Order Case 102 of 2009

Embed Size (px)

Citation preview

  • 8/3/2019 Order Case 102 of 2009

    1/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 1 of121

    Before the

    MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

    World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai400 005

    Email: [email protected]

    Website: www.mercindia.org.in

    Case No. 102 of 2009

    IN THE MATTER OF

    Petition filed by The Maharashtra State Power Generating Company Limited (MSPGCL)

    for approval of Truing up for FY 2008-09, Annual Performance Review for FY 2009-10

    and Determination of Tariff for FY 2010-11

    Shri V. P. Raja, Chairman

    Shri S. B. Kulkarni, Member

    Shri V. L. Sonavane, Member

    Date: September 12, 2010

    O R D E R

    In accordance with MERC (Terms and Conditions of Tariff) Regulations, 2005 and upondirections from the Maharashtra Electricity Regulatory Commission (hereinafter referred as

    MERC or the Commission), Maharashtra State Power Generating Company Limited (MSPGCL),

    submitted its application on affidavit for approval of truing up of Aggregate Revenue

    Requirement (ARR) for FY 2008-09, Annual Performance Review (APR) for FY 2009-10 and

    tariff for FY 2010-11. The Commission, in exercise of the powers vested in it under Section 61

    and Section 62 of the Electricity Act, 2003 (EA 2003) and all other powers enabling it in this

    behalf, and after taking into consideration all the submissions made by MSPGCL, all the

    suggestions and objections of the public, responses of MSPGCL, issues raised during the Public

    Hearing, and all other relevant material, and after review of Annual Performance for FY 2009-

    10, determines the tariff for MSPGCL for FY 2010-11 as under.

  • 8/3/2019 Order Case 102 of 2009

    2/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 2 of121

    List of AbbreviationsAAD Advance Against Depreciation

    AOH Annual Overhaul

    APR Annual Performance Review

    ATE Appellate Tribunal for Electricity

    A&G Administrative and General

    APR Annual Performance Review

    ARR Aggregate Revenue Requirement

    APH Air Pre Heater

    AOH Annual Overhauling

    BHEL Bharat Heavy Electrical Ltd.

    Capex Capital Expenditure

    CPI Consumer Price Index

    CEA Central Electricity Authority

    CERC Central Electricity Regulatory Commission

    Cu.m Cubic meter

    CV Calorific Value

    COD Commercial Operation DateCPRI Central Power Research Institute

    DPR Detailed Project Report

    EA 2003 Electricity Act, 2003

    FAC Fuel Adjustment Cost

    FOCA Fuel & Other Cost Adjustment

    FY Financial Year

    GAAP Generally Accepted Accounting Principles

    GCV Gross Calorific Value

    GFA Gross Fixed Assets

    GOM Government of Maharashtra

    GOMWRD Government of Maharashtra-Water Resource Department

    ID Induced draftITAT Income Tax Appellate Tribunal

    ICAI Institute of Chartered Accountants of India

    IWC Interest on Working Capital

    Kcal kilo calories

    kW kilo Watt

    kWh kilowatt hour

    LD Liquidity Damages

    MCM Million Cubic Meter

    MMSCMD Million Metric Standard Cubic Meters per Day

    MERC Maharashtra Electricity Regulatory Commission

    MSEB Maharashtra State Electricity BoardMSETCL Maharashtra State Electricity Transmission Company Limited

    MSLDC Maharashtra State Load Despatch Centre

    MSPGCL Maharashtra State Power Generation Company Limited

  • 8/3/2019 Order Case 102 of 2009

    3/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 3 of121

    MT Metric Tonnes

    MU Million Units

    MW Mega Watt

    MYT Multi Year Tariff

    OEM Original Equipment Manufacturer

    O&M Operations and Maintenance

    PLF Plant Load Factor

    PLR Prime Lending Rate

    PPA Power Purchase Agreement

    R&M Repair and Maintenance

    RH Re-heater

    RLNG Re-gasified Liquid Natural Gas

    SFOC Secondary Fuel Oil Consumption

    SH Super Heater

    SHPs Small Hydel Plants

    TVS Technical Validation Session

    WPI Wholesale Price Index

  • 8/3/2019 Order Case 102 of 2009

    4/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 4 of121

    Table of Contents

    1 BACKGROUND AND BRIEF HISTORY .......................................................................................... 7

    1.1 TARIFF REGULATIONS ............................................................................................................ 7

    1.2 COMMISSIONS ORDER ON ARR AND TARIFF PETITION FOR FY 2005-06 AND FY

    2006-07 ..................................................................................................................................................... 7

    1.3 REVIEW PETITION ON TARIFF ORDER FOR FY 2006-07 ................................................... 7

    1.4 COMMISSIONS ORDER ON MYT PETITION OF MSPGCL FOR FY 2007-08 TO FY

    2009-10 ..................................................................................................................................................... 8

    1.5 MSPGCLS APPEAL BEFORE ATE AND ATE JUDGMENT ................................................. 8

    1.6 COMMISSION'S ORDER IN THE MATTER OF TRUING UP PROCESS FOR MSPGCL

    FOR FY 2005-06, FY 2006-07 & FY 2007-08 BASED ON APPELLATE TRIBUNALS JUDGMENT

    AND CPRI REPORT. ............................................................................................................................. 14

    1.7 PETITION FOR ANNUAL PERFORMANCE REVIEW FOR FY 2009-10 ANDDETERMINATION OF TARIFF FOR FY 2010-11 ............................................................................. 15

    1.8 ADMISSION OF PETITIONS AND PUBLIC PROCESS ........................................................ 16

    1.9 ORGANISATION OF THE ORDER ......................................................................................... 17

    2 OBJECTIONS RECEIVED, MSPGCLS RESPONSE AND COMMISSIONS RULING .............. 19

    2.1 Non Compliance to MYT framework ......................................................................................... 19

    2.2 Inadequate Time for Filing Suggestions and Objections ............................................................ 19

    2.3 Capital Expenditure and Capitalisation ....................................................................................... 20

    2.4 Interest Expenses ........................................................................................................................ 222.5 Depreciation Including Advance Against Depreciation ............................................................. 23

    2.6 O&M Expense Projections.......................................................................................................... 24

    2.7 Earned Leave Encashment .......................................................................................................... 25

    2.8 Material Cost Variance ............................................................................................................... 26

    2.9 Performance Parameters and Variable Cost ................................................................................ 27

    2.10 Coal Price .................................................................................................................................... 29

    2.11 Renovation & Modernisation Schemes ....................................................................................... 30

    2.12 Comparative Analysis of MSPGCL and NTPC Plants ............................................................... 31

    2.13 Lease Rent ................................................................................................................................... 32

  • 8/3/2019 Order Case 102 of 2009

    5/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 5 of121

    2.14 Power Purchase Agreement ........................................................................................................ 32

    2.15 Uniform Tariff for all Generating Stations ................................................................................. 33

    2.16 ARR for Ensuing Year ................................................................................................................ 33

    3 TRUING UP OF REVENUE REQUIREMENT FOR FY 2008-09 ................................................... 35

    3.1 PERFORMANCE PARAMETERS AND FUEL COSTS .......................................................... 35

    Gross Generation ................................................................................................................................ 37

    Auxiliary Consumption ....................................................................................................................... 40

    Station Heat Rate (SHR) ..................................................................................................................... 40

    Secondary Fuel Oil Consumption ....................................................................................................... 41

    Transit Loss ......................................................................................................................................... 42

    Fuel Price, Fuel Mix and Calorific Value ........................................................................................... 42

    Other Variable Charges ....................................................................................................................... 42

    Total Variable Costs ........................................................................................................................... 44

    3.2 OPERATION & MAINTENANCE (O&M) EXPENSES .......................................................... 44

    Establishment Expenses ...................................................................................................................... 45

    Administrative & General Expenses ................................................................................................... 47

    Repair & Maintenance Expense .......................................................................................................... 47

    3.3 CAPITAL EXPENDITURE (CAPEX) AND CAPITALISATION ........................................... 48

    3.4 DEPRECIATION AND ADVANCE AGAINST DEPRECIATION (AAD) ............................. 50

    3.5 INTEREST EXPENSES AND FINANCE CHARGES ............................................................. 53

    3.6 Return on Equity ......................................................................................................................... 54

    3.7 Income Tax ................................................................................................................................. 57

    3.8 Interest on Working Capital ........................................................................................................ 58

    3.9 Other Debits ................................................................................................................................ 59

    3.10 Prior Period Items ....................................................................................................................... 60

    3.11 Revenue side Truing-up computation ......................................................................................... 61

    3.12 Reduction in Annual Fixed Charges on account of Reduction in Availability ........................... 62

    3.13 Sharing of Gains and Losses ....................................................................................................... 633.14 Provisional Truing up for FY 2008-09 ....................................................................................... 65

    4 PERFORMANCE PARAMETERS .................................................................................................... 66

