the Electric Gridyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Installed Capacity of Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1Trends in the Licensed Output of Nuclear Power Plants that

    Supply General Electric Enterprises with Electricityyyyyyyyyyyyyyyy

    Table -2Trends in the Electric Energy Produced by Different Power Generating

    Sources at the End of Fiscal Years (Public Power Supply Industry)yyyy

    Table -3Trends in the Annual Electric Energy Generated

    (Public Power Supply Industry)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    STATUS OF OPERATION OF NUCLEAR POWER PLANTSyyyyyyyyyyyyyyyyyy

    General Situationyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-1 Capacity factor of nuclear power stations

    for the electric power industry in FY 2009yyyyyyyyyyyyyyyyyyyyyTable -1-2 BWR plants in shutdown with relatively large degree of influence

    on capacity factoryyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-3 PWR plants in shutdown with relatively large degree of influence

    on capacity factoryyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1 Past Operation Recordsyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Figure -1Trend in the Capacity Factor by Reactor Typeyyyyyyyyyyyyyyyyyyyy

    Table -2 Trends in Periodical Inspection Duration (Average Excluding GCR)yyy

    Table -3 Trends in Operating Period (Average Excluding GCR)yyyyyyyyyyyyy

    Table -4 Breakdowns of Output Lossyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -5 Circumstances of Reactor Shutdowns in FY2009yyyyyyyyyyyyyyyyyy

    Table -6 Trends in the Frequency of Nuclear Reactor Shutdownsyyyyyyyyyyyy

    Table -7 Trends in the Frequency of Nuclear Reactor Shutdownsyyyyyyyyyyyy

    Table -8 Operating Records by Nuclear Power Plant in FY2009yyyyyyyyyyyyy

    Table -9 Operating Records by Unit in FY2009yyyyyyyyyyyyyyyyyyyyyyyyyy

    Capacity Factoryyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -10Trends in Capacity Factoryyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -11Trends in the Capacity Factor of Each Electric Power Companyyyyyyy

    Table -12Capacity Factor by Unit (by Month in FY2009)yyyyyyyyyyyyyyyyyyy

    Table -13Trends in the Capacity Factor of Each Unityyyyyyyyyyyyyyyyyyyyyy

    1

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    5/726

    Operation Factoryyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -14Trends in Operation Factoryyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -15Trends in Operation Factor of Each Electric Power Companyyyyyyyyy

    Table -16Operation Factor by Unit (by Month in FY2009)yyyyyyyyyyyyyyyyyy

    Table -17Trends in the Operation Factor of Each Unityyyyyyyyyyyyyyyyyyyyy

    Electric Energy Generatedyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -18Trends in Electric Energy Generatedyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -19Trends in the Electric Energy Generated by Each Electric Power

    Companyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -20Electric Energy Generated by Unit (by Month in FY2009)yyyyyyyyyy

    Table -21Trends in the Electric Energy Generated by Each Unityyyyyyyyyyyyy

    Generating Timeyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -22Trends in Generating Timeyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -23Trends in Generating Time by Each Electric Power Companyyyyyyyy

    Table -24Generating Time by Unit (by Month in FY2009)yyyyyyyyyyyyyyyyyy

    Table -25Trends in Generating Time of Each Unityyyyyyyyyyyyyyyyyyyyyyyy

    Power History of Each Unityyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    STATUS OF PERIODICAL INSPECTIONS OF NUCLEAR POWER PLANTSyyy

    Overview of Periodical Inspections of Nuclear Power Plantsyyyyyyyyyyyyyyy

    Periodical Inspections by Unityyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    STATUS OF PERIODICAL SAFETY MANAGEMENT REVIEWSOF NUCLEAR POWER PLANTSyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Outline of Periodical Safety Management Reviews of Nuclear Power Plantsyy

    Status of Periodical Safety Management Reviews of Nuclear Power Plantsyyy

    STATUS OF SAFETY INSPECTION FOR NUCLEAR POWER PLANTSyyyyyyy

    General Information on Safety Inspection for Nuclear Power Plantsyyyyyyyy

    Circumstances of Safety Inspections by Nuclear Power Plantyyyyyyyyyyyyyy

    STATUS OF APPROVALS AND INSPECTIONS FOR CONSTRUCTION PLANSAND FUEL ASSEMBLY DESIGNS OF NUCLEAR POWER PLANTSyyyyyyyyyy

    Status of Approvals and Inspections for Construction Plans and

    Fuel Assembly Designs of Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyyyyy

    Approval of Construction Plans for Commercial Power Reactorsyyyyyyyyyyyy

    Approvals for Fuel Assembly Designs Concerning Commercial Reactorsyyyyy

    OPERATIONAL PLANS FOR NUCLEAR POWER PLANTSyyyyyyyyyyyyyyyyy

    Table -1 FY2010 Operational Planyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Figure -1Diagram of FY2010 Reactor Shutdown Scheduleyyyyyyyyyyyyyyyyy

    2

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    6/726

    STATUS OF OPERATIONAL MANAGEMENT OF NUCLEAR POWER PLANTS

    Operational Management at Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyyy

    Education and Training of Operation Staffyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-1 Examples of Long-term Operator Development PlansyyyyyyyyyyyTable -2-2 Outline of Operator Training Centers in Japan (BTC)yyyyyyyyyyy

    Table -2-3 Outline of Operator Training Centers in Japan (NTC)yyyyyyyyyyy

    Table -2-4 Outline of Training Courses at BWR Operator Training Centeryyy

    Table -2-5 Outline of Training Courses at the Nuclear Power Training

    Center Ltd.yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-6 Training Results at the BWR Operator Training Centeryyyyyyyyy

    Table -2-7 Training Results at the Nuclear Power Training Center Ltd.yyyyyy

    Figure -2-1 Training Results at the BWR Operator Training Centeryyyyyyyyy

    Figure -2-2 Training Results at the Nuclear Power Training Center Ltd.yyyyyy

    Education and Training for Maintenance Staffyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -3-1 Maintenance Staff Development Pattern (Example 1)yyyyyyyyyyy

    Table -3-2 Maintenance Staff Development Pattern (Example 2)yyyyyyyyyyy

    Table -3-3 Outline of Maintenance Training Facilitiesyyyyyyyyyyyyyyyyyyy

    5(),1,1*18&/($5)8(/)$%5,&$7,2163(17)8(/6725$*(5(352&(66,1*$1'5$',2$&7,9(:$67(',6326$/)$&,/,7,(6

    LISTS OF REFINING, NUCLEAR FUEL FABRICATION,SPENT FUEL STORAGE, REPROCESSING AND RADIOACTIVE WASTE

    DISPOSAL FACILITIESyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Operation and Construction Status of Refining, Nuclear Fuel Fabrication,

    Spent Fuel Storage, Reprocessing and Radioactive Waste Disposal Facilitiesy

    List of Operation and Construction Status of Fabrication Facilitiesyyyyyyyyy

    List of Operation and Construction Status of Reprocessing Facilitiesyyyyyyyy

    List of Operation and Construction Status of Disposal Facilitiesyyyyyyyyyyyy

    Location Map of Nuclear Fuel Fabrication, Reprocessing and Radioactive

    Waste Disposal Facilitiesyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    STATUS OF OPERATION OF REFINING, NUCLEAR FUEL FABRICATION,

    SPENT FUEL STORAGE, REPROCESSING AND RADIOACTIVE WASTE

    DISPOSAL FACILITIES, AND TRANSPORT CONFIRMATION RESULTS

    OF NUCLEAR FUEL MATERIALyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Status of Operation of Refining, Nuclear Fuel Fabrication,

    Spent Fuel Storage, Reprocessing and Radioactive Waste Disposal Facilitiesy

    Table -1Trends in Maximum Nuclear Fuel Material Capacity at

    Fabrication Facilities at the End of Fiscal Yearsyyyyyyyyyyyyyyyyyy

    Table -2Trends in Maximum Nuclear Fuel Material Capacity at FabricationFacilities (Conversion Processing) at the End of Fiscal Yearsyyyyyyyy

    3

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    7/726

    Table -3Trends in Maximum Nuclear Fuel Material Capacity at Fabrication

    Facilities (Uranium Enrichment) at the End of Fiscal Yearsyyyyyyyyy

    Table -4Trends of Reprocessing Amounts by Fiscal Yearyyyyyyyyyyyyyyyyyyy

    Table -5Trends in the Amount of Radioactive Waste Buried and Managed

    at Waste Disposal Facilitiesyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Transport Confirmation Results of Nuclear Fuel Materialyyyyyyyyyyyyyyyyy

