59
Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Embed Size (px)

Citation preview

Page 1: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Orange TeamRyan Null

Project Manager

CS 410 Orange Team10 December, 2008

10 December, 2008 1Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 2: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Team OrangeProfessor Brunelle

DavidHardware Specialist

RyanProject Manager

AndrewFinance and Webmaster

SpencerSoftware and Market

NicoleSoftware Specialist

GenerosoSystems Specialist

Experts

Dr. Daniel Garland M.D.President of Pathologist

DepartmentObici Hospital

Suffolk

Mrs. Janet Jackson BSN RNHCMSDM Regulatory Compliance Manager

Amerigroup CorporationVirginia Beach

10 December, 2008 2Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 3: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Cardiac Rehabilitation Retention

Cardiac patients do not commit to the

long-term rehabilitation necessary to

extend their life.

10 December, 2008 3Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 4: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Societal Cost of Cardiac Failure

The direct and indirect cost to the U. S. in 2008alone are staggering. [1]

• $156.4 billion for Cardiac Heart Disease

• $448.5 billion for Cardio Vascular Disease

[1] http://www.americanheart.org/presenter.jhtml?identifier=3050603

10 December, 2008 4Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 5: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Need for Cardiac Rehabilitation Is Increasing

• 22 million people experience heart failure every year [1]

• 5 million people in the United States are living with a heart condition [2]

• 500, 000 additional cases are diagnosed each year

[1] Popular Science Magazine, December 2008, 61 - 63[2] http://www.americanheart.org/presenter.jhtml?identifier=3047844

10 December, 2008 5Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 6: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

80% of Patients Cease Cardiac Rehabilitation

Completion of Rehabilitation

20%

Pre-Mature Death63%

Survival Absent Rehabilitation

17%

Rehabilitation Outcomes

Team Orange SBIR page 9

10 December, 2008 6Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 7: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Rehabilitation Exercises Extend Life

Doctor prescribed exercises are essential to successful rehabilitation.[1]

• Increased heart strength and mobility• Lower blood pressure, cholesterol, and BMI• Reduced emotional stress, depression, and

anxiety

[1] http://www.mayoclinic.com/health/cardiac-rehabilitation/HB00017

10 December, 2008 7Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 8: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Challenges to Monitoring Cardiac Patient Exercise

Team Orange SBIR Appendix J

10 December, 2008 8Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 9: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Tools to Encourage Rehabilitation Are Needed

According to Dr. Suaya “We need to find ways to increase the use of cardiac rehabilitation, because it is used very little by patients who could benefit a lot…” [1]

The A.H.A. “recommends physicians aggressively encourage cardiac rehabilitation…”

[1] http://www.americanheart.org/presenter.jhtml?identifier=3050603

10 December, 2008 9Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 10: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Patient Involvement Is Key to Rehabilitation

According to Beaumont Hospitals• “Active involvement of the patient and family

is vital to the success of the program.”[1]

And ABC reports• “[…] If the patient is actively engaged […] they

feel like they have some control over what they will do and how they will do it.”[2]

[1] https://www.beaumonthospitals.com/health-library/P06321[2] http://www.abc.net.au/rn/healthreport/stories/2007/2023663.htm

10 December, 2008 10Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 11: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Current Rehabilitation System

Team Orange SBIR page 11

10 December, 2008 11Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 12: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Tools Available for Cardiac Rehabilitation

Team Orange SBIR page 16

10 December, 2008 12Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 13: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Goals of Cardiac Rehabilitation Retention Solutions

Lifestyle Education• Increase involvement in rehabilitation process• Illustrate concrete benefits of changes through

historical data

Support• Accountability and control of exercise regimen• Positive feedback on progress

Team Orange SBIR page 9-10

10 December, 2008 13Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 14: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Heart Exercise Accelerometer Rehabilitation Tool

• Contains mechanics to monitor and record patients’ heart rate, exercise type, intensity, and duration each time they exercise

• Give feedback to reinforce positive progress with reports and analysis of future potential benefits

• Be utilized during rehabilitation, home exercises, and patient follow-ups

• Be non-intrusive and not substantially modify established rehabilitation processes

10 December, 2008 14Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 15: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Modified Rehabilitation System

Team Orange SBIR page 12

10 December, 2008 15Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 16: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Technical Overview

