57
# Activity ID Activity Name Original Duration Start Finish 1 ISBL ISBL 0h 2 OSBL OSBL 1576h 01-Jan-15 12:00 AM 07-Mar-15 04:00 PM 3 CGC CGC 700h 01-Jan-15 06:00 AM 28-Feb-15 10:00 AM 4 R15U-000-005 R15U-000-005 RC2-31-099-10-BD-020 - RC2-31-000-43-DCSPDB 0001 IDNETIFY CB 484h 01-Jan-15 06:00 AM 10-Feb-15 10:00 AM 5 PRE-SHUTD PRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 6 OE100000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 7 SHUTDOWN SHUTDOWN 16h 09-Feb-15 06:00 AM 10-Feb-15 10:00 AM 8 OE100005 Obtain PTW 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM 9 OE100010 Verify CB's for the Instrument Dev ice 7h 09-Feb-15 07:00 AM 09-Feb-15 02:00 PM 10 OE100015 Electrical assist for activities in RIE 7h 09-Feb-15 02:00 PM 10-Feb-15 09:00 AM 11 OE100020 Witness and Fix Proper Tag in the Ins truments 1h 10-Feb-15 09:00 AM 10-Feb-15 10:00 AM 12 POST SHUT POST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 13 OE100025 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 14 R15U-000-006 R15U-000-006 RC2-31-099-10-BD-020 - RC2-31-000-43-DCSPDB 0002 IDNETIFY CB 500h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM 15 PRE-SHUTD PRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 16 OE100030 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 17 SHUTDOWN SHUTDOWN 16h 10-Feb-15 10:00 AM 11-Feb-15 02:00 PM 18 OE100035 Obtain PTW 1h 10-Feb-15 10:00 AM 10-Feb-15 11:00 AM 19 OE100040 Verify CB's for the Instrument Dev ice 7h 10-Feb-15 11:00 AM 10-Feb-15 06:00 PM 20 OE100045 Electrical assist for activities in RIE 7h 11-Feb-15 06:00 AM 11-Feb-15 01:00 PM 21 OE100050 Witness and Fix Proper Tag in the Ins truments 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM 22 POST SHUT POST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 23 OE100055 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 24 R15U-000-007 R15U-000-007 RC2-31-099-10-BD-021 - RC2-31-000-43-DCSPDB 0010 IDNETIFY CB 492h 01-Jan-15 06:00 AM 10-Feb-15 06:00 PM 25 PRE-SHUTD PRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 26 OE100060 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 27 SHUTDOWN SHUTDOWN 16h 09-Feb-15 02:00 PM 10-Feb-15 06:00 PM 28 OE100065 Obtain PTW 1h 09-Feb-15 02:00 PM 09-Feb-15 03:00 PM 29 OE100070 Verify CB's for the Instrument Dev ice 7h 09-Feb-15 03:00 PM 10-Feb-15 10:00 AM 30 OE100075 Electrical assist for activities in RIE 7h 10-Feb-15 10:00 AM 10-Feb-15 05:00 PM 31 OE100080 Witness and Fix Proper Tag in the Ins truments 1h 10-Feb-15 05:00 PM 10-Feb-15 06:00 PM 32 POST SHUT POST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 33 OE100085 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 34 R15U-000-008 R15U-000-008 RC2-31-099-10-BD-021 - RC2-31-000-43-DCSPDB 0011 IDNETIFY CB 508h 01-Jan-15 06:00 AM 12-Feb-15 10:00 AM 35 PRE-SHUTD PRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 36 OE100090 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 37 SHUTDOWN SHUTDOWN 16h 11-Feb-15 06:00 AM 12-Feb-15 10:00 AM 38 OE100095 Obtain PTW 1h 11-Feb-15 06:00 AM 11-Feb-15 07:00 AM 39 OE100100 Verify CB's for the Instrument Dev ice 7h 11-Feb-15 07:00 AM 11-Feb-15 02:00 PM 40 OE100105 Electrical assist for activities in RIE 7h 11-Feb-15 02:00 PM 12-Feb-15 09:00 AM 41 OE100110 Witness and Fix Proper Tag in the Ins truments 1h 12-Feb-15 09:00 AM 12-Feb-15 10:00 AM 42 POST SHUT POST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 43 OE100115 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM 44 R15U-000-010 R15U-000-010 RC2-30-000- - CUI FOR OSBL & ISBL PROCESS LINES 700h 01-Jan-15 06:00 AM 28-Feb-15 10:00 AM 45 PRE-SHUTD PRE-SHUTDOWN 346h 01-Jan-15 06:00 AM 29-Jan-15 04:00 PM 46 OM106160 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM 47 OM106165 Erect Scaffolding, wherever reqd. 200h 01-Jan-15 08:00 AM 17-Jan-15 04:00 PM 48 OM106170 Remove Insulation, wherever reqd. 144h 17-Jan-15 04:00 PM 29-Jan-15 04:00 PM 49 SHUTDOWN SHUTDOWN 256h 07-Feb-15 06:00 AM 28-Feb-15 10:00 AM 50 OM106175 Verify LT&T and Obtain PTW 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM 51 OM106180 Carryout buffing on inspection areas 48h 07-Feb-15 10:00 AM 11-Feb-15 10:00 AM 52 OM106185 Carryout CUI on suspected areas 240h 08-Feb-15 10:00 AM 28-Feb-15 10:00 AM 53 OM106190 Further removal of insulation, As per ERG 12h 13-Feb-15 10:00 AM 14-Feb-15 10:00 AM 54 OM106195 Cleaning/ Recoating, As per ERG 48h 14-Feb-15 10:00 AM 18-Feb-15 10:00 AM S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08 RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 57 TASK filters: FILTERS, FILTERS_1. © Oracle Corporation

OSBL-DETAIL EXECUTION SCH-29112014

Embed Size (px)

Citation preview

Page 1: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1 ISBLISBL 0h

2 OSBLOSBL 1576h 01-Jan-15 12:00 AM 07-Mar-15 04:00 PM

3 CGCCGC 700h 01-Jan-15 06:00 AM 28-Feb-15 10:00 AM

4 R15U-000-005 RC2-31-099-10-BD-020 - RC2-31-000-43-DCSPDB 0001 IDNETIFY CB FOR FIELD INSTR15U-000-005 RC2-31-099-10-BD-020 - RC2-31-000-43-DCSPDB 0001 IDNETIFY CB FOR FIELD INST484h 01-Jan-15 06:00 AM 10-Feb-15 10:00 AM

5 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

6 OE100000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

7 SHUTDOWNSHUTDOWN 16h 09-Feb-15 06:00 AM 10-Feb-15 10:00 AM

8 OE100005 Obtain PTW 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM

9 OE100010 Verify CB's for the Instrument Dev ice 7h 09-Feb-15 07:00 AM 09-Feb-15 02:00 PM

10 OE100015 Electrical assist for activities in RIE 7h 09-Feb-15 02:00 PM 10-Feb-15 09:00 AM

11 OE100020 Witness and Fix Proper Tag in the Ins truments 1h 10-Feb-15 09:00 AM 10-Feb-15 10:00 AM

12 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

13 OE100025 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

14 R15U-000-006 RC2-31-099-10-BD-020 - RC2-31-000-43-DCSPDB 0002 IDNETIFY CB FOR FIELD INSTR15U-000-006 RC2-31-099-10-BD-020 - RC2-31-000-43-DCSPDB 0002 IDNETIFY CB FOR FIELD INST500h 01-Jan-15 06:00 AM 11-Feb-15 02:00 PM

15 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

16 OE100030 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

17 SHUTDOWNSHUTDOWN 16h 10-Feb-15 10:00 AM 11-Feb-15 02:00 PM

18 OE100035 Obtain PTW 1h 10-Feb-15 10:00 AM 10-Feb-15 11:00 AM

19 OE100040 Verify CB's for the Instrument Dev ice 7h 10-Feb-15 11:00 AM 10-Feb-15 06:00 PM

20 OE100045 Electrical assist for activities in RIE 7h 11-Feb-15 06:00 AM 11-Feb-15 01:00 PM

21 OE100050 Witness and Fix Proper Tag in the Ins truments 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM

22 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

23 OE100055 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

24 R15U-000-007 RC2-31-099-10-BD-021 - RC2-31-000-43-DCSPDB 0010 IDNETIFY CB FOR FIELD INSTR15U-000-007 RC2-31-099-10-BD-021 - RC2-31-000-43-DCSPDB 0010 IDNETIFY CB FOR FIELD INST492h 01-Jan-15 06:00 AM 10-Feb-15 06:00 PM

25 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

26 OE100060 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

27 SHUTDOWNSHUTDOWN 16h 09-Feb-15 02:00 PM 10-Feb-15 06:00 PM

28 OE100065 Obtain PTW 1h 09-Feb-15 02:00 PM 09-Feb-15 03:00 PM

29 OE100070 Verify CB's for the Instrument Dev ice 7h 09-Feb-15 03:00 PM 10-Feb-15 10:00 AM

30 OE100075 Electrical assist for activities in RIE 7h 10-Feb-15 10:00 AM 10-Feb-15 05:00 PM

31 OE100080 Witness and Fix Proper Tag in the Ins truments 1h 10-Feb-15 05:00 PM 10-Feb-15 06:00 PM

32 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

33 OE100085 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

34 R15U-000-008 RC2-31-099-10-BD-021 - RC2-31-000-43-DCSPDB 0011 IDNETIFY CB FOR FIELD INSTR15U-000-008 RC2-31-099-10-BD-021 - RC2-31-000-43-DCSPDB 0011 IDNETIFY CB FOR FIELD INST508h 01-Jan-15 06:00 AM 12-Feb-15 10:00 AM

35 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

36 OE100090 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

37 SHUTDOWNSHUTDOWN 16h 11-Feb-15 06:00 AM 12-Feb-15 10:00 AM

38 OE100095 Obtain PTW 1h 11-Feb-15 06:00 AM 11-Feb-15 07:00 AM

39 OE100100 Verify CB's for the Instrument Dev ice 7h 11-Feb-15 07:00 AM 11-Feb-15 02:00 PM

40 OE100105 Electrical assist for activities in RIE 7h 11-Feb-15 02:00 PM 12-Feb-15 09:00 AM

41 OE100110 Witness and Fix Proper Tag in the Ins truments 1h 12-Feb-15 09:00 AM 12-Feb-15 10:00 AM

42 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

43 OE100115 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

44 R15U-000-010 RC2-30-000- - CUI FOR OSBL & ISBL PROCESS LINESR15U-000-010 RC2-30-000- - CUI FOR OSBL & ISBL PROCESS LINES 700h 01-Jan-15 06:00 AM 28-Feb-15 10:00 AM

45 PRE-SHUTDOWNPRE-SHUTDOWN 346h 01-Jan-15 06:00 AM 29-Jan-15 04:00 PM

46 OM106160 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

47 OM106165 Erect Scaffolding, wherever reqd. 200h 01-Jan-15 08:00 AM 17-Jan-15 04:00 PM

48 OM106170 Remove Insulation, wherever reqd. 144h 17-Jan-15 04:00 PM 29-Jan-15 04:00 PM

49 SHUTDOWNSHUTDOWN 256h 07-Feb-15 06:00 AM 28-Feb-15 10:00 AM

50 OM106175 Verify LT&T and Obtain PTW 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM

51 OM106180 Carryout buffing on inspection areas 48h 07-Feb-15 10:00 AM 11-Feb-15 10:00 AM

52 OM106185 Carryout CUI on suspected areas 240h 08-Feb-15 10:00 AM 28-Feb-15 10:00 AM

53 OM106190 Further removal of insulation, As per ERG 12h 13-Feb-15 10:00 AM 14-Feb-15 10:00 AM

54 OM106195 Cleaning/ Recoating, As per ERG 48h 14-Feb-15 10:00 AM 18-Feb-15 10:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 1 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 2: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

55 OM106200 Final Inspection 24h 26-Feb-15 10:00 AM 28-Feb-15 10:00 AM

56 POST SHUTDOWNPOST SHUTDOWN 150h 01-Jan-15 06:00 AM 13-Jan-15 12:00 PM

57 OM106205 Fix back insulation 144h 01-Jan-15 06:00 AM 12-Jan-15 06:00 PM

58 OM106210 Remove scaffolding 150h 01-Jan-15 06:00 AM 13-Jan-15 12:00 PM

59 OM106215 Housekeeping & Close PTW 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM

60 R15U-099-001 RC2-31-099-29-EL-3131 - SD MAINT OF EL-3131R15U-099-001 RC2-31-099-29-EL-3131 - SD MAINT OF EL-3131 608h 01-Jan-15 06:00 AM 20-Feb-15 02:00 PM

61 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

62 OE102455 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

63 SHUTDOWNSHUTDOWN 8h 20-Feb-15 06:00 AM 20-Feb-15 02:00 PM

64 OE102460 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

65 OE102465 Do Insp. & Maint. as per Checklist 7h 20-Feb-15 07:00 AM 20-Feb-15 02:00 PM

66 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

67 OE102470 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

68 R15U-099-002 RC2-31-099-29-EL-3131A - SD MAINT OF EL-3131AR15U-099-002 RC2-31-099-29-EL-3131A - SD MAINT OF EL-3131A 616h 01-Jan-15 06:00 AM 21-Feb-15 10:00 AM

69 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

70 OE102475 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

71 SHUTDOWNSHUTDOWN 8h 20-Feb-15 02:00 PM 21-Feb-15 10:00 AM

72 OE102480 Verify LT&T and Obtain permit 1h 20-Feb-15 02:00 PM 20-Feb-15 03:00 PM

73 OE102485 Do Insp. & Maint. as per Checklist 7h 20-Feb-15 03:00 PM 21-Feb-15 10:00 AM

74 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

75 OE102490 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

76 R15U-099-003 RC2-31-099-29-EL-3132 - SD MAINT OF EL-3132R15U-099-003 RC2-31-099-29-EL-3132 - SD MAINT OF EL-3132 624h 01-Jan-15 06:00 AM 21-Feb-15 06:00 PM

77 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

78 OE102495 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

79 SHUTDOWNSHUTDOWN 8h 21-Feb-15 10:00 AM 21-Feb-15 06:00 PM

80 OE102500 Verify LT&T and Obtain permit 1h 21-Feb-15 10:00 AM 21-Feb-15 11:00 AM

81 OE102505 Do Insp. & Maint. as per Checklist 7h 21-Feb-15 11:00 AM 21-Feb-15 06:00 PM

82 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

83 OE102510 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

84 R15U-099-004 RC2-31-099-29-EL-3132A - SD MAINT OF EL-3132AR15U-099-004 RC2-31-099-29-EL-3132A - SD MAINT OF EL-3132A 632h 01-Jan-15 06:00 AM 22-Feb-15 02:00 PM

85 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

86 OE102515 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

87 SHUTDOWNSHUTDOWN 8h 22-Feb-15 06:00 AM 22-Feb-15 02:00 PM

88 OE102520 Verify LT&T and Obtain permit 1h 22-Feb-15 06:00 AM 22-Feb-15 07:00 AM

89 OE102525 Do Insp. & Maint. as per Checklist 7h 22-Feb-15 07:00 AM 22-Feb-15 02:00 PM

90 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

91 OE102530 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

92 R15U-099-005 RC2-31-099-29-EL-3141 - SD MAINT OF EL-3141R15U-099-005 RC2-31-099-29-EL-3141 - SD MAINT OF EL-3141 633h 01-Jan-15 06:00 AM 22-Feb-15 03:00 PM

93 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

94 OE102535 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

95 SHUTDOWNSHUTDOWN 633h 01-Jan-15 06:00 AM 22-Feb-15 03:00 PM

96 OE102540 Verify LT&T and Obtain permit 1h 22-Feb-15 02:00 PM 22-Feb-15 03:00 PM

97 OE102545 Do Insp. & Maint. as per Checklist 7h 01-Jan-15 06:00 AM 01-Jan-15 01:00 PM

98 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

99 OE102550 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

100 R15U-099-006 RC2-31-099-29-EL-3181 - SD MAINT OF EL-3181R15U-099-006 RC2-31-099-29-EL-3181 - SD MAINT OF EL-3181 646h 01-Jan-15 06:00 AM 23-Feb-15 04:00 PM

101 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

102 OE102555 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

103 SHUTDOWNSHUTDOWN 8h 23-Feb-15 08:00 AM 23-Feb-15 04:00 PM

104 OE102560 Verify LT&T and Obtain permit 1h 23-Feb-15 08:00 AM 23-Feb-15 09:00 AM

105 OE102565 Do Insp. & Maint. as per Checklist 7h 23-Feb-15 09:00 AM 23-Feb-15 04:00 PM

106 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

107 OE102570 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

108 R15U-099-007 RC2-31-099-29-EL-3191 - SD MAINT OF EL-3191R15U-099-007 RC2-31-099-29-EL-3191 - SD MAINT OF EL-3191 647h 01-Jan-15 06:00 AM 23-Feb-15 05:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 2 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 3: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

109 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

110 OE102575 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

111 SHUTDOWNSHUTDOWN 647h 01-Jan-15 06:00 AM 23-Feb-15 05:00 PM

112 OE102580 Verify LT&T and Obtain permit 1h 23-Feb-15 04:00 PM 23-Feb-15 05:00 PM

113 OE102585 Do Insp. & Maint. as per Checklist 7h 01-Jan-15 06:00 AM 01-Jan-15 01:00 PM

114 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

115 OE102590 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

116 R15U-099-012 RC2-31-099-29-EL-3281 - SD MAINT OF EL-3281R15U-099-012 RC2-31-099-29-EL-3281 - SD MAINT OF EL-3281 658h 01-Jan-15 06:00 AM 24-Feb-15 04:00 PM

117 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

118 OE102595 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

119 SHUTDOWNSHUTDOWN 8h 24-Feb-15 08:00 AM 24-Feb-15 04:00 PM

120 OE102600 Verify LT&T and Obtain permit 1h 24-Feb-15 08:00 AM 24-Feb-15 09:00 AM

121 OE102605 Do Insp. & Maint. as per Checklist 7h 24-Feb-15 09:00 AM 24-Feb-15 04:00 PM

122 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

123 OE102610 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

124 R15U-099-060 RC2-31-099-29-EL-3111 - SD MAINT OF EL-3111R15U-099-060 RC2-31-099-29-EL-3111 - SD MAINT OF EL-3111 662h 01-Jan-15 06:00 AM 25-Feb-15 08:00 AM

125 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

126 OE102615 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

127 SHUTDOWNSHUTDOWN 8h 24-Feb-15 12:00 PM 25-Feb-15 08:00 AM

128 OE102620 Verify LT&T and Obtain permit 1h 24-Feb-15 12:00 PM 24-Feb-15 01:00 PM

129 OE102625 Do Insp. & Maint. as per Checklist 7h 24-Feb-15 01:00 PM 25-Feb-15 08:00 AM

130 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

131 OE102630 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

132 R15U-099-061 RC2-31-099-29-EL-3111 - SD MAINT OF MCC MODULER15U-099-061 RC2-31-099-29-EL-3111 - SD MAINT OF MCC MODULE 670h 01-Jan-15 06:00 AM 25-Feb-15 04:00 PM

133 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

134 OE102635 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

135 SHUTDOWNSHUTDOWN 8h 25-Feb-15 08:00 AM 25-Feb-15 04:00 PM

136 OE102640 Verify LT&T and Obtain permit 1h 25-Feb-15 08:00 AM 25-Feb-15 09:00 AM

137 OE102645 Do Insp. & Maint. as per Checklist 7h 25-Feb-15 09:00 AM 25-Feb-15 04:00 PM

138 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

139 OE102650 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

140 R15U-099-062 RC2-31-099-29-EL-6722 - SD MAINT OF EL-6722R15U-099-062 RC2-31-099-29-EL-6722 - SD MAINT OF EL-6722 678h 01-Jan-15 06:00 AM 26-Feb-15 12:00 PM

141 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

142 OE102655 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

143 SHUTDOWNSHUTDOWN 8h 25-Feb-15 04:00 PM 26-Feb-15 12:00 PM

144 OE102660 Verify LT&T and Obtain permit 1h 25-Feb-15 04:00 PM 25-Feb-15 05:00 PM

145 OE102665 Do Insp. & Maint. as per Checklist 7h 25-Feb-15 05:00 PM 26-Feb-15 12:00 PM

146 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

147 OE102670 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

148 R15U-099-063 RC2-31-099-29-EL-6723 - SD MAINT OF EL-6723R15U-099-063 RC2-31-099-29-EL-6723 - SD MAINT OF EL-6723 686h 01-Jan-15 06:00 AM 27-Feb-15 08:00 AM

149 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

150 OE102675 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

151 SHUTDOWNSHUTDOWN 8h 26-Feb-15 12:00 PM 27-Feb-15 08:00 AM

152 OE102680 Verify LT&T and Obtain permit 1h 26-Feb-15 12:00 PM 26-Feb-15 01:00 PM

153 OE102685 Do Insp. & Maint. as per Checklist 7h 26-Feb-15 01:00 PM 27-Feb-15 08:00 AM

154 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

155 OE102690 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

156 R15U-005-017 RC2-31-005-29-EL-1109-MAINT OF PYGAS HEATER CONTROLR15U-005-017 RC2-31-005-29-EL-1109-MAINT OF PYGAS HEATER CONTROL 499h 01-Jan-15 06:00 AM 11-Feb-15 01:00 PM

157 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

158 OE100520 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

159 SHUTDOWNSHUTDOWN 7h 11-Feb-15 06:00 AM 11-Feb-15 01:00 PM

160 OE100525 Verify LT&T and Obtain permit 1h 11-Feb-15 06:00 AM 11-Feb-15 07:00 AM

161 OE100530 Do Insp. & Maint. as per Checklist 6h 11-Feb-15 07:00 AM 11-Feb-15 01:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 3 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 4: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

162 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

163 OE100535 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

164 R15U-005-035 RC2-31-005-29-EL-1212-MAINT OF PROCESS HEATER XFMRR15U-005-035 RC2-31-005-29-EL-1212-MAINT OF PROCESS HEATER XFMR 492h 01-Jan-15 06:00 AM 10-Feb-15 06:00 PM

165 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

166 OE101020 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

167 SHUTDOWNSHUTDOWN 8h 10-Feb-15 10:00 AM 10-Feb-15 06:00 PM

168 OE101025 Verify LT&T and Obtain permit 1h 10-Feb-15 10:00 AM 10-Feb-15 11:00 AM

169 OE101030 Do Insp. & Maint. as per Checklist 7h 10-Feb-15 11:00 AM 10-Feb-15 06:00 PM

170 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

171 OE101035 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

172 R15U-005-077 RC2-31-005-29-EL-2105-MAINT OF NORMAL LIGHTING PANELR15U-005-077 RC2-31-005-29-EL-2105-MAINT OF NORMAL LIGHTING PANEL 452h 01-Jan-15 06:00 AM 07-Feb-15 02:00 PM

173 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

174 OE101550 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

175 SHUTDOWNSHUTDOWN 8h 07-Feb-15 06:00 AM 07-Feb-15 02:00 PM

176 OE101555 Verify LT&T and Obtain permit 1h 07-Feb-15 06:00 AM 07-Feb-15 07:00 AM

177 OE101560 Do Insp. & Maint. as per Checklist 7h 07-Feb-15 07:00 AM 07-Feb-15 02:00 PM

178 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

179 OE101565 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

180 R15U-005-078 RC2-31-005-29-EL-2106-MAINT OF EMERGENCY LIGHTINGR15U-005-078 RC2-31-005-29-EL-2106-MAINT OF EMERGENCY LIGHTING 490h 01-Jan-15 06:00 AM 10-Feb-15 04:00 PM

181 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

182 OE101570 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

183 SHUTDOWNSHUTDOWN 8h 10-Feb-15 08:00 AM 10-Feb-15 04:00 PM

184 OE101575 Verify LT&T and Obtain permit 1h 10-Feb-15 08:00 AM 10-Feb-15 09:00 AM

185 OE101580 Do Insp. & Maint. as per Checklist 7h 10-Feb-15 09:00 AM 10-Feb-15 04:00 PM

186 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

187 OE101585 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

188 R15U-005-079 RC2-31-005-29-EL-2107-MAINT OF POWER WELDING PANELR15U-005-079 RC2-31-005-29-EL-2107-MAINT OF POWER WELDING PANEL 656h 01-Jan-15 06:00 AM 24-Feb-15 02:00 PM

189 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

190 OE101590 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

191 SHUTDOWNSHUTDOWN 8h 24-Feb-15 06:00 AM 24-Feb-15 02:00 PM

192 OE101595 Verify LT&T and Obtain permit 1h 24-Feb-15 06:00 AM 24-Feb-15 07:00 AM

193 OE101600 Do Insp. & Maint. as per Checklist 7h 24-Feb-15 07:00 AM 24-Feb-15 02:00 PM

194 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

195 OE101605 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

196 R15U-005-080 RC2-31-005-29-EL-2107-MAINT OF POWER WELDINGMODULER15U-005-080 RC2-31-005-29-EL-2107-MAINT OF POWER WELDINGMODULE 660h 01-Jan-15 06:00 AM 24-Feb-15 06:00 PM

197 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

198 OE101610 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

199 SHUTDOWNSHUTDOWN 4h 24-Feb-15 02:00 PM 24-Feb-15 06:00 PM

200 OE101615 Verify LT&T and Obtain permit 1h 24-Feb-15 02:00 PM 24-Feb-15 03:00 PM

201 OE101620 Do Insp. & Maint. as per Checklist 3h 24-Feb-15 03:00 PM 24-Feb-15 06:00 PM

202 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

203 OE101625 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

204 R15U-005-081 RC2-31-005-29-EL-2108-MAINT OF SMALL POWER PANELR15U-005-081 RC2-31-005-29-EL-2108-MAINT OF SMALL POWER PANEL 594h 01-Jan-15 06:00 AM 19-Feb-15 12:00 PM

205 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

206 OE101630 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

207 SHUTDOWNSHUTDOWN 8h 18-Feb-15 04:00 PM 19-Feb-15 12:00 PM

208 OE101635 Verify LT&T and Obtain permit 1h 18-Feb-15 04:00 PM 18-Feb-15 05:00 PM

209 OE101640 Do Insp. & Maint. as per Checklist 7h 18-Feb-15 05:00 PM 19-Feb-15 12:00 PM

210 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

211 OE101645 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

212 R15U-005-082 RC2-31-005-29-EL-2109-MAINT OF MOV PANELR15U-005-082 RC2-31-005-29-EL-2109-MAINT OF MOV PANEL 608h 01-Jan-15 06:00 AM 20-Feb-15 02:00 PM

213 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

214 OE101650 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 4 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 5: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

215 SHUTDOWNSHUTDOWN 8h 20-Feb-15 06:00 AM 20-Feb-15 02:00 PM

216 OE101655 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

217 OE101660 Do Insp. & Maint. as per Checklist 7h 20-Feb-15 07:00 AM 20-Feb-15 02:00 PM

218 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

219 OE101665 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

220 R15U-005-083 RC2-31-005-29-EL-2109-MAINT OF MOV MODULER15U-005-083 RC2-31-005-29-EL-2109-MAINT OF MOV MODULE 604h 01-Jan-15 06:00 AM 20-Feb-15 10:00 AM

221 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

222 OE101670 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

223 SHUTDOWNSHUTDOWN 4h 20-Feb-15 06:00 AM 20-Feb-15 10:00 AM

224 OE101675 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

225 OE101680 Do Insp. & Maint. as per Checklist 3h 20-Feb-15 07:00 AM 20-Feb-15 10:00 AM

226 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

227 OE101685 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

228 R15U-005-093 RC2-31-005-29-EL-2207-MAINT OF LV DISTRIBUTION XFMR15U-005-093 RC2-31-005-29-EL-2207-MAINT OF LV DISTRIBUTION XFM 452h 01-Jan-15 06:00 AM 07-Feb-15 02:00 PM

229 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

230 OE101810 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

231 SHUTDOWNSHUTDOWN 8h 07-Feb-15 06:00 AM 07-Feb-15 02:00 PM

232 OE101815 Verify LT&T and Obtain permit 1h 07-Feb-15 06:00 AM 07-Feb-15 07:00 AM

233 OE101820 Do Insp. & Maint. as per Checklist 7h 07-Feb-15 07:00 AM 07-Feb-15 02:00 PM

234 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

235 OE101825 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

236 R15U-005-094 RC2-31-005-29-EL-2207-MAINT OF LV DISTRIBUTION XFMR15U-005-094 RC2-31-005-29-EL-2207-MAINT OF LV DISTRIBUTION XFM 453h 01-Jan-15 06:00 AM 07-Feb-15 03:00 PM

237 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

238 OE101830 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

239 SHUTDOWNSHUTDOWN 3h 07-Feb-15 12:00 PM 07-Feb-15 03:00 PM

240 OE101835 Verify LT&T and Obtain permit 1h 07-Feb-15 12:00 PM 07-Feb-15 01:00 PM

241 OE101840 Do Insp. & Maint. as per Checklist 2h 07-Feb-15 01:00 PM 07-Feb-15 03:00 PM

242 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

243 OE101845 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

244 R15U-005-095 RC2-31-005-29-EL-2208-MAINT OF LV DISTRIBUTION XFMR15U-005-095 RC2-31-005-29-EL-2208-MAINT OF LV DISTRIBUTION XFM 473h 01-Jan-15 06:00 AM 09-Feb-15 11:00 AM

245 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

246 OE101850 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

247 SHUTDOWNSHUTDOWN 9h 08-Feb-15 02:00 PM 09-Feb-15 11:00 AM

248 OE101855 Verify LT&T and Obtain permit 1h 08-Feb-15 02:00 PM 08-Feb-15 03:00 PM

249 OE101860 Do Insp. & Maint. as per Checklist 8h 08-Feb-15 03:00 PM 09-Feb-15 11:00 AM

250 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

251 OE101865 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

252 R15U-005-096 RC2-31-005-29-EL-2208-MAINT OF LV DISTRIBUTION XFMR15U-005-096 RC2-31-005-29-EL-2208-MAINT OF LV DISTRIBUTION XFM 480h 01-Jan-15 06:00 AM 09-Feb-15 06:00 PM

253 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

254 OE101870 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

255 SHUTDOWNSHUTDOWN 4h 09-Feb-15 02:00 PM 09-Feb-15 06:00 PM

256 OE101875 Verify LT&T and Obtain permit 1h 09-Feb-15 02:00 PM 09-Feb-15 03:00 PM

257 OE101880 Do Insp. & Maint. as per Checklist 3h 09-Feb-15 03:00 PM 09-Feb-15 06:00 PM

258 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

259 OE101885 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

260 R15U-005-097 RC2-31-005-29-EL-2209-MAINT OF LV DISTRIBUTION XFMR15U-005-097 RC2-31-005-29-EL-2209-MAINT OF LV DISTRIBUTION XFM 590h 01-Jan-15 06:00 AM 19-Feb-15 08:00 AM

261 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

262 OE101890 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

263 SHUTDOWNSHUTDOWN 8h 18-Feb-15 12:00 PM 19-Feb-15 08:00 AM

264 OE101895 Verify LT&T and Obtain permit 1h 18-Feb-15 12:00 PM 18-Feb-15 01:00 PM

265 OE101900 Do Insp. & Maint. as per Checklist 7h 18-Feb-15 01:00 PM 19-Feb-15 08:00 AM

266 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

267 OE101905 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 5 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 6: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

268 R15U-005-098 RC2-31-005-29-EL-2209-MAINT OF LV DISTRIBUTION XFMR15U-005-098 RC2-31-005-29-EL-2209-MAINT OF LV DISTRIBUTION XFM 598h 01-Jan-15 06:00 AM 19-Feb-15 04:00 PM

269 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

270 OE101910 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

271 SHUTDOWNSHUTDOWN 4h 19-Feb-15 12:00 PM 19-Feb-15 04:00 PM

272 OE101915 Verify LT&T and Obtain permit 1h 19-Feb-15 12:00 PM 19-Feb-15 01:00 PM

273 OE101920 Do Insp. & Maint. as per Checklist 3h 19-Feb-15 01:00 PM 19-Feb-15 04:00 PM

274 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

275 OE101925 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

276 R15U-005-112 RC2-31-005-29-EL-2421-MAINT OF GENRAL UPS DISTRIBUTIONR15U-005-112 RC2-31-005-29-EL-2421-MAINT OF GENRAL UPS DISTRIBUTION 544h 01-Jan-15 06:00 AM 15-Feb-15 10:00 AM

277 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

278 OE101930 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

279 SHUTDOWNSHUTDOWN 6h 14-Feb-15 04:00 PM 15-Feb-15 10:00 AM

280 OE101935 Verify LT&T and Obtain permit 1h 14-Feb-15 04:00 PM 14-Feb-15 05:00 PM

281 OE101940 Do Insp. & Maint. as per Checklist 5h 14-Feb-15 05:00 PM 15-Feb-15 10:00 AM

282 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

283 OE101945 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

284 R15U-005-113 RC2-31-005-29-EL-2423-MAINT OF GENRAL UPS DISTRIBUTIONR15U-005-113 RC2-31-005-29-EL-2423-MAINT OF GENRAL UPS DISTRIBUTION 550h 01-Jan-15 06:00 AM 15-Feb-15 04:00 PM

285 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

286 OE101950 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

287 SHUTDOWNSHUTDOWN 6h 15-Feb-15 10:00 AM 15-Feb-15 04:00 PM

288 OE101955 Verify LT&T and Obtain permit 1h 15-Feb-15 10:00 AM 15-Feb-15 11:00 AM

289 OE101960 Do Insp. & Maint. as per Checklist 5h 15-Feb-15 11:00 AM 15-Feb-15 04:00 PM

290 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

291 OE101965 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

292 R15U-005-114 RC2-31-005-29-EL-2701-MAINT OF SWITCH GEARR15U-005-114 RC2-31-005-29-EL-2701-MAINT OF SWITCH GEAR 490h 01-Jan-15 06:00 AM 10-Feb-15 04:00 PM

293 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

294 OE101970 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

295 SHUTDOWNSHUTDOWN 8h 10-Feb-15 08:00 AM 10-Feb-15 04:00 PM

296 OE101975 Verify LT&T and Obtain permit 1h 10-Feb-15 08:00 AM 10-Feb-15 09:00 AM

297 OE101980 Do Insp. & Maint. as per Checklist 7h 10-Feb-15 09:00 AM 10-Feb-15 04:00 PM

298 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

299 OE101985 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

300 R15U-005-118 RC2-31-005-29-EL-2910-MAINT OF IRP PANELR15U-005-118 RC2-31-005-29-EL-2910-MAINT OF IRP PANEL 464h 01-Jan-15 06:00 AM 08-Feb-15 02:00 PM

301 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

302 OE101990 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

303 SHUTDOWNSHUTDOWN 8h 08-Feb-15 06:00 AM 08-Feb-15 02:00 PM

304 OE101995 Verify LT&T and Obtain permit 1h 08-Feb-15 06:00 AM 08-Feb-15 07:00 AM

305 OE102000 Do Insp. & Maint. as per Checklist 7h 08-Feb-15 07:00 AM 08-Feb-15 02:00 PM

306 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

307 OE102005 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

308 R15U-005-119 RC2-31-005-29-EL-2990-MAINT OF ECS PANELR15U-005-119 RC2-31-005-29-EL-2990-MAINT OF ECS PANEL 464h 01-Jan-15 06:00 AM 08-Feb-15 02:00 PM

309 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

310 OE102010 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

311 SHUTDOWNSHUTDOWN 8h 08-Feb-15 06:00 AM 08-Feb-15 02:00 PM

312 OE102015 Verify LT&T and Obtain permit 1h 08-Feb-15 06:00 AM 08-Feb-15 07:00 AM

313 OE102020 Do Insp. & Maint. as per Checklist 7h 08-Feb-15 07:00 AM 08-Feb-15 02:00 PM

314 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

315 OE102025 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

316 R15U-005-136 RC2-31-005-29-EL-4703-MAINT OF CONVENIENCE PNLR15U-005-136 RC2-31-005-29-EL-4703-MAINT OF CONVENIENCE PNL 452h 01-Jan-15 06:00 AM 07-Feb-15 02:00 PM

317 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

318 OE102155 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

319 SHUTDOWNSHUTDOWN 8h 07-Feb-15 06:00 AM 07-Feb-15 02:00 PM

320 OE102160 Verify LT&T and Obtain permit 1h 07-Feb-15 06:00 AM 07-Feb-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 6 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 7: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

321 OE102165 Do Insp. & Maint. as per Checklist 7h 07-Feb-15 07:00 AM 07-Feb-15 02:00 PM

322 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

323 OE102170 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

324 R15U-005-137 RC2-31-005-29-EL-4706-MAINT OF CONVENIENCE PNLR15U-005-137 RC2-31-005-29-EL-4706-MAINT OF CONVENIENCE PNL 604h 01-Jan-15 06:00 AM 20-Feb-15 10:00 AM

325 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

326 OE102175 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

327 SHUTDOWNSHUTDOWN 8h 19-Feb-15 02:00 PM 20-Feb-15 10:00 AM

328 OE102180 Verify LT&T and Obtain permit 1h 19-Feb-15 02:00 PM 19-Feb-15 03:00 PM

329 OE102185 Do Insp. & Maint. as per Checklist 7h 19-Feb-15 03:00 PM 20-Feb-15 10:00 AM

330 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

331 OE102190 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

332 R15U-005-138 RC2-31-005-29-EL-4709-MAINT OF CONVENIENCE PNLR15U-005-138 RC2-31-005-29-EL-4709-MAINT OF CONVENIENCE PNL 460h 01-Jan-15 06:00 AM 08-Feb-15 10:00 AM

333 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

334 OE102195 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

335 SHUTDOWNSHUTDOWN 8h 07-Feb-15 02:00 PM 08-Feb-15 10:00 AM

336 OE102200 Verify LT&T and Obtain permit 1h 07-Feb-15 02:00 PM 07-Feb-15 03:00 PM

337 OE102205 Do Insp. & Maint. as per Checklist 7h 07-Feb-15 03:00 PM 08-Feb-15 10:00 AM

338 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

339 OE102210 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

340 R15U-005-139 RC2-31-005-29-EL-4712-MAINT OF CONVENIENCE PNLR15U-005-139 RC2-31-005-29-EL-4712-MAINT OF CONVENIENCE PNL 604h 01-Jan-15 06:00 AM 20-Feb-15 10:00 AM

341 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

342 OE102215 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

343 SHUTDOWNSHUTDOWN 8h 19-Feb-15 02:00 PM 20-Feb-15 10:00 AM

344 OE102220 Verify LT&T and Obtain permit 1h 19-Feb-15 02:00 PM 19-Feb-15 03:00 PM

345 OE102225 Do Insp. & Maint. as per Checklist 7h 19-Feb-15 03:00 PM 20-Feb-15 10:00 AM

346 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

347 OE102230 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

348 R15U-005-140 RC2-31-005-29-EL-4715-MAINT OF CONVENIENCE PNLR15U-005-140 RC2-31-005-29-EL-4715-MAINT OF CONVENIENCE PNL 468h 01-Jan-15 06:00 AM 08-Feb-15 06:00 PM

349 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

350 OE102235 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

351 SHUTDOWNSHUTDOWN 8h 08-Feb-15 10:00 AM 08-Feb-15 06:00 PM

352 OE102240 Verify LT&T and Obtain permit 1h 08-Feb-15 10:00 AM 08-Feb-15 11:00 AM

353 OE102245 Do Insp. & Maint. as per Checklist 7h 08-Feb-15 11:00 AM 08-Feb-15 06:00 PM

354 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

355 OE102250 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

356 R15U-005-141 RC2-31-005-29-EL-4718-MAINT OF CONVENIENCE PNLR15U-005-141 RC2-31-005-29-EL-4718-MAINT OF CONVENIENCE PNL 604h 01-Jan-15 06:00 AM 20-Feb-15 10:00 AM

357 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

358 OE102255 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

359 SHUTDOWNSHUTDOWN 8h 19-Feb-15 02:00 PM 20-Feb-15 10:00 AM

360 OE102260 Verify LT&T and Obtain permit 1h 19-Feb-15 02:00 PM 19-Feb-15 03:00 PM

361 OE102265 Do Insp. & Maint. as per Checklist 7h 19-Feb-15 03:00 PM 20-Feb-15 10:00 AM

362 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

363 OE102270 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

364 R15U-005-142 RC2-31-005-29-EL-4752-MAINT OF CONVENIENCE PNLR15U-005-142 RC2-31-005-29-EL-4752-MAINT OF CONVENIENCE PNL 628h 01-Jan-15 06:00 AM 22-Feb-15 10:00 AM

365 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

366 OE102275 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

367 SHUTDOWNSHUTDOWN 8h 21-Feb-15 02:00 PM 22-Feb-15 10:00 AM

368 OE102280 Verify LT&T and Obtain permit 1h 21-Feb-15 02:00 PM 21-Feb-15 03:00 PM

369 OE102285 Do Insp. & Maint. as per Checklist 7h 21-Feb-15 03:00 PM 22-Feb-15 10:00 AM

370 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

371 OE102290 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

372 R15U-005-143 RC2-31-005-29-EL-4755-MAINT OF CONVENIENCE PNLR15U-005-143 RC2-31-005-29-EL-4755-MAINT OF CONVENIENCE PNL 636h 01-Jan-15 06:00 AM 22-Feb-15 06:00 PM