    STATUS OF PERIODICAL FACILITY INSPECTIONS AT NUCLEAR

    FUEL FABRICATION, SPENT FUEL STORAGE, REPROCESSING

    AND RADIOACTIVE WASTE DISPOSAL FACILITIESyyyyyyyyyyyyyyyyyyyyy

    Outline of Periodical Facility Inspections at Nuclear Fuel Fabrication,

    Spent Fuel Storage, Reprocessing and Radioactive Waste Disposal Facilitiesyy

    Status of Periodical Facility Inspections by Plantyyyyyyyyyyyyyyyyyyyyyyy

    STATUS OF NUCLEAR FUEL SAFETY INSPECTIONS AT REFINING,NUCLEAR FUEL FABRICATION, SPENT FUEL STORAGE,

    REPROCESSING AND RADIOACTIVE WASTE DISPOSAL FACILITIESyyyyyy

    Status of Safety Inspections at Refining, Nuclear Fuel Fabrication,

    Spent Fuel Storage, Reprocessing and Radioactive Waste Disposal Facilitiesyy

    Status of Safety Inspections by Plantyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    STATUS OF APPROVAL AND INSPECTION OF DESIGN AND

    CONSTRUCTION METHODS AT NUCLEAR FUEL FABRICATION,

    SPENT FUEL STORAGE, REPROCESSING AND RADIOACTIVEWASTE DISPOSAL FACILITIESyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Status of Approval and Inspection of Design and Construction Methods

    at Nuclear Fuel Fabrication, Spent Fuel Storage, Reprocessing and

    Radioactive Waste Disposal Facilitiesyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Approvals of Design and Construction Methodsyyyyyyyyyyyyyyyyyyyyyyyyy

    $&&,'(17

    STATUS OF ACCIDENTyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy Overview of Accidents at Nuclear Power Plants in FY2009

    (Excluding Power Reactors in the Research and Development Stage)yyyy

    Table -1-1 Trends in the Number of Reported Accidents

    at Nuclear Power Plants

    Figure -1-1Trends in the Number of Reported Accidents at Nuclear Power

    Plants and the Average Number of Accidents per Reactor Unityyy

    Figure -1-2Trends in the Number of Reported Accidents at Nuclear Power

    Plants by Accident Type

    Accidents at Nuclear Power Plants to be Reportedyyyyyyyyyyyyyyyyyyy Analysis of Accidents at Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyyy

    4

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    8/726

    Table -1-2 Trends in the Number of Accidents at Nuclear Power Plants

    by the Number of Years Elapsed after the Start of Operationyyyyy

    Figure -1-3Trends in the Number of Accidents at Nuclear Power Plants

    by the Number of Years Elapsed after the Start of Operationyyyyy

    Table -1-3 Accidents at Nuclear Power Plants by Fiscal Year

    (Automatic Shutdown)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-4 Accidents at Nuclear Power Plants by Fiscal Year

    (Manual Shutdown)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-5 Accidents at Nuclear Power Plants by Fiscal Year

    (During Shutdowns such as Periodical Inspections)yyyyyyyyyyyy

    Table -1-6 Accidents at Nuclear Power Plants by Fiscal Year

    (Output Fluctuation)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-7 Accidents at Nuclear Power Plants by Fiscal Year

    (Component Damage during Operation)yyyyyyyyyyyyyyyyyyyy

    Table -1-8 Accidents at Nuclear Power Plants by Fiscal Year (Others)yyyyyy

    Table -1-9 Systems of Component involved in Accident

    in Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-10Components involved in Accident in Nuclear Power Plantsyyyyyy

    Table -1-11Causes of Accident in Nuclear Power Plantsyyyyyyyyyyyyyyyyyy

    Table -1-12Operational Status When Accident Occurred

    in Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -1-13How Accident detected in Nuclear Power Plantsyyyyyyyyyyyyyyy

    Numbers of Reported Accidents in Nuclear Power Plantsyyyyyyyyyyyyy

    Overview of Accidents at Nuclear Power Plantsyyyyyyyyyyyyyyyyyyyyy

    Press Releases on Accidents at Nuclear Power Plantsyyyyyyyyyyyyyyyy Overview of Accidents at Nuclear Power Reactors

    in the Research and Development Stage in FY2009yyyyyyyyyyyyyyyyyy

    Table -2-1 Trends in the Number of Reported Accidents at Nuclear Power

    Reactors in a Research and Development Stage

    Figure -2-1Trends in the Number of Reported Accidents at Nuclear Power

    Reactors in the Research and Development Stage

    Figure -2-2Trends in the Number of Reported Accidents at Nuclear Power

    Reactors in the Research and Development Stage

    by Accident Type

    Accidents Reported at Nuclear Power Reactors in the Research andDevelopment Stageyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-2 Accidents in Nuclear Power Reactors in the Research and

    Development Stage by Fiscal Year (Automatic Shutdown)yyyyyyyy

    Table -2-3 Accidents in Nuclear Power Reactors in the Research and

    Development Stage by Fiscal Year (Manual Shutdown)yyyyyyyyyy

    Table -2-4 Accidents in Nuclear Power Reactors in the Research and

    Development Stage by Fiscal Year (When Not in Operation

    for an Inspection or Other Reason)yyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-5 Accidents in Nuclear Power Reactors in the Research and

    Development Stage by Fiscal Year (Others)yyyyyyyyyyyyyyyyyyy

    5

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    9/726

    Table -2-6Systems of Component Involved in Accident in Nuclear Power

    Reactors in the Research and Development Stageyyyyyyyyyyyyyy

    Table -2-7Component Involved in Accident in Nuclear Power Reactors

    in the Research and Development Stageyyyyyyyyyyyyyyyyyyyyyy

    Table -2-8Causes of Accident in Nuclear Power Reactors in the Research

    and Development Stageyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-9Operational Status When Accidents Occurred in Nuclear Power

    Reactors in the Research and Development Stageyyyyyyyyyyyyyy

    Table-2-10How Accidents Detected in Nuclear Power Reactorsin the Research and Development Stageyyyyyyyyyyyyyyyyyyyyyy

    Numbers of Reported Accidents in Nuclear Power Reactors

    in the Research and Development Stage

    Overview of Accidents in Nuclear Power Reactors

    in the Research and Development Stage

    Press Releases on Accidents in Nuclear Power Reactors

    in the Research and Development Stage

    Overview of Accidents at Nuclear Fuel Fabrication, Reprocessing,

    Radioactive Waste Disposal and Waste Management Facilities in FY2009y

    Table -3-1Trends in the Number of Reported Accidents at Nuclear Fuel

    Fabrication, Reprocessing, Radioactive Waste Disposal

    and Waste Management Facilitiesyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Accidents Reported at Nuclear Fuel Fabrication, Reprocessing,

    Radioactive Waste Disposal and Waste Management Facilitiesyyyyyyyyy

    Overview of Accidents at Nuclear Fuel Fabrication, Reprocessing,

    Radioactive Waste Disposal and Waste Management Facilitiesyyyyyyyyy Press Releases on Accidents at Nuclear Fuel Fabrication, Reprocessing,

    Radioactive Waste Disposal and Waste Management Facilitiesyyyyyyyyy

    EVALUATION OF EVENTSyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Outline of International Nuclear Event Scale (INES)yyyyyyyyyyyyyyyyyyyy

    Table -1-1 The International Nuclear Event Scaleyyyyyyyyyyyyyyyyyyyyyyy-2 Outline of Event Rating in FY2009yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-1 Events at Nuclear Power Plants Evaluated in FY2009

    (Events in FY2008)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-2 Events at Nuclear Power Plants Evaluated in FY2009

    (Events in FY2008)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-3 Events at Nuclear Power Plants Evaluated in FY2010

    (Events in FY2009)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    Table -2-4 Events at Nuclear Power Plant in the Research and

    Development Stage Evaluated in FY2010 (Events in FY2009) yyyy

    Table -2-5 Events at Reprocessing Facilities Evaluated in FY2010

    (Evens in FY2009)yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    -3 Press Release Documents Related to the International Nuclear Event Scale(INES) for Accidents at Nuclear Facilitiesyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    6

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    10/726

    5$',2$&7,9(:$67(0$1$*(0(17$1'2&&83$7,21$/5$',$7,21(;32685(0$1$*(0(17

    RADIOACTIVE WASTE MANAGEMENT AND OCCUPATIONAL RADIATION

    EXPOSURE MANAGEMENTyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy

    -1 Status of Radioactive Waste Management yyyyyyyyyyyyyyyyyyyyyyyyyyyy-2 Status of Occupational Radiation Exposure Management yyyyyyyyyyyyyyy-3 ISOE: Information System on Occupational Exposureyyyyyyyyyyyyyyyyyyyy

    6$)(7

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    11/726

    Preface

    This document is a summary of the outline of the safety regulation

    administration of nuclear facilities as well as various data on the commercial

    nuclear power reactor facilities, research and development nuclear power

    reactor facilities, fabrication facilities, reprocessing facilities, and disposal

    facilities in fiscal year 2009 (from April 2009 to March 2010). We sincerely

    hope this document is used widely by many people engaged in work related

    to ensuring nuclear safety.