Team Orange SBIR page 13

10 December, 2008 16Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 17: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Cardiac Patient Use

Team Orange SBIR page 14

10 December, 2008 17Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 18: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Patient and Rehabilitation Software

Team Orange SBIR page 13

10 December, 2008 18Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 19: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Cardiac Patient Software Report

Team Orange SBIR page 13

10 December, 2008 19Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 20: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Limitations

The system is not capable of the following• Medical diagnosis• Exercise prescription • Compulsion of proper utilization of the system

by the doctor, rehabilitation specialist, and patient

Team Orange SBIR Appendix H

10 December, 2008 20Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 21: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Required Measurements for Cardiac Rehabilitation Tools

Team Orange SBIR Appendix J

10 December, 2008 21Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 22: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Capabilities

Team Orange SBIR page 16

10 December, 2008 22Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 23: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Project ManagementManagement Plan

Marketing Plan Development Plan

Evaluation PlanStaffing Plan

Financial Plan Work Breakdown Structure

Funding Plan Risk Management Plan

10 December, 2008 23Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 24: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Risk Management

• Identify and categorize risks according to severity and probability

• Mitigate the impact of risks by preventing the cause or alleviate current risks

• Continually re-examine risks throughout all phases

• Anticipate and be aware of new risks

Team Orange SBIR Appendix G

10 December, 2008 24Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 25: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Risk AnalysisProbability

Not Likely Low Moderate

High Expected

ImpactExtreme T1, F1

High F2 C1

Moderate T3 C2 T2 F3

Low

Negligible

Item Technical Risks Probability Impact

T1 Hardware and Software Interoperability 2 5

T2 Hardware and Software Accuracy 1 3

T3 Malfunction (Device and Software) 3 3

Item Financial Risks Probability Impact

F1 FDA Rejection 2 5

F2 Insurance Rejection 2 4

F3 Market Competition 4 3

Item Customer Risks Probability Impact

C1 Rehabilitation Acceptance 3 4

C2 Proper Utilization 2 3

10 December, 2008 25Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 26: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 0 Organization

Team Orange SBIR Appendix C

10 December, 2008 26Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 27: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 0 Task List

Team Orange SBIR Appendix F

10 December, 2008 27Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 28: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 0 Gantt

Team Orange SBIR Appendix F

10 December, 2008 28Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 29: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 0 Marketing

Team Orange SBIR Appendix B

$977,421

$434,898

$67,931

$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

$1,200,000

Pro

fit in

Do

lla

rs

Rehabilitation Market Analysis

Large Medium Small

10 December, 2008 29Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 30: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 0 Funding

Old Dominion University will provide the funding for all necessary resources.

Team Orange SBIR Appendix D

10 December, 2008 30Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 31: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 0 Evaluation

Phase 0 will be a success if it accomplishes the following on schedule

• WBS

• Feasibility, Milestone, and Approval Presentation

• Product Website

• SBIR Phase 1 Proposal approval

Team Orange SBIR Appendix H

10 December, 2008 31Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 32: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Organization

Team Orange SBIR Appendix C

10 December, 2008 32Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 33: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Task List

Team Orange SBIR Appendix F

10 December, 2008 33Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 34: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Gantt

Team Orange SBIR Appendix F

10 December, 2008 34Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 35: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Marketing

The focus of Marketing in Phase 1 includes the following

• Secure SBIR grant for Phase 2

• Pay down on outstanding notes

• Generate product demand for Phase 2

Team Orange SBIR Appendix B

10 December, 2008 35Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 36: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Hardware BudgetHardware Qty Unit Cost Total

Heart Rate Monitor 2 $100.00 $200.00 Piezoelectric Accelerometer 4 $50.00 $200.00 Software (QA) 1 $10.00 $10.00 Receivers 2 $10.00 $20.00 Transmitters 4 $10.00 $40.00 Production 2 $10.00 $20.00 Material (Box, Paper, assoc, etc) 2 $10.00 $20.00 Assembly and Manufacturing 2 $30.00 $60.00 Memory, Battery, cables, base station 4 $75.00 $300.00 Prototype I 1 $50,000.00 $50,000.00 Prototype II 1 $18,000.00 $18,000.00 Labor and AV technicians 2 $300.00 $600.00 Tax (8.8%) $6,037 $6,113 Total Phase 1 Hardware Budget $75,583