373 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 7 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 8: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

374 OE102295 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

375 SHUTDOWNSHUTDOWN 8h 22-Feb-15 10:00 AM 22-Feb-15 06:00 PM

376 OE102300 Verify LT&T and Obtain permit 1h 22-Feb-15 10:00 AM 22-Feb-15 11:00 AM

377 OE102305 Do Insp. & Maint. as per Checklist 7h 22-Feb-15 11:00 AM 22-Feb-15 06:00 PM

378 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

379 OE102310 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

380 R15U-005-144 RC2-31-005-29-EL-4756-MAINT OF JBEP CHEMICAL STORAGER15U-005-144 RC2-31-005-29-EL-4756-MAINT OF JBEP CHEMICAL STORAGE 608h 01-Jan-15 06:00 AM 20-Feb-15 02:00 PM

381 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

382 OE102315 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

383 SHUTDOWNSHUTDOWN 8h 20-Feb-15 06:00 AM 20-Feb-15 02:00 PM

384 OE102320 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

385 OE102325 Do Insp. & Maint. as per Checklist 7h 20-Feb-15 07:00 AM 20-Feb-15 02:00 PM

386 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

387 OE102330 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

388 ETHANE STORAGEETHANE STORAGE 1486h 01-Jan-15 12:00 AM 03-Mar-15 10:00 PM

389 R15U-071-006 RC2-31-071-PV-0041-CV-OVERHAUL & SERVICINGR15U-071-006 RC2-31-071-PV-0041-CV-OVERHAUL & SERVICING 1161h 01-Jan-15 12:00 AM 18-Feb-15 09:00 AM

390 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

391 OI100510 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

392 OI100515 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

393 SHUTDOWNSHUTDOWN 27h 17-Feb-15 06:00 AM 18-Feb-15 09:00 AM

394 OI100520 Verify LT&T and Obtain permit 1h 17-Feb-15 06:00 AM 17-Feb-15 07:00 AM

395 OI100525 Disconnect Signals / Connections for CV 1h 17-Feb-15 07:00 AM 17-Feb-15 08:00 AM

396 OI100530 Removal of CV & Install Blinds 4h 17-Feb-15 08:00 AM 17-Feb-15 12:00 PM

397 OI100535 Transport CV to Work Shop 1h 17-Feb-15 12:00 PM 17-Feb-15 01:00 PM

398 OI100540 Overhaul / Service CV 8h 17-Feb-15 01:00 PM 17-Feb-15 09:00 PM

399 OI100545 Test Valve (Refer Documentation) 2h 17-Feb-15 09:00 PM 17-Feb-15 11:00 PM

400 OI100550 Transport CV to Unit / Remove Blinds 1h 17-Feb-15 11:00 PM 18-Feb-15 12:00 AM

401 OI100555 Install CV 6h 18-Feb-15 12:00 AM 18-Feb-15 06:00 AM

402 OI100560 Loop Check & Stroke test 2h 18-Feb-15 06:00 AM 18-Feb-15 08:00 AM

403 OI100565 Inspection by RLOC 1h 18-Feb-15 08:00 AM 18-Feb-15 09:00 AM

404 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

405 OI100570 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

406 OI100575 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

407 R15U-071-007 RC2-31-071-PV-0042A-CV-OVERHAUL & SERVICINGR15U-071-007 RC2-31-071-PV-0042A-CV-OVERHAUL & SERVICING 1185h 01-Jan-15 12:00 AM 19-Feb-15 09:00 AM

408 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

409 OI100580 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

410 OI100585 Errect Scaffolding / Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

411 SHUTDOWNSHUTDOWN 27h 18-Feb-15 06:00 AM 19-Feb-15 09:00 AM

412 OI100590 Verify LT&T and Obtain permit 1h 18-Feb-15 06:00 AM 18-Feb-15 07:00 AM

413 OI100595 Disconnect Signals / Connections for CV 1h 18-Feb-15 07:00 AM 18-Feb-15 08:00 AM

414 OI100600 Removal of CV & Install Blinds 4h 18-Feb-15 08:00 AM 18-Feb-15 12:00 PM

415 OI100605 Transport CV to Work Shop 1h 18-Feb-15 12:00 PM 18-Feb-15 01:00 PM

416 OI100610 Overhaul / Service CV 8h 18-Feb-15 01:00 PM 18-Feb-15 09:00 PM

417 OI100615 Test Valve (Refer Documentation) 2h 18-Feb-15 09:00 PM 18-Feb-15 11:00 PM

418 OI100620 Transport CV to Unit / Remove Blinds 1h 18-Feb-15 11:00 PM 19-Feb-15 12:00 AM

419 OI100625 Install CV 6h 19-Feb-15 12:00 AM 19-Feb-15 06:00 AM

420 OI100630 Loop Check & Stroke test 2h 19-Feb-15 06:00 AM 19-Feb-15 08:00 AM

421 OI100635 Inspection by RLOC 1h 19-Feb-15 08:00 AM 19-Feb-15 09:00 AM

422 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

423 OI100640 Reinsulate CV / Removal of Scaffolding 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

424 OI100645 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

425 R15U-071-008 RC2-31-071-PV-0042B-CV-OVERHAUL & SERVICINGR15U-071-008 RC2-31-071-PV-0042B-CV-OVERHAUL & SERVICING 1207h 01-Jan-15 12:00 AM 20-Feb-15 07:00 AM

426 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

427 OI100650 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

428 OI100655 Errect Scaffolding / Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 8 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 9: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

429 SHUTDOWNSHUTDOWN 25h 19-Feb-15 06:00 AM 20-Feb-15 07:00 AM

430 OI100660 Verify LT&T and Obtain permit 1h 19-Feb-15 06:00 AM 19-Feb-15 07:00 AM

431 OI100665 Disconnect Signals / Connections for CV 1h 19-Feb-15 07:00 AM 19-Feb-15 08:00 AM

432 OI100670 Removal of CV & Install Blinds 3h 19-Feb-15 08:00 AM 19-Feb-15 11:00 AM

433 OI100675 Transport CV to Work Shop 1h 19-Feb-15 11:00 AM 19-Feb-15 12:00 PM

434 OI100680 Overhaul / Service CV 8h 19-Feb-15 12:00 PM 19-Feb-15 08:00 PM

435 OI100685 Test Valve (Refer Documentation) 2h 19-Feb-15 08:00 PM 19-Feb-15 10:00 PM

436 OI100690 Transport CV to Unit / Remove Blinds 1h 19-Feb-15 10:00 PM 19-Feb-15 11:00 PM

437 OI100695 Install CV 5h 19-Feb-15 11:00 PM 20-Feb-15 04:00 AM

438 OI100700 Loop Check & Stroke test 2h 20-Feb-15 04:00 AM 20-Feb-15 06:00 AM

439 OI100705 Inspection by RLOC 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

440 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

441 OI100710 Reinsulate CV / Removal of Scaffolding 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

442 OI100715 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

443 R15U-071-014 RC2-31-071-EIV-0045-CV-OVERHAUL & SERVICINGR15U-071-014 RC2-31-071-EIV-0045-CV-OVERHAUL & SERVICING 1233h 01-Jan-15 12:00 AM 21-Feb-15 09:00 AM

444 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

445 OI100720 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

446 OI100725 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

447 SHUTDOWNSHUTDOWN 27h 20-Feb-15 06:00 AM 21-Feb-15 09:00 AM

448 OI100730 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

449 OI100735 Disconnect Signals / Connections for CV 1h 20-Feb-15 07:00 AM 20-Feb-15 08:00 AM

450 OI100740 Removal of CV & Install Blinds 4h 20-Feb-15 08:00 AM 20-Feb-15 12:00 PM

451 OI100745 Transport CV to Work Shop 1h 20-Feb-15 12:00 PM 20-Feb-15 01:00 PM

452 OI100750 Overhaul / Service CV 8h 20-Feb-15 01:00 PM 20-Feb-15 09:00 PM

453 OI100755 Test Valve (Refer Documentation) 2h 20-Feb-15 09:00 PM 20-Feb-15 11:00 PM

454 OI100760 Transport CV to Unit / Remove Blinds 1h 20-Feb-15 11:00 PM 21-Feb-15 12:00 AM

455 OI100765 Install CV 6h 21-Feb-15 12:00 AM 21-Feb-15 06:00 AM

456 OI100770 Loop Check & Stroke test 2h 21-Feb-15 06:00 AM 21-Feb-15 08:00 AM

457 OI100775 Inspection by RLOC 1h 21-Feb-15 08:00 AM 21-Feb-15 09:00 AM

458 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

459 OI100780 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

460 OI100785 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

461 R15U-071-015 RC2-31-071-95-TK-1140-INTER & EXTERNAL INSPR15U-071-015 RC2-31-071-95-TK-1140-INTER & EXTERNAL INSP 1486h 01-Jan-15 12:00 AM 03-Mar-15 10:00 PM

462 PRE-SHUTDOWNPRE-SHUTDOWN 12h 01-Jan-15 12:00 AM 01-Jan-15 12:00 PM

463 OM100975 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

464 OM100980 Erect Scaffolding 10h 01-Jan-15 02:00 AM 01-Jan-15 12:00 PM

465 SHUTDOWNSHUTDOWN 472h 12-Feb-15 06:00 AM 03-Mar-15 10:00 PM

466 OM100985 Verify LT&T and Obtain permit 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM

467 OM100990 Mechanical Isolation & Blinding 10h 12-Feb-15 12:00 PM 12-Feb-15 10:00 PM

468 OM100995 Manway Opening & Providing a Ventilation & Lighting 8h 12-Feb-15 10:00 PM 13-Feb-15 06:00 AM

469 OM101000 Obtain Confined space permit & Erect Internal Scaffolding 36h 13-Feb-15 06:00 AM 14-Feb-15 06:00 PM

470 OM101005 Preliminary Inspection 6h 14-Feb-15 06:00 PM 15-Feb-15 12:00 AM

471 OM101010 Cleaning & Repair 360h 15-Feb-15 12:00 AM 02-Mar-15 12:00 AM

472 OM101015 Remove Internal Scaffolding 24h 02-Mar-15 12:00 AM 03-Mar-15 12:00 AM

473 OM101020 Final Inspection 6h 03-Mar-15 12:00 AM 03-Mar-15 06:00 AM

474 OM101025 Manway Box-up 6h 03-Mar-15 06:00 AM 03-Mar-15 12:00 PM

475 OM101030 De-Blinding 10h 03-Mar-15 12:00 PM 03-Mar-15 10:00 PM

476 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

477 OM101035 Remove Scaffolding 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

478 OM101040 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

479 OM101045 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

480 R15U-071-017 RC2-31-071-EIV-0005 - CV-OVERHAUL & SERVICINGR15U-071-017 RC2-31-071-EIV-0005 - CV-OVERHAUL & SERVICING 1257h 01-Jan-15 12:00 AM 22-Feb-15 09:00 AM

481 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

482 OI100790 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

483 OI100795 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 9 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 10: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

484 SHUTDOWNSHUTDOWN 27h 21-Feb-15 06:00 AM 22-Feb-15 09:00 AM

485 OI100800 Verify LT&T and Obtain permit 1h 21-Feb-15 06:00 AM 21-Feb-15 07:00 AM

486 OI100805 Disconnect Signals / Connections for CV 1h 21-Feb-15 07:00 AM 21-Feb-15 08:00 AM

487 OI100810 Removal of CV & Install Blinds 4h 21-Feb-15 08:00 AM 21-Feb-15 12:00 PM

488 OI100815 Transport CV to Work Shop 1h 21-Feb-15 12:00 PM 21-Feb-15 01:00 PM

489 OI100820 Overhaul / Service CV 8h 21-Feb-15 01:00 PM 21-Feb-15 09:00 PM

490 OI100825 Test Valve (Refer Documentation) 2h 21-Feb-15 09:00 PM 21-Feb-15 11:00 PM

491 OI100830 Transport CV to Unit / Remove Blinds 1h 21-Feb-15 11:00 PM 22-Feb-15 12:00 AM

492 OI100835 Install CV 6h 22-Feb-15 12:00 AM 22-Feb-15 06:00 AM

493 OI100840 Loop Check & Stroke test 2h 22-Feb-15 06:00 AM 22-Feb-15 08:00 AM

494 OI100845 Inspection by RLOC 1h 22-Feb-15 08:00 AM 22-Feb-15 09:00 AM

495 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

496 OI100850 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

497 OI100855 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

498 R15U-097-001 RC2-31-097-43-AT-0050-INST-SAMPLE PROBE REPLACMENTR15U-097-001 RC2-31-097-43-AT-0050-INST-SAMPLE PROBE REPLACMENT 11h 23-Feb-15 11:00 AM 23-Feb-15 10:00 PM

499 SHUTDOWNSHUTDOWN 11h 23-Feb-15 11:00 AM 23-Feb-15 10:00 PM

500 OI102160 Review JSA 1h 23-Feb-15 11:00 AM 23-Feb-15 12:00 PM

501 OI102165 Verify LT&T and Obtain permit 1h 23-Feb-15 12:00 PM 23-Feb-15 01:00 PM

502 OI102170 Disconnect the Tubings / Lines 1h 23-Feb-15 01:00 PM 23-Feb-15 02:00 PM

503 OI102175 Retraction of the probe from Process line 1h 23-Feb-15 02:00 PM 23-Feb-15 03:00 PM

504 OI102180 Close the Process Main valve 1h 23-Feb-15 03:00 PM 23-Feb-15 04:00 PM

505 OI102185 Remove the existing Probe 1h 23-Feb-15 04:00 PM 23-Feb-15 05:00 PM

506 OI102190 Fix back New Sample Probe 2h 23-Feb-15 05:00 PM 23-Feb-15 07:00 PM

507 OI102195 Connect the Tubings / Lines 1h 23-Feb-15 07:00 PM 23-Feb-15 08:00 PM

508 OI102200 Inspection by RLOC 1h 23-Feb-15 08:00 PM 23-Feb-15 09:00 PM

509 OI102205 House keeping & Close PTW 1h 23-Feb-15 09:00 PM 23-Feb-15 10:00 PM

510 R15U-097-002 RC2-31-097-43-F-0022-VALVE SERVICINGR15U-097-002 RC2-31-097-43-F-0022-VALVE SERVICING 664h 01-Jan-15 06:00 AM 25-Feb-15 10:00 AM

511 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

512 OM105285 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

513 SHUTDOWNSHUTDOWN 142h 13-Feb-15 12:00 PM 25-Feb-15 10:00 AM

514 OM105290 Purging, Flushing, Gas testing, LEL checking 8h 13-Feb-15 12:00 PM 14-Feb-15 08:00 AM

515 OM105295 Verify LT&T and Obtain permit 2h 14-Feb-15 08:00 AM 14-Feb-15 10:00 AM

516 OM105300 Blinding as per blind list. 4h 14-Feb-15 10:00 AM 14-Feb-15 02:00 PM

517 OM105305 Remove inst. cable and drop positioner 1h 14-Feb-15 02:00 PM 14-Feb-15 03:00 PM

518 OM105310 Drop valves (2 nos) & Provide end blind 10h 14-Feb-15 03:00 PM 15-Feb-15 01:00 PM

519 OM105315 Shift removed valves to shop for servicing 2h 15-Feb-15 01:00 PM 15-Feb-15 03:00 PM

520 OM105320 Repair, Testing & Witnessing of valves 96h 15-Feb-15 03:00 PM 23-Feb-15 03:00 PM

521 OM105325 Shifting of serviced valves to job area 2h 23-Feb-15 03:00 PM 23-Feb-15 05:00 PM

522 OM105330 Fix the valves with new gaskets & Tight the bolts in sequence 12h 23-Feb-15 05:00 PM 24-Feb-15 05:00 PM

523 OM105335 Refix the instrumentation cable on valve 1h 24-Feb-15 05:00 PM 24-Feb-15 06:00 PM

524 OM105340 Carryout De-Blinding 4h 25-Feb-15 06:00 AM 25-Feb-15 10:00 AM

525 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

526 OM105345 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

527 R15U-097-003 RC2-31-097-43-F-0023-VALVE SERVICINGR15U-097-003 RC2-31-097-43-F-0023-VALVE SERVICING 672h 01-Jan-15 06:00 AM 25-Feb-15 06:00 PM

528 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

529 OM105350 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

530 SHUTDOWNSHUTDOWN 142h 14-Feb-15 08:00 AM 25-Feb-15 06:00 PM

531 OM105355 Purging, Flushing, Gas testing, LEL checking 8h 14-Feb-15 08:00 AM 14-Feb-15 04:00 PM

532 OM105360 Verify LT&T and Obtain permit 2h 14-Feb-15 04:00 PM 14-Feb-15 06:00 PM

533 OM105365 Blinding as per blind list. 4h 15-Feb-15 06:00 AM 15-Feb-15 10:00 AM

534 OM105370 Remove inst. cable and drop positioner 1h 15-Feb-15 10:00 AM 15-Feb-15 11:00 AM

535 OM105375 Drop valves (2 nos) & Provide end blind 10h 15-Feb-15 11:00 AM 16-Feb-15 09:00 AM

536 OM105380 Shift removed valves to shop for servicing 2h 16-Feb-15 09:00 AM 16-Feb-15 11:00 AM

537 OM105385 Repair, Testing & Witnessing of valves 96h 16-Feb-15 11:00 AM 24-Feb-15 11:00 AM

538 OM105390 Shifting of serviced valves to job area 2h 24-Feb-15 11:00 AM 24-Feb-15 01:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 10 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 11: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

539 OM105395 Fix the valves with new gaskets & Tight the bolts in sequence 12h 24-Feb-15 01:00 PM 25-Feb-15 01:00 PM

540 OM105400 Refix the instrumentation cable on valve 1h 25-Feb-15 01:00 PM 25-Feb-15 02:00 PM

541 OM105405 Carryout De-Blinding 4h 25-Feb-15 02:00 PM 25-Feb-15 06:00 PM

542 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

543 OM105410 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

544 R15U-097-007 RC2-31-097-43-FI-0022-INST-SENIOR ORIFICE INSPECTIONR15U-097-007 RC2-31-097-43-FI-0022-INST-SENIOR ORIFICE INSPECTION 1367h 01-Jan-15 12:00 AM 26-Feb-15 11:00 PM

545 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 12:00 AM 01-Jan-15 05:00 AM

546 OI102210 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

547 OI102215 Erect Scaffolding 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

548 SHUTDOWNSHUTDOWN 473h 07-Feb-15 06:00 AM 26-Feb-15 11:00 PM

549 OI102220 Verify LT&T and Obtain permit 2h 07-Feb-15 06:00 AM 07-Feb-15 08:00 AM

550 OI102225 Asst. Vendor for Servic e Orific e Fittings 24h 07-Feb-15 08:00 AM 08-Feb-15 08:00 AM

551 OI102230 Troubleshoot/Correct/Replace accessories 12h 08-Feb-15 08:00 AM 08-Feb-15 08:00 PM

552 OI102235 Inspection by RLOC 1h 08-Feb-15 08:00 PM 08-Feb-15 09:00 PM

553 OI102275 Inspection by RLOC 1h 26-Feb-15 10:00 PM 26-Feb-15 11:00 PM

554 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

555 OI102240 Removal of scaffolds 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

556 OI102245 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

557 R15U-097-008 RC2-31-097-43-FI-0023-INST-SENIOR ORIFICE INSPECTIONR15U-097-008 RC2-31-097-43-FI-0023-INST-SENIOR ORIFICE INSPECTION 1366h 01-Jan-15 12:00 AM 26-Feb-15 10:00 PM

558 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 12:00 AM 01-Jan-15 05:00 AM

559 OI102250 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

560 OI102255 Erect Scaffolding 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

561 SHUTDOWNSHUTDOWN 38h 25-Feb-15 08:00 AM 26-Feb-15 10:00 PM

562 OI102260 Verify LT&T and Obtain permit 2h 25-Feb-15 08:00 AM 25-Feb-15 10:00 AM

563 OI102265 Asst. Vendor for Servic e Orific e Fittings 24h 25-Feb-15 10:00 AM 26-Feb-15 10:00 AM

564 OI102270 Troubleshoot/Correct/Replace accessories 12h 26-Feb-15 10:00 AM 26-Feb-15 10:00 PM

565 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

566 OI102280 Removal of scaffolds 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

567 OI102285 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

568 R15U-097-009 RC2-32-151-35-F-225-VALVE SERVICINGR15U-097-009 RC2-32-151-35-F-225-VALVE SERVICING 602h 01-Jan-15 06:00 AM 20-Feb-15 08:00 AM

569 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 06:00 AM 01-Jan-15 11:00 AM

570 OM105490 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

571 OM105495 Shift blinds to location 4h 01-Jan-15 07:00 AM 01-Jan-15 11:00 AM

572 SHUTDOWNSHUTDOWN 60h 15-Feb-15 08:00 AM 20-Feb-15 08:00 AM

573 OM105500 Verify LT&T and Obtain PTW 2h 15-Feb-15 08:00 AM 15-Feb-15 10:00 AM

574 OM105505 Blinding as per blindlist. 3h 15-Feb-15 10:00 AM 15-Feb-15 01:00 PM

575 OM105510 Drop I/L, O/L valves & provide end blinds 12h 15-Feb-15 01:00 PM 16-Feb-15 01:00 PM

576 OM105515 Shift removed valves to valve shop for servicing 4h 16-Feb-15 01:00 PM 16-Feb-15 05:00 PM

577 OM105520 Servicing of valve 24h 16-Feb-15 05:00 PM 18-Feb-15 05:00 PM

578 OM105525 Shift the serviced valves from valve shop 3h 18-Feb-15 05:00 PM 19-Feb-15 08:00 AM

579 OM105530 Remove end blinds & install the valves 12h 19-Feb-15 08:00 AM 20-Feb-15 08:00 AM

580 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

581 OM105535 De-Blinding 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

582 OM105540 Housekeeping and close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

583 C3/C4C3/C4 1272h 01-Jan-15 12:00 AM 23-Feb-15 12:00 AM

584 R15U-073-004 RC2-31-073-43-AT-0064-INST-SAMPLE PROBE REPLACMENTR15U-073-004 RC2-31-073-43-AT-0064-INST-SAMPLE PROBE REPLACMENT 11h 22-Feb-15 01:00 PM 23-Feb-15 12:00 AM

585 SHUTDOWNSHUTDOWN 11h 22-Feb-15 01:00 PM 23-Feb-15 12:00 AM

586 OI102060 Review JSA 1h 22-Feb-15 01:00 PM 22-Feb-15 02:00 PM

587 OI102065 Verify LT&T and Obtain permit 1h 22-Feb-15 02:00 PM 22-Feb-15 03:00 PM

588 OI102070 Disconnect the Tubings / Lines 1h 22-Feb-15 03:00 PM 22-Feb-15 04:00 PM

589 OI102075 Retraction of the probe from Process line 1h 22-Feb-15 04:00 PM 22-Feb-15 05:00 PM

590 OI102080 Close the Process Main valve 1h 22-Feb-15 05:00 PM 22-Feb-15 06:00 PM

591 OI102085 Remove the existing Probe 1h 22-Feb-15 06:00 PM 22-Feb-15 07:00 PM

592 OI102090 Fix back New Sample Probe 2h 22-Feb-15 07:00 PM 22-Feb-15 09:00 PM

593 OI102095 Connect the Tubings / Lines 1h 22-Feb-15 09:00 PM 22-Feb-15 10:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 11 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 12: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

594 OI102100 Inspection by RLOC 1h 22-Feb-15 10:00 PM 22-Feb-15 11:00 PM

595 OI102105 House keeping & Close PTW 1h 22-Feb-15 11:00 PM 23-Feb-15 12:00 AM

596 R15U-073-005 RC2-31-073-93-V-0052A-VALVE REPLACEMENTR15U-073-005 RC2-31-073-93-V-0052A-VALVE REPLACEMENT 502h 01-Jan-15 06:00 AM 11-Feb-15 04:00 PM

597 PRE-SHUTDOWNPRE-SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM

598 OM105205 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

599 OM105210 Hydrotest new valve & Shift to location 3h 01-Jan-15 07:00 AM 01-Jan-15 10:00 AM

600 SHUTDOWNSHUTDOWN 10h 11-Feb-15 06:00 AM 11-Feb-15 04:00 PM

601 OM105215 Purging, Flushing, Gas testing, LEL check 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM

602 OM105220 Verify LT&T and Obtain permit 1h 11-Feb-15 10:00 AM 11-Feb-15 11:00 AM

603 OM105225 Unbolt the flanges and drop the valve 2h 11-Feb-15 11:00 AM 11-Feb-15 01:00 PM

604 OM105230 Shift removed valve to shop for servicing 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM

605 OM105235 Install the new valve in position 2h 11-Feb-15 02:00 PM 11-Feb-15 04:00 PM

606 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

607 OM105240 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

608 R15U-073-006 RC2-31-073-93-V-0052B-VALVE REPLACEMENTR15U-073-006 RC2-31-073-93-V-0052B-VALVE REPLACEMENT 506h 01-Jan-15 06:00 AM 12-Feb-15 08:00 AM

609 PRE-SHUTDOWNPRE-SHUTDOWN 4h 01-Jan-15 06:00 AM 01-Jan-15 10:00 AM

610 OM105245 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

611 OM105250 Hydrotest new valve & Shift to location 3h 01-Jan-15 07:00 AM 01-Jan-15 10:00 AM

612 SHUTDOWNSHUTDOWN 10h 11-Feb-15 10:00 AM 12-Feb-15 08:00 AM

613 OM105255 Purging, Flushing, Gas testing, LEL check 4h 11-Feb-15 10:00 AM 11-Feb-15 02:00 PM

614 OM105260 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

615 OM105265 Unbolt the flanges and drop the valve 2h 11-Feb-15 03:00 PM 11-Feb-15 05:00 PM

616 OM105270 Shift removed valve to shop for servicing 1h 11-Feb-15 05:00 PM 11-Feb-15 06:00 PM

617 OM105275 Install the new valve in position 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM

618 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

619 OM105280 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

620 R15U-073-008 RC2-31-073-EIV-0070-CV-OVERHAUL & SERVICINGR15U-073-008 RC2-31-073-EIV-0070-CV-OVERHAUL & SERVICING 921h 01-Jan-15 12:00 AM 08-Feb-15 09:00 AM

621 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 12:00 AM 01-Jan-15 07:00 AM

622 OI101490 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

623 OI101495 Errect Scaffolding 6h 01-Jan-15 01:00 AM 01-Jan-15 07:00 AM

624 SHUTDOWNSHUTDOWN 27h 07-Feb-15 06:00 AM 08-Feb-15 09:00 AM

625 OI101500 Verify LT&T and Obtain permit 1h 07-Feb-15 06:00 AM 07-Feb-15 07:00 AM

626 OI101505 Disconnect Signals / Connections for CV 1h 07-Feb-15 07:00 AM 07-Feb-15 08:00 AM

627 OI101510 Removal of CV & Install Blinds 4h 07-Feb-15 08:00 AM 07-Feb-15 12:00 PM

628 OI101515 Transport CV to Work Shop 1h 07-Feb-15 12:00 PM 07-Feb-15 01:00 PM

629 OI101520 Overhaul / Service CV 8h 07-Feb-15 01:00 PM 07-Feb-15 09:00 PM

630 OI101525 Test Valve (Refer Documentation) 2h 07-Feb-15 09:00 PM 07-Feb-15 11:00 PM

631 OI101530 Transport CV to Unit / Remove Blinds 1h 07-Feb-15 11:00 PM 08-Feb-15 12:00 AM

632 OI101535 Install CV 6h 08-Feb-15 12:00 AM 08-Feb-15 06:00 AM

633 OI101540 Loop Check & Stroke test 2h 08-Feb-15 06:00 AM 08-Feb-15 08:00 AM

634 OI101545 Inspection by RLOC 1h 08-Feb-15 08:00 AM 08-Feb-15 09:00 AM

635 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

636 OI101550 Removal of Scafflods 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

637 OI101555 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

638 PYGASPYGAS 1400h 01-Jan-15 12:00 AM 28-Feb-15 08:00 AM

639 R15U-074-002 RC2-31-074-95-TK-1152-INTER & EXTERNAL INSPR15U-074-002 RC2-31-074-95-TK-1152-INTER & EXTERNAL INSP 1400h 01-Jan-15 12:00 AM 28-Feb-15 08:00 AM

640 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

641 OM101125 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

642 OM101130 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

643 SHUTDOWNSHUTDOWN 506h 07-Feb-15 06:00 AM 28-Feb-15 08:00 AM

644 OM101135 Verify LT&T and Obtain permit 4h 07-Feb-15 06:00 AM 07-Feb-15 10:00 AM

645 OM101140 Mechanical Isolation & Blinding 8h 07-Feb-15 10:00 AM 07-Feb-15 06:00 PM

646 OM101145 Manway Opening & Providing a Ventilation & Lighting 12h 07-Feb-15 06:00 PM 08-Feb-15 06:00 AM

647 OM101150 Obtain Confined space permit & Erect Internal Scaffolding 24h 08-Feb-15 06:00 AM 09-Feb-15 06:00 AM

648 OM101155 Preliminary Inspection 6h 09-Feb-15 06:00 AM 09-Feb-15 12:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 12 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 13: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

649 OM101160 Cleaning & Repair 360h 09-Feb-15 12:00 PM 24-Feb-15 12:00 PM

650 OM101165 Renew the Primary & Secondary Seals 48h 24-Feb-15 12:00 PM 26-Feb-15 12:00 PM

651 OM101170 Remove Internal Scaffolding 18h 26-Feb-15 12:00 PM 27-Feb-15 06:00 AM

652 OM101175 Final Inspection 6h 27-Feb-15 06:00 AM 27-Feb-15 12:00 PM

653 OM101180 Manway Box-up 12h 27-Feb-15 12:00 PM 28-Feb-15 12:00 AM

654 OM101185 De-Blinding 8h 28-Feb-15 12:00 AM 28-Feb-15 08:00 AM

655 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

656 OM101190 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

657 OM101195 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

658 OM101200 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

659 R15U-074-004 RC2-31-074-43-AT-0128-INST-SAMPLE PROBE REPLACMENTR15U-074-004 RC2-31-074-43-AT-0128-INST-SAMPLE PROBE REPLACMENT 11h 23-Feb-15 06:00 AM 23-Feb-15 05:00 PM

660 SHUTDOWNSHUTDOWN 11h 23-Feb-15 06:00 AM 23-Feb-15 05:00 PM

661 OI102110 Review JSA 1h 23-Feb-15 06:00 AM 23-Feb-15 07:00 AM

662 OI102115 Verify LT&T and Obtain permit 1h 23-Feb-15 07:00 AM 23-Feb-15 08:00 AM

663 OI102120 Disconnect the Tubings / Lines 1h 23-Feb-15 08:00 AM 23-Feb-15 09:00 AM

664 OI102125 Retraction of the probe from Process line 1h 23-Feb-15 09:00 AM 23-Feb-15 10:00 AM

665 OI102130 Close the Process Main valve 1h 23-Feb-15 10:00 AM 23-Feb-15 11:00 AM

666 OI102135 Remove the existing Probe 1h 23-Feb-15 11:00 AM 23-Feb-15 12:00 PM

667 OI102140 Fix back New Sample Probe 2h 23-Feb-15 12:00 PM 23-Feb-15 02:00 PM

668 OI102145 Connect the Tubings / Lines 1h 23-Feb-15 02:00 PM 23-Feb-15 03:00 PM

669 OI102150 Inspection by RLOC 1h 23-Feb-15 03:00 PM 23-Feb-15 04:00 PM

670 OI102155 House keeping & Close PTW 1h 23-Feb-15 04:00 PM 23-Feb-15 05:00 PM

671 R15U-074-005 RC2-31-074-ESV-0130-CV-OVERHAUL & SERVICINGR15U-074-005 RC2-31-074-ESV-0130-CV-OVERHAUL & SERVICING 33h 08-Feb-15 06:00 AM 09-Feb-15 03:00 PM

672 SHUTDOWNSHUTDOWN 33h 08-Feb-15 06:00 AM 09-Feb-15 03:00 PM

673 OI101560 Review JSA 1h 08-Feb-15 06:00 AM 08-Feb-15 07:00 AM

674 OI101565 Verify LT&T and Obtain permit 1h 08-Feb-15 07:00 AM 08-Feb-15 08:00 AM

675 OI101570 Disconnect Signals / Connections for CV 1h 08-Feb-15 08:00 AM 08-Feb-15 09:00 AM

676 OI101575 Removal of CV & Install Blinds 4h 08-Feb-15 09:00 AM 08-Feb-15 01:00 PM

677 OI101580 Transport CV to Work Shop 1h 08-Feb-15 01:00 PM 08-Feb-15 02:00 PM

678 OI101585 Overhaul / Service CV 12h 08-Feb-15 02:00 PM 09-Feb-15 02:00 AM

679 OI101590 Test Valve (Refer Documentation) 2h 09-Feb-15 02:00 AM 09-Feb-15 04:00 AM

680 OI101595 Transport CV to Unit / Remove Blinds 1h 09-Feb-15 04:00 AM 09-Feb-15 05:00 AM

681 OI101600 Install CV 6h 09-Feb-15 05:00 AM 09-Feb-15 11:00 AM

682 OI101605 Inspection by RLOC 1h 09-Feb-15 11:00 AM 09-Feb-15 12:00 PM

683 OI101610 Loop Check & Stroke test 2h 09-Feb-15 12:00 PM 09-Feb-15 02:00 PM

684 OI101615 House keeping & Close PTW 1h 09-Feb-15 02:00 PM 09-Feb-15 03:00 PM

685 STEAM/ CONDENSATE (HP/MP/LP & CON)STEAM/ CONDENSATE (HP/MP/LP & CON) 1357h 01-Jan-15 12:00 AM 26-Feb-15 01:00 PM

686 R15U-005-129 RC2-31-005-29-EL-1203 - PROVISION OF SAFETY COVERSR15U-005-129 RC2-31-005-29-EL-1203 - PROVISION OF SAFETY COVERS 579h 01-Jan-15 06:00 AM 18-Feb-15 09:00 AM

687 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

688 OE102070 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

689 SHUTDOWNSHUTDOWN 51h 14-Feb-15 06:00 AM 18-Feb-15 09:00 AM

690 OE102075 Verify LT&T and Obtain permit 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

691 OE102080 Preparation for Fixing the Covers 25h 14-Feb-15 07:00 AM 16-Feb-15 08:00 AM

692 OE102085 Install 25 No's of ACB cover 25h 16-Feb-15 08:00 AM 18-Feb-15 09:00 AM

693 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

694 OE102090 Housekeeping & Close PTW 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

695 R15U-000-003 RC2-30-000- STEAM TRAP REPLACEMENTR15U-000-003 RC2-30-000- STEAM TRAP REPLACEMENT 1147h 01-Jan-15 12:00 AM 17-Feb-15 07:00 PM

696 PRE-SHUTDOWNPRE-SHUTDOWN 15h 01-Jan-15 12:00 AM 01-Jan-15 03:00 PM

697 OM101880 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

698 OM101885 Obtain permit for scaffolding 2h 01-Jan-15 01:00 AM 01-Jan-15 03:00 AM

699 OM101890 Erect scaffolding 10h 01-Jan-15 03:00 AM 01-Jan-15 01:00 PM

700 OM101895 Removal of insulation 2h 01-Jan-15 01:00 PM 01-Jan-15 03:00 PM

701 SHUTDOWNSHUTDOWN 64h 15-Feb-15 03:00 AM 17-Feb-15 07:00 PM

702 OM101900 Verify LT&T and Obtain permit 4h 15-Feb-15 03:00 AM 15-Feb-15 07:00 AM

703 OM101905 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 15-Feb-15 07:00 AM 15-Feb-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 13 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 14: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

704 OM101910 Cut, remove & fix new valves and traps 12h 15-Feb-15 07:00 AM 15-Feb-15 07:00 PM

705 OM101915 Carryout welding 24h 15-Feb-15 07:00 PM 16-Feb-15 07:00 PM

706 OM101920 NDT on weld joints 4h 16-Feb-15 07:00 PM 16-Feb-15 11:00 PM

707 OM101925 Carry out repair on weld, if any 6h 16-Feb-15 11:00 PM 17-Feb-15 05:00 AM

708 OM101930 Hydrotesting weld joints 12h 17-Feb-15 05:00 AM 17-Feb-15 05:00 PM

709 OM101935 Painting on weld joints 2h 17-Feb-15 05:00 PM 17-Feb-15 07:00 PM

710 OM101940 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 17-Feb-15 07:00 PM 17-Feb-15 07:00 PM

711 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

712 OM101945 Fix back insulation 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

713 OM101950 Remove scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

714 OM101955 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

715 OM101960 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

716 R15U-000-009 RC2-31-000-61-T-LS-ATTEND END BLIND LEAKR15U-000-009 RC2-31-000-61-T-LS-ATTEND END BLIND LEAK 1205h 01-Jan-15 12:00 AM 20-Feb-15 05:00 AM

717 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 12:00 AM 01-Jan-15 07:00 AM

718 OM101595 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

719 OM101600 Erect Scaffolding 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

720 OM101605 Remove Insulation 2h 01-Jan-15 05:00 AM 01-Jan-15 07:00 AM

721 SHUTDOWNSHUTDOWN 17h 19-Feb-15 12:00 PM 20-Feb-15 05:00 AM

722 OM101610 Verify LT&T and Obtain permit 2h 19-Feb-15 12:00 PM 19-Feb-15 02:00 PM

723 OM101615 Mechanical Isolation & Blinding 0h 19-Feb-15 02:00 PM 19-Feb-15 02:00 PM

724 OM101620 Cut & Remove 3h 19-Feb-15 02:00 PM 19-Feb-15 05:00 PM

725 OM101625 Fit up & Welding 4h 19-Feb-15 05:00 PM 19-Feb-15 09:00 PM

726 OM101630 Inspection 4h 19-Feb-15 09:00 PM 20-Feb-15 01:00 AM

727 OM101635 Hydro Tes ting 4h 20-Feb-15 01:00 AM 20-Feb-15 05:00 AM

728 OM101640 De-Blinding 0h 20-Feb-15 05:00 AM 20-Feb-15 05:00 AM

729 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

730 OM101645 Paint on Welded joints 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

731 OM101650 Reinstall insulations 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

732 OM101655 Remove Scaffolding 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

733 OM101660 Carry out House keeping 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

734 OM101665 Close Work permit 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

735 R15U-002-001 RC2-31-002-24-A-1206-FIN FAN COOLER PIPE REPAIRR15U-002-001 RC2-31-002-24-A-1206-FIN FAN COOLER PIPE REPAIR 1214h 01-Jan-15 12:00 AM 20-Feb-15 02:00 PM

736 PRE-SHUTDOWNPRE-SHUTDOWN 14h 01-Jan-15 12:00 AM 01-Jan-15 02:00 PM

737 OM101965 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

738 OM101970 Obtain permit for scaffolding 2h 01-Jan-15 01:00 AM 01-Jan-15 03:00 AM

739 OM101975 Shift blinds to location 1h 01-Jan-15 03:00 AM 01-Jan-15 04:00 AM

740 OM101980 Erect scaffolding 8h 01-Jan-15 04:00 AM 01-Jan-15 12:00 PM

741 OM101985 Removal of insulation 2h 01-Jan-15 12:00 PM 01-Jan-15 02:00 PM

742 SHUTDOWNSHUTDOWN 39h 18-Feb-15 11:00 PM 20-Feb-15 02:00 PM

743 OM101990 Verify LT&T and Obtain permit 3h 18-Feb-15 11:00 PM 19-Feb-15 02:00 AM

744 OM101995 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4 also) 6h 19-Feb-15 02:00 AM 19-Feb-15 08:00 AM

745 OM102000 Remove the furminated clamp 2h 19-Feb-15 08:00 AM 19-Feb-15 10:00 AM

746 OM102005 Cut & remove the damaged portion 1h 19-Feb-15 10:00 AM 19-Feb-15 11:00 AM

747 OM102010 Edge preparation & Fix the new line 1h 19-Feb-15 11:00 AM 19-Feb-15 12:00 PM

748 OM102015 Carryout welding 4h 19-Feb-15 12:00 PM 19-Feb-15 04:00 PM

749 OM102020 NDT on weld joints 6h 19-Feb-15 04:00 PM 19-Feb-15 10:00 PM

750 OM102025 Carry out repair on weld, if any 1h 19-Feb-15 10:00 PM 19-Feb-15 11:00 PM

751 OM102030 Hydrotesting weld joints 6h 19-Feb-15 11:00 PM 20-Feb-15 05:00 AM

752 OM102035 Painting on weld joints 1h 20-Feb-15 05:00 AM 20-Feb-15 06:00 AM

753 OM102040 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 8h 20-Feb-15 06:00 AM 20-Feb-15 02:00 PM

754 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

755 OM102045 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

756 OM102050 Remove scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

757 OM102055 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

758 OM102060 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 14 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 15: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

759 R15U-002-005 RC2-31-002-43-T-0078-TCV BYPASS VALVE REPLACEMENTR15U-002-005 RC2-31-002-43-T-0078-TCV BYPASS VALVE REPLACEMENT 1230h 01-Jan-15 12:00 AM 21-Feb-15 06:00 AM

760 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 12:00 AM 01-Jan-15 09:00 AM