    November 2010

    Technology and Information General Office

    Policy Planning and Coordination Division

    Japan Nuclear Energy Safety Organization

    Independent Administrative Agency

    9

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    12/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    13/726

    -1 Status of Operation, Construction and Decommissioning of

    Nuclear Power Plants

    (1) Commercial power reactor facilities

    As of the end of FY2009, the number of units in operation at nuclearelectric power plants were 54 with their total output 48,847,000 kW.Hamaoka Nuclear Power Station, Units 1 (540,000 kW: BWR) and

    2 (840,000 kW: BWR) were legally closed on January 30, 2009 and havebeen in the decommissioning stage since FY2009

    The Japan Atomic Power Company's Tokai Power Station (166,000 kW:GCR) discontinued commercial operations at the end of FY1997 and hasbeen in the decommissioning stage since FY2001.

    As of the end of FY2009

    Total

    OperatingNumber of units

    Output (10,000 kW)

    Underconstruction

    Number of units

    Output (10,000 kW)

    Preparing forconstruction

    Number of units

    Output (10,000 kW)

    Beingdecommissioned

    Number of units

    Output (10,000 kW)

    (2) Nuclear power reactor facilities in the research and development stage

    As of the end of FY2009

    prototypereactor

    prototypereactor

    Total

    Underconstruction

    Number of units

    Output (10,000 kW)

    Beingdecommissioned

    Number of units

    Output (10,000 kW)

    13

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    14/726

    -2 Status of Operation and Construction of Nuclear Power Plants(1) Commercial power reactor facilities

    Name of establisherName of power stations

    (facility number)Address Reactor type

    The Japan Atomic Power

    Company Co., Ltd.

    Tokai Daini Power Station

    Tsuruga Power Station Unit 1

    Tsuruga Power Station Unit 2

    Tokai Village, Naka County, Ibaraki Prefecture

    Tsuruga City, Fukui Prefecture

    Tsuruga City, Fukui Prefecture

    BWR

    BWR

    PWR

    Hokkaido Electric Power Co.,

    Inc.

    Tomari Power Station Unit 1

    Tomari Power Station Unit 2

    Tomari Power Station Unit 3

    Tomari Village, Furuu County, Hokkaido

    Tomari Village, Furuu County, Hokkaido

    Tomari Village, Furuu County, Hokkaido

    PWR

    PWR

    PWR

    Tohoku Electric Power

    Co., Inc.

    Onagawa Nuclear Power Station Unit 1

    Onagawa Nuclear Power Station Unit 2

    Onagawa Nuclear Power Station Unit 3

    Higashidori Nuclear Power Station Unit 1

    Onagawa Town Oshika County and Ishinomaki City, Miyagi Prefecture

    Onagawa Town Oshika County and Ishinomaki City, Miyagi Prefecture

    Onagawa Town Oshika County and Ishinomaki City, Miyagi Prefecture

    Higashidori Village ,Shimokita County, Aomori Prefecture

    BWR

    BWR

    BWR

    BWR

    Tokyo Electric Power

    Co., Inc.

    Fukushima Daiichi Nuclear Power Station Unit 1

    Fukushima Daiichi Nuclear Power Station Unit 2

    Fukushima Daiichi Nuclear Power Station Unit 3

    Fukushima Daiichi Nuclear Power Station Unit 4

    Fukushima Daiichi Nuclear Power Station Unit 5

    Fukushima Daiichi Nuclear Power Station Unit 6

    Fukushima Daini Nuclear Power Station Unit 1

    Fukushima Daini Nuclear Power Station Unit 2

    Fukushima Daini Nuclear Power Station Unit 3

    Fukushima Daini Nuclear Power Station Unit 4

    Kashiwazaki-Kariwa Nuclear Power Station Unit 1

    Kashiwazaki-Kariwa Nuclear Power Station Unit 2

    Kashiwazaki-Kariwa Nuclear Power Station Unit 3

    Kashiwazaki-Kariwa Nuclear Power Station Unit 4

    Kashiwazaki-Kariwa Nuclear Power Station Unit 5

    Kashiwazaki-Kariwa Nuclear Power Station Unit 6

    Kashiwazaki-Kariwa Nuclear Power Station Unit 7

    Futaba Town and Okuma Town , Futaba County, Fukushima Prefecture

    Futaba Town and Okuma Town , Futaba County, Fukushima Prefecture

    Futaba Town and Okuma Town , Futaba County, Fukushima Prefecture

    Futaba Town and Okuma Town , Futaba County, Fukushima Prefecture

    Futaba Town and Okuma Town , Futaba County, Fukushima Prefecture

    Futaba Town and Okuma Town , Futaba County, Fukushima Prefecture

    Naraha Town and Tomioka Town, Futaba County, Fukushima Prefecture

    Naraha Town and Tomioka Town, Futaba County, Fukushima Prefecture

    Naraha Town and Tomioka Town, Futaba County, Fukushima Prefecture

    Naraha Town and Tomioka Town, Futaba County, Fukushima Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    Kariwa Village, Kariwa County, and Kashiwazaki City, Niigata Prefecture

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    BWR

    ABWR

    ABWR

    Chubu Electric PowerCo., Inc.

    Hamaoka Nuclear Power Station Unit 3

    Hamaoka Nuclear Power Station Unit 4

    Hamaoka Nuclear Power Station Unit 5

    Sakura, Omaezaki City, Shizuoka Prefecture

    Sakura, Omaezaki City, Shizuoka Prefecture

    Sakura, Omaezaki City, Shizuoka Prefecture

    BWR

    BWR

    ABWR

    Hokuriku Electric Power Co.Shika Nuclear Power Station Unit 1

    Shika Nuclear Power Station Unit 2

    Shika Town, Hakui County, Ishikawa Prefecture

    Shika Town, Hakui County, Ishikawa Prefecture

    BWR

    ABWR

    Kansai Electric Power

    Co., Inc.

    Mihama Power Station Unit 1

    Mihama Power Station Unit 2

    Mihama Power Station Unit 3

    Takahama Power Station Unit 1

    Takahama Power Station Unit 2

    Takahama Power Station Unit 3

    Takahama Power Station Unit 4

    Ohi Power Station Unit 1

    Ohi Power Station Unit 2Ohi Power Station Unit 3

    Ohi Power Station Unit 4

    Mihama Town, Mikata County, Fukui Prefecture

    Mihama Town, Mikata County, Fukui Prefecture

    Mihama Town, Mikata County, Fukui Prefecture

    Takahama Town, Ohi County, Fukui Prefecture

    Takahama Town, Ohi County, Fukui Prefecture

    Takahama Town, Ohi County, Fukui Prefecture

    Takahama Town, Ohi County, Fukui Prefecture

    Ohi Town, Ohi County, Fukui Prefecture

    Ohi Town, Ohi County, Fukui PrefectureOhi Town, Ohi County, Fukui Prefecture

    Ohi Town, Ohi County, Fukui Prefecture

    PWR

    PWR

    PWR

    PWR

    PWR

    PWR

    PWR

    PWR

    PWRPWR

    PWR

    Chugoku Electric Power

    Co., Inc.

    Shimane Nuclear Power Station Unit 1

    Shimane Nuclear Power Station Unit 2

    Kashimacho, Matsue City, Shimane Prefecture

    Kashimacho, Matsue City, Shimane Prefecture

    BWR

    BWR

    Shikoku Electric Power

    Co., Inc.

    Ikata Power Station Unit 1

    Ikata Power Station Unit 2

    Ikata Power Station Unit 3

    Ikata Town, Nishiuwa County, Ehime Prefecture

    Ikata Town, Nishiuwa County, Ehime Prefecture

    Ikata Town, Nishiuwa County, Ehime Prefecture

    PWR

    PWR

    PWR

    Kyushu Electric Power

    Co., Inc.