  • 8/3/2019 Order Case 102 of 2009

    6/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 6 of121

    4.1 GENERATING STATIONS OF MSPGCL ............................................................................... 66

    4.2 STATION-WISE PERFORMANCE PARAMETERS AND TARIFF ...................................... 71

    4.2.1 Availability and PLF of MSPGCLs Generating Stations .................................................. 71

    4.2.2 Auxiliary Consumption ....................................................................................................... 80

    4.2.3 Heat Rate ............................................................................................................................. 84

    4.2.4 Transit Loss ......................................................................................................................... 85

    4.2.5 Secondary Fuel Oil Consumption ....................................................................................... 87

    5 ANALYSIS OF ENERGY AVAILABILITY, ENERGY CHARGE AND ANNUAL FIXED

    CHARGES FOR FY 2009-10 AND FY 2010-11 ....................................................................................... 89

    5.1 ENERGY AVAILABILITY DURING FY 2009-10 .................................................................. 89

    5.2 ENERGY AVAILABILITY AND GROSS GENERATION DURING FY 2010-11 ................ 91

    5.2.1 Generation from Hydel Stations ......................................................................................... 91

    5.2.2 Generation from Thermal Stations ...................................................................................... 91

    5.3 VARIABLE COSTS OF THERMAL GENERATING STATIONS .......................................... 92

    5.3.1 Fuel Costs for FY 2009-10.................................................................................................. 92

    5.3.2 Fuel Price and Fuel Calorific Value for FY 2010-11 .......................................................... 93

    5.3.3 Cost of Lubricants, Other Consumables and Water Charges, etc. ...................................... 96

    5.3.4 Rate of Energy Charge ........................................................................................................ 96

    5.4 LEASE RENT FOR HYDEL STATIONS ................................................................................. 97

    5.5 OPERATION & MAINTENANCE (O&M) EXPENSES .......................................................... 98

    5.6 CAPITAL EXPENDITURE AND CAPITALISATION .......................................................... 100

    6 TARIFF OF MSPGCLS GENERATING STATIONS ................................................................... 113

    6.1 TARIFF FOR THERMAL POWER GENERATING STATIONS .......................................... 113

    6.2 TARIFF FOR HYDEL POWER GENERATING STATIONS ................................................ 116

    6.3 Provisional Tariff for Paras Unit 4 and Parli Unit 7 ................................................................. 119

    6.4 APPLICABILITY OF ORDER AND TARIFF ........................................................................ 120

  • 8/3/2019 Order Case 102 of 2009

    7/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 7 of121

    1 BACKGROUND AND BRIEF HISTORYThis Order relates to the Petition filed by the Maharashtra State Power Generation Company

    Limited (MSPGCL) for approval of Annual Performance Review for FY 2009-10 and tariff

    determination for FY 2010-11. The Maharashtra State Power Generation Company Limited(MSPGCL or Mahagenco) is a Company formed under the Government of Maharashtra General

    Resolution No. ELA-1003/P.K.8588/Bhag-2/Urja-5 dated January 24, 2005 with effect from

    June 6, 2005 according to the provisions envisaged in the Electricity Act, 2003 (EA 2003).

    MSPGCL has been registered with the Registrar of Companies, Mumbai under the Companies

    Act, 1956.

    The provisional Transfer Scheme was notified under Section 131(5)(g) of the EA 2003 on June

    6, 2005, which resulted in the creation of following four successor companies and MSEB

    Residual Company, to the erstwhile Maharashtra State Electricity Board (MSEB), namely,

    MSEB Holding Company Ltd.,

    Maharashtra State Power Generation Company Ltd.,

    Maharashtra State Electricity Transmission Company Ltd., and

    Maharashtra State Electricity Distribution Company Ltd.

    1.1 TARIFF REGULATIONSThe Commission, in exercise of the powers conferred by the EA 2003, notified the Maharashtra

    Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2005,

    (hereinafter referred as the MERC Tariff Regulations) on August 26, 2005. These Regulations

    superseded the MERC (Terms and Conditions of Tariff) Regulations, 2004.

    1.2 COMMISSIONS ORDER ON ARR AND TARIFF PETITION FOR FY 2005-06AND FY 2006-07

    The Commission issued the Order on the ARR Petition of MSPGCL for FY 2005-06 and ARR

    and Tariff Petition of MSPGCL for FY 2006-07 in Case No. 48 of 2005 on September 7, 2006.

    1.3 REVIEW PETITION ON TARIFF ORDER FOR FY 2006-07MSPGCL filed a Review Petition (numbered as Case No. 34 of 2006) against the above saidCommissions Order. The Commission disposed off the Review Petition vide its Order dated

    December 7, 2006.

  • 8/3/2019 Order Case 102 of 2009

    8/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 8 of121

    1.4 COMMISSIONS ORDER ON MYT PETITION OF MSPGCL FOR FY 2007-08 TOFY 2009-10

    The Commission issued the MYT Order (Case No. 68 of 2006) for MSPGCL for the first

    Control Period, i.e., FY 2007-08 to FY 2009-10, on April 25, 2007, which came into effect from

    April 25, 2007.

    1.5 MSPGCLS APPEAL BEFORE ATE AND ATE JUDGMENTMSPGCL filed two Appeals before the Honble Appellate Tribunal for Electricity (ATE), viz.,

    Appeal No. 86 of 2007 on the Commissions Order dated September 7, 2006 on ARR and Tariff

    for FY 2005-06 and FY 2006-07 in Case No. 48 of 2005, and Appeal No. 87 of 2007 on the

    Commissions Order dated April 25, 2007 on MSPGCLs MYT Petition in Case No. 68 of 2006.

    MSPGCL challenged the Commissions Order for FY 2005-06 and FY 2006-07 on the following

    issues:

    Administrative and General expenses

    Transit loss of coal

    Station Heat Rate

    Tariff for small hydro projects.

    MSPGCL challenged the Commissions MYT Order on the following issues:

    Truing up of the fuel expenses for FY 2005-06

    Disapproval of A&G expenses

    Truing up of depreciationTruing up of other debits

    Truing up of interest expenses and financing charges

    Truing up of revenue earned

    Transit loss of coal

    Station Heat Rate

    Auxiliary consumption of various stations

    Secondary Fuel Oil Consumption

    O&M expenses for base year for MYT Period

    Hydel tariff

    Tariff for small hydro power stations

    Reactive energy charges

  • 8/3/2019 Order Case 102 of 2009

    9/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 9 of121

    Normative O&M expenses for hydel plants

    Employee incentive schemes

    The Honble ATE dealt with the above issues vide its Judgment dated April 10, 2008 in Appeal

    Nos. 86 and 87 of 2007. The ATEs ruling on various aspects raised in MSPGCLs Appeals havebeen summarised below:

    ATE upheld MSPGCLs appeal regarding allowance of actual A&G expenses for FY

    2005-06 for truing up purposes and directed the Commission to true up the said expenses

    based on actuals, subject to prudence check. ATE also directed the Commission not to

    consider the A&G expenses towards projects under construction as recoverable through

    tariff, since such expenses should be capitalised.

    ATE directed the Commission to consider the transit loss levels in terms of the station-

    wise loss reduction trajectory approved by the Commission in its Tariff Order for FY

    2003-04.

    ATE directed the Commission to engage an appropriate agency/ies either on its own or

    through MSPGCL, to carry out a study in a time bound manner (preferably within three

    months) to reasonably assess the achievable heat rate of the plants owned by MSPGCL

    and to suggest measures to improve the heat rates over a period of time. ATE further

    directed the Commission to determine the heat rate based on the outcome of the study

    and directed that the pre-existing tariffs may be continued, subject to truing up based on

    the revised heat rates, when available.

    ATE directed the Commission to take into consideration the independent study and reset

    the operating parameters, viz., transit loss of coal, station heat rate, auxiliary

    consumption, and secondary fuel oil consumption, and align its Regulations by

    prescribing achievable norms and not merely ideal norms. ATE also advised the

    Commission to ensure that deliberate inefficiencies on the part of the Utility are not

    passed on to the consumers.

    Regarding the tariff for small hydro power stations, the ATE stipulated that fixed chargeas determined by the Commission is subject to change only on account of re-

    determination of the lease rent payable to Government of Maharashtra and change in the

    working capital on account of the change in the expenses towards lease rentals.

  • 8/3/2019 Order Case 102 of 2009

    10/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 10 of121

    ATE rejected MSPGCLs appeal for entitlement of higher tariff for small hydro projects

    as the Commissions Order in this regard is applicable only in the case of new projects.

    The ATE also did not agree with MSPGCLs contention that the Commission has

    disregarded the provisions of Section 61 (h) of the Electricity Act, 2003, while

    undertaking the tariff fixation of small hydro projects.ATE upheld MSPGCLs appeal for monthly billing of the incentives and held that any

    under or over recovery on account of such claims may be adjusted on monthly basis.

    ATE upheld MSPGCLs appeal as regards truing up of actual fuel expenses till such time

    the re-assessed improvement trajectory of performance parameters is available.