761 OM102065 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

762 OM102070 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

763 OM102075 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

764 OM102080 Removal of insulation 1h 01-Jan-15 08:00 AM 01-Jan-15 09:00 AM

765 SHUTDOWNSHUTDOWN 16h 20-Feb-15 02:00 PM 21-Feb-15 06:00 AM

766 OM102085 Verify LT&T and Obtain permit 4h 20-Feb-15 02:00 PM 20-Feb-15 06:00 PM

767 OM102090 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 20-Feb-15 06:00 PM 20-Feb-15 06:00 PM

768 OM102095 Cutting & Fitup with new valve 2h 20-Feb-15 06:00 PM 20-Feb-15 08:00 PM

769 OM102100 Carryout welding 3h 20-Feb-15 08:00 PM 20-Feb-15 11:00 PM

770 OM102105 NDT on weld joints 1h 20-Feb-15 11:00 PM 21-Feb-15 12:00 AM

771 OM102110 Carry out repair on weld, if any 1h 21-Feb-15 12:00 AM 21-Feb-15 01:00 AM

772 OM102115 Hydrotesting weld joints 4h 21-Feb-15 01:00 AM 21-Feb-15 05:00 AM

773 OM102120 Painting on weld joints 1h 21-Feb-15 05:00 AM 21-Feb-15 06:00 AM

774 OM102125 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 21-Feb-15 06:00 AM 21-Feb-15 06:00 AM

775 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

776 OM102130 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

777 OM102135 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

778 OM102140 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

779 OM102145 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

780 R15U-002-011 RC2-31-002-PV-0075-CV-OVERHAUL & SERVICINGR15U-002-011 RC2-31-002-PV-0075-CV-OVERHAUL & SERVICING 1147h 01-Jan-15 12:00 AM 17-Feb-15 07:00 PM

781 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

782 OI100000 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

783 OI100005 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

784 SHUTDOWNSHUTDOWN 33h 16-Feb-15 10:00 AM 17-Feb-15 07:00 PM

785 OI100010 Verify LT&T and Obtain permit 1h 16-Feb-15 10:00 AM 16-Feb-15 11:00 AM

786 OI100015 Disconnect Signals / Connections for CV 1h 16-Feb-15 11:00 AM 16-Feb-15 12:00 PM

787 OI100020 Removal of CV & Install Blinds 5h 16-Feb-15 12:00 PM 16-Feb-15 05:00 PM

788 OI100025 Transport CV to Work Shop 1h 16-Feb-15 05:00 PM 16-Feb-15 06:00 PM

789 OI100030 Overhaul / Service CV 12h 16-Feb-15 06:00 PM 17-Feb-15 06:00 AM

790 OI100035 Test Valve (Refer Documentation) 2h 17-Feb-15 06:00 AM 17-Feb-15 08:00 AM

791 OI100040 Transport CV to Unit / Remove Blinds 1h 17-Feb-15 08:00 AM 17-Feb-15 09:00 AM

792 OI100045 Install CV 7h 17-Feb-15 09:00 AM 17-Feb-15 04:00 PM

793 OI100050 Loop Check & Stroke test 2h 17-Feb-15 04:00 PM 17-Feb-15 06:00 PM

794 OI100055 Inspection by RLOC 1h 17-Feb-15 06:00 PM 17-Feb-15 07:00 PM

795 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

796 OI100060 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

797 OI100065 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

798 R15U-002-016 RC2-31-002-TV-0078-CV-OVERHAUL & SERVICINGR15U-002-016 RC2-31-002-TV-0078-CV-OVERHAUL & SERVICING 27h 17-Feb-15 07:00 AM 18-Feb-15 10:00 AM

799 SHUTDOWNSHUTDOWN 27h 17-Feb-15 07:00 AM 18-Feb-15 10:00 AM

800 OI100070 Review JSA 1h 17-Feb-15 07:00 AM 17-Feb-15 08:00 AM

801 OI100075 Verify LT&T and Obtain permit 1h 17-Feb-15 08:00 AM 17-Feb-15 09:00 AM

802 OI100080 Disconnect Signals / Connections for CV 1h 17-Feb-15 09:00 AM 17-Feb-15 10:00 AM

803 OI100085 Removal of CV & Install Blinds 3h 17-Feb-15 10:00 AM 17-Feb-15 01:00 PM

804 OI100090 Transport CV to Work Shop 1h 17-Feb-15 01:00 PM 17-Feb-15 02:00 PM

805 OI100095 Overhaul / Service CV 8h 17-Feb-15 02:00 PM 17-Feb-15 10:00 PM

806 OI100100 Test Valve (Refer Documentation) 2h 17-Feb-15 10:00 PM 18-Feb-15 12:00 AM

807 OI100105 Transport CV to Unit / Remove Blinds 1h 18-Feb-15 12:00 AM 18-Feb-15 01:00 AM

808 OI100110 Install CV 5h 18-Feb-15 01:00 AM 18-Feb-15 06:00 AM

809 OI100115 Loop Check & Stroke test 2h 18-Feb-15 06:00 AM 18-Feb-15 08:00 AM

810 OI100120 Inspection by RLOC 1h 18-Feb-15 08:00 AM 18-Feb-15 09:00 AM

811 OI100125 House keeping & Close PTW 1h 18-Feb-15 09:00 AM 18-Feb-15 10:00 AM

812 R15U-002-020 RC2-31-002-PRV-0089A-CHANGE VALVE ORIENTATIONR15U-002-020 RC2-31-002-PRV-0089A-CHANGE VALVE ORIENTATION 624h 01-Jan-15 06:00 AM 22-Feb-15 06:00 AM

813 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 06:00 AM 01-Jan-15 12:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 15 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 16: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

814 OM102150 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

815 OM102155 Removal of insulation 1h 01-Jan-15 08:00 AM 01-Jan-15 09:00 AM

816 OM102160 Verify LT&T and Obtain permit 3h 01-Jan-15 09:00 AM 01-Jan-15 12:00 PM

817 OM102165 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 01-Jan-15 12:00 PM 01-Jan-15 12:00 PM

818 SHUTDOWNSHUTDOWN 12h 21-Feb-15 06:00 AM 22-Feb-15 06:00 AM

819 OM102170 Drop the valve 6h 21-Feb-15 06:00 AM 21-Feb-15 12:00 PM

820 OM102175 Re-orient & Fix the valve 6h 21-Feb-15 12:00 PM 21-Feb-15 06:00 PM

821 OM102180 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 22-Feb-15 06:00 AM 22-Feb-15 06:00 AM

822 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

823 OM102185 Fix back insulation 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

824 OM102190 Housekeeping and close PTW 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

825 R15U-005-001 RC2-31-005-29-EL-1100A-MAINT OF 33 KV SWITCH GEARR15U-005-001 RC2-31-005-29-EL-1100A-MAINT OF 33 KV SWITCH GEAR 525h 01-Jan-15 06:00 AM 13-Feb-15 03:00 PM

826 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

827 OE100120 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

828 SHUTDOWNSHUTDOWN 9h 13-Feb-15 06:00 AM 13-Feb-15 03:00 PM

829 OE100125 Verify LT&T and Obtain permit 1h 13-Feb-15 06:00 AM 13-Feb-15 07:00 AM

830 OE100130 Do Insp. & Maint. as per Checklist 7h 13-Feb-15 07:00 AM 13-Feb-15 02:00 PM

831 OE100135 Witness the Job as per the Checklist 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM

832 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

833 OE100140 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

834 R15U-005-002 RC2-31-005-29-EL-1100B-MAINT OF 33 KV SWITCH GEARR15U-005-002 RC2-31-005-29-EL-1100B-MAINT OF 33 KV SWITCH GEAR 585h 01-Jan-15 06:00 AM 18-Feb-15 03:00 PM

835 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

836 OE100145 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

837 SHUTDOWNSHUTDOWN 9h 18-Feb-15 06:00 AM 18-Feb-15 03:00 PM

838 OE100150 Verify LT&T and Obtain permit 1h 18-Feb-15 06:00 AM 18-Feb-15 07:00 AM

839 OE100155 Do Insp. & Maint. as per Checklist 7h 18-Feb-15 07:00 AM 18-Feb-15 02:00 PM

840 OE100160 Witness the Job as per the Checklist 1h 18-Feb-15 02:00 PM 18-Feb-15 03:00 PM

841 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

842 OE100165 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

843 R15U-005-003 RC2-31-005-29-EL-1101A-MAINT OF 6.6 KVR15U-005-003 RC2-31-005-29-EL-1101A-MAINT OF 6.6 KV 617h 01-Jan-15 06:00 AM 21-Feb-15 11:00 AM

844 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

845 OE100170 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

846 SHUTDOWNSHUTDOWN 113h 12-Feb-15 06:00 AM 21-Feb-15 11:00 AM

847 OE100175 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

848 OE100180 Assist with the Vendor for Support 110h 12-Feb-15 07:00 AM 21-Feb-15 09:00 AM

849 OE100185 Do Insp. & Maint. as per Checklist 110h 12-Feb-15 07:00 AM 21-Feb-15 09:00 AM

850 OE100190 Witness the Job as per the Checklist 2h 21-Feb-15 09:00 AM 21-Feb-15 11:00 AM

851 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

852 OE100195 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

853 R15U-005-004 RC2-31-005-29-EL-1101B-MAINT OF 6.6 KVR15U-005-004 RC2-31-005-29-EL-1101B-MAINT OF 6.6 KV 641h 01-Jan-15 06:00 AM 23-Feb-15 11:00 AM

854 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

855 OE100200 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

856 SHUTDOWNSHUTDOWN 113h 14-Feb-15 06:00 AM 23-Feb-15 11:00 AM

857 OE100205 Verify LT&T and Obtain permit 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

858 OE100210 Assist with the Vendor for Support 110h 14-Feb-15 07:00 AM 23-Feb-15 09:00 AM

859 OE100215 Do Insp. & Maint. as per Checklist 110h 14-Feb-15 07:00 AM 23-Feb-15 09:00 AM

860 OE100220 Witness the Job as per the Checklist 2h 23-Feb-15 09:00 AM 23-Feb-15 11:00 AM

861 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

862 OE100225 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

863 R15U-005-005 RC2-31-005-29-EL-1102A-MAINT OF 415 VR15U-005-005 RC2-31-005-29-EL-1102A-MAINT OF 415 V 559h 01-Jan-15 06:00 AM 16-Feb-15 01:00 PM

864 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

865 OE100230 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

866 SHUTDOWNSHUTDOWN 59h 11-Feb-15 02:00 PM 16-Feb-15 01:00 PM

867 OE100235 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 16 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 17: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

868 OE100240 Assist with the Vendor for Support 28h 11-Feb-15 03:00 PM 14-Feb-15 07:00 AM

869 OE100245 Do Insp. & Maint. as per Checklist 28h 14-Feb-15 07:00 AM 16-Feb-15 11:00 AM

870 OE100250 Witness the Job as per the Checklist 2h 16-Feb-15 11:00 AM 16-Feb-15 01:00 PM

871 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

872 OE100255 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

873 R15U-005-006 RC2-31-005-29-EL-1102B-MAINT OF 415 VR15U-005-006 RC2-31-005-29-EL-1102B-MAINT OF 415 V 613h 01-Jan-15 06:00 AM 21-Feb-15 07:00 AM

874 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

875 OE100260 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

876 SHUTDOWNSHUTDOWN 59h 16-Feb-15 08:00 AM 21-Feb-15 07:00 AM

877 OE100265 Verify LT&T and Obtain permit 1h 16-Feb-15 08:00 AM 16-Feb-15 09:00 AM

878 OE100270 Assist with the Vendor for Support 28h 16-Feb-15 09:00 AM 18-Feb-15 01:00 PM

879 OE100275 Do Insp. & Maint. as per Checklist 28h 18-Feb-15 01:00 PM 20-Feb-15 05:00 PM

880 OE100280 Witness the Job as per the Checklist 2h 20-Feb-15 05:00 PM 21-Feb-15 07:00 AM

881 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

882 OE100285 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

883 R15U-005-007 RC2-31-005-29-EL-1102C-MAINT OF 415 VR15U-005-007 RC2-31-005-29-EL-1102C-MAINT OF 415 V 667h 01-Jan-15 06:00 AM 25-Feb-15 01:00 PM

884 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

885 OE100290 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

886 SHUTDOWNSHUTDOWN 59h 20-Feb-15 02:00 PM 25-Feb-15 01:00 PM

887 OE100295 Verify LT&T and Obtain permit 1h 20-Feb-15 02:00 PM 20-Feb-15 03:00 PM

888 OE100300 Assist with the Vendor for Support 28h 20-Feb-15 03:00 PM 23-Feb-15 07:00 AM

889 OE100305 Do Insp. & Maint. as per Checklist 28h 23-Feb-15 07:00 AM 25-Feb-15 11:00 AM

890 OE100310 Witness the Job as per the Checklist 2h 25-Feb-15 11:00 AM 25-Feb-15 01:00 PM

891 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

892 OE100315 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

893 R15U-005-008 RC2-31-005-29-EL-1103A-MAINT OF 415 VR15U-005-008 RC2-31-005-29-EL-1103A-MAINT OF 415 V 553h 01-Jan-15 06:00 AM 16-Feb-15 07:00 AM

894 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

895 OE100320 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

896 SHUTDOWNSHUTDOWN 53h 11-Feb-15 02:00 PM 16-Feb-15 07:00 AM

897 OE100325 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

898 OE100330 Assist with the Vendor for Support 25h 11-Feb-15 03:00 PM 13-Feb-15 04:00 PM

899 OE100335 Do Insp. & Maint. as per Checklist 25h 13-Feb-15 04:00 PM 15-Feb-15 05:00 PM

900 OE100340 Witness the Job as per the Checklist 2h 15-Feb-15 05:00 PM 16-Feb-15 07:00 AM

901 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

902 OE100345 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

903 R15U-005-009 RC2-31-005-29-EL-1103B-MAINT OF 415 VR15U-005-009 RC2-31-005-29-EL-1103B-MAINT OF 415 V 585h 01-Jan-15 06:00 AM 18-Feb-15 03:00 PM

904 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

905 OE100350 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

906 SHUTDOWNSHUTDOWN 31h 16-Feb-15 08:00 AM 18-Feb-15 03:00 PM

907 OE100355 Verify LT&T and Obtain permit 1h 16-Feb-15 08:00 AM 16-Feb-15 09:00 AM

908 OE100360 Assist with the Vendor for Support 14h 16-Feb-15 09:00 AM 17-Feb-15 11:00 AM

909 OE100365 Do Insp. & Maint. as per Checklist 14h 17-Feb-15 11:00 AM 18-Feb-15 01:00 PM

910 OE100370 Witness the Job as per the Checklist 2h 18-Feb-15 01:00 PM 18-Feb-15 03:00 PM

911 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

912 OE100375 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

913 R15U-005-020 RC2-31-005-29-EL-1201-MAINT OF 33 KV XFMRR15U-005-020 RC2-31-005-29-EL-1201-MAINT OF 33 KV XFMR 566h 01-Jan-15 06:00 AM 17-Feb-15 08:00 AM

914 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM

915 OE100540 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

916 OE100545 Inform KHARAMA for switching schedule from Bus bar 'A' to 'B' 3h 01-Jan-15 08:00 AM 01-Jan-15 11:00 AM

917 OE100550 Inform KHARAMA for switching schedule from Bus bar 'A' to 'B' 1h 01-Jan-15 11:00 AM 01-Jan-15 12:00 PM

918 OE100555 Mobilization of Scaffolding Materials 2h 01-Jan-15 12:00 PM 01-Jan-15 02:00 PM

919 SHUTDOWNSHUTDOWN 62h 12-Feb-15 06:00 AM 17-Feb-15 08:00 AM

920 OE100560 Transfer 6.6 kv bus bar from 'A' to 'B' in all 2 sub station 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

921 OE100565 Isolate power to 33 KV line as per checklist & SMP 1h 12-Feb-15 07:00 AM 12-Feb-15 08:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 17 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 18: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

922 OE100570 Carry out LT&T for incomer 1 2h 12-Feb-15 08:00 AM 12-Feb-15 10:00 AM

923 OE100575 Isolate power to 6.6kv line & carry out LT&T 2h 12-Feb-15 10:00 AM 12-Feb-15 12:00 PM

924 OE100580 Obtain PTW 1h 12-Feb-15 12:00 PM 12-Feb-15 01:00 PM

925 OE100585 Erect scaffolding for OLTC removal 3h 12-Feb-15 01:00 PM 12-Feb-15 04:00 PM

926 OE100590 Remove OLTC & perform inspection 3h 12-Feb-15 04:00 PM 13-Feb-15 07:00 AM

927 OE100595 Carry out servicing as per inspection findings 8h 13-Feb-15 07:00 AM 13-Feb-15 03:00 PM

928 OE100600 Reinstate OLTC in tank 2h 13-Feb-15 03:00 PM 13-Feb-15 05:00 PM

929 OE100605 Modify the scaffolding as per request 3h 13-Feb-15 05:00 PM 14-Feb-15 08:00 AM

930 OE100610 PM Transformer EL-1201 as per chec klist 12h 14-Feb-15 08:00 AM 15-Feb-15 08:00 AM

931 OE100615 Perform oil filteration/replacement as per findings 12h 15-Feb-15 08:00 AM 16-Feb-15 08:00 AM

932 OE100620 Test all protective equipments,Alarms & Trip circuits 5h 16-Feb-15 08:00 AM 16-Feb-15 01:00 PM

933 OE100625 Final inspection of complete unit 2h 16-Feb-15 01:00 PM 16-Feb-15 03:00 PM

934 OE100630 Remove scaffolds 2h 16-Feb-15 03:00 PM 16-Feb-15 05:00 PM

935 OE100635 Energise 6.6kv line as per SMP 1h 16-Feb-15 05:00 PM 16-Feb-15 06:00 PM

936 OE100640 Energise 33Kv line as per SMP 1h 17-Feb-15 06:00 AM 17-Feb-15 07:00 AM

937 OE100645 Housekeeping & Close PTW 1h 17-Feb-15 07:00 AM 17-Feb-15 08:00 AM

938 R15U-005-021 RC2-31-005-29-EL-1201-MAINT OF XFMR AUX MODULER15U-005-021 RC2-31-005-29-EL-1201-MAINT OF XFMR AUX MODULE 503h 01-Jan-15 06:00 AM 11-Feb-15 05:00 PM

939 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

940 OE100650 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

941 SHUTDOWNSHUTDOWN 3h 11-Feb-15 02:00 PM 11-Feb-15 05:00 PM

942 OE100655 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

943 OE100660 Do Insp. & Maint. as per Checklist 2h 11-Feb-15 03:00 PM 11-Feb-15 05:00 PM

944 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

945 OE100665 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

946 R15U-005-022 RC2-31-005-29-EL-1202-MAINT OF 33 KV XFMRR15U-005-022 RC2-31-005-29-EL-1202-MAINT OF 33 KV XFMR 626h 01-Jan-15 06:00 AM 22-Feb-15 08:00 AM

947 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM

948 OE100670 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

949 OE100675 Inform KHARAMA for switching schedule from Bus bar 'A' to 'B' 3h 01-Jan-15 08:00 AM 01-Jan-15 11:00 AM

950 OE100680 Inform KHARAMA for switching schedule from Bus bar 'A' to 'B' 1h 01-Jan-15 11:00 AM 01-Jan-15 12:00 PM

951 OE100685 Mobilization of Scaffolding Materials 2h 01-Jan-15 12:00 PM 01-Jan-15 02:00 PM

952 SHUTDOWNSHUTDOWN 62h 17-Feb-15 06:00 AM 22-Feb-15 08:00 AM

953 OE100690 Transfer 6.6 kv bus bar from 'A' to 'B' in all 2 sub station 1h 17-Feb-15 06:00 AM 17-Feb-15 07:00 AM

954 OE100695 Isolate power to 33 KV line as per checklist & SMP 1h 17-Feb-15 07:00 AM 17-Feb-15 08:00 AM

955 OE100700 Carry out LT&T for incomer 1 2h 17-Feb-15 08:00 AM 17-Feb-15 10:00 AM

956 OE100705 Isolate power to 6.6kv line & carry out LT&T 2h 17-Feb-15 10:00 AM 17-Feb-15 12:00 PM

957 OE100710 Obtain PTW 1h 17-Feb-15 12:00 PM 17-Feb-15 01:00 PM

958 OE100715 Erect scaffolding for OLTC removal 3h 17-Feb-15 01:00 PM 17-Feb-15 04:00 PM

959 OE100720 Remove OLTC & perform inspection 3h 17-Feb-15 04:00 PM 18-Feb-15 07:00 AM

960 OE100725 Carry out servicing as per inspection findings 8h 18-Feb-15 07:00 AM 18-Feb-15 03:00 PM

961 OE100730 Reinstate OLTC in tank 2h 18-Feb-15 03:00 PM 18-Feb-15 05:00 PM

962 OE100735 Modify the scaffolding as per request 3h 18-Feb-15 05:00 PM 19-Feb-15 08:00 AM

963 OE100740 PM Transformer EL-1201 as per chec klist 12h 19-Feb-15 08:00 AM 20-Feb-15 08:00 AM

964 OE100745 Perform oil filteration/replacement as per findings 12h 20-Feb-15 08:00 AM 21-Feb-15 08:00 AM

965 OE100750 Test all protective equipments,Alarms & Trip circuits 5h 21-Feb-15 08:00 AM 21-Feb-15 01:00 PM

966 OE100755 Final inspection of complete unit 2h 21-Feb-15 01:00 PM 21-Feb-15 03:00 PM

967 OE100760 Remove scaffolds 2h 21-Feb-15 03:00 PM 21-Feb-15 05:00 PM

968 OE100765 Energise 6.6kv line as per SMP 1h 21-Feb-15 05:00 PM 21-Feb-15 06:00 PM

969 OE100770 Energise 33Kv line as per SMP 1h 22-Feb-15 06:00 AM 22-Feb-15 07:00 AM

970 OE100775 Housekeeping & Close PTW 1h 22-Feb-15 07:00 AM 22-Feb-15 08:00 AM

971 R15U-005-023 RC2-31-005-29-EL-1202-MAINT OF XFMR AUX MODULER15U-005-023 RC2-31-005-29-EL-1202-MAINT OF XFMR AUX MODULE 551h 01-Jan-15 06:00 AM 15-Feb-15 05:00 PM

972 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

973 OE100780 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

974 SHUTDOWNSHUTDOWN 3h 15-Feb-15 02:00 PM 15-Feb-15 05:00 PM

975 OE100785 Verify LT&T and Obtain permit 1h 15-Feb-15 02:00 PM 15-Feb-15 03:00 PM

976 OE100790 Do Insp. & Maint. as per Checklist 2h 15-Feb-15 03:00 PM 15-Feb-15 05:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 18 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 19: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

977 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

978 OE100795 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

979 R15U-005-024 RC2-31-005-29-EL-1203-MAINT OF POWER DISTRIBUTIONR15U-005-024 RC2-31-005-29-EL-1203-MAINT OF POWER DISTRIBUTION 523h 01-Jan-15 06:00 AM 13-Feb-15 01:00 PM

980 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

981 OE100800 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

982 SHUTDOWNSHUTDOWN 11h 12-Feb-15 02:00 PM 13-Feb-15 01:00 PM

983 OE100805 Verify LT&T and Obtain permit 1h 12-Feb-15 02:00 PM 12-Feb-15 03:00 PM

984 OE100810 Do Insp. & Maint. as per Checklist 10h 12-Feb-15 03:00 PM 13-Feb-15 01:00 PM

985 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

986 OE100815 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

987 R15U-005-025 RC2-31-005-29-EL-1204-MAINT OF POWER DISTRIBUTIONR15U-005-025 RC2-31-005-29-EL-1204-MAINT OF POWER DISTRIBUTION 538h 01-Jan-15 06:00 AM 14-Feb-15 04:00 PM

988 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

989 OE100820 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

990 SHUTDOWNSHUTDOWN 10h 14-Feb-15 06:00 AM 14-Feb-15 04:00 PM

991 OE100825 Verify LT&T and Obtain permit 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

992 OE100830 Do Insp. & Maint. as per Checklist 9h 14-Feb-15 07:00 AM 14-Feb-15 04:00 PM

993 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

994 OE100835 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

995 R15U-005-026 RC2-31-005-29-EL-1205-MAINT OF POWER DISTRIBUTIONR15U-005-026 RC2-31-005-29-EL-1205-MAINT OF POWER DISTRIBUTION 523h 01-Jan-15 06:00 AM 13-Feb-15 01:00 PM

996 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

997 OE100840 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

998 SHUTDOWNSHUTDOWN 11h 12-Feb-15 02:00 PM 13-Feb-15 01:00 PM

999 OE100845 Verify LT&T and Obtain permit 1h 12-Feb-15 02:00 PM 12-Feb-15 03:00 PM

1000 OE100850 Do Insp. & Maint. as per Checklist 10h 12-Feb-15 03:00 PM 13-Feb-15 01:00 PM

1001 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1002 OE100855 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1003 R15U-005-027 RC2-31-005-29-EL-1206-MAINT OF POWER DISTRIBUTIONR15U-005-027 RC2-31-005-29-EL-1206-MAINT OF POWER DISTRIBUTION 540h 01-Jan-15 06:00 AM 14-Feb-15 06:00 PM

1004 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1005 OE100860 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1006 SHUTDOWNSHUTDOWN 12h 14-Feb-15 06:00 AM 14-Feb-15 06:00 PM

1007 OE100865 Verify LT&T and Obtain permit 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

1008 OE100870 Do Insp. & Maint. as per Checklist 11h 14-Feb-15 07:00 AM 14-Feb-15 06:00 PM

1009 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1010 OE100875 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1011 R15U-005-060 RC2-31-005-29-EL-1901-MAINT OF NERR15U-005-060 RC2-31-005-29-EL-1901-MAINT OF NER 512h 01-Jan-15 06:00 AM 12-Feb-15 02:00 PM

1012 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1013 OE101160 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1014 SHUTDOWNSHUTDOWN 8h 12-Feb-15 06:00 AM 12-Feb-15 02:00 PM

1015 OE101165 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

1016 OE101170 Do Insp. & Maint. as per Checklist 7h 12-Feb-15 07:00 AM 12-Feb-15 02:00 PM

1017 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1018 OE101175 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1019 R15U-005-061 RC2-31-005-29-EL-1902-MAINT OF NERR15U-005-061 RC2-31-005-29-EL-1902-MAINT OF NER 536h 01-Jan-15 06:00 AM 14-Feb-15 02:00 PM

1020 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1021 OE101180 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1022 SHUTDOWNSHUTDOWN 8h 14-Feb-15 06:00 AM 14-Feb-15 02:00 PM

1023 OE101185 Verify LT&T and Obtain permit 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

1024 OE101190 Do Insp. & Maint. as per Checklist 7h 14-Feb-15 07:00 AM 14-Feb-15 02:00 PM

1025 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1026 OE101195 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1027 R15U-005-068 RC2-31-005-29-EL-2101A-MAINT OF 6.6 KVR15U-005-068 RC2-31-005-29-EL-2101A-MAINT OF 6.6 KV 617h 01-Jan-15 06:00 AM 21-Feb-15 11:00 AM

1028 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1029 OE101280 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 19 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 20: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1030 SHUTDOWNSHUTDOWN 113h 12-Feb-15 06:00 AM 21-Feb-15 11:00 AM

1031 OE101285 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

1032 OE101290 Assist with the Vendor for Support 110h 12-Feb-15 07:00 AM 21-Feb-15 09:00 AM

1033 OE101295 Do Insp. & Maint. as per Checklist 110h 12-Feb-15 07:00 AM 21-Feb-15 09:00 AM

1034 OE101300 Witness the Job as per the Checklist 2h 21-Feb-15 09:00 AM 21-Feb-15 11:00 AM

1035 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1036 OE101305 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1037 R15U-005-069 RC2-31-005-29-EL-2101B-MAINT OF 6.6 KVR15U-005-069 RC2-31-005-29-EL-2101B-MAINT OF 6.6 KV 617h 01-Jan-15 06:00 AM 21-Feb-15 11:00 AM

1038 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1039 OE101310 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1040 SHUTDOWNSHUTDOWN 113h 12-Feb-15 06:00 AM 21-Feb-15 11:00 AM

1041 OE101315 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

1042 OE101320 Assist with the Vendor for Support 110h 12-Feb-15 07:00 AM 21-Feb-15 09:00 AM

1043 OE101325 Do Insp. & Maint. as per Checklist 110h 12-Feb-15 07:00 AM 21-Feb-15 09:00 AM

1044 OE101330 Witness the Job as per the Checklist 2h 21-Feb-15 09:00 AM 21-Feb-15 11:00 AM

1045 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1046 OE101335 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1047 R15U-005-070 RC2-31-005-29-EL-2102A-MAINT OF 415 VR15U-005-070 RC2-31-005-29-EL-2102A-MAINT OF 415 V 533h 01-Jan-15 06:00 AM 14-Feb-15 11:00 AM

1048 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1049 OE101340 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1050 SHUTDOWNSHUTDOWN 43h 10-Feb-15 04:00 PM 14-Feb-15 11:00 AM

1051 OE101345 Verify LT&T and Obtain permit 1h 10-Feb-15 04:00 PM 10-Feb-15 05:00 PM

1052 OE101350 Assist with the Vendor for Support 20h 10-Feb-15 05:00 PM 12-Feb-15 01:00 PM

1053 OE101355 Do Insp. & Maint. as per Checklist 20h 12-Feb-15 01:00 PM 14-Feb-15 09:00 AM

1054 OE101360 Witness the Job as per the Checklist 2h 14-Feb-15 09:00 AM 14-Feb-15 11:00 AM

1055 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1056 OE101365 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1057 R15U-005-071 RC2-31-005-29-EL-2102B-MAINT OF 415 VR15U-005-071 RC2-31-005-29-EL-2102B-MAINT OF 415 V 597h 01-Jan-15 06:00 AM 19-Feb-15 03:00 PM

1058 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1059 OE101370 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1060 SHUTDOWNSHUTDOWN 47h 15-Feb-15 04:00 PM 19-Feb-15 03:00 PM

1061 OE101375 Verify LT&T and Obtain permit 1h 15-Feb-15 04:00 PM 15-Feb-15 05:00 PM

1062 OE101380 Assist with the Vendor for Support 22h 15-Feb-15 05:00 PM 17-Feb-15 03:00 PM

1063 OE101385 Do Insp. & Maint. as per Checklist 22h 17-Feb-15 03:00 PM 19-Feb-15 01:00 PM

1064 OE101390 Witness the Job as per the Checklist 2h 19-Feb-15 01:00 PM 19-Feb-15 03:00 PM

1065 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1066 OE101395 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1067 R15U-005-072 RC2-31-005-29-EL-2102C-MAINT OF 415 VR15U-005-072 RC2-31-005-29-EL-2102C-MAINT OF 415 V 679h 01-Jan-15 06:00 AM 26-Feb-15 01:00 PM

1068 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1069 OE101400 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1070 SHUTDOWNSHUTDOWN 79h 20-Feb-15 06:00 AM 26-Feb-15 01:00 PM

1071 OE101405 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

1072 OE101410 Assist with the Vendor for Support 38h 20-Feb-15 07:00 AM 23-Feb-15 09:00 AM

1073 OE101415 Do Insp. & Maint. as per Checklist 38h 23-Feb-15 09:00 AM 26-Feb-15 11:00 AM

1074 OE101420 Witness the Job as per the Checklist 2h 26-Feb-15 11:00 AM 26-Feb-15 01:00 PM

1075 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1076 OE101425 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1077 R15U-005-073 RC2-31-005-29-EL-2103A-MAINT OF 415 VR15U-005-073 RC2-31-005-29-EL-2103A-MAINT OF 415 V 545h 01-Jan-15 06:00 AM 15-Feb-15 11:00 AM

1078 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1079 OE101430 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1080 SHUTDOWNSHUTDOWN 55h 10-Feb-15 04:00 PM 15-Feb-15 11:00 AM

1081 OE101435 Verify LT&T and Obtain permit 1h 10-Feb-15 04:00 PM 10-Feb-15 05:00 PM

1082 OE101440 Assist with the Vendor for Support 26h 10-Feb-15 05:00 PM 13-Feb-15 07:00 AM

1083 OE101445 Do Insp. & Maint. as per Checklist 26h 13-Feb-15 07:00 AM 15-Feb-15 09:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 20 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 21: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1084 OE101450 Witness the Job as per the Checklist 2h 15-Feb-15 09:00 AM 15-Feb-15 11:00 AM

1085 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1086 OE101455 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1087 R15U-005-074 RC2-31-005-29-EL-2103B-MAINT OF 415 VR15U-005-074 RC2-31-005-29-EL-2103B-MAINT OF 415 V 609h 01-Jan-15 06:00 AM 20-Feb-15 03:00 PM

1088 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1089 OE101460 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1090 SHUTDOWNSHUTDOWN 59h 15-Feb-15 04:00 PM 20-Feb-15 03:00 PM

1091 OE101465 Verify LT&T and Obtain permit 1h 15-Feb-15 04:00 PM 15-Feb-15 05:00 PM

1092 OE101470 Assist with the Vendor for Support 28h 15-Feb-15 05:00 PM 18-Feb-15 09:00 AM

1093 OE101475 Do Insp. & Maint. as per Checklist 28h 18-Feb-15 09:00 AM 20-Feb-15 01:00 PM

1094 OE101480 Witness the Job as per the Checklist 2h 20-Feb-15 01:00 PM 20-Feb-15 03:00 PM

1095 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1096 OE101485 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1097 R15U-005-075 RC2-31-005-29-EL-2104A-MAINT OF 415 VR15U-005-075 RC2-31-005-29-EL-2104A-MAINT OF 415 V 527h 01-Jan-15 06:00 AM 13-Feb-15 05:00 PM

1098 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1099 OE101490 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1100 SHUTDOWNSHUTDOWN 37h 10-Feb-15 04:00 PM 13-Feb-15 05:00 PM

1101 OE101495 Verify LT&T and Obtain permit 1h 10-Feb-15 04:00 PM 10-Feb-15 05:00 PM

1102 OE101500 Assist with the Vendor for Support 17h 10-Feb-15 05:00 PM 12-Feb-15 10:00 AM

1103 OE101505 Do Insp. & Maint. as per Checklist 17h 12-Feb-15 10:00 AM 13-Feb-15 03:00 PM

1104 OE101510 Witness the Job as per the Checklist 2h 13-Feb-15 03:00 PM 13-Feb-15 05:00 PM

1105 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1106 OE101515 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1107 R15U-005-076 RC2-31-005-29-EL-2104B-MAINT OF 415 VR15U-005-076 RC2-31-005-29-EL-2104B-MAINT OF 415 V 577h 01-Jan-15 06:00 AM 18-Feb-15 07:00 AM

1108 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1109 OE101520 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1110 SHUTDOWNSHUTDOWN 27h 15-Feb-15 04:00 PM 18-Feb-15 07:00 AM

1111 OE101525 Verify LT&T and Obtain permit 1h 15-Feb-15 04:00 PM 15-Feb-15 05:00 PM

1112 OE101530 Assist with the Vendor for Support 12h 15-Feb-15 05:00 PM 16-Feb-15 05:00 PM

1113 OE101535 Do Insp. & Maint. as per Checklist 12h 16-Feb-15 05:00 PM 17-Feb-15 05:00 PM

1114 OE101540 Witness the Job as per the Checklist 2h 17-Feb-15 05:00 PM 18-Feb-15 07:00 AM

1115 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1116 OE101545 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1117 R15U-005-087 RC2-31-005-29-EL-2201-MAINT OF POWER DISTRIBUTIONR15U-005-087 RC2-31-005-29-EL-2201-MAINT OF POWER DISTRIBUTION 515h 01-Jan-15 06:00 AM 12-Feb-15 05:00 PM

1118 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1119 OE101690 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1120 SHUTDOWNSHUTDOWN 11h 12-Feb-15 06:00 AM 12-Feb-15 05:00 PM

1121 OE101695 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

1122 OE101700 Do Insp. & Maint. as per Checklist 10h 12-Feb-15 07:00 AM 12-Feb-15 05:00 PM

1123 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1124 OE101705 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1125 R15U-005-088 RC2-31-005-29-EL-2202-MAINT OF POWER DISTRIBUTIONR15U-005-088 RC2-31-005-29-EL-2202-MAINT OF POWER DISTRIBUTION 563h 01-Jan-15 06:00 AM 16-Feb-15 05:00 PM

1126 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1127 OE101710 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1128 SHUTDOWNSHUTDOWN 11h 16-Feb-15 06:00 AM 16-Feb-15 05:00 PM

1129 OE101715 Verify LT&T and Obtain permit 1h 16-Feb-15 06:00 AM 16-Feb-15 07:00 AM

1130 OE101720 Do Insp. & Maint. as per Checklist 10h 16-Feb-15 07:00 AM 16-Feb-15 05:00 PM

1131 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1132 OE101725 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1133 R15U-005-089 RC2-31-005-29-EL-2203-MAINT OF POWER DISTRIBUTIONR15U-005-089 RC2-31-005-29-EL-2203-MAINT OF POWER DISTRIBUTION 515h 01-Jan-15 06:00 AM 12-Feb-15 05:00 PM

1134 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1135 OE101730 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1136 SHUTDOWNSHUTDOWN 11h 12-Feb-15 06:00 AM 12-Feb-15 05:00 PM

1137 OE101735 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 21 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 22: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1138 OE101740 Do Insp. & Maint. as per Checklist 10h 12-Feb-15 07:00 AM 12-Feb-15 05:00 PM

1139 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1140 OE101745 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1141 R15U-005-090 RC2-31-005-29-EL-2204-MAINT OF POWER DISTRIBUTIONR15U-005-090 RC2-31-005-29-EL-2204-MAINT OF POWER DISTRIBUTION 551h 01-Jan-15 06:00 AM 15-Feb-15 05:00 PM

1142 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1143 OE101750 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1144 SHUTDOWNSHUTDOWN 11h 15-Feb-15 06:00 AM 15-Feb-15 05:00 PM

1145 OE101755 Verify LT&T and Obtain permit 1h 15-Feb-15 06:00 AM 15-Feb-15 07:00 AM

1146 OE101760 Do Insp. & Maint. as per Checklist 10h 15-Feb-15 07:00 AM 15-Feb-15 05:00 PM

1147 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1148 OE101765 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1149 R15U-005-091 RC2-31-005-29-EL-2205-MAINT OF POWER DISTRIBUTIONR15U-005-091 RC2-31-005-29-EL-2205-MAINT OF POWER DISTRIBUTION 515h 01-Jan-15 06:00 AM 12-Feb-15 05:00 PM

1150 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1151 OE101770 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1152 SHUTDOWNSHUTDOWN 11h 12-Feb-15 06:00 AM 12-Feb-15 05:00 PM

1153 OE101775 Verify LT&T and Obtain permit 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

1154 OE101780 Do Insp. & Maint. as per Checklist 10h 12-Feb-15 07:00 AM 12-Feb-15 05:00 PM

1155 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1156 OE101785 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1157 R15U-005-092 RC2-31-005-29-EL-2206-MAINT OF POWER DISTRIBUTIONR15U-005-092 RC2-31-005-29-EL-2206-MAINT OF POWER DISTRIBUTION 563h 01-Jan-15 06:00 AM 16-Feb-15 05:00 PM

1158 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1159 OE101790 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1160 SHUTDOWNSHUTDOWN 11h 16-Feb-15 06:00 AM 16-Feb-15 05:00 PM

1161 OE101795 Verify LT&T and Obtain permit 1h 16-Feb-15 06:00 AM 16-Feb-15 07:00 AM

1162 OE101800 Do Insp. & Maint. as per Checklist 10h 16-Feb-15 07:00 AM 16-Feb-15 05:00 PM

1163 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1164 OE101805 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1165 R15U-005-130 RC2-31-005-29-EL-1102C-MAINT OF 415 VR15U-005-130 RC2-31-005-29-EL-1102C-MAINT OF 415 V 625h 01-Jan-15 06:00 AM 22-Feb-15 07:00 AM

1166 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1167 OE102095 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1168 SHUTDOWNSHUTDOWN 17h 20-Feb-15 02:00 PM 22-Feb-15 07:00 AM

1169 OE102100 Verify LT&T and Obtain permit 1h 20-Feb-15 02:00 PM 20-Feb-15 03:00 PM

1170 OE102105 Assist with the Vendor for Support 7h 20-Feb-15 03:00 PM 21-Feb-15 10:00 AM

1171 OE102110 Provide Emergency 24VDC Power supply EL-1102C 7h 21-Feb-15 10:00 AM 21-Feb-15 05:00 PM

1172 OE102115 Witness and Do Preliminary Tes t 2h 21-Feb-15 05:00 PM 22-Feb-15 07:00 AM

1173 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1174 OE102120 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1175 R15U-005-131 RC2-31-005-29-EL-2102C-MAINT OF 415 VR15U-005-131 RC2-31-005-29-EL-2102C-MAINT OF 415 V 617h 01-Jan-15 06:00 AM 21-Feb-15 11:00 AM

1176 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1177 OE102125 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1178 SHUTDOWNSHUTDOWN 17h 20-Feb-15 06:00 AM 21-Feb-15 11:00 AM