    Genkai Nuclear Power Station Unit 1

    Genkai Nuclear Power Station Unit 2

    Genkai Nuclear Power Station Unit 3

    Genkai Nuclear Power Station Unit 4

    Sendai Nuclear Power Station Unit 1

    Sendai Nuclear Power Station Unit 2

    Genkai Town, Higashimatsura County, Saga Prefecture

    Genkai Town, Higashimatsura County, Saga Prefecture

    Genkai Town, Higashimatsura County, Saga Prefecture

    Genkai Town, Higashimatsura County, Saga Prefecture

    Satsumasendai City, Kagoshima Prefecture

    Satsumasendai City, Kagoshima Prefecture

    PWR

    PWR

    PWR

    PWR

    PWR

    PWR

    Ope

    rating

    Subtotal (54 units)

    Continued over

    14

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    15/726

    As of the end of FY2009

    Licensed output

    (10,000 kW)

    Date of authorization by the Electric

    Power Development Coordination

    Council

    Date of the establishment

    license issue

    Date of the construction start

    (see note 2)

    Date of the commercial

    operation

    110.0

    35.7

    116.0

    1972- 1

    1965- 6

    1979- 1

    1972-12-23

    1966- 4-22

    1982- 1-26

    1973- 4

    1967- 2

    1982- 3

    1978-11-28

    1970- 3-14

    1987- 2-17

    57.9

    57.9

    91.2

    1982- 4

    1982- 4

    2000-11

    1984- 6-14

    1984- 6-14

    2003- 7- 2

    1984- 8

    1984- 8

    2003-11

    1989- 6-22

    1991- 4-12

    2009-12-22

    52.4

    82.5

    82.5

    110.0

    1970- 6

    1987- 4

    1994- 3

    1996-7

    1970-12-10

    1989- 2-28

    1996- 4-12

    1998-8-31

    1971- 5

    1989- 6

    1996- 9

    1998-12

    1984- 6- 1

    1995- 7-28

    2002- 1-30

    2005-12-8

    46.0

    78.4

    78.4

    78.4

    78.4

    110.0

    110.0

    110.0

    110.0

    110.0

    110.0

    110.0

    110.0

    110.0

    110.0

    135.6

    135.6

    1966- 4

    1968- 1

    1969- 7

    1971- 7

    1971- 3

    1972- 1

    1972- 7

    1975- 3

    1977- 3

    1978- 7

    1974- 8

    1981- 4

    1985- 4

    1985- 4

    1981- 4

    1988- 4

    1988- 4

    1966-12- 1

    1968- 3-29

    1970- 1-23

    1972- 1-13

    1971- 9-23

    1972-12-12

    1974- 4-30

    1978- 6-26

    1980- 8- 4

    1980- 8- 4

    1977- 9- 1

    1983- 5- 6

    1987- 4- 9

    1987- 4- 9

    1983- 5- 6

    1991- 5-15

    1991- 5-15

    1967- 9

    1969- 5

    1970-10

    1972- 5

    1971-12

    1973- 3

    1975- 8

    1979- 1

    1980-11

    1980-11

    1978-11

    1983- 8

    1987- 6

    1987- 6

    1983- 8

    1991- 8

    1991- 8

    1971- 3-26

    1974- 7-18

    1976- 3-27

    1978-10-12

    1978- 4-18

    1979-10-24

    1982- 4-20

    1984- 2- 3

    1985- 6-21

    1987- 8-25

    1985- 9-18

    1990- 9-28

    1993- 8-11

    1994- 8-11

    1990- 4-10

    1996-11- 7

    1997- 7- 2

    110.0

    113.7

    126.7

    1978-11

    1986-11

    1997- 4

    1981-11-16

    1988- 8-10

    1998-12-25

    1982- 6

    1988-10

    1999- 3

    1987- 8-28

    1993- 9- 3

    2005- 1-18

    54.0

    120.6

    1987- 1

    1997-4

    1988- 8-22

    1999-4-14

    1988-11

    1999-8

    1993- 7-30

    2006-3-15

    34.0

    50.0

    82.6

    82.6

    82.6

    87.0

    87.0

    117.5

    117.5118.0

    118.0

    1966- 4

    1968- 1

    1971- 7

    1969- 7

    1970- 6

    1978- 3

    1978- 3

    1970-11

    1970-111985- 2

    1985- 2

    1966-12- 1

    1968- 5-10

    1972- 3-13

    1969-12-12

    1970-11-25

    1980- 8- 4

    1980- 8- 4

    1972- 7- 4

    1972- 7- 41987- 2-10

    1987- 2-10

    1967- 8

    1968-12

    1972- 7

    1970- 4

    1971- 2

    1980-11

    1980-11

    1972-10

    1972-111987- 3

    1987- 3

    1970-11-28

    1972- 7-25

    1976-12- 1

    1974-11-14

    1975-11-14

    1985- 1-17

    1985- 6- 5

    1979- 3-27

    1979-12- 51991-12-18

    1993- 2- 2

    46.0

    82.0

    1969- 7

    1981- 4

    1969-11-13

    1983- 9-22

    1970- 2

    1984- 2

    1974- 3-29

    1989- 2-10

    56.6

    56.6

    89.0

    1972- 3

    1975- 3

    1983- 4

    1972-11-29

    1977- 3-30

    1986- 5-26

    1973- 4

    1977-12

    1986- 8

    1977- 9-30

    1982- 3-19

    1994-12-15

    55.9

    55.9

    118.0

    118.0

    89.0

    89.0

    1970- 6

    1974- 8

    1982-10

    1982-10

    1976- 3

    1978- 7

    1970-12-10

    1976- 1-23

    1984-10-12

    1984-10-12

    1977-12-17

    1980-12-22

    1971- 3

    1976- 5

    1985- 3

    1985- 3

    1978-11

    1981- 3

    1975-10-15

    1981- 3-30

    1994- 3-18

    1997- 7-25

    1984- 7- 4

    1985-11-284,884.7

    15

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    16/726

    Name of establisherName of power stations

    (facility number)Address Reactor type

    Chugoku Electric Power Co.,Inc.

    Shimane Nuclear Power Station Unit 3 Kashimacho, Matsue City, Shimane Prefecture ABWR

    Electric Power DevelopmentCo., Ltd.

    Ohma Nuclear Power StationOhma Town, Shimokita County, AomoriPrefecture

    ABWRUnder construction

    Subtotal (2 units)

    The Japan Atomic PowerCompany Co., Ltd.

    Tsuruga Power Station

    Tsuruga Power Station

    Unit 3

    Unit 4

    Tsuruga City, Fukui Prefecture

    Tsuruga City, Fukui Prefecture

    APWR

    APWR

    Namie-Odaka Nuclear PowerStation

    Namie Town, Futaba County, and Odaka Town,Soma County, Fukushima Prefecture

    BWRTohoku Electric Power Co.,Inc.

    Higashidori Nuclear Power Station Unit 2Higashidoori Village, Shimokita County, AomoriPrefecture

    ABWR

    Fukushima Daiichi Nuclear PowerStation

    Unit 7Okuma Town, Futaba County, FukushimaPrefecture

    ABWR

    Fukushima Daiichi Nuclear PowerStation

    Unit 8Okuma Town, Futaba County, FukushimaPrefecture

    ABWR

    Higashidori Nuclear Power Station Unit 1Higashidoori Village, Shimokita County, AomoriPrefecture

    ABWR

    Tokyo Electric Power Co., Inc.

    Higashidori Nuclear Power Station Unit 2Higashidoori Village, Shimokita County, Aomori

    PrefectureABWR

    Chubu Electric Power Co., Inc. Hamaoka Nuclear Power Station Unit 6 Sakura, Omaezaki City, Shizuoka Prefecture ABWR

    Kaminoseki Nuclear Power Station Unit 1Kaminoseki Town, Kumage County, YamaguchiPrefecture

    ABWRChugoku Electric Power Co.,Inc.

    Kaminoseki Nuclear Power Station Unit 2Kaminoseki Town, Kumage County, YamaguchiPrefecture

    ABWR

    Kyushu Electric Power Co., Inc. Sendai Nuclear Power Station Unit 3 Satsumasendai City, Kagoshima Prefecture APWR

    Preparing for construction

    Subtotal (12 units)

    Hamaoka Nuclear Power Station Unit 1 Sakura, Omaezaki City, Shizuoka Prefecture BWRChubu Electric Power Co., Inc.

