24
Operations Management For Competitive Advantage 1 Material Requirements Planning Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Embed Size (px)

Citation preview

Page 1: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 1

Material Requirements PlanningMaterial Requirements Planning

Operations ManagementFor Competitive Advantage

Chapter 14

Page 2: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 2

Chapter 14

Materials Requirements Planning

Material Requirements Planning (MRP) MRP Logic and Product Structure Trees Time Fences MRP Example MRP II Lot Sizing in MRP Programs

Page 3: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 3

Material Requirements PlanningDefined Materials requirements planning (MRP) is the

logic for determining the number of parts, components, and materials needed to produce a product.

MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced.

Dependent demand drives MRP. MRP is a software system.

Page 4: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 4

Example of MRP Logic and Product Structure Tree

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

Product Structure Tree for Assembly ALead TimesA 1 dayB 2 daysC 1 dayD 3 daysE 4 daysF 1 day

DemandDay 10 50 ADay 8 20 B (Spares)Day 6 15 D (Spares)

Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed.

Page 5: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 5

LT = 1 day

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50

First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” in the 9 th week to receive them in the 10th week.

Page 6: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 6

Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50B Required 20 200

Order Placement 20 200

SparesLT = 2

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A 4x50=200

Page 7: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

LT=1 Order Placement 50B Required 20 200

LT=2 Order Placement 20 200C Required 100

LT=1 Order Placement 100D Required 55 400 300

LT=3 Order Placement 55 400 300E Required 20 200

LT=4 Order Placement 20 200F Required 200

LT=1 Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

40 + 15 spares

Part D: Day 6

Finally, repeating the process for all components, we have the final materials requirements plan:

7

Page 8: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 8

Master Production Schedule (MPS)

Time-phased plan specifying how many and when the firm plans to build each end item.

Aggregate Plan(Product Groups)

MPS(Specific End Items)

Page 9: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 9

Types of Time Fences Frozen

– No schedule changes allowed within this window. Moderately Firm

– Specific changes allowed within product groups as long as parts are available.

Flexible– Significant variation allowed as long as overall

capacity requirements remain at the same levels.

Page 10: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 10

Example of Time Fences

8 15 26

Weeks

FrozenModerately

Firm Flexible

Firm Customer Orders

Forecast and availablecapacity

Capacity

Exhibit 14.5Exhibit 14.5

Page 11: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 11

Material Requirements Planning System

Based on a master production schedule, a material requirements planning system:– Creates schedules identifying the

specific parts and materials required to produce end items.

– Determines exact unit numbers needed.

– Determines the dates when orders for those materials should be released, based on lead times.

Page 12: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Firm orders from knowncustomers

Forecastsof demand

from randomcustomers

Aggregateproduct

plan

Masterproductionschedule

(MPS)

Materialplanning(MRP)

Engineeringdesign

changes

Bill ofmaterial

file

Inventorytransactions

Inventoryrecord

file

ReportsFrom Exhibit 14.6From Exhibit 14.6

12

Page 13: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 13

Bill of Materials (BOM) FileA Complete Product Description Materials Parts Components Production sequence Modular BOM

– Subassemblies Planning BOM

– Fractional options

Page 14: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 14

Inventory Records File

Each inventory item carried as a separate file– Status according to “time buckets”.

Pegging– Identify each parent item that created demand.

Page 15: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 15

Primary MRP Reports Planned orders to be released at a future

time. Order release notices to execute the

planned orders. Changes in due dates of open orders due to

rescheduling. Cancellations or suspensions of open

orders due to cancellation or suspension of orders on the master production schedule.

Inventory status data.

Page 16: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 16

Secondary MRP Reports

Planning reports, for example, forecasting inventory requirements over a period of time.

Performance reports used to determine agreement between actual and programmed usage and costs.

Exception reports used to point out serious discrepancies, such as late or overdue orders.

Page 17: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 17

Net Change System

Activity driven Net change schedules Potential for system nervousness

Page 18: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 18

Additional MRP Scheduling Terminology Gross Requirements

On-hand

Net requirements

Planned order receipt

Planned order release

Page 19: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 19

MRP Example

A(2) B(1)

D(5)C(2)

X

C(3)

Item On-Hand Lead Time (Weeks)X 50 2A 75 3B 25 1C 10 2D 20 2

Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10 plus the following spares:

Spares 1 2 3 4 5 6 7 8 9 10A 12B 7C 10D 15

Page 20: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 20

C Gross Requirements 45 36 64LT=2 On-Hand=10 10

Net Requirements 35 36 64Planned Order Receipt 35 36 64Planner Order Release 35 36 64

D Gross Requirements 15 135LT=2 On-Hand=20 15 5

Net Requirements 130Planned Order Receipt 130Planner Order Release 130

A(2) B(1)

D(5)C(2)

X

C(3)

Page 21: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 21

Day: 1 2 3 4 5 6 7 8 9 10X Gross Requirements 95

LT=2 On-Hand=50 50Net Requirements 45Planned Order Receipt 45Planner Order Release 45

A Gross Requirements 90 12LT=3 On-Hand=75 75

Net Requirements 15 12Planned Order Receipt 15 12Planner Order Release 15 12

B Gross Requirements 7 45LT=1 On-Hand=25 7 18

Net Requirements 27Planned Order Receipt 27Planner Order Release 27

C Gross Requirements 45 36 54 10LT=2 On-Hand=10 10

Net Requirements 35 36 54 10Planned Order Receipt 35 36 54 10Planner Order Release 35 36 54 10

D Gross Requirements 15 135LT=2 On-Hand=20 15 5

Net Requirements 130Planned Order Receipt 130Planner Order Release 130

Page 22: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 22

Closed Loop MRP

Production PlanningMaster Production SchedulingMaterial Requirements PlanningCapacity Requirements Planning

Realistic?No

Feedback

Execute:Capacity PlansMaterial Plans

Yes

Feedback

Page 23: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 23

Manufacturing Resource Planning (MRP II) Goal: Plan and monitor all resources of a

manufacturing firm (closed loop):– manufacturing– marketing– finance– engineering

Simulate the manufacturing system

Page 24: Operations Management For Competitive Advantage 1 Material Requirements Planning Operations Management For Competitive Advantage Chapter 14

Operations Management For Competitive Advantage 24

Lot Sizing in MRP Programs

Lot-for-lot (L4L) Economic order quantity (EOQ) Least total cost (LTC) Least unit cost (LUC)