1179 OE102130 Verify LT&T and Obtain permit 1h 20-Feb-15 06:00 AM 20-Feb-15 07:00 AM

1180 OE102135 Assist with the Vendor for Support 7h 20-Feb-15 07:00 AM 20-Feb-15 02:00 PM

1181 OE102140 Provide Emergency 24VDC Power supply EL-1102C 7h 20-Feb-15 02:00 PM 21-Feb-15 09:00 AM

1182 OE102145 Witness and Do Preliminary Tes t 2h 21-Feb-15 09:00 AM 21-Feb-15 11:00 AM

1183 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1184 OE102150 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1185 R15U-011-001 RC2-31-011-07-B-1207A-HS DRAIN VALVE REPLACEMENTR15U-011-001 RC2-31-011-07-B-1207A-HS DRAIN VALVE REPLACEMENT 1059h 01-Jan-15 12:00 AM 14-Feb-15 03:00 AM

1186 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1187 OM102195 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1188 OM102200 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1189 OM102205 Erect scaffolding 1h 01-Jan-15 04:00 AM 01-Jan-15 05:00 AM

1190 OM102210 Removal of insulation 1h 01-Jan-15 05:00 AM 01-Jan-15 06:00 AM

1191 SHUTDOWNSHUTDOWN 27h 13-Feb-15 12:00 AM 14-Feb-15 03:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 22 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 23: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1192 OM102215 Verify LT&T and Obtain permit 2h 13-Feb-15 12:00 AM 13-Feb-15 02:00 AM

1193 OM102220 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 13-Feb-15 02:00 AM 13-Feb-15 02:00 AM

1194 OM102225 Cutting & Fitup with new valves 6h 13-Feb-15 02:00 AM 13-Feb-15 08:00 AM

1195 OM102230 Carryout welding 9h 13-Feb-15 08:00 AM 13-Feb-15 05:00 PM

1196 OM102235 NDT on weld joints 1h 13-Feb-15 05:00 PM 13-Feb-15 06:00 PM

1197 OM102240 Carry out repair on weld if any 4h 13-Feb-15 06:00 PM 13-Feb-15 10:00 PM

1198 OM102245 Hydrotesting weld joints 4h 13-Feb-15 10:00 PM 14-Feb-15 02:00 AM

1199 OM102250 Painting on weld joints 1h 14-Feb-15 02:00 AM 14-Feb-15 03:00 AM

1200 OM102255 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 14-Feb-15 03:00 AM 14-Feb-15 03:00 AM

1201 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1202 OM102260 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1203 OM102265 Remove scaffolding 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1204 OM102270 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1205 OM102275 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1206 R15U-011-002 RC2-31-011-07-B-1207A-BOILER HS VALVE REPLACEMENR15U-011-002 RC2-31-011-07-B-1207A-BOILER HS VALVE REPLACEMEN 1089h 01-Jan-15 12:00 AM 15-Feb-15 09:00 AM

1207 PRE-SHUTDOWNPRE-SHUTDOWN 54h 01-Jan-15 12:00 AM 03-Jan-15 06:00 AM

1208 OM102280 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1209 OM102285 Pre-fabricate the lines as per dwg. 24h 01-Jan-15 02:00 AM 02-Jan-15 02:00 AM

1210 OM102290 Inspection of weld joints 4h 02-Jan-15 02:00 AM 02-Jan-15 06:00 AM

1211 OM102295 Hydrotest the new valves 2h 02-Jan-15 06:00 AM 02-Jan-15 08:00 AM

1212 OM102300 Shift tested valves, prefab lines, blinds 4h 02-Jan-15 08:00 AM 02-Jan-15 12:00 PM

1213 OM102305 Obtain permit for scaffolding 2h 02-Jan-15 12:00 PM 02-Jan-15 02:00 PM

1214 OM102310 Erect scaffolding 12h 02-Jan-15 02:00 PM 03-Jan-15 02:00 AM

1215 OM102315 Removal of insulation 4h 03-Jan-15 02:00 AM 03-Jan-15 06:00 AM

1216 SHUTDOWNSHUTDOWN 75h 12-Feb-15 06:00 AM 15-Feb-15 09:00 AM

1217 OM102320 Verify LT&T and Obtain permit 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM

1218 OM102325 Blinding as per blindlist (OSBL Steam System LT&T) 16h 12-Feb-15 08:00 AM 13-Feb-15 12:00 AM

1219 OM102330 Drop the valves 6h 13-Feb-15 12:00 AM 13-Feb-15 06:00 AM

1220 OM102335 Fix new valves in position 8h 13-Feb-15 06:00 AM 13-Feb-15 02:00 PM

1221 OM102340 Shift removed valves for servicing 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM

1222 OM102345 Cut & remove the pipe 2h 13-Feb-15 03:00 PM 13-Feb-15 05:00 PM

1223 OM102350 Fitup the fabricated line in position 1h 13-Feb-15 05:00 PM 13-Feb-15 06:00 PM

1224 OM102355 Carryout welding 4h 13-Feb-15 06:00 PM 13-Feb-15 10:00 PM

1225 OM102360 NDT on weld joints 2h 13-Feb-15 10:00 PM 14-Feb-15 12:00 AM

1226 OM102365 Carry out repair on weld if any 2h 14-Feb-15 12:00 AM 14-Feb-15 02:00 AM

1227 OM102370 Hydrotesting weld joints 6h 14-Feb-15 02:00 AM 14-Feb-15 08:00 AM

1228 OM102375 Painting on weld joints 1h 14-Feb-15 08:00 AM 14-Feb-15 09:00 AM

1229 OM102380 De-blinding (OSBL Steam System LT&T) 24h 14-Feb-15 09:00 AM 15-Feb-15 09:00 AM

1230 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1231 OM102385 Fix back insulation 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1232 OM102390 Remove scaffolding 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1233 OM102395 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1234 OM102400 Q.C. documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1235 R15U-012-001 RC2-31-012-07-B-1207B-HS DRAIN VALVE REPLACEMENTR15U-012-001 RC2-31-012-07-B-1207B-HS DRAIN VALVE REPLACEMENT 1091h 01-Jan-15 12:00 AM 15-Feb-15 11:00 AM

1236 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1237 OM102405 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1238 OM102410 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1239 OM102415 Erect scaffolding 1h 01-Jan-15 04:00 AM 01-Jan-15 05:00 AM

1240 OM102420 Removal of insulation 1h 01-Jan-15 05:00 AM 01-Jan-15 06:00 AM

1241 SHUTDOWNSHUTDOWN 27h 14-Feb-15 08:00 AM 15-Feb-15 11:00 AM

1242 OM102425 Verify LT&T and Obtain permit 2h 14-Feb-15 08:00 AM 14-Feb-15 10:00 AM

1243 OM102430 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 14-Feb-15 10:00 AM 14-Feb-15 10:00 AM

1244 OM102435 Cutting & Fitup with new valves 6h 14-Feb-15 10:00 AM 14-Feb-15 04:00 PM

1245 OM102440 Carryout welding 9h 14-Feb-15 04:00 PM 15-Feb-15 01:00 AM

1246 OM102445 NDT on weld joints 1h 15-Feb-15 01:00 AM 15-Feb-15 02:00 AM

1247 OM102450 Carry out repair on weld if any 4h 15-Feb-15 02:00 AM 15-Feb-15 06:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 23 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 24: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1248 OM102455 Hydrotesting weld joints 4h 15-Feb-15 06:00 AM 15-Feb-15 10:00 AM

1249 OM102460 Painting on weld joints 1h 15-Feb-15 10:00 AM 15-Feb-15 11:00 AM

1250 OM102465 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 15-Feb-15 11:00 AM 15-Feb-15 11:00 AM

1251 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1252 OM102470 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1253 OM102475 Remove scaffolding 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1254 OM102480 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1255 OM102485 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1256 R15U-012-002 RC2-31-012-07-B-1207B-BOILER HS VALVE REPLACEMENTR15U-012-002 RC2-31-012-07-B-1207B-BOILER HS VALVE REPLACEMENT 1135h 01-Jan-15 12:00 AM 17-Feb-15 07:00 AM

1257 PRE-SHUTDOWNPRE-SHUTDOWN 54h 01-Jan-15 12:00 AM 03-Jan-15 06:00 AM

1258 OM102490 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1259 OM102495 Pre-fabricate the lines as per dwg. 24h 01-Jan-15 02:00 AM 02-Jan-15 02:00 AM

1260 OM102500 Inspection of weld joints 4h 02-Jan-15 02:00 AM 02-Jan-15 06:00 AM

1261 OM102505 Hydrotest the new valves 2h 02-Jan-15 06:00 AM 02-Jan-15 08:00 AM

1262 OM102510 Shift tested valves, pre-fab lines 4h 02-Jan-15 08:00 AM 02-Jan-15 12:00 PM

1263 OM102515 Obtain permit for scaffolding 2h 02-Jan-15 12:00 PM 02-Jan-15 02:00 PM

1264 OM102520 Erect scaffolding 12h 02-Jan-15 02:00 PM 03-Jan-15 02:00 AM

1265 OM102525 Removal of insulation 4h 03-Jan-15 02:00 AM 03-Jan-15 06:00 AM

1266 SHUTDOWNSHUTDOWN 35h 15-Feb-15 08:00 PM 17-Feb-15 07:00 AM

1267 OM102530 Verify LT&T and Obtain permit 2h 15-Feb-15 08:00 PM 15-Feb-15 10:00 PM

1268 OM102535 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 15-Feb-15 10:00 PM 15-Feb-15 10:00 PM

1269 OM102540 Drop the valves 6h 15-Feb-15 10:00 PM 16-Feb-15 04:00 AM

1270 OM102545 Fix new valves in position 8h 16-Feb-15 04:00 AM 16-Feb-15 12:00 PM

1271 OM102550 Shift removed valves for servicing 1h 16-Feb-15 12:00 PM 16-Feb-15 01:00 PM

1272 OM102555 Cut & remove the pipe 2h 16-Feb-15 01:00 PM 16-Feb-15 03:00 PM

1273 OM102560 Fitup the fabricated line in position 1h 16-Feb-15 03:00 PM 16-Feb-15 04:00 PM

1274 OM102565 Carryout welding 4h 16-Feb-15 04:00 PM 16-Feb-15 08:00 PM

1275 OM102570 NDT on weld joints 2h 16-Feb-15 08:00 PM 16-Feb-15 10:00 PM

1276 OM102575 Carry out repair on weld if any 2h 16-Feb-15 10:00 PM 17-Feb-15 12:00 AM

1277 OM102580 Hydrotesting weld joints 6h 17-Feb-15 12:00 AM 17-Feb-15 06:00 AM

1278 OM102585 Painting on weld joints 1h 17-Feb-15 06:00 AM 17-Feb-15 07:00 AM

1279 OM102590 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 17-Feb-15 07:00 AM 17-Feb-15 07:00 AM

1280 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1281 OM102595 Fix back insulation 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1282 OM102600 Remove scaffolding 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1283 OM102605 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1284 OM102610 Q.C. documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1285 R15U-013-001 RC2-31-013-07-B-1207C-HS DRAIN VALVE REPLACEMENTR15U-013-001 RC2-31-013-07-B-1207C-HS DRAIN VALVE REPLACEMENT 1175h 01-Jan-15 12:00 AM 18-Feb-15 11:00 PM

1286 PRE-SHUTDOWNPRE-SHUTDOWN 54h 01-Jan-15 12:00 AM 03-Jan-15 06:00 AM

1287 OM102615 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1288 OM102620 Pre-fabricate the lines as per dwg. 24h 01-Jan-15 02:00 AM 02-Jan-15 02:00 AM

1289 OM102625 Inspection of weld joints 4h 02-Jan-15 02:00 AM 02-Jan-15 06:00 AM

1290 OM102630 Hydrotest the new valves 2h 02-Jan-15 06:00 AM 02-Jan-15 08:00 AM

1291 OM102635 Shift tested valves, pre-fab lines 4h 02-Jan-15 08:00 AM 02-Jan-15 12:00 PM

1292 OM102640 Obtain permit for scaffolding 2h 02-Jan-15 12:00 PM 02-Jan-15 02:00 PM

1293 OM102645 Erect scaffolding 12h 02-Jan-15 02:00 PM 03-Jan-15 02:00 AM

1294 OM102650 Removal of insulation 4h 03-Jan-15 02:00 AM 03-Jan-15 06:00 AM

1295 SHUTDOWNSHUTDOWN 35h 17-Feb-15 12:00 PM 18-Feb-15 11:00 PM

1296 OM102655 Verify LT&T and Obtain permit 2h 17-Feb-15 12:00 PM 17-Feb-15 02:00 PM

1297 OM102660 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 17-Feb-15 02:00 PM 17-Feb-15 02:00 PM

1298 OM102665 Drop the valves 6h 17-Feb-15 02:00 PM 17-Feb-15 08:00 PM

1299 OM102670 Fix new valves in position 8h 17-Feb-15 08:00 PM 18-Feb-15 04:00 AM

1300 OM102675 Shift removed valves for servicing 1h 18-Feb-15 04:00 AM 18-Feb-15 05:00 AM

1301 OM102680 Cut & remove the pipe 2h 18-Feb-15 05:00 AM 18-Feb-15 07:00 AM

1302 OM102685 Fitup the fabricated line in position 1h 18-Feb-15 07:00 AM 18-Feb-15 08:00 AM

1303 OM102690 Carryout welding 4h 18-Feb-15 08:00 AM 18-Feb-15 12:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 24 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 25: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1304 OM102695 NDT on weld joints 2h 18-Feb-15 12:00 PM 18-Feb-15 02:00 PM

1305 OM102700 Carry out repair on weld if any 2h 18-Feb-15 02:00 PM 18-Feb-15 04:00 PM

1306 OM102705 Hydrotesting weld joints 6h 18-Feb-15 04:00 PM 18-Feb-15 10:00 PM

1307 OM102710 Painting on weld joints 1h 18-Feb-15 10:00 PM 18-Feb-15 11:00 PM

1308 OM102715 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 18-Feb-15 11:00 PM 18-Feb-15 11:00 PM

1309 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1310 OM102720 Fix back insulation 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1311 OM102725 Remove scaffolding 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1312 OM102730 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1313 OM102735 Q.C. documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1314 R15U-013-003 RC2-31-013-84-ST-1207C-HS DRAIN VALVE REPLACEMENTR15U-013-003 RC2-31-013-84-ST-1207C-HS DRAIN VALVE REPLACEMENT 1123h 01-Jan-15 12:00 AM 16-Feb-15 07:00 PM

1315 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1316 OM102740 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1317 OM102745 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1318 OM102750 Erect scaffolding 1h 01-Jan-15 04:00 AM 01-Jan-15 05:00 AM

1319 OM102755 Removal of insulation 1h 01-Jan-15 05:00 AM 01-Jan-15 06:00 AM

1320 SHUTDOWNSHUTDOWN 27h 15-Feb-15 04:00 PM 16-Feb-15 07:00 PM

1321 OM102760 Verify LT&T and Obtain permit 2h 15-Feb-15 04:00 PM 15-Feb-15 06:00 PM

1322 OM102765 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 15-Feb-15 06:00 PM 15-Feb-15 06:00 PM

1323 OM102770 Cutting & Fitup with new valves 6h 15-Feb-15 06:00 PM 16-Feb-15 12:00 AM

1324 OM102775 Carryout welding 9h 16-Feb-15 12:00 AM 16-Feb-15 09:00 AM

1325 OM102780 NDT on weld joints 1h 16-Feb-15 09:00 AM 16-Feb-15 10:00 AM

1326 OM102785 Carry out repair on weld if any 4h 16-Feb-15 10:00 AM 16-Feb-15 02:00 PM

1327 OM102790 Hydrotesting weld joints 4h 16-Feb-15 02:00 PM 16-Feb-15 06:00 PM

1328 OM102795 Painting on weld joints 1h 16-Feb-15 06:00 PM 16-Feb-15 07:00 PM

1329 OM102800 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4als o) 0h 16-Feb-15 07:00 PM 16-Feb-15 07:00 PM

1330 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1331 OM102805 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1332 OM102810 Remove scaffolding 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1333 OM102815 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1334 OM102820 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1335 R15U-020-003 RC2-31-020-41-E-1205-EXCH-INTER & EXTERNAL INSPR15U-020-003 RC2-31-020-41-E-1205-EXCH-INTER & EXTERNAL INSP 1258h 01-Jan-15 12:00 AM 22-Feb-15 10:00 AM

1336 PRE-SHUTDOWNPRE-SHUTDOWN 11h 01-Jan-15 12:00 AM 01-Jan-15 11:00 AM

1337 OM105545 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1338 OM105550 Shift blinds to location 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1339 OM105555 Erect Scaffolding & load bearings. 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1340 OM105560 Removal of Insulation 3h 01-Jan-15 08:00 AM 01-Jan-15 11:00 AM

1341 SHUTDOWNSHUTDOWN 100h 18-Feb-15 06:00 AM 22-Feb-15 10:00 AM

1342 OM105565 Purging to be carried out 6h 18-Feb-15 06:00 AM 18-Feb-15 12:00 PM

1343 OM105570 Verify LT&T and Obtain PTW 2h 18-Feb-15 12:00 PM 18-Feb-15 02:00 PM

1344 OM105575 Drop spools & carryout blinding. 4h 18-Feb-15 02:00 PM 18-Feb-15 06:00 PM

1345 OM105580 Open stub end & return bend housing flanges 3h 18-Feb-15 06:00 PM 18-Feb-15 09:00 PM

1346 OM105585 Carryout prelim. inspn & Offer for AFI 2h 18-Feb-15 09:00 PM 18-Feb-15 11:00 PM

1347 OM105590 Pull out tube bundle & perform AFI 6h 18-Feb-15 11:00 PM 19-Feb-15 05:00 AM

1348 OM105595 Shift tube bundle to jetting area 2h 19-Feb-15 05:00 AM 19-Feb-15 07:00 AM

1349 OM105600 100% Hydrojetting of tube external & internal 8h 19-Feb-15 07:00 AM 19-Feb-15 03:00 PM

1350 OM105605 Hydrojetting of shell, channel cover & flange 3h 19-Feb-15 03:00 PM 19-Feb-15 06:00 PM

1351 OM105610 Inspn. of tube bundle, channel head & shell 3h 19-Feb-15 06:00 PM 19-Feb-15 09:00 PM

1352 OM105615 Carryout RFECT inspection on 50 tubes. 10h 19-Feb-15 09:00 PM 20-Feb-15 07:00 AM

1353 OM105620 NDT as per ERG recommendation 3h 20-Feb-15 07:00 AM 20-Feb-15 10:00 AM

1354 OM105625 Visual inspection & Thickness monitoring 3h 20-Feb-15 10:00 AM 20-Feb-15 01:00 PM

1355 OM105630 Shift back tube bundle to the locaton 2h 20-Feb-15 01:00 PM 20-Feb-15 03:00 PM

1356 OM105635 Reinstallation of tube bundle 5h 20-Feb-15 03:00 PM 20-Feb-15 08:00 PM

1357 OM105640 Hydrotest both shell side & tube side 5h 20-Feb-15 08:00 PM 21-Feb-15 01:00 AM

1358 OM105645 Inspection report and repairs, if any 20h 21-Feb-15 01:00 AM 21-Feb-15 09:00 PM

1359 OM105650 Final inspection 2h 21-Feb-15 09:00 PM 21-Feb-15 11:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 25 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 26: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1360 OM105655 Boxup the exchanger tighten the bolts. 5h 21-Feb-15 11:00 PM 22-Feb-15 04:00 AM

1361 OM105660 De-Blinding & Reinstall spools 6h 22-Feb-15 04:00 AM 22-Feb-15 10:00 AM

1362 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1363 OM105665 Reinstall insulations 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1364 OM105670 Removal of Scaffolds 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1365 OM105675 Housekeeping and close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1366 R15U-020-004 RC2-31-020-41-E-1210-EXCH-EXTERNAL & CUI INSPR15U-020-004 RC2-31-020-41-E-1210-EXCH-EXTERNAL & CUI INSP 594h 01-Jan-15 06:00 AM 19-Feb-15 12:00 PM

1367 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 06:00 AM 01-Jan-15 03:00 PM

1368 OM105955 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

1369 OM105960 Site visit with ERG & verify inspn. areas 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM

1370 OM105965 Erect Scaffolding, wherever required 5h 01-Jan-15 10:00 AM 01-Jan-15 03:00 PM

1371 SHUTDOWNSHUTDOWN 34h 16-Feb-15 02:00 PM 19-Feb-15 12:00 PM

1372 OM105970 Obtain PTW 2h 16-Feb-15 02:00 PM 16-Feb-15 04:00 PM

1373 OM105975 Remove Insulations as reqd. for inspn. 8h 16-Feb-15 04:00 PM 17-Feb-15 12:00 PM

1374 OM105980 Inspn. of nozzles, shell, suspected areas & CUI 12h 17-Feb-15 12:00 PM 18-Feb-15 12:00 PM

1375 OM105985 Carryout repair. 10h 18-Feb-15 12:00 PM 19-Feb-15 10:00 AM

1376 OM105990 Final inspection 2h 19-Feb-15 10:00 AM 19-Feb-15 12:00 PM

1377 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM

1378 OM105995 Reinstall insulations 8h 01-Jan-15 06:00 AM 01-Jan-15 02:00 PM

1379 OM106000 Dismantle & remove scaffolds. 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

1380 OM106005 Housekeeping and close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1381 R15U-020-005 RC2-31-020-41-E-1211-EXCH-INTER, EXTERNAL & CUIR15U-020-005 RC2-31-020-41-E-1211-EXCH-INTER, EXTERNAL & CUI 1152h 01-Jan-15 12:00 AM 18-Feb-15 12:00 AM

1382 PRE-SHUTDOWNPRE-SHUTDOWN 21h 01-Jan-15 12:00 AM 01-Jan-15 09:00 PM

1383 OM105815 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1384 OM105820 Shift blinds to location 3h 01-Jan-15 02:00 AM 01-Jan-15 05:00 AM

1385 OM105825 Site visit with ERG & verify inspn. areas 2h 01-Jan-15 05:00 AM 01-Jan-15 07:00 AM

1386 OM105830 Erect Scaffolding, wherever required 8h 01-Jan-15 07:00 AM 01-Jan-15 03:00 PM

1387 OM105835 Removal of Insulation 6h 01-Jan-15 03:00 PM 01-Jan-15 09:00 PM

1388 SHUTDOWNSHUTDOWN 138h 12-Feb-15 06:00 AM 18-Feb-15 12:00 AM

1389 OM105840 Purging to be carried out 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM

1390 OM105845 Verify LT&T and Obtain PTW 2h 12-Feb-15 12:00 PM 12-Feb-15 02:00 PM

1391 OM105850 Drop spools & carryout blinding. 10h 12-Feb-15 02:00 PM 13-Feb-15 12:00 AM

1392 OM105855 Detorque, & remove the channel cover 5h 13-Feb-15 12:00 AM 13-Feb-15 05:00 AM

1393 OM105860 Carryout prelim. inspn & Offer for AFI 2h 13-Feb-15 05:00 AM 13-Feb-15 07:00 AM

1394 OM105865 Pull out tube bundle & perform AFI 7h 13-Feb-15 07:00 AM 13-Feb-15 02:00 PM

1395 OM105870 Shift tube bundle to jetting area 2h 13-Feb-15 02:00 PM 13-Feb-15 04:00 PM

1396 OM105875 100% Hydrojetting of tube external & internal 18h 13-Feb-15 04:00 PM 14-Feb-15 10:00 AM

1397 OM105880 Hydrojetting of shell, channel cover & flange 4h 14-Feb-15 10:00 AM 14-Feb-15 02:00 PM

1398 OM105885 Inspn. of tube bundle, channel head & shell 2h 14-Feb-15 02:00 PM 14-Feb-15 04:00 PM

1399 OM105890 Carryout RFECT inspection on 125 tubes. 16h 14-Feb-15 04:00 PM 15-Feb-15 08:00 AM

1400 OM105895 NDT of welds & suspected areas 3h 15-Feb-15 08:00 AM 15-Feb-15 11:00 AM

1401 OM105900 Thickness monitoring & CUI 6h 15-Feb-15 11:00 AM 15-Feb-15 05:00 PM

1402 OM105905 Shift back tube bundle to the locaton 2h 15-Feb-15 05:00 PM 15-Feb-15 07:00 PM

1403 OM105910 Reinstallation of tube bundle 5h 15-Feb-15 07:00 PM 16-Feb-15 12:00 AM

1404 OM105915 Hydrotest shell with test flange, shell & tube side 8h 16-Feb-15 12:00 AM 16-Feb-15 08:00 AM

1405 OM105920 Inspection report and repairs, if any 20h 16-Feb-15 08:00 AM 17-Feb-15 04:00 AM

1406 OM105925 Final inspection 2h 17-Feb-15 04:00 AM 17-Feb-15 06:00 AM

1407 OM105930 Box up and tighten the bolts. 6h 17-Feb-15 06:00 AM 17-Feb-15 12:00 PM

1408 OM105935 De-Blinding & Reinstall spools 12h 17-Feb-15 12:00 PM 18-Feb-15 12:00 AM

1409 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1410 OM105940 Reinstall insulations 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1411 OM105945 Removal of Scaffolds 5h 01-Jan-15 12:00 AM 01-Jan-15 05:00 AM

1412 OM105950 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1413 R15U-020-006 RC2-31-020-43-F-0003-INST-FT REPLACEMENTR15U-020-006 RC2-31-020-43-F-0003-INST-FT REPLACEMENT 1094h 01-Jan-15 12:00 AM 15-Feb-15 02:00 PM

1414 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 12:00 AM 01-Jan-15 05:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 26 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 27: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1415 OI101750 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1416 OI101755 Erect Scaffolding 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

1417 SHUTDOWNSHUTDOWN 20h 14-Feb-15 06:00 PM 15-Feb-15 02:00 PM

1418 OI101760 Verify LT&T and Obtain permit 2h 14-Feb-15 06:00 PM 14-Feb-15 08:00 PM

1419 OI101765 Disconnect connections 3h 14-Feb-15 08:00 PM 14-Feb-15 11:00 PM

1420 OI101770 Remove the existing flowmeter 4h 14-Feb-15 11:00 PM 15-Feb-15 03:00 AM

1421 OI101775 Fix back new flowmeter 5h 15-Feb-15 03:00 AM 15-Feb-15 08:00 AM

1422 OI101780 Re - Connect & check reading 4h 15-Feb-15 08:00 AM 15-Feb-15 12:00 PM

1423 OI101785 Inspection by RLOC 2h 15-Feb-15 12:00 PM 15-Feb-15 02:00 PM

1424 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1425 OI101790 Remove Scaffolding 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1426 OI101795 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1427 R15U-020-008 RC2-31-020-95-D-1221-LINE REPLACEMENTR15U-020-008 RC2-31-020-95-D-1221-LINE REPLACEMENT 1181h 01-Jan-15 12:00 AM 19-Feb-15 05:00 AM

1428 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 12:00 AM 01-Jan-15 09:00 AM

1429 OM101670 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1430 OM101675 Erect Scaffolding 6h 01-Jan-15 01:00 AM 01-Jan-15 07:00 AM

1431 OM101680 Remove Insulation 2h 01-Jan-15 07:00 AM 01-Jan-15 09:00 AM

1432 SHUTDOWNSHUTDOWN 17h 18-Feb-15 12:00 PM 19-Feb-15 05:00 AM

1433 OM101685 Verify LT&T and Obtain permit 2h 18-Feb-15 12:00 PM 18-Feb-15 02:00 PM

1434 OM101690 Mechanical Isolation & Blinding 0h 18-Feb-15 02:00 PM 18-Feb-15 02:00 PM

1435 OM101695 Cut & Remove 3h 18-Feb-15 02:00 PM 18-Feb-15 05:00 PM

1436 OM101700 Fit up & Welding 4h 18-Feb-15 05:00 PM 18-Feb-15 09:00 PM

1437 OM101705 Inspection 4h 18-Feb-15 09:00 PM 19-Feb-15 01:00 AM

1438 OM101710 Hydro Tes ting 4h 19-Feb-15 01:00 AM 19-Feb-15 05:00 AM

1439 OM101715 De-Blinding 0h 19-Feb-15 05:00 AM 19-Feb-15 05:00 AM

1440 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1441 OM101720 Paint on Welded joints 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1442 OM101725 Reinstall insulations 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1443 OM101730 Remove Scaffolding 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1444 OM101735 Carry out House keeping 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1445 OM101740 Close Work permit 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1446 R15U-020-009 RC2-31-020-95-D-1221-INTER, EXTERNAL & CUI INSPR15U-020-009 RC2-31-020-95-D-1221-INTER, EXTERNAL & CUI INSP 1150h 01-Jan-15 12:00 AM 17-Feb-15 10:00 PM

1447 PRE-SHUTDOWNPRE-SHUTDOWN 26h 01-Jan-15 12:00 AM 02-Jan-15 02:00 AM

1448 OM100005 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1449 OM100010 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

1450 OM100015 Remove Insulation 8h 01-Jan-15 10:00 AM 01-Jan-15 06:00 PM

1451 OM100020 CUI-Scaffolding & remove insulation 8h 01-Jan-15 06:00 PM 02-Jan-15 02:00 AM

1452 SHUTDOWNSHUTDOWN 76h 14-Feb-15 06:00 PM 17-Feb-15 10:00 PM

1453 OM100025 Verify LT&T and Obtain permit 4h 14-Feb-15 06:00 PM 14-Feb-15 10:00 PM

1454 OM100030 Mechanical Isolation & Blinding 8h 14-Feb-15 10:00 PM 15-Feb-15 06:00 AM

1455 OM100035 Manway Opening & Providing a Ventilation & Lighting 8h 15-Feb-15 06:00 AM 15-Feb-15 02:00 PM

1456 OM100040 CUI Inspection & Repair 12h 15-Feb-15 02:00 PM 16-Feb-15 02:00 AM

1457 OM100045 Obtain Confined space permit & Erect Internal Scaffolding 8h 16-Feb-15 02:00 AM 16-Feb-15 10:00 AM

1458 OM100050 Preliminary Inspection 4h 16-Feb-15 10:00 AM 16-Feb-15 02:00 PM

1459 OM100055 Cleaning & Repair 12h 16-Feb-15 02:00 PM 17-Feb-15 02:00 AM

1460 OM100060 Remove Internal Scaffolding 4h 17-Feb-15 02:00 AM 17-Feb-15 06:00 AM

1461 OM100065 Final Inspection 4h 17-Feb-15 06:00 AM 17-Feb-15 10:00 AM

1462 OM100070 Manway Box-up 4h 17-Feb-15 10:00 AM 17-Feb-15 02:00 PM

1463 OM100075 De-Blinding 8h 17-Feb-15 02:00 PM 17-Feb-15 10:00 PM

1464 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1465 OM100080 Reinstall insulations 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1466 OM100085 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1467 OM100090 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1468 OM100095 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1469 R15U-020-012 RC2-31-020-95-D-1222-LP CONDENSATE REPAIRR15U-020-012 RC2-31-020-95-D-1222-LP CONDENSATE REPAIR 1234h 01-Jan-15 12:00 AM 21-Feb-15 10:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 27 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 28: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1470 PRE-SHUTDOWNPRE-SHUTDOWN 182h 01-Jan-15 12:00 AM 08-Jan-15 02:00 PM

1471 OM101745 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1472 OM101750 Erect Scaffolding 120h 01-Jan-15 02:00 AM 06-Jan-15 02:00 AM

1473 OM101755 Remove Insulation 60h 06-Jan-15 02:00 AM 08-Jan-15 02:00 PM

1474 SHUTDOWNSHUTDOWN 220h 12-Feb-15 06:00 AM 21-Feb-15 10:00 AM

1475 OM101760 Verify LT&T and Obtain permit 4h 12-Feb-15 06:00 AM 12-Feb-15 10:00 AM

1476 OM101765 Mechanical Isolation & Blinding 0h 12-Feb-15 10:00 AM 12-Feb-15 10:00 AM

1477 OM101770 Cut & Remove 72h 12-Feb-15 10:00 AM 15-Feb-15 10:00 AM

1478 OM101775 Fit up & Welding 144h 13-Feb-15 10:00 AM 19-Feb-15 10:00 AM

1479 OM101780 Inspection 96h 16-Feb-15 10:00 AM 20-Feb-15 10:00 AM

1480 OM101785 Hydro Tes ting 24h 20-Feb-15 10:00 AM 21-Feb-15 10:00 AM

1481 OM101790 De-Blinding 0h 21-Feb-15 10:00 AM 21-Feb-15 10:00 AM

1482 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1483 OM101795 Paint on Welded joints 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1484 OM101800 Reinstall insulations 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1485 OM101805 Remove Scaffolding 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1486 OM101810 Carry out House keeping 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1487 OM101815 Close Work permit 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1488 R15U-020-018 RC2-31-020-LV-0001-CV-OVERHAUL & SERVICINGR15U-020-018 RC2-31-020-LV-0001-CV-OVERHAUL & SERVICING 29h 11-Feb-15 06:00 AM 12-Feb-15 11:00 AM

1489 SHUTDOWNSHUTDOWN 29h 11-Feb-15 06:00 AM 12-Feb-15 11:00 AM

1490 OI100130 Review JSA 1h 11-Feb-15 06:00 AM 11-Feb-15 07:00 AM

1491 OI100135 Verify LT&T and Obtain permit 1h 11-Feb-15 07:00 AM 11-Feb-15 08:00 AM

1492 OI100140 Disconnect Signals / Connections for CV 1h 11-Feb-15 08:00 AM 11-Feb-15 09:00 AM

1493 OI100145 Removal of CV & Install Blinds 4h 11-Feb-15 09:00 AM 11-Feb-15 01:00 PM

1494 OI100150 Transport CV to Work Shop 1h 11-Feb-15 01:00 PM 11-Feb-15 02:00 PM

1495 OI100155 Overhaul / Service CV 8h 11-Feb-15 02:00 PM 11-Feb-15 10:00 PM

1496 OI100160 Test Valve (Refer Documentation) 2h 11-Feb-15 10:00 PM 12-Feb-15 12:00 AM

1497 OI100165 Transport CV to Unit / Remove Blinds 1h 12-Feb-15 12:00 AM 12-Feb-15 01:00 AM

1498 OI100170 Install CV 6h 12-Feb-15 01:00 AM 12-Feb-15 07:00 AM

1499 OI100175 Loop Check & Stroke test 2h 12-Feb-15 07:00 AM 12-Feb-15 09:00 AM

1500 OI100180 Inspection by RLOC 1h 12-Feb-15 09:00 AM 12-Feb-15 10:00 AM

1501 OI100185 House keeping & Close PTW 1h 12-Feb-15 10:00 AM 12-Feb-15 11:00 AM

1502 R15U-020-019 RC2-31-020-LV-0030-CV-OVERHAUL & SERVICINGR15U-020-019 RC2-31-020-LV-0030-CV-OVERHAUL & SERVICING 29h 12-Feb-15 06:00 AM 13-Feb-15 11:00 AM

1503 SHUTDOWNSHUTDOWN 29h 12-Feb-15 06:00 AM 13-Feb-15 11:00 AM

1504 OI100190 Review JSA 1h 12-Feb-15 06:00 AM 12-Feb-15 07:00 AM

1505 OI100195 Verify LT&T and Obtain permit 1h 12-Feb-15 07:00 AM 12-Feb-15 08:00 AM

1506 OI100200 Disconnect Signals / Connections for CV 1h 12-Feb-15 08:00 AM 12-Feb-15 09:00 AM

1507 OI100205 Removal of CV & Install Blinds 4h 12-Feb-15 09:00 AM 12-Feb-15 01:00 PM

1508 OI100210 Transport CV to Work Shop 1h 12-Feb-15 01:00 PM 12-Feb-15 02:00 PM

1509 OI100215 Overhaul / Service CV 8h 12-Feb-15 02:00 PM 12-Feb-15 10:00 PM

1510 OI100220 Test Valve (Refer Documentation) 2h 12-Feb-15 10:00 PM 13-Feb-15 12:00 AM

1511 OI100225 Transport CV to Unit / Remove Blinds 1h 13-Feb-15 12:00 AM 13-Feb-15 01:00 AM

1512 OI100230 Install CV 6h 13-Feb-15 01:00 AM 13-Feb-15 07:00 AM

1513 OI100235 Loop Check & Stroke test 2h 13-Feb-15 07:00 AM 13-Feb-15 09:00 AM

1514 OI100240 Inspection by RLOC 1h 13-Feb-15 09:00 AM 13-Feb-15 10:00 AM

1515 OI100245 House keeping & Close PTW 1h 13-Feb-15 10:00 AM 13-Feb-15 11:00 AM

1516 R15U-020-020 RC2-31-020-LV-0033-CV-OVERHAUL & SERVICINGR15U-020-020 RC2-31-020-LV-0033-CV-OVERHAUL & SERVICING 1063h 01-Jan-15 12:00 AM 14-Feb-15 07:00 AM

1517 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1518 OI100250 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1519 OI100255 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

1520 SHUTDOWNSHUTDOWN 25h 13-Feb-15 06:00 AM 14-Feb-15 07:00 AM

1521 OI100260 Verify LT&T and Obtain permit 1h 13-Feb-15 06:00 AM 13-Feb-15 07:00 AM

1522 OI100265 Disconnect Signals / Connections for CV 1h 13-Feb-15 07:00 AM 13-Feb-15 08:00 AM

1523 OI100270 Removal of CV & Install Blinds 3h 13-Feb-15 08:00 AM 13-Feb-15 11:00 AM

1524 OI100275 Transport CV to Work Shop 1h 13-Feb-15 11:00 AM 13-Feb-15 12:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 28 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 29: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1525 OI100280 Overhaul / Service CV 8h 13-Feb-15 12:00 PM 13-Feb-15 08:00 PM

1526 OI100285 Test Valve (Refer Documentation) 2h 13-Feb-15 08:00 PM 13-Feb-15 10:00 PM

1527 OI100290 Transport CV to Unit / Remove Blinds 1h 13-Feb-15 10:00 PM 13-Feb-15 11:00 PM

1528 OI100295 Install CV 5h 13-Feb-15 11:00 PM 14-Feb-15 04:00 AM

1529 OI100300 Loop Check & Stroke test 2h 14-Feb-15 04:00 AM 14-Feb-15 06:00 AM

1530 OI100305 Inspection by RLOC 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

1531 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1532 OI100310 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1533 OI100315 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1534 R15U-022-001 RC2-31-022-35-F-1202-MIDEA REPLACEMENTR15U-022-001 RC2-31-022-35-F-1202-MIDEA REPLACEMENT 1240h 01-Jan-15 12:00 AM 21-Feb-15 04:00 PM

1535 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1536 OM106220 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1537 OM106225 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

1538 SHUTDOWNSHUTDOWN 70h 18-Feb-15 06:00 PM 21-Feb-15 04:00 PM

1539 OM106230 Verify LT&T & Obtain Permit 4h 18-Feb-15 06:00 PM 18-Feb-15 10:00 PM

1540 OM106235 Mechanical Isolation & Blinding 8h 18-Feb-15 10:00 PM 19-Feb-15 06:00 AM

1541 OM106240 Open Manway, Provide Ventilation & Lighting 8h 19-Feb-15 06:00 AM 19-Feb-15 02:00 PM

1542 OM106245 Obtain Confined space permit 2h 19-Feb-15 02:00 PM 19-Feb-15 04:00 PM

1543 OM106250 Preliminary Inspection 4h 19-Feb-15 04:00 PM 19-Feb-15 08:00 PM

1544 OM106255 Erect Internal Scaffolding 4h 19-Feb-15 08:00 PM 20-Feb-15 12:00 AM

1545 OM106260 Cleaning & Repair 12h 20-Feb-15 12:00 AM 20-Feb-15 12:00 PM

1546 OM106265 Remove Internal Scaffolding 4h 20-Feb-15 12:00 PM 20-Feb-15 04:00 PM

1547 OM106270 Renew Mushroom Strainers 8h 20-Feb-15 04:00 PM 21-Feb-15 12:00 AM

1548 OM106275 Final Inspection 4h 21-Feb-15 12:00 AM 21-Feb-15 04:00 AM

1549 OM106280 Manway Box-up 4h 21-Feb-15 04:00 AM 21-Feb-15 08:00 AM

1550 OM106285 De-Blinding 8h 21-Feb-15 08:00 AM 21-Feb-15 04:00 PM

1551 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1552 OM106290 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1553 OM106295 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1554 OM106300 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1555 R15U-022-002 RC2-31-022-35-F-1202-INTER & EXTERNAL INSPR15U-022-002 RC2-31-022-35-F-1202-INTER & EXTERNAL INSP 1252h 01-Jan-15 12:00 AM 22-Feb-15 04:00 AM

1556 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1557 OM106305 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1558 SHUTDOWNSHUTDOWN 12h 21-Feb-15 04:00 PM 22-Feb-15 04:00 AM