    Hamaoka Nuclear Power Station Unit 2 Sakura, Omaezaki City, Shizuoka Prefecture BWR

    The Japan Atomic PowerCompany Co., Ltd.

    Tokai Power Station Tokai Village, Naka County, Ibaraki Prefecture GCR

    Being decommissioned

    Subtotal (3 units)

    (2) Nuclear power reactor facilities in the research and development stage

    Name of establisher Name of power station Address Reactor type

    Under constructionMonju Prototype Fast Breeder

    ReactorTsuruga City, FukuiPrefecture

    FBR(prototype reactor)

    Beingdecommissioned

    Japan Atomic EnergyAgency

    Fugen Decommissioning

    Engineering CenterTsuruga City, FukuiPrefecture

    ATR(prototype reactor)

    16

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    17/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    18/726

    -3 Nuclear Power Plant Site Map (as of the end of FY2009)

    Kanazawa

    FukuiMatsue

    Yamaguchi

    Kagoshima

    Matsuyama

    Shika Nuclear Power Station,Hokuriku Electric Power Co.Unit 1 and 2 (operating

    Tsuruga Power Station, Japan Atomic Power Company Co., Ltd.

    Units 1 and 2 (operating), Units 3 and 4 (preparing forconstruction)

    Japan Atomic Energy AgencyFugen Decommissioning Engineering Center(being decommissioned )

    Japan Atomic Energy Agency

    Monju (under construction)

    Mihama Power Station,Kansai Electric Power Co., Inc.

    Units 1, 2 and 3 (operating)

    Ohi Power Station, Kansai ElectricPower Co., Inc.Units 1, 2, 3 and 4 (operating)

    Takahama Power Station, KansaiElectric Power Co., Inc.Units 1, 2, 3 and 4 (operating)

    Shimane Nuclear Power Station, ChugokuElectric Power Co., Inc. Units 1 and 2(operating), Unit 3 (under construction)

    Kaminoseki Nuclear Power Station,Chugoku Electric Power Co., Inc.Units 1 and 2 (preparing forconstruction)

    Ikata Power Station, ShikokuElectric Power Co., Inc.Units 1, 2 and 3 (operating)

    Genkai Nuclear Power Station,Kyushu Electric Power Co., Inc.Units 1, 2, 3 and 4 (operating)

    Sendai Nuclear Power Station,Kyushu Electric Power Co., Inc.

    Units 1 and 2 (operating)Units 3 (preparing for construction)

    Saga

    18

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    19/726

    Sapporo

    Aomori

    Sendai

    Fukushima

    Tokyo

    Niigata

    Mito

    Shizuoka

    Tomari Power Station, HokkaidoElectric Power Co., Inc.

    Units 1, 2 and 3 (operating)

    Fukushima Daini Nuclear Power Station,

    Tokyo Electric Power Co., Inc.Units 1, 2, 3 and 4 (operating)

    Japan Atomic Power Company Co., Ltd.Tokai Power Station(being decommissioned)

    Tokai Daini Power Station (operating)

    Hamaoka Nuclear Power Station,Chubu Electric Power Co., Inc.Units 3, 4 and 5 (operating)

    Units 6 (preparing for construction)

    Units 1 and 2 (being decommissioned)

    Fukushima Daiichi Nuclear Power Station,Tokyo Electric Power Co., Inc.Units 1, 2, 3, 4, 5 and 6 (operating)Units 7 and 8 (preparing for construction)

    Onagawa Nuclear Power Station,Tohoku Electric Power Co., Inc.Units 1, 2 and 3 (operating)

    Higashidori Nuclear Power Station, Tohoku ElectricPower Co., Inc.Unit 1 (operating), Unit 2 (preparing for construction)

    Ohma Nuclear Power Station, ElectricPower Development Co., Ltd.(under construction )

    Kashiwazaki-Kariwa Nuclear Power Station, TokyoElectric Co., Inc.

    Units 1, 2, 3, 4, 5, 6 and 7 (operating)

    Higashidori Nuclear Power Station TokyoElectric Power Co., Inc.Units 1 and 2 (preparing for construction)

    Namie-Odaka Nuclear Power Station (preparing forconstruction), Tohoku Electric Power Co., Inc.

    19

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    20/726

    I-4 Dates When Nuclear Power Plants Attained the First

    Criticality and Became Synchronized to the Electric GridUnit names

    Licensed

    output

    (10,000 kW)

    Date of first

    fuel loading

    Date of initial

    criticality

    Date of grid

    connection

    Date of initial

    commercial

    operation

    Tokai Daini

    Tsuruga Unit 1

    Tsuruga Unit 2

    Tomari Unit 1

    Tomari Unit 2

    Tomari Unit 3

    Onagawa Unit 1

    Onagawa Unit 2

    Onagawa Unit 3

    Higashidori Unit 1

    Fukushima Daiichi Unit 1

    Fukushima Daiichi Unit 2

    Fukushima Daiichi Unit 3

    Fukushima Daiichi Unit 4

    Fukushima Daiichi Unit 5

    Fukushima Daiichi Unit 6

    Fukushima Daini Unit 1

    Fukushima Daini Unit 2

    Fukushima Daini Unit 3

    Fukushima Daini Unit 4

    Kashiwazaki- Kariwa Unit 1

    Kashiwazaki- Kariwa Unit 2

    Kashiwazaki- Kariwa Unit 3

    Kashiwazaki- Kariwa Unit 4

    Kashiwazaki- Kariwa Unit 5

    Kashiwazaki- Kariwa Unit 6

    Kashiwazaki- Kariwa Unit 7

    20

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    21/726

    Unit namesLicensed output

    (10,000 kW)

    Date of first

    fuel loading

    Date of initial

    criticality

    Date of grid

    connection

    Date of initial

    commercial

    operation

    Hamaoka Unit 11

    Hamaoka Unit 21

    Hamaoka Unit 3

    Hamaoka Unit 4

    Hamaoka Unit 5

    Shika Unit 1

    Shika Unit 2

    Mihama Unit 1

    Mihama Unit 2

    Mihama Unit 3

    Takahama Unit 1

    Takahama Unit 2

    Takahama Unit 3

    Takahama Unit 4

    Ohi Unit 1

    Ohi Unit 2

    Ohi Unit 3

    Ohi Unit 4

    Shimane Unit 1

    Shimane Unit 2

    Ikata Unit 1

    Ikata Unit 2

    Ikata Unit 3

    Genkai Unit 1

    Genkai Unit 2

    Genkai Unit 3

    Genkai Unit 4

    Sendai Unit 1

    Sendai Unit 2

    Fugen

    21

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    22/726

    -5 Installed Capacity of Nuclear Power Plants

    Japan's nuclear electric power plants have an installed capacity of 54units and 48,847,000 kW as of the end of FY2009, as shown in Table I-1.The number of units accounts for 20.2% of all power generating facilitiesoperated to supply general electricity, while the electric energy generated

    accounts for 29.3% of the total electric energy produced annually.

    22

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    23/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    24/726

    24

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    25/726

    STATUS OF OPERATION OF NUCLEAR

    POWER PLANTS

    25

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    26/726

    -1 General situation

    At the end of FY2009, the capacity factor of nuclear power stations for electric power industry in Japan was

    65.7% on average for all nuclear power stations in operation (54 units with a total power generating capacity of

    48,847,000 kW).

    Table -1-1: Capacity factor of nuclear power stations for the electric power industry in FY2009

    Boiling water reactor(BWR)

    Pressurized waterreactor (PWR)

    Total

    Number of units 30 24 54

    Power (10 MW) 2,856.9 2,027.8 4,884.7

    Capacity factor (%) 55.5 80.6 65.7

    Looking at the operational status of plants in Japan in FY2009, the total capacity factor was 65.7%, exceeding the

    60.0% of the previous year.

    Considering reactor types, the capacity factor of BWRs was 55.5%, exceeding the 51.1% of the previous year. The

    major cause of this rise was increased power generation due to resumption of Kashiwazaki Nuclear Power Station

    Units 6 and 7, and Shika Nuclear Power Station Unit 1.The capacity factor of PWRs was 80.6%, exceeding the 73.7% of the previous year. The major cause of this rise

    was increased power generation due to operation at rated thermal output, even although the hourly operating rate

    fell under the planned value.

