Optimize your Shutdown, Turnarounds, and Outages Zack Fox, Business Development Representative Stephen Taylor, Product Manager Brian Hying, Functional Consultant Cor Ruiten, Sr. Solutions Architect Date: March 14, 2019

Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Optimize your Shutdown, Turnarounds, and Outages

Zack Fox, Business Development RepresentativeStephen Taylor, Product ManagerBrian Hying, Functional ConsultantCor Ruiten, Sr. Solutions Architect

Date: March 14, 2019

Page 2: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Agenda

• Introduction to Prometheus Group• Prometheus STO Manger• Demonstration

Page 3: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Prometheus Group

• Founded in 1998• Headquartered in Raleigh, NC, USA • Asset Management Experts • Integrated and Intuitive Software• Trusted by the largest asset-intensive

companies in the world

Page 4: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Key Customers

Page 5: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Prometheus Platform

Page 6: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

STO Manager

Page 7: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

The STO timeline vs. our product offering

STO Planning begins (18-24 months before execution start)

Scope Freeze

Material Procurement

Scheduling

Execution Start

Execution Finish

Syntempo + Maxavera + SchedulerLittle Use of Prometheus products during 90% of the turnaround lifecycle!

Page 8: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Key Benefits of STO Manager

• Scope Management• What are we working on in the STO?• Who has approved the work?• How can I assure that we are working on the right work?

• Planning Process Tracking• Are we ready for the STO to start?• “I think we’re ready” vs. “I know we’re ready”

• Materials Management• Inspection Planning and Execution• QA/QC Packages• Work Execution with Syntempo

Page 9: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

Demonstration

Page 10: Optimize your Shutdown, Turnarounds, and Outages · 3/14/2019  · STO Planning begins (18 -24 months before execution start) Scope Freeze. Material Procurement. Scheduling. Execution

STO Timeline

Refueling Outage Planning begins (18-24 months

before execution start)

Scope Freeze

Material Procurement

Execution Start

Execution Finish