    ATE upheld MSPGCLs appeal as regards truing-up of depreciation, while ruling that if

    the Commission has allowed any extra recovery in the past under the head of

    depreciation, the same may be adjusted.

    ATE, while allowing the truing up of other debits due to bad debts written off, held that

    o Both, MSPGCL and the consumers may bear the burden on this account, andhence, the sum to be recovered from the consumers may be spread over a period

    of three years, without any interest, to lessen the burden on the consumers.

    However, the above cannot be taken as a precedent for making similar claims in

    the future.

    o The Commission should examine the claim of MSPGCL for truing up on accountof miscellaneous losses and write off, sundry expenses, intangible assets writtenoff and intangible assets interest charges for HVDC, subject to prudence check.

    ATE directed the Commission to consider the interest on working capital on normative

    basis for FY 2005-06.

    As regards truing up of other income, the ATE ruled that if the other income cannot be

    reasonably linked to any cost item allowed by the Commission as a part of the ARR, the

    same should not be adjusted against the ARR of MSPGCL.

    As regards O&M expenses, ATE directed MSPGCL to take up the claim for base O&M

    expense for FY 2006-07 based on the audited accounts subject to prudence check as

    submitted by the Commission during the course of proceedings before the ATE.

  • 8/3/2019 Order Case 102 of 2009

    11/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 11 of121

    ATE directed the Commission to devise a mechanism, which addresses the concern of

    peak and off peak generation from hydel stations, by determining the ratio of peak and

    off-peak generation after taking into consideration the operational capacity of MSPGCL

    and system pattern.

    ATE held that since MSPGCL is incurring additional expenditure without being

    compensated for extending support for reactive energy generation/absorption for grid

    stability, the Commission should either work out a scheme specifically for State power

    generators for compensation for incurring the additional expenditure or extend the

    incentive/penalty mechanism applicable for transmission licensees, distribution licensees

    and open access users, to the State generators.

    ATE rejected MSPGCLs request to set aside the norm for O&M expenses set by the

    Commission for old hydel plants and ruled that since the existing hydro electric plants are

    not covered by the Policy of the Government, it will be inappropriate to compare the

    O&M expenses of the existing plants with that of the new hydel stations covered under

    MERC Tariff Regulations.

    ATE directed the Commission to consider the issue of employee incentive schemes in

    accordance with law.

    The ATE, in view of the above findings/observations, set aside the impugned Tariff Orders

    and allowed the appeals partially, and remitted the matter back to the Commission for re-

    determination of the tariff for MSPGCL. The Commission asked MSPGCL to submit the

    impact of the ATE Judgment for each year separately along with appropriate reasons and

    justification as follows:

    Impact on Truing up of Revenue and Expenses for FY 2005-06

    Impact on Truing up of Revenue and Expenses for FY 2006-07

    Impact on Revised estimates of expenses for FY 2007-08

    Impact on Projected Expenses for FY 2008-09

    The Commission, in the APR Order for FY 2007-08 in Case No. 71 of 2007, has ruled as

    under:

  • 8/3/2019 Order Case 102 of 2009

    12/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 12 of121

    The Commission is of the view that as the Orders of the Commission have been setaside

    and the ATE in its Order has directed the Commission to re-determine the tariff, and as

    the original Orders in both the cases, i.e., ARR and Tariff Determination for FY 2006-07

    and MYT Order for the first Control Period, i.e., FY 2007-08 to FY 2009-10 were issued

    after following the due public process including public hearing, the re-determination of ARR and tariff for MSPGCL needs to be undertaken after following the due public

    process including public hearing. The Commission will initiate a separate process for re-

    determination of tariff for MSPGCL for FY 2005-06, 2006-07 and FY 2007-08. However,

    this Order has to be issued, since the tariff payable to MSPGCL is a major input cost to

    MSEDCL, and the Order of MSEDCL cannot be delayed till such time the complete data

    is submitted by MSPGCL and the due regulatory process is followed to revise the tariff of

    MSPGCL.

    As regards norms for performance parameters, viz., transit loss of coal, station heat rate,

    auxiliary consumption, and specific oil consumption of MSPGCLs generating stations,

    ATE directed the Commission to undertake an independent study, either through

    MSPGCL or on its own, and reset the operating parameters and align its Regulations by

    prescribing achievable norms and not merely ideal norms after taking into consideration

    the results of such independent study. ATE, in its Order, has also mentioned that till such

    time the Commission re-determines the Station Heat Rate, MSPGCL may continue with

    the pre-existing tariff, subject to truing up when revised Station Heat Rates when

    available. The Commission, abiding by the directions of ATE, will engage an appropriateindependent agency to carry out independent study to reasonably assess the achievable

    performance of MSPGCL stations and to suggest the measures to improve the

    performance over a period of time. Based on the outcome of the study, the Commission

    will re-determine the performance parameters of MSGPCL's generating stations, whether

    higher or lower than the norms stipulated in the Tariff Regulations and norms approved

    in the Tariff Orders, and will carry out the truing up of MSPGCL's expense and revenue

    based on re-determined performance parameters.

    Further, the impact of directions of ATE in respect of following heads of expenses and revenue

    needs to be assessed based on additional information/clarifications:

    A&G Expenses

    Truing up of Depreciation for FY 2005-06

  • 8/3/2019 Order Case 102 of 2009

    13/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 13 of121

    Truing up of Other Debits for FY 2005-06

    Truing up of Interest and Finance Charges for FY 2005-06

    Truing up of Revenue earned in FY 2005-06

    Truing up of non-tariff income earned in FY 2005-06 and FY 2006-07

    Compensation for Reactive Energy generation.

    The Commission, in its Order dated April 25, 2007 on MYT Petition for the first Control Period,

    has already undertaken the final truing up of expenses and revenue for FY 2005-06. However,

    consequent to ATE Order, the truing up of expenses and revenue for FY 2005-06 will have to be

    undertaken again considering the ATEs directions and based on impact and additional

    information/clarifications submitted by MSPGCL. The Commission is of the view that it will be

    preferable to carry out the truing up of all elements of expenses and revenue for FY 2005-06

    once again based on impact of truing up and additional information/clarifications from

    MSPGCL and after following due public process. The Commission has therefore not undertaken

    the truing up of expenses and revenue for FY 2005-06 again in this Order. The Commission,

    after following the due public process, will issue an Order which will deal with the truing up of

    all the elements of expenses and revenue for FY 2005-06.

    The truing up of expenses and revenue for FY 2005-06 will have certain implications on ARR for

    FY 2006-07 and for subsequent years. The O&M expenses for FY 2005-06 approved after truing

    up, will have a bearing on allowable O&M expenses in subsequent years. Similarly, the truing

    up of depreciation for FY 2005-06 may have effect on depreciation expenses to be allowed for

    FY 2006-07 and subsequent years. As regards truing up of fuel expenses for FY 2006-07, the

    Commission is of the view that MSPGCL has already recovered variation in fuel prices through

    the FAC mechanism and truing up of fuel expenses on account of variation in performance

    parameters has to be examined based on approved performance parameters upon completion of

    study by independent agency. The Commission, in this Order, has therefore undertaken the

    truing up of certain expenses and revenue for FY 2006-07. The Commission will undertake the

    final truing up of expenses and revenue for FY 2006-07 along with truing up of expenses and

    revenue for FY 2005-06 and re-determination of performance parameters."

  • 8/3/2019 Order Case 102 of 2009

    14/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 14 of121

    Subsequently, the Commission appointed M/s Central Power Research Institute (CPRI) to carry

    out a detailed study of the various performance parameters in accordance with the Honble

    Tribunals Judgment in Appeal Nos. 86 and 87 of 2007.

    Based on the draft report submitted by CPRI, the Commission observed certain differences in thefigures of actual station heat rate and other performance parameters as provided by MSPGCL to

    CPRI and as submitted by MSPGCL under its APR Petitions under affidavit. The Commission,

    vide its letter dated December 30, 2009, asked MSPGCL to submit the reasons for the

    differences between the actual performance parameters as recorded by CPRI based on the station

    records and as submitted by MSPGCL for selected Stations under its APR Petitions. MSPGCL

    submitted its replies vide its letter dated January 5, 2010. Further, the Commission, vide letter

    dated January 5, 2010 asked MSPGCL to submit the impact of the Honble Tribunals directives

    and the CPRIs report, which was submitted by MSPGCL on January 8, 2010.

    1.6 COMMISSION'S ORDER IN THE MATTER OF TRUING UP PROCESS FORMSPGCL FOR FY 2005-06, FY 2006-07 & FY 2007-08 BASED ON APPELLATE

    TRIBUNALS JUDGMENT AND CPRI REPORT.

    For undertaking the final truing up of expenses and revenue, the Commission asked MSPGCL to

    submit the impact of the ATE Judgment and accordingly submit the year-wise truing up

    requirement from FY 2005-06 onwards. MSPGCL submitted the year-wise truing up

    requirement from FY 2005-06 onwards considering the impact of the ATE Judgment and CPRIReport, on January 8, 2010.