1559 OM106310 Verify LT&T & Obtain Permit 4h 21-Feb-15 04:00 PM 21-Feb-15 08:00 PM

1560 OM106315 Open Manway, Provide Ventilation & Lighting 8h 21-Feb-15 08:00 PM 22-Feb-15 04:00 AM

1561 OM106320 Obtain Confined space permit 2h 22-Feb-15 02:00 AM 22-Feb-15 04:00 AM

1562 OM106325 Removal of Media 8h 21-Feb-15 08:00 PM 22-Feb-15 04:00 AM

1563 OM106330 Load new Media 8h 21-Feb-15 08:00 PM 22-Feb-15 04:00 AM

1564 OM106335 Final Inspection 4h 22-Feb-15 12:00 AM 22-Feb-15 04:00 AM

1565 OM106340 Manway Box-up 4h 22-Feb-15 12:00 AM 22-Feb-15 04:00 AM

1566 OM106345 De-Blinding 8h 21-Feb-15 08:00 PM 22-Feb-15 04:00 AM

1567 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1568 OM106350 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1569 OM106355 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1570 OM106360 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1571 R15U-022-004 RC2-31-022-84-ST-1203-POLISHED WATER DRAIN VALVER15U-022-004 RC2-31-022-84-ST-1203-POLISHED WATER DRAIN VALVE 1144h 01-Jan-15 12:00 AM 17-Feb-15 04:00 PM

1572 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 12:00 AM 01-Jan-15 09:00 AM

1573 OM102825 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1574 OM102830 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1575 OM102835 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1576 OM102840 Removal of insulation 1h 01-Jan-15 08:00 AM 01-Jan-15 09:00 AM

1577 SHUTDOWNSHUTDOWN 16h 17-Feb-15 12:00 AM 17-Feb-15 04:00 PM

1578 OM102845 Verify LT&T and Obtain permit 4h 17-Feb-15 12:00 AM 17-Feb-15 04:00 AM

1579 OM102850 Blinding as per blindlist (Refer R15U-011-002 & R15U-024-010) 0h 17-Feb-15 04:00 AM 17-Feb-15 04:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 29 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 30: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1580 OM102855 Cutting & Fitup with new valve 2h 17-Feb-15 04:00 AM 17-Feb-15 06:00 AM

1581 OM102860 Carryout welding 3h 17-Feb-15 06:00 AM 17-Feb-15 09:00 AM

1582 OM102865 NDT on weld joints 1h 17-Feb-15 09:00 AM 17-Feb-15 10:00 AM

1583 OM102870 Carry out repair on weld, if any 1h 17-Feb-15 10:00 AM 17-Feb-15 11:00 AM

1584 OM102875 Hydrotesting weld joints 4h 17-Feb-15 11:00 AM 17-Feb-15 03:00 PM

1585 OM102880 Painting on weld joints 1h 17-Feb-15 03:00 PM 17-Feb-15 04:00 PM

1586 OM102885 De-blinding (Refer R15U-011-002 & R15U-024-010) 0h 17-Feb-15 04:00 PM 17-Feb-15 04:00 PM

1587 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1588 OM102890 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1589 OM102895 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1590 OM102900 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1591 OM102905 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1592 R15U-022-005 RC2-31-022-84-ST-1203-PROVISION FOR BLIND INSTALLR15U-022-005 RC2-31-022-84-ST-1203-PROVISION FOR BLIND INSTALL 1245h 01-Jan-15 12:00 AM 21-Feb-15 09:00 PM

1593 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1594 OM102910 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1595 OM102915 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1596 OM102920 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1597 OM102925 Removal of insulation 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM

1598 SHUTDOWNSHUTDOWN 77h 18-Feb-15 04:00 PM 21-Feb-15 09:00 PM

1599 OM102930 Verify LT&T and Obtain permit 2h 18-Feb-15 04:00 PM 18-Feb-15 06:00 PM

1600 OM102935 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 18-Feb-15 06:00 PM 18-Feb-15 06:00 PM

1601 OM102940 Cut, remove & Fitup the flanges 12h 18-Feb-15 06:00 PM 19-Feb-15 06:00 AM

1602 OM102945 Carryout welding 20h 19-Feb-15 06:00 AM 20-Feb-15 02:00 AM

1603 OM102950 NDT on weld joints 16h 20-Feb-15 02:00 AM 20-Feb-15 06:00 PM

1604 OM102955 Carry out repair on weld, if any 6h 20-Feb-15 06:00 PM 21-Feb-15 12:00 AM

1605 OM102960 Hydrotesting weld joints 12h 21-Feb-15 12:00 AM 21-Feb-15 12:00 PM

1606 OM102965 Provide paddle & tight flanges 3h 21-Feb-15 12:00 PM 21-Feb-15 03:00 PM

1607 OM102970 Painting on weld joints 2h 21-Feb-15 03:00 PM 21-Feb-15 05:00 PM

1608 OM102975 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 21-Feb-15 05:00 PM 21-Feb-15 05:00 PM

1609 OM102980 Fix back insulation 2h 21-Feb-15 05:00 PM 21-Feb-15 07:00 PM

1610 OM102985 Remove scaffolding 2h 21-Feb-15 07:00 PM 21-Feb-15 09:00 PM

1611 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1612 OM102990 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1613 OM102995 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1614 R15U-022-006 RC2-31-022-95-S-1228-INTERNAL INSPR15U-022-006 RC2-31-022-95-S-1228-INTERNAL INSP 1173h 01-Jan-15 12:00 AM 18-Feb-15 09:00 PM

1615 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1616 OM100100 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1617 SHUTDOWNSHUTDOWN 60h 16-Feb-15 09:00 AM 18-Feb-15 09:00 PM

1618 OM100105 Verify LT&T and Obtain permit 4h 16-Feb-15 09:00 AM 16-Feb-15 01:00 PM

1619 OM100110 Mechanical Isolation & Blinding 8h 16-Feb-15 01:00 PM 16-Feb-15 09:00 PM

1620 OM100115 Clean the Sump with Super Sucker/ Manual 8h 16-Feb-15 09:00 PM 17-Feb-15 05:00 AM

1621 OM100120 Erect Internal Scaffolding 8h 17-Feb-15 05:00 AM 17-Feb-15 01:00 PM

1622 OM100125 Preliminary Inspection 4h 17-Feb-15 01:00 PM 17-Feb-15 05:00 PM

1623 OM100130 Cleaning & Repair 12h 17-Feb-15 05:00 PM 18-Feb-15 05:00 AM

1624 OM100135 Remove Internal Scaffolding 4h 18-Feb-15 05:00 AM 18-Feb-15 09:00 AM

1625 OM100140 Final Inspection 4h 18-Feb-15 09:00 AM 18-Feb-15 01:00 PM

1626 OM100145 De-Blinding 8h 18-Feb-15 01:00 PM 18-Feb-15 09:00 PM

1627 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1628 OM100150 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1629 OM100155 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1630 R15U-022-007 RC2-31-022-95-TK-1263-INTER & EXTERNAL INSPR15U-022-007 RC2-31-022-95-TK-1263-INTER & EXTERNAL INSP 1141h 01-Jan-15 12:00 AM 17-Feb-15 01:00 PM

1631 PRE-SHUTDOWNPRE-SHUTDOWN 12h 01-Jan-15 12:00 AM 01-Jan-15 12:00 PM

1632 OM100160 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1633 OM100165 Erect Scaffolding 6h 01-Jan-15 02:00 AM 01-Jan-15 08:00 AM

1634 OM100170 Remove Insulation 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 30 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 31: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1635 SHUTDOWNSHUTDOWN 55h 15-Feb-15 06:00 AM 17-Feb-15 01:00 PM

1636 OM100175 Verify LT&T and Obtain permit 4h 15-Feb-15 06:00 AM 15-Feb-15 10:00 AM

1637 OM100180 Mechanical Isolation & Blinding 6h 15-Feb-15 10:00 AM 15-Feb-15 04:00 PM

1638 OM100185 Manway Opening & Providing a Ventilation & Lighting 6h 15-Feb-15 04:00 PM 15-Feb-15 10:00 PM

1639 OM100190 Obtain Confined space permit & Erect Internal Scaffolding 6h 15-Feb-15 10:00 PM 16-Feb-15 04:00 AM

1640 OM100195 Preliminary Inspection 3h 16-Feb-15 04:00 AM 16-Feb-15 07:00 AM

1641 OM100200 Cleaning & Repair 12h 16-Feb-15 07:00 AM 16-Feb-15 07:00 PM

1642 OM100205 Remove Internal Scaffolding 4h 16-Feb-15 07:00 PM 16-Feb-15 11:00 PM

1643 OM100210 Final Inspection 3h 16-Feb-15 11:00 PM 17-Feb-15 02:00 AM

1644 OM100215 Manway Box-up 3h 17-Feb-15 02:00 AM 17-Feb-15 05:00 AM

1645 OM100220 De-Blinding 8h 17-Feb-15 05:00 AM 17-Feb-15 01:00 PM

1646 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1647 OM100225 Reinstall insulations 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1648 OM100230 Remove Scaffolding 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1649 OM100235 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1650 OM100240 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1651 R15U-022-008 RC2-31-022-95-TK-1264-INTER & EXTERNAL INSPR15U-022-008 RC2-31-022-95-TK-1264-INTER & EXTERNAL INSP 1189h 01-Jan-15 12:00 AM 19-Feb-15 01:00 PM

1652 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1653 OM100245 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1654 OM100250 Erect Scaffolding 6h 01-Jan-15 02:00 AM 01-Jan-15 08:00 AM

1655 SHUTDOWNSHUTDOWN 55h 17-Feb-15 06:00 AM 19-Feb-15 01:00 PM

1656 OM100255 Verify LT&T and Obtain permit 4h 17-Feb-15 06:00 AM 17-Feb-15 10:00 AM

1657 OM100260 Mechanical Isolation & Blinding 6h 17-Feb-15 10:00 AM 17-Feb-15 04:00 PM

1658 OM100265 Manway Opening & Providing a Ventilation & Lighting 6h 17-Feb-15 04:00 PM 17-Feb-15 10:00 PM

1659 OM100270 Obtain Confined space permit & Erect Internal Scaffolding 6h 17-Feb-15 10:00 PM 18-Feb-15 04:00 AM

1660 OM100275 Preliminary Inspection 3h 18-Feb-15 04:00 AM 18-Feb-15 07:00 AM

1661 OM100280 Cleaning & Repair 12h 18-Feb-15 07:00 AM 18-Feb-15 07:00 PM

1662 OM100285 Remove Internal Scaffolding 4h 18-Feb-15 07:00 PM 18-Feb-15 11:00 PM

1663 OM100290 Final Inspection 3h 18-Feb-15 11:00 PM 19-Feb-15 02:00 AM

1664 OM100295 Manway Box-up 3h 19-Feb-15 02:00 AM 19-Feb-15 05:00 AM

1665 OM100300 De-Blinding 8h 19-Feb-15 05:00 AM 19-Feb-15 01:00 PM

1666 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1667 OM100305 Remove Scaffolding 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1668 OM100310 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1669 OM100315 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1670 R15U-024-001 RC2-31-024-43-P-0090-PV BYPASS VALVE REPLACEMENTR15U-024-001 RC2-31-024-43-P-0090-PV BYPASS VALVE REPLACEMENT 1161h 01-Jan-15 12:00 AM 18-Feb-15 09:00 AM

1671 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 12:00 AM 01-Jan-15 07:00 AM

1672 OM103000 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1673 OM103005 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1674 OM103010 Erect scaffolding 2h 01-Jan-15 04:00 AM 01-Jan-15 06:00 AM

1675 OM103015 Removal of insulation 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1676 SHUTDOWNSHUTDOWN 15h 17-Feb-15 06:00 PM 18-Feb-15 09:00 AM

1677 OM103020 Verify LT&T and Obtain permit 3h 17-Feb-15 06:00 PM 17-Feb-15 09:00 PM

1678 OM103025 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4 & R15U-024-010) 0h 17-Feb-15 09:00 PM 17-Feb-15 09:00 PM

1679 OM103030 Cutting & Fitup with new valve 2h 17-Feb-15 09:00 PM 17-Feb-15 11:00 PM

1680 OM103035 Carryout welding 3h 17-Feb-15 11:00 PM 18-Feb-15 02:00 AM

1681 OM103040 NDT on weld joints 1h 18-Feb-15 02:00 AM 18-Feb-15 03:00 AM

1682 OM103045 Carry out repair on weld, if any 1h 18-Feb-15 03:00 AM 18-Feb-15 04:00 AM

1683 OM103050 Hydrotesting weld joints 4h 18-Feb-15 04:00 AM 18-Feb-15 08:00 AM

1684 OM103055 Painting on weld joints 1h 18-Feb-15 08:00 AM 18-Feb-15 09:00 AM

1685 OM103060 De-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4 & R15U-024-010) 0h 18-Feb-15 09:00 AM 18-Feb-15 09:00 AM

1686 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1687 OM103065 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1688 OM103070 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1689 OM103075 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 31 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 32: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1690 OM103080 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1691 R15U-024-006 RC2-31-024-84-ST-1202-PROVISION FOR BLIND INSTALR15U-024-006 RC2-31-024-84-ST-1202-PROVISION FOR BLIND INSTAL 1135h 01-Jan-15 12:00 AM 17-Feb-15 07:00 AM

1692 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1693 OM103085 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1694 OM103090 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1695 OM103095 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1696 OM103100 Removal of insulation 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM

1697 SHUTDOWNSHUTDOWN 85h 13-Feb-15 06:00 PM 17-Feb-15 07:00 AM

1698 OM103105 Verify LT&T and Obtain permit 2h 13-Feb-15 06:00 PM 13-Feb-15 08:00 PM

1699 OM103110 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 13-Feb-15 08:00 PM 13-Feb-15 08:00 PM

1700 OM103115 Cut, remove & Fitup the flanges 16h 13-Feb-15 08:00 PM 14-Feb-15 12:00 PM

1701 OM103120 Carryout welding 24h 14-Feb-15 12:00 PM 15-Feb-15 12:00 PM

1702 OM103125 NDT on weld joints 16h 15-Feb-15 12:00 PM 16-Feb-15 04:00 AM

1703 OM103130 Carry out repair on weld, if any 6h 16-Feb-15 04:00 AM 16-Feb-15 10:00 AM

1704 OM103135 Hydrotesting weld joints 12h 16-Feb-15 10:00 AM 16-Feb-15 10:00 PM

1705 OM103140 Provide paddle & tight flanges 3h 16-Feb-15 10:00 PM 17-Feb-15 01:00 AM

1706 OM103145 Painting on weld joints 2h 17-Feb-15 01:00 AM 17-Feb-15 03:00 AM

1707 OM103150 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 17-Feb-15 03:00 AM 17-Feb-15 03:00 AM

1708 OM103155 Fix back insulation 2h 17-Feb-15 03:00 AM 17-Feb-15 05:00 AM

1709 OM103160 Remove scaffolding 2h 17-Feb-15 05:00 AM 17-Feb-15 07:00 AM

1710 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1711 OM103165 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1712 OM103170 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1713 R15U-024-007 RC2-31-024-84-ST-1202-ST.TRAP DRAIN VALVE REPLACER15U-024-007 RC2-31-024-84-ST-1202-ST.TRAP DRAIN VALVE REPLACE 1161h 01-Jan-15 12:00 AM 18-Feb-15 09:00 AM

1714 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 12:00 AM 01-Jan-15 09:00 AM

1715 OM103175 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1716 OM103180 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1717 OM103185 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1718 OM103190 Removal of insulation 1h 01-Jan-15 08:00 AM 01-Jan-15 09:00 AM

1719 SHUTDOWNSHUTDOWN 14h 17-Feb-15 07:00 PM 18-Feb-15 09:00 AM

1720 OM103195 Verify LT&T and Obtain permit 2h 17-Feb-15 07:00 PM 17-Feb-15 09:00 PM

1721 OM103200 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 17-Feb-15 09:00 PM 17-Feb-15 09:00 PM

1722 OM103205 Cutting & Fitup with new valve 2h 17-Feb-15 09:00 PM 17-Feb-15 11:00 PM

1723 OM103210 Carryout welding 3h 17-Feb-15 11:00 PM 18-Feb-15 02:00 AM

1724 OM103215 NDT on weld joints 1h 18-Feb-15 02:00 AM 18-Feb-15 03:00 AM

1725 OM103220 Carry out repair on weld, if any 1h 18-Feb-15 03:00 AM 18-Feb-15 04:00 AM

1726 OM103225 Hydrotesting weld joints 4h 18-Feb-15 04:00 AM 18-Feb-15 08:00 AM

1727 OM103230 Painting on weld joints 1h 18-Feb-15 08:00 AM 18-Feb-15 09:00 AM

1728 OM103235 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 18-Feb-15 09:00 AM 18-Feb-15 09:00 AM

1729 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1730 OM103240 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1731 OM103245 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1732 OM103250 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1733 OM103255 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1734 R15U-024-008 RC2-31-024-84-ST-1224-HP DRAIN VALVE REPLACEMENTR15U-024-008 RC2-31-024-84-ST-1224-HP DRAIN VALVE REPLACEMENT 1175h 01-Jan-15 12:00 AM 18-Feb-15 11:00 PM

1735 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 12:00 AM 01-Jan-15 09:00 AM

1736 OM103260 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1737 OM103265 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1738 OM103270 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1739 OM103275 Removal of insulation 1h 01-Jan-15 08:00 AM 01-Jan-15 09:00 AM

1740 SHUTDOWNSHUTDOWN 14h 18-Feb-15 09:00 AM 18-Feb-15 11:00 PM

1741 OM103280 Verify LT&T and Obtain permit 2h 18-Feb-15 09:00 AM 18-Feb-15 11:00 AM

1742 OM103285 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 18-Feb-15 11:00 AM 18-Feb-15 11:00 AM

1743 OM103290 Cutting & Fitup with new valve 2h 18-Feb-15 11:00 AM 18-Feb-15 01:00 PM

1744 OM103295 Carryout welding 3h 18-Feb-15 01:00 PM 18-Feb-15 04:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 32 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 33: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1745 OM103300 NDT on weld joints 1h 18-Feb-15 04:00 PM 18-Feb-15 05:00 PM

1746 OM103305 Carry out repair on weld, if any 1h 18-Feb-15 05:00 PM 18-Feb-15 06:00 PM

1747 OM103310 Hydrotesting weld joints 4h 18-Feb-15 06:00 PM 18-Feb-15 10:00 PM

1748 OM103315 Painting on weld joints 1h 18-Feb-15 10:00 PM 18-Feb-15 11:00 PM

1749 OM103320 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 18-Feb-15 11:00 PM 18-Feb-15 11:00 PM

1750 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1751 OM103325 Fix back insulation 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1752 OM103330 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1753 OM103335 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1754 OM103340 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1755 R15U-024-009 RC2-31-024-84-ST-1224-PROVISION FOR BLIND INSTALR15U-024-009 RC2-31-024-84-ST-1224-PROVISION FOR BLIND INSTAL 1171h 01-Jan-15 12:00 AM 18-Feb-15 07:00 PM

1756 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

1757 OM103345 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1758 OM103350 Obtain permit for scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1759 OM103355 Erect scaffolding 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1760 OM103360 Removal of insulation 2h 01-Jan-15 08:00 AM 01-Jan-15 10:00 AM

1761 SHUTDOWNSHUTDOWN 85h 15-Feb-15 06:00 AM 18-Feb-15 07:00 PM

1762 OM103365 Verify LT&T and Obtain permit 2h 15-Feb-15 06:00 AM 15-Feb-15 08:00 AM

1763 OM103370 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 15-Feb-15 08:00 AM 15-Feb-15 08:00 AM

1764 OM103375 Cut, remove & Fitup the flanges 16h 15-Feb-15 08:00 AM 16-Feb-15 12:00 AM

1765 OM103380 Carryout welding 24h 16-Feb-15 12:00 AM 17-Feb-15 12:00 AM

1766 OM103385 NDT on weld joints 16h 17-Feb-15 12:00 AM 17-Feb-15 04:00 PM

1767 OM103390 Carry out repair on weld, if any 6h 17-Feb-15 04:00 PM 17-Feb-15 10:00 PM

1768 OM103395 Hydrotesting weld joints 12h 17-Feb-15 10:00 PM 18-Feb-15 10:00 AM

1769 OM103400 Provide spectacle blind & tight flanges 3h 18-Feb-15 10:00 AM 18-Feb-15 01:00 PM

1770 OM103405 Painting on weld joints 2h 18-Feb-15 01:00 PM 18-Feb-15 03:00 PM

1771 OM103410 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 18-Feb-15 03:00 PM 18-Feb-15 03:00 PM

1772 OM103415 Fix back insulation 2h 18-Feb-15 03:00 PM 18-Feb-15 05:00 PM

1773 OM103420 Remove scaffolding 2h 18-Feb-15 05:00 PM 18-Feb-15 07:00 PM

1774 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1775 OM103425 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1776 OM103430 Q.C documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1777 R15U-024-010 RC2-31-024-95-D-1223-INTER, EXTERNAL & CUI INSPR15U-024-010 RC2-31-024-95-D-1223-INTER, EXTERNAL & CUI INSP 1126h 01-Jan-15 12:00 AM 16-Feb-15 10:00 PM

1778 PRE-SHUTDOWNPRE-SHUTDOWN 26h 01-Jan-15 12:00 AM 02-Jan-15 02:00 AM

1779 OM100320 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1780 OM100325 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

1781 OM100330 Remove Insulation 8h 01-Jan-15 10:00 AM 01-Jan-15 06:00 PM

1782 OM100335 CUI-Scaffolding & remove insulation 8h 01-Jan-15 06:00 PM 02-Jan-15 02:00 AM

1783 SHUTDOWNSHUTDOWN 112h 12-Feb-15 06:00 AM 16-Feb-15 10:00 PM

1784 OM100340 Verify LT&T and Obtain permit 6h 12-Feb-15 06:00 AM 12-Feb-15 12:00 PM

1785 OM100345 Mechanical Isolation & Blinding 16h 12-Feb-15 12:00 PM 13-Feb-15 04:00 AM

1786 OM100350 Manway Opening & Providing a Ventilation & Lighting 8h 13-Feb-15 04:00 AM 13-Feb-15 12:00 PM

1787 OM100355 CUI Inspection & Repair 12h 13-Feb-15 12:00 PM 14-Feb-15 12:00 AM

1788 OM100360 Obtain Confined space permit & Erect Internal Scaffolding 8h 14-Feb-15 12:00 AM 14-Feb-15 08:00 AM

1789 OM100365 Preliminary Inspection 6h 14-Feb-15 08:00 AM 14-Feb-15 02:00 PM

1790 OM100370 Cleaning & Repair 24h 14-Feb-15 02:00 PM 15-Feb-15 02:00 PM

1791 OM100375 Remove Internal Scaffolding 4h 15-Feb-15 02:00 PM 15-Feb-15 06:00 PM

1792 OM100380 Final Inspection 6h 15-Feb-15 06:00 PM 16-Feb-15 12:00 AM

1793 OM100385 Manway Box-up 6h 16-Feb-15 12:00 AM 16-Feb-15 06:00 AM

1794 OM100390 De-Blinding 16h 16-Feb-15 06:00 AM 16-Feb-15 10:00 PM

1795 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1796 OM100395 Reinstall insulations 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1797 OM100400 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1798 OM100405 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1799 OM100410 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 33 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 34: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1800 R15U-024-013 RC2-31-024-41-E-1201-EXCH-INTER & EXTERNAL INSPR15U-024-013 RC2-31-024-41-E-1201-EXCH-INTER & EXTERNAL INSP 1186h 01-Jan-15 12:00 AM 19-Feb-15 10:00 AM

1801 PRE-SHUTDOWNPRE-SHUTDOWN 11h 01-Jan-15 12:00 AM 01-Jan-15 11:00 AM

1802 OM105680 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1803 OM105685 Shift blinds to location 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1804 OM105690 Erect Scaffolding & load bearings. 4h 01-Jan-15 04:00 AM 01-Jan-15 08:00 AM

1805 OM105695 Removal of Insulation 3h 01-Jan-15 08:00 AM 01-Jan-15 11:00 AM

1806 SHUTDOWNSHUTDOWN 100h 15-Feb-15 06:00 AM 19-Feb-15 10:00 AM

1807 OM105700 Purging to be carried out 6h 15-Feb-15 06:00 AM 15-Feb-15 12:00 PM

1808 OM105705 Verify LT&T and Obtain PTW 2h 15-Feb-15 12:00 PM 15-Feb-15 02:00 PM

1809 OM105710 Drop spools & carryout blinding. 4h 15-Feb-15 02:00 PM 15-Feb-15 06:00 PM

1810 OM105715 Open stub end & return bend housing flanges 3h 15-Feb-15 06:00 PM 15-Feb-15 09:00 PM

1811 OM105720 Carryout prelim. inspn & Offer for AFI 2h 15-Feb-15 09:00 PM 15-Feb-15 11:00 PM

1812 OM105725 Pull out tube bundle & perform AFI 6h 15-Feb-15 11:00 PM 16-Feb-15 05:00 AM

1813 OM105730 Shift tube bundle to jetting area 2h 16-Feb-15 05:00 AM 16-Feb-15 07:00 AM

1814 OM105735 100% Hydrojetting of tube external & internal 8h 16-Feb-15 07:00 AM 16-Feb-15 03:00 PM

1815 OM105740 Hydrojetting of shell, channel cover & flange 3h 16-Feb-15 03:00 PM 16-Feb-15 06:00 PM

1816 OM105745 Inspn. of tube bundle, channel head & shell 3h 16-Feb-15 06:00 PM 16-Feb-15 09:00 PM

1817 OM105750 Carryout RFECT inspection on 48 tubes. 10h 16-Feb-15 09:00 PM 17-Feb-15 07:00 AM

1818 OM105755 NDT as per ERG recommendation 3h 17-Feb-15 07:00 AM 17-Feb-15 10:00 AM

1819 OM105760 Visual inspection & Thickness monitoring 3h 17-Feb-15 10:00 AM 17-Feb-15 01:00 PM

1820 OM105765 Shift back tube bundle to the locaton 2h 17-Feb-15 01:00 PM 17-Feb-15 03:00 PM

1821 OM105770 Reinstallation of tube bundle 5h 17-Feb-15 03:00 PM 17-Feb-15 08:00 PM

1822 OM105775 Hydrotest both shell side & tube side 5h 17-Feb-15 08:00 PM 18-Feb-15 01:00 AM

1823 OM105780 Inspection report and repairs, if any 20h 18-Feb-15 01:00 AM 18-Feb-15 09:00 PM

1824 OM105785 Final inspection 2h 18-Feb-15 09:00 PM 18-Feb-15 11:00 PM

1825 OM105790 Boxup the exchanger tighten the bolts. 5h 18-Feb-15 11:00 PM 19-Feb-15 04:00 AM

1826 OM105795 De-Blinding & Reinstall spools 6h 19-Feb-15 04:00 AM 19-Feb-15 10:00 AM

1827 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1828 OM105800 Reinstall insulations 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1829 OM105805 Removal of Scaffolds 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

1830 OM105810 Housekeeping and close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1831 R15U-024-016 RC2-31-024-AI-0034 -INST-SAMPLE PROBE REPLACEMENTR15U-024-016 RC2-31-024-AI-0034 -INST-SAMPLE PROBE REPLACEMENT 1027h 01-Jan-15 12:00 AM 12-Feb-15 07:00 PM

1832 PRE-SHUTDOWNPRE-SHUTDOWN 14h 01-Jan-15 12:00 AM 01-Jan-15 02:00 PM

1833 OI101800 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1834 OI101805 Erect Scaffolding 12h 01-Jan-15 01:00 AM 01-Jan-15 01:00 PM

1835 OI101810 Shift Probe from groung floor to top 1h 01-Jan-15 01:00 PM 01-Jan-15 02:00 PM

1836 SHUTDOWNSHUTDOWN 10h 12-Feb-15 09:00 AM 12-Feb-15 07:00 PM

1837 OI101815 Verify LT&T and Obtain permit 2h 12-Feb-15 09:00 AM 12-Feb-15 11:00 AM

1838 OI101820 Disconnect the Tubings / Lines 1h 12-Feb-15 11:00 AM 12-Feb-15 12:00 PM

1839 OI101825 Retraction the probe from Process line 1h 12-Feb-15 12:00 PM 12-Feb-15 01:00 PM

1840 OI101830 Close the Process Main valve 1h 12-Feb-15 01:00 PM 12-Feb-15 02:00 PM

1841 OI101835 Remove the existing Probe 1h 12-Feb-15 02:00 PM 12-Feb-15 03:00 PM

1842 OI101840 Fix back New Sample Probe 2h 12-Feb-15 03:00 PM 12-Feb-15 05:00 PM

1843 OI101845 Connect the Tubings / Lines 1h 12-Feb-15 05:00 PM 12-Feb-15 06:00 PM

1844 OI101850 Inspection by RLOC 1h 12-Feb-15 06:00 PM 12-Feb-15 07:00 PM

1845 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1846 OI101855 Remove Scaffolding 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

1847 OI101860 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1848 R15U-024-017 RC2-31-024-LV-0001-CV-OVERHAUL & SERVICINGR15U-024-017 RC2-31-024-LV-0001-CV-OVERHAUL & SERVICING 29h 14-Feb-15 06:00 AM 15-Feb-15 11:00 AM

1849 SHUTDOWNSHUTDOWN 29h 14-Feb-15 06:00 AM 15-Feb-15 11:00 AM

1850 OI100320 Review JSA 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

1851 OI100325 Verify LT&T and Obtain permit 1h 14-Feb-15 07:00 AM 14-Feb-15 08:00 AM

1852 OI100330 Disconnect Signals / Connections for CV 1h 14-Feb-15 08:00 AM 14-Feb-15 09:00 AM

1853 OI100335 Removal of CV & Install Blinds 4h 14-Feb-15 09:00 AM 14-Feb-15 01:00 PM

1854 OI100340 Transport CV to Work Shop 1h 14-Feb-15 01:00 PM 14-Feb-15 02:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 34 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 35: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1855 OI100345 Overhaul / Service CV 8h 14-Feb-15 02:00 PM 14-Feb-15 10:00 PM

1856 OI100350 Test Valve (Refer Documentation) 2h 14-Feb-15 10:00 PM 15-Feb-15 12:00 AM

1857 OI100355 Transport CV to Unit / Remove Blinds 1h 15-Feb-15 12:00 AM 15-Feb-15 01:00 AM

1858 OI100360 Install CV 6h 15-Feb-15 01:00 AM 15-Feb-15 07:00 AM

1859 OI100365 Loop Check & Stroke test 2h 15-Feb-15 07:00 AM 15-Feb-15 09:00 AM

1860 OI100370 Inspection by RLOC 1h 15-Feb-15 09:00 AM 15-Feb-15 10:00 AM

1861 OI100375 House keeping & Close PTW 1h 15-Feb-15 10:00 AM 15-Feb-15 11:00 AM

1862 R15U-024-023 RC2-31-024-PV-0110-CV-OVERHAUL & SERVICINGR15U-024-023 RC2-31-024-PV-0110-CV-OVERHAUL & SERVICING 1111h 01-Jan-15 12:00 AM 16-Feb-15 07:00 AM

1863 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1864 OI100380 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1865 OI100385 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

1866 SHUTDOWNSHUTDOWN 25h 15-Feb-15 06:00 AM 16-Feb-15 07:00 AM

1867 OI100390 Verify LT&T and Obtain permit 1h 15-Feb-15 06:00 AM 15-Feb-15 07:00 AM

1868 OI100395 Disconnect Signals / Connections for CV 1h 15-Feb-15 07:00 AM 15-Feb-15 08:00 AM

1869 OI100400 Removal of CV & Install Blinds 3h 15-Feb-15 08:00 AM 15-Feb-15 11:00 AM

1870 OI100405 Transport CV to Work Shop 1h 15-Feb-15 11:00 AM 15-Feb-15 12:00 PM

1871 OI100410 Overhaul / Service CV 8h 15-Feb-15 12:00 PM 15-Feb-15 08:00 PM

1872 OI100415 Test Valve (Refer Documentation) 2h 15-Feb-15 08:00 PM 15-Feb-15 10:00 PM

1873 OI100420 Transport CV to Unit / Remove Blinds 1h 15-Feb-15 10:00 PM 15-Feb-15 11:00 PM

1874 OI100425 Install CV 5h 15-Feb-15 11:00 PM 16-Feb-15 04:00 AM

1875 OI100430 Loop Check & Stroke test 2h 16-Feb-15 04:00 AM 16-Feb-15 06:00 AM

1876 OI100435 Inspection by RLOC 1h 16-Feb-15 06:00 AM 16-Feb-15 07:00 AM

1877 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1878 OI100440 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1879 OI100445 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1880 R15U-025-012 RC2-31-025-84-ST-1205-PROVISION FOR BLIND INSTALR15U-025-012 RC2-31-025-84-ST-1205-PROVISION FOR BLIND INSTAL 1209h 01-Jan-15 12:00 AM 20-Feb-15 09:00 AM

1881 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 12:00 AM 01-Jan-15 07:00 AM

1882 OM103765 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1883 OM103770 Erect Scaffolding 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

1884 OM103775 Removal of Insulations. 2h 01-Jan-15 05:00 AM 01-Jan-15 07:00 AM

1885 SHUTDOWNSHUTDOWN 74h 17-Feb-15 07:00 AM 20-Feb-15 09:00 AM

1886 OM103780 Verify LT&T and Obtain permit 2h 17-Feb-15 07:00 AM 17-Feb-15 09:00 AM

1887 OM103785 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 17-Feb-15 09:00 AM 17-Feb-15 09:00 AM

1888 OM103790 Cut & remove the pipeline as per dwg. 10h 17-Feb-15 09:00 AM 17-Feb-15 07:00 PM

1889 OM103795 Fit up with flanges on the pipeline 12h 17-Feb-15 07:00 PM 18-Feb-15 07:00 AM

1890 OM103800 Carryout welding 12h 18-Feb-15 07:00 AM 18-Feb-15 07:00 PM

1891 OM103805 NDT on weld joints (As per RAT sheet) 12h 18-Feb-15 07:00 PM 19-Feb-15 07:00 AM

1892 OM103810 Hydrotesting on weld joints 12h 19-Feb-15 07:00 AM 19-Feb-15 07:00 PM

1893 OM103815 Carryout repair on weld joints, if any 4h 19-Feb-15 07:00 PM 19-Feb-15 11:00 PM

1894 OM103820 Provide the spect. Blind 8h 19-Feb-15 11:00 PM 20-Feb-15 07:00 AM

1895 OM103825 Painting on weld joints 2h 20-Feb-15 07:00 AM 20-Feb-15 09:00 AM

1896 OM103830 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 20-Feb-15 09:00 AM 20-Feb-15 09:00 AM

1897 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1898 OM103835 Fix back the insulation 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1899 OM103840 Remove scaffolding 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1900 OM103845 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1901 OM103850 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1902 R15U-037-002 RC2-31-037-84-ST-1201-PROVISION FOR BLIND INSTALR15U-037-002 RC2-31-037-84-ST-1201-PROVISION FOR BLIND INSTAL 1088h 01-Jan-15 12:00 AM 15-Feb-15 08:00 AM

1903 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 12:00 AM 01-Jan-15 07:00 AM

1904 OM104000 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1905 OM104005 Erect Scaffolding 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

1906 OM104010 Removal of Insulations. 2h 01-Jan-15 05:00 AM 01-Jan-15 07:00 AM

1907 SHUTDOWNSHUTDOWN 74h 12-Feb-15 06:00 AM 15-Feb-15 08:00 AM

1908 OM104015 Verify LT&T and Obtain permit 2h 12-Feb-15 06:00 AM 12-Feb-15 08:00 AM

1909 OM104020 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 12-Feb-15 08:00 AM 12-Feb-15 08:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 35 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 36: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1910 OM104025 Cut & remove the pipeline as per dwg. 10h 12-Feb-15 08:00 AM 12-Feb-15 06:00 PM

1911 OM104030 Fit up the flanges in position 12h 12-Feb-15 06:00 PM 13-Feb-15 06:00 AM

1912 OM104035 Carryout welding 12h 13-Feb-15 06:00 AM 13-Feb-15 06:00 PM

1913 OM104040 NDT on weld joints 12h 13-Feb-15 06:00 PM 14-Feb-15 06:00 AM

1914 OM104045 Hydrotest on weld joints 12h 14-Feb-15 06:00 AM 14-Feb-15 06:00 PM

1915 OM104050 Carryout repair works, if any 4h 14-Feb-15 06:00 PM 14-Feb-15 10:00 PM

1916 OM104055 Provide spect. blind 8h 14-Feb-15 10:00 PM 15-Feb-15 06:00 AM

1917 OM104060 Painting on weld joints 2h 15-Feb-15 06:00 AM 15-Feb-15 08:00 AM

1918 OM104065 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 15-Feb-15 08:00 AM 15-Feb-15 08:00 AM

1919 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1920 OM104070 Fix back the insulation 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1921 OM104075 Remove scaffolding 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

1922 OM104080 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1923 OM104085 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1924 R15U-037-008 RC2-31-037-84-ST-1201-TRAP BYPASS VALVE REPLACEMENTR15U-037-008 RC2-31-037-84-ST-1201-TRAP BYPASS VALVE REPLACEMENT 1225h 01-Jan-15 12:00 AM 21-Feb-15 01:00 AM

1925 PRE-SHUTDOWNPRE-SHUTDOWN 5h 01-Jan-15 12:00 AM 01-Jan-15 05:00 AM

1926 OM104090 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1927 OM104095 Erect Scaffolding 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1928 OM104100 Removal of Insulations. 1h 01-Jan-15 04:00 AM 01-Jan-15 05:00 AM

1929 SHUTDOWNSHUTDOWN 16h 20-Feb-15 09:00 AM 21-Feb-15 01:00 AM

1930 OM104105 Verify LT&T and Obtain permit 2h 20-Feb-15 09:00 AM 20-Feb-15 11:00 AM

1931 OM104110 Blinding as per blindlist. 0h 20-Feb-15 11:00 AM 20-Feb-15 11:00 AM

1932 OM104115 Cut, remove damaged valve & Fitup new valve 3h 20-Feb-15 11:00 AM 20-Feb-15 02:00 PM

1933 OM104120 Carryout welding 3h 20-Feb-15 02:00 PM 20-Feb-15 05:00 PM

1934 OM104125 NDT on field joints ( As per RAT sheet) 2h 20-Feb-15 05:00 PM 20-Feb-15 07:00 PM

1935 OM104130 Hydrotesting on weld joints 4h 20-Feb-15 07:00 PM 20-Feb-15 11:00 PM

1936 OM104135 Carry out repair on weld if any 1h 20-Feb-15 11:00 PM 21-Feb-15 12:00 AM

1937 OM104140 Painting on weld joints 1h 21-Feb-15 12:00 AM 21-Feb-15 01:00 AM

1938 OM104145 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 21-Feb-15 01:00 AM 21-Feb-15 01:00 AM

1939 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1940 OM104150 Fix back the insulation 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1941 OM104155 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1942 OM104160 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1943 OM104165 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1944 R15U-046-003 RC2-31-046-41-E-1207B-KOD BYPASS VALVE REPLACEMENTR15U-046-003 RC2-31-046-41-E-1207B-KOD BYPASS VALVE REPLACEMENT 1236h 01-Jan-15 12:00 AM 21-Feb-15 12:00 PM

1945 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

1946 OM106100 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1947 OM106105 Erect Firebox. 2h 01-Jan-15 02:00 AM 01-Jan-15 04:00 AM

1948 OM106110 Removal of Insulation 2h 01-Jan-15 04:00 AM 01-Jan-15 06:00 AM

1949 SHUTDOWNSHUTDOWN 10h 21-Feb-15 02:00 AM 21-Feb-15 12:00 PM

1950 OM106115 Verify LT&T and Obtain PTW 2h 21-Feb-15 02:00 AM 21-Feb-15 04:00 AM

1951 OM106120 Blinding as per blindlist. 0h 21-Feb-15 04:00 AM 21-Feb-15 04:00 AM

1952 OM106125 Cut & remove the valve. 2h 21-Feb-15 04:00 AM 21-Feb-15 06:00 AM

1953 OM106130 Fit up new valve & carryout welding 2h 21-Feb-15 06:00 AM 21-Feb-15 08:00 AM

1954 OM106135 NDT on weld joints 4h 21-Feb-15 08:00 AM 21-Feb-15 12:00 PM

1955 OM106140 De-Blinding 0h 21-Feb-15 12:00 PM 21-Feb-15 12:00 PM

1956 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1957 OM106145 Reinstall insulations 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1958 OM106150 Remove Firebox 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1959 OM106155 Housekeeping and close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1960 R15U-046-005 RC2-31-046-67-P-1270-FLARE LINE VALVE REPLACEMENTR15U-046-005 RC2-31-046-67-P-1270-FLARE LINE VALVE REPLACEMENT 1230h 01-Jan-15 12:00 AM 21-Feb-15 06:00 AM

1961 PRE-SHUTDOWNPRE-SHUTDOWN 11h 01-Jan-15 12:00 AM 01-Jan-15 11:00 AM

1962 OM104170 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1963 OM104175 Hydrotest new valve & Shift to job area 4h 01-Jan-15 01:00 AM 01-Jan-15 05:00 AM

1964 OM104180 Erect Scaffolding 4h 01-Jan-15 05:00 AM 01-Jan-15 09:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 36 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 37: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