Team Orange SBIR Appendix E

10 December, 2008 36Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 37: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Staffing Budget

Title Qty Salary Hours Hourly Rate Total

Project Manager 1 $31,200 70 $15 $1,050 Software Manager 1 $31,200 460 $15 $6,900 Hardware Manager 1 $31,200 380 $15 $5,700 Financial Director 1 $31,200 45 $15 $675 Marketing Director 1 $31,200 65 $15 $975 Risk Director 1 $31,200 60 $15 $900 Documentation Specialist 1 $31,200 55 $15 $825 Webmaster 1 $31,200 15 $15 $225 Total Cost $17,025 All employees are Students 40% Overhead $6,810 Phase 1 = 6 month period Total Phase 1 Staffing Budget: $23,835

Phase 1 Total Budget: $99,418Team Orange SBIR page 29

10 December, 2008 37Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 38: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Funding

Grants.gov• $33,000,000: Research Experiences for Undergraduate

Funding• $750,000: Cardiac Translational Research

Implementation• $250,000: Improving Heart Failure Disease

Management

Small Business Administration• $100,000: SBIR Phase 1 Grant

Team Orange SBIR Appendix D

10 December, 2008 38Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 39: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 1 Evaluation

Phase 1 will be a success if it accomplishes the following on schedule

• Functional H.E.A.R.T. Prototype

• SBIR Phase 2 Proposal approval

• Approval from FDA, insurance companies, and

rehabilitation centers

Team Orange SBIR Appendix H

10 December, 2008 39Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 40: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Organization

Team Orange SBIR Appendix C

10 December, 2008 40Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 41: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Task List

Team Orange SBIR Appendix F

10 December, 2008 41Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 42: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Gantt

Team Orange SBIR Appendix F

10 December, 2008 42Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 43: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Break Even Analysis

Team Orange SBIR Appendix B

10 December, 2008 43Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 44: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Marketing

The focus of Marketing in Phase 2 includes the following

• $150,000 revenue by second year of Phase 2

• $180,000 profit

• Identify new markets and increase market share

Team Orange SBIR Appendix B

10 December, 2008 44Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 45: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Hardware BudgetHardware Quantity CpU Total Cost

Heart Rate Monitor 1,000 $45.00 $45,000.00

Piezoelectric Accelerometer 2,000 $15.00 $30,000.00

Receivers 2,000 $5.00 $10,000.00

Transmitters 2,000 $5.00 $10,000.00

Production 2,000 $5.00 $10,000.00

Material (Box, Paper, assoc, etc) 2,000 $5.00 $10,000.00

Assembly and Manufacturing 2,000 $10.00 $20,000.00Memory, Battery, cables, base station 2,000 $30.00 $60,000.00

Training 45 $80.00 $3,600.00

Testing 100 $150.00 $15,000.00

Tax (8.8%) $30.80 $18,796.80

Total Phase 3 Hardware Budget $137,396.80

Team Orange SBIR Appendix E

10 December, 2008 45Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 46: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Staffing BudgetTitle Qty Salary Hours Hourly Total

Project Manager 1 $87,000 1200 $42 $50,192 Software Engineer 2 $71,000 2000 $34 $136,538 Hardware Engineer 2 $81,000 1800 $39 $140,192 Financial Director 1 $62,000 420 $30 $12,519 Marketing Director 1 $44,000 460 $21 $9,731 Documentation Specialist 1 $42,000 600 $20 $12,115 HR Manager 1 $56,000 220 $27 $5,923 Technical Director 1 $70,000 680 $34 $22,885 Software/Hardware Tester 1 $69,000 450 $33 $14,928 Webmaster 1 $40,000 160 $19 $3,077 Total Cost $405,024 All employees are Full Time 40% Overhead $162,010Phase 2 = 2 year period Total Phase 2 Staffing Budget: $567,034

Phase 2 Total Budget: $704,430Team Orange SBIR page 29

10 December, 2008 46Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 47: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Funding

US Small Business Administration

• SBIR Grants

–Up to $750,000

• SBIR Loans

US Department of Commerce

Team Orange SBIR Appendix D

10 December, 2008 47Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 48: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 2 Evaluation

Phase 2 will be a success if it accomplishes the following on schedule

• Fully functional H.E.A.R.T. System

• Production ready prototype

• Break-Even-Point reached and exceeded

Team Orange SBIR Appendix H

10 December, 2008 48Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 49: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Organization