    Table -1-2: BWR plants in shutdown with relatively large degrees of influence on capacity factor

    Shutdown period (days)Degree of influence in

    FY2009Plant

    Licensedpower(MW) Periodical

    inspectionTrouble

    Externalfactor

    Others Total% of allBWRs

    % of total

    Kashiwazaki-Kariwa Unit 1 1100 365 365 3.9% 2.3%Kashiwazaki-Kariwa Unit 2 1100 365 365 3.9% 2.3%

    Kashiwazaki-Kariwa Unit 3 1100 365 365 3.9% 2.3%

    Kashiwazaki-Kariwa Unit 4 1100 365 365 3.9% 2.3%

    Kashiwazaki-Kariwa Unit 5 1100 365 365 3.9% 2.3%

    Kashiwazaki-Kariwa Unit 6 1356 153 14 167 2.2% 1.3%

    Hamaoka Unit 5 1267 17 88 216 321 3.9% 2.3%

    Shika Unit 2 1206 108 80 188 2.2% 1.3%

    Tokai Daini 1100 205 34 239 2.5% 1.5%

    Table -1-3: PWR plants in shutdown with relatively large degrees of influence on capacity factor

    Shutdown period (days)Degree of influence in

    FY2009Plant

    Licensed

    power(MW) Periodical

    inspectionTrouble

    External

    factorOthers Total % of all PWRs % of total

    Ohi Unit 1 1175 114 54 168 2.8% 1.1%

    Degree of influence: percentage of power generation loss of a plant in available power generating capacity(licensed power calendar time) by type of reactor or in total available power generatingcapacity

    27

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    27/726

    The capacity factor, operation factor, generated power, etc. of nuclear power stations in Japan are summarized

    in the following pages.

    Please note that generated power is expressed by using the output at the generating end (gross).

    Notes on the use of these tables are as follows; unless otherwise stated, commissioning before the start of

    commercial operation is not included.

    (1) Capacity factor = (%)100(h)imecalendar t(MW)powerLicensed

    (MWh)powerGeneratedu

    u

    (Note) In case of constant rated thermal power operation, capacity factor may exceed 100%.

    (2) Operation factor

    c Operation factor of unit

    Operation factor (%) = 100)h(imeCalendar t

    )h(timeGenerationu

    d Operation factor (average Operation factor) by station, by power company, and totalAverage operation factor is power divided proportionally.

    Average Operation factor (%) = 100

    ])h(imecalendar t)MW(power[licensed

    ])h(timegeneration)MW(power[licensed

    1

    1 u

    u

    u

    N

    n

    N

    n

    N: Number of units

    (3) Reactor year =(h)yearoneofimeCalendar t(h)reactoroftimeOperating

    Operating time of reactor is the time between the startup and shutdown of the reactor.

    (4) The electric power generation and generation time in the fiscal year and month of startup are counted from

    00:00 am on the commercial operation starting date.

    (5) The capacity factor and operation factor in the fiscal year and month of startup are counted according to

    calendar time from the commercial operation starting date.

    (6) The total and subtotal by licensee and the sum total after startup are the summation of generated power

    (minimum unit is MWh) and time (minimum unit is hour before FY1995, and minute after FY1996) for

    each fiscal year and each unit.

    (7) The Japan Atomic Power Company, Tokai Power Station finished commercial operation at the end of

    FY1997 and has been in the decommissioning stage.

    (8) Chubu Electric Power Company, Hamaoka Nuclear Power Station, Units 1 and 2 were legally closed on

    January 30, 2009.

    (9) The licensed power generation of Japan Atomic Power Company, Tsuruga Power Station, Unit 1 was

    changed from 331 MW to 357 MW on December 15, 1970.

    (10) The licensed power generation of Chubu Electric Power Company, Hamaoka Nuclear Power Station, Unit 5

    was changed from 1,380 MW to 1,267 MW on March 13, 2007.

    (11) The licensed power generation of Hokuriku Electric Power Company, Shika Nuclear Power Station, Unit 2was changed from 1,358 MW to 1,206 MW on June 5, 2008.

    (12) The following are the Total or Grand Total in table II-1, 8 to 11, 13 to 15, 17 to 19, 21 to 23, 25 as the Total

    from the commercial operation starting date. It is not indicate the total of numbers in the table.

    28

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    28/726

    FY Capacity Factor Operation FactorGenerated

    power

    Generation

    time

    Reactor

    operation

    (%) (%) (million kWh) (hr) time (hr)

    2000 81.7 82.1 321,337 358,688 361,110

    2001 80.5 80.9 317,539 359,541 361,900

    2002 73.4 73.2 294,073 336,822 338,533

    2003 59.7 59.0 240,013 275,388 277,796

    2004 68.9 68.4 277,857 307,308 310,883

    2005 71.9 71.4 299,163 327,921 331,538

    2006 69.9 69.3 303,426 330,082 333,212

    2007 60.7 60.3 263,832 294,513 297,527

    2008 60.0 59.4 258,071 290,077 292,873

    2009 65.7 65.0 277,470 314,102 317,669

    Total 72.0 72.7 7,119,569 8,697,809 8,788,725

    Table -1: Past Operational Records

    Figure -1: Trend in the Capacity Factor by Reactor Type

    20

    40

    60

    80

    100

    2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

    CapacityFactor(%)

    0

    1,000

    2,000

    3,000

    4,000

    5,000

    6,000

    7,000

    8,000

    9,000

    10,000

    Licensedpow

    er

    Total BWR PWR

    (Note) values of each FY.

    (10 MW)

    29

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    29/726

    30

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    30/726

    31

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    31/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    32/726

    Fiscal Year

    33

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    33/726

    34

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    34/726

    35

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    35/726

    36

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    36/726

    (Unit:)

    37

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    37/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    38/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    39/726

    40

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    40/726

    41

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    41/726

    42

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    42/726

    43

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    43/726

    44

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    44/726

    45

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    45/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    46/726

    47

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    47/726

    48

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    48/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    49/726

    50

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    50/726

    51

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    51/726

    52

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    52/726

    53

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    53/726

    54

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    54/726

    55

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    55/726

    56

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    56/726

    57

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    57/726

    58

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    58/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    59/726

    60

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    60/726

    61

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    61/726

    62

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    62/726

    63

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    63/726

    64

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    64/726

    65

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    65/726

    66

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    66/726

    67

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    67/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    68/726

    (2) Tsuruga Power Station Unit 1

    FY2005

    12 31 27 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    22 30 16 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    1 26 7 31 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    15 1 16 31 7 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    10 8Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Control rod pattern adjustmentControl rod patternalteration

    Confirmation ofcontrol rod integrity

    Power drop due to inspection of reactor

    feedwater pump A and auxiliary oil

    pump of reactor feedwater pump C

    Power drop due

    to commissioning

    of reactor

    feedwater pump

    A and switchover

    of reactor

    feedwater pump

    30th periodical

    inspection

    Coast down operation

    %100

    50

    0

    Control rod patternadjustment

    31stperiodical

    inspectionPower drop to repair thecondenser sea water leaking place

    Power stopped to replace

    mechanical seals on B reactorcoolant recirculation pump

    Control rod pattern adjustment

    Power down dueto large quantity of

    ellyfish

    %100

    50

    0

    31st periodicalinspection

    Control rod patternadjustment

    Power stopped to replacemechanical seals on A and C

    reactor coolant recirculation pumps

    %100

    50

    0

    Power stoppedto replacemechanicalseals on A andC reactorrecirculation

    pumps

    Control rod pattern

    adjustment

    Power stopped toreplace mechanicalseals on B and Creactor

    recirculation

    pumps

    Power drop due to inspection of the mechanicalseal on the coupling side of the reactorreplenishment water pump (A) and the

    mechanical seal on the auxiliary oil pump of thereactor feedwater pump (C)

    Coast down operation

    32nd periodical inspection

    %100

    50

    0

    32nd periodical inspection

    Control rod patternadjustment

    69

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    69/726

    (3) Tsuruga Power Station Unit 2

    FY2005 * * * * * * * * * * *

    9 3 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2006 * * * * * *

    23 30 1 13 5 24 22 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2007

    * * *

    26 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2008

    8 16 15 13Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2009

    * * * * * * * * * *

    21Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    %100

    50

    0

    Shutdown to inspect and

    repair boric acid leak in thecontainment

    Isolated operation with power for

    plant operation due to powertransmission line accident

    %100

    50

    0

    15th periodical

    inspectionPower generation stoppedto repair water level

    control of deaeration pump

    Power generationstopped toinspect and

    repair the coolingwater cooler forthe standby

    reactor

    %100

    50

    0

    Power drop to repair the damagedequipment due to marine organisms

    16th periodical inspection

    %100

    50

    0

    16th periodical inspectionPower generation stopped due to crackedwelded section of the radial pin on the firsthigh-pressure turbine blade ring