    The Order in Case No. 16 of 2008 was issued on March 5, 2010 based on Appellate Tribunals

    Judgment in Appeal No. 86 and 87 of 2007 and CPRI Report. The Commission, in its Order

    dated March 5, 2010 approved the truing up of expenses and revenue for MSPGCL for FY 2005-

    06, FY 2006-07 and FY 2007-08 and provisional truing up of certain elements of the Annual

    Fixed Cost and variable charges for FY 2008-09, considering the re-setting of norms of various

    performance parameters and change in the normative expenses, if any, for FY 2008-09.

  • 8/3/2019 Order Case 102 of 2009

    15/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 15 of121

    1.7 PETITION FOR ANNUAL PERFORMANCE REVIEW FOR FY 2009-10 ANDDETERMINATION OF TARIFF FOR FY 2010-11

    In accordance with Regulation 9.1 of the MERC Tariff Regulations, the application for the

    determination of tariff has to be made to the Commission not less than 120 days before the date

    from which the tariff is intended to be made effective. Further, the first proviso to Regulation 9.1states that the

    date of receipt of application for the purpose of this Regulation shall be the date of intimation

    about the receipt of a complete application in accordance with Regulation 8.4 above:

    MSPGCL submitted its Petition for APR for FY 2009-10 and tariff determination for FY 2010-

    11 on December 31, 2009, based on actual audited expenditure for FY 2008-09, actual

    expenditure for first half of FY 2009-10, i.e., from April to September 2009 and revised

    estimated expenses for October 2009 to March 2010, and projections for FY 2010-11. MSPGCL,

    in its Petition, requested the Commission to

    Undertake truing up for FY 2008-09 based on actual audited data and normative

    parameters as applicable for various heads of expenditure;

    Approve the revised ARR for FY 2009-10 and FY 2010-11 in accordance with the

    submissions and rationale given in the Petition;

    Approve the tariff of its generating stations for FY 2010-11;

    Allow MSPGCL to apply the tariff approved by the Commission from the beginning of

    FY 2010-11.

    Subsequently, MSPGCL in its additional submission dated April 8, 2010 requested the

    Commission to approve provisional tariff for Paras Unit4 and Parli Unit-7.

    The Commission, vide its letter dated January 29, 2010, forwarded the preliminary data gaps and

    information required from MSPGCL. MSPGCL submitted its replies to preliminary data gaps

    and information requirement on February 11, 2010 and March 4, 2010. The Commission held a

    Technical Validation Session (TVS) on MSPGCLs Petition for approval of APR for FY 2009-

    10 and Tariff for FY 2010-11, on February 15, 2010 in the presence of Consumer

    Representatives authorised under Section 94(3) of the EA 2003 to represent the interest of

    consumers in the proceedings before the Commission.

  • 8/3/2019 Order Case 102 of 2009

    16/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 16 of121

    The list of individuals, who participated in the TVS, is provided at Appendix-1. During the

    TVS, the Commission directed MSPGCL to provide additional information and clarifications on

    the issues raised during the TVS. The Commission also directed MSPGCL to submit the draft

    Public Notice in English and Marathi in the format prescribed by the Commission.

    1.8 ADMISSION OF PETITIONS AND PUBLIC PROCESSMSPGCL submitted its responses to the queries raised during the TVS on February 15, 2010.

    MSPGCL submitted the replies to queries raised during TVS on March 22, 2010 and the

    Commission admitted the APR Petition of MSPGCL on April 8, 2010. MSPGCL also submitted

    supplementary petition dated April 08, 2010 submitting impact of additional import of coal and

    asking for provisional true up for Paras unit 4 and Parli unit 7. In accordance with Section 64 of

    the EA 2003, the Commission directed MSPGCL to publish its application in the prescribedabridged form and manner, to ensure adequate public participation. The Commission also

    directed MSPGCL to reply expeditiously to all the suggestions and comments received from

    stakeholders on its Petition. MSPGCL published the Public Notice in Business Standard, Indian

    Express, Sakal and Maharashtra Times newspapers on April 12, 2010, inviting suggestions and

    objections from stakeholders on its APR Petition. The copies of MSPGCL's Petition and its

    Executive Summary were made available for inspection/purchase to members of the public at

    MSPGCL's offices and on MSPGCL's website (www.mahagenco.in). The copy of the Public

    Notice and the Executive Summary of the Petition was also uploaded on the website of the

    Commission (www.mercindia.org.in) in downloadable format. The Public Notice specified that

    the suggestions and objections, either in English or Marathi, may be filed in the form of affidavit

    along with proof of service on MSPGCL. The Commission received written suggestions and

    objections expressing concerns on O&M expenses, performance parameters, fuel expenses, etc.

    The Public Hearings were held at the following six locations across the State as per the given

    schedule:

    Sl. Place/Venue of Public Hearing Time Date of

    Hearing1 Amravati:

    Hall No. 1, Divisional Commissioner's Office Camp,Amravati, District - Amravati

    11.00

    hours

    Friday, May

    14, 2010

  • 8/3/2019 Order Case 102 of 2009

    17/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 17 of121

    Sl. Place/Venue of Public Hearing Time Date of

    Hearing

    2 Nagpur:Vanamati Hall, V.I.P Road, Dharampeth, Nagpur,

    District - Nagpur

    11.00

    hours

    Saturday, May

    15, 2010

    3 Nashik:Office of the Commissioner, Niyojan Bhavan, NasikRevenue Division, Nashik Road, Nashik - 422101

    11.00

    hours

    Monday, May

    17, 2010

    4 Pune :Council Hall, Office of the Divisional Commissioner,Pune, District - Pune - 411011

    11.00

    hours

    Wednesday,

    May 19, 2010

    5 Aurangabad:Meeting Hall, Office of the Divisional Commissioner,

    Aurangabad, District - Aurangabad

    11.00

    hours

    Friday, May

    21, 2010

    6 Navi Mumbai:Conference hall, 7th Floor, CIDCO Bhavan, CBD,

    Belapur, Navi Mumbai - 400614

    11.00hours Saturday, May22, 2010

    The list of objectors, who participated in the Public Hearing, is provided in Appendix- 2.

    The Commission has ensured that the due process, contemplated under law to ensure

    transparency and public participation, has been followed at every stage meticulously and

    adequate opportunity was given to all the persons concerned to file their say in the matter. This

    Order deals with the truing up for FY 2008-09, APR of FY 2009-10 and determination of tariff

    of MSPGCL for FY 2010-11. Various suggestions and objections that were raised on

    MSPGCLs Petition after issuing the Public Notice, both in writing as well as during the Public

    Hearing, along with MSPGCLs response and the Commissions rulings have been detailed in

    Section 2 of this Order.

    1.9 ORGANISATION OF THE ORDERThis Order is organised in the following six Sections:

    Section 1 of the Order provides a brief history of the quasi-judicial regulatory process

    undertaken by the Commission. For the sake of convenience, a list of abbreviations with their

    expanded forms has been included.

  • 8/3/2019 Order Case 102 of 2009

    18/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 18 of121

    Section 2 of the Order lists out the various objections raised by the objectors in writing as well as

    during the Public Hearing before the Commission. The various objections have been

    summarized, followed by the response of MSPGCL and the rulings of the Commission on each

    of the issues.

    Section 3 of the Order details the Commission's analysis and ruling on MSPGCLs proposal for

    final truing up of expenses and revenue for FY 2008-09.

    Section 4 of the Order details the performance parameters as approved by the Commission in

    MYT Order for first Control Period, MSPGCLs proposal for performance parameters during FY

    2009-10 and FY 2010-11 and the Commissions approved performance parameters for FY 2010-

    11.

    Section 5 of the Order comprises the review of performance for FY 2009-10 (including

    provisional truing up) and the Commission's analysis of various components of Energy Charges

    and Annual Fixed Charges of MSPGCLs Stations for FY 2010-11.

    Section 6 of the Order details the tariff design for MSPGCLs Stations and the approved Annual

    Fixed Charges and Energy Charges for FY 2010-11.

  • 8/3/2019 Order Case 102 of 2009

    19/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 19 of121

    2 OBJECTIONS RECEIVED, MSPGCLS RESPONSE AND COMMISSIONSRULING

    2.1 Non Compliance to MYT frameworkM/s Vidarbha Industries Association and M/s ISPAT Industries Limited submitted that the

    Petition filed by MSPGCL should be filed under Multi Year Tariff. MSPGCL had to file Petition

    for 5 years based on future projections; however, they have filed for FY 2010-11 only.

    MSPGCLs Response

    MSPGCL submitted that it did not file a MYT Petition, as the first Control Period under MYT

    framework was pertaining to the period from FY 2007-08 to FY 2009-10. The new MYT

    Regulations are yet to be finalized by the Commission. Moreover, the single year APR Petition

    for FY 2010-11 was filed based on the directive of the Commission.

    Commissions Ruling

    The Commission has initiated the process of framing new MYT Regulations for the next Control

    Period. In the meantime, the Commission directed the Generating Companies and Utilities to file

    ARR and Tariff Petition for FY 2010-11 and accordingly, MSPGCL has filed a single year

    Petition for approval of Annual Performance Review for FY 2009-10 and tariff for FY 2010-11.