1965 OM104185 Removal of Insulations. 2h 01-Jan-15 09:00 AM 01-Jan-15 11:00 AM

1966 SHUTDOWNSHUTDOWN 46h 19-Feb-15 08:00 AM 21-Feb-15 06:00 AM

1967 OM104190 Verify LT&T and Obtain permit 2h 19-Feb-15 08:00 AM 19-Feb-15 10:00 AM

1968 OM104195 Blinding as per blindlist (Refer OSBL Steam System & ISBL LT&T2,3,4) 0h 19-Feb-15 10:00 AM 19-Feb-15 10:00 AM

1969 OM104200 Unbolt the flanges and drop the valve 3h 19-Feb-15 10:00 AM 19-Feb-15 01:00 PM

1970 OM104205 Shift removed valve to shop for servicing 1h 19-Feb-15 01:00 PM 19-Feb-15 02:00 PM

1971 OM104210 Clean & Check the flange faces 1h 19-Feb-15 02:00 PM 19-Feb-15 03:00 PM

1972 OM104215 Erect Scaffolding, if flange to be renewed 2h 19-Feb-15 03:00 PM 19-Feb-15 05:00 PM

1973 OM104220 Cut & remove damaged flange (As per ERG) 4h 19-Feb-15 05:00 PM 19-Feb-15 09:00 PM

1974 OM104225 Fit up the new flange 4h 19-Feb-15 09:00 PM 20-Feb-15 01:00 AM

1975 OM104230 Carryout welding 6h 20-Feb-15 01:00 AM 20-Feb-15 07:00 AM

1976 OM104235 NDT on weld joints (As per RAT sheet) 6h 20-Feb-15 07:00 AM 20-Feb-15 01:00 PM

1977 OM104240 Hydrotesting on weld joints 8h 20-Feb-15 01:00 PM 20-Feb-15 09:00 PM

1978 OM104245 Carry out repair on weld if any 3h 20-Feb-15 09:00 PM 21-Feb-15 12:00 AM

1979 OM104250 Fix the new valve in position 2h 21-Feb-15 12:00 AM 21-Feb-15 02:00 AM

1980 OM104255 Tight the flange bolts in sequence 3h 21-Feb-15 02:00 AM 21-Feb-15 05:00 AM

1981 OM104260 Painting on weld joints 1h 21-Feb-15 05:00 AM 21-Feb-15 06:00 AM

1982 OM104265 Carryout de-blinding (Refer OSBL Steam System & ISBL LT&T2,3,4also) 0h 21-Feb-15 06:00 AM 21-Feb-15 06:00 AM

1983 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1984 OM104270 Fix back the insulation 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1985 OM104275 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1986 OM104280 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

1987 OM104285 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

1988 COOLING WATER/SEA WATERCOOLING WATER/SEA WATER 1316h 01-Jan-15 12:00 AM 24-Feb-15 08:00 PM

1989 R15U-005-010 RC2-31-005-29-EL-1104-MAINT OF NORMAL LIGHTING PANELR15U-005-010 RC2-31-005-29-EL-1104-MAINT OF NORMAL LIGHTING PANEL 476h 01-Jan-15 06:00 AM 09-Feb-15 02:00 PM

1990 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1991 OE100380 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1992 SHUTDOWNSHUTDOWN 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM

1993 OE100385 Verify LT&T and Obtain permit 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM

1994 OE100390 Do Insp. & Maint. as per Checklist 7h 09-Feb-15 07:00 AM 09-Feb-15 02:00 PM

1995 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1996 OE100395 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1997 R15U-005-011 RC2-31-005-29-EL-1105-MAINT OF EMERGENCY LIGHTINGR15U-005-011 RC2-31-005-29-EL-1105-MAINT OF EMERGENCY LIGHTING 508h 01-Jan-15 06:00 AM 12-Feb-15 10:00 AM

1998 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

1999 OE100400 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2000 SHUTDOWNSHUTDOWN 8h 11-Feb-15 02:00 PM 12-Feb-15 10:00 AM

2001 OE100405 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

2002 OE100410 Do Insp. & Maint. as per Checklist 7h 11-Feb-15 03:00 PM 12-Feb-15 10:00 AM

2003 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2004 OE100415 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2005 R15U-005-012 RC2-31-005-29-EL-1106-MAINT OF POWER WELDING PANELR15U-005-012 RC2-31-005-29-EL-1106-MAINT OF POWER WELDING PANEL 652h 01-Jan-15 06:00 AM 24-Feb-15 10:00 AM

2006 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2007 OE100420 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2008 SHUTDOWNSHUTDOWN 8h 23-Feb-15 02:00 PM 24-Feb-15 10:00 AM

2009 OE100425 Verify LT&T and Obtain permit 1h 23-Feb-15 02:00 PM 23-Feb-15 03:00 PM

2010 OE100430 Do Insp. & Maint. as per Checklist 7h 23-Feb-15 03:00 PM 24-Feb-15 10:00 AM

2011 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2012 OE100435 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2013 R15U-005-013 RC2-31-005-29-EL-1106-MAINT OF MCC POWER WELDINGR15U-005-013 RC2-31-005-29-EL-1106-MAINT OF MCC POWER WELDING 658h 01-Jan-15 06:00 AM 24-Feb-15 04:00 PM

2014 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2015 OE100440 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2016 SHUTDOWNSHUTDOWN 6h 24-Feb-15 10:00 AM 24-Feb-15 04:00 PM

2017 OE100445 Verify LT&T and Obtain permit 1h 24-Feb-15 10:00 AM 24-Feb-15 11:00 AM

2018 OE100450 Do Insp. & Maint. as per Checklist 5h 24-Feb-15 11:00 AM 24-Feb-15 04:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 37 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 38: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2019 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2020 OE100455 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2021 R15U-005-014 RC2-31-005-29-EL-1107-MAINT OF SMALL POWER PANELR15U-005-014 RC2-31-005-29-EL-1107-MAINT OF SMALL POWER PANEL 601h 01-Jan-15 06:00 AM 20-Feb-15 07:00 AM

2022 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2023 OE100460 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2024 SHUTDOWNSHUTDOWN 11h 19-Feb-15 08:00 AM 20-Feb-15 07:00 AM

2025 OE100465 Verify LT&T and Obtain permit 1h 19-Feb-15 08:00 AM 19-Feb-15 09:00 AM

2026 OE100470 Do Insp. & Maint. as per Checklist 10h 19-Feb-15 09:00 AM 20-Feb-15 07:00 AM

2027 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2028 OE100475 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2029 R15U-005-015 RC2-31-005-29-EL-1108-MAINT OF MOV PANELR15U-005-015 RC2-31-005-29-EL-1108-MAINT OF MOV PANEL 610h 01-Jan-15 06:00 AM 20-Feb-15 04:00 PM

2030 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2031 OE100480 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2032 SHUTDOWNSHUTDOWN 8h 20-Feb-15 08:00 AM 20-Feb-15 04:00 PM

2033 OE100485 Verify LT&T and Obtain permit 1h 20-Feb-15 08:00 AM 20-Feb-15 09:00 AM

2034 OE100490 Do Insp. & Maint. as per Checklist 7h 20-Feb-15 09:00 AM 20-Feb-15 04:00 PM

2035 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2036 OE100495 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2037 R15U-005-016 RC2-31-005-29-EL-1108-MAINT OF MOV MODULER15U-005-016 RC2-31-005-29-EL-1108-MAINT OF MOV MODULE 606h 01-Jan-15 06:00 AM 20-Feb-15 12:00 PM

2038 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2039 OE100500 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2040 SHUTDOWNSHUTDOWN 4h 20-Feb-15 08:00 AM 20-Feb-15 12:00 PM

2041 OE100505 Verify LT&T and Obtain permit 1h 20-Feb-15 08:00 AM 20-Feb-15 09:00 AM

2042 OE100510 Do Insp. & Maint. as per Checklist 3h 20-Feb-15 09:00 AM 20-Feb-15 12:00 PM

2043 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2044 OE100515 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2045 R15U-005-028 RC2-31-005-29-EL-1208-MAINT OF LV DISTRIBUTION XFMRR15U-005-028 RC2-31-005-29-EL-1208-MAINT OF LV DISTRIBUTION XFMR 602h 01-Jan-15 06:00 AM 20-Feb-15 08:00 AM

2046 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2047 OE100880 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2048 SHUTDOWNSHUTDOWN 8h 19-Feb-15 12:00 PM 20-Feb-15 08:00 AM

2049 OE100885 Verify LT&T and Obtain permit 1h 19-Feb-15 12:00 PM 19-Feb-15 01:00 PM

2050 OE100890 Do Insp. & Maint. as per Checklist 7h 19-Feb-15 01:00 PM 20-Feb-15 08:00 AM

2051 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2052 OE100895 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2053 R15U-005-029 RC2-31-005-29-EL-1208-MAINT OF LV DISTRIBUTION XFMRR15U-005-029 RC2-31-005-29-EL-1208-MAINT OF LV DISTRIBUTION XFMR 606h 01-Jan-15 06:00 AM 20-Feb-15 12:00 PM

2054 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2055 OE100900 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2056 SHUTDOWNSHUTDOWN 4h 20-Feb-15 08:00 AM 20-Feb-15 12:00 PM

2057 OE100905 Verify LT&T and Obtain permit 1h 20-Feb-15 08:00 AM 20-Feb-15 09:00 AM

2058 OE100910 Do Insp. & Maint. as per Checklist 3h 20-Feb-15 09:00 AM 20-Feb-15 12:00 PM

2059 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2060 OE100915 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2061 R15U-005-030 RC2-31-005-29-EL-1209-MAINT OF LV DISTRIBUTION XFMRR15U-005-030 RC2-31-005-29-EL-1209-MAINT OF LV DISTRIBUTION XFMR 476h 01-Jan-15 06:00 AM 09-Feb-15 02:00 PM

2062 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2063 OE100920 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2064 SHUTDOWNSHUTDOWN 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM

2065 OE100925 Verify LT&T and Obtain permit 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM

2066 OE100930 Do Insp. & Maint. as per Checklist 7h 09-Feb-15 07:00 AM 09-Feb-15 02:00 PM

2067 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2068 OE100935 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2069 R15U-005-031 RC2-31-005-29-EL-1209-MAINT OF LV DISTRIBUTION XFMRR15U-005-031 RC2-31-005-29-EL-1209-MAINT OF LV DISTRIBUTION XFMR 472h 01-Jan-15 06:00 AM 09-Feb-15 10:00 AM

2070 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2071 OE100940 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 38 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 39: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2072 SHUTDOWNSHUTDOWN 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM

2073 OE100945 Verify LT&T and Obtain permit 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM

2074 OE100950 Do Insp. & Maint. as per Checklist 3h 09-Feb-15 07:00 AM 09-Feb-15 10:00 AM

2075 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2076 OE100955 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2077 R15U-005-032 RC2-31-005-29-EL-1210-MAINT OF LV DISTRIBUTION XFMRR15U-005-032 RC2-31-005-29-EL-1210-MAINT OF LV DISTRIBUTION XFMR 508h 01-Jan-15 06:00 AM 12-Feb-15 10:00 AM

2078 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2079 OE100960 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2080 SHUTDOWNSHUTDOWN 8h 11-Feb-15 02:00 PM 12-Feb-15 10:00 AM

2081 OE100965 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

2082 OE100970 Do Insp. & Maint. as per Checklist 7h 11-Feb-15 03:00 PM 12-Feb-15 10:00 AM

2083 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2084 OE100975 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2085 R15U-005-033 RC2-31-005-29-EL-1210-MAINT OF LV DISTRIBUTION XFMRR15U-005-033 RC2-31-005-29-EL-1210-MAINT OF LV DISTRIBUTION XFMR 504h 01-Jan-15 06:00 AM 11-Feb-15 06:00 PM

2086 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2087 OE100980 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2088 SHUTDOWNSHUTDOWN 4h 11-Feb-15 02:00 PM 11-Feb-15 06:00 PM

2089 OE100985 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

2090 OE100990 Do Insp. & Maint. as per Checklist 3h 11-Feb-15 03:00 PM 11-Feb-15 06:00 PM

2091 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2092 OE100995 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2093 R15U-005-034 RC2-31-005-29-EL-1211-MAINT OF PROCESS HEATER XFMRR15U-005-034 RC2-31-005-29-EL-1211-MAINT OF PROCESS HEATER XFMR 484h 01-Jan-15 06:00 AM 10-Feb-15 10:00 AM

2094 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2095 OE101000 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2096 SHUTDOWNSHUTDOWN 8h 09-Feb-15 02:00 PM 10-Feb-15 10:00 AM

2097 OE101005 Verify LT&T and Obtain permit 1h 09-Feb-15 02:00 PM 09-Feb-15 03:00 PM

2098 OE101010 Do Insp. & Maint. as per Checklist 7h 09-Feb-15 03:00 PM 10-Feb-15 10:00 AM

2099 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2100 OE101015 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2101 R15U-005-036 RC2-31-005-29-EL-1220-MAINT OF XFMRR15U-005-036 RC2-31-005-29-EL-1220-MAINT OF XFMR 520h 01-Jan-15 06:00 AM 13-Feb-15 10:00 AM

2102 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2103 OE101040 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2104 SHUTDOWNSHUTDOWN 8h 12-Feb-15 02:00 PM 13-Feb-15 10:00 AM

2105 OE101045 Verify LT&T and Obtain permit 1h 12-Feb-15 02:00 PM 12-Feb-15 03:00 PM

2106 OE101050 Do Insp. & Maint. as per Checklist 7h 12-Feb-15 03:00 PM 13-Feb-15 10:00 AM

2107 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2108 OE101055 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2109 R15U-005-037 RC2-31-005-29-EL-1221-MAINT OF XFMRR15U-005-037 RC2-31-005-29-EL-1221-MAINT OF XFMR 536h 01-Jan-15 06:00 AM 14-Feb-15 02:00 PM

2110 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2111 OE101060 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2112 SHUTDOWNSHUTDOWN 8h 14-Feb-15 06:00 AM 14-Feb-15 02:00 PM

2113 OE101065 Verify LT&T and Obtain permit 1h 14-Feb-15 06:00 AM 14-Feb-15 07:00 AM

2114 OE101070 Do Insp. & Maint. as per Checklist 7h 14-Feb-15 07:00 AM 14-Feb-15 02:00 PM

2115 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2116 OE101075 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2117 R15U-005-050 RC2-31-005-29-EL-1404-MAINT OF DC UPSR15U-005-050 RC2-31-005-29-EL-1404-MAINT OF DC UPS 532h 01-Jan-15 06:00 AM 14-Feb-15 10:00 AM

2118 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2119 OE101080 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2120 SHUTDOWNSHUTDOWN 8h 13-Feb-15 02:00 PM 14-Feb-15 10:00 AM

2121 OE101085 Verify LT&T and Obtain permit 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM

2122 OE101090 Do Insp. & Maint. as per Checklist 7h 13-Feb-15 03:00 PM 14-Feb-15 10:00 AM

2123 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2124 OE101095 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 39 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 40: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2125 R15U-005-053 RC2-31-005-29-EL-1420-MAINT OF GENRAL UPS DISTRIBUTIONR15U-005-053 RC2-31-005-29-EL-1420-MAINT OF GENRAL UPS DISTRIBUTION 530h 01-Jan-15 06:00 AM 14-Feb-15 08:00 AM

2126 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2127 OE101100 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2128 SHUTDOWNSHUTDOWN 6h 13-Feb-15 02:00 PM 14-Feb-15 08:00 AM

2129 OE101105 Verify LT&T and Obtain permit 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM

2130 OE101110 Do Insp. & Maint. as per Checklist 5h 13-Feb-15 03:00 PM 14-Feb-15 08:00 AM

2131 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2132 OE101115 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2133 R15U-005-054 RC2-31-005-29-EL-1422-MAINT OF GENRAL UPS DISTRIBUTIONR15U-005-054 RC2-31-005-29-EL-1422-MAINT OF GENRAL UPS DISTRIBUTION 530h 01-Jan-15 06:00 AM 14-Feb-15 08:00 AM

2134 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2135 OE101120 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2136 SHUTDOWNSHUTDOWN 6h 13-Feb-15 02:00 PM 14-Feb-15 08:00 AM

2137 OE101125 Verify LT&T and Obtain permit 1h 13-Feb-15 02:00 PM 13-Feb-15 03:00 PM

2138 OE101130 Do Insp. & Maint. as per Checklist 5h 13-Feb-15 03:00 PM 14-Feb-15 08:00 AM

2139 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2140 OE101135 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2141 R15U-005-055 RC2-31-005-29-EL-1701-MAINT OF SWITCH GEARR15U-005-055 RC2-31-005-29-EL-1701-MAINT OF SWITCH GEAR 508h 01-Jan-15 06:00 AM 12-Feb-15 10:00 AM

2142 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2143 OE101140 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2144 SHUTDOWNSHUTDOWN 8h 11-Feb-15 02:00 PM 12-Feb-15 10:00 AM

2145 OE101145 Verify LT&T and Obtain permit 1h 11-Feb-15 02:00 PM 11-Feb-15 03:00 PM

2146 OE101150 Do Insp. & Maint. as per Checklist 7h 11-Feb-15 03:00 PM 12-Feb-15 10:00 AM

2147 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2148 OE101155 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2149 R15U-005-062 RC2-31-005-29-EL-1903-MAINT OF 33 KV XFMR AVR CTRLR15U-005-062 RC2-31-005-29-EL-1903-MAINT OF 33 KV XFMR AVR CTRL 558h 01-Jan-15 06:00 AM 16-Feb-15 12:00 PM

2150 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2151 OE101200 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2152 SHUTDOWNSHUTDOWN 4h 16-Feb-15 08:00 AM 16-Feb-15 12:00 PM

2153 OE101205 Verify LT&T and Obtain permit 1h 16-Feb-15 08:00 AM 16-Feb-15 09:00 AM

2154 OE101210 Do Insp. & Maint. as per Checklist 3h 16-Feb-15 09:00 AM 16-Feb-15 12:00 PM

2155 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2156 OE101215 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2157 R15U-005-063 RC2-31-005-29-EL-1903-MAINT OF MODULER15U-005-063 RC2-31-005-29-EL-1903-MAINT OF MODULE 558h 01-Jan-15 06:00 AM 16-Feb-15 12:00 PM

2158 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2159 OE101220 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2160 SHUTDOWNSHUTDOWN 4h 16-Feb-15 08:00 AM 16-Feb-15 12:00 PM

2161 OE101225 Verify LT&T and Obtain permit 1h 16-Feb-15 08:00 AM 16-Feb-15 09:00 AM

2162 OE101230 Do Insp. & Maint. as per Checklist 3h 16-Feb-15 09:00 AM 16-Feb-15 12:00 PM

2163 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2164 OE101235 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2165 R15U-005-066 RC2-31-005-29-EL-1910-MAINT OF IRP PANELR15U-005-066 RC2-31-005-29-EL-1910-MAINT OF IRP PANEL 476h 01-Jan-15 06:00 AM 09-Feb-15 02:00 PM

2166 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2167 OE101240 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2168 SHUTDOWNSHUTDOWN 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM

2169 OE101245 Verify LT&T and Obtain permit 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM

2170 OE101250 Do Insp. & Maint. as per Checklist 7h 09-Feb-15 07:00 AM 09-Feb-15 02:00 PM

2171 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2172 OE101255 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2173 R15U-005-067 RC2-31-005-29-EL-1990-MAINT OF ECS PANELR15U-005-067 RC2-31-005-29-EL-1990-MAINT OF ECS PANEL 476h 01-Jan-15 06:00 AM 09-Feb-15 02:00 PM

2174 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2175 OE101260 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2176 SHUTDOWNSHUTDOWN 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM

2177 OE101265 Verify LT&T and Obtain permit 1h 09-Feb-15 06:00 AM 09-Feb-15 07:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 40 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 41: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2178 OE101270 Do Insp. & Maint. as per Checklist 7h 09-Feb-15 07:00 AM 09-Feb-15 02:00 PM

2179 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2180 OE101275 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2181 R15U-005-126 RC2-31-005-29-EL-4471-MAINT OF GENRAL UPS DISTRIBUTIONR15U-005-126 RC2-31-005-29-EL-4471-MAINT OF GENRAL UPS DISTRIBUTION 548h 01-Jan-15 06:00 AM 15-Feb-15 02:00 PM

2182 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2183 OE102030 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2184 SHUTDOWNSHUTDOWN 6h 15-Feb-15 08:00 AM 15-Feb-15 02:00 PM

2185 OE102035 Verify LT&T and Obtain permit 1h 15-Feb-15 08:00 AM 15-Feb-15 09:00 AM

2186 OE102040 Do Insp. & Maint. as per Checklist 5h 15-Feb-15 09:00 AM 15-Feb-15 02:00 PM

2187 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2188 OE102045 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2189 R15U-005-127 RC2-31-005-29-EL-4571-MAINT OF GENRAL UPS DISTRIBUTIONR15U-005-127 RC2-31-005-29-EL-4571-MAINT OF GENRAL UPS DISTRIBUTION 548h 01-Jan-15 06:00 AM 15-Feb-15 02:00 PM

2190 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2191 OE102050 Carry out JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2192 SHUTDOWNSHUTDOWN 6h 15-Feb-15 08:00 AM 15-Feb-15 02:00 PM

2193 OE102055 Verify LT&T and Obtain permit 1h 15-Feb-15 08:00 AM 15-Feb-15 09:00 AM

2194 OE102060 Do Insp. & Maint. as per Checklist 5h 15-Feb-15 09:00 AM 15-Feb-15 02:00 PM

2195 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2196 OE102065 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2197 R15U-024-021 RC2-31-024-ST-1202B-CHANGE VALVE ORIENTATIONR15U-024-021 RC2-31-024-ST-1202B-CHANGE VALVE ORIENTATION 580h 01-Jan-15 06:00 AM 18-Feb-15 10:00 AM

2198 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2199 OM103435 Conduct JSA 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2200 SHUTDOWNSHUTDOWN 10h 17-Feb-15 12:00 PM 18-Feb-15 10:00 AM

2201 OM103440 Verify LT&T and Obtain permit 2h 17-Feb-15 12:00 PM 17-Feb-15 02:00 PM

2202 OM103445 Drop the valve 4h 17-Feb-15 02:00 PM 17-Feb-15 06:00 PM

2203 OM103450 Re-orient & Fix the valve 4h 18-Feb-15 06:00 AM 18-Feb-15 10:00 AM

2204 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2205 OM103455 Housekeeping and close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2206 R15U-025-001 RC2-31-025-80" SEA WATER LINE INTER INSPR15U-025-001 RC2-31-025-80" SEA WATER LINE INTER INSP 1302h 01-Jan-15 12:00 AM 24-Feb-15 06:00 AM

2207 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2208 OM100415 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2209 OM100420 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2210 SHUTDOWNSHUTDOWN 360h 09-Feb-15 06:00 AM 24-Feb-15 06:00 AM

2211 OM100425 Verify LT&T and Obtain permit 8h 09-Feb-15 06:00 AM 09-Feb-15 02:00 PM

2212 OM100430 Mechanical Isolation & Blinding 48h 09-Feb-15 02:00 PM 11-Feb-15 02:00 PM

2213 OM100435 Manway Opening & Providing a Ventilation & Lighting 24h 11-Feb-15 02:00 PM 12-Feb-15 02:00 PM

2214 OM100440 Obtain Confined space permit & Erect Internal Scaffolding 12h 12-Feb-15 02:00 PM 13-Feb-15 02:00 AM

2215 OM100445 Preliminary Inspection 8h 13-Feb-15 02:00 AM 13-Feb-15 10:00 AM

2216 OM100450 Cleaning 48h 13-Feb-15 10:00 AM 15-Feb-15 10:00 AM

2217 OM100455 Coating Inspection and Repair 120h 15-Feb-15 10:00 AM 20-Feb-15 10:00 AM

2218 OM100460 Remove Internal Scaffolding 12h 20-Feb-15 10:00 AM 20-Feb-15 10:00 PM

2219 OM100465 Final Inspection 8h 20-Feb-15 10:00 PM 21-Feb-15 06:00 AM

2220 OM100470 Manway Box-up 24h 21-Feb-15 06:00 AM 22-Feb-15 06:00 AM

2221 OM100475 De-Blinding 48h 22-Feb-15 06:00 AM 24-Feb-15 06:00 AM

2222 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2223 OM100480 Remove Scaffolding 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2224 OM100485 Carry out House keeping 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2225 OM100490 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2226 R15U-025-005 RC2-31-025-INST-MECI FLOW COMPUTERS UPGRADATIONR15U-025-005 RC2-31-025-INST-MECI FLOW COMPUTERS UPGRADATION 121h 13-Feb-15 07:00 AM 18-Feb-15 08:00 AM

2227 SHUTDOWNSHUTDOWN 121h 13-Feb-15 07:00 AM 18-Feb-15 08:00 AM

2228 OI101865 Review JSA 1h 13-Feb-15 07:00 AM 13-Feb-15 08:00 AM

2229 OI101870 Verify LT&T and Obtain permit 2h 13-Feb-15 08:00 AM 13-Feb-15 10:00 AM

2230 OI101875 Backup the Old data from FC1 & FC2 22h 13-Feb-15 10:00 AM 14-Feb-15 08:00 AM

2231 OI101880 Remove the Existing CDN 12 FC1 & FC2 22h 14-Feb-15 08:00 AM 15-Feb-15 06:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 41 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 42: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2232 OI101885 Implement the New CDN 16 FC1 & FC2 36h 15-Feb-15 06:00 AM 16-Feb-15 06:00 PM

2233 OI101890 Load the backup data in new FC1 & FC2 36h 16-Feb-15 06:00 PM 18-Feb-15 06:00 AM

2234 OI101892 Inspection by RLOC 1h 18-Feb-15 06:00 AM 18-Feb-15 07:00 AM

2235 OI101895 House keeping & Close PTW 1h 18-Feb-15 07:00 AM 18-Feb-15 08:00 AM

2236 R15U-025-007 RC2-31-025-41-E-1204 A TO O-CW LINE VALVE SERVICER15U-025-007 RC2-31-025-41-E-1204 A TO O-CW LINE VALVE SERVICE 1216h 01-Jan-15 12:00 AM 20-Feb-15 04:00 PM

2237 PRE-SHUTDOWNPRE-SHUTDOWN 66h 01-Jan-15 12:00 AM 03-Jan-15 06:00 PM

2238 OM103460 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2239 OM103465 Hydrotest the new valves 48h 01-Jan-15 02:00 AM 03-Jan-15 02:00 AM

2240 OM103470 Shift tested valves from shop to job area 4h 03-Jan-15 02:00 AM 03-Jan-15 06:00 AM

2241 OM103475 Erect scaffolding 12h 03-Jan-15 06:00 AM 03-Jan-15 06:00 PM

2242 SHUTDOWNSHUTDOWN 280h 09-Feb-15 12:00 AM 20-Feb-15 04:00 PM

2243 OM103480 Verify LT&T and Obtain permit 4h 09-Feb-15 12:00 AM 09-Feb-15 04:00 AM

2244 OM103485 Blinding as per blindlist (Refer R15U-025-010) 24h 09-Feb-15 04:00 AM 10-Feb-15 04:00 AM

2245 OM103490 Unbolt & drop the 24" I/V's (30 nos.) 60h 10-Feb-15 04:00 AM 12-Feb-15 04:00 PM

2246 OM103495 Shift removed 24" valves for servicing 6h 10-Feb-15 04:00 PM 10-Feb-15 10:00 PM

2247 OM103500 Servicing of 24" valves 144h 10-Feb-15 10:00 PM 16-Feb-15 10:00 PM

2248 OM103505 Drop the root vent & drain valves (45 nos 45h 10-Feb-15 10:00 PM 12-Feb-15 07:00 PM

2249 OM103510 Shift the removed 2" valves to valve shop 8h 12-Feb-15 07:00 PM 13-Feb-15 03:00 AM

2250 OM103515 Cut, remove & Fitup vent valves (15 nos) 30h 12-Feb-15 07:00 PM 14-Feb-15 01:00 AM

2251 OM103520 Carryout welding 45h 13-Feb-15 07:00 AM 15-Feb-15 04:00 AM

2252 OM103525 NDT on weld joints 15h 13-Feb-15 07:00 PM 14-Feb-15 10:00 AM

2253 OM103530 Carry out repair on weld, if any 24h 14-Feb-15 10:00 AM 15-Feb-15 10:00 AM

2254 OM103535 Hydrotesting weld joints 12h 14-Feb-15 10:00 PM 15-Feb-15 10:00 AM

2255 OM103540 Shift the serviced 24" valve to job area 6h 16-Feb-15 10:00 PM 17-Feb-15 04:00 AM

2256 OM103545 Fix the serviced 24" valves in position 60h 17-Feb-15 04:00 AM 19-Feb-15 04:00 PM

2257 OM103550 Fix the 2" root vent valves in position 45h 15-Feb-15 06:00 AM 17-Feb-15 03:00 AM

2258 OM103555 De-blinding (Refer R15U-025-010) 24h 19-Feb-15 04:00 PM 20-Feb-15 04:00 PM

2259 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2260 OM103560 Painting of weld joints 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2261 OM103565 Remove scaffolding 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2262 OM103570 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2263 OM103575 Q.C. Documents Submission 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2264 R15U-025-008 RC2-31-025-41-E-1204 E-VALVE REPLACEMENTR15U-025-008 RC2-31-025-41-E-1204 E-VALVE REPLACEMENT 538h 01-Jan-15 06:00 AM 14-Feb-15 04:00 PM

2265 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 06:00 AM 01-Jan-15 12:00 PM

2266 OM106010 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2267 OM106015 Conduct Hydrotest of new valve. 4h 01-Jan-15 08:00 AM 01-Jan-15 12:00 PM

2268 SHUTDOWNSHUTDOWN 22h 13-Feb-15 06:00 AM 14-Feb-15 04:00 PM

2269 OM106020 Verify LT&T and Obtain PTW 2h 13-Feb-15 06:00 AM 13-Feb-15 08:00 AM

2270 OM106025 Blinding as per blindlist (Refer R15U-025-001) 0h 13-Feb-15 08:00 AM 13-Feb-15 08:00 AM

2271 OM106030 Unbolt & drop the valve and end blind 10h 13-Feb-15 08:00 AM 13-Feb-15 06:00 PM

2272 OM106035 Remove end blind & Fix the new valve 10h 14-Feb-15 06:00 AM 14-Feb-15 04:00 PM

2273 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2274 OM106040 Shift the removed valve to valve shop 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2275 OM106045 De-Blinding (Refer job R15U-025-001) 0h 01-Jan-15 06:00 AM 01-Jan-15 06:00 AM

2276 OM106050 Housekeeping and close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2277 R15U-025-009 RC2-31-025-41-E-1204G-VALVE REPLACEMENTR15U-025-009 RC2-31-025-41-E-1204G-VALVE REPLACEMENT 570h 01-Jan-15 06:00 AM 17-Feb-15 12:00 PM

2278 PRE-SHUTDOWNPRE-SHUTDOWN 7h 01-Jan-15 06:00 AM 01-Jan-15 01:00 PM

2279 OM106055 Conduct JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2280 OM106060 Conduct Hydrotest of new valve. 5h 01-Jan-15 08:00 AM 01-Jan-15 01:00 PM

2281 SHUTDOWNSHUTDOWN 42h 14-Feb-15 06:00 AM 17-Feb-15 12:00 PM

2282 OM106065 Verify LT&T and Obtain PTW 2h 14-Feb-15 06:00 AM 14-Feb-15 08:00 AM

2283 OM106070 Blinding as per blindlist (Refer R15U-025-001) 0h 14-Feb-15 08:00 AM 14-Feb-15 08:00 AM

2284 OM106075 Unbolt & drop 2 valves and end blind 20h 14-Feb-15 08:00 AM 15-Feb-15 04:00 PM

2285 OM106080 Remove end blind & Fix 2 new valves 20h 15-Feb-15 04:00 PM 17-Feb-15 12:00 PM

2286 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 42 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 43: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2287 OM106085 Shift the removed valve to valve shop 3h 01-Jan-15 06:00 AM 01-Jan-15 09:00 AM

2288 OM106090 De-Blinding (Refer job R15U-025-001) 0h 01-Jan-15 06:00 AM 01-Jan-15 06:00 AM

2289 OM106095 Housekeeping and close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2290 R15U-025-010 RC2-31-025-67-P-1205A-CCCW 80" LINE ALIGNMENTR15U-025-010 RC2-31-025-67-P-1205A-CCCW 80" LINE ALIGNMENT 1305h 01-Jan-15 12:00 AM 24-Feb-15 09:00 AM

2291 PRE-SHUTDOWNPRE-SHUTDOWN 86h 01-Jan-15 12:00 AM 04-Jan-15 02:00 PM

2292 OM103580 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2293 OM103585 Shift blinds to location 24h 01-Jan-15 02:00 AM 02-Jan-15 02:00 AM

2294 OM103590 Erect Scaffolding 60h 02-Jan-15 02:00 AM 04-Jan-15 02:00 PM

2295 SHUTDOWNSHUTDOWN 369h 09-Feb-15 12:00 AM 24-Feb-15 09:00 AM

2296 OM103595 Verify LT&T and Obtain permit 12h 09-Feb-15 12:00 AM 09-Feb-15 12:00 PM

2297 OM103600 Drop chem. injection line from blind B2 1h 09-Feb-15 12:00 PM 09-Feb-15 01:00 PM

2298 OM103605 Remove all inst. accessories in 80" spool 1h 09-Feb-15 01:00 PM 09-Feb-15 02:00 PM

2299 OM103610 Blinding as per blindlist 24h 09-Feb-15 12:00 PM 10-Feb-15 12:00 PM

2300 OM103615 Drop the 80" spools & provide end blinds 12h 09-Feb-15 12:00 PM 10-Feb-15 12:00 AM

2301 OM103620 Unbolt & drop the bellows (Refer R15U-025-011, Vendor supervision reqd.) 0h 10-Feb-15 12:00 AM 10-Feb-15 12:00 AM

2302 OM103625 Erect Scaffolding 4h 10-Feb-15 12:00 AM 10-Feb-15 04:00 AM

2303 OM103630 Check & Cut the misaligned flanges (3 nos.) 24h 10-Feb-15 04:00 AM 11-Feb-15 04:00 AM

2304 OM103635 Edge preparation of pipeline 36h 11-Feb-15 04:00 AM 12-Feb-15 04:00 PM

2305 OM103640 Fit-up the flange by rectify mis-alignment 24h 12-Feb-15 04:00 PM 13-Feb-15 04:00 PM

2306 OM103645 Carryout welding 56h 13-Feb-15 04:00 PM 16-Feb-15 12:00 AM

2307 OM103650 NDT on weld joints 24h 16-Feb-15 12:00 AM 17-Feb-15 12:00 AM

2308 OM103655 RT on weld joints 32h 18-Feb-15 12:00 AM 19-Feb-15 08:00 AM

2309 OM103660 Carry out repair on weld, if any 24h 17-Feb-15 12:00 AM 18-Feb-15 12:00 AM

2310 OM103665 Hydrotesting weld joints 48h 19-Feb-15 08:00 AM 21-Feb-15 08:00 AM

2311 OM103670 Fix & Tight new bellows (Refer R15U-025-011, Vendor supervision reqd.) 0h 21-Feb-15 08:00 AM 21-Feb-15 08:00 AM

2312 OM103675 Drop 80" end blinds & fix the spools 36h 21-Feb-15 08:00 AM 22-Feb-15 08:00 PM

2313 OM103680 Fix back instrument accessories 1h 22-Feb-15 08:00 PM 22-Feb-15 09:00 PM

2314 OM103685 Carryout de-blinding 72h 21-Feb-15 08:00 AM 24-Feb-15 08:00 AM

2315 OM103690 Fix back chem. injection line on B2 1h 24-Feb-15 08:00 AM 24-Feb-15 09:00 AM

2316 POST SHUTDOWNPOST SHUTDOWN 24h 01-Jan-15 12:00 AM 02-Jan-15 12:00 AM

2317 OM103695 Remove scaffolding 24h 01-Jan-15 12:00 AM 02-Jan-15 12:00 AM

2318 OM103700 Housekeeping and close PTW 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2319 OM103705 Q.C documents submission 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2320 R15U-025-011 RC2-31-025-67-P-1205A-REPLACING CW BELLOWR15U-025-011 RC2-31-025-67-P-1205A-REPLACING CW BELLOW 1316h 01-Jan-15 12:00 AM 24-Feb-15 08:00 PM

2321 PRE-SHUTDOWNPRE-SHUTDOWN 28h 01-Jan-15 12:00 AM 02-Jan-15 04:00 AM

2322 OM103710 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2323 OM103715 Shift bellows from warehouse to job area 3h 01-Jan-15 01:00 AM 01-Jan-15 04:00 AM

2324 OM103720 Erect Scaffolding 24h 01-Jan-15 04:00 AM 02-Jan-15 04:00 AM

2325 SHUTDOWNSHUTDOWN 76h 21-Feb-15 04:00 PM 24-Feb-15 08:00 PM

2326 OM103725 Verify LT&T and Obtain permit 4h 21-Feb-15 04:00 PM 21-Feb-15 08:00 PM

2327 OM103730 Blinding as per blindlist (Refer R15U-025-010) 0h 21-Feb-15 08:00 PM 21-Feb-15 08:00 PM

2328 OM103735 Drop the bellows 24h 21-Feb-15 08:00 PM 22-Feb-15 08:00 PM

2329 OM103740 Fix new bellows in presence of Vendor 24h 22-Feb-15 08:00 PM 23-Feb-15 08:00 PM

2330 OM103745 Tight the bolts in Vendor presence 24h 23-Feb-15 08:00 PM 24-Feb-15 08:00 PM

2331 OM103750 De-blinding (Refer R15U-025-010) 0h 24-Feb-15 08:00 PM 24-Feb-15 08:00 PM

2332 POST SHUTDOWNPOST SHUTDOWN 24h 01-Jan-15 12:00 AM 02-Jan-15 12:00 AM

2333 OM103755 Remove scaffolding 24h 01-Jan-15 12:00 AM 02-Jan-15 12:00 AM

2334 OM103760 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2335 R15U-025-014 RC2-31-025-95-D-1227-INTER & EXTERNAL INSPR15U-025-014 RC2-31-025-95-D-1227-INTER & EXTERNAL INSP 1290h 01-Jan-15 12:00 AM 23-Feb-15 06:00 PM

2336 PRE-SHUTDOWNPRE-SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2337 OM100495 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2338 OM100500 Erect Scaffolding 6h 01-Jan-15 02:00 AM 01-Jan-15 08:00 AM

2339 SHUTDOWNSHUTDOWN 60h 21-Feb-15 06:00 AM 23-Feb-15 06:00 PM

2340 OM100505 Verify LT&T and Obtain permit 8h 21-Feb-15 06:00 AM 21-Feb-15 02:00 PM

2341 OM100510 Mechanical Isolation & Blinding 0h 21-Feb-15 02:00 PM 21-Feb-15 02:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 43 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 44: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2342 OM100515 Manway Opening & Providing a Ventilation & Lighting 8h 21-Feb-15 02:00 PM 21-Feb-15 10:00 PM

2343 OM100520 Obtain Confined space permit & Erect Internal Scaffolding 8h 21-Feb-15 10:00 PM 22-Feb-15 06:00 AM

2344 OM100525 Preliminary Inspection 4h 22-Feb-15 06:00 AM 22-Feb-15 10:00 AM

2345 OM100530 Cleaning & Repair 18h 22-Feb-15 10:00 AM 23-Feb-15 04:00 AM

2346 OM100535 Remove Internal Scaffolding 4h 23-Feb-15 04:00 AM 23-Feb-15 08:00 AM

2347 OM100540 Final Inspection 4h 23-Feb-15 08:00 AM 23-Feb-15 12:00 PM

2348 OM100545 Manway Box-up 6h 23-Feb-15 12:00 PM 23-Feb-15 06:00 PM

2349 OM100550 De-Blinding 0h 23-Feb-15 06:00 PM 23-Feb-15 06:00 PM

2350 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2351 OM100555 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2352 OM100560 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2353 OM100565 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2354 R15U-025-015 RC2-31-025-P-1205 A/B/C-INST-STROKE TEST OF VALVESR15U-025-015 RC2-31-025-P-1205 A/B/C-INST-STROKE TEST OF VALVES 65h 19-Feb-15 08:00 AM 22-Feb-15 01:00 AM

2355 SHUTDOWNSHUTDOWN 65h 19-Feb-15 08:00 AM 22-Feb-15 01:00 AM

2356 OI101900 Review JSA 1h 19-Feb-15 08:00 AM 19-Feb-15 09:00 AM

2357 OI101905 Verify LT&T and Obtain permit 2h 19-Feb-15 09:00 AM 19-Feb-15 11:00 AM

2358 OI101910 Asst. Vendor for Strok e Chec k the Valves 24h 19-Feb-15 11:00 AM 20-Feb-15 11:00 AM

2359 OI101915 Replace Ac cessories/Power cards*if necessary 36h 20-Feb-15 11:00 AM 21-Feb-15 11:00 PM

2360 OI101917 Inspection by RLOC 1h 21-Feb-15 11:00 PM 22-Feb-15 12:00 AM

2361 OI101920 Housekeeping & Close PTW 1h 22-Feb-15 12:00 AM 22-Feb-15 01:00 AM

2362 R15U-025-016 RC2-31-025-PV-0020A-CV-OVERHAUL & SERVICINGR15U-025-016 RC2-31-025-PV-0020A-CV-OVERHAUL & SERVICING 27h 10-Feb-15 06:00 AM 11-Feb-15 09:00 AM