    %100

    50

    0

    17thperiodical

    inspection

    70

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    70/726

    (4) Tomari Power Station Unit 1FY2005

    * * * * * * * * *

    26 16 14Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2006 * * * * * * * * * * * *

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2007

    * * * * * * * * *

    13 10 5 20 30 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2008

    * * * * * * *

    4 16 15Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    FY2009

    * * * * * * * * *

    11 18Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    %100

    50

    0

    %100

    50

    0

    PCCS stop

    %100

    50

    0

    14th periodicalinspection

    Stop due to failure to operate the

    emergency diesel generator

    %100

    50

    0

    15th periodical inspection

    %100

    50

    0

    16th periodicalinspection

    13th periodical

    inspection

    71

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    71/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    72/726

    (6) Tomari Power Station Unit 3FY2009

    * * *

    22Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    * Stem-free test for each turbine valve

    %100

    50

    0

    (Commercial

    operationstarted)

    73

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    73/726

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    74/726

    (8) Onagawa Nuclear Power Station Unit 2

    FY2005

    30 28 16 19 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    11 16 13 9 21 15 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    11 30 27Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    26Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    27 22 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    7th periodical

    inspectionReactor automatically shut

    down due to earthquake Control rod patternadjustment

    Control rodoperation check

    %100

    50

    0

    8th periodical inspectionIntermediate

    shutdown

    Control rod pattern adjustment

    Inspection of shaft seal

    portion of reactor

    recirculation pump

    %100

    50

    0

    9th periodical inspection

    %100

    50

    0

    Coast down operation

    10th periodicalinspection

    Control rod pattern adjustment

    %100

    50

    0

    10th periodical inspection

    75

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    75/726

    (9) Onagawa Nuclear Power Station Unit 3

    FY2005

    16 27 23Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    18 7 25 7 25Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    10 10 23 25Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    26 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    1 23 1 18 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    3rd periodical inspection

    Reactorautomaticallyshut down due

    to earthquake

    %100

    50

    0

    Intermediate shutdownIntermediate

    shutdown3rdperiodical

    in

    spection

    %100

    50

    0

    Power drop due to a survey conducted toinvestigate the cause of the increase inradioactive material concentration on the

    gaseous radioactive waste treatment system

    4th periodical inspection

    Manual reactor emergency shutdown due to increase of hydrogenconcentration in gaseous waste

    treatment system

    Power drop due to a survey conducted to investigate

    the cause of the increase in the reading on thegaseous waste processing system radiation monitor

    %100

    50

    0

    Control rod pattern adjustment

    5th periodical inspection

    %100

    50

    0

    5th periodical inspection

    Power down to inspect the waterlevel adjustment valve of the2nd low-pressure feedwater

    heater (A)

    76

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    76/726

    (10) Higashidori Nuclear Power Station Unit 1

    FY2005

    8 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    7 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    9 6 22Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    18 13 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    12 7 7 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Controlrod

    operationcheck

    %100

    50

    0

    1st periodical inspection

    Power drop dueto low air

    Control rod pattern adjustment

    %100

    50

    0

    1stperiodicalinspection

    Control rod pattern adjustment

    2nd periodicalinspection

    (Commercial

    operationstarted)

    %100

    50

    0

    2nd periodical inspection

    Control rod pattern adjustment

    %100

    50

    0

    Coast down operation

    3rd periodical inspection

    Control rod pattern adjustment

    77

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    77/726

    (11) Fukushima Daiichi Nuclear Power Station Unit 1

    FY2005

    13 15 24 12 28 30

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    28 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    3 5 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    17 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    18 20 25Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    23rd periodical inspection

    Intermediate shutdown tocheck major plant facilities Intermediate shutdown

    to check spring waterfrom basement of

    turbine building

    %100

    50

    0

    Control rod pattern adjustment

    Generator output suppression to check

    tubes of condensers A1, A2 24th periodical inspection

    %100

    50

    24th periodical inspection

    %100

    50

    0

    25th periodical inspection

    Control rod patternadjustment

    %100

    50

    0

    25thperiodical

    inspection

    Generator outputsuppression to check tubesof condensers A1, A2

    26th periodicalinspection

    Control rod pattern adjustment

    78

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    78/726

    (12) Fukushima Daiichi Nuclear Power Station Unit 2

    FY2005

    18 4 4 10 12 20Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    20 4 28 1Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    12 21 12Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    21 20 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    22 21 19 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Reactor manually shutdown due to trippingof reactor coolantrecirculation pump (B)

    Outputsuppression to

    repaircondenser (B)

    Contro

    lrodpattern

    adjustm

    ent

    Power down forcontrol rod operation

    confirmation testReactor manually shutdown due to tripping of

    reactor coolantrecirculation pump (A)

    %100

    50

    0

    Reactor manuallyshut down due totripping of reactorcoolantrecirculation pump(A)

    %100

    50

    0

    Intermediate shutdown to repair the seawater flow control valve of the residual

    heat removal system 2

    3rdperiodical

    inspection

    21st periodicalinspection

    22nd periodical inspection

    %100

    50

    0

    23rdperiodicalinspection

    Control rod pattern adjustment

    %100

    50

    0

    24th periodical inspectionDrop in output due toinspection of the maincondenser

    79

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    79/726

    (13) Fukushima Daiichi Nuclear Power Station Unit 3

    FY2005

    11 22Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    29 7 10 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    15 2 31 14 24 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    24 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    10 8 13 28 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Power drop for control rod patternadjustment and verification test of

    control rod operations

    Control rod patternadjustment

    Intermediateshutdown dueto trouble withmechanicalseals onreactor coolantrecirculationpump (B)

    %100

    50

    0

    21st periodical

    inspection

    Output suppression to

    check cleaning system ofcondenser

    Intermediateshutdown due

    to troublewithmechanical

    seals onreactorcoolantrecirculation

    pump (B)

    %100

    50

    0

    Generator outputsuppression to checkcleaning system ofcondenser

    Intermediate shutdown due to

    leak from the outlet pipe drainof the turbine gland seal steamevaporator

    Con

    trolrodpattern

    adju

    stment

    Generator outputsuppression to identifyleaked fuel

    22nd periodical inspection

    20th periodical

    inspection

    %100

    50

    0

    23rdperiodicalinspection

    Control rod pattern adjustment

    %100

    50

    0

    23rd periodical inspection

    Intermediate shutdown to inspectthe electrically-powered valve inthe high-pressure injectionsystem

    80

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    80/726

    21stperiodicalinspection

    (14) Fukushima Daiichi Nuclear Power Station Unit 4

    FY2005

    5 25 3 13 3Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    7 22 2 3 11Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    2 1 28Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    17 5 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    29 30 8 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Intermediate

    shutdown due to

    leak from feedwater heater room

    20th periodical inspectionIntermediate shutdown due to

    leaking weld on a sample tube at

    the entrance of the condensatebooster pump

    Power drop due to removingscaffolding for an on-site checkof decreased vacuum in the

    condenser

    %100

    50

    0

    Intermediateshutdown to replace

    leaking fuel Output suppression to checkcleaning system of condenser

    Intermediate shutdown to

    remove attached materialon transmission line

    20thperiodical

    in

    spection

    %100

    50

    0

    21stperiodicalinspection

    Generator outputsuppression toidentify leaked fuel

    Control rod pattern adjustmentOutput control due tothermal limit deviationpreventive operation

    Coast down operation

    22n

    dperiodical

    insp

    ection

    Control rod pattern adjustment

    Control rod pattern adjustment

    %100

    50

    0

    22nd periodical inspection

    Control rod pattern adjustment

    %100

    50

    0

    Control rod pattern adjustment

    23rd periodicalinspection

    81

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    81/726

    (15) Fukushima Daiichi Nuclear Power Station Unit 5

    FY2005

    10 21 23 10

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    31 13 27 20 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    26 20 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    22 1 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    1 2 3 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    %100

    50

    0

    21st periodical inspection

    Coast down operationReactor

    manually shutdown due totrouble inminimum flowvolume bypassvalve of core

    spray system(A)

    %100

    50

    0

    Manual reactor shutdown due to troubleof minimum flow volume bypass valve

    of core spray system (A)

    Control rod pattern adjustment

    22nd periodicalinspection

    Control rod patternadjustment

    Control rod patternadjustment

    %100

    50

    0

    22nd periodical inspection

    Output suppressed to repair thefeedwater heater water leveladjustment valve

    20th periodicalinspection

    Reactormanually shutdown due totrouble in testbypass valve of

    core spraysystem (B)