    2.2 Inadequate Time for Filing Suggestions and ObjectionsM/s Vidarbha Industries Association and ISPAT Industries Limited submitted that the Petitioner

    has failed to comply with the requirement of timely submission of its filings. The analysis of

    Petition and its implications on the consumers requires substantial amount of time and effort and

    adequate time has not been provided to the public for filing their comments.

    MSPGCLs Response

    MSPGCL submitted that it was awaiting the finalization of the MYT Regulations for the next

    Control Period, under which, an MYT Petition was envisaged to be filed during the year.

    However, pending finalization of the same, based on the directive of the Commission, MSPGCLhas met the deadline for December 31, 2009 for filing the said Petition.

    Commissions Ruling

  • 8/3/2019 Order Case 102 of 2009

    20/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 20 of121

    As mentioned in Section 1 of the Order, MSPGCL submitted its Petition for approval of Annual

    Performance Review for FY 2009-10 and tariff determination for FY 2010-11 on December 31,

    2009. The Commission communicated the data gaps in the Petition and held a Technical

    Validation Session on MSPGCLs Petition, in the presence of authorised Consumer

    Representatives. Upon submission of revised Petition by MSPGCL incorporating the additionalinformation and replies to queries raised by the Commission, the Petition was admitted for

    further public process on April 8, 2010. The Commission directed MSPGCL to host the detailed

    Revised APR Petition and formats in MS Excel on its website for easy download by interested

    stakeholders.

    The Public Notice was published on April 12, 2010 in leading newspapers and the public

    hearings were scheduled from May 14, 2010 to May 22, 2010. Thus, adequate time, as envisaged

    under the Regulations has been provided to stakeholders to submit their views/suggestions beforethe Public Hearing, and additional time of 7 days was also provided to file rejoinders. In any

    case, since tariff determination is a time bound exercise under Section 64 of the EA 2003, no

    further relaxation of time could be made for submission of suggestions and objections by the

    public in the interests of consumers as the same would have resulted in delay in issuing of the

    Tariff Order.

    2.3 Capital Expenditure and CapitalisationM/s ISPAT Industries Limited, M/s Vidarbha Industries Association and others submitted that

    actual Capital Expenditure (capex) incurred in FY 2008-09 is higher than that approved by the

    Commission, whereas, the estimated figures for capex for FY 2009-10 have been doubled as

    compared to approved MYT Petition. MSPGCL should submit the reasons behind delayed

    capitalisation of expenses and to submit the reasons behind considerable increase in the capital

    expenditure in FY 2010-11.

    M/s Vidarbha Industries Association, M/s ISPAT Industries Limited and others submitted that

    there is a gap between the actual capitalisation provided in the workings and the amount

    approved by the Commission. For FY 2007-08, the audited capitalisation figures are lower than

    approved amount, whereas in FY 2008-09, the audited capitalisation is higher than that approved

    by the Commission.

  • 8/3/2019 Order Case 102 of 2009

    21/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 21 of121

    Further, the non-capitalisation of certain projects leads to non-accrual of benefits and affects the

    performance of the Utility. The excess capitalisation over approved amount has not been justified

    by any description of physical progress. Hence, they requested the Commission to direct

    MSPGCL to provide the justification on physical progress of projects and justification of

    projections for FY 2010-11.

    MSPGCLs Response

    MSPGCL submitted that there are several schemes that are currently being implemented in

    various power stations. It may be appreciated that at times, the parts for such old generating

    assets are not readily available and therefore, need to be manufactured using reverse engineering

    techniques. This sometimes leads to delay in ordering, causing spillover of the schemes to the

    next financial year.

    Regarding the increase in projected Capex for FY 2010-11, MSPGCL submitted that it is in the

    process of implementing the recommendations made by M/s CPRI for bringing in technical

    improvements in the stations. MSPGCL is preparing the DPRs for such schemes, which will be

    submitted to the Commission for approval shortly.

    MSPGCL submitted that the consumer has produced tables, which represent that the actual

    capitalization is either lower than the approved capitalization or vice versa. In this regard,

    MSPGCL submitted that the capitalization of a scheme depends upon the month in which the

    scheme is implemented. A scheme, if started in May (say) may get capitalized in the month of

    November (assuming that the implementation period is around 6 months). However, in case due

    to some practical difficulties, the scheme gets started in the month of December, it will get

    capitalized only in the next financial year even if the implementation period remains the same. In

    certain cases, the requirement of reverse engineering for very old assets may require complete

    spillover of the scheme to the next financial year. Besides, spillover may also happen in case

    adequate time for shut down of Units is not available on account of persistent grid shortages.

    Under such cases, the schemes are bundled to be undertaken as soon as MSPGCL gets an

    opportunity in the planned overhauls. Due to such practical reasons, the actual capitalization of

    the scheme may deviate from the approved capitalization.

    MSPGCL has transparently submitted the details of capex incurred during the previous year,

    expected capex during the current year and likely capital expenditure in the ensuing year. All

    such details have been provided in Forms F5.3 and F5.4 of the main submission. MSPGCL

  • 8/3/2019 Order Case 102 of 2009

    22/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 22 of121

    submits that apart from the DPR schemes, which are examined in detail by the Commission, bulk

    of the capital expenditure comprises of small schemes, which do not have much scope of cost

    overrun. However, with the recent directive of the Commission, even such small schemes are to

    be clustered and will get classified into the DPR schemes, which will also get monitored by the

    Commission in the long run. With such regulatory arrangements in place, it is expected that theapprehensions of the consumers will get answered more explicitly.

    As far as projection of capex and capitalisation during FY 2010-11 is concerned, MSPGCL

    submitted that the capex is based on the recommendations of M/s CPRI and subject to approval

    of the Commission, the projected capex may get capitalised to a large extent. The capex planned

    in FY 2010-11 is subject to approval of the Commission and the actual progress will be

    submitted in the subsequent Petition of MSPGCL.

    Commissions Ruling

    The Commission has taken note of the concerns raised by several stakeholders regarding the

    capital expenditure being undertaken by MSPGCL, and the impact of the same on the tariff. The

    Commission has carried out a detailed analysis of the capital expenditure and capitalisation and

    the treatment of the same on tariff in Section 5 of this Order. The Commissions computations in

    this regard have been elaborated subsequently in Section 3 on truing up of expenses and revenue

    for FY 2008-09 and in Section 5 while approving the revised revenue requirement for FY 2009-

    10 and FY 2010-11.

    2.4 Interest ExpensesM/s ISPAT Industries Limited, M/s Vidarbha Industries Association and others submitted that

    the interest expenses shown are very high (the interest rate for some of the loans is as high as 15-

    17%), and MSPGCL should submit the reasons behind the high interest bearing loans along with

    loan drawal and repayment information.

    MSPGCLs Response

    MSPGCL submitted that there had been a levy of Debt Restructuring premium charged to

    revenue. On addition of such premium, the net interest expenses appears to be on the higher side.

    The actual interest rates are not higher than 13-14% in any case.

    Further, MSPGCL has been submitting copies of loan agreements to the Commission as and

    when required, for prudence check by the Commission. MSPGCL understands that the

  • 8/3/2019 Order Case 102 of 2009

    23/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 23 of121

    Commission will undertake the necessary prudence check before allowing such interest expenses

    as part of the tariff.

    Commissions Ruling

    The Commission has examined the interest expenses for FY 2008-09 in Section 3 while carrying

    out the truing up, and for FY 2009-10 and FY 2010-11 in Section 5 of the Order. The

    Commission has considered the addition to the loans corresponding only to the schemes

    approved by the Commission and hence, the interest expenses as approved by the Commission

    have reduced substantially as compared to interest expenses projected by MSPGCL.

    2.5 Depreciation Including Advance Against DepreciationM/s Vidarbha Industries Association, M/s ISPAT Industries Limited and others

    submitted that MSPGCL has not followed the MERC Tariff Regulations for computing

    depreciation including AAD. MSPGCL has stated that the apportionment has been done on the

    basis of capacity of individual plants. It is inappropriate for the Utility to carry out such

    segregation based on capacity of the plant. Further, it is observed that the depreciation projected

    by MSPGCL is around Rs. 341.18 crore, which is much higher than the actual loan repayment of

    Rs. 199.84 crore in FY 2008-09 as per audited accounts. Therefore, MSPGCL should submit the

    reasons behind AAD sought by MSPGCL.

    MSPGCLs Response

    MSPGCL submitted that the issue of AAD is sub-judice in Appeal 191 of 2009 and MSPGCL

    will abide by the decision of the ATE. However, MSPGCL has submitted the entire rationale for

    asking AAD in its Petitions. MSPGCL has been requesting the Commission to work out

    appropriate methodology for rational allocation of loan.