2363 SHUTDOWNSHUTDOWN 27h 10-Feb-15 06:00 AM 11-Feb-15 09:00 AM

2364 OI100450 Review JSA 1h 10-Feb-15 06:00 AM 10-Feb-15 07:00 AM

2365 OI100455 Verify LT&T and Obtain permit 1h 10-Feb-15 07:00 AM 10-Feb-15 08:00 AM

2366 OI100460 Disconnect Signals / Connections for CV 1h 10-Feb-15 08:00 AM 10-Feb-15 09:00 AM

2367 OI100465 Removal of CV & Install Blinds 3h 10-Feb-15 09:00 AM 10-Feb-15 12:00 PM

2368 OI100470 Transport CV to Work Shop 1h 10-Feb-15 12:00 PM 10-Feb-15 01:00 PM

2369 OI100475 Overhaul / Service CV 8h 10-Feb-15 01:00 PM 10-Feb-15 09:00 PM

2370 OI100480 Test Valve (Refer Documentation) 2h 10-Feb-15 09:00 PM 10-Feb-15 11:00 PM

2371 OI100485 Transport CV to Unit / Remove Blinds 1h 10-Feb-15 11:00 PM 11-Feb-15 12:00 AM

2372 OI100490 Install CV 5h 11-Feb-15 12:00 AM 11-Feb-15 05:00 AM

2373 OI100495 Loop Check & Stroke test 2h 11-Feb-15 05:00 AM 11-Feb-15 07:00 AM

2374 OI100500 Inspection by RLOC 1h 11-Feb-15 07:00 AM 11-Feb-15 08:00 AM

2375 OI100505 House keeping & Close PTW 1h 11-Feb-15 08:00 AM 11-Feb-15 09:00 AM

2376 R15U-025-018 RC2-31-025-41-E-1204 A-O-CW LINE VALVE SERVICINGR15U-025-018 RC2-31-025-41-E-1204 A-O-CW LINE VALVE SERVICING 1214h 01-Jan-15 12:00 AM 20-Feb-15 02:00 PM

2377 PRE-SHUTDOWNPRE-SHUTDOWN 74h 01-Jan-15 12:00 AM 04-Jan-15 02:00 AM

2378 OM103855 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2379 OM103860 Hydrotest the new valves 36h 01-Jan-15 02:00 AM 02-Jan-15 02:00 PM

2380 OM103865 Shift tested valves to job area 24h 02-Jan-15 02:00 PM 03-Jan-15 02:00 PM

2381 OM103870 Erect scaffolding 12h 03-Jan-15 02:00 PM 04-Jan-15 02:00 AM

2382 SHUTDOWNSHUTDOWN 278h 09-Feb-15 12:00 AM 20-Feb-15 02:00 PM

2383 OM103875 Verify LT&T and Obtain permit 4h 09-Feb-15 12:00 AM 09-Feb-15 04:00 AM

2384 OM103880 Blinding as per blindlist. 24h 09-Feb-15 04:00 AM 10-Feb-15 04:00 AM

2385 OM103885 Unbolt & drop the 80" isolation valves 72h 10-Feb-15 04:00 AM 13-Feb-15 04:00 AM

2386 OM103890 Shift removed 80" valves for servicing 12h 11-Feb-15 04:00 AM 11-Feb-15 04:00 PM

2387 OM103895 Unbolt & drop the 24" I/V's (30 nos.) 60h 11-Feb-15 04:00 PM 14-Feb-15 04:00 AM

2388 OM103900 Shift removed 24" valves for servicing 6h 12-Feb-15 04:00 PM 12-Feb-15 10:00 PM

2389 OM103905 Unbolt the 4" valves (19 nos.) 40h 14-Feb-15 04:00 AM 15-Feb-15 08:00 PM

2390 OM103910 Unbolt the 2" valves (15 nos.) 30h 14-Feb-15 04:00 AM 15-Feb-15 10:00 AM

2391 OM103915 Shift removed valves to shop for servicing 12h 15-Feb-15 10:00 AM 15-Feb-15 10:00 PM

2392 OM103920 Cut & remove the 1" SW valves (15 nos.) 30h 15-Feb-15 10:00 PM 17-Feb-15 04:00 AM

2393 OM103925 Fit up the new valve in position 30h 16-Feb-15 10:00 AM 17-Feb-15 04:00 PM

2394 OM103930 Carryout welding 45h 16-Feb-15 10:00 PM 18-Feb-15 07:00 PM

2395 OM103935 NDT on weld joints (As per RAT sheet) 15h 17-Feb-15 10:00 AM 18-Feb-15 01:00 AM

2396 OM103940 Carryout repairs, if any 24h 18-Feb-15 01:00 AM 19-Feb-15 01:00 AM

2397 OM103945 Shift the tested 80" & 24" valves from valve shop to job location 24h 15-Feb-15 10:00 PM 16-Feb-15 10:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 44 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 45: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2398 OM103950 Shift the tested valves to job area 12h 15-Feb-15 10:00 PM 16-Feb-15 10:00 AM

2399 OM103955 Fix the tested 80" valves in position 72h 16-Feb-15 10:00 PM 19-Feb-15 10:00 PM

2400 OM103960 Fix the tested 24" valves in position 60h 16-Feb-15 10:00 PM 19-Feb-15 10:00 AM

2401 OM103965 Fix the tested 4" valves in position 60h 15-Feb-15 08:00 PM 18-Feb-15 08:00 AM

2402 OM103970 Fix the tested 2" valves in position 30h 18-Feb-15 08:00 AM 19-Feb-15 02:00 PM

2403 OM103975 De-Blinding (Refer R15U-025-001 Sea Water System) 24h 19-Feb-15 02:00 PM 20-Feb-15 02:00 PM

2404 POST SHUTDOWNPOST SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2405 OM103980 Painting of weld joints 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2406 OM103985 Remove scaffolding 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2407 OM103990 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2408 OM103995 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2409 INSTRUMENT AIR, PLANT AIR & HP AIR SYSTEMINSTRUMENT AIR, PLANT AIR & HP AIR SYSTEM 1220h 01-Jan-15 12:00 AM 20-Feb-15 08:00 PM

2410 R15U-037-007 RC2-31-037-FI-0013-PROVIDE ISO. DRAIN VALVER15U-037-007 RC2-31-037-FI-0013-PROVIDE ISO. DRAIN VALVE 1220h 01-Jan-15 12:00 AM 20-Feb-15 08:00 PM

2411 PRE-SHUTDOWNPRE-SHUTDOWN 126h 01-Jan-15 12:00 AM 06-Jan-15 06:00 AM

2412 OM105415 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2413 OM105420 Carryout hydrotest of new valves. 3h 01-Jan-15 01:00 AM 01-Jan-15 04:00 AM

2414 OM105425 Prefab. of piping as per dwg. 120h 01-Jan-15 04:00 AM 06-Jan-15 04:00 AM

2415 OM105430 Shift blinds to location 2h 06-Jan-15 04:00 AM 06-Jan-15 06:00 AM

2416 SHUTDOWNSHUTDOWN 40h 19-Feb-15 04:00 AM 20-Feb-15 08:00 PM

2417 OM105435 Erect Scaffolding & Firebox. 4h 19-Feb-15 04:00 AM 19-Feb-15 08:00 AM

2418 OM105440 Verify LT&T and Obtain PTW 4h 19-Feb-15 08:00 AM 19-Feb-15 12:00 PM

2419 OM105445 Drop spool & Blinding as per blindlist. 6h 19-Feb-15 12:00 PM 19-Feb-15 06:00 PM

2420 OM105450 Unbolt & drop the valve FI-0013 3h 19-Feb-15 06:00 PM 19-Feb-15 09:00 PM

2421 OM105455 Cut & remove the pipings as per dwg. 8h 19-Feb-15 09:00 PM 20-Feb-15 05:00 AM

2422 OM105460 Fit up & carryout welding 6h 20-Feb-15 05:00 AM 20-Feb-15 11:00 AM

2423 OM105465 Install the valves 4h 20-Feb-15 11:00 AM 20-Feb-15 03:00 PM

2424 OM105470 NDT on weld joints 5h 20-Feb-15 03:00 PM 20-Feb-15 08:00 PM

2425 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2426 OM105475 Reinstall spools & Carryout De-Blinding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2427 OM105480 Removal of Scaffolds 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2428 OM105485 Housekeeping and close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2429 ETHYLENE STORAGEETHYLENE STORAGE 1440h 01-Jan-15 12:00 AM 02-Mar-15 12:00 AM

2430 R15U-072-008 RC2-31-072-93-V-0115-PROVIDE ISO. & DRAIN VALVER15U-072-008 RC2-31-072-93-V-0115-PROVIDE ISO. & DRAIN VALVE 1397h 01-Jan-15 12:00 AM 28-Feb-15 05:00 AM

2431 PRE-SHUTDOWNPRE-SHUTDOWN 34h 01-Jan-15 12:00 AM 02-Jan-15 10:00 AM

2432 OM104685 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2433 OM104690 Pre-fab the pipe with drain as per dwg. 24h 01-Jan-15 01:00 AM 02-Jan-15 01:00 AM

2434 OM104695 Inspect the weld joint 4h 02-Jan-15 01:00 AM 02-Jan-15 05:00 AM

2435 OM104700 Erect Scaffolding 2h 02-Jan-15 05:00 AM 02-Jan-15 07:00 AM

2436 OM104705 Removal of Insulations. 3h 02-Jan-15 07:00 AM 02-Jan-15 10:00 AM

2437 SHUTDOWNSHUTDOWN 43h 26-Feb-15 10:00 AM 28-Feb-15 05:00 AM

2438 OM104710 Purging / Flushing the line & Perform gas test / LEL checking 8h 26-Feb-15 10:00 AM 26-Feb-15 06:00 PM

2439 OM104715 Verify LT&T and Obtain permit 2h 26-Feb-15 06:00 PM 26-Feb-15 08:00 PM

2440 OM104720 Blinding as per blindlist (Refer R15U-072-012) 0h 26-Feb-15 08:00 PM 26-Feb-15 08:00 PM

2441 OM104725 Cut & remove the pipeline as per dwg. 4h 26-Feb-15 08:00 PM 27-Feb-15 12:00 AM

2442 OM104730 Fitup the pipeline & valve in position 4h 27-Feb-15 12:00 AM 27-Feb-15 04:00 AM

2443 OM104735 Carryout welding 4h 27-Feb-15 04:00 AM 27-Feb-15 08:00 AM

2444 OM104740 NDT on weld joints (As per RAT sheet) 8h 27-Feb-15 08:00 AM 27-Feb-15 04:00 PM

2445 OM104745 Hydrotest on weld joints 8h 27-Feb-15 04:00 PM 28-Feb-15 12:00 AM

2446 OM104750 Carry out repair on weld if any 4h 28-Feb-15 12:00 AM 28-Feb-15 04:00 AM

2447 OM104755 Painting on weld joints 1h 28-Feb-15 04:00 AM 28-Feb-15 05:00 AM

2448 OM104760 De-Blinding (Refer R15U-072-012) 0h 28-Feb-15 05:00 AM 28-Feb-15 05:00 AM

2449 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

2450 OM104765 Fix back the insulation 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

2451 OM104770 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2452 OM104775 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 45 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 46: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2453 OM104780 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2454 R15U-072-009 RC2-31-072-93-V-0121-PROVIDE ISO. & DRAIN VALVER15U-072-009 RC2-31-072-93-V-0121-PROVIDE ISO. & DRAIN VALVE 1440h 01-Jan-15 12:00 AM 02-Mar-15 12:00 AM

2455 PRE-SHUTDOWNPRE-SHUTDOWN 34h 01-Jan-15 12:00 AM 02-Jan-15 10:00 AM

2456 OM104785 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2457 OM104790 Pre-fab the pipe with drain as per dwg. 24h 01-Jan-15 01:00 AM 02-Jan-15 01:00 AM

2458 OM104795 Inspect the weld joint 4h 02-Jan-15 01:00 AM 02-Jan-15 05:00 AM

2459 OM104800 Erect Scaffolding 2h 02-Jan-15 05:00 AM 02-Jan-15 07:00 AM

2460 OM104805 Removal of Insulations. 3h 02-Jan-15 07:00 AM 02-Jan-15 10:00 AM

2461 SHUTDOWNSHUTDOWN 43h 28-Feb-15 05:00 AM 02-Mar-15 12:00 AM

2462 OM104810 Purging / Flushing the line & Perform gas test / LEL checking 8h 28-Feb-15 05:00 AM 28-Feb-15 01:00 PM

2463 OM104815 Verify LT&T and Obtain permit 2h 28-Feb-15 01:00 PM 28-Feb-15 03:00 PM

2464 OM104820 Blinding as per blindlist (Refer R15U-072-012) 0h 28-Feb-15 03:00 PM 28-Feb-15 03:00 PM

2465 OM104825 Cut & remove the pipeline as per dwg. 4h 28-Feb-15 03:00 PM 28-Feb-15 07:00 PM

2466 OM104830 Fitup the pipeline & valve in position 4h 28-Feb-15 07:00 PM 28-Feb-15 11:00 PM

2467 OM104835 Carryout welding 4h 28-Feb-15 11:00 PM 01-Mar-15 03:00 AM

2468 OM104840 NDT on weld joints (As per RAT sheet) 8h 01-Mar-15 03:00 AM 01-Mar-15 11:00 AM

2469 OM104845 Hydrotest on weld joints 8h 01-Mar-15 11:00 AM 01-Mar-15 07:00 PM

2470 OM104850 Carry out repair on weld if any 4h 01-Mar-15 07:00 PM 01-Mar-15 11:00 PM

2471 OM104855 Painting on weld joints 1h 01-Mar-15 11:00 PM 02-Mar-15 12:00 AM

2472 OM104860 De-Blinding (Refer R15U-072-012) 0h 02-Mar-15 12:00 AM 02-Mar-15 12:00 AM

2473 POST SHUTDOWNPOST SHUTDOWN 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

2474 OM104865 Fix back the insulation 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

2475 OM104870 Remove scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2476 OM104875 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2477 OM104880 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2478 R15U-072-013 RC2-31-072-EIV-0001-CV-OVERHAUL & SERVICINGR15U-072-013 RC2-31-072-EIV-0001-CV-OVERHAUL & SERVICING 1283h 01-Jan-15 12:00 AM 23-Feb-15 11:00 AM

2479 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2480 OI100860 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2481 OI100865 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2482 SHUTDOWNSHUTDOWN 29h 22-Feb-15 06:00 AM 23-Feb-15 11:00 AM

2483 OI100870 Verify LT&T and Obtain permit 1h 22-Feb-15 06:00 AM 22-Feb-15 07:00 AM

2484 OI100875 Disconnect Signals / Connections for CV 1h 22-Feb-15 07:00 AM 22-Feb-15 08:00 AM

2485 OI100880 Removal of CV & Install Blinds 5h 22-Feb-15 08:00 AM 22-Feb-15 01:00 PM

2486 OI100885 Transport CV to Work Shop 1h 22-Feb-15 01:00 PM 22-Feb-15 02:00 PM

2487 OI100890 Overhaul / Service CV 8h 22-Feb-15 02:00 PM 22-Feb-15 10:00 PM

2488 OI100895 Test Valve (Refer Documentation) 2h 22-Feb-15 10:00 PM 23-Feb-15 12:00 AM

2489 OI100900 Transport CV to Unit / Remove Blinds 1h 23-Feb-15 12:00 AM 23-Feb-15 01:00 AM

2490 OI100905 Install CV 7h 23-Feb-15 01:00 AM 23-Feb-15 08:00 AM

2491 OI100910 Loop Check & Stroke test 2h 23-Feb-15 08:00 AM 23-Feb-15 10:00 AM

2492 OI100915 Inspection by RLOC 1h 23-Feb-15 10:00 AM 23-Feb-15 11:00 AM

2493 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2494 OI100920 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2495 OI100925 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2496 R15U-072-015 RC2-31-072-EIV-0031-CV-OVERHAUL & SERVICINGR15U-072-015 RC2-31-072-EIV-0031-CV-OVERHAUL & SERVICING 1307h 01-Jan-15 12:00 AM 24-Feb-15 11:00 AM

2497 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2498 OI100930 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2499 OI100935 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2500 SHUTDOWNSHUTDOWN 29h 23-Feb-15 06:00 AM 24-Feb-15 11:00 AM

2501 OI100940 Verify LT&T and Obtain permit 1h 23-Feb-15 06:00 AM 23-Feb-15 07:00 AM

2502 OI100945 Disconnect Signals / Connections for CV 1h 23-Feb-15 07:00 AM 23-Feb-15 08:00 AM

2503 OI100950 Removal of CV & Install Blinds 5h 23-Feb-15 08:00 AM 23-Feb-15 01:00 PM

2504 OI100955 Transport CV to Work Shop 1h 23-Feb-15 01:00 PM 23-Feb-15 02:00 PM

2505 OI100960 Overhaul / Service CV 8h 23-Feb-15 02:00 PM 23-Feb-15 10:00 PM

2506 OI100965 Test Valve (Refer Documentation) 2h 23-Feb-15 10:00 PM 24-Feb-15 12:00 AM

2507 OI100970 Transport CV to Unit / Remove Blinds 1h 24-Feb-15 12:00 AM 24-Feb-15 01:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 46 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 47: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2508 OI100975 Install CV 7h 24-Feb-15 01:00 AM 24-Feb-15 08:00 AM

2509 OI100980 Loop Check & Stroke test 2h 24-Feb-15 08:00 AM 24-Feb-15 10:00 AM

2510 OI100985 Inspection by RLOC 1h 24-Feb-15 10:00 AM 24-Feb-15 11:00 AM

2511 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2512 OI100990 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2513 OI100995 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2514 R15U-072-017 RC2-31-072-EIV-0052-CV-OVERHAUL & SERVICINGR15U-072-017 RC2-31-072-EIV-0052-CV-OVERHAUL & SERVICING 1331h 01-Jan-15 12:00 AM 25-Feb-15 11:00 AM

2515 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2516 OI101000 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2517 OI101005 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2518 SHUTDOWNSHUTDOWN 29h 24-Feb-15 06:00 AM 25-Feb-15 11:00 AM

2519 OI101010 Verify LT&T and Obtain permit 1h 24-Feb-15 06:00 AM 24-Feb-15 07:00 AM

2520 OI101015 Disconnect Signals / Connections for CV 1h 24-Feb-15 07:00 AM 24-Feb-15 08:00 AM

2521 OI101020 Removal of CV & Install Blinds 5h 24-Feb-15 08:00 AM 24-Feb-15 01:00 PM

2522 OI101025 Transport CV to Work Shop 1h 24-Feb-15 01:00 PM 24-Feb-15 02:00 PM

2523 OI101030 Overhaul / Service CV 8h 24-Feb-15 02:00 PM 24-Feb-15 10:00 PM

2524 OI101035 Test Valve (Refer Documentation) 2h 24-Feb-15 10:00 PM 25-Feb-15 12:00 AM

2525 OI101040 Transport CV to Unit / Remove Blinds 1h 25-Feb-15 12:00 AM 25-Feb-15 01:00 AM

2526 OI101045 Install CV 7h 25-Feb-15 01:00 AM 25-Feb-15 08:00 AM

2527 OI101050 Loop Check & Stroke test 2h 25-Feb-15 08:00 AM 25-Feb-15 10:00 AM

2528 OI101055 Inspection by RLOC 1h 25-Feb-15 10:00 AM 25-Feb-15 11:00 AM

2529 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2530 OI101060 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2531 OI101065 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2532 R15U-072-019 RC2-31-072-EIV-0054-CV-OVERHAUL & SERVICINGR15U-072-019 RC2-31-072-EIV-0054-CV-OVERHAUL & SERVICING 1331h 01-Jan-15 12:00 AM 25-Feb-15 11:00 AM

2533 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2534 OI101070 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2535 OI101075 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2536 SHUTDOWNSHUTDOWN 29h 24-Feb-15 06:00 AM 25-Feb-15 11:00 AM

2537 OI101080 Verify LT&T and Obtain permit 1h 24-Feb-15 06:00 AM 24-Feb-15 07:00 AM

2538 OI101085 Disconnect Signals / Connections for CV 1h 24-Feb-15 07:00 AM 24-Feb-15 08:00 AM

2539 OI101090 Removal of CV & Install Blinds 5h 24-Feb-15 08:00 AM 24-Feb-15 01:00 PM

2540 OI101095 Transport CV to Work Shop 1h 24-Feb-15 01:00 PM 24-Feb-15 02:00 PM

2541 OI101100 Overhaul / Service CV 8h 24-Feb-15 02:00 PM 24-Feb-15 10:00 PM

2542 OI101105 Test Valve (Refer Documentation) 2h 24-Feb-15 10:00 PM 25-Feb-15 12:00 AM

2543 OI101110 Transport CV to Unit / Remove Blinds 1h 25-Feb-15 12:00 AM 25-Feb-15 01:00 AM

2544 OI101115 Install CV 7h 25-Feb-15 01:00 AM 25-Feb-15 08:00 AM

2545 OI101120 Loop Check & Stroke test 2h 25-Feb-15 08:00 AM 25-Feb-15 10:00 AM

2546 OI101125 Inspection by RLOC 1h 25-Feb-15 10:00 AM 25-Feb-15 11:00 AM

2547 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2548 OI101130 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2549 OI101135 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2550 R15U-072-020 RC2-31-072-EIV-0061-CV-OVERHAUL & SERVICINGR15U-072-020 RC2-31-072-EIV-0061-CV-OVERHAUL & SERVICING 1355h 01-Jan-15 12:00 AM 26-Feb-15 11:00 AM

2551 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2552 OI101140 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2553 OI101145 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2554 SHUTDOWNSHUTDOWN 29h 25-Feb-15 06:00 AM 26-Feb-15 11:00 AM

2555 OI101150 Verify LT&T and Obtain permit 1h 25-Feb-15 06:00 AM 25-Feb-15 07:00 AM

2556 OI101155 Disconnect Signals / Connections for CV 1h 25-Feb-15 07:00 AM 25-Feb-15 08:00 AM

2557 OI101160 Removal of CV & Install Blinds 5h 25-Feb-15 08:00 AM 25-Feb-15 01:00 PM

2558 OI101165 Transport CV to Work Shop 1h 25-Feb-15 01:00 PM 25-Feb-15 02:00 PM

2559 OI101170 Overhaul / Service CV 8h 25-Feb-15 02:00 PM 25-Feb-15 10:00 PM

2560 OI101175 Test Valve (Refer Documentation) 2h 25-Feb-15 10:00 PM 26-Feb-15 12:00 AM

2561 OI101180 Transport CV to Unit / Remove Blinds 1h 26-Feb-15 12:00 AM 26-Feb-15 01:00 AM

2562 OI101185 Install CV 7h 26-Feb-15 01:00 AM 26-Feb-15 08:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 47 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 48: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2563 OI101190 Loop Check & Stroke test 2h 26-Feb-15 08:00 AM 26-Feb-15 10:00 AM

2564 OI101195 Inspection by RLOC 1h 26-Feb-15 10:00 AM 26-Feb-15 11:00 AM

2565 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2566 OI101200 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2567 OI101205 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2568 R15U-072-021 RC2-31-072-EIV-0081-CV-OVERHAUL & SERVICINGR15U-072-021 RC2-31-072-EIV-0081-CV-OVERHAUL & SERVICING 1385h 01-Jan-15 12:00 AM 27-Feb-15 05:00 PM

2569 PRE-SHUTDOWNPRE-SHUTDOWN 9h 01-Jan-15 12:00 AM 01-Jan-15 09:00 AM

2570 OI101210 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2571 OI101215 Errect Scaffolding / Remove Insulation 8h 01-Jan-15 01:00 AM 01-Jan-15 09:00 AM

2572 SHUTDOWNSHUTDOWN 35h 26-Feb-15 06:00 AM 27-Feb-15 05:00 PM

2573 OI101220 Verify LT&T and Obtain permit 1h 26-Feb-15 06:00 AM 26-Feb-15 07:00 AM

2574 OI101225 Disconnect Signals / Connections for CV 1h 26-Feb-15 07:00 AM 26-Feb-15 08:00 AM

2575 OI101230 Removal of CV & Install Blinds 6h 26-Feb-15 08:00 AM 26-Feb-15 02:00 PM

2576 OI101235 Transport CV to Work Shop 1h 26-Feb-15 02:00 PM 26-Feb-15 03:00 PM

2577 OI101240 Overhaul / Service CV 8h 26-Feb-15 03:00 PM 26-Feb-15 11:00 PM

2578 OI101245 Test Valve (Refer Documentation) 2h 26-Feb-15 11:00 PM 27-Feb-15 01:00 AM

2579 OI101250 Transport CV to Unit / Remove Blinds 1h 27-Feb-15 01:00 AM 27-Feb-15 02:00 AM

2580 OI101255 Install CV 12h 27-Feb-15 02:00 AM 27-Feb-15 02:00 PM

2581 OI101260 Loop Check & Stroke test 2h 27-Feb-15 02:00 PM 27-Feb-15 04:00 PM

2582 OI101265 Inspection by RLOC 1h 27-Feb-15 04:00 PM 27-Feb-15 05:00 PM

2583 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2584 OI101270 Reinsulate CV / Removal of Scaffolds 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2585 OI101275 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2586 R15U-072-022 RC2-31-072-FV-0145-CV-OVERHAUL & SERVICINGR15U-072-022 RC2-31-072-FV-0145-CV-OVERHAUL & SERVICING 1377h 01-Jan-15 12:00 AM 27-Feb-15 09:00 AM

2587 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2588 OI101280 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2589 OI101285 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2590 SHUTDOWNSHUTDOWN 27h 26-Feb-15 06:00 AM 27-Feb-15 09:00 AM

2591 OI101290 Verify LT&T and Obtain permit 1h 26-Feb-15 06:00 AM 26-Feb-15 07:00 AM

2592 OI101295 Disconnect Signals / Connections for CV 1h 26-Feb-15 07:00 AM 26-Feb-15 08:00 AM

2593 OI101300 Removal of CV & Install Blinds 4h 26-Feb-15 08:00 AM 26-Feb-15 12:00 PM

2594 OI101305 Transport CV to Work Shop 1h 26-Feb-15 12:00 PM 26-Feb-15 01:00 PM

2595 OI101310 Overhaul / Service CV 8h 26-Feb-15 01:00 PM 26-Feb-15 09:00 PM

2596 OI101315 Test Valve (Refer Documentation) 2h 26-Feb-15 09:00 PM 26-Feb-15 11:00 PM

2597 OI101320 Transport CV to Unit / Remove Blinds 1h 26-Feb-15 11:00 PM 27-Feb-15 12:00 AM

2598 OI101325 Install CV 6h 27-Feb-15 12:00 AM 27-Feb-15 06:00 AM

2599 OI101330 Loop Check & Stroke test 2h 27-Feb-15 06:00 AM 27-Feb-15 08:00 AM

2600 OI101335 Inspection by RLOC 1h 27-Feb-15 08:00 AM 27-Feb-15 09:00 AM

2601 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2602 OI101340 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2603 OI101345 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2604 R15U-072-024 RC2-31-072-PV-0101-CV-OVERHAUL & SERVICINGR15U-072-024 RC2-31-072-PV-0101-CV-OVERHAUL & SERVICING 1401h 01-Jan-15 12:00 AM 28-Feb-15 09:00 AM

2605 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2606 OI101350 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2607 OI101355 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2608 SHUTDOWNSHUTDOWN 27h 27-Feb-15 06:00 AM 28-Feb-15 09:00 AM

2609 OI101360 Verify LT&T and Obtain permit 1h 27-Feb-15 06:00 AM 27-Feb-15 07:00 AM

2610 OI101365 Disconnect Signals / Connections for CV 1h 27-Feb-15 07:00 AM 27-Feb-15 08:00 AM

2611 OI101370 Removal of CV & Install Blinds 4h 27-Feb-15 08:00 AM 27-Feb-15 12:00 PM

2612 OI101375 Transport CV to Work Shop 1h 27-Feb-15 12:00 PM 27-Feb-15 01:00 PM

2613 OI101380 Overhaul / Service CV 8h 27-Feb-15 01:00 PM 27-Feb-15 09:00 PM

2614 OI101385 Test Valve (Refer Documentation) 2h 27-Feb-15 09:00 PM 27-Feb-15 11:00 PM

2615 OI101390 Transport CV to Unit / Remove Blinds 1h 27-Feb-15 11:00 PM 28-Feb-15 12:00 AM

2616 OI101395 Install CV 6h 28-Feb-15 12:00 AM 28-Feb-15 06:00 AM

2617 OI101400 Loop Check & Stroke test 2h 28-Feb-15 06:00 AM 28-Feb-15 08:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 48 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 49: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2618 OI101405 Inspection by RLOC 1h 28-Feb-15 08:00 AM 28-Feb-15 09:00 AM

2619 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2620 OI101410 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2621 OI101415 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2622 R15U-072-026 RC2-31-072-PV-0102B-CV-OVERHAUL & SERVICINGR15U-072-026 RC2-31-072-PV-0102B-CV-OVERHAUL & SERVICING 1401h 01-Jan-15 12:00 AM 28-Feb-15 09:00 AM

2623 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2624 OI101420 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2625 OI101425 Remove Insulation 1h 01-Jan-15 01:00 AM 01-Jan-15 02:00 AM

2626 SHUTDOWNSHUTDOWN 27h 27-Feb-15 06:00 AM 28-Feb-15 09:00 AM

2627 OI101430 Verify LT&T and Obtain permit 1h 27-Feb-15 06:00 AM 27-Feb-15 07:00 AM

2628 OI101435 Disconnect Signals / Connections for CV 1h 27-Feb-15 07:00 AM 27-Feb-15 08:00 AM

2629 OI101440 Removal of CV & Install Blinds 4h 27-Feb-15 08:00 AM 27-Feb-15 12:00 PM

2630 OI101445 Transport CV to Work Shop 1h 27-Feb-15 12:00 PM 27-Feb-15 01:00 PM

2631 OI101450 Overhaul / Service CV 8h 27-Feb-15 01:00 PM 27-Feb-15 09:00 PM

2632 OI101455 Test Valve (Refer Documentation) 2h 27-Feb-15 09:00 PM 27-Feb-15 11:00 PM

2633 OI101460 Transport CV to Unit / Remove Blinds 1h 27-Feb-15 11:00 PM 28-Feb-15 12:00 AM

2634 OI101465 Install CV 6h 28-Feb-15 12:00 AM 28-Feb-15 06:00 AM

2635 OI101470 Loop Check & Stroke test 2h 28-Feb-15 06:00 AM 28-Feb-15 08:00 AM

2636 OI101475 Inspection by RLOC 1h 28-Feb-15 08:00 AM 28-Feb-15 09:00 AM

2637 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2638 OI101480 Reinsulate CV 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2639 OI101485 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2640 R15U-072-027 RC2-31-072-P-1111A-VALVE REPLACEMENTR15U-072-027 RC2-31-072-P-1111A-VALVE REPLACEMENT 1297h 01-Jan-15 12:00 AM 24-Feb-15 01:00 AM

2641 PRE-SHUTDOWNPRE-SHUTDOWN 13h 01-Jan-15 12:00 AM 01-Jan-15 01:00 PM

2642 OM104985 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2643 OM104990 Hydrotest new valves & Shift to location 8h 01-Jan-15 01:00 AM 01-Jan-15 09:00 AM

2644 OM104995 Removal of Insulations 4h 01-Jan-15 09:00 AM 01-Jan-15 01:00 PM

2645 SHUTDOWNSHUTDOWN 57h 21-Feb-15 04:00 PM 24-Feb-15 01:00 AM

2646 OM105000 Purging, Flushing, Gas testing, LEL check 4h 21-Feb-15 04:00 PM 21-Feb-15 08:00 PM

2647 OM105005 Verify LT&T and Obtain permit 2h 21-Feb-15 08:00 PM 21-Feb-15 10:00 PM

2648 OM105010 Blinding as per blindlist (Refer R15U-072-012) 0h 21-Feb-15 10:00 PM 21-Feb-15 10:00 PM

2649 OM105015 Unbolt & drop suction & discharge valves 8h 21-Feb-15 10:00 PM 22-Feb-15 06:00 AM

2650 OM105020 Shift removed valves to shop for servicing 1h 22-Feb-15 06:00 AM 22-Feb-15 07:00 AM

2651 OM105025 Erect Scaffolding 4h 22-Feb-15 07:00 AM 22-Feb-15 11:00 AM

2652 OM105030 Cut & remove the valves (as per dwg.) 4h 22-Feb-15 11:00 AM 22-Feb-15 03:00 PM

2653 OM105035 Fit-up the new valve in position 3h 22-Feb-15 03:00 PM 22-Feb-15 06:00 PM

2654 OM105040 Carryout welding 4h 22-Feb-15 06:00 PM 22-Feb-15 10:00 PM

2655 OM105045 NDT on weld joints As per RAT sheet 4h 22-Feb-15 10:00 PM 23-Feb-15 02:00 AM

2656 OM105050 Hydrotest on weld joints 8h 23-Feb-15 02:00 AM 23-Feb-15 10:00 AM

2657 OM105055 Carryout repair on welds (As per ERG) 4h 23-Feb-15 10:00 AM 23-Feb-15 02:00 PM

2658 OM105060 Remove scaffolding 2h 23-Feb-15 02:00 PM 23-Feb-15 04:00 PM

2659 OM105065 Install the new valves 8h 23-Feb-15 04:00 PM 24-Feb-15 12:00 AM

2660 OM105070 Painting on weld joints 1h 24-Feb-15 12:00 AM 24-Feb-15 01:00 AM

2661 OM105075 De-Blinding (Refer R15U-072-012) 0h 24-Feb-15 01:00 AM 24-Feb-15 01:00 AM

2662 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2663 OM105080 Fix back the insulation 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2664 OM105085 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2665 OM105090 Q.C Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2666 R15U-072-028 RC2-31-072-43-FT-0104-INST-FT REPLACEMENTR15U-072-028 RC2-31-072-43-FT-0104-INST-FT REPLACEMENT 1298h 01-Jan-15 12:00 AM 24-Feb-15 02:00 AM

2667 PRE-SHUTDOWNPRE-SHUTDOWN 35h 01-Jan-15 12:00 AM 02-Jan-15 11:00 AM

2668 OI101925 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2669 OI101930 Pre-fabricate the NEW line as per dwg. 24h 01-Jan-15 01:00 AM 02-Jan-15 01:00 AM

2670 OI101935 Inspection 6h 02-Jan-15 01:00 AM 02-Jan-15 07:00 AM

2671 OI101940 Erect Scaffolding 2h 02-Jan-15 07:00 AM 02-Jan-15 09:00 AM

2672 OI101945 Removal of Insulations. 2h 02-Jan-15 09:00 AM 02-Jan-15 11:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 49 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 50: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2673 SHUTDOWNSHUTDOWN 1298h 01-Jan-15 12:00 AM 24-Feb-15 02:00 AM

2674 OI101950 Purging / Flushing the line 6h 21-Feb-15 03:00 PM 21-Feb-15 09:00 PM

2675 OI101955 Verify LT&T and Obtain permit 4h 21-Feb-15 09:00 PM 22-Feb-15 01:00 AM

2676 OI101960 Blinding as per blindlist. 0h 22-Feb-15 01:00 AM 22-Feb-15 01:00 AM

2677 OI101965 Cut, Remove & fit up the Pre-fab lines 10h 22-Feb-15 01:00 AM 22-Feb-15 11:00 AM

2678 OI101970 Carryout Welding 12h 22-Feb-15 11:00 AM 22-Feb-15 11:00 PM

2679 OI101975 NDT on Weld joints 6h 22-Feb-15 11:00 PM 23-Feb-15 05:00 AM

2680 OI101980 Hydrotesting on weld joints 8h 23-Feb-15 09:00 AM 23-Feb-15 05:00 PM

2681 OI101985 Carry out repair on weld, if any 4h 23-Feb-15 05:00 AM 23-Feb-15 09:00 AM

2682 OI101990 Disconnect Signals / Cable connections 2h 22-Feb-15 01:00 AM 22-Feb-15 03:00 AM

2683 OI101995 Removal of Flowmeter 1h 22-Feb-15 03:00 AM 22-Feb-15 04:00 AM

2684 OI102000 Transport NEW flowmeter to the location 1h 22-Feb-15 01:00 AM 22-Feb-15 02:00 AM

2685 OI102005 Install the NEW flow meter 3h 23-Feb-15 05:00 PM 23-Feb-15 08:00 PM

2686 OI102010 Reconnect Signals / Cable connections 2h 23-Feb-15 08:00 PM 23-Feb-15 10:00 PM

2687 OI102015 Function test & Obtain inspection Cert. 2h 23-Feb-15 10:00 PM 24-Feb-15 12:00 AM

2688 OI102020 Painting on weld joints 2h 24-Feb-15 12:00 AM 24-Feb-15 02:00 AM

2689 OI102022 Inspection by RLOC 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2690 OI102025 Carryout de-blinding 0h 01-Jan-15 01:00 AM 01-Jan-15 01:00 AM

2691 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2692 OI102030 Fix back the insulation 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2693 OI102035 Remove scaffolding 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2694 OI102040 Housekeeping and close ptw 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2695 OI102045 Q.C. Documents submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2696 OI102050 Obtain PTW for Post shutdown jobs 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2697 OI102055 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2698 R15U-072-029 RC2-31-072-P-1111 B-VALVE REPLACEMENTR15U-072-029 RC2-31-072-P-1111 B-VALVE REPLACEMENT 1354h 01-Jan-15 12:00 AM 26-Feb-15 10:00 AM

2699 PRE-SHUTDOWNPRE-SHUTDOWN 13h 01-Jan-15 12:00 AM 01-Jan-15 01:00 PM

2700 OM105095 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2701 OM105100 Hydrotest new valves & Shift to location 8h 01-Jan-15 01:00 AM 01-Jan-15 09:00 AM

2702 OM105105 Removal of Insulations 4h 01-Jan-15 09:00 AM 01-Jan-15 01:00 PM

2703 SHUTDOWNSHUTDOWN 57h 24-Feb-15 01:00 AM 26-Feb-15 10:00 AM

2704 OM105110 Purging, Flushing, Gas testing, LEL check 4h 24-Feb-15 01:00 AM 24-Feb-15 05:00 AM

2705 OM105115 Verify LT&T and Obtain permit 2h 24-Feb-15 05:00 AM 24-Feb-15 07:00 AM

2706 OM105120 Blinding as per blindlist (Refer R15U-072-012) 0h 24-Feb-15 07:00 AM 24-Feb-15 07:00 AM

2707 OM105125 Unbolt & drop suction & discharge valves 8h 24-Feb-15 07:00 AM 24-Feb-15 03:00 PM

2708 OM105130 Shift removed valves to shop for servicing 1h 24-Feb-15 03:00 PM 24-Feb-15 04:00 PM

2709 OM105135 Erect Scaffolding 4h 24-Feb-15 04:00 PM 24-Feb-15 08:00 PM

2710 OM105140 Cut & remove the valves (as per dwg.) 4h 24-Feb-15 08:00 PM 25-Feb-15 12:00 AM

2711 OM105145 Fit-up the new valve in position 3h 25-Feb-15 12:00 AM 25-Feb-15 03:00 AM

2712 OM105150 Carryout welding 4h 25-Feb-15 03:00 AM 25-Feb-15 07:00 AM

2713 OM105155 NDT on weld joints As per RAT sheet 4h 25-Feb-15 07:00 AM 25-Feb-15 11:00 AM

2714 OM105160 Hydrotest on weld joints 8h 25-Feb-15 11:00 AM 25-Feb-15 07:00 PM

2715 OM105165 Carryout repair on welds (As per ERG) 4h 25-Feb-15 07:00 PM 25-Feb-15 11:00 PM

2716 OM105170 Remove scaffolding 2h 25-Feb-15 11:00 PM 26-Feb-15 01:00 AM

2717 OM105175 Install the new valves 8h 26-Feb-15 01:00 AM 26-Feb-15 09:00 AM

2718 OM105180 Painting on weld joints 1h 26-Feb-15 09:00 AM 26-Feb-15 10:00 AM

2719 OM105185 De-Blinding (Refer R15U-072-012) 0h 26-Feb-15 10:00 AM 26-Feb-15 10:00 AM

2720 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2721 OM105190 Fix back the insulation 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2722 OM105195 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2723 OM105200 Q.C Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2724 C9+ STORAGEC9+ STORAGE 1427h 01-Jan-15 12:00 AM 01-Mar-15 11:00 AM

2725 R15U-075-006 RC2-31-075-95-TK-1144-INTER & EXTERNAL INSPR15U-075-006 RC2-31-075-95-TK-1144-INTER & EXTERNAL INSP 1400h 01-Jan-15 12:00 AM 28-Feb-15 08:00 AM

2726 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2727 OM101205 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 50 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 51: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2728 OM101210 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2729 SHUTDOWNSHUTDOWN 458h 09-Feb-15 06:00 AM 28-Feb-15 08:00 AM