Team Orange SBIR Appendix C

10 December, 2008 49Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 50: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Task List

Team Orange SBIR Appendix F

10 December, 2008 50Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 51: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Gantt

Team Orange SBIR Appendix F

10 December, 2008 51Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 52: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Marketing

The focus of Marketing in Phase 3 includes the following

• Analysis of market campaign and market share

• Customer analysis of retention and refinements

• Acquire new markets

Team Orange SBIR Appendix B

10 December, 2008 52Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 53: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Hardware BudgetHardware Qty CpU Total Cost

Heart Rate Monitor 1,500 $45.00 $67,500.00Piezoelectric Accelerometer 3,000 $15.00 $45,000.00Receivers 3,000 $5.00 $15,000.00Transmitters 3,000 $5.00 $15,000.00Production 3,000 $5.00 $15,000.00Material (Box, Paper, assoc, etc) 3,000 $5.00 $15,000.00Assembly and Manufacturing 3,000 $10.00 $30,000.00Memory, Battery, cables, base station 3,000 $30.00 $90,000.00Training 100 $80.00 $8,000.00Testing 500 $150.00 $75,000.00Tax (8.8%) $30.80 $33,044.00Total Phase 2 Hardware Budget $266,044.00

Team Orange SBIR Appendix E

10 December, 2008 53Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 54: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Staffing BudgetTitle Qty Salary Hours Hourly Total

Project Manager 1 $87,000 600 $42 $25,096 Software Engineer 1 $71,000 1000 $34 $34,135 Hardware Engineer 1 $81,000 800 $39 $31,154 Financial Director 1 $62,000 450 $30 $13,413 Marketing Director 1 $44,000 500 $21 $10,577 Documentation Specialist 1 $42,000 400 $20 $8,077 HR Manager 1 $56,000 170 $27 $4,577 Technical Director 1 $70,000 440 $34 $14,808 Software/Hardware Tester 1 $69,000 500 $33 $16,587 Lawyers 1 $64,000 900 $31 $27,692 Procurement Manager 1 $50,000 350 $24 $8,413 Customer Service 5 $41,000 650 $20 $64,063 Webmaster 1 $40,000 160 $19 $3,077 Total Cost $258,591 All employees are Full Time 40% Overhead $103,437Phase 3 = Production Total Phase 3 Staffing Budget: $362,028

Phase 3 Total Budget: $628,072Team Orange SBIR page 29

10 December, 2008 54Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 55: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Budget Overview

Phase Staffing Hardware Phase Total

Phase 1 (6 months) $23,835 $1,599 $99,800

Phase 2 (Two Years) $567,034 $137,397 $704,430

Phase 3 (Per Year) $362,028 $266,044 $628,072

Total Phases 1-3 $952,897 $405,040 $1,357,937

Team Orange SBIR page 29 - 31

10 December, 2008 55Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 56: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3: Funding

Various Investor Groups:

• National Venture Capital Association

• Funding Universe

• U.S. Angel Investors

• Vision 2 Reality (v2r.com)

Team Orange SBIR Appendix D

10 December, 2008 56Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 57: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

Phase 3 Evaluation

Phase 3 will be a success if it accomplishes the following on schedule

• A commercially viable H.E.A.R.T. System

• Acquire new markets and functionality for the

H.E.A.R.T. System

Team Orange SBIR Appendix H

10 December, 2008 57Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 58: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Conclusion Financial Incentives

• Generate historical data on exercises and their associated heart rate for scientific study and innovation

• Reduce health care costs by decreasing future cardiac intervention and hospitalization

• Return-On-Investment after 866 units sold

10 December, 2008 58Old Dominion University: Computer Science CS 410 Orange Team - HEART

Page 59: Orange Team Ryan Null Project Manager CS 410 Orange Team 10 December, 2008 1 Old Dominion University: Computer Science CS 410 Orange Team - HEART

H.E.A.R.T. Conclusion Cardiac Rehabilitation Patient Incentives

The patient will• Be involved in managing their rehabilitation

through feedback on progress• Develop and maintain positive long-term

lifestyle changes as recommended by their rehabilitation specialists

• Be educated and accountable for their long term exercise and rehabilitation regimen

10 December, 2008 59Old Dominion University: Computer Science CS 410 Orange Team - HEART