    Commissions Ruling

    The Commission, in accordance with the treatment in previous Orders, has not computed the

    advance against depreciation by allocating loans to various stations as the basic objective of the

    advance against depreciation is to provide cash shortfall for meeting the repayment obligations,

  • 8/3/2019 Order Case 102 of 2009

    24/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 24 of121

    and for the Company as a whole, the total depreciation allowed by the Commission is much

    higher than the total repayment.

    2.6 O&M Expense ProjectionsM/s Vidarbha Industries Association, M/s ISPAT Industries Limited and others

    submitted that the MERC Tariff Regulations clearly stipulates the methodology for calculating

    O&M expenditure, and projections made by MSPGCL are not in line with the specified

    methodology.

    The Commission adopted a different methodology to arrive at the escalation rate of 5.38%

    whereas; MSPGCL has varied even from this, to arrive at the escalation rate of 6.1%.

    In the APR Petition, MSPGCL has pointed out that barring the new items in FY 2008-09 the

    base O&M expense has actually increased by 2.88%. The purpose of allowing an escalation was

    to enable the Petitioner to create provisions for future liabilities that might occur. The actual

    escalation in base O&M expense by MSPGCL was only 2.88%, thus, the additional escalation

    being allowed should have been used to meet future liabilities.

    MSPGCLs Response

    MSPGCL submitted that the base expenses of FY 2006-07 have been considered for the purpose

    of estimation of approved O&M expenses from FY 2007-08 onwards. The Commission agreed

    to the rationale submitted by MSPGCL that the O&M expenses on generation assets during the

    erstwhile MSEB period were on the lower side. Further, the escalation rates have been worked

    out by the Commission based on CPI and WPI indices in the MYT Order. MSPGCL submitted

    that the base expenses of FY 2006-07 have been considered for the purpose of estimation of

    approved O&M expenses from FY 2007-08 onwards.

    MSPGCL submitted that the escalation rate has been computed correctly. However, the same

    may be examined by the Commission for prudence. Escalation rates are applied to cover the

    expenses envisaging certain increase in base year expenses. Working out such expenses on the

    conservative side may have financial impact on the working of the Utility. In any case, MSPGCL

    understands that such charges are subject to true-up and are not entirely retained by the Utility.

    MSPGCL submitted that the actual increase in O&M expenses, excluding expenses that result in

    an increase in the base year expenses (viz., leave encashment, etc.) is around 2.88%.

  • 8/3/2019 Order Case 102 of 2009

    25/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 25 of121

    MSPGCL submitted that for FY 2008-09, the impact of pay revision arrears has been considered

    as Rs 95 Crore.

    MSPGCL submitted that the items considered under Repairs and Maintenance expenses are

    recurring in nature and are essentially consumable items. The one-time expenses are largely

    considered as part of the capex schemes for which, a separate claim is being placed. MSPGCL

    submitted that the annual accounts are verified by statutory auditors and are also subject to

    prudence check by the Commission. Being a public Company, MSPGCL is following all

    accounting practices as per the applicable laws/rules. MSPGCL is open to share the details of the

    accounts in case required by the Commission for undertaking any prudence check of the same.

    Commissions Ruling

    The Commission, in its Order dated March 5, 2010 in Case No. 16 of 2008 carried out the truing

    up of O&M expenses for FY 2005-06 and FY 2006-07. In accordance with the ATE Judgment in

    Appeal No. 86 and 87 of 2007, the Commission in its Order dated March 5, 2010 considered the

    actual expenses for FY 2006-07 as base expenses and revised the O&M expenses for the first

    Control Period i.e., from FY 2007-08 to FY 2009-10.

    The Commission, in this Order, for carrying out the truing up of O&M expenses for FY 2008-09

    has considered the revised O&M expenses approved in its Order dated March 5, 2010 as base

    O&M expenses. The Commission has also considered the pay revision arrears as submitted by

    MSPGCL. The details of O&M expenses approved by the Commission for FY 2008-09 after

    sharing of gains and losses as per provisions of MERC Tariff Regulations are discussed in

    Section 3 of the Order.

    2.7 Earned Leave EncashmentM/s Vidarbha Industries Association, M/s ISPAT Industries Limited and others

    submitted that allowing escalation in cost is to enable the MSPGCL to make yearly provisions

    for future costs including pay revision. However, MSPGCL has asked for Rs. 35.47 Crore

    additional cost for earned leave encashment amortisation over and above the escalation.

    MSPGCLs Response

    The Commission, in its APR order dated August 17, 2009, had allowed Rs 177.37 Crore towards

    provisioning for earned leave encashment liability towards existing power stations of MSPGCL,

  • 8/3/2019 Order Case 102 of 2009

    26/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 26 of121

    but had stipulated that such expense would be spread over five years starting from FY 2007-08.

    Accordingly, the Petitioner has added the impact of earned leave encashment liability for FY

    2009-10 and FY 2010-11 at Rs 35.47 Crore each year.

    Commissions Ruling

    The Commission agrees with the MSPGCLs reply in the matter and the Commission has also

    considered the same while approving the O&M expenses for FY 2009-10 and FY 2010-11.

    2.8 Material Cost VarianceM/s ISPAT Industries Limited and others submitted that the primary expense on this account has

    been incurred for recognising loss on account of old stores. The amount of Rs. 59.23 Crore

    cannot be established from annual accounts provided along with the Petition. Holding obsolete

    stock to an extent of Rs. 59.23 Crore signifies that the management is unable to utilise the stock

    in an efficient manner leading to deterioration of assets.

    Further, MSPGCL has requested for a true up of Rs. 0.10 crore on account of bad debts written

    off. In FY 2008-09 MSPGCL also incurred additional O&M and Coal cost. Therefore, the

    Objectors requested the Commission to direct MSPGCL to undertake proper steps to avoid

    additional expenditure and disallow the same.

    MSPGCLs Response

    MSPGCL submitted that material cost variance is an integral part of the core business of theCompany, and therefore, any such incidental expenses needs to be allowed in the tariff.

    There is significant expense on account of recognition of loss on obsolescence of old stores. The

    statutory auditors of MSPGCL had observed that the company had not made any provision on

    slow moving, non-moving, obsolete and damaged items of stock". Accordingly MSPGCL has

    made a provision equivalent to 100% value of obsolete stock, 60% value of non-moving stock

    and 30% value of slow-moving stock in its audited accounts amounting to Rs 57.64 crore.

    MSPGCL submitted that such items were procured earlier for safe and smooth operations of

    plants, however, the same were not required during the life of such equipments.

    MSPGCL quoted from the Judgment of ATE in Appeal No.s 86 and 87 of 2007 regarding

    recovery of bad and doubtful debts pertaining to MSEB period. ATE had ruled that It can

    reasonably be inferred that had MSEB continued in its earlier form, the Commission would have

  • 8/3/2019 Order Case 102 of 2009

    27/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 27 of121

    taken a decision on the basis of actual facts of the matter but at the same time delay in claiming

    such irrecoverable sums and then passing on the same to paying consumers results into greater

    uncertainties for the consumers. Disallowing any pass through in the form of tariff would have

    an adverse impact of the financial position of the Appellant on the one hand and passing on

    entire non-recovered amount after such a long period to the consumers would not be fair fromthe consumers point of view on the other. Hence, under the circumstances we feel it to be

    reasonable that both, the Appellant and the consumers may bear the burden on this account. The

    sum to be recovered from the consumers may be spread over a period of three years, without any

    interest, to lessen the burden on the consumers.

    In view of the above, MSPGCL should be allowed to recover the bad and a doubtful debt, which

    in this case, generally pertains to advances made to suppliers for implementing various contracts.

    MSPGCL submitted that such costs are incidental to the core business of the Company.

    Moreover, such cost is not even 0.05% of the total ARR of the Company. However, MSPGCL

    endeavours to ensure that there is no such incidence that unnecessarily inflates the cost of its

    operations.

    Commissions Ruling

    The Commission has deliberated on this issue in detail in its Order dated March 5, 2010 in Case

    No. 16 of 2008 while carrying out the truing up of ARR for FY 2005-06, FY 2006-07 and FY

    2007-08 in accordance with the ATE Judgment in Appeal No. 86 and 87 of 2007.

    2.9 Performance Parameters and Variable CostM/s ISPAT Industries and others submitted that in the true up Petition for FY 2008-09,

    MSPGCLprojected fuel cost of Rs. 6952.32 crore against the Commissions approved amount of

    Rs. 6223.15 crore. The reasons provided by MSPGCL are, decrease in gross generation, change

    in GCV and price of the fuel, change in imported coal and washed coal quantities, and deviation

    in technical parameters. Based on the previous submissions made by MSPGCL, one of the

    recurring reasons for increase in fuel cost was higher secondary fuel oil consumption due to wet

    coal related issues during rainy season. Since this is a repetitive situation leading to increase in

    fuel expenses, they requested the Commission to direct MSPGCL to provide information on

    steps taken to overcome this issue.