2730 OM101215 Verify LT&T and Obtain permit 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM

2731 OM101220 Mechanical Isolation & Blinding 8h 09-Feb-15 10:00 AM 09-Feb-15 06:00 PM

2732 OM101225 Manway Opening & Providing a Ventilation & Lighting 12h 09-Feb-15 06:00 PM 10-Feb-15 06:00 AM

2733 OM101230 Obtain Confined space permit & Erect Internal Scaffolding 24h 10-Feb-15 06:00 AM 11-Feb-15 06:00 AM

2734 OM101235 Preliminary Inspection 6h 11-Feb-15 06:00 AM 11-Feb-15 12:00 PM

2735 OM101240 Cleaning & Repair 360h 11-Feb-15 12:00 PM 26-Feb-15 12:00 PM

2736 OM101245 Remove Internal Scaffolding 18h 26-Feb-15 12:00 PM 27-Feb-15 06:00 AM

2737 OM101250 Final Inspection 6h 27-Feb-15 06:00 AM 27-Feb-15 12:00 PM

2738 OM101255 Manway Box-up 12h 27-Feb-15 12:00 PM 28-Feb-15 12:00 AM

2739 OM101260 De-Blinding 8h 28-Feb-15 12:00 AM 28-Feb-15 08:00 AM

2740 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2741 OM101265 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2742 OM101270 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2743 OM101275 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2744 R15U-075-009 RC2-31-075-EIV-0119-CV-OVERHAUL & SERVICINGR15U-075-009 RC2-31-075-EIV-0119-CV-OVERHAUL & SERVICING 1425h 01-Jan-15 12:00 AM 01-Mar-15 09:00 AM

2745 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2746 OI101620 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2747 OI101625 Errect Scaffolding / Remove Insulation 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2748 SHUTDOWNSHUTDOWN 27h 28-Feb-15 06:00 AM 01-Mar-15 09:00 AM

2749 OI101630 Verify LT&T and Obtain permit 1h 28-Feb-15 06:00 AM 28-Feb-15 07:00 AM

2750 OI101635 Disconnect Signals / Connections for CV 1h 28-Feb-15 07:00 AM 28-Feb-15 08:00 AM

2751 OI101640 Removal of CV & Install Blinds 4h 28-Feb-15 08:00 AM 28-Feb-15 12:00 PM

2752 OI101645 Transport CV to Work Shop 1h 28-Feb-15 12:00 PM 28-Feb-15 01:00 PM

2753 OI101650 Overhaul / Service CV 8h 28-Feb-15 01:00 PM 28-Feb-15 09:00 PM

2754 OI101655 Test Valve (Refer Documentation) 2h 28-Feb-15 09:00 PM 28-Feb-15 11:00 PM

2755 OI101660 Transport CV to Unit / Remove Blinds 1h 28-Feb-15 11:00 PM 01-Mar-15 12:00 AM

2756 OI101665 Install CV 6h 01-Mar-15 12:00 AM 01-Mar-15 06:00 AM

2757 OI101670 Loop Check & Stroke test 2h 01-Mar-15 06:00 AM 01-Mar-15 08:00 AM

2758 OI101675 Inspection by RLOC 1h 01-Mar-15 08:00 AM 01-Mar-15 09:00 AM

2759 POST SHUTDOWNPOST SHUTDOWN 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2760 OI101680 Reinsulate CV / Removal of Scafflods 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2761 OI101685 House keeping & Close PTW 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2762 R15U-075-011 RC2-31-075-EIV-0069-CV-OVERHAUL & SERVICINGR15U-075-011 RC2-31-075-EIV-0069-CV-OVERHAUL & SERVICING 29h 28-Feb-15 06:00 AM 01-Mar-15 11:00 AM

2763 SHUTDOWNSHUTDOWN 29h 28-Feb-15 06:00 AM 01-Mar-15 11:00 AM

2764 OI101690 Review JSA 1h 28-Feb-15 06:00 AM 28-Feb-15 07:00 AM

2765 OI101695 Verify LT&T and Obtain permit 1h 28-Feb-15 07:00 AM 28-Feb-15 08:00 AM

2766 OI101700 Disconnect Signals / Connections for CV 1h 28-Feb-15 08:00 AM 28-Feb-15 09:00 AM

2767 OI101705 Removal of CV & Install Blinds 4h 28-Feb-15 09:00 AM 28-Feb-15 01:00 PM

2768 OI101710 Transport CV to Work Shop 1h 28-Feb-15 01:00 PM 28-Feb-15 02:00 PM

2769 OI101715 Overhaul / Service CV 8h 28-Feb-15 02:00 PM 28-Feb-15 10:00 PM

2770 OI101720 Test Valve (Refer Documentation) 2h 28-Feb-15 10:00 PM 01-Mar-15 12:00 AM

2771 OI101725 Transport CV to Unit / Remove Blinds 1h 01-Mar-15 12:00 AM 01-Mar-15 01:00 AM

2772 OI101730 Install CV 6h 01-Mar-15 01:00 AM 01-Mar-15 07:00 AM

2773 OI101735 Loop Check & Stroke test 2h 01-Mar-15 07:00 AM 01-Mar-15 09:00 AM

2774 OI101740 Inspection by RLOC 1h 01-Mar-15 09:00 AM 01-Mar-15 10:00 AM

2775 OI101745 House keeping & Close PTW 1h 01-Mar-15 10:00 AM 01-Mar-15 11:00 AM

2776 THERMAL OXIDIZERTHERMAL OXIDIZER 1576h 01-Jan-15 12:00 AM 07-Mar-15 04:00 PM

2777 R15U-050-003 RC2-31-050-36-C-1224-REFRACTORY INSP & REPAIRR15U-050-003 RC2-31-050-36-C-1224-REFRACTORY INSP & REPAIR 1576h 01-Jan-15 12:00 AM 07-Mar-15 04:00 PM

2778 PRE-SHUTDOWNPRE-SHUTDOWN 18h 01-Jan-15 12:00 AM 01-Jan-15 06:00 PM

2779 OM100570 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2780 OM100575 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2781 OM100580 Remove Insulation 8h 01-Jan-15 10:00 AM 01-Jan-15 06:00 PM

2782 SHUTDOWNSHUTDOWN 634h 09-Feb-15 06:00 AM 07-Mar-15 04:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 51 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 52: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2783 OM100585 Verify LT&T and Obtain permit 4h 09-Feb-15 06:00 AM 09-Feb-15 10:00 AM

2784 OM100590 Mechanical Isolation & Blinding 8h 09-Feb-15 10:00 AM 09-Feb-15 06:00 PM

2785 OM100595 Stack Manway Opening & Providing a Ventilation & Lighting 8h 09-Feb-15 06:00 PM 10-Feb-15 02:00 AM

2786 OM100600 Obtain Confined space permit & Erect Internal Scaffolding 8h 10-Feb-15 02:00 AM 10-Feb-15 10:00 AM

2787 OM100605 Preliminary Inspection 4h 10-Feb-15 10:00 AM 10-Feb-15 02:00 PM

2788 OM100610 Cleaning & Refractory Repair & Installation in Bottom & Above Segments 576h 10-Feb-15 02:00 PM 06-Mar-15 02:00 PM

2789 OM100615 Remove Internal Scaffolding 8h 06-Mar-15 02:00 PM 06-Mar-15 10:00 PM

2790 OM100620 Final Inspection 6h 06-Mar-15 10:00 PM 07-Mar-15 04:00 AM

2791 OM100625 Manway Box-up 4h 07-Mar-15 04:00 AM 07-Mar-15 08:00 AM

2792 OM100630 De-Blinding 8h 07-Mar-15 08:00 AM 07-Mar-15 04:00 PM

2793 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2794 OM100635 Reinstall insulations 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2795 OM100640 Remove Scaffolding 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2796 OM100645 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2797 OM100650 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2798 SPENT CAUSTIC OXIDATION SYSTEMSPENT CAUSTIC OXIDATION SYSTEM 1396h 01-Jan-15 12:00 AM 28-Feb-15 04:00 AM

2799 R15U-080-004 RC2-31-080-95-D-1290-INTER & EXTERNAL INSPR15U-080-004 RC2-31-080-95-D-1290-INTER & EXTERNAL INSP 1383h 01-Jan-15 12:00 AM 27-Feb-15 03:00 PM

2800 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2801 OM101430 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2802 OM101435 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2803 SHUTDOWNSHUTDOWN 59h 25-Feb-15 04:00 AM 27-Feb-15 03:00 PM

2804 OM101440 Verify LT&T and Obtain permit 4h 25-Feb-15 04:00 AM 25-Feb-15 08:00 AM

2805 OM101445 Mechanical Isolation & Blinding 8h 25-Feb-15 08:00 AM 25-Feb-15 04:00 PM

2806 OM101450 Manway Opening & Providing a Ventilation & Lighting 8h 25-Feb-15 04:00 PM 26-Feb-15 12:00 AM

2807 OM101455 Obtain Confined space permit 2h 26-Feb-15 12:00 AM 26-Feb-15 02:00 AM

2808 OM101460 Preliminary Inspection 3h 26-Feb-15 02:00 AM 26-Feb-15 05:00 AM

2809 OM101465 Cleaning & Repair 18h 26-Feb-15 05:00 AM 26-Feb-15 11:00 PM

2810 OM101470 Final Inspection 4h 26-Feb-15 11:00 PM 27-Feb-15 03:00 AM

2811 OM101475 Manway Box-up 4h 27-Feb-15 03:00 AM 27-Feb-15 07:00 AM

2812 OM101480 De-Blinding 8h 27-Feb-15 07:00 AM 27-Feb-15 03:00 PM

2813 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2814 OM101485 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2815 OM101490 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2816 OM101495 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2817 R15U-080-005 RC2-31-080-95-TK-341-INTER, EXTERNAL & CUI INSPR15U-080-005 RC2-31-080-95-TK-341-INTER, EXTERNAL & CUI INSP 1396h 01-Jan-15 12:00 AM 28-Feb-15 04:00 AM

2818 PRE-SHUTDOWNPRE-SHUTDOWN 26h 01-Jan-15 12:00 AM 02-Jan-15 02:00 AM

2819 OM101500 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2820 OM101505 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2821 OM101510 Remove Insulation 8h 01-Jan-15 10:00 AM 01-Jan-15 06:00 PM

2822 OM101515 CUI-Scaffolding & remove insulation 8h 01-Jan-15 06:00 PM 02-Jan-15 02:00 AM

2823 SHUTDOWNSHUTDOWN 406h 11-Feb-15 06:00 AM 28-Feb-15 04:00 AM

2824 OM101520 Verify LT&T and Obtain permit 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM

2825 OM101525 Mechanical Isolation & Blinding 10h 11-Feb-15 10:00 AM 11-Feb-15 08:00 PM

2826 OM101530 Manway Opening & Providing a Ventilation & Lighting 8h 11-Feb-15 08:00 PM 12-Feb-15 04:00 AM

2827 OM101535 CUI Inspection & Repair 24h 12-Feb-15 04:00 AM 13-Feb-15 04:00 AM

2828 OM101540 Obtain Confined space permit & Erect Internal Scaffolding 18h 13-Feb-15 04:00 AM 13-Feb-15 10:00 PM

2829 OM101545 Preliminary Inspection 6h 13-Feb-15 10:00 PM 14-Feb-15 04:00 AM

2830 OM101550 Cleaning & Repair 300h 14-Feb-15 04:00 AM 26-Feb-15 04:00 PM

2831 OM101555 Remove Internal Scaffolding 12h 26-Feb-15 04:00 PM 27-Feb-15 04:00 AM

2832 OM101560 Final Inspection 6h 27-Feb-15 04:00 AM 27-Feb-15 10:00 AM

2833 OM101565 Manway Box-up 8h 27-Feb-15 10:00 AM 27-Feb-15 06:00 PM

2834 OM101570 De-Blinding 10h 27-Feb-15 06:00 PM 28-Feb-15 04:00 AM

2835 POST SHUTDOWNPOST SHUTDOWN 12h 01-Jan-15 12:00 AM 01-Jan-15 12:00 PM

2836 OM101575 Reinstall insulations 12h 01-Jan-15 12:00 AM 01-Jan-15 12:00 PM

2837 OM101580 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 52 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 53: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2838 OM101585 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2839 OM101590 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2840 ACID STORAGE AND DISTRIBUTION SYSTEMACID STORAGE AND DISTRIBUTION SYSTEM 1140h 01-Jan-15 12:00 AM 17-Feb-15 12:00 PM

2841 R15U-075-008 RC2-31-075-95-TK-1148-INTER & EXTERNAL INSPR15U-075-008 RC2-31-075-95-TK-1148-INTER & EXTERNAL INSP 1140h 01-Jan-15 12:00 AM 17-Feb-15 12:00 PM

2842 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2843 OM101355 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2844 OM101360 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2845 SHUTDOWNSHUTDOWN 150h 11-Feb-15 06:00 AM 17-Feb-15 12:00 PM

2846 OM101365 Verify LT&T and Obtain permit 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM

2847 OM101370 Mechanical Isolation & Blinding 8h 11-Feb-15 10:00 AM 11-Feb-15 06:00 PM

2848 OM101375 Manway Opening & Providing a Ventilation & Lighting 8h 11-Feb-15 06:00 PM 12-Feb-15 02:00 AM

2849 OM101380 Obtain Confined space permit & Erect Internal Scaffolding 24h 12-Feb-15 02:00 AM 13-Feb-15 02:00 AM

2850 OM101385 Preliminary Inspection 6h 13-Feb-15 02:00 AM 13-Feb-15 08:00 AM

2851 OM101390 Cleaning & Repair 60h 13-Feb-15 08:00 AM 15-Feb-15 08:00 PM

2852 OM101395 Remove Internal Scaffolding 18h 15-Feb-15 08:00 PM 16-Feb-15 02:00 PM

2853 OM101400 Final Inspection 6h 16-Feb-15 02:00 PM 16-Feb-15 08:00 PM

2854 OM101405 Manway Box-up 8h 16-Feb-15 08:00 PM 17-Feb-15 04:00 AM

2855 OM101410 De-Blinding 8h 17-Feb-15 04:00 AM 17-Feb-15 12:00 PM

2856 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2857 OM101415 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2858 OM101420 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2859 OM101425 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2860 CAUSTIC STORAGE AND DISTRIBUTION SYSTEMCAUSTIC STORAGE AND DISTRIBUTION SYSTEM 1140h 01-Jan-15 12:00 AM 17-Feb-15 12:00 PM

2861 R15U-060-007 RC2-31-060-95-TK-1213-INTER & EXTERNAL INSPR15U-060-007 RC2-31-060-95-TK-1213-INTER & EXTERNAL INSP 1113h 01-Jan-15 12:00 AM 16-Feb-15 09:00 AM

2862 PRE-SHUTDOWNPRE-SHUTDOWN 14h 01-Jan-15 12:00 AM 01-Jan-15 02:00 PM

2863 OM100740 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2864 OM100745 Erect Scaffolding 6h 01-Jan-15 02:00 AM 01-Jan-15 08:00 AM

2865 OM100750 Remove Insulation 6h 01-Jan-15 08:00 AM 01-Jan-15 02:00 PM

2866 SHUTDOWNSHUTDOWN 51h 14-Feb-15 06:00 AM 16-Feb-15 09:00 AM

2867 OM100755 Verify LT&T and Obtain permit 4h 14-Feb-15 06:00 AM 14-Feb-15 10:00 AM

2868 OM100760 Mechanical Isolation & Blinding 6h 14-Feb-15 10:00 AM 14-Feb-15 04:00 PM

2869 OM100765 Manway Opening & Providing a Ventilation & Lighting 6h 14-Feb-15 04:00 PM 14-Feb-15 10:00 PM

2870 OM100770 Obtain Confined space permit & Erect Internal Scaffolding 4h 14-Feb-15 10:00 PM 15-Feb-15 02:00 AM

2871 OM100775 Preliminary Inspection 3h 15-Feb-15 02:00 AM 15-Feb-15 05:00 AM

2872 OM100780 Cleaning & Repair 12h 15-Feb-15 05:00 AM 15-Feb-15 05:00 PM

2873 OM100785 Remove Internal Scaffolding 4h 15-Feb-15 05:00 PM 15-Feb-15 09:00 PM

2874 OM100790 Final Inspection 3h 15-Feb-15 09:00 PM 16-Feb-15 12:00 AM

2875 OM100795 Manway Box-up 3h 16-Feb-15 12:00 AM 16-Feb-15 03:00 AM

2876 OM100800 De-Blinding 6h 16-Feb-15 03:00 AM 16-Feb-15 09:00 AM

2877 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2878 OM100805 Reinstall insulations 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2879 OM100810 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2880 OM100815 Carry out House keeping 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

2881 OM100820 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2882 R15U-075-007 RC2-31-075-95-TK-1147-INTER & EXTERNAL INSPR15U-075-007 RC2-31-075-95-TK-1147-INTER & EXTERNAL INSP 1140h 01-Jan-15 12:00 AM 17-Feb-15 12:00 PM

2883 PRE-SHUTDOWNPRE-SHUTDOWN 10h 01-Jan-15 12:00 AM 01-Jan-15 10:00 AM

2884 OM101280 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2885 OM101285 Erect Scaffolding 8h 01-Jan-15 02:00 AM 01-Jan-15 10:00 AM

2886 SHUTDOWNSHUTDOWN 150h 11-Feb-15 06:00 AM 17-Feb-15 12:00 PM

2887 OM101290 Verify LT&T and Obtain permit 4h 11-Feb-15 06:00 AM 11-Feb-15 10:00 AM

2888 OM101295 Mechanical Isolation & Blinding 8h 11-Feb-15 10:00 AM 11-Feb-15 06:00 PM

2889 OM101300 Manway Opening & Providing a Ventilation & Lighting 8h 11-Feb-15 06:00 PM 12-Feb-15 02:00 AM

2890 OM101305 Obtain Confined space permit & Erect Internal Scaffolding 24h 12-Feb-15 02:00 AM 13-Feb-15 02:00 AM

2891 OM101310 Preliminary Inspection 6h 13-Feb-15 02:00 AM 13-Feb-15 08:00 AM

2892 OM101315 Cleaning & Repair 60h 13-Feb-15 08:00 AM 15-Feb-15 08:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 53 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 54: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2893 OM101320 Remove Internal Scaffolding 18h 15-Feb-15 08:00 PM 16-Feb-15 02:00 PM

2894 OM101325 Final Inspection 6h 16-Feb-15 02:00 PM 16-Feb-15 08:00 PM

2895 OM101330 Manway Box-up 8h 16-Feb-15 08:00 PM 17-Feb-15 04:00 AM

2896 OM101335 De-Blinding 8h 17-Feb-15 04:00 AM 17-Feb-15 12:00 PM

2897 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2898 OM101340 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2899 OM101345 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2900 OM101350 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2901 WASTE WATER TREATMENT SYSTEMWASTE WATER TREATMENT SYSTEM 1491h 01-Jan-15 12:00 AM 04-Mar-15 03:00 AM

2902 R15U-060-003 RC2-31-060-30-M-1272-REFURBISHMENT OF MOTORR15U-060-003 RC2-31-060-30-M-1272-REFURBISHMENT OF MOTOR 602h 01-Jan-15 06:00 AM 20-Feb-15 08:00 AM

2903 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2904 OE102335 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2905 SHUTDOWNSHUTDOWN 62h 15-Feb-15 06:00 AM 20-Feb-15 08:00 AM

2906 OE102340 Verify LT&T and Obtain permit 1h 15-Feb-15 06:00 AM 15-Feb-15 07:00 AM

2907 OE102345 Isolate the Motor 1h 15-Feb-15 07:00 AM 15-Feb-15 08:00 AM

2908 OE102350 Mech assist for De-Coupling of Motors 1h 15-Feb-15 08:00 AM 15-Feb-15 09:00 AM

2909 OE102355 Crane As sistanc e to Remove Motor 2h 15-Feb-15 09:00 AM 15-Feb-15 11:00 AM

2910 OE102360 Rigger Assistance to Remove Motor 2h 15-Feb-15 11:00 AM 15-Feb-15 01:00 PM

2911 OE102365 Motor has to sent for External Service 48h 15-Feb-15 01:00 PM 19-Feb-15 01:00 PM

2912 OE102370 Rigger Assistance to Fix back Motor 2h 19-Feb-15 01:00 PM 19-Feb-15 03:00 PM

2913 OE102375 Crane As sistanc e to Fix back Motor 2h 19-Feb-15 03:00 PM 19-Feb-15 05:00 PM

2914 OE102380 Mech assistance for Coupling of Motors 2h 19-Feb-15 05:00 PM 20-Feb-15 07:00 AM

2915 OE102385 Check the Motor for Proper Function and Witness 1h 20-Feb-15 07:00 AM 20-Feb-15 08:00 AM

2916 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2917 OE102390 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2918 R15U-060-004 RC2-31-060-30-M-1275-REFURBISHMENT OF MOTORR15U-060-004 RC2-31-060-30-M-1275-REFURBISHMENT OF MOTOR 602h 01-Jan-15 06:00 AM 20-Feb-15 08:00 AM

2919 PRE-SHUTDOWNPRE-SHUTDOWN 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2920 OE102395 Carry out JSA 2h 01-Jan-15 06:00 AM 01-Jan-15 08:00 AM

2921 SHUTDOWNSHUTDOWN 62h 15-Feb-15 06:00 AM 20-Feb-15 08:00 AM

2922 OE102400 Verify LT&T and Obtain permit 1h 15-Feb-15 06:00 AM 15-Feb-15 07:00 AM

2923 OE102405 Isolate the Motor 1h 15-Feb-15 07:00 AM 15-Feb-15 08:00 AM

2924 OE102410 Mech assist for De-Coupling of Motors 1h 15-Feb-15 08:00 AM 15-Feb-15 09:00 AM

2925 OE102415 Crane As sistanc e to Remove Motor 2h 15-Feb-15 09:00 AM 15-Feb-15 11:00 AM

2926 OE102420 Rigger Assistance to Remove Motor 2h 15-Feb-15 11:00 AM 15-Feb-15 01:00 PM

2927 OE102425 Motor has to sent for External Service 48h 15-Feb-15 01:00 PM 19-Feb-15 01:00 PM

2928 OE102430 Rigger Assistance to Fix back Motor 2h 19-Feb-15 01:00 PM 19-Feb-15 03:00 PM

2929 OE102435 Crane As sistanc e to Fix back Motor 2h 19-Feb-15 03:00 PM 19-Feb-15 05:00 PM

2930 OE102440 Mech assistance for Coupling of Motors 2h 19-Feb-15 05:00 PM 20-Feb-15 07:00 AM

2931 OE102445 Check the Motor for Proper Function and Witness 1h 20-Feb-15 07:00 AM 20-Feb-15 08:00 AM

2932 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2933 OE102450 Housekeeping & Close PTW 1h 01-Jan-15 06:00 AM 01-Jan-15 07:00 AM

2934 R15U-060-006 RC2-31-060-95-TK-1212-INTER & EXTERNAL INSPR15U-060-006 RC2-31-060-95-TK-1212-INTER & EXTERNAL INSP 1491h 01-Jan-15 12:00 AM 04-Mar-15 03:00 AM

2935 PRE-SHUTDOWNPRE-SHUTDOWN 14h 01-Jan-15 12:00 AM 01-Jan-15 02:00 PM

2936 OM100655 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2937 OM100660 Erect Scaffolding 6h 01-Jan-15 02:00 AM 01-Jan-15 08:00 AM

2938 OM100665 Remove Insulation 6h 01-Jan-15 08:00 AM 01-Jan-15 02:00 PM

2939 SHUTDOWNSHUTDOWN 51h 02-Mar-15 12:00 AM 04-Mar-15 03:00 AM

2940 OM100670 Verify LT&T and Obtain permit 4h 02-Mar-15 12:00 AM 02-Mar-15 04:00 AM

2941 OM100675 Mechanical Isolation & Blinding 6h 02-Mar-15 04:00 AM 02-Mar-15 10:00 AM

2942 OM100680 Manway Opening & Providing a Ventilation & Lighting 6h 02-Mar-15 10:00 AM 02-Mar-15 04:00 PM

2943 OM100685 Obtain Confined space permit & Erect Internal Scaffolding 4h 02-Mar-15 04:00 PM 02-Mar-15 08:00 PM

2944 OM100690 Preliminary Inspection 3h 02-Mar-15 08:00 PM 02-Mar-15 11:00 PM

2945 OM100695 Cleaning & Repair 12h 02-Mar-15 11:00 PM 03-Mar-15 11:00 AM

2946 OM100700 Remove Internal Scaffolding 4h 03-Mar-15 11:00 AM 03-Mar-15 03:00 PM

2947 OM100705 Final Inspection 3h 03-Mar-15 03:00 PM 03-Mar-15 06:00 PM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 54 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 55: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

2948 OM100710 Manway Box-up 3h 03-Mar-15 06:00 PM 03-Mar-15 09:00 PM

2949 OM100715 De-Blinding 6h 03-Mar-15 09:00 PM 04-Mar-15 03:00 AM

2950 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2951 OM100720 Reinstall insulations 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2952 OM100725 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

2953 OM100730 Carry out House keeping 3h 01-Jan-15 12:00 AM 01-Jan-15 03:00 AM

2954 OM100735 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2955 R15U-060-008 RC2-31-060-95-TK-1244-INTER & EXTERNAL INSPR15U-060-008 RC2-31-060-95-TK-1244-INTER & EXTERNAL INSP 1430h 01-Jan-15 12:00 AM 01-Mar-15 02:00 PM

2956 PRE-SHUTDOWNPRE-SHUTDOWN 12h 01-Jan-15 12:00 AM 01-Jan-15 12:00 PM

2957 OM100825 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2958 OM100830 Erect Scaffolding 10h 01-Jan-15 02:00 AM 01-Jan-15 12:00 PM

2959 SHUTDOWNSHUTDOWN 464h 10-Feb-15 06:00 AM 01-Mar-15 02:00 PM

2960 OM100835 Verify LT&T and Obtain permit 6h 10-Feb-15 06:00 AM 10-Feb-15 12:00 PM

2961 OM100840 Mechanical Isolation & Blinding 10h 10-Feb-15 12:00 PM 10-Feb-15 10:00 PM

2962 OM100845 Manway Opening & Providing a Ventilation & Lighting 12h 10-Feb-15 10:00 PM 11-Feb-15 10:00 AM

2963 OM100850 Obtain Confined space permit & Erect Internal Scaffolding 24h 11-Feb-15 10:00 AM 12-Feb-15 10:00 AM

2964 OM100855 Preliminary Inspection 6h 12-Feb-15 10:00 AM 12-Feb-15 04:00 PM

2965 OM100860 Cleaning & Repair 360h 12-Feb-15 04:00 PM 27-Feb-15 04:00 PM

2966 OM100865 Remove Internal Scaffolding 18h 27-Feb-15 04:00 PM 28-Feb-15 10:00 AM

2967 OM100870 Final Inspection 6h 28-Feb-15 10:00 AM 28-Feb-15 04:00 PM

2968 OM100875 Manway Box-up 12h 28-Feb-15 04:00 PM 01-Mar-15 04:00 AM

2969 OM100880 De-Blinding 10h 01-Mar-15 04:00 AM 01-Mar-15 02:00 PM

2970 POST SHUTDOWNPOST SHUTDOWN 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2971 OM100885 Remove Scaffolding 8h 01-Jan-15 12:00 AM 01-Jan-15 08:00 AM

2972 OM100890 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

2973 OM100895 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2974 R15U-060-011 RC2-31-060-95-TK-1244-NOZZLE REPLACEMENTR15U-060-011 RC2-31-060-95-TK-1244-NOZZLE REPLACEMENT 1379h 01-Jan-15 12:00 AM 27-Feb-15 11:00 AM

2975 PRE-SHUTDOWNPRE-SHUTDOWN 49h 01-Jan-15 12:00 AM 03-Jan-15 01:00 AM

2976 OM104290 Conduct JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

2977 OM104295 Pre-fab lines & nozzle as per dwg. 24h 01-Jan-15 01:00 AM 02-Jan-15 01:00 AM

2978 OM104300 Inspection of weld joints 12h 02-Jan-15 01:00 AM 02-Jan-15 01:00 PM

2979 OM104305 Hydrotest new valves & Shift to job area 8h 02-Jan-15 01:00 PM 02-Jan-15 09:00 PM

2980 OM104310 Erect Scaffolding 4h 02-Jan-15 09:00 PM 03-Jan-15 01:00 AM

2981 SHUTDOWNSHUTDOWN 94h 23-Feb-15 01:00 PM 27-Feb-15 11:00 AM

2982 OM104315 Purging, Flushing, Gas testing, LEL checking 8h 23-Feb-15 01:00 PM 23-Feb-15 09:00 PM

2983 OM104320 Verify LT&T and Obtain permit 2h 23-Feb-15 09:00 PM 23-Feb-15 11:00 PM

2984 OM104325 Blinding as per blindlist (Refer R15U-060-008) 0h 23-Feb-15 11:00 PM 23-Feb-15 11:00 PM

2985 OM104330 Cut & remove the clamped portions & pipelines to be modified 6h 23-Feb-15 11:00 PM 24-Feb-15 05:00 AM

2986 OM104335 Fitup the prefab lines in position 6h 24-Feb-15 05:00 AM 24-Feb-15 11:00 AM

2987 OM104340 Carryout welding 12h 24-Feb-15 11:00 AM 24-Feb-15 11:00 PM

2988 OM104345 Remove the existing hose from the tank 2h 24-Feb-15 11:00 PM 25-Feb-15 01:00 AM

2989 OM104350 Fix the existing pipeline in position 3h 25-Feb-15 01:00 AM 25-Feb-15 04:00 AM

2990 OM104355 NDT on weld joints (As per RAT sheet) 12h 25-Feb-15 04:00 AM 25-Feb-15 04:00 PM

2991 OM104360 Hydrotesting on weld joints 24h 25-Feb-15 04:00 PM 26-Feb-15 04:00 PM

2992 OM104365 Carry out repair on weld if any 12h 26-Feb-15 04:00 PM 27-Feb-15 04:00 AM

2993 OM104370 Fix the new valves with new gaskets 6h 27-Feb-15 04:00 AM 27-Feb-15 10:00 AM

2994 OM104375 Painting on weld joints 1h 27-Feb-15 10:00 AM 27-Feb-15 11:00 AM

2995 OM104380 De-Blinding (Refer R15U-060-008) 0h 27-Feb-15 11:00 AM 27-Feb-15 11:00 AM

2996 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2997 OM104385 Remove Scaffolding 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2998 OM104390 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

2999 OM104395 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3000 R15U-060-013 RC2-31-060-95-TK-1248-INTER & EXTERNAL INSPR15U-060-013 RC2-31-060-95-TK-1248-INTER & EXTERNAL INSP 1447h 01-Jan-15 12:00 AM 02-Mar-15 07:00 AM

3001 PRE-SHUTDOWNPRE-SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

3002 OM100900 Carry out JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 55 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 56: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

3003 OM100905 Erect Scaffolding 4h 01-Jan-15 02:00 AM 01-Jan-15 06:00 AM

3004 SHUTDOWNSHUTDOWN 73h 27-Feb-15 06:00 AM 02-Mar-15 07:00 AM

3005 OM100910 Verify LT&T and Obtain permit 6h 27-Feb-15 06:00 AM 27-Feb-15 12:00 PM

3006 OM100915 Mechanical Isolation & Blinding 8h 27-Feb-15 12:00 PM 27-Feb-15 08:00 PM

3007 OM100920 Manway Opening & Providing a Ventilation & Lighting 6h 27-Feb-15 08:00 PM 28-Feb-15 02:00 AM

3008 OM100925 Obtain Confined space permit & Erect Internal Scaffolding 8h 28-Feb-15 02:00 AM 28-Feb-15 10:00 AM

3009 OM100930 Preliminary Inspection 3h 28-Feb-15 10:00 AM 28-Feb-15 01:00 PM

3010 OM100935 Cleaning & Repair 24h 28-Feb-15 01:00 PM 01-Mar-15 01:00 PM

3011 OM100940 Remove Internal Scaffolding 4h 01-Mar-15 01:00 PM 01-Mar-15 05:00 PM

3012 OM100945 Final Inspection 3h 01-Mar-15 05:00 PM 01-Mar-15 08:00 PM

3013 OM100950 Manway Box-up 3h 01-Mar-15 08:00 PM 01-Mar-15 11:00 PM

3014 OM100955 De-Blinding 8h 01-Mar-15 11:00 PM 02-Mar-15 07:00 AM

3015 POST SHUTDOWNPOST SHUTDOWN 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

3016 OM100960 Remove Scaffolding 6h 01-Jan-15 12:00 AM 01-Jan-15 06:00 AM

3017 OM100965 Carry out House keeping 4h 01-Jan-15 12:00 AM 01-Jan-15 04:00 AM

3018 OM100970 Close Work permit 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3019 R15U-060-015 RC2-31-060-95-TK-1254-REPLACE THE SCAPPERR15U-060-015 RC2-31-060-95-TK-1254-REPLACE THE SCAPPER 1266h 01-Jan-15 12:00 AM 22-Feb-15 06:00 PM

3020 PRE-SHUTDOWNPRE-SHUTDOWN 73h 01-Jan-15 12:00 AM 04-Jan-15 01:00 AM

3021 OM104400 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3022 OM104405 Pre-fab clarifier rake assy as per dwg. 24h 01-Jan-15 02:00 AM 02-Jan-15 02:00 AM

3023 OM104410 Pre-fab the bottom scrapper as per dwg. 24h 02-Jan-15 02:00 AM 03-Jan-15 02:00 AM

3024 OM104415 Inspect pre-fab scrapper & rake assy 4h 03-Jan-15 02:00 AM 03-Jan-15 06:00 AM

3025 OM104420 Carryout repair, if any (As per ERG) 12h 03-Jan-15 06:00 AM 03-Jan-15 06:00 PM

3026 OM104425 Shift the assembly from shop to job location (Forklift required) 2h 03-Jan-15 06:00 PM 03-Jan-15 08:00 PM

3027 OM104430 Shift blinds to job location 1h 03-Jan-15 08:00 PM 03-Jan-15 09:00 PM

3028 OM104435 Erect scaffolding 4h 03-Jan-15 09:00 PM 04-Jan-15 01:00 AM

3029 SHUTDOWNSHUTDOWN 84h 19-Feb-15 06:00 AM 22-Feb-15 06:00 PM

3030 OM104440 Perform gas test / LEL checking 4h 19-Feb-15 06:00 AM 19-Feb-15 10:00 AM

3031 OM104445 Verify LT&T and Obtain permit 2h 19-Feb-15 10:00 AM 19-Feb-15 12:00 PM

3032 OM104450 Blinding as per blindlist. 8h 19-Feb-15 12:00 PM 19-Feb-15 08:00 PM

3033 OM104455 Cleaning the tank 24h 19-Feb-15 08:00 PM 20-Feb-15 08:00 PM

3034 OM104460 Erect internal scaffolding, if required 4h 20-Feb-15 08:00 PM 21-Feb-15 12:00 AM

3035 OM104465 Remove U-clamp from scrapper support pipe 2h 21-Feb-15 12:00 AM 21-Feb-15 02:00 AM

3036 OM104470 Remove the chain from scrapper 2h 21-Feb-15 02:00 AM 21-Feb-15 04:00 AM

3037 OM104475 Fix the pre-fab scrapper as per dwg. 8h 21-Feb-15 04:00 AM 21-Feb-15 12:00 PM

3038 OM104480 Provide chain on scrapper to stiling well 4h 21-Feb-15 12:00 PM 21-Feb-15 04:00 PM

3039 OM104485 Offer for inspection after fixing 4h 21-Feb-15 04:00 PM 21-Feb-15 08:00 PM

3040 OM104490 Carryout repair, if any (As per ERG) 6h 21-Feb-15 08:00 PM 22-Feb-15 02:00 AM

3041 OM104495 Remove internal scaffolding 4h 22-Feb-15 02:00 AM 22-Feb-15 06:00 AM

3042 OM104500 Carryout De-Blinding 8h 22-Feb-15 06:00 AM 22-Feb-15 02:00 PM

3043 OM104505 Remove scaffolding at blind locations 4h 22-Feb-15 02:00 PM 22-Feb-15 06:00 PM

3044 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3045 OM104510 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3046 OM104515 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3047 R15U-060-016 RC2-31-060-95-TK-1254-BROKEN SUPPORT REPLACEMENTR15U-060-016 RC2-31-060-95-TK-1254-BROKEN SUPPORT REPLACEMENT 1305h 01-Jan-15 12:00 AM 24-Feb-15 09:00 AM

3048 PRE-SHUTDOWNPRE-SHUTDOWN 44h 01-Jan-15 12:00 AM 02-Jan-15 08:00 PM

3049 OM104520 Conduct JSA 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3050 OM104525 Pre-fabricate the supports as per dwg. 24h 01-Jan-15 02:00 AM 02-Jan-15 02:00 AM

3051 OM104530 Inspect the fabricated supports 4h 02-Jan-15 02:00 AM 02-Jan-15 06:00 AM

3052 OM104535 Carryout repair on supports (As per ERG) 12h 02-Jan-15 06:00 AM 02-Jan-15 06:00 PM

3053 OM104540 Shift fabricated supports to job area 2h 02-Jan-15 06:00 PM 02-Jan-15 08:00 PM

3054 SHUTDOWNSHUTDOWN 63h 21-Feb-15 06:00 PM 24-Feb-15 09:00 AM

3055 OM104545 Verify LT&T and Obtain permit 2h 21-Feb-15 06:00 PM 21-Feb-15 08:00 PM

3056 OM104550 Blinding as per blindlist (Refer R15U-060-015) 0h 21-Feb-15 08:00 PM 21-Feb-15 08:00 PM

3057 OM104555 Erect internal scaffolding 4h 21-Feb-15 08:00 PM 22-Feb-15 12:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 56 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation

Page 57: OSBL-DETAIL EXECUTION SCH-29112014

# Activity ID Activity Name OriginalDuration

Start Finish

3058 OM104560 Offer for initial inspection 5h 22-Feb-15 12:00 AM 22-Feb-15 05:00 AM

3059 OM104565 Unbolt & remove the broken supports 8h 22-Feb-15 05:00 AM 22-Feb-15 01:00 PM

3060 OM104570 Fix the fabricated supports in position 24h 22-Feb-15 01:00 PM 23-Feb-15 01:00 PM

3061 OM104575 Tight the supports with the weir rings 12h 23-Feb-15 01:00 PM 24-Feb-15 01:00 AM

3062 OM104580 Final inspection 4h 24-Feb-15 01:00 AM 24-Feb-15 05:00 AM

3063 OM104585 Remove internal scaffolding 4h 24-Feb-15 05:00 AM 24-Feb-15 09:00 AM

3064 OM104590 De-Blinding (Refer R15U-060-015) 0h 24-Feb-15 09:00 AM 24-Feb-15 09:00 AM

3065 POST SHUTDOWNPOST SHUTDOWN 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3066 OM104595 Housekeeping and close PTW 2h 01-Jan-15 12:00 AM 01-Jan-15 02:00 AM

3067 OM104600 Q.C. Documents Submission 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3068 R15U-060-019 RC2-31-060-95-TK-1249-FLOATING TANK REPAIRR15U-060-019 RC2-31-060-95-TK-1249-FLOATING TANK REPAIR 1360h 01-Jan-15 12:00 AM 26-Feb-15 04:00 PM

3069 PRE-SHUTDOWNPRE-SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3070 OM101820 Carry out JSA 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3071 SHUTDOWNSHUTDOWN 46h 24-Feb-15 06:00 PM 26-Feb-15 04:00 PM

3072 OM101825 Verify LT&T and Obtain permit 2h 24-Feb-15 06:00 PM 24-Feb-15 08:00 PM

3073 OM101830 Mechanical Isolation & Blinding 6h 24-Feb-15 08:00 PM 25-Feb-15 02:00 AM

3074 OM101835 Providing a Ventilation & Lighting 4h 25-Feb-15 02:00 AM 25-Feb-15 06:00 AM

3075 OM101840 Obtain Confined space permit & Erect Internal Scaffolding 6h 25-Feb-15 06:00 AM 25-Feb-15 12:00 PM

3076 OM101845 Preliminary Inspection 3h 25-Feb-15 12:00 PM 25-Feb-15 03:00 PM

3077 OM101850 Cleaning & Repair 12h 25-Feb-15 03:00 PM 26-Feb-15 03:00 AM

3078 OM101855 Remove Internal Scaffolding 4h 26-Feb-15 03:00 AM 26-Feb-15 07:00 AM

3079 OM101860 Final Inspection 3h 26-Feb-15 07:00 AM 26-Feb-15 10:00 AM

3080 OM101865 De-Blinding 6h 26-Feb-15 10:00 AM 26-Feb-15 04:00 PM

3081 POST SHUTDOWNPOST SHUTDOWN 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3082 OM101870 Carry out House keeping 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

3083 OM101875 Close Work permit 1h 01-Jan-15 12:00 AM 01-Jan-15 01:00 AM

S S M T W T Fri S S M T W T Fri Sat S M T W Thr Fri S S M T W T Fri S S M T W T Fri Sat S M T W Thr

Feb 01 Feb 08 Feb 15 Feb 22 Mar 01 Mar 08

RLOC TURNAROUND 2015 - DETAILED EXECUTION SCHEDULE RLOC TA 2015 - EX SCH 29-Nov-14 01:37 PM

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 57 of 57 TASK filters: FILTERS, FILTERS_1.

© Oracle Corporation