    %100

    50

    0

    Control rod pattern adjustment

    23rd periodicalinspection

    Power drop for control rodpattern adjustment andverification test of control

    rod operations

    82

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    82/726

    (16) Fukushima Daiichi Nuclear Power Station Unit 6

    FY2005

    21

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    6 1 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    30 8 12Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    11Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    12 14 4 15Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Control rod patternadjustment

    19th periodical inspection

    %100

    50

    0

    Control rod pattern adjustment

    %100

    50

    0

    Control rod pattern adjustment

    Coast down operation

    20th periodical inspection

    Power adjustment due tostop of turbine drivenreactor feedwater pump (A)

    19th periodical

    inspection

    %100

    50

    0

    21stperiodical

    inspection

    %100

    50

    0

    21st periodicalinspection

    Intermediate shutdown due toinspection and repair of thehigh-pressure turbine extraction

    drain pipes

    83

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    83/726

    (17) Fukushima Daini Nuclear Power Station Unit 1

    FY2005

    23 25 5 21 11 21 17 24 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    20 24 7 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    24 25 18 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    17 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    27 26 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Power drop for control rodpattern adjustment andverification test of controlrod operations

    17

    thperiodical

    inspection

    Intermediate shutdowndue to trouble withmechanical seals onreactor coolant

    recirculation pump (A)

    %100

    50

    0

    %100

    50

    0

    Control rod pattern adjustment

    Coast down operation

    19th periodical inspection

    %100

    50

    0

    Control rod pattern adjustment

    Control rod pattern adjustment 20th periodicalinspection

    18th periodical inspection

    %100

    50

    0

    20thperiodical

    inspection

    Control rod pattern adjustment

    Intermediate shutdowndue to trouble withmechanical seals onreactor coolantrecirculation pump (B)

    Intermediateshutdown due

    to incorrectmeasurement

    of atmospheric

    monitor inreactor

    containment

    84

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    84/726

    (18) Fukushima Daini Nuclear Power Station Unit 2

    FY2005

    25 26 28Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    6 10 5 1 17 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    5 12 6 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    6Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Coast down operation

    %100

    50

    0Coast down operation

    Control rod pattern adjustment

    Control rod pattern adjustment

    %100

    50

    0

    17th periodical inspection

    Intermediate shutdown toinspect switchyard

    equipment

    Coast down operation

    %100

    50

    0

    Control rod pattern adjustment

    Control rod pattern adjustment 18th periodicalinspection

    16th periodical inspection

    %100

    50

    0

    Control rod pattern adjustmentControl rod pattern adjustment

    19thperiodical

    inspection

    Control rod pattern adjustment

    85

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    85/726

    (19) Fukushima Daini Nuclear Power Station Unit 3

    FY2005

    16 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    27 14 6 9Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    26 20 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    9 16 6 6 9 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    7 14Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    13th periodical inspection

    Power drop for control rodpattern adjustment and

    verification test of controlrod operations

    %100

    50

    0

    1

    4thperiodical

    in

    spection

    Intermediate shutdown toreplace hafnium plate

    type control rodControl rod pattern

    adjustment

    Control rod pattern adjustment

    Control rod patternadjustment

    13

    thperiodical

    in

    spection

    %100

    50

    0

    14th periodical inspection

    Control rod pattern adjustment

    %100

    50

    0

    Control rod pattern adjustment

    Coast down operation

    Intermediate shutdown due to trouble with mechanical

    seals on reactor coolant recirculation pump (A)

    15th periodical inspection

    %100

    50

    0

    Control rod pattern adjustment

    Control rod pattern adjustment

    16th periodicalinspection

    86

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    86/726

    (20) Fukushima Daini Nuclear Power Station Unit 4

    FY2005

    22 16 20Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    15 16 24 21Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    30 25 3Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    27 23 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    7 14 9 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    14th periodical inspection

    Intermediate

    shutdown dueto trouble withmechanical

    seals on reactorcoolant

    recirculationpump (A)

    %100

    50

    0

    Intermediate shutdown toinspect main transformer

    13th periodical inspection

    Intermediateshutdown

    due to

    trouble withmechanical

    seals onreactor

    coolant

    recirculation

    pump (A)

    %100

    50

    0

    14thperiodical

    inspection Control rod pattern adjustment

    Control rod pattern adjustment

    15th periodicalinspection

    Control rod pattern adjustment

    %100

    50

    0

    15thperiodical

    inspection

    Control rod pattern adjustment

    %100

    50

    0

    Control rod patternadjustment

    16th periodical inspection

    Drop in output due tostoppage of the reactorrecirculation pump (A)

    Control rod pattern adjustment

    Control rod pattern adjustment

    87

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    87/726

    (21) Kashiwazaki-Kariwa Nuclear Power Station Unit 1

    FY2005

    14 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    30 30 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    4Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0Controlrodpattern

    adjustment Power

    adjusted

    operation dueto minor fuel

    leakage

    14th periodical inspection

    %100

    50

    0

    14thperiodicalinspection

    Control rod pattern adjustment

    Control rod pattern adjustment

    %100

    50

    0

    Control rod pattern adjustment

    15th periodical inspection

    %100

    50

    0

    15th periodical inspection

    %100

    50

    0

    15th periodical inspection

    88

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    88/726

    (22) Kashiwazaki-Kariwa Nuclear Power Station Unit 2

    FY2005

    3 25 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    9 19Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    10 5Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Control rod pattern adjustment

    11th periodical inspection

    Power drop due to control rodoperation verification test

    Coast down operation

    %100

    50

    0

    Control rod pattern adjustment

    Control rod pattern adjustment11thperiodical

    inspection

    12thperiodicalinspection

    %100

    50

    0

    12th periodical inspection Intermediate shutdown due to oil leak from the turbine control system

    %100

    50

    0

    Intermediate shutdown due to oil leak from the turbine control system

    %100

    50

    0

    Intermediate shutdown due to oil leak from the turbine control system

    89

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    89/726

    (23) Kashiwazaki-Kariwa Nuclear Power Station Unit 3

    FY2005

    13 8 7 15 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    12 27 15 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    16 19 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    8thperiodicalinspection

    Control rod pattern adjustment

    Intermediate shutdown due to

    inspection of relief valve of2nd feedwater heater A

    Powersuppressiondue to trippingof PLR pump(B) caused bythe tripping of

    New Niigatatrunk line No. 2

    Control rod

    patternadjustment

    Power downfor control rodoperation

    confirmationtest

    %100

    50

    0

    9th periodicalinspection Control rod pattern adjustment

    Control rod pattern adjustment

    %100

    50

    0

    Control rod pattern adjustmentAutomatic reactorshutdown due tothe NiigataChuetsu-OkiEarthquake 10th periodical inspection

    %100

    50

    0

    10th periodical inspection

    %100

    50

    0

    10th periodical inspection

    90

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    90/726

    (24) Kashiwazaki-Kariwa Nuclear Power Station Unit 4

    FY2005

    20 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    9 14 11 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    16 11Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2009

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    8th

    periodical

    inspection

    Control rod pattern adjustmentControl rod pattern adjustment

    %100

    50

    0

    Coast down operation

    9th periodical inspection

    %100

    50

    0

    Control rod pattern adjustment

    Automatic reactor shutdown due to the Niigata Chuetsu-OkiEarthquake

    10thperiodicalinspection

    %100

    50

    0

    10th periodical inspection

    %100

    50

    0

    10th periodical inspection

    Coast down operation

    91

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    91/726

    (25) Kashiwazaki-Kariwa Nuclear Power Station Unit 5

    FY2005

    34 8 2 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    24 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2007

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2008

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    (;

    Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    %100

    50

    0

    Control rod pattern adjustment

    Reactor automatically shut

    down due to condenservacuum level drop

    11th periodical inspection

    Control rod pattern adjustment

    %100

    50

    0

    Control rod pattern adjustment

    12th periodical inspection

    %100

    50

    0

    12th periodical inspection

    %100

    50

    0

    12th periodical inspection

    %100

    50

    0

    12th periodical inspection

    92

  • 8/7/2019 Operational Status of Nuclear Facilities in Japan 2010 Edition by The Japan Nuclear Energy Safety Organization

    92/726

    (26) Kashiwazaki-Kariwa Nuclear Power Station Unit 6

    FY2005

    9 Month Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar.

    FY2006

    13 12 Month Apr. May Jun. Jul. Aug. Sep.