  • 8/3/2019 Order Case 102 of 2009

    28/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 28 of121

    M/s ISPAT Industries Limited and others submitted that all the actual performance parameters

    of the plant in FY 2008-09 were below approved values, which resulted in increase in variable

    cost by 46% against approved values. They requested the Commission to direct MSPGCL to

    provide reasons for the significant gap between actual PLF and target PLF during April-

    September 2009.

    Further, in compliance with the ATE Judgment, the Commission appointed CPRI to carry out a

    comprehensive study of the operational parameters for variable expenses. Based on CPRI

    Report, MSPGCL has requested to allow the recovery of normative fuel cost of Rs. 6267 crore.

    They requested the Commission to not take the results of the Report and to adhere to the existing

    normative parameters, which are the reflection of the cost and operational effectiveness of

    MSPGCL.

    MSPGCLs Response

    MSPGCL submitted that it has no control on coal getting wet during rail route transportation.

    However, on receipt, MSPGCL is taking all possible measures to retain the quality of coal. The

    stacked coal is covered with tarpaulin in rainy season to avoid deterioration of quality of coal.

    MSPGCL highlighted that in FY 2008-09, on account of the coal shortages, where barely 1-2

    days of coal stock was available with the stations, the quality of coal as received was directly fed

    to the boilers. The problem aggravates during rainy season when wet and sticky coal is directly

    fed for power generation. Such issues with coal cannot be overcome by any power plant

    operator.

    MSPGCL submitted that the Terms of Reference for the appointment of M/s CPRI were decidedby the Commission. The agency had submitted its report to the Commission and the Commission

    has already been apprised of the key findings of the report. The report prescribes implementation

    of certain schemes for improvement in the technical performance. MSPGCL is religiously

    pursuing implementation of such schemes for which detailed DPRs will be submitted to the

    Commission shortly. MSPGCL understands that the performance parameters suggested by CPRI

    adequately address the practical difficulties of MSPGCL and the recommendations of such a

    third party report need to be taken into consideration while deciding on the normative

    performance parameters. It may be highlighted that setting up of optimistic performance

    parameters without taking into cognizance the actual ground conditions has led to significant

    disallowance of fuel cost in the past. The same were however, allowed later, pursuant to the

  • 8/3/2019 Order Case 102 of 2009

    29/121

  • 8/3/2019 Order Case 102 of 2009

    30/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 30 of121

    imported coal. The escalation rates for these sub components as considered by CERC for release

    of payments to the generators show that the escalation in price of coal sub component had been

    as high as 112% during April 2008-Septemeber 2008. In order to avoid such risks in the overall

    process, for procuring its small quantity of imported coal, MSPGCL prefers to enter into short

    term firm price contracts for one year. MSPGCL furthers submitted that the procurement ofimported coal even for the period less than one year, is done through a competitive bidding

    process. Considering the increasing requirement of imported coal, MSPGCL is exploring options

    to procure imported coal on long-term basis and is planning to appoint a Consultant to explore

    different possible options of procurement/tie up of imported coal on long-term basis and cost

    benefit and feasibility study of options.

    Commissions Ruling

    The Commission has addressed the issue of coal prices in Section 5 of the Order while

    determining the Energy Charges. As regards reduction in fuel prices, the Commission has

    obtained and analysed the month-wise actual fuel prices for the period from January 2010 to

    March 2010 and has considered the same for projecting the fuel costs for FY 2009-10.

    2.11 Renovation & Modernisation SchemesM/s Vidarbha Industries Association, M/s ISPAT Industries Limited and others submitted that

    one of the reasons for non-achievement of norms as submitted by MSPGCL was vintage of

    power plants. They requested the Commission to direct MSPGCL to provide the details of

    Renovation & Modernisation schemes.

    MSPGCLs Response

    MSPGCL submitted that several Renovation & Modernization schemes have been planned

    though the aid of World Bank in the XIth

    Plan and the details of the schemes are as follows:

    1. Koradi TPS 210 MW Unit No.62. Chandrapur STPS 210 MW Unit No.1 and 23. Bhusawal TPS 210 MW Unit No.2

  • 8/3/2019 Order Case 102 of 2009

    31/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 31 of121

    4. Parli TPS 210MW Unit No.3

    Besides, MSPGCL is implementing the recommendations of CPRI and for this purpose the capex

    schemes are detailed out in form 5.3 of the petition.

    Commissions Ruling

    The Commission has taken note of Renovation & Modernization schemes planned by MSPGCL

    and the Commission directs the MSPGCL to submit the detailed status of R&M schemes

    planned by it within one month from the date of issue of this Order.

    2.12 Comparative Analysis of MSPGCL and NTPC PlantsM/s Vidarbha Industries Association and M/s ISPAT Industries Limited provided the

    comparison of performance of MSPGCL's stations with NTPC Korba, which is the oldest power

    plant of NTPC commissioned in 1983 and Badarpur, which was commissioned in 1973. They

    submitted that the fixed cost of generation for Paras and Khaperkheda stations are higher than

    that of the NTPC plants. The per unit O&M costs of these plants are also high as compared to the

    same parameters of the NTPC stations.

    MSPGCLs Response

    MSPGCL submitted that the consumers have given a comparison of Paras with that of other

    Units. In this regard, MSPGCL submitted that Paras Unit is under consideration for scrapping

    and the Unit is being run with bare minimum R&M expenses, in order to mitigate the grave

    power shortages in the State. Besides, MSPGCL submitted that it is not correct to compare fixed

    cost per unit or O&M cost per unit of two stations of different capacities. The comparison of

    fixed cost per unit itself holds no meaning because the fixed cost does not increase in proportion

    to the capacity of a station. It is obvious that a 2100 MW Korba Station is likely to produce more

    units. Dividing the fixed cost with such high generation will obviously reduce the per unit fixed

    cost. However, it cannot be used to say if any one of the plants is operating efficiently or not. Forexample, it may be observed that Khaperkheda plant in absolute terms is getting just half the

    O&M expenses in comparison to Korba units. However, in per unit terms, the expenses of

  • 8/3/2019 Order Case 102 of 2009

    32/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 32 of121

    Khaperkheda are relatively higher. Therefore, such comparison may be inconclusive for the

    purpose of comparing the technical performance.

    Commissions Ruling

    The tariff for the generating stations of MSPGCL has been determined in accordance with the

    MERC Tariff Regulations. Further, while inter-Utility comparison has its advantages, there are

    certain disadvantages too, and comparison has to be done between Plants of similar capacity and

    vintage.

    2.13 Lease RentShri N. Ponrathnam, an authorised Consumer Representative, submitted that the concept of

    Hydro Power Generating Stations paying rent to State Government or State Government

    collecting money as lease rent from MSPGCL in any form is illegal and should not be approved.

    Commission Ruling

    The Commission does not find any merit in the objection, as lease rentals are charges to be paid

    by MSPGCL to GoM, as the hydel generating stations are owned by GoM which has given these

    stations on lease to MSPGCL for power generation.

    2.14 Power Purchase AgreementShri N. Ponrathnam submitted that the Power Purchase Agreement (PPA) between MSPGCL

    and MSEDCL should be approved by the Commission. The total generation of MSPGCL is

    purchased by MSEDCL as on date. PPA should be executed to fix the price of electricity and to

    ensure the availability of electricity in the time of shortage. The Fuel Adjustment Cost (FAC)

    Charges should be specified separately in PPA and it should be transparent to the public.

    Commissions Ruling

    As regards the issue of FAC computations, it is clarified that the FAC computations are being

    carried out by Utilities and being vetted on post-facto basis by the Commission in accordance

    with the MERC Tariff Regulations. It is also clarified that the PPA between MSPGCL and

  • 8/3/2019 Order Case 102 of 2009

    33/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 33 of121

    MSEDCL has been approved by the Commission after following the due regulatory process,

    including Public Hearing.

    2.15 Uniform Tariff for all Generating StationsShri. N. Ponrathnam submitted that the electricity is produced by various means such as Hydro

    Power, Thermal Power, Wind Energy, Nuclear Power, Geothermal Energy, Solar Energy, etc.,

    and the cost of generation varies with size of the generating station and the fuel. He suggested

    that the energy produced by coal should be taken as the benchmark tariff (cost of generation of

    electricity supply) and the units generated by all power stations with similar generation profile

    should be charged the same.

    Commissions Ruling

    As regards the suggestion of uniform tariff for all generating stations, the Commission does not

    find any merit in the suggestion, as each generating station has different capital cost based on the

    capacity of the plant and vintage of station, the fuel mix at each generating station is different,

    and landed fuel cost at each generating station varies depending upon the fuel mix and source of

    fuel. In such circumstances, it is not possible to approve uniform tariff across all the generating

    stations, as the generation tariff has to reflect the cost of generation of the respective generating

    station.

    2.16 ARR for Ensuing YearMaharashtra Rajya Veej Grahak Sangathana submitted that approved ARR for FY 2009-10 was

    Rs 9812.29 Crore. For FY 2010-11, the total ARR is estimated at Rs. 11175.34 Crore which is

    higher by Rs.1000 Crore, as compared to ARR approved by the Commission for FY 2009-10.

    Therefore, ARR for FY 2009-10 and 2010-11 should be kept same as that in FY 2008-09, and

    the Commission should not approve inappropriate reduction in generation and inappropriate

    increase in expenditure.

  • 8/3/2019 Order Case 102 of 2009

    34/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 34 of121

    Commissions Ruling

    The Commission does not find any merit in the objection as input cost and other costs are bound

    to vary year on year. Further, the total ARR also depends upon the quantum of power generation

    and if the power generation increases, the ARR is bound to increase. It is clarified that the ARR

    for the generating stations of MSPGCL has been determined in accordance with the MERCTariff Regulations.

  • 8/3/2019 Order Case 102 of 2009

    35/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 35 of121

    3 TRUING UP OF REVENUE REQUIREMENT FOR FY 2008-09MSPGCL, in its Petition for Annual Performance Review for FY 2009-10 and determination of

    tariff for FY 2010-11, has included a Section on the final truing up of expenditure and revenue

    for FY 2008-09 based on actual expenditure as per audited accounts. MSPGCL has provided the

    comparison of actual expenditure with the expenditure approved by the Commission along with

    the reasons for deviations.

    The Commission, in its MYT Order in Case No. 68 of 2006 dated April 25, 2007 stipulated that

    the gains and losses on account of controllable and uncontrollable factors will be shared between

    the Generating Company and the Licensee at the time of truing up of ARR based on actuals, in

    accordance with Regulation 19 of the MERC Tariff Regulations.

    3.1 PERFORMANCE PARAMETERS AND FUEL COSTSMSPGCL, in its Petition, submitted that the total actual fuel cost for FY 2008-09 as per Audited

    Accounts for the existing stations (excluding Paras Unit-3 and Parli Unit-6) was Rs. 6953.32

    Crore (including other fuel related costs of Rs. 270.66 Crore) as against the approved amount of

    Rs. 6223.15 Crore (including other fuel related costs of Rs. 184.82 Crore). MSPGCL submitted

    the key reasons for the deviation in fuel cost as follows:

    Decrease in gross generation,

    Change in GCV and price of fuel,Change in quantities of imported coal and washed coal, and

    Deviation in technical parameters.

    MSPGCL provided the financial impact of each of the above mentioned aspects as given in

    Table below:

    Table: Element-wise impact of deviation on Actual Fuel Cost for FY- 2008-09 (Rs Crore)

    Particulars Impact

    Decrease in gross generation -557Change in GCV and Price of fuel 318

    Change in Imported coal and washed coalquantities -71

  • 8/3/2019 Order Case 102 of 2009

    36/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 36 of121

    Particulars Impact

    Deviation in technical parameters 710

    Change in Gas Quantity & price at Uran 244

    Total Impact 644

    In this regard MSPGCL, submitted as follows:

    a. Decrease in GenerationMSPGCL submitted that the decrease in generation led to a reduction in the overall fuel cost by

    Rs 557 Crore. MSPGCL further submitted that one of the key reasons for reduction in generation

    is because the Commission has considered a PLF of 80% for the purpose of projecting the gross

    generation, however, the actual PLF is significantly lower than the normative PLF for 2008-09.

    MSPGCL submitted that the major reason for reduction in PLF is the increased planned andforced outages of the Units. MSPGCL added that that the reduction in PLF results in an increase

    in auxiliary consumption and secondary fuel oil consumption, which eventually increases the

    effective SHR of the station.

    MSPGCL further submitted that besides the above mentioned reasons, the generation was further

    reduced on account of backing down of stations due to non-availability of transmission lines or

    due to reduction in demand from the system. On this account, MSPGCL was not able to supply

    around 67.39 MU in 2008. MSPGCL submitted that such grid issues not only reduce the net

    generation of the stations, but also lead to significant increase in fuel oil consumption (required

    for flame stability) thereby increasing the Station Heat Rate of the station.

    b. Change in CV and Price of the fuelMSPGCL submitted that the other important factor that led to deviation in fuel cost is the

    variation in fuel price and calorific value of fuel. MSPGCL submitted a comparison of the actual

    price and GCV of the fuel vis--vis that considered by the Commission. MSPGCL submitted that

    the change in calorific value and price of the fuel has led to an increase in fuel cost by

    approximately Rs. 318 Crore.

    c. Change in quantum of imported and washed coal

  • 8/3/2019 Order Case 102 of 2009

    37/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 37 of121

    MSPGCL submitted the actual quantum of imported and washed coal vis--vis the consumption

    considered by the Commission and submitted that that the impact of change in quantity of

    washed coal and imported coal is around Rs. 71 Crore.

    d. Deviation in Performance Parameters of the stationsMSPGCL submitted that the normative performance parameters approved by the Commission

    for the purpose of deriving the variable cost of generation were very optimistic MSPGCL

    submitted that it had contested such optimistic performance parameters before the ATE and as

    per the directions of the ATE, the Commission had appointed M/s CPRI for estimating the

    current level of performance of the stations of MSPGCL and recommend the investments

    required to improve the performance of the Units. CPRI has determined the current level of

    performance of the stations by operating the Units at a load factor of 80% and have considered

    other factors influencing the performance of the Units. Accordingly, CPRI has suggested thecurrent level of performance for such Units, viz., the current SHR and auxiliary consumption and

    has also given an estimate of the stacking losses prevalent at the stations.

    MSPGCL highlighted that if the parameters as derived by CPRI are applied to the actual

    consumption of imported and washed coal and further considering the actual price and CV of

    fuels, the cost as per CPRI parameters is higher than the actual cost of generation as per the

    books of accounts.

    MSPGCL further submitted that the Report submitted by M/s CPRI defined the current state of

    operations of the stations duly taking into account the operational constraints and other ground

    realities. MSPGCL submitted that considering such realistic operational parameters as

    demonstrated in the CPRI report, MSPGCL understands that its claim for true-up in fuel cost

    may be approved by the Commission. However, the above true-up amount pertaining to price of

    the fuel is already recovered in the FAC claims and such recovery of cost will be considered in

    the revenue side true-up and therefore, no separate treatment has been considered by MSPGCL.

    Gross Generation

    The actual gross generation achieved by MSPGCL during FY 2008-09 is 44506 MU as

    compared to gross generation of 48194 MU approved by the Commission in APR Order.

  • 8/3/2019 Order Case 102 of 2009

    38/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 38 of121

    The summary of station-wise gross generation as approved by the Commission in its APR Order

    for FY 2008-09 and actual achieved during FY 2008-09 is given in the Table below:

    Stations

    Gross Generation

    (MU)

    APR Order Actual

    Khaparkheda 5993 6320

    Paras 385 341

    Bhusawal 3329 3042

    Nasik 6167 5698

    Parli 4695 3919

    Koradi 7288 5744

    Chandrapur 16399 15004Uran 3938 4438

    Total 48194 44506

    For the purpose of truing up of expenses and revenue for FY 2008-09, the Commission has

    considered the actual gross generation.

    The Commission approved the Station-wise Availability in its MYT Order for each year of the

    Control Period. The Stations for which MSPGCL projected the availability lower than 80% (i.e.,

    Bhusawal and Parli); the Commission approved the availability of 80%. However, for Uran Gasbased station, considering the short supply of gas, in its MYT Order, the Commission approved

    the availability as projected by MSPGCL for recovery of full fixed charges. For the Control

    Period, the Commission approved the Station-wise PLF considering the PLF projections of

    MSPGCL, and for stations for which MSPGCL projected PLF lower than 80%, the Commission

    considered the PLF of 80%, since in times of severe supply shortage, the PLF will be equal to

    Availability, and full recovery of fixed costs is possible only when the normative availability of

    80% is achieved.

    The Commission, in its Order dated March 5, 2010 in Case No. 16 of 2008, considered the actual

    availability and PLF from FY 2005-06 to FY 2007-08 and did not disallow any amount

    pertaining to Annual Fixed Charges for existing stations on account of lower availability. Further

  • 8/3/2019 Order Case 102 of 2009

    39/121

    Case No. 102 of 2009 MERC Order for MSPGCL for APR of FY 2009-10 and Tariff for FY 2010-11

    MERC, Mumbai Page 39 of121

    the Commission in the said Order stated that From FY 2008-09 onwards, the Commission

    would consider the targets for Unit-wise availability and PLF based on CPRI

    recommendations.

    As regards the availability and PLF, the recommendations made by CPRI in its reports are asfollows:

    Koradi units (1-4) have never exceeded 80 % PLF in their lifetime in spite of de-rating.

    As per steady trends in Figure 3, the Units the achievable PLFs are around 65 %.

    As per the trends Nasik units (1-2) are capable of achieving PLFs of around 75 % after

    de-rating.

    Bhusawal (Unit 1), Paras (Unit 2) and Parli units (1 & 2) are capable of achieving PLF

    of 80 %.

    Units of 210 MW and above can easily achieve the PLF of 80 % with focused attention on coal

    quality, R & M programs, adherence to planned maintenance schedule, leakage control,

    operational optimization, etc.